a)
0.6-1.7 m3/min
(20-60 SCFM) adjustable flow range
b)
Equipped with a
timing/control device with +/- 5 minutes accuracy for 24 hours operation
c)
Installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation
d)
Capable of providing
a minimum exposed area of 406 cm2 (63 in2)
e)
Flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period
f)
Equipped with a
shelter to protect the filter and sampler
g)
Incorporated with
an electronic mass flow rate controller or other equivalent devices
h)
Equipped with a
flow recorder for continuous monitoring
i)
Provided with a
peaked roof inlet
j)
Incorporated with
a manometer
k)
Able to hold and
seal the filter paper to the sampler housing at horizontal position
l)
Easy to change
the filter
m)
Capable of operating
continuously for 24-hour period.
a)
The wind sensors
should be installed 10m above ground so that they are clear of obstructions or
turbulence caused by buildings
b)
The wind data
should be captured by a data logger.
The data shall be down loaded for analysis at least once a month
c)
The wind data
monitoring equipment should be re-calibrated at least once every six months
d)
Wind direction
should be divided into 16 sectors of 22.5 degrees each.
Table 2.1 Proposed
Air Quality Monitoring Stations
Identification
No. |
Location |
CA1 |
School in
Area 65C |
CA2 |
Residential
building in Area 72 |
CA3 |
Soccer
Pitch in Area 77 |
CA4 |
Planned school in Area
72 |
a)
At the site
boundary or such locations close to the major dust emission source
b)
Close to the
sensitive receptors (Figure 2.1)
c)
Take into account
the prevailing meteorological conditions.
a)
A horizontal
platform with appropriate support to secure the samplers against gusty wind
should be provided
b)
No two samplers
should be placed less than 2 meters apart
c)
The distance
between the sampler and an obstacle, such as buildings, must be at least twice
the height that the obstacle protrudes above the sampler
d)
A minimum of 2
meters of separation from walls, parapets and penthouses is required for
rooftop samplers
e)
A minimum of 2
meters separation from any supporting structure, measured horizontally is
required
f)
No furnace or
incinerator flue is nearby
g)
Airflow around
the sampler is unrestricted
h)
The sampler is
more than 20 meters from the dripline
i)
Any wire fence
and gate, to protect the sampler, should not cause any obstruction during
monitoring
j)
Permission must
be obtained to set up the samplers and to obtain access to the monitoring
stations
k)
A secured supply
of electricity is needed to operate the samplers.
Table
2.2 Action / Limit Levels for Air
Quality
Parameters |
Action |
Limit |
24 Hour
TSP Level in m |
For baseline level £ 200 m For baseline level > 200 m |
260 |
1 Hour
TSP Level in |
For baseline level £ 384 m For
baseline level > 384 m |
500 |
Table 2.3 Event / Action Plan for Air Quality
EVENT |
ACTION |
||||
|
ET |
|
ER |
CONTRACTOR |
|
ACTION LEVEL |
|
|
|||
1. Exceedance for one sample |
1. Identify source, investigate the causes of exceedance and
propose remedial measures; 2. Inform 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method. |
1. Notify Contractor. |
1. Rectify any unacceptable practice; 2. Amend working methods if appropriate. |
|
2. Exceedance for two or more consecutive samples |
1. Identify source; 2. Inform
3. Advise
the ER on the effectiveness of the proposed remedial measures 4. Repeat measurements to confirm findings; 5. Increase monitoring frequency to daily; 6. Discuss with 7. If exceedance continues, arrange meeting with 8. If exceedance stops, cease additional monitoring; |
1.
Check monitoring data submitted by ET; 2.
Check Contractor’s working method; 3.
Discuss with ET and Contractor on possible remedial measures; 4.
Advise the ER on the Effectiveness of the proposed remedial measures 5.
Supervise implementation of remedial measures. |
1.
Confirm receipt of notification of failure in writing; 2.
Notify Contractor; 3.
Ensure remedial measures properly implemented |
1. Submit proposals for remedial to 2. Implement the agreed proposals; 3. Amend proposal if appropriate. |
|
LIMIT LEVEL |
|
|
|||
1. Exceedance for one sample |
1. Identify source, investigate the causes of exceedance and
propose remedial measures; 2. Inform ER, Contractor and EPD; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily; 5. Assess effectiveness of Contractor’s remedial actions and
keep |
1.
Check monitoring data submitted by ET; 2.
Check Contractor’s working method; 3.
Discuss with ET and Contractor on possible remedial measures; 4.
Advise the ER on the Effectiveness of the proposed remedial measures 5.
Supervise implementation of remedial measures. |
1.
Confirm receipt of notification of failure in writing; 2.
Notify Contractor; 3.
Ensure remedial measures properly implemented |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to 3. Implement the agreed proposals; 4. Amend proposal if appropriate. |
|
2. Exceedance for two or more consecutive samples |
1. Notify 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency to daily; 5. Carry out analysis of Contractor’s working procedures to
determine possible mitigation to be implemented; 6. Arrange meeting with 7. Assess effectiveness of Contractor’s remedial actions and
keep 8. If exceedance stops, cease additional monitoring. |
1.
Discuss amongst ER, ET, and Contractor on the potential remedial
actions; 2.
Review Contractor’s remedial actions whenever necessary to assure
their effectiveness and advise the ER accordingly; 3.
Supervise the implementation of remedial measures. |
1.
Confirm receipt of notification of failure in writing; 2.
Notify Contractor; 3.
In consultation with the 4.
Ensure remedial measures properly implemented; 5.
If exceedance continues, consider what portion of the work is
responsible and instruct the Contractor to stop that portion of work until
the exceedance is abated. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not under control; 5. Stop the relevant portion of works as determined by the ER until
the exceedance is abated. |
|
Use of regular
watering to reduce dust emissions from exposed site surfaces and unpaved roads,
at least twice daily with complete coverage, particularly during dry weather;
Use of frequent
watering for particularly dusty static construction areas and areas close to
air quality sensitive receivers;
Side enclosure
and covering of any aggregate or dusty material storage piles to reduce
emissions. Where this is not
practicable owing to frequent usage, watering should be applied to aggregate
fines;
Open stockpiles
should be avoided or covered. Where
possible, prevent placing dusty material storage piles near air quality
sensitive receivers;
Provision of
barriers, which may be the temporary noise barriers, between the site and
nearby air quality sensitive receivers to act as dust barriers;
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations;
Establishment and
use of vehicle wheel and body washing facilities at the exit points of the
site, combined with cleaning of public roads where necessary;
Provision of wind
shield and dust extractextraction units or similar dust mitigation
measures at the loading points, and use of water sprinklers at the loading area
where dust generation is likely during the loading process of loose material
particularly in dry seasons/periodsor at the loading points
and use of water sprinklers at the loading area;
Imposition of
speed controls for vehicles on unpaved site roads. Eight kilometres per hour is the recommended limit;
Where feasible,
routing of vehicles and positioning of construction plant should be at the
maximum possible distance from air quality sensitive receivers;
Instigation of an
environmental monitoring and auditing program to monitor the construction
process in order to enforce controls and modify methods of work if dusty
conditions arise; and
Good site
practices.