Civil Engineering Department
The Government of the
Special Administrative Region
Agreement No. CE 15/99
Demolition of Buildings and Structures
in the Proposed
Comprehensive
Development Area Site
EM&A Manual
September 2001
Atkins
China Ltd
DOCUMENT TITLE PAGE |
|||||
Client : Civil
Engineering Department |
Contract No. (if any) : - CE
15/99 |
||||
Project Title : Environmental Impact
Assessment for Demolition of Kwai Chung Incinerator
Plant and Kennedy Town CDA |
Project No. : 2996 |
||||
Document No. : 2996-OR028-04 |
Controlled Copy No. : |
||||
Document
Title : EM&A Manual
KTCDA |
|||||
Covering Letter / Transmittal Ref. No. : 2996/15.109/ELT /DG/OG |
Date of Issue : September 2001 |
||||
Revision, Review and
Approval/Authorisation Records |
|||||
|
|
/ |
/ |
/ |
|
04 |
5th Issue |
Various/ |
JWS/
|
DG/ |
|
03 |
4th Issue |
Various/ |
JWS/
|
DG/ |
|
02 |
3rd Issue |
Various/ |
JWS/
|
DG/ |
|
01 |
2nd Issue |
Various/ |
WD/
|
DG/ |
|
00 |
1st Issue |
Various/ |
JWS/
|
DG/ |
|
Revision |
Description |
Prepared by / date |
Reviewed by / date |
App. or Auth. By / date |
|
Distribution (if insufficient space, please use separate paper)
Controlled Copy No. |
Issued to |
1-45 |
Civil Engineering Department |
46-47 |
ACL – ELAN |
|
|
CONTENTS
1.2 Requirements
for EM&A Programme
1.4 Sensitive
Receivers and Constraints to Demolition
1.5 General
Approach to Demolition of Buildings and Structures at KTCDA
1.6 Principles
of Chimney Demolition at KTCDA
1.7 Remedial
Action Plan for Contaminated Soils
1.8 Environmental
Study Requirements
2.2 Total
Suspended Particulates
2.4 Laboratory
Measurement/ Analysis
2.5 Dust
Sensitive Receivers and Monitoring Locations
2.8 Event
and Action Plan for Air Quality
3.7 Event
and Action Plan for Noise
3.8 Noise
Mitigation Measures.
4.1 Sources
of Water Quality Impacts
4.3 Site
Run-off and Surface Water Drainage during Demolition
4.4 Site
Run-off and Surface Water Drainage during Soil Remediation
5.3 Waste
Management Requirements
6.3 Protection
of Site Workers during excavation and treatment of soils
7.2 Compliance
with Legal and Contractual Requirements
8.2 Baseline
Monitoring Report
8.4 Contamination
Remediation Report
8.6 Interim
Notifications of Environmental Quality Limit Exceedances
9. Schedule Mitigation Measures from the eia
List of Appendix
Appendix A Preferred
Demolition Methodology (Extracted
From WP1 Originally Presented November 1999)
Appendix B Role
Of Independent Checker (Environmental) IC(E)
Appendix C Water
Quality Standards
Appendix D Criteria
for Soil Contamination and Landfill Disposal of Contaminated Soil
Appendix E Site
Safety Precautions
List of Tables
Table 1.1 Structures
to be demolished at KTCDA
Table
1.1 Structures to be demolished
at KTCDA
Table
2.1 Action and Limit Levels for
Air Quality
Table
2.2 Event/Action Plan for Air
Quality
Table
2.3 Data Sheet for TSP
Monitoring
Table
3.1 Action and Limit Levels for
Construction Noise
Table
3.3 Noise Monitoring Field
Record Sheet
Table
5.1 Summary of Waste Management
Impacts
Table
6.1 Actions Required Post
Demolition
Table
7.1 Event Contingency Plan for
Environmental Complaints
Table
8.1 Sample Template for Interim
Notifications of Environmental Quality Limits Exceedances
Table
9.1 Schedule of Impacts and
Mitigation Measures
List of Figures
Figure 1.1 Kennedy
Town CDA Locality Plan
Figure 1.2 Typical Perimeter Noise Barrier
Figure 1.3 EM&A
Management Structure
Figure 2.1 Proposed Dust Monitoring Locations
Figure 2.2 Proposed Airborne Fibre Monitoring Locations
Figure 3.1 Proposed Noise Monitoring Locations
Figure 6.1 KTCDA Borehole Contaminated Location Requiring Clean Up
Figure 6.2 Principles
of Remedial Action Plan
LIST OF Abbreviations
BC Bayanihan Centre
CNP Construction
Noise Permit
EM & A Environmental Monitoring and Audit
