Civil Engineering Department
The
Government of the
Special
Administrative Region
Agreement No. CE 15/99
Environmental Impact Assessment for
Demolition of Kwai
Chung
Incineration Plant and
Kennedy Town CDA
Kwai Chung Incineration
Plant
EM&A
Manual
September
2001
Atkins China Ltd
DOCUMENT TITLE PAGE |
|||||
Client
: Civil
Engineering Department |
Contract
No. (if any) : - CE 15/99 |
||||
Project Title : Environmental Impact
Assessment for Demolition of Kwai Chung Incinerator
Plant and Kennedy Town CDA |
Project
No. : 2996 |
||||
Document
No. : 2996-OR027-03 |
Controlled
Copy No. : |
||||
Document
Title : Kwai Chung Incineration Plant EM&A Manual |
|||||
Covering
Letter / Transmittal Ref. No. : 2996/15.99/ELT /DG/jw/OG |
Date
of Issue : September
2001 |
||||
Revision, Review and Approval/Authorisation
Records |
|||||
|
|
/ |
/ |
/ |
|
|
|
/ |
/ |
/ |
|
03 |
4th Issue |
Various/ |
JWS/ |
DG/ |
|
02 |
3rd Issue |
Various/ |
JWS/ |
DG/ |
|
01 |
2nd Issue |
Various/ |
JWS/ |
DG/ |
|
00 |
1st Issue |
Various/ |
JWS/ |
DG/ |
|
Revision |
Description |
Prepared by / date |
Reviewed by / date |
App. or Auth. By / date |
|
Distribution
(if
insufficient space, please use separate paper)
Controlled Copy No. |
Issued to |
1 - 45 |
Civil Engineering Department |
46 - 47 |
ACL – ELAN |
48 - 65 |
ACE |
Note : App. and Auth. mean “Approved” and “Authorized” respectively.
Table of
Contents
1.2 Requirement
for EM&A Programme
1.4 Sensitive
Receivers and Constraints to Demolition
1.5 General
Approach to Demolition of Buildings and Structures at KCIP
1.6 Principles
of Chimney Demolition at KCIP
1.7 Remedial
Action Plan for Contaminated Soils
2.2 Total
Suspended Particulates
2.4 Laboratory
Measurement/ Analysis
2.8 Event
and Action Plan for Air Quality
4. Landfill Gas Precautionary Measures
4.2 Preparation
of Safety Plan
5.1 Sources
of Water Quality Impacts
5.3 Site
Run-off and Surface Water Drainage during Demolition
5.4 Site
Run-off and Surface Water Drainage during Soil Remediation
7.3 Protection
of Site Workers during excavation and treatment of soils
8.2 Compliance
with Legal and Contractual Requirements
9.2 Baseline
Monitoring Report
9.4 Contamination
Remediation Report
9.6 Interim
Notifications of Environmental Quality Limit Exceedances
10. Schedule of Mitigation from the EIA
Table 1.1 Structures to be demolished
at KCIP
Table 2.1 Action and Limit Levels for
Air Quality
Table 2.2 Event/Action Plan for Air
Quality
Table 4.1 Landfill
Gas Detection Action Plan
Table 6.1 Summary of Waste Management
Impacts
Table 7.1 Actions Required Post
Demolition
Table 8.1 Event Contingency Plan for
Environmental Complaints
Table 9.1 Sample Template for Interim
Notifications of Environmental Quality Limits Exceedances
Table 10.1 Schedule of Impacts and
Mitigation Measures
LIST
OF APPENDICES
Appendix A Preferred
Demolition Methodology (Extracted From WP1
Originally
Presented November 1999)
Appendix B Role Of Independent Checker (Environmental) IC(E)
Appendix C Water Quality Standards
Appendix D Criteria for Soil Contamination and Landfill Disposal
of Contaminated Soil
Appendix E Site Safety Precautions
LIST OF FIGURES
Figure 1.1 Kwai Chung Incineration Plant Constraints & Sensitive
Receivers
Figure 1.2 Typical
Site Hoarding
Figure 1.3 Project
Organisation Chart
Figure 2.1 Proposed
Dust Monitoring Location
Figure 7.1 KCIP
Borehole Locations and Contaminated Locations for Remedial Action
Figure 7.2 Principle
of Remedial Action Plan
LIST OF ABBREVIATIONS
|
Action/limit |
APCO |
Air Pollution control Ordinance |
AQO |
Air Quality Objective |
CNP |
Construction Noise Permit |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EM & A |
Environmental Monitoring and Audit |
EPD |
Environmental Protection Department |
ER |
Engineer’s Representative |
ET |
Environmental Monitoring Team |
ETL |
Environmental Monitoring Team Leader |
FIUO |
Factories and Industrial Undertakings Ordinance |
IC(E) |
|
HKPSG |
|
HVS |
High Volume Sampler |
HyD |
Highways Department |
KCPTW |
|
NCO |
Noise Control Ordinance |
NSR |
Noise Sensitive Receiver |
SR |
Sensitive Receiver |
TM |
Technical Memorandum |
TSP |
Total Suspended Particulates |
USAEPA |
|
WDO |
Waste Disposal Ordinance |
WPCO |
Water Pollution Control Ordinance |
· ensure that any environmental impacts resulting from the demolition of Kwai Chung Incineration Plant (KCIP) are kept to within acceptable levels;
· check that mitigation measures have been applied and are effective, and that the appropriate corrective actions are undertaken, if and when required; and
· provide a means of checking compliance with environmental objectives, recording anomalies and documenting corrective action.
· available information on the KCIP demolition project, the project organisation and demolition programme;
· general EM&A principles and the EM&A team organisation;
· monitoring parameters, schedules, Action/Limit Levels and action plans;
· complaints procedures; and
· reporting procedures.
· to provide a contract document between a Client and a Contractor defining the monitoring requirements and other duties in a form that is consistent with accepted contract practice.
· to provide additional controls that are implemented through the provisions of the Environmental Permit that are applicable to the project, but for which the responsibility does not rest with the Contractor (such as the role of the Environmental Team employed directly by the Proponent).
(a) to protect sensitive receivers from environmental impacts if mitigation is not implemented;
(b) to protect the ecosystem;
(c) to monitor activities in areas of high conservation value;
(d) to monitor the effectiveness of mitigation measures which involves a long period to establish;
(e) to monitor any unproven technology;
(f) to validate the hypothesis in analysis and design;
(g) to audit the changing project scheduling; and
(h) others.
Background
Table 1.1 Structures to be demolished at KCIP
Building |
Brief Description |
KCIP Chimney |
Reinforced concrete construction of diameter 6m – 12m and 150m high. Internal metal flues and platforms |
KCIP Buildings |
High, single storey steel frame, with weather cladding, pre-cast concrete slab, reinforced concrete partitions, corrugated metal sheet external wall and roof. The overall size is approximately 83m x 92m on plan. |
|
Single Storey. Approximately 4m x 13m on plan. |
Site Office/ |
Two storey high prefabricated building. Approximately 40m x 7.5m on plan. |
Residential
· The Rambler Channel marine traffic and ferry services.
· Rambler Channel Typhoon Shelter and PCWA.
· The Public Fill Barging Point (PFBP) at Area 30D.
· The seawalls and drainage channels other infrastructure around the area.
· The 200m Sewerage Tunnel Protection Area.
· The Kwai Ching Primary Treatment Works.
·
The Kwai Chung Park (
·
The
· The Tsing Yi Bridge.
·
·
Container
Terminal 5 (
General Demolition Principles
General Safety Measures
General Approach
· sampling, analysis and statistical evaluation of monitoring parameters with reference to the EIA Study recommendations and requirements.
· environmental site surveillance;
· audit of compliance with environmental protection and pollution prevention and control regulations;
· monitor the implementation of the environmental mitigation;
· monitor compliance with the environmental protection clauses/specifications in the Contract;
· review construction (demolition) programme and comment as necessary;
· review construction (demolition) methodology and comments as necessary;
· complaint investigation , evaluation and identification of corrective measures;
· liaison with IC(E) on environmental performance matters and submission of EM&A deliverables to IC(E) for approval; and
·
advise on environmental improvement
and enhancement.
· 0.6-1.7 m3/min (20-60 SCFM) adjustable flow range;
· equipped with a timing/control device with +/- 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
· capable of providing a minimum exposed area of 406 cm2 (63 in2);
· flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;
· equipped with a shelter to protect the filter and sampler;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter; and
· capable of operating continuously for 24-hour period.
· a horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;
· the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
· a minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;
· a minimum of 2 metre separation from any supporting structure, measured horizontally is required;
· no active furnace or active incinerator flues should be nearby;
· airflow around the sampler should be unrestricted;
· the sampler should be more than 20 metres from any dripline;
· any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring;
· permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity is needed to operate the samplers.
