5.
LANDFILL
GAS MONITORING
5.1
Landfill Gas Parameters (Methane, Carbon Dioxide, and Oxygen)
5.1.1
Although a
comprehensive landfill gas management system has been constructed under the
Restoration Contract for Tseung Kwan O Stage I Landfill, the efficiency of the
system has not been demonstrated at this time.
Landfill gas monitoring for methane, carbon dioxide and oxygen shall be
carried out to identify any migration between the landfill and the site and to
ensure the safety of the Contractor’s personnel.
5.1.2
Certain information,
such as the proposed routing of utilities in relation to the sensitive elements
of the development will be determined at the detailed design stage. It is mentioned in the EIA report that in
the event that there are substantial changes in the alignments of Roads D1, D8
and D10, a review of the qualitative source-pathway-target analysis as
presented in Table 7.15 of the EIA report is considered necessary.
5.1.3
Monitoring
shall be carried out and reported in a similar manner to that for the
Restoration Contract to provide comparable data. An example of landfill gas monitoring field measurement recording
sheet as used in the Restoration Contract is presented in Appendix B3. The presentation format for landfill gas
monitoring shall be based on this format and agreed with EPD.
5.2
Monitoring Equipment
Monitoring of Construction
Works
5.2.1
Intrinsically
safe, portable gas detectors shall be used when working in any confined space
which has the potential for the presence of landfill gas, and the risk of
explosion or asphyxiation. The
landfill gas monitoring instrument shall :
Where possible, comply
with BS6020 and be approved by BASEEFA as intrinsically safe, suitable for use
in a Zone 2 area to BS5345;
Be capable of continuous
monitoring of methane, oxygen and carbon dioxide;
Be capable of continuous
barometric pressure and gas pressure measurement;
Normally operate in
diffusion mode unless required for spot sampling, when it should be capable of
operating by means of an aspirator or pump;
Have low battery, fault
and over range indication incorporated;
Store monitoring date, and
shall be capable of being down-loaded directly to a PC;
Measure in the following
ranges:
Methane 0-100% LEL & 0-100% v/v
Oxygen 0-25% v/v
Carbon dioxide 0-100% v/v
Barometric pressure mBar (absolute)
Gas pressure (relative to
atmosphere) Pascals
Temperature 0-100oC
5.2.2
The monitoring equipment
shall alarm (both audibly and visually) in the event that the concentrations of
the following are exceeded :
Methane – higher
than 10 % LEL
Carbon dioxide –
higher than 0.5 %
Oxygen – lower
than 18 % by volume
5.2.3
The
equipment used to monitor LFG concentrations in excavations may shall be the
same as that described for routine for landfill
gas monitoring LFG monitoring of for utility manholes and chambers.
described in Section 5.2.1 above, as long as safety parameters described above
can be achieved.
5.3
Monitoring Locations
Monitoring of Construction Works
5.3.1
During
construction, excavations of 1m depth or more, LFG concentration shall be
monitored before entry and periodically during the works. It
is recommended that pre-entry monitoring shall be undertaken, where applicable, in accordance with the
requirements of the Factories and Industrial Undertaking (Confined Spaces)
Regulation. The periodic monitoring
shall be undertaken at the beginning of each half working day (i.e.
morning and afternoon) throughout the entire period the excavation remains open. If drilling is
required, the procedures for safety management and working procedures described
in the EPD’s Landfill Gas Hazard
Assessment – Guidance Note should be adopted.
Monitoring of Utilities
5.3.2
Following
construction, pre-entry and routine monitoring may be required at service voids
and utility boxes. It is recommended that pre-entry monitoring
shall be undertaken, where applicable, in accordance with the requirements of the
Factories and Industrial Undertaking (Confined Spaces) Regulation. The frequency of the routine monitoring is
recommended to be biweekly during the initial stage. The “initial stage” is considered as the
“initial stage” of the operational phase of the project. However, there is no government’s
regulation/guideline on the duration of such “initial stage” for monitoring. As such, it is recommended that the “initial
stage” refer to the first 3 months of the operational phase. The frequency shall be subsequently reviewed
on a quarterly basis through discussion with EPD based on all the available
monitoring data for methane, carbon dioxide and oxygen (including that of
pre-entry monitoring). In
the event that there are substantial changes in the alignments of Roads D1, D8
and D10, the monitoring requirement and specific locations of monitoring points
should be established based on the findings of the review of the qualitative
source-pathway-target analysis as presented in Table 7.15 of the EIA
report. The need for continued
monitoring should be reviewed on a quarterly basis through discussion with EPD, based on all the
available monitoring data for methane, carbon dioxide and oxygen (including
that of pre-entry monitoring).
Operational Landfill Gas Monitoring
5.3.3
In the
event that there are substantial changes in the alignments of Roads D1, D8 and
D10, the monitoring requirement during the operational phase should be
established based on the findings of the review of the qualitative
source-pathway-target analysis as presented in Table 7.15 of the EIA report, in
consultation with EPD.
5.4
Limit Levels and Action Plan for Landfill Gas
5.4.1
As a
general measure to minimise the risk of explosion due to the presence of
methane, “no smoking” signs shall be placed at entry or access points of the
work site.
5.4.2
The Limit
Levels and relevant Action Plan for landfill gas detected in utilities and any
on-site areas following construction are shown in Table 5.1 below.
Table 5.1 Limit Levels and Action Plan for Landfill Gas
Parameter
|
Level
|
Action
|
Oxygen
|
<19%
|
Ventilate
trench/void to restore O2 to >19%
|
<18%
|
Stop
works
Evacuate
personnel / prohibit entry
Increase
ventilation to restore O2 to >19%
|
Methane
|
>10%
LEL
|
Post
“No Smoking” signs at concerned areas in addition to to site entry/access
points
Prohibit
hot works
Increase
ventilation to restore CH4 to <10% LEL
|
>20%
LEL
|
Stop
works
Evacuate
personnel / prohibit entry
Increase
ventilation to restore CH4 to <10% LEL
|
Carbon
Dioxide
|
>0.5%
|
Ventilate
to restore CO2 to < 0.5%
|
>1.5%
|
Stop
works
Evacuate
personnel / prohibit entry
Increase
ventilation to restore CO2 to < 0.5%
|
5.5
Landfill Gas Mitigation Measures
5.5.1
The EIA
report has recommended specific mitigation measures to be incorporated into the
detailed design. The Contractor shall
follow the safe working practices to detect landfill gas accumulations in any
utility trenches. Safe working
practices to detect landfill gas accumulations in the utilities trenches in the
vicinity of the faults are outlined in EPD’s Landfill Gas Hazard Assessment - Guidance Note and shall be adopted
by the relevant Utilities Companies.
5.5.2
Notwithstanding,
the requirement for a critical review of the detailed design, mitigation
measures to be incorporated in the detailed design include :
Portable gas
detectors shall be used to regularly check the levels of methane, carbon
dioxide and oxygen in depressions, trenches, and other excavations;
Void around any
service ducts, pipes or cables etc. within conduits shall be filled with gas
resistant mastic;
All ducts,
manholes and chambers shall be sealed off from the ground to prevent gas entry
and provided with vented covers;
Atmosphere within
manholes or chambers shall be checked for methane, carbon dioxide and oxygen
prior to entry; and
Atmosphere within
manholes or chambers shall be checked for methane, carbon dioxide and oxygen on
a regular basis. The frequency of the
monitoring will be subject to the results of the initial monitoring exercise.
5.5.3
The
implementation schedule for the mitigation measures is presented in Appendixces C5a and C5b.