EPD Environmental Protection Department
ER Engineer’s Representative
ET Environmental Monitoring Team
ETL Independent Environmental Monitoring Team Leader
EWC Environmental Works Checker
HKWDS
HVS High Volume Sampler
HyD Highways Department
IC(E) Independent Checker (Environment)
IWRTS
JCC Jockey Club Clinic
KTCDA
KTPMQ
LAR
MDCA Mount
NCO Noise Control Ordinance
NSR Noise Sensitive Receiver
SIS
SR Sensitive Receiver
TDSR Territorial Development Strategy Review
TM Technical Memorandum
TSP Total Suspended Particulates
USAEPA
· Ensure that any environmental impacts resulting from the demolition of the KTCDA are minimised or kept to acceptable levels.
· Check that mitigation measures have been applied and are effective, and that the appropriate corrective actions are undertaken, if and when required.
· Provide a means of checking compliance with environmental objectives, recording anomalies and documenting corrective action.
· Information on the KTCDA demolition project, the project organisation and construction programme;
· General EM&A principles and the EM&A team organisation;
· Monitoring parameters, schedules, Action/Limit Levels and action plans;
· Complaints procedures.
· Reporting procedures.
(a) to protect sensitive receivers from environmental impacts if mitigation is not implemented;
(b) to protect the ecosystem;
(c) to monitor activities in areas of high conservation value;
(d) to monitor the effectiveness of mitigation measures which involves a long period to establish;
(e) to monitor any unproven technology;
(f) to validate the hypothesis in analysis and design;
(g) to audit the changing project scheduling; and
(h) others.
·
·
·
· Car / lorry park (CP);
· FEHD Refuse Collection Point (RCP); and
·
Table 1.1 Structures to be demolished at KTCDA
Building |
Brief Description |
KTIP Chimneys |
Two reinforced concrete chimneys, 60m high, 3.5m in diameter. |
|
Reinforced concrete structure of approximately 3,025m² on plan Refuse Pier |
|
5-storey reinforced concrete structures of approximately 9,500m² on plan, including, Reception Pier |
|
Boiler House and One reinforced concrete chimney, 25m high, 3m in diameter. |
|
Offices and Vehicle Inspection Bays. Overall size is approximately 600m² on plan. Diesel storage tank and lubrication oil store. |
|
Single Storey Transformer House (adjacent to lairage) |
|
Open landscaped area with street lighting and sitting areas |
Sai See Street Refuse Collection Point |
Prefabricated steel and concrete structure, single storey. |
Residential, Government, Institutional and Community
· Kennedy Town Police Married Quarters currently overlooks the site. The premises are scheduled to be vacated but parts of the buildings will potentially be occupied up to March 2002.
· The Mount Davis Cottage Area has already been vacated.
·
The new Housing
Society development (Cayman Rise) at
·
There are
occupied residential buildings at
NWFB and RCP
Other
Issues
General Approach
· sampling, analysis and statistical evaluation of monitoring parameters with reference to the EIA Study recommendations and requirements.
· environmental site surveillance;
· audit of compliance with environmental protection and pollution prevention and control regulations;
· monitor the implementation of the environmental mitigation;
· monitor compliance with the environmental protection clauses/specifications in the Contract;
· review construction (demolition) programme and comment as necessary;
· review construction (demolition) methodology and comments as necessary;
· complaint investigation , evaluation and identification of corrective measures;
· liaison with IC(E) on environmental performance matters and submission of EM&A deliverables to IC(E) for approval; and
·
advise on environmental improvement
and enhancement.