Total Suspended Particulates
Total Suspended Particulates
Table 2.1 Action and Limit Levels for Air Quality
Table 2.2 Event/Action Plan for Air Quality
|
|
|
ACTION |
|
EVENT |
ET |
IC(E) |
ER |
CONTRACTOR |
ACTION LEVEL |
||||
1. Exceedance for one sample |
1. Identify
source 2. Inform
(C(E) and ER 3. Repeat
measurement to confirm finding 4. Increase
monitoring frequency to daily |
1. Check monitoring data submitted by ET 2. Check Contractor’s working method |
1. Notify
Contractor 2. Check monitoring
data and Contractor's working methods |
1. Rectify any unacceptable practice 2. Amend working methods if appropriate |
2. Exceedance for two or more consecutive samples |
1. Identify
source 2. Inform
IC(E) and ER 3. Repeat measurements
to confirm findings 4. Increase
monitoring frequency to daily 5. Discuss
with Contractor , IC(E) and ER for remedial actions required 6. If exceedance continues, arrange meeting with IC(E) and ER 7. If exceedance stops, cease additional monitoring |
1. Checking monitoring data submitted by ET 2. Check Contractor’s working method 3. Discuss with ET and Contractor on possible
remedial measures 4. Advise the ER on the effectiveness of the
proposed remedial measures 5. Supervise implementation of remedial
measures |
1. Confirm
receipt of notification of failure in writing 2. Notify
Contractor 3. Check
monitoring data and Contractor's working methods 4. Discuss with
IC(E) and Contractor on potential remedial actions 5. Ensure remedial
actions properly implemented |
1. Submit proposals for remedial actions to ER
within 3 working days of notification 2. Implement the agreed proposals 3. Amend proposal if appropriate |
LIMIT LEVEL |
||||
1. Exceedance for one sample |
1. Identify source 2. Inform ER and EPD 3. Repeat measurement to confirm finding 4. Increase monitoring frequency to daily 5. Assess effectiveness of Contractor's
remedial actions and keep IC(E), EPD and ER informed of the results |
1. Checking monitoring data submitted by ET 2. Check Contractor’s working method 3. Discuss with ET and Contractor on possible
remedial measures 4. Advise the ER on the effectiveness of the
proposed remedial measures 5. Supervisor implementation of remedial measures |
1. Confirm
receipt of notification of failure in writing 2. Notify
Contractor 3. Check
monitoring data and Contractor's working methods 4. Discuss with
ET Leader and Contractor potential remedial actions 5. Ensure
remedial actions properly implemented |
1. Take immediate action to avoid further exceedance 2. Submit proposals for remedial actions to ER
within 3 working days of notification 3. Implement the agreed proposals 4. Amend proposal if appropriate |
2. Exceedance for two or more consecutive samples |
1. Identify source 2. Inform IC(E), ER and EPD the causes &
actions taken for the exceedances 3. Repeat measurement to confirm findings 4. Increase monitoring frequency to daily 5. Investigate the causes of exceedance, Contractor’s working procedures to identify
possible mitigation 6. Arrange meeting with IC(E) and ER to
discuss the remedial actions to be taken 7. Assess effectiveness of Contractor's
remedial actions and keep IC(E), EPD and ER informed of the results 8. If exceedance
stops, cease additional monitoring |
1. Discuss amongst ER, ET and Contractor as
the potential remedial actions 2. Review Contractor’s remedial actions
whenever necessary to ensure their effectiveness and advise the ER
accordingly 3 Supervise the implementation of remedial
measures |
1. Confirm
receipt of notification of failure in writing 2. Notify
Contractor 3. Carry out
analysis of Contractor's working procedures with IC(E) to determine possible
mitigation to be implemented 4. Discuss amongst
Environmental Team Leader and the Contractor potential remedial actions 5. Review
Contractor's remedial actions whenever necessary to assure their
effectiveness 6. If exceedance continues, consider what portion of the work
is responsible and instruct the Contractor to stop that portion of work until
the exceedance is abated |
1. Take immediate action to avoid further exceedance 2. Submit proposals for remedial actions to ER
within 3 working days of notification 3. Implement the agreed proposals 4. Resubmit proposals if problem still not
under control 5. Stop the relevant portion of works as
determined by the ER until the exceedance is abated |
· Adoption of good site practices;
· Avoid practices likely to raise dust level;
· Frequent cleaning and damping down of stockpiles and dusty areas of the site;
· Reducing drop height during material handling or wall felling;
· Imposing a vehicle speed restriction of 15 km/hr within the site;
· Provision of wheel washes facilities for site vehicles leaving the site;
· Regular plant maintenance to minimise exhaust emission; and
· Collection and sweeping up of accumulations of surplus dust and debris at the end of each shift.
· details of responsible parties and timeframes for actions/responses to different monitoring scenarios, details of essential staff training requirements, and requirements for back-up monitoring equipment should also be provided;
· all relevant workers should undergo training about the risks and indications of landfill gas and should be thoroughly versed in first aid and emergency and evacuation techniques;
· a no smoking policy should be strictly applied;
· the possibility of methane rich air being taken into diesel-engined plant should not be overlooked;
· provisions should also be made to control water contamination that may arise if leachate infiltrates from the landfill;
· a mechanical ventilation system should be in use at all times when personnel are working on qualifying works. No such works should be carried out in the absence of mechanical ventilation or without the presence of a suitably trained safety officer.
· all electrical equipment (including extension leads) should be fitted with spark arrestors or be intrinsically safe;
· as a minimum, no qualifying works should be undertaken in the absence of fire extinguishers or emergency breathing apparatus (details should be provided in the safety plan);
· monitoring of methane, carbon dioxide and oxygen should be undertaken at all times during qualifying works using suitable equipment. Specific details of measurement equipment, personnel, lines of responsibility and monitoring frequency should be set out in the Safety Plan. The actions set out in Table 4.1 below will be carried out in the event of gas trigger levels being breached.
Table 4.1 Landfill Gas Detection Action Plan
Parameter |
Measurement |
Required Action |
O2 |
< 19 % |
Increase ventilation to restore O2 to >19% |
< 18 % |
Stop work |
|
Evacuate Personnel |
||
Increase ventilation to restore O2 to >19% |
||
CH4 |
> 10 % LEL |
Prohibit hot works |
Increase ventilation to restore CH4 to < 10 % LEL |
||
> 20 % LEL |
Stop work |
|
Evacuate Personnel |
||
Increase ventilation to restore CH4 to < 10 % LEL |
||
CO2 |
> 0.5 % |
Increase ventilation to restore CO2 to < 0.5 % |
> 1.5 % |
Stop work |
|
Evacuate Personnel |
||
Increase ventilation to restore CO2 to < 0.5 % |
Methane |
0 - 100 % LEL and 0 -
100 % v/v |
Carbon Dioxide |
0 - 20 % v/v |
Oxygen |
0 - 21 % v/v |
· The use of sediment traps, where appropriate; and
· The adequate maintenance of drainage systems to prevent flooding and overflow.
· minimising the ingress of surface water, which would mix with groundwater extracted during ground excavation if any; and
· reusing water on-site in ground remediation processes (mixing with cement).
Treatment of Surplus Groundwater Prior to Discharge
· Construction and Demolition (C&D) materials;;
· Chemical waste; and
· General refuse.
Table 6.1 Summary of Waste Management Impacts
Introduction
Waste Management Hierarchy
· Avoidance and minimisation by not generating waste through changing or improving practices and design;
· Reusing materials and therefore avoiding disposal (generally with only limited reprocessing);
· Recovery and recycling, avoiding disposal (although reprocessing may be required); and
· Treatment and disposal, according to relevant laws, guidelines and good practice.
C&D material
Chemical Waste
· Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;
· Have a capacity of less than 450 l unless the specifications have been approved by the EPD; and
· Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.
· Be clearly labelled and used solely for the storage of chemical waste;
· Be enclosed on at least 3 sides;
· Have an impermeable floor and bunding, of capacity to accommodate 100% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;
· Have adequate ventilation;
· Be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and
· Be arranged so that incompatible materials are adequately separated.
· Be via a licensed waste collector; and
· Be to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility which also offers a chemical waste collection service and can supply the necessary storage containers; or
· Be to a recycling or reprocessing facility , licensed by EPD.
Disposal of Residual Ash Waste (Ash Bunker Wall)
Protection of Site Workers
General Refuse
Storage areas for different waste types
Trip-ticket system
Training and Records of wastes
· Wastes should be handled and stored in a manner which ensures that they are held securely without loss or leakage thereby minimising the potential for pollution;
· Only reputable waste collectors authorised to collect the specific category of waste concerned should be employed;
· Appropriate measures should be employed to minimise windblown litter and dust during transportation by either covering trucks or transporting wastes in enclosed containers;
· The necessary waste disposal permits should be obtained from the appropriate authorities, if they are required, in accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation and the Government Land Ordinance (Cap 28);
· Collection of general refuse should be carried out frequently, preferably daily;
· Waste should only be disposed of at licensed sites and site staff and the civil engineering Contractor should develop procedures to ensure that illegal disposal of wastes does not occur;
· Waste storage areas should be well maintained and cleaned regularly; and
· Records should be maintained of the quantities of wastes generated, recycled and disposed, determined by weighing each load.
