1.
Introduction
1.1
Background
1.1.1
Citybus Limited is one of the major
bus services operators in Hong Kong.
To date, it still does not have its own permanent bus depot. The
reliance of the company’s engineering and maintenance services on temporary
depots build on short-term tenancy sites has proven over the past years not to
be a preferable practice. The need
to decommission the temporary depot at Aldrich Bay in near future will create
an immediate demand. It would be
difficult for Citybus to maintain its quality bus services to the Hong Kong
public in the lack of stable facilities for bus maintenance, repairing,
refuelling, washing, etc.
1.1.2
According to Part 1 Schedule 2 Section
A.6 (Roads, railways and depot) of the EIA Ordinance (EIAO), a transport depot
located in less than 200m from the nearest boundary of an existing or planned
residential area and educational institution is classified as a Designated
Project. An Environmental Permit
issued by the Director of Environmental Protection (DEP) is required prior to
the construction and operation of the proposed bus depot.
1.1.3
An application (No: ESB-065/2001) for
an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the
EIAO was submitted to DEP on 19th January 2001 with a Project
Profile. A Study Brief {No. ESB-065/2001} was issued by the Authority to the
applicant (Citybus) under Section 5(7)(a) of the EIAO on 5th March
2001 for the preparation of the EIA report.
1.1.4
Public inputs obtained during the
public inspection period of the Project Profile, and issues related to the EIA
study raised by some members of the Eastern District Council have been respected
and taken account of in the study.
1.1.5
A consultancy team led by Ling Chan +
Partners Limited (LCP) has been commissioned by Citybus in December 2000 to
study the architectural design and engineering requirements of the proposed
development. CH2M HILL (China) Limited (formerly named as EHS Consultants
Limited) has been commissioned by Citybus as a sub-consultant of LCP to carry
out an EIA Study for the proposed bus depot development. Input with respect to architectural,
engineering traffic, landscape/ visual design of the development were provided
by the team, including LCP, Wong Pak Lam & Associates, Thomas Anderson
& Partners, LLA Consultancy Limited, EDAW Earthasia Limited, and MDA Hong
Kong Limited through a series of design co-ordination meetings with
Citybus.
1.2
Site
Selection
1.2.1
Citybus currently operates about 90
routes with a fleet of about 790 buses on the Hong Kong Island. While over 400 buses are serving routes
in the Southern District, some 300 buses are for routes running in the Eastern
and Central Districts. Besides,
around 50 buses are running on cross-harbour routes.
1.2.2
Operationally, Citybus needs two
permanent bus depots.
Location-wise, it would be more efficient and environmental friendly to
have one depot in the Eastern District and another in the Southern
District. As a significant portion
of buses are heading towards the Central District from Eastern District when
the bus service commences early in the morning, and returning from Central
District to Eastern District for parking, establishment of a bus depot in the
Eastern District will minimize the travelled routes, distance and time between
the bus depot and the various bus terminuses. The establishment of a new bus depot in other districts may
affect Citybus’ existing operation in serving the public. The operational needs of the buses
running in the Southern District are currently met by the depot facility at Ap
Lei Chau. A permanent depot facility
in the Eastern District is in demand after the decommissioning of the temporary
bus depot in Aldrich Bay.
1.2.3
Taking into consideration the
operational requirements of the multi-storey bus depot in terms of the driveway
and ramp system with 15-m turning radius, and areas required for bus parking,
maintenance bays, sunken pits, workshops, storage areas, staff changing rooms,
etc., the minimum size of the site needed for the construction of a
multi-storey bus depot was identified to be about 1ha.
1.2.4
The bus depot need was discussed with
the Government since early 2000.
Bus depots are preferably to be located on industrial areas to ensure
the compatibility of the landuses.
Planning Department identified that available industrial areas in the
Eastern District are extremely rare.
These include A Kung Ngam Industrial Area in Shau Kei Wan, and Chai Wan
East Industrial Area. Most
industrial sites in A Kung Ngam have already been developed, leaving only three
patches of undeveloped sites with a site area ranging from about 920m2
to 1,900m2. The
available site area in A Kung Ngam industrial area is not sufficient for the
construction of a multi-storey bus depot with sufficient number of bus parking
spaces to meet the long-term operational need of Citybus.