Table
1.1 Structures to be demolished at
KTCDA
Building |
Brief Description |
KTIP Chimneys |
Two reinforced concrete chimneys, 60m high, 3.5m in diameter. |
|
Reinforced concrete structure of approximately 3,025m² on plan Refuse Pier |
|
5-storey reinforced concrete structures of approximately 9,500m² on plan, including, Reception Pier |
|
Boiler House and One reinforced concrete chimney, 25m high, 3m in diameter. |
|
Offices and Vehicle Inspection Bays. Overall size is approximately 600m² on plan. Diesel storage tank and lubrication oil store. |
|
Single Storey Transformer House (adjacent to lairage) |
|
Open landscaped area with street lighting and sitting areas |
Sai See Street Refuse Collection Point |
Prefabricated steel and concrete structure, single storey. * |
· 0.6-1.7 m3/min (20-60 SCFM) adjustable flow range;
· Equipped with a timing/control device with +/- 5 minutes accuracy for 24 hours operation;
· Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
· Capable of providing a minimum exposed area of 406 cm2 (63 in2);
· Flow control accuracy: +/- 2.5% deviation over 24-hr sampling period;
· Equipped with a shelter to protect the filter and sampler;
· Incorporated with an electronic mass flow rate controller or other equivalent devices;
· Equipped with a flow recorder for continuous monitoring;
· Provided with a peaked roof inlet;
· Incorporated with a manometer;
· Able to hold and seal the filter paper to the sampler housing at horizontal position;
· Easy to change the filter; and
· Capable of operating continuously for 24-hr period.
· Serene Court
·
·
·
·
· Sai Wan Estate
· Bayanihan Centre
· Jockey Club Clinic (JCC)
·
St. Luke’s Church
and
· Sai Wan New Apartments
·
·
· Future URA Development
· Hong Kong Housing Society Residential Development (Cayman Rise)
·
Proposed Residential
Development,
·
· A horizontal platform with appropriate support to secure the samplers against gusty wind shall be provided;
· No two samplers shall be placed less than 2 metres apart;
· The distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
· A minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;
· A minimum of 2 metre separation, measured horizontally, from any supporting structure, is required;
· No furnace or incinerator flues shall be nearby;
· Airflow around the sampler shall be unrestricted;
· The sampler shall be more than 20 metres from the dripline;
· Any wire fence and gate, to protect the sampler, shall not cause any obstruction during monitoring;
· Permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
· A secured supply of electricity will be needed to operate the samplers.
· take into consideration the prevailing meteorological conditions;
·
at the site
boundary or such locations close to the major dust emission source; and
·
as close to the sensitive receivers
as possible to reflect conditions at the sensitive receivers.
Table 2.1 Action and Limit Levels for Air Quality
Action |
Limit* |
|
24 Hour TSP
Level in mg/m3 |
For baseline
level < 200 mg/m Action level =
(Baseline level * 1.3 + Limit level)/2; For baseline level > 200 mg/m Action level = Limit level |
260 |
1 Hour TSP Level
in mg/m3 |
For baseline
level < 384 mg/m Action Level = (Baseline level * 1.3 +
Limit level)/2; For baseline level > 384 mg/m Action level = Limit level |
500 |
Airborne fiblre level in fibres/ml |
0.006 f/ml |
0.01 |
Table 2.2 Event/Action Plan for Air Quality
|
|
|
ACTION |
|
EVENT |
ET |
IC(E) |
ER |
CONTRACTOR |
ACTION LEVEL |
||||
1. Exceedance for one
sample |
1. Identify source 2. Inform (C(E) and ER 3. Repeat measurement to confirm finding 4. Increase monitoring frequency to daily |
1. Check
monitoring data submitted by ET 2. Check
Contractor’s working method |
1. Notify Contractor 2. Check monitoring data and Contractor's
working methods |
1. Rectify
any unacceptable practice 2. Amend
working methods if appropriate |
2. Exceedance for two
or more consecutive samples |
1. Identify source 2. Inform IC(E) and ER 3. Repeat measurements to confirm findings 4. Increase monitoring frequency to daily 5. Discuss with Contractor , IC(E) and ER for
remedial actions required 6. If exceedance
continues, arrange meeting with IC(E) and ER 7. If exceedance
stops, cease additional monitoring |
1. Checking
monitoring data submitted by ET 2. Check
Contractor’s working method 3. Discuss
with ET and Contractor on possible remedial measures 4. Advise