EM&A Requirements
Management of Contaminated Soil Material
Volume of Soil for Immobilisation
Volume of Soil to Landfill
Table 7.1 Actions Required Post Demolition
Borehole |
Action Required |
Remove concrete surface and clear
uncontaminated surface material and stockpile |
Proposed depth of Material for Removal or
Treatment |
Remedial Action * |
Estimate quantity of contaminated material
for Treatment (m3 , #) |
Reassurance /
Confirmatory Sampling |
Sampling Strategy |
B1 |
Yes |
Down to 1m depth |
Immobilisation * |
100 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
|
Yes |
Down to 2m depth |
2m to 3m |
Immobilisation * |
100 |
Yes, determine extent of HM (Pb, Cu) contamination
at edge and base of hole.* |
5 samples 5m N, S, E, W and base of borehole, |
|
B3 |
Yes |
Down to 2m depth |
Immobilisation * |
150 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
|
B4 |
Yes |
Concrete down to 1.5m depth |
Below concrete down to 2m |
Immobilisation * |
50 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
B5 |
Yes |
Down to 1.5m depth |
1.5m to 3.5m |
Immobilisation * |
200 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
B6 |
Yes |
Concrete down to 0.4m depth |
Below concrete down to 1.4m |
Immobilisation * |
100 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
B7 |
Yes |
Concrete down to 0.9m depth |
Below concrete to 1.9m |
Immobilisation * |
100 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
B8 |
No Clean Up |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
B9 |
No Clean Up |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
B10 |
No Clean Up |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
B11 |
Yes |
Down to 1.5m depth |
1.5m to 3.5m |
Immobilisation * |
200 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
B12 |
No Clean Up |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
B13 |
No Clean Up |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
B14 |
No Clean Up |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
B15 |
Yes $$ |
Excavate concrete down to 0.9m.
(TPH contamination
as bolus of tarry bitumen at 0.9m (only). |
0.9m to 2.0m |
TCLP test followed by removal of 1m to 2m landfill. Immobilisation if necessary **. @ |
110 |
Yes, determine extent of HM
(Cu and TPH) contamination. * $$ |
5 samples 5m N, S, E, W and
base of borehole, |
B16 |
No Clean Up |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
B17 |
No Clean Up |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
B18 |
Yes |
Excavate concrete down to 0.6m depth |
Below concrete (0.6m) down to 1.6m |
TCLP test followed by removal of 0.6m to 1.6m to landfill, @. |
100 |
Yes, determine extent of
TPH contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
B19 (surface) |
No Clean Up |
Concrete down to 1.6m depth |
N/A |
N/A |
N/A |
N/A |
N/A |
B19 (middle) |
Yes |
N/A |
1.6m down to 2.6m |
Immobilisation. |
100 |
Yes, determine extent of HM
(Cu, Zn and Pb) contamination at edge and base of
hole.* |
5 samples 5m N, S, E ,W of borehole,
|
B19 (bottom) |
Yes |
N/A |
2.6m down to rockhead (say 3.2m) |
TCLP test followed by removal of 2.6m to 3.6m landfill.
Immobilisation if necessary **, @. |
<100 |
Yes, determine extent of HM
(Pb, Zn and Cu) PCB, PAH and TPH) contamination at edge
and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
B20 |
No clean Up |
Down to 2.5m depth |
N/A |
N/A |
N/A |
N/A |
N/A |
B20 |
Yes |
N/A |
2.5m to 4.0m (or rockhead) |
TCLP test followed by removal of 2.5m to 4m to landfill. Immobilisation
if necessary**, @ |
150 |
Yes, determine extent of HM
(Cu, Pb, Zn) PAH and TPH contamination at edge and
base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
B21 (top) |
No Clean Up |
Concrete down to 2.5m Remove soil to 4.0m depth |
Assume surface to 4.0m not contaminated. |
N/A |
N/A |
N/A |
N/A |
B21 (bottom) |
Yes |
N/A |
4.0m to 6.0m contaminated |
Immobilisation * |
200 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N & S, 2m
E & W and base of borehole. |
B22 |
Yes |
Concrete down to 1.5m depth |
Immediately below concrete at 1.5m down to 4.0m (or rockhead) |
Immobilisation* |
250 |
Yes, determine extent of HM
(Pb, Cu and Zn) contamination at edge and base of
excavated hole.* |
5 samples 5m N, S, E ,W and
base of borehole |
B23 |
Yes |
Down to 1.5m depth |
Immobilisation* |
200 |
Yes, determine extent of HM
(Pb) contamination at edge and base of hole.* |
5 samples 5m N, S, E, W and
base of borehole, |
|
Refuse and Ash Bunkers |
Yes |
N/A |
N/A |
Landfill disposal |
To be determined after inspection of bunkers |
Examine bunker refuse prior
to demolition |
Consider analysis depending
on bunker contents |
Main Hall Ash Bunker Wall |
Yes |
N/A |
|
Remove ash under controlled conditions up to 5m up wall. Landfill disposal to meet EPD criteria. |
Assume materials within 5m of ground contaminated |
Visual inspection of walls
to ensure all visible dust and debris removed. |
- |
Main Hall Floors |
Yes |
N/A |
- |
Remove ash under controlled conditions up to 5m from wall. Landfill disposal to meet EPD criteria. |
Assume materials within 5m of wall contaminated. |
Visual inspection of floor within
5m of wall to ensure all visible dust and debris removed. |
- |
Chimney |
Reassurance sampling only |
N/A |
|
|
|
Review requirements after
demolition and confirmatory sampling. |
- |
* If contamination confirmed by reassurance sampling
extract a further 1.0m
into the soil, immobilise and resample.
** TCLP test for all
metals identified in Table E1 in EPD Contaminated Sites Investigation and
Remediation Guidance Notes
$$ TPH Contamination
isolated to bolus of tarry bitumen found only at one depth. Isolated contaminant.
# According to the
quantity of contaminated material estimated for each borehole location, the
total quantity of contaminated soil should be about 2200m3. .
About 1750m3. of
the total volume is estimated to require treatment on site by immobilisation
(Broad brush estimate based on depths to which materials >Dutch B are
identified by current round of sampling and all material within 5m (10m x 10m
square hole) to that depth (rounded up to nearest 10m3.)
@ Broad brush estimate
of materials to be transferred to landfill (rounded up to nearest 10m3. (Total about 450m3, broad brush
estimate as # , requiring confirmation).
· the EIA Report recommendations on environmental protection and pollution control mitigation measures;
· works progress and programme;
· individual works methodology proposals (which shall include proposals on associated pollution control measures);
· the contract specifications on environmental protection;
· the relevant environmental protection and pollution control laws; and
· previous site inspection results.
· log complaint and date of receipt onto the complaint database;
· investigate the complaint to determine its validity, and to assess whether the source of the problem is due to works activities;
· if a complaint is valid and due to works, identify mitigation measures;
· if mitigation measures are required, advise the Contractor accordingly;
· review the Contractor’s response on the identified mitigation measures, and the updated situation;
· if the complaint is submitted by EPD, submit interim report to EPD on status of the complaint investigation and follow-up action within the time frame agreed between the ER and relevant Government Departments;
· undertake additional monitoring and audit to verify the situation if necessary, and review that any valid reason for complaint does not recur;
· report the investigation results and the subsequent actions to the source of the complaint for responding to the complainant (if the source of complaint is EPD, the results should be reported within the time frame agreed with the ER and relevant Government Departments); and;
· record the complaint, investigation, the subsequent actions and the results in the monthly EM&A reports.
Table 8.1 Event Contingency Plan for Environmental Complaints
¨ action party
à enter comments/proposals into appropriate complaint record where applicable
· a 1-2 page executive summary;
· brief project background information;
· drawings showing locations of the baseline monitoring station;
· monitoring results (in both hard and diskette copies) together with the following information:
- monitoring methodology;
- equipment used and calibration details;
- parameters monitored;
- monitoring locations; and
- monitoring date, time, frequency and duration.
· details on influencing factors, including:
- major activities, if any, being carried out on the site during the period;
- weather conditions during the period; and
- other factors which might affect the results.
· determination of the Action and Limit Levels for each monitoring parameter and statistical analysis of the baseline data;
· revisions for inclusion in the EM&A Manual; and
· comments and conclusions.
· 1-2 pages executive summary;
· basic project information including a synopsis of the project organisation, programme and management structure, and the work undertaken during the month;
· a brief summary of EM&A requirement including :
- all monitoring parameters;
- environmental quality performance limits (Action and Limit levels);
- Event-Action Plans;
- environmental mitigation measures, as recommended in the project EIA study final report;
- environmental requirements in contract documents;
· advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA study report, summarised in the updated implementation schedule;
· drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
· monitoring results (in both hard and diskette copies) together with the following information:
·
monitoring methodology;
·
equipment used and calibration details
·
parameters monitored
·
monitoring locations
·
monitoring date, time, frequency, and duration;
·
major activities being carried out on site during the
period;
·
weather conditions during the period; and
·
any other factors which might affect the monitoring
results;
·
advice on the solid and liquid waste management
status;
·
a summary of non-compliance (exceedances)
of the environmental quality performance limits (Action and Limit levels);
·
a review of the reasons for and the implications of
non-compliance and deficiency reporting and any follow-up procedures;
·
a description of the actions taken in the event of
non-compliance and deficiency reporting and any follow-up procedures related to
earlier non-compliance;
·
a summary record of all complaints received (written
or verbal) for each media, including locations and nature of complaints,
liaison and consultation undertaken, actions and follow-up procedures taken and
summary of complaints; and
·
an account of the future key issues as
reviewed form the works programme and work method statements.
· title page;
· Executive Summary (1-2 pages);
-
breaches of
- complaint Log;
- reporting Changes; and
- future key issues.
· contents page;
· environmental status;
- drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
- summary of non-compliance with the environmental quality performance limits; and
- summary of complaints.
· environmental issues and actions;
- review issues carried forward and any follow-up procedures related to earlier non-compliance (complaints and deficiencies);
- description of the actions taken in the event of non-compliance and deficiency reporting;
- recommendations (should be specific and target the appropriate party for action); and
- implementation status of the mitigation measures and the corresponding effectiveness of the measures.