1.2.5
The existing China Motor Bus (CMB)
depot located at Chai Wan Road will be rented by Citybus for temporary use
after decommissioning of its existing temporary bus depot at Aldrich Bay until
the planned completion of the new depot in mid 2003. The CMB depot site has been rezoned into a Comprehensive Development
Area (CDA) for redevelopment.
Further use of the site as a bus depot is therefore not preferable. Besides, there are numerous existing
residential buildings located in close proximity to the existing bus depot at
Chai Wan Road. Longer-term use of
the site as a permanent bus depot is not a preferred option from an
environmental viewpoint given the close proximity of the existing bus depot to
the nearby sensitive receivers.
1.2.6
A 0.78 hectare site located to the
immediate south of New World First Bus Depot in the Chai Wan East Industrial
Area was initially identified to be available by the Government. The site was not further considered as
the site area involved is not sufficient.
Two candidate sites, Site B and Site C, also located within the Chai Wan
East Industrial Area were identified and considered with the Government
departments. Site C was selected
taking into consideration its likely better environmental performance as it is
located farther away from most nearby sensitive receivers.
1.3
Objectives
of the EIA
1.3.1
The main objective of this EIA study
is to provide information on the nature and extent of the potential
environmental impacts arising from the construction and operation of the
proposed bus depot and related activities taking place concurrently. The study
will provide information for DEP’s decisions on:
(a) the overall acceptability of any
adverse environmental consequences that are likely to arise as a result of the
proposed project;
(b) the conditions and requirements for
the detailed design, construction and operation of the proposed project to
mitigate against adverse environmental consequences wherever practicable; and
(c) the acceptability of residual
impacts after the proposed mitigation measures are implemented.
1.3.2
The objectives of this EIA study, as stated
in Section 2.1 of the Study Brief, are as follows:
(a)
to
describe the proposed project and associated works together with the
requirements for carrying out the proposed project;
(b)
to
consider alternative site(s) and to compare the environmental benefits and
dis-benefits of each of the site in selecting a preferred site;
(c)
to
identify and describe the elements of the community and environment likely to
be affected by the proposed project, including both the natural and man-made
environment;
(d)
to identify
and quantify emission sources and determine the significance of impacts on
sensitive receivers and potential affected uses;
(e)
to
propose the provision of mitigation measures so as to minimize pollution,
environmental disturbance and nuisance during construction and operation of the
project;
(f)
to
identify, predict and evaluate the residual (i.e. after practicable mitigation)
environmental impacts and the cumulative effects expected to arise during the
construction and operational phases of the project in relation to the sensitive
receivers and potential affected uses;
(g)
to
identify, assess and specify methods, measures and standards, to be included in
the detailed design, construction and operation of the project which are
necessary to mitigate environmental impacts and to reduce them to acceptable
levels;
(h)
to
investigate the extent of the secondary environmental impacts that may arise
from the proposed mitigation measures and to identify the constraints
associated with the mitigation measures recommended in the EIA study as well as
the provision of any necessary modification; and
(i)
to
design and specify the environmental monitoring and audit requirements, if
required, to ensure the implementation and the effectiveness of the
environmental protection and pollution control measures adopted.
2.
Project Description
2.1
The
Subject Site And Its Environs
2.1.1
Figure A shows the location of the
available site for the construction of the proposed bus depot. The site has an
approximate area of 1 hectare.
Located at a minimum distance of 80m to the North-west of the future bus
depot is Hong Kong Institute of Vocational Education (IVE) (Chai Wan). Lying between the college and the bus
depot site are the MTR railway tracks leading to the Chai Wan Station to the
south and Shing Tai Road. To the immediate North of IVE is its associated Staff
Quarters. Tsui Wan Estate is
situated at more than 165m to the South-west of the site. The nearest residential blocks at Heng
Fa Chuen is located at approximately 390m to the north of the site. The bus depot of New World First
Bus is located at over 135m to the north-east of the subject site.