the ER on the effectiveness of the proposed remedial measures 5. Supervise
implementation of remedial measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Check monitoring data and Contractor's
working methods 4. Discuss with IC(E) and Contractor on
potential remedial actions 5. Ensure remedial actions properly implemented |
1. Submit
proposals for remedial actions to ER within 3 working days of notification 2. Implement
the agreed proposals 3. Amend
proposal if appropriate |
LIMIT LEVEL |
||||
1. Exceedance for one sample |
1. Identify
source 2. Inform
ER and EPD 3. Repeat
measurement to confirm finding 4. Increase
monitoring frequency to daily 5. Assess
effectiveness of Contractor's remedial actions and keep IC(E), EPD and ER
informed of the results |
1. Checking
monitoring data submitted by ET 2. Check
Contractor’s working method 3. Discuss
with ET and Contractor on possible remedial measures 4. Advise
the ER on the effectiveness of the proposed remedial measures 5. Supervisor
implementation of remedial measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Check monitoring data and Contractor's
working methods 4. Discuss with ET Leader and Contractor
potential remedial actions 5. Ensure remedial actions properly implemented |
1. Take
immediate action to avoid further exceedance 2. Submit
proposals for remedial actions to ER within 3 working days of notification 3. Implement
the agreed proposals 4. Amend
proposal if appropriate |
2. Exceedance for two
or more consecutive samples |
1. Identify
source 2. Inform
IC(E), ER and EPD the causes & actions taken for the exceedances 3. Repeat
measurement to confirm findings 4. Increase
monitoring frequency to daily 5. Investigate
the causes of exceedance, Contractor’s working
procedures to identify possible mitigation 6. Arrange
meeting with IC(E) and ER to discuss the remedial actions to be taken 7. Assess
effectiveness of Contractor's remedial actions and keep IC(E), EPD and ER
informed of the results 8. If
exceedance stops, cease additional monitoring |
1. Discuss
amongst ER, ET and Contractor as the potential remedial actions 2. Review
Contractor’s remedial actions whenever necessary to ensure their
effectiveness and advise the ER accordingly 3 Supervise
the implementation of remedial measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Carry out analysis of Contractor's working
procedures with IC(E) to determine possible mitigation to be implemented 4. Discuss amongst Environmental Team Leader and
the Contractor potential remedial actions 5. Review Contractor's remedial actions whenever
necessary to assure their effectiveness 6. If exceedance
continues, consider what portion of the work is responsible and instruct the
Contractor to stop that portion of work until the exceedance
is abated |
1. Take
immediate action to avoid further exceedance 2. Submit
proposals for remedial actions to ER within 3 working days of notification 3. Implement
the agreed proposals 4. Resubmit
proposals if problem still not under control 5. Stop
the relevant portion of works as determined by the ER until the exceedance is abated |
· Stockpiles of dusty waste materials greater than 20m3 shall be enclosed on three sides, with walls extending above the pile and 2 metres beyond the front of the pile.
· Any vehicle with an open load carrying area used for moving potentially dusty material shall have properly fitting side and tail-boards. Materials having the potential to create dust shall not be loaded to a level higher than the side and tail boards and shall be covered by a clean tarpaulin in good condition. The tarpaulin shall be properly secured and shall extend at least 300mm over the edges of the side and tail-boards.
· Effective water sprays shall be used during the collection and loading of dusty wastes and other similar materials, when dust is likely to be created and to dampen all stored materials during dry and windy weather.
· Areas within the Site where there is a regular movement of vehicles, shall have an approved hard surface and be kept clean of loose surface material.
· Conveyor belts shall be fitted with wind-boards, and conveyor transfer points and hopper discharge areas shall be enclosed to minimise dust emission. All conveyors carrying materials which have the potential to create dust shall be totally enclosed and fitted with belt cleaners.