· future key issues;
· appendices;
-
- graphical plots of trends of monitored parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:
i. major activities being carried out site during the period;
ii. weather conditions during the period; and
iii. any other factors which might affect the monitoring results.
- monitoring schedule for the present and next reporting periods;
- cumulative complaints statistics; and
- details of complaints, outstanding issues and deficiencies.
· all reports issued;
· site inspection forms and reports;
· monitoring field and laboratory records;
· complaints and related follow-up action information; and
· revised mitigation measures proposals adopted during the course of the works programme.
Table 9.1 Sample Template for Interim Notifications of Environmental Quality Limits Exceedances
Project |
|
Date |
|
Time |
|
Monitoring Location |
|
Parameter |
|
Action & Limit Levels |
|
Measured Level |
|
Possible reason for Action or Limit Level
Non-compliance |
|
Actions taken / to be taken |
|
Remarks |
|
|
|
|
|
Location Plan |
Prepared by : |
|
|
|
|
Designation : |
|
|
|
|
Signature : |
|
|
|
|
Date : |
|
|
|
|
Table 10.1 Schedule of Impacts and Mitigation Measures
No. |
Activity |
Mitigation/EIA
Recommendations |
Responsibility for
Implementation |
Location Duration
completion of measures |
Implemen-tation Stage |
Relevant Guidelines
Legislation |
1 |
Ash Disposal |
|
|
|
|
|
I |
Treatment |
Reconfirm
extent of contaminated ash deposits by sampling for dioxins and furans. Handling, transportation and disposal of the
ash waste in line with relevant regulations.
Collection, immobilisation and testing of waste for disposal to
landfill shall be carried out according to the relevant regulations and
recommendations of the EIA including immobilisation by collection and mixing
the ash material with cement. Pilot
mixing and TCLP tests should establish the ratio of cement to ash to the
satisfaction of EPD. Ash waste to be
treated and placed into steel drums lined with plastic sheeting. The drums should be adequately sealed and
in new or good condition. Prior
agreement of the disposal criteria from EPD and agreement to disposal from
the landfill operator must be obtained. |
CED’s Contractor |
KCIP work areas.
Duration of the ash removal |
A@ |
1, 10, EIA |
II |
Disposal |
To
monitor the disposal of waste at landfills, a “trip-ticket” system (WBTC No.
5/99) for all solid waste transfer/disposal operations should be
implemented. The system should be
included as a contractual requirement, and monitored by the Environmental Team
and audited by the Independent Checker (Environment). |
CED’s Contractor |
As above |
A |
1, 5, 9 |
III |
Asbestos
Removal |
An
asbestos abatement programme should be submitted to EPD for approval prior to
the commencement of the asbestos abatement work. |
CED
and Contractor |
As above |
A |
4 |
2 |
Demolition |
|
|
|
|
|
A1 |
Non-blasting
Methodology |
Demolition
by Non-Blasting Methodology Only. All structures
and buildings should be demolished and removed prior to demolition of
chimneys |
CED |
KCIP work areas.
Duration of the demolition |
C# |
8 |
A2 |
Waste
Management Plan. |
A
Waste Management Plan shall be submitted to EPD for approval. The Waste Management Plan shall include,
but not be limited to, the findings of the Waste Management Paper of the EIA,
the types, quantities, disposal methods, timing, locations
of final disposition, responsibilities for implementation and the possible
recycling and reuse of wastes generated. |
CED
and Contractor |
Prior to
commencement of the demolition works |
Prior to C# |
1 |
B |
Material
Storage |
Covers
for dusty stockpiles and control of dust emissions from construction (demolition)
works requires appropriate dust control measures to be implemented in
accordance with the requirements in the Air Pollution Control (Construction
Dust) Regulation. |
CED’s Contractor |
KCIP work areas.
Duration of the demolition |
C |
4 |
C |
Vehicle
movement |
Haul
road watering, vehicle wheel wash prior to exit. Where practical, access
roads should be protected with crushed gravel. |
CED’s Contractor |
As above |
C |
4 |
D |
Plant
maintenance |
All
plant shall be maintained to prevent any undue air emissions. |
CED’s Contractor |
As above |
Prior to start of
works |
4 |
E |
Demolition
Techniques |
Selection
of non-blasting demolition techniques to minimise noise and vibration. |
CED’s Contractor |
As above |
C |
8 |
F |
Plant
maintenance |
All
plant shall be maintained to prevent any undue noise nuisance. |
CED’s Contractor |
As above |
C |
2, 3 |
G |
Wheel
wash |
All
wheel wash water shall be diverted to a sediment pit. |
CED’s Contractor |
As above |
C |
5 |
H |
Sediment
control |
Sediment
removal facilities shall provided and be maintained and excavated as
necessary to prevent sedimentation of channels. Perimeter channels should be provided. Works
should be programmed for the dry season where feasible. Environmental guidelines for the handling
and disposal of discharges from construction sites, as stipulated in the
Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) to be followed. |
CED’s Contractor |
As above |
C |
5, 12 |
I |
Surface
water diversion |
All
clean surface water shall be diverted around the site. |
CED’s Contractor |
As above |
C |
5, 12 |
J |
Fuel
can storage |
All
fuel cans shall be placed within a bunded area. Any
fuel spills shall be mopped up as necessary. |
CED’s Contractor |
As above |
C |
5,6 |
K |
Material,
plant move-ment & fuel can filling. |
Any
fuel or oil spills shall be excavated and disposed of. |
CED’s Contractor |
As above |
C |
6,7 |
L |
Generators
|
All
generators shall be placed within a bunded area.
Any fuel spills shall be mopped up as necessary. |
CED’s Contractor |
As above |
C |
5,6,7 |
M |
Material
containers |
All
empty bags and containers shall be collected for disposal. |
CED’s Contractor |
As above |
C |
6,7 |
N |
Worker
generated litter and Waste |
Litter
receptacles shall be placed around the site. Litter shall be taken regularly to
the refuse collection points. Chemical toilets (or suitable equivalent)
should be provided for workers. Any canteens should have grease traps. |
CED’s Contractor |
As above |
C |
6 |
O |
Neighbourhood
nuisance |
All
complaints regarding construction works shall be relayed to the environmental
team. |
CED’s Contractor |
As above |
C |
1, 6 |
P |
Legal
requirements |
Different
types of waste should be segregated, stored, transported and disposed of in accordance
with the relevant legislative requirements and guidelines |
CED’s Contractor |
As above |
C |
1,6 |
Q |
On-site
separation |
On-site
separation of municipal solid waste and construction/demolition wastes shall be
conducted in order to minimise the amount of solid waste to be disposed to
landfill. |
CED’s Contractor |
As above |
C |
1, 11 |
R |
Temporary
storage area |
Separated
wastes should be stored in different containers, skips, or stockpiles to enhance
reuse or recycling of materials and encourage their proper disposal. |
CED’s Contractor |
As above |
C |
1, 11 |
S |
Record
of wastes |
Records
of quantities of wastes generated, recycled and disposed (with locations)
shall be kept. |
CED’s Contractor |
As above |
C |
1, 9 |
T |
Trip-ticket
system |
To
monitor the disposal of waste at landfills and control fly-tipping, a
“trip-ticket” system under WBTC N0.5/99 for all solid waste transfer/disposal
operations should be implemented. The system
should be included as a contractual requirement, and monitored by the
Environmental Team and audited by the Independent Checker (Environment). |
CED’s Contractor |
As above |
C |
1, 9 |
3 |
Soil Remediation Phase |
|
|
|
|
|
U |
B,
C, D, F, G, I, J, K, L, M, N, O, P, Q, R, S and T as above |
As
above (see W for soil remediation). |
As
above |
As above |
R |
As above |
V |
De-watering |
Collect
and recycle extracted groundwater and leachate by
mixing with cement for soil remediation.
Environmental guidelines for the handling and disposal of discharges
from construction sites, as stipulated in the Practice Note for Professional
Persons, Construction Site Drainage (ProPECC PN
1/94) to be followed. Any surplus groundwate and leachate requiring
disposal to be disposed of under the relevant legislation or treated to meet
the standards given in Table 9a of the WPCO TM. |
CED’s Contractor |
KCIP work areas.
Duration of the soil remediation |
R |
5 |
W |
Immobilisation |
Immobilisation
and testing of waste soil shall be carried out according to the relevant
regulations and recommendations of the EIA including immobilisation by
collection and mixing the contaminated soil material with cement. Pilot mixing and TCLP tests should verify
the effectiveness and establish the ratio of cement to soil to the
satisfaction of EPD. Reassurance
confirmatory sampling shall be carried out to confirm the extent of
contamination. Soil waste to be cast
in blocks and replaced in the ground.
Extracted soils and materials and stabilisation/solidification to be
conducted in bunded area to prevent surface
run-off. See also item 2(H)
above. Final soil decontamination
report to be submitted to EPD. |
CED’s Contractor |
As above |
R |
1, 10 |
4 |
Monitoring and Audit |
To
be carried out in accordance with the Schedule in the EM&A Manual. |
CED*/
Contractor/ RSS |
KCIP works areas During demolition
and at end of demolition throughout execution of Remediation Action Plan |
C |
1 |
* Normally undertaken by a specialist monitoring team employed directly by the proponent and audited by the Independent Checker (Environment)
@ A = during ash removal (before demolition)
# C = during construction (i.e. demolition phase).
* R = during soil remediation phase (after demolition)
1.
