2.1.1 A review has been undertaken of the current planning goals and objectives, statutory land-use and landscape planning designations for the Study Area.
Road D1
road d8
ROAD D10
ROAD P2
Table 2.1 Preliminary
Implementation Programme for Roads D1, D8, D10 and the extended Road P2
Road |
Commencement
date |
Completion
date |
D1 |
September 2003 (Phase
1) December 2003 (Phase
2) |
December 2004 (Phase
1) December 2006 (Phase
2) |
D8 |
December 2003 |
December 2006 |
D10 |
October 2003 (Phase 1) May 2004 (Phase 2) |
November 2005 (Phase
1) May 2007 (Phase 2) |
Minor road junction improvement works at road junction of
Road D10/Wan Po Road, and road junctions along Roads D1 and D8 |
2002 |
2009 |
Extended Road P2 (at-grade) |
December 2003 |
December 2006 |
Extended Road P2 (elevated) |
July 2007 |
December 2010 |
Table 2.2 Environmental
Benefits and Disbenefits of Alternative Road Alignment
Options
Road Alignment |
Environmental
Benefits |
Environmental
Disbenefits |
Figure |
Realign Roads D1 and D8 to the north |
Reduce visual impact from sensitive
receivers viewing from TKO Bay; reduce environmental and visual impacts to
sensitive receivers along the waterfront. |
Increase air quality and noise impact if
the road is cutting across areas of higher population density and/or
environmental sensitivity. The realisation of land. |
2.5 |
Realign Road D1 to the south |
Reduce air quality and noise impact to
the southern façade of the proposed developments at Areas 65D and 67B. |
Construction on viaduct hence potential
adverse water quality and visual impact, also potential to reduce the
flexibility for landuse planning if there is further reclamation to the south
in the future. |
2.5 |
Realign Road D10 to the east |
Reduce air quality and noise impact to
the northern facade of the proposed developments at Areas 86. |
Cutting through landfills hence potential
landfill gas and leachate migration problems, also increase air quality and
noise impacts to the proposed recreational uses on the restored landfill. |
2.6 |
Realign Road D10 to the west |
Reduce air quality and noise impacts to
the proposed recreational uses on the restored landfill. |
Construction on viaduct hence potential
adverse water quality and visual impacts. |
2.6 |