2.2
Bus
Depot Design
2.2.1
The bus depot will be constructed in
form of a low-rise building occupying a site area of approximately 1 hectare
(approximately 100m long x 100m).
The maximum building height is approximately 17m for the bus depot and
31m for the southern office block extension, respectively.
2.2.2
The development will provide spaces
for bus parking, maintenance, and office areas. Figure B shows the preliminary design of the ground floor
plan of the bus depot. Additional floor plans can be found in the EIA report.
As shown with the design layout plans, the bus depot will consist of three
stories located at ground floor (G/F), first floor (1/F) and roof floor (3/F). As shown on the preliminary plans, the
G/F will house approximately 2 refuelling bays, 2 washing bays, 29 sunken pits,
4 brake testers and 5 maintenance bays. The 1/F will provide some 46
maintenance bays for annual maintenance works. The 3/F (bus parking roof) floor
will provide about 100 bus parking areas.
The 4/F and 5/F that will only be built at the southern portion of the
site will be used for office areas.
2.3
Implementation
Programme
2.3.1
Construction works are planned to
start on 1 December 2001 to meet the urgent demand to have the constructed
depot ready for operation in mid-2003.
Figure C shows the preliminary construction programme of the
project. The development is
expected to be completed in mid-2003.
3.
Air Quality Impact
3.1.1
Dust generation from construction
activities is identified to be of key interest during construction phase of the
project. The major dust emission sources arising from the planned construction
works have been are identified to include excavation, material
handling and vehicle movement on unpaved haul roads.
3.1.2
Potential construction dust impact
arising from the key dust emission sources on the nearby existing ASRs has been
predicted using the air quality model “Fugitive
Dust Model” (FDM).
3.1.3
Hourly meteorological data for a whole
year has been inputted into the air quality model to give the worst-case
maximum 1-hour and daily Total Suspended Particulate (TSP) concentrations at
the representative assessment points.
The modelled TSP concentrations were compared with the 1-hour and daily
TSP limits of 500mg/m3 and 260mg/m3 respectively after summation of the relevant
background TSP level. The
modelling study indicates that construction dust impact on the nearby Air
Sensitive Receivers will be kept well within acceptable levels when the dust
mitigation measures required under the Air Pollution Control (Construction
Dust) Regulation are implemented.
3.1.4
Various forms of practicable dust
control measures, including frequent watering, enclosure of dust emission
sources as well as establishment and use of vehicle wheel and body washing
station at exit points, etc. will be included into the Contract Specification
for implementation by the appointed Contractor. The implementation of sufficient dust mitigation measures by
the contractor will be checked by an Environmental Monitoring and Audit
(EM&A) Programme to be carried out by an Environmental Team. This will allow the contractor to react
immediately and take actions to ensure protection of the nearby air sensitive
landuses from unacceptable dust impact through implementation of sufficient
dust mitigation measures.
3.2.1
During the operational phase of the
bus depot, vehicular emission from buses running within the depot and commuting
to and from the depot have been assessed quantitatively using the air quality
models ISCST3 and CALINE4.
Representative Air Sensitive Receivers (ASRs) have been selected for the
modelling study.
3.2.2
Potential cumulative air quality
impact from the concurrent operation of the NWFB depot in the area, as well as
traffic emissions from the nearby road carriageways have been taken account of
quantitatively in the study.
Traffics generated from the future landuses within the Chai Wan East
Industrial Area have been considered in the traffic forecast by the Project
Traffic Consultant.
3.2.3
Hourly meteorological data for a whole
year has been used for the prediction of the worst case maximum 1-hour and
daily Nitrogen Dioxide (NO2) concentrations, maximum 1-hour Carbon
Monoxide (CO) and daily Respirable Suspended Particulate (RSP) levels at the
representative ASRs. With
summation of the background pollutant levels, the modelled pollutant
concentrations at the representative ASRs were compared with the relevant Air
Quality Objectives (AQOs).
3.2.4
All predicted air pollutant
concentrations at various levels of the ASRs are well within the AQOs. The assessment results reveal that
vehicular emissions from open road traffic and direct emission from the two bus
depots will unlikely pose an unacceptable air quality impact on the surrounding
ASRs.