Environmental Impact
Assessment Ordinance Technical Memorandum (EIAO)
2.
Noise Control Ordinance
3.
The ProPECC
Note PN2/93 (Construction Noise daytime limits)
4.
Air Pollution Control
Ordinance (APCO)
5.
Water Pollution Control
Ordinance (WPCO)(Cap. 358)
6.
Waste Disposal Ordinance (Cap
354)
7.
Waste Disposal (Chemical
Waste)(General) Regulation (Cap 354)
8.
Draft Code of Practice on
Demolition of Buildings (BD, 1998)
9.
Works Bureau Technical
Circular No. 5/99, Trip-ticket System for Disposal of Construction and
Demolition Material
10. Guidance
Notes for Investigation and Remediation of Contaminated Sites
11. Works
Bureau Technical Circular No. 5/98, On Site Sorting of Construction Waste on
Demolition Sites
12. ProPECC Note PN 1/94Construction Site Drainage
List of Abbreviations
AAP |
Asbestos Abatement Plan |
ACE |
Advisory Committee on Environment |
ACM |
Asbestos Containing Material |
AIR |
Asbestos Investigation Report |
AP |
Authorised Person |
APCO |
Air Pollution Control Ordinance |
BOO |
Building Ordinance Office |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CED |
Civil Engineering Department |
CPLD |
Committee on Planning & Land Development |
DCDB |
Draft Code of Practice on Demolition of Buildings |
DSD |
Drainage Services Department |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EM&A |
Environmental Monitoring & Audit |
EMSD |
Electrical & Mechanical Services Department |
EPD |
Environmental Protection Department |
G I/C |
Government, Institutional/Community |
GDBL |
Gin Drinker’s Bay Landfill |
KCIP |
Kwai Chung Incineration Plant |
KCPTW |
Kwai Chung Preliminary Treatment Works |
LEHAGN |
Landfill Gas Hazard Assessment Guidance Note |
NWFB |
|
PCWA |
Public Cargo Working Area |
PFBP |
Public Fill Barging Point |
PQA |
Preliminary Quanlitative Assessment |
PTW |
Preliminary Treatment Works |
RAC |
Registered Asbestos Consultant |
RSE |
Resident Site Engineer |
SR |
Sensitive Receiver |
TIA |
Traffic Impact Assessment |
TM |
Technical Memorandum |
I.
The Study Brief requires that the alternative methods of demolition of the Kwai Chung Incineration Plant and the
Kennedy Town Comprehensive Development Area (the Project) to be investigated as a basis
for defining the activities to be addressed within the environmental
assessment. This Working Paper sets out
the analysis of the alternative demolition options for both facilities and the
major conclusions regarding demolition methods.
The Working Paper also presents the major
constraints associated with the Project.
II.
The PPFS for Kwai Chung Incineration Plant concluded that it was not feasible to
demolish the chimney by implosion (blasting) due to the short distances between
the chimney and the surrounding structures and other local facilities, the high
risk and the lack of cost effectiveness.
Preliminary
investigations for this Study have confirmed the severe concerns raised by various Government departments at the PPFS stage
and confirmed the conclusion that blasting techniques should not be used for
the felling of the chimney or the main building structures.
III.
In addition to the original concerns it is now confirmed that parts of the
chimney and the cladding of the buildings include asbestos containing materials
(ACM). The presence of these materials
alone is sufficient grounds to require that a non-blasting approach is adopted
as all ACM must be removed in line with statutory requirements. A conceptual demolition method has been
developed which avoids the any form of blasting to fell the chimneys or the
associated buildings. Details of the
engineering requirements for such an approach are presented in this report.
IV.
The details of the constraints to demolition are presented in the main
report. A conceptual demolition method
has been developed which avoids most of the complications associated with
blasting and provides flexibility for the implementation stages of the works.
V. The conclusion of this Working Paper is that non-explosive demolition methods should be used for the demolition of the Kwai Chung Incineration Plant.
A1.1.1 The Civil Engineering Department (CED) has appointed Atkins China Ltd. (ACL) to undertake the Environmental Impact Assessment (EIA) for the Demolition of the Kwai Chung Incineration Plant and the Kennedy Town Comprehensive Development Area (Agreement No. CE 15/99). The Kwai Chung Incineration Plant (KCIP) ceased to operate in May 1997 and has been decommissioned and the facilities require demolition. The main plant items have already been removed. The demolition of the remaining facilities on the site constitutes the Project as defined under the requirements of the Environmental Impact Assessment Ordinance (EIAO).
A1.1.2 The
primary aim of this paper is to establish a conceptual demolition method and to
define the major constraints, which must be considered in the final demolition
process. The paper presents information to facilitate
decisions on acceptable conceptual demolition methods for the Project as a
basis for the remainder of the Study.
A1.1.3 To satisfy the requirements of the EIA it is
necessary to define clearly the nature of the works involved in the demolition
process. The development of a conceptual
scheme for the demolition process in turn requires detailed analysis of the
facilities and those surrounding uses and activities which might influence
decisions on demolition. This paper
presents this analysis. The conceptual
scheme for demolition of the facilities has been developed based on practical
experience and current demolition practice in Hong Kong as well as
internationally.
A1.1.4 A description of the elements of the community and environment, likely to be affected by the proposed demolition activities is provided to ensure that any potential constraints on demolition works due to the need to protect sensitive receivers, surrounding infrastructure or facilities are considered. Such requirements may constrain the way the proposed Project is executed and affect the methods that can be used so as to influence the choice of demolition methods.
A1.2 Structure of the Report
A1.2.1 In addition to this introduction Working Paper 1 Report includes sections covering the following:
· Section 2 Project and Study Area
· Section 3 Appreciation and Understanding of Constraints to Demolition.
· Section 4 General Approach to Demolition of Buildings and Structures.
· Section 5 Conceptual Demolition Method for Chimney at KCIP.
· Section 6 Conclusions.
A2 proJecT and STUDY AREA
A2.1 Kwai
Chung Incineration Plant (KCIP) Study Area
A2.1.1 The Kwai Chung Incineration Plant (KCIP) is located at Kwai Yue Road, Kwai Chung, facing the Rambler Channel and Tsing Yi South Bridge, with a site area of about 14,000 m2 (Figure 2.1). The site is close to the Kwai Chung Park, the former Gin Drinkers Bay Landfill, and therefore may be impacted by contaminants and landfill gas generated from the landfill site.
A2.1.2 The KCIP site is adjacent to the Kwai Chung Preliminary Treatment Works (KCPTW) and part of the KCIP site overlaps the “Sewerage Tunnel Protection Area” of the Strategic Sewerage Disposal Scheme (SSDS), administered by Drainage Services Department (DSD).
A2.1.3 The KCIP site is currently zoned as “G/IC”,
with no identified long term use of the area after demolition. However, the future land use is unlikely to
be residential given the close proximity of the site to Gin Drinkers Bay
Landfill and the
A2.1.4 A Public Fill Barging Point (PFBP), located on reclaimed land (Area 30D) to the north of the KCIP, is planned to be operational in early 2002. Construction of the PFBP is scheduled to commence in early 2001 for completion by the end of 2001. The PFBP is also subject to EIA under a separate study.
A2.1.5 The site is opposite the Rambler Channel Typhoon Shelter and Public Cargo Working Area. These facilities accommodate a range of cargo related activities including permanently moored barges. The structures which remain to be demolished are summarised in Table 2.1.
Table
2.1 Structures to be demolished at KCIP
Building |
Brief Description |
KCIP Chimney |
Reinforced concrete construction of diameter
6m – 12m and 150m high. Internal metal
flues and platforms |
KCIP Buildings |
Single storey with steel frame, precast concrete slab, reinforced concrete partition, corrugated steel sheet external wall and roof. The overall size is approximately 83m x 92m on plan. |
|
Approximately 4m x 13m on plan. |
Site Office/ |
2 storey height prefabricated building overall size is approximately 40m x 7.5m on plan. |
A3 Appreciation
and Understanding of Constraints to Demolition
A3.1.1 This section identifies the sensitive receives (SRs) affected by the Project as defined in the EIAO and discusses the implications of these and other nearby sensitive engineering projects and infrastructure with respect to the constraints they will place on demolition methods. Where relevant we have also noted the implications such sensitive locations may have on the potential for explosive demolition. Sensitive receivers and other constraints are shown in Figures 2.1 for KCIP.
A3.1.2 It has been assumed that the demolition for KTCDA will take place as soon as possible in order to allow future developments on and near the site. The earliest start date will be in 2001 with demolition works lasting about one year. There is currently no planned programme for the demolition of KCIP although a 16 month demolition phase was assumed in the PPFS.
A3.2 Sensitive Receivers at KCIP
Residential
A3.2.1 There are few SRs such
as residential premises which are so close to the works at KCIP as to be
severely affected by either explosive or conventional top down demolition. However residential receivers within 700m
will be included in the EIA. This
includes Cheung Ching Estate,
A3.3.1 There are several engineering and other locations, which would be very sensitive to controlled demolition by implosion. These include:
· The Rambler Channel marine traffic and ferry services.
· Rambler Channel Typhoon Shelter and PCWA.
· The Public Fill Barging Point (PFBP) at Area 300.
·
Container
Terminal 5 (
· The seawalls and drainage channels other infrastructure around the area.