· Adequate dust suppression plant including water bowsers with spray bars shall be provided.
· Unless otherwise approved by the ER the Contractor shall restrict all motorised vehicles on the Site to a maximum speed of 15 km per hour and confine haulage and waste collection vehicles to designated roadways inside the Site.
Table 2.3 Data Sheet for TSP Monitoring
Monitoring Location |
|
Details of Location |
|
Sampler Identification |
|
Date & Time of Sampling |
|
Elapsed-time |
Start (min.) |
Meter
|
Stop (min.) |
Total Sampling Time (min.) |
|
Weather Conditions |
|
Site Conditions |
|
|
Pi (mmHg) |
Initial Flow Rate, Qsi |
Ti (oC) |
|
Hi (in.) |
|
Qsi (Std. m3) |
|
Pf (mmHg) |
Final Flow Rate, Qsf |
Tf (oC) |
|
Hf (in.) |
|
Qsf (Std. m3) |
Average Flow Rate (Std. M3) |
|
Total Volume (Std. m3) |
|
Filter Identification No. |
|
Initial Wt. Of Filter (g) |
|
Final Wt. Of Filter (g) |
|
Measured TSP Level (µg/m3) |
|
|
Name & Designation |
|
Signature |
|
Date |
Field Operator |
: |
|
|
|
|
|
Laboratory Staff |
: |
|
|
|
|
|
Checked by |
: |
|
|
|
|
|
· at locations close to the major site activities which are likely to have noise impacts; and
· close to the noise sensitive receivers.
·
Site Boundary
opposite Jockey Club Clinic/St. Luke’s Church and
· Site boundary east of KTIP
·
Site boundary
opposite future UPA Development in
a) One set of measurements between 0700-1900 hours on normal weekdays
b) One set of measurements between 1900-2300 hours (if evening activities are undertaken)
c) One set of measurements between 2300-0700 hours next day (if there are night activities).
d) One set of measurements between 0700-1900 hours on holidays (if work is undertaken)
Table 3.1 Action and Limit Levels for Construction Noise
Time Period |
Action |
Limit |
0700-1900 hrs on normal weekdays |
|
75*dB(A) |
0700-2300 hrs on holidays; and 1900-2300 hrs on all other days |
When one documented complaint is received |
60/65/70**dB(A) |
2300-0700 hrs of next day |
|
45/50/55**dB(A) |
* reduce to 70dB(A) for schools and 65 dB (A) during school examination periods.
** to be selected based on Area Sensitivity Rating as defined under the Noise Control Ordinance.
· Noise Control (Hand Held Percussive Breakers) Regulations
· Noise Control (Air Compressors) Regulations
· Noise Control (Hearing Protection) Regulations
· The Factories and Industrial Undertakings (Noise at Work) Regulations are also applicable.
Table 3.3 Noise Monitoring Field Record Sheet
Monitoring Location |
|
Description of Location |
|
Date of Monitoring |
|
Measurement Start Time (hh:mm) |
|
Measurement Time Length (min.) |
|
Noise Meter Model/Identification |
|
Calibrator Model/Identification |
|
|
L90 (dB(A)) |
Measurement Results |
L10 (dB(A)) |
|
Leq (dB(A)) |
Major Construction Noise Source(s) During Monitoring |
|
Other Noise Source(s) During Monitoring |
|
Remarks |
|
|
Name & Designation |
|
Signature |
|
Date |
Recorded By |
: |
|
|
|
|
|
Checked by |
: |
|
|
|
|
|
· The use of sediment traps, where appropriate; and
· The adequate maintenance of drainage systems to prevent flooding and overflow.
· minimising the ingress of surface water, which would mix with groundwater extracted during ground excavation if any; and
· reusing water on-site in ground remediation processes (mixing with cement).
Treatment of Surplus Groundwater Prior to Discharge
· Construction and Demolition (C&D) materials;;
· Chemical waste; and
· General refuse.
Table 5.1 Summary of Waste Management Impacts
Waste Type |
General Evaluation |
C&D material |
The total quantities of C&D materials which will be generated will be about 250te day-1, in comparison with