4.
Noise Impact ASSEssment
4.1
Construction
Phase
4.1.1
During the construction phase,
potential noise impact arising from the operation of powered mechanical
equipment (PME) at the work sites is the key interest.
4.1.2
Construction noise is controlled under
the Noise Control Ordinance (NCO)
which prohibits the use of powered mechanical equipment (PME) during the
restricted hours (7 p.m. to 7 a.m. on normal weekdays and any time on a public
holiday, including Sunday) without a valid Construction Noise Permit (CNP)
granted by the Authority.
Relevant technical details are provided in the “Technical Memorandum on
Noise From Construction Works Other than Percussive Piling”.
4.1.3
With effect from 1 November 96, the
use of specified powered mechanical equipment (SPME) for carrying out
construction work other than percussive piling and/ or the carrying out of
prescribed construction work (PCW) within a designated area are also brought
under control. The relevant technical details are provided in the “Technical
Memorandum on Noise from Construction Work in Designated Areas”.
4.1.4
Percussive piling is controlled
similarly by a noise permit system and described in the NCO and the “Technical
Memorandum On Noise From Percussive Piling” (TM3) which restrict the number of
hours during which piling can be conducted. No percussive piling may be carried out in the territory
without a valid CNP issued by the Authority. Besides, a CNP will only be granted for percussive piling
which is scheduled during normal working hours between 7 a.m. to 7 p.m. from
Monday to Saturday. The carrying
out percussive piling is prohibited at any time on Sundays and public holidays
as well as during the weekday from 7 p.m. to 7 a.m. the next day.
4.1.5
Details on the PME to be used during
the construction phase would not be available before the appointment of the
Contractor. Nevertheless, a
reasonable PME inventory (equipment types and number of equipment) has been developed
by the Project Engineer based on the preliminary construction programme at this
planning stage to enable the carrying out of a detailed quantitative
assessment.
4.1.6
The assessment results demonstrated
that with the combined use of various practicable noise control measures at
locations close to the Noise Sensitive Receivers (NSRs), the construction noise
impact on the nearby noise sensitive receivers (NSRs) can be mitigated to
acceptable levels. The common and
practicable noise mitigation options include use of quiet equipment, erecting
temporary noise barriers and provision of noise enclosure, phasing of
construction activities, reducing number of equipment operating together, as
well as good site practice and noise management. The mitigated noise levels predicted demonstrated that the
progressive increase in use of these measure shall be able to reduce the
construction noise impact on all nearby NSRs to acceptable levels. The requirement to adopt these
mitigation measures as far as practicable during the execution of the project
shall be written to the contract specification.
4.1.7
Implementation of sufficient noise
control measures by the contractor will also be checked through the recommended
EM&A programme. Details on the
EM&A Programme are presented in the EM&A Manual.
4.2
Operational
Phase Fixed Noise Impact
4.2.1
Potential noise impact from fixed
noise sources of the bus depot was assessed. Noise standards are given in the Technical Memorandum for
the Assessment of Noise from Places other than Domestic Premises, Public Places
or Construction Sites. To plan for
a better environment, a “5dB(A) margin” has been considered in accordance with
the requirement under Table 1A in Annex 5 of the EIAO-TM. For NSRs with an ASR “C”, the
applicable noise assessment criteria, “Acceptable Noise Level – 5dB(A)” criteria,
are Leq(30min) 65dB(A) and 55dB(A) during daytime/ evening (from
0700 to 2300 hours) and night-time (from 2300 to 0700 hours). For NSRs with an ASR “B”, the
corresponding applicable noise criteria are 60dB(A) and 50dB(A). The Hong Kong Institute of Vocational
Education (IVE) (Chai Wan) is not expected to be sensitive during the
night-time period when the noise criteria are most stringent.
4.2.2
The fixed noise sources and associated
noise levels associated with their operation were identified and measured by
the consultants through several visits to Citybus’ existing bus depot in
Aldrich Bay. The major noise
sources are identified to be engine noise generated during brake testing,
engine testing and bus parking.