· The 200m Sewerage Tunnel Protection Area.
· The Kwai Ching Preliminary Treatment Works.
·
The Kwai Chung Park (
·
The
· The Tsing Yi Bridge.
·
A3.4.1 The PPFS concluded that due to the short distances between the chimney and the surrounding structures, the high risk and lack of cost effectiveness meant that demolition of the single chimney by implosion was not feasible.
A3.4.2 The chimney at KCIP is 150m high. The exclusion zone under the “Draft Code of Practice for Demolition of Buildings (Buildings Department) would therefore require evacuation of an area up to 375m from the chimney during blasting. In the event that a Risk Assessment Report were conducted for this site, the result could require such a zone to be greater in order to minimise risks from ejecta. The possible limits of exclusion with respect to the chimney at KCIP are shown on Figure 2.1.
A3.4.3 The distance of residential SRs at Cheung Ching Estate,
A3.4.4 The distance to industrial buildings over the Rambler Channel would fall within a three chimney height radius and these buildings may require evacuation in then event that demolition by implosion was chosen
A3.4.5 Engineering and other locations are much nearer and would be very sensitive to controlled explosive demolition. The proximity of some facilities places them at physical risk of damage from vibration or flying debris. Others would be impacted by the need to suspend services and the costs of co-ordinating the closure of many services in the area could be unacceptable. Either individually or together the impact on these facilities/works could be sufficient to dictate against the use of demolition by blasting.
A3.4.6 A large section of the Rambler Channel, the Rambler Channel Typhoon Shelter, the PCWA and part of Container Terminal 5 would be likely to fall within an exclusion zone for explosive demolition. The suspension of services and marine traffic in the Rambler Channel, necessary for an demolition by blasting, presents a major potential impact. Marine Department have indicated that prima facie the closing the Rambler Channel to marine traffic is unacceptable and that they have an in principle objection to this line of action. The implications of demolition by blasting for evacuation of Rambler Channel, Typhoon Shelter and suspension of activities in the PCWA and Container Terminal 5 are therefore considered to be unacceptable.
A3.4.7 The Public Fill Barging Point (PFBP) at Area 30D is scheduled to be under construction some time in 2001 which is before the target date for the completion of the demolition indicated in the PPFS. If the chimney were to be felled using a blasting technique, the target area for the fall could just fit within the KCIP site towards the east. Otherwise the target area would be Area 30D. In the latter case there is a potential conflict for demolition by explosive methods which would be impossible prior to the subsequent cessation of activities at Area 30D as and when the barging point closes.
A3.4.8 The Kwai Chung Preliminary Treatment Works (KCPTW) is located immediately adjacent to the KCIP and the base of the chimney is only about 20m from the main KCPTW control building. The control centre is manned during the daytime and runs with automatic control from late afternoon, overnight, until early morning. The Drainage Services Department has indicated that the control equipment is very sensitive to vibration and they are especially concerned that vibration caused by blasting of the chimney could damage the equipment and possibly even the building fabric. Regardless of the method of demolition, vibration control techniques for the site may be required because of the proximity of the Kwai Chung PTW.
A3.4.9 The demolition works and the chimney are within 100m of the vertical shaft tunnel of the SSDS and require special scrutiny by Government. Part of the site is within the 200m outer limit of the Sewerage Tunnel Protection Area. The Technical Notes for Guidance in Assessing Effects of Civil Engineering Works/Building Development on Sewage Tunnel Works (PNAP 165) require that peak particle velocities (PPV) at any sewerage tunnel structure resulting from blasting or other operations which can induce prolonged vibration, shall not exceed 25mm/sec. The maximum peak particle velocities for other operations shall not exceed 15mm/sec. Drainage Services Department have also expressed concerns that such maximum PPV could be exceeded at the sewage tunnels with blasting techniques. Given the sensitivity of the SSDS project, the use of implosion techniques is considered to be unacceptable.
A3.4.10 The
approach viaduct of the
A3.4.11 There are potential landfill gas hazards associated with the Kwai Chung Park (Gin Drinkers Bay Landfill). The landfill gas hazard assessment, undertaken to identify the nature and extent of landfill gas release, is included in the EIA Report. At this stage explosure demolition would appear to be a very high risk option. Site safety measures implemented in the site investigation stage will need to be implemented in the demolition phase, in accordance with established standards and guidelines and the findings of the hazard assessment.
A3.4.12 The local road network is currently busy with much heavy traffic serving not only the PCWA but also other industrial facilities nearby. Transport Department expressed general concerns about the potential impact of the need to close roads to allow blasting techniques. Generally road closures would be unacceptable unless proved acceptable. A TIA would be required to assess impacts on all roads in the exclusion zone and the public transport system and a feasible traffic diversion scheme would need to be developed. Emergency plans would also need to be developed. Given the plethora of other non-traffic constraints, these measures have not been detailed at this stage.
A3.5.1 Asbestos Investigation Reports and Asbestos Abatement Plans for both sites are required under the Air Pollution Control Ordinance (APCO) prior to the commencement of any asbestos abatement work. Reports and plans prepared by Registered Asbestos Consultants (EPD register RACs 1014 and 1019) indicate asbestos containing materials (ACM) are present at the Site.
A3.5.2 The Brief assumes that any asbestos containing materials
(ACM) present in the chimneys and superstructures within the two sites will be
removed before commencement of the demolition works. However, experience suggests that in practice
the asbestos abatement processes will run more smoothly if both asbestos
contractors and civil demolition contractors work in tandem, as has been the
case with the civil demolition of the remaining buildings and structures at
other large industrial locations in
A3.5.3 Bulk asbestos removal of ACM from the incineration plant was undertaken by Government, prior to the removal of plant and machinery. Inspection of the plans and recent site surveys show that low risk asbestos containing materials are present in the chimney of the KCIP. The cladding to the superstructures of the KCIP incinerator building is also similar to other typical corrugated metal weather cladding with asbestos paint (ACM).
A3.5.4 There is also low risk asbestos containing
material (ACM) present in the ventilation louvres to
the chimney. The louvres
are also made from metal with an asbestos type mastic protective paint
coating. This is identical to ACM
typically found on louvres at other industrial sites
in
A3.5.5 Drawings indicate that an asbestos cement plate was used as a thermal insulation to the chimneys internal flue guide sections. Physical inspection of this material shows it to be a low risk ACM in good condition. However the location means that a controlled removal may only be possible as the chimney is progressively dismantled and as the chimney and flue sections are removed. Therefore blasting will not be an option.
A3.5.6 Other areas have been investigated but no potential ACM has been identified. Details are presented in the dedicated Asbestos Study Report (Asbestos Investigation Report and Asbestos Abatement Plan).
A3.6.1 Based on the information presented in Section 3 the consultants believe that sufficient information has been gathered to recommend that the preferred method of demolition should adopt a top-down, non-explosive, non-blasting approach for the demolition of the Kwai Chung Incineration Plant.
A4 General
Approach to Demolition of Buildings and Structures at KCIP
A4.1.1 This section seeks to illustrate some of the more general procedures for demolition that apply at KCIP. The intention in this and sections 5 is not to prescribe a precise method or provide a work specification or a demolition plan but to indicate the approach which should be taken, in sufficient detail to facilitate broad agreement on the methodology and progress EIA.
A4.1.2 Whereas the eventual detailed demolition plan of the selected demolition contractor(s) may not necessarily adopt the methodology proposed in this working paper, the consultants believe that general characteristics of the methods are appropriate. The methods are sufficiently effective and applicable for the tasks and where possible methods that will help reduce noise and dust nuisances have been chosen. The options selected are also broadly in line with the Draft Code of Practice for Demolition of Buildings (DCDB, Buildings Department 1998) which will also need to be observed at the detailed design stage.
A4.1.3 The overriding concerns for the demolition Project will be safety and minimisation of environmental impacts. This will include the safety of the operatives, safety of the other workers on the site and safety of the general public as well as protection of adjacent facilities and minimisation of nuisances.
A4.1.4 The Contractor should during the course of demolition, ensure and verify that all utilities and services have been rendered safe.
A4.2.1 Typical hoardings would to be provided along the site boundaries. Portable barricades will be used to cordon off different work zones where demolition is in progress. Where conditions warrant the Contractor should seek opinion and advice from the Site Engineer/AP/RSE in order to modify such plans accordingly.
A4.2.2 The buildings and chimneys are totally within the proposed Project sites and access would be controlled by security guards. No members of the public or unauthorised person would be allowed to enter the sites.
A4.2.3 Only contractors’ personnel and Government officials concerned with the demolition would be allowed within the contractors working area.
A4.3.1 Building and other structures should generally be demolished in the reverse order to that of their construction. The order of demolition for building would be progressive, storey by storey, having regard to the type of construction.
A4.3.2 As a general rule, wherever possible, external non-loading bearing cladding or any non-structural work should be removed first. All asbestos containing materials (ACM, particularly any ACM panels, would be removed prior to commencement of demolition works where ever possible. Other ACM may need to be removed as access is gained to particular areas and as the demolition progresses (see also section 3).
A4.3.3 Overloading of any parts of the remaining structure with debris or other materials should be avoided. Where materials and debris and are lowered from higher levels, care should be taken to prevent the material from swinging in such a manner that it creates a danger to the workers on site or the surrounding structures. Larger pieces of debris should be broken down into manageable sizes, subject to a maximum of 1.0m x 1.0m. The weight of loaded buckets for unloading debris would be limited to say, 200 kg.
