Table 6.1
Monitoring Programme
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring of design works against the
recommendations of the landscape and visual impact assessments within the
EIA, should be undertaken during
detailed design and tender stages, to ensure that they fulfil the intentions
of the mitigation measures. Any
changes to the design, including design changes on site should also be
checked. |
Report
by ER confirming that the design conforms to requirements of EP |
Approved by Client (TDD/CED/
HyD) |
At Completion of Design
Stage |
Construction |
Monitoring of the contractor’s operations
during the construction period. |
Report on Contractor's
compliance, by ET |
Counter-signature of report
by IEC |
Weekly |
Establishment Works |
Monitoring of the planting works during the 12 |
Report on Contractor's
compliance, by ET |
Counter-signature of report
by IEC |
3 months |
Design
Construction & Establishment
Period
Criteria for Exceedance
Construction and Establishment Stage
Table 6.2 Construction & Establishment
Periods
EVENT |
ACTION |
|||
ACTION LEVEL |
ET |
IEC |
ER |
CONTRACTOR |
Exceedance
on one occasion |
·
Identify Source ·
Inform IEC and ER ·
Discuss remedial actions with IEC, ER and
Contractor ·
Monitor remedial actions until rectification
has been completed |
·
Check report ·
Check Contractor's working method ·
Discuss with ET and Contractor on possible
remedial measures ·
Advise ER on effectiveness of proposed
remedial measures. ·
Check implementation of remedial measures. |
·
Notify Contractor ·
Ensure remedial measures are properly
implemented |
·
Amend working methods ·
Rectify damage and undertake any necessary
replacement |
Repeated
Exceedance |
·
Identify Source ·
Inform IEC and ER ·
Increase monitoring frequency ·
Discuss remedial actions with IEC, ER and
Contractor ·
Monitor remedial actions until rectification
has been completed ·
If exceedance stops, cease additional
monitoring |
·
Check monitoring report ·
Check Contractor's working method ·
Discuss with ET and Contractor on possible
remedial measures ·
Advise ER on effectiveness of proposed
remedial measures ·
Supervise implementation of remedial measures. |
·
Notify Contractor ·
Ensure remedial measures are properly
implemented |
·
Amend working methods ·
Rectify damage and undertake any necessary
replacement |
Landscape and
Visual Mitigation Measures during Construction Phase
·
Regular
checks shall be carried out to ensure that the work site boundaries are not
transgressed, hoardings are properly maintained and that no damage is being
caused to the surrounding areas (CM1).
Any irregularities shall be brought to the attention of the appropriate
adjacent management and maintenance agencies (e.g. private land owner, or HyD,
LCSD, or HKHA etc.). Remedial measures
shall be designed and implemented as appropriate.
·
Erection
of decorative screen hoarding particularly in areas adjacent to existing
developments (CM2). (Hoardings next to
undeveloped areas / construction sites need not be decorative).
·
Storage
of materials and plant shall be limited to areas less visible to visually
sensitive receivers (CM3).
·
Control
of night-time lighting to prevent upward glare to visually sensitive
receivers. Lighting should be directed
to where it is required for security purposes only (or night working if
permitted) (CM4).
·
Potential
conflicts between landscape works and other works shall be avoided. Utilities works in particular shall be
checked to ensure that they do not compromise landscape and visual mitigation
measures. Where potential conflicts
occur, engineering and utility layouts shall wherever
possible be redesigned to avoid conflicts (CM5).
·
For construction works associated with the
deckovers proposed in Assessment 1 - Worst Case Scenario, all impacts on all
trees and shrubs shall be minimised For construction works
associated with the deckovers proposed in Assessment 1 - Worst Case Scenario,
minimise construction impacts on trees and shrubs located along Road D1, and
transplant any trees that will be affected by deckovers (CM6).
Landscape and
Visual Mitigation Measures during Operation Phase
·
Aesthetic
design of elevated structures on Roads P2 and D10 with particular regard to
form and finishes so as to create as slender and elegant an appearance as
possible. ACABAS approval shall be
required (OM1).
·
Sensitive
integration of road embankments with surrounding ground levels (OM2). The engineering and landscape designs should
be prepared to create smooth changes in level at edges of embankments, with
rounded profiles wherever possible;
·
Aesthetic
design of all noise barriers and noise enclosures with particular regard to
chromatic treatments. ACABAS approval
shall be required (OM3);
·
Aesthetic
design of road lighting with glare control measures (OM4). Light fittings and columns should be of an
attractive design suitable to the streetscape setting and the overall style in
TKO. The light fittings should be of a
type which efficiently projects light onto the intended areas, and does not
cause any glare to adjacent residents;
·
Sensitive
hard and soft landscape design to edge of Area 77 and landfill beneath viaduct
(OM5) so as to provide an attractive waterfront edge and promenade walk;
·
Sensitive
hard landscape design along roadsides, with particular regard to the creation
of an attractive and user friendly pedestrian environment (OM6). The preferred width of soft landscape
amenity areas should generally
be 3m (but can be narrower e.g. at bus bay ingress / egress);
·
Tree,
shrub and climber planting adjacent to the roads and structures with particular
regard to the softening and screening of noise barriers, provision of shade
trees along footpaths, and climbing plants against abutment walls and viaduct
columns (OM7);
·
Tree,
planting along roadside amenity strips and central dividers to provide
structure planting for the townscape (OM8);
·
In
Assessment 1 (Worst Case Scenario) the two full deckovers over Road D1 in areas
65 and 67 shall be designed as landscape decks. Structural design of the deck shall allow for adequate soil depth
to permit tree planting (1.5m min). The appropriate maintenance agencies
shall be involved in the approval of the design of the deckover (refer to
Appendix C5).
·
Attractive
design of pedestrian subways including murals.
ACABAS approval shall be required. (OM10)