The key time period of interest was the morning period when buses are
leaving the bus depot to the bus terminuses for the commencement of the daily
service to serve the public.
4.2.3
As a prudent approach to avoid
potential noise impact generated from the roof level of the bus depot, a 3m
high solid vertical wall will be provided near the southern, western and
northern edge of the bus depot at roof level as shown in Figure D. Besides, the northern and southern
façades of the bus depot building to which Heng Fa Chuen and Tsui Wan Estate
are facing will be constructed as a solid façade.
4.2.4
The assessment results confirmed that
the noise assessment criteria will be met at all NSRs.
4.3
Operational
Phase Traffic Noise Impact
4.3.1
Operation of the proposed bus depot
will inevitably generate some additional traffic on the adjacent road
carriageways. As a prudent
approach in avoiding significant traffic noise impact, the routeing plan for
buses commuting to the depot was formulated with consideration on potential traffic
and traffic noise impact, taking into account the existing traffic flows on the
carriageways. The bus routeing
plan has been agreed with the relevant Government departments and is presented
in the final TIA report. Figure E
shows the planned bus routing plan agreed with the Government.
4.3.2
Taking into account the public view,
which is also considered appropriate from a traffic and environmental
point-of-view, buses heading towards or arriving from Siu Sai Wan will not be
allowed to use Wing Tai Road and Shing Tai Road at all time periods during normal
operation.
4.3.3
A road traffic noise standard of L10(1-hr)
70dB(A) and L10(1-hr) 65dB(A) for domestic premises and
educational institutions respectively is specified in Table 1 under Annex 5 of
the EIAO-TM based on peak hour traffic.
These noise limits are meant for the hour having the overall peak
traffic flows, and apply to uses which rely on opened windows for
ventilation. They are therefore
not directly applicable in the current EIA study for the hours during which
there will be maximum number of buses returning and/or leaving the bus depot.
4.3.4
To assess whether the future operation
of the proposed bus depot will give a significant contribution to the overall
traffic noise on the nearby NSRs, traffic forecast for the years 2003 and 2018
were considered to represent the worst-case scenarios. Traffic generation from other future
developments in the area has been considered in the traffic forecast. The early morning and near mid-night
scenarios were considered as these represent the worst-case scenarios when the
highest traffic flows would be generated from the operation of the bus
depot.
4.3.5
Traffic noise levels were predicted at
all representative assessment points for the “with bus depot” and “without bus
depot” scenarios. A comparison of
the two scenarios for the year 2003 and 2018 scenarios indicated that noise
contribution from the bus depot at all NSRs are less than 1.0dB(A), indicating
that the contribution to the overall traffic noise impact is insignificant.
5.
wASTE mANAGEMENT
5.1.1
The waste management implications
during the construction and operational phases were evaluated and assessed.
5.1.2
Implementation of proper waste
management during the construction phase is necessary. At this planning stage, appropriate
disposal method for each type of waste was identified, along with consideration
of opportunities for construction waste reduction, reuse or recycling. The potential impacts arising from the
handling, collection, and disposal of construction wastes and the environmental
mitigation measures required to mitigate these environmental impacts were
identified and recommended.
5.1.3
The major source of Construction and
Demolition (C&D) Material from the construction activities is expected to
arise from the required excavation activities for the foundation works from
bored piling activities, pile cap construction, manholes and other underground
utilities and facilities, including underground fuel tanks and sunken
pits.
5.1.4
A preliminary estimate is 28,000m3
for the bored piling works and 55,000m3 from other excavation
activities. Based on the
preliminary construction programme, the daily quantity of excavation material
to be handled is estimated to be some 900m3/day on average. The building construction activities
would generate some additional C&D waste, but the contribution to the
overall quantity is expected to be insignificant and will be minimised by the
Contractor through minimisation of waste generation, reuse and recycling as far
as practicable. Chemical waste and
general refuse generated from the construction activities shall also be
properly disposed of. A waste
management plan (WMP) is recommended to be developed by the Contractor based on
the recommended control measures for the handling of C&DM.