A4.3.4 All debris would be removed at frequent intervals and stockpiles should not be allowed to build up excessively. In general it is anticipated that demolition waste would be removed on a daily basis with several tens of lorries leaving the site each day at the peak of demolition activities.
A4.3.5 Reinforced concrete structural members should be cut into lengths appropriate to the weight and size of member before being lowered to the ground. Where possible, crane and lifting gear should be used to support beams and columns whilst they are being cut and lowered to the ground.
A4.3.6 Removal of bricks walls should be from top to bottom in horizontal runs of not more that 300mm wide.
A4.3.7 Before and during demolition, the Contractor should pay attention to the nature and condition of the concrete, the condition and position of reinforcement, and the possibility of lack of continuity of reinforcement should be ascertained. Attention should also be paid to the principles of the structural design to identify parts of the structure, which cannot be removed in isolation. If uncertainties exist then advice of the Site Engineer/AP/RSE’s advice should be sought.
A4.3.8 During demolition works, if anomalies or irregularities are discovered in structural elements, regarding reinforcement bar details, alteration and addition works, unauthorized building works, etc, demolition works should stop immediately. AP/RSE should be informed and works will commence only after AP/RSE approval is obtained.
A4.3.9 If the Contractor discovers that the removal of certain parts of the buildings or structure during demolition would result in other parts becoming unsafe, it would be necessary to determine where temporary support will be needed and the advice of the Site Engineer/AP/RSE should be sought.
A4.4.1 The Contractor will need to carry out works in accordance with the Factories and Industrial Undertakings Ordinance, particularly the Construction Site (Safety) Regulations and the Code of Practice for Scaffold Safety, as well as all other statutory requirements and guidelines covering health and safety issues.
A4.4.2 All contractor and sub-contractors should be competent and qualified in demolition works. Site Engineer/AP/RSE(s) will need to ensure that all levels of Contractor(s) and his subordinates are fully conversant with the demolition plans, method statements and procedures.
A4.4.3 Where scaffolding is used, the Contractor should arrange for a competent scaffolder to visit site and inspect the scaffolding work, and to make any adjustments required to the scaffolding as the work proceeds, to ensure its stability.
A4.4.4 The Contractor shall also appoint a competent person, experienced or trained in the type of operation being performed at that particular time, to supervise and control the work on site.
A4.4.5 The Contractor should ensure that every work place, approach and opening, which may pose a danger to persons employed and others should be properly illuminated and protected.
A4.4.6 The use of all mobile cranes must be strictly controlled to ensure that cranes of adequate capacity will be used for lifting under different loading conditions.
A5 Principles
of Chimney Demolition at KCIP
A5.1 Access
A5.1.1 The main site would be protected by security personnel and a high hoarding such that the public would be totally excluded from the Project.
A5.1.2 The area beneath the chimneys would be cordoned off and only authorized staff involved in the demolition of the chimneys would be allowed admission into the vicinity of the chimney structures.
A5.2.1 The principle of the demolition procedure for the upper portion of the chimneys (10m from ground level or greater) is that the chimneys will be cut into small pieces by hand held tools on the spot by operatives who would work from working platforms inside the chimney. Hydraulic breakers would be used for the remaining lower portions of the chimneys.
A5.2.2 The concrete liner and the metal flues will be removed manually. The principle of the demolition procedure is that the chimney and flues would be cut up into pieces and these pieces lowered to the ground by derrick. This method would ensure that full control of the debris and that the pieces of reinforced concrete are not left to free fall (Figure 5.1).
A5.3.1 The area surrounding the chimney would be made secure and all necessary barricades erected. Only Authorized personnel would be allowed into the area.
A5.3.2 Two crane shafts each size 1.5m x 1.5m would be erected inside the chimney up to 100m high. The two crane shafts would be reduced to 1m x 1m above 100m high.
A5.3.3 A derrick would be mounted on the top of each crane shaft for hoisting & lowering of tools and debris.
A5.3.4 A working platform would be constructed at a level 2m below the top of the chimney.
A5.3.5 Panel of mesh flooring of the existing steel platform at each level would be removed to facilitate creation of the crane shaft and the lowering of debris.
A5.4.1 Using hand held tools, the insulation of the flue (non-ACM) would be removed down to 2m below top level.
A5.4.2 On the platform the concrete liner and metal flues are removed by hand and loaded into skips for lowering down to adjacent ground.
A5.4.3 The metal flues would be flame cut into 2m maximum length for lowering down to ground level.
A5.4.4 Using light weight chain saws, the chimney would be cut up into pieces of maximum size 1m x 1m, each piece being secured by a cable to a derrick to ensure that when the cutting is completed the concrete is fully supported.
A5.4.5 The individual pieces can then be lowered to the ground in a safe and controlled manner, thus ensuring there will be no free falling of material.
A5.4.6 The crane shafts and derricks can then be lowered by 2m. A new platform will be erected 2m below the new top level of the remaining chimney portion. The platform size would be progressively enlarged, as demolition progresses downward to accommodate the increasing diameter of the Chimney.
A5.4.7 This process would be repeated until only the lower 10m of the chimney remained. These remaining lower levels would be within the reach of normal, mobile hydraulic breakers. Such breakers would be on the ground and the lower portion of the chimney would be removed by these means.
A5.5.1 The buildings and chimney at KCIP can be demolished and removed by the conventional top down demolition using hand held tools and mechanical breaking methods. In order to avoid hazards caused to the adjacent areas, all the structures and other buildings near to the chimneys would be demolished and removed prior to the demolition of the chimneys. The estimated time for the completion of these works included in the PPFS was 16months which would appear to be ample time for demolition base on the above methodology.
A6.1.1 This working paper has presented information concerning the difficulties associated with the demolition of the Kwai Chung Incineration Plant and the demolition of Kennedy Town Comprehensive Development Area (the Project). In order to facilitate the progress of the Initial Assessment Report and the EIA process as a whole it is necessary to define the Project in sufficient detail in line with the objectives of the Study.
A6.1.2 The
primary aim of this working paper is to establish a conceptual demolition
method for both Project in order to facilitate
progress the EIAs.
During the preliminary investigations the consultants have taken note of
the work conducted previously and also initiated discussions with relevant
Government departments, many of whom have expressed severe concerns with the
proposals to include any form of blasting techniques for the felling of the
chimneys or the main building structures at either site.
A6.1.3 In the selection of an appropriate demolition method the physical effects on local sensitive receivers and adjacent structures are very important. There are also hidden costs arising from the need to carefully co-ordinate a demolition by implosion. The effect on marine and road transport systems and the complexity of implementing controls is also an important factor. The cumulative impacts of the surrounding interfaces on the project methods have been assessed and make demolition by implosion at either site a potentially costly and a very high risk proposal.
A6.1.4 In order to facilitate the progress of the Initial Assessment Report the consultants therefore seek endorsement of the content of this working paper. Whereas the eventual detailed demolition plan of the selected demolition contractor(s) may not necessarily adopt the precise methodology proposed in this working paper, the methods used should adopt top-down, non-explosive methods for the demolition of the Kwai Chung Incineration Plant and the demolition of Kennedy Town Comprehensive Development Area.
Role
Of Independent Checker (Environmental) IC(E)
B.1.1 The information in this section is advisory only and does not form part of the works contract. In addition to the specific duties identified, any additional advisory services between the IC(E), ER and the project proponent could be provided on an as needed basis, subject to agreement between the parties.
B.1.2 The role of the IC(E) shall be independent from the management of construction works; but the IC(E) shall be empowered to audit the environmental performance of construction. The IC(E) shall have a similar of level of experience as the ETL. The ER shall approve the proposed nominated IC(E).
B.1.3 The duties of the IC(E) are to:
·
Review and audit all aspects
of the EM&A programme
·
Validate and confirm that
monitoring is undertaken in accordance with the procedures, frequencies,
equipment and locations specified in the EM&A Manual, and any other
conditions imposed in the EP with regard to the EM&A programme.
·
Conduct site inspections as
considered necessary to verify site conditions.
·
Audit EIA and EP construction
phase mitigation requirements against the status of implementation.
·
Review effectiveness of
construction phase environmental mitigation and performance
·
Approve alternative working
methods proposed by the contractor where these reduce impacts. Audit working
methods as instructed by the ER to determine if there are alternatives that can
be adopted.
·
Audit complaint cases to
confirm follow up actions are in accordance with the EM&A Manual
requirements
·
Carry out any specific
requirements in the EP specified for action by the IC(E).
B.1.4 With reference to Event and Action Plans, where an event requires the ET or contractor to inform the ER, the ER will have a duty to inform the IC(E). For contractual reasons this arrangement should be adopted, rather than contractual requirements for the ET or contractor to communicate with the IC(E) directly. Actions required by the IC(E) in verifying implementation of the Event Action Plans should be clearly defined in the Scope of Works for the construction phase of the project. This would either be defined through the duties of the Engineer, or through a separate agreement between the project proponent and a third party IC(E).