5.1.5
The operation of the proposed bus
depot is expected to generate limited and similar types of wastes as many other
industrial undertakings.
Significant environmental impact is not anticipated. Requirements on proper chemical waste
management have been included in the EIA for future implementation.
6.
lAND Contamination Impact
6.1.1
Operation of the proposed bus depot
will inevitably involve storage and delivery of diesel fuel on-site. Chemicals will also be used, through
not expected to be in a significant quantity. These facilities are identified in the EIA to have the
potential to cause land contamination in the long run if the fuel and chemicals
are not properly stored, handled, managed and disposed of during operation.
6.1.2
Potential sources of land
contamination were identified.
Appropriate operational practices, waste management strategies and
precautionary measures have been formulated to prevent the occurrence of land
contamination problem as far as practicable.
7.
Wastewater Treatment and Disposal
Facilities
7.1.1
Wastewater effluent generated from the
construction work stage shall be managed in accordance with the requirements
under ProPECC Note PN1/94 such that unacceptable water quality impact would not
be resulted. No effluent shall be
allowed to be discharged into the Cargo Handling Basin, or stormwater drain at
road carriageways and other public areas durig the construction phase.
7.1.2
During the operational phase,
wastewater effluent generated from designated bus washing areas may contain
petrol and should be diverted to petrol interceptors before being discharged
into government foul sewers.
Sewage arising from the site such as kitchen area should also be
diverted to grease traps before disposal to foul sewer. The design of the petrol interceptors
and grease traps to be installed shall enable the treated effluent to meet the
limits stipulated in the Technical Effluent Discharged into Drainage and
Sewerage Systems, Inland and Coastal Waters.
7.1.3
Sufficient stormwater drainage
facility should be provided for the development. All rainwater collected from the roof floor bus parking
areas shall be diverted to petrol/oil interceptor before disposal. The design of the interceptors should
allow stormwater bypass during peak flow periods.
8.
Hazard Impact
8.1.1
An “Other Specified Uses” (“OU”) site
located on the northern side of the development is zoned for the development of
a petrol filling cum liquefied petroleum gas (LPG) filling station, as shown in
the latest Draft Outline Zoning Plan (Plan No. S/H20/11).
8.1.2
Electrical and Mechanical Services
Department (EMSD) requires a minimum separation distance of 15m between LPG
filling station and industrial/ commercial buildings to minimise potential
hazard associated with operation of LPG filling station. Planning Department (PlanD) has advised
that in identifying a suitable site for the LPG/ Petrol filling station, the
requirement of providing a separation distance of 15m between the LPG filling
station and the proposed bus depot has been observed.
8.1.3
Given the close proximity of the
proposed bus depot to the future LPG/ Petrol filling station, as a prudent
approach, a Quantitative Risk Assessment (QRA) has been conducted to ascertain
if the risk posed by the LPG filling station on the bus depot is within
acceptable level. Precautionary measures
have also been identified and incorporated into the design of the bus depot.
8.1.4
The QRA study assessed and quantified
the risk associated with the operation of the LPG/ petrol filling station in
form of Societal Risk and Individual Risk for comparison with the risk
guidelines. The calculated societal
risk level is within the acceptable region as specified in the Risk Guidelines
for PHI and the Potential Loss of Life (PLL) is 2.5 x 10-5 per
year. On the other hand the
individual risk level also falls within the acceptable limit of 1 in 100,000 per
year.
8.1.5
The findings of the study confirm that
with the provision of standard risk control measures incorporated into the
design of the LPG/ Petrol filling station, and the precautionary measure of
providing a solid concrete wall for the entire northern façade of the bus depot
building, the project will not be subject to unacceptable risk from the
operation of the LPG/ Petrol filling station and the overall societal risk
impact will be within acceptable level.
9.
Landscape and visual impacts
9.1.1
A baseline study has been carried out
and identify that the only landscape resource is the existing vegetation
scattered throughout the study area.
As such, a comprehensive tree survey has been carried out to identify
the baseline conditions of the existing landscape resources. The trees are mainly common species
with trunk diameter varies from 0.1m to 0.4m. The bus depot building has to cover the entire site due to
the need to accommodate the following provisions onsite – driveway and ramp
system, maintenance spaces, parking spaces and other supporting
facilities. A total 88 number of
trees will be required to be removed from the site during the site clearance
period.
9.1.2
In order to mitigate the landscape
impact, it is suggested to transplant 13 numbers of good quality trees to Chai
Wan Park, Cape Collinson Chinese Permanent Cemetery, Yee Shing Lane Sitting Out
Area or the proposed town park at Aldrich Bay.
9.1.3
In addition, a planting proposal is
developed according to the proposed building layout with the intention to
introduce greenery where possible to mitigate the landscape impact and further
enhance the quality of the environment.
9.1.4
As the quality of streetscape is
important to mitigate the landscape impact, it is further recommended that a
row of heavy standard Delonix regia should be planted along the footpath of
Road 20/4 and Shing Tai Road.
9.1.5
To avoid potential visual impact
associated with the bus depot building design, strategies including the use of
recessed grove lines to divide wall into panels to reduce its massive scale,
and use of colours to further breakdown the scale by means of spray-painting on
plaster. Metal cladding and tiling
will also be used for the main elevations facing Road 20/4 and Shing Tai Road
to add richness in texture and colour.
It is expected that these measures will ensure visual compatibility with
its environmental context.
9.1.6
Representative illustrations showing
the landscape treatment and preliminary design of the depot are presented in
Annex I. Additional drawings can
be found in Appendix 9-2 of the EIA Report.
10.
Environmental Management Plan
10.1.1
An Environmental Management Plan (EMP)
has been prepared as part of the EIA Study. The EMP recommends the Environmental Monitoring and Audit
(EM&A) requirements during the construction phase of the project, as well
as the setting up of an “impact-mitigation oriented” Environmental Management
System (EMS) during the operational phase.
10.1.2
Regular construction noise and dust
monitoring are recommended to be carried out by an Environmental Team. The monitoring requirements in terms of
locations, frequencies, monitoring equipment and parameters, action and limit
levels, event/ action plan have been recommended. Site audit requirements have also been recommended.
10.1.3
The tree transplanting works will be
carried out strictly according to the Transplanting Specification under the
close monitoring by the ER who should be a qualified landscape architect or
arboriculturist. The various responsible parties have been identified and
reported in the implementation schedule.
10.1.4
An impact mitigation oriented EMS is
recommended to be established to achieve the objectives that the long-term
operation of the bus depot will not only satisfy the relevant environmental
legislation and regulations and the environmental conditions, but also conform
to the Environmental Policy of the project proponent. The establishment of this Environmental Policy is not a
statutory requirement but reflects the project proponent’s commitment to taking
the relevant environmental factors into consideration as appropriate in the
operation of the bus depot development.
An initial list of environmental factors and recommended mitigation
strategy have been draw up for further review during the detailed design stage
and operational phase by the project proponent to maintain their relevance,
practicability and effectiveness in achieving the project proponent’s
Environmental Policy.
11.
Conclusion
11.1.1
This Environmental Impact Assessment
(EIA) covers all key environmental issues of the project, including air quality
impact, noise impact, waste management implications, land contamination
prevention, wastewater treatment and disposal, hazard impact, landscape and
visual consideration. Quantitative
and/or qualitative assessments have been undertaken as appropriate in
accordance with the requirements of the Study Brief for comparison with the
relevant standards and requirements.
Practicable and cost-effective mitigation measures have been recommended
where necessary to minimise the identified adverse impacts to acceptable
levels. EM&A programme has
been recommended for checking the implementation of sufficient mitigation
measures with respect to the key environmental issues of concern during the
construction phase. An EMS is also
recommended to enable the consideration of relevant environmental factors
during the operation of the bus depot.
11.1.2
In conclusion, with the implementation
of the proposed environmental mitigation measures, potential environmental
impacts associated with the construction of the Project will be alleviated to
acceptable levels. With these
measures, the construction and operation of the proposed bus depot should
unlikely cause any unacceptable impact from an environmental perspective.