(Source: Standards for Effluents Discharged into
Drainage and Sewerage Systems Inland and Coastal Waters, EPD)
Criteria for Soil Contamination and Landfill Disposal of Contaminated Soil
Landfill Disposal Criteria
for Contaminated Land
Metals
Parameter |
TCLP
Limit (ppm) |
Cadmium |
10 |
Chromium |
50 |
Copper |
250 |
Nickel |
250 |
Lead |
50 |
Zinc |
250 |
Mercury |
1 |
Tin |
250 |
Silver |
50 |
Antimony |
150 |
Arsenic |
50 |
Beryllium |
10 |
Thallium |
50 |
Vanadium |
250 |
Selenium |
1 |
Barium |
1000 |
Source : Guidance
Notes for Investigation and Remediation of Contaminated Sites (EPD TR1 / 99).
Toxicity Characteristics Leaching Procedure (TCLP) test
for materials contaminated with heavy metals needs to be carried out in
accordance with the testing frequency and requirements as stipulated in EPD’s Guidance Notes for Investigation and Remediation of
Contaminated Sites.
TPH and PAH
Toxicity Characteristic Leachate
Testing Procedure (TCLP) tests for TPH, PAH and BTEX contaminated materials
have to be carried out according to the testing frequency and requirenments as stipulated in EPD’s
“Guidance Notes for
Investigation and Remediation of Contaminated Sites. Pretreatment is
required to bring levels of TPH to below the TCLP limit of 2,500ppm PAH/BTEX to
below the TCLP limit 1,000ppm.
Dioxins and Furans (PCDD/PCDF)
Toxicity Characteristic Leachate
Testing Procedure (TCLP) tests for PCDD/PCDF contaminated materials have to be
carried out according to the testing frequency and requirenments
as stipulated in EPD’s “Guidance Notes for
Investigation and Remediation of Contaminated Sites. Pretreatment is
required to bring levels of PCDD/PCDF to below the TCLP limit of 1ppb PCDD/PCDF
(TEQ) with TCLP testing at a frequency of one sample per 100tonnes.
N.B.
TEQ =toxicity equivalent units.
ppm =
mg/kg (miligrams / kilogram)
ppm = mg/g (micrograms / gram)
ppb = ng/g (nanograms / gram)
ppb = 1000pg/g (picograms / gram)
1. Hazards and Safety
Precautions
1.1 Introduction
1.1.1 Hazards which may arise at KCIP generally be classified under the following headings:
· General Hazards
· Gas hazards
· Landfill leachate
Operators
1.2.1 Operators should be experienced and licensed drivers. Where possible, all operators should be required to demonstrate their driving ability in the equipment they will be operating and under actual job conditions before recruitment.
1.2.2 Only personnel with valid driving licences are permitted to drive any site cars or vehicles. In the case of vehicles which are not intended for road use, the driver should hold a licence for the nearest comparable class of road vehicle.
1.2.3 For operators employed, a photocopy of their driving licence should be obtained. Their validity and the class of vehicle licences to drive should be checked.
1.2.4 The site office should keep an up to date list of names and copies of driving licences of drivers of motor vehicles and plant.
Equipment
1.2.5 Drivers should make a daily inspection of their vehicles. The check should include steering, brakes, mirrors, lights, horn, tires and windshield wipers. Reverse alarms which must be installed on all trucks and lorries should also be checked to ensure safe operation. Drivers are required to report all defects to the plant mechanic foreman, and repairs should be made promptly.
Roads
1.2.6 Site roads should be maintained in safe operating condition at all times. Roads should be built to provide adequate drainage and width and should avoid sharp curves, abrupt changes in gradient and excessive gradients. The use of one-way traffic roads is recommended wherever possible. Site roads must have clearly visible signs in both Chinese and English.
Transporting Personnel
1.2.7 Personnel should only ride in vehicles designed for the purposes. It is forbidden for personnel to take rides with operations where no specific sear has been provided for passengers.
Loading Lorries
1.2.8 Materials loaded onto lorries should be within the permitted safe weight limit and should not project beyond the lorry body or be placed in an unsafe pile in such a manner as to present a hazard to other vehicles, pedestrians or structures.
General Requirements
1.2.9 Drivers leaving the driver leaves the driving seat of a vehicle shall ensure the engine shall is switched off, the gear engaged and parking brakes applied. The wheels shall be chocked on slopes.
1.2.10 Lorries should only be backed under the direction of a marshal or spotter. In dumping areas, the marshal and spotters should be identified by a reflective vests.
1.2.11 All operators and drivers are required to observe speed limits at all times.
1.2.12 All pedestrians requiring to pass close to an operating machine shall ensure that the machine operator has been them and has stopped operation prior to proceeding.
1.2.13 All personnel working on site roads or directing traffic shall wear reflective vests.
Plant Noise
1.2.14 The foreman shall ensure that noise assessments are carried out on all noisy plant used on site. Any plant that creates noise exceeding the first action level stated in the Factories and Industrial Undertakings (Noise at Work) Regulations should be identified, with notices fixed to the plant and appropriate action should be taken as described in the Regulations to avoid exposure to the noise. Attention shall also be paid to the recommended Environmental Monitoring and Audit plan for the site.
1.3.1 Waste in the landfill emits a mixture of gases. The composition of gases at KCIP is not known however leachate gases of the following composition would not be untypical for such a site approximately as follow:
· 45-55% methane – Explosive.
· 44-54% Carbon Dioxide – Asphyxiant.
· 1% Other gases – mainly organic vapours.
1.3.2 The main danger from landfill gas is due to explosion of methane, however, if large concentrations of gas displace air there can be a danger of asphyxiation or poisoning. Gas concentrations are likely to be higher near the tops of gas wells and near exposed areas of leachate collection stone.
1.3.3 All personnel are advised to observe the following guidelines to avoid gas accidents:
· No smoking on the site.
· Do not enter trial pits unless the air quality has been tested (see 1.6)
· If any personnel has any of the following health symptoms while working at, in or near a trial pit on the Site he should move away from the area of the trial pit immediately:
- Headache,
- Dizziness / lightheadedness,
- Tingling or numbness,
- Nausea,
- Blue lips or bright red skin.
1.3.4 Once the affected person has moved to a position remote from the trail pit he should inform his supervisor who will evaluate the situation, decide whether other persons should be evacuated from the immediate area whether medical aid is required.
1.4 Landfill Leachate
1.4.1 Solid waste in the reclamation under the site or leachate originating from GDBL may be toxic, the following rules should therefore be observed:
· If leachate has to be handled, or groundwater samples lotion ensure that the operatives wear protective clothing and gloves. If any operatives come into contact with leachate, should be immediately wash the affected area with clean fresh water.
· Ensure that any broken skin, cuts, graze and the like do not come into contact with waste or leachate. All cuts etc should be covered prior to working on the site.
· Safety boots should be worn on the site.
· All operatives should keep a lookout for sharp objects on the site such as broken glass, syringe needles, nails in pieces of wood and the such like.
· If any operative receives any cuts or grazes whilst he is on he landfill, he should report this immediately to his supervisor who will arrange for medical attention.
1.5.1 All operational and supervisory staff’s attention shall be drawn to the hazards of landfill gas generated by decaying refuse in the landfill which may have migrated to the KCIP Site. This gas can endanger the safety of workers, as the flammable gas it contains explosive potential once it is mixed with air. Attention shall also be given to other components of the gas which have the potential to cause asphyxiation or toxic effects under appropriate conditions.
1.5.2 Smoking and the use of naked lights and welding shall be prohibited in areas of the site where landfill gas likely to be present and can migrate. Warning signs designating “no smoking areas” shall be put up to remind workers of these restrictions.
1.5.3 Plant and mobile plant shall carry fire extinguishers, and shall be equipped with properly functioning spark arrestors and automatic air intake shut down valves. Wherever possible diesel operated plant shall be used.
1.5.4 No fires shall be permitted on the site. Operational and supervisory staff shall immediately extinguish any fires within the site.
1.5.5 Confined spaces and excavation where entry is required shall be treated as described under Section 1.6.
1.5.6 Temporary offices, huts and storage containers shall not be located where infiltration of gas could occur, and in any event shall be provided with simple gas protection measures and detection systems where appropriate.
1.5.7 Fire fighting facilities shall be maintained on the site, and shall be property housed and kept readily available for instant use.
1.5.8 The site designated emergency co-ordinator shall liaise with the Fire Services Department to ensure that they are in a position to respond quickly to any fire or explosion which may occur. The emergency co-ordinator shall notify the Fire Services Department immediately in the event of any such emergency.
1.5.9 The site agent shall carry out the following:
· Prepare detailed working procedures and safety precautions for the work being carried out.
· Instruct the workmen and other staff in the working procedures and safety precautions to be followed.
· Record in writing that the workmen and other staff have been so instructed.
· Provided sufficient equipment so the working procedures and safety precautions can be followed.
· Ensure the working procedures and safety precautions are adhered to.
1.6 Working in Confined Spaces
1.6.1 The Site contractor shall ensure that any work in a confined space, as defined in the Factories and Industrial Undertakings (Confined Spaces) Regulations, complies with the requirements of the Regulations and is in accordance with the Guide to the Regulations published by the Labour Department.
1.6.2 All entries into confined spaces will be subject to a written detailed safe working procedure and a permit to work procedure. The written safe working procedure will include, but may not be limited to, details of the following: -
· arrangements for detecting toxic or explosive gas or oxygen deficiency, and the detection equipment to be used.
· supervision arrangements
· safety and emergency rescue equipment to be used, including breathing apparatus, safety harness and safety ropes
· permit to work procedures
1.6.3 All persons entering a confined space shall have received appropriate training from authorised bodies.
1.6.4 All written safe working procedures and completed “Permit-To-Work Certificate” shall be kept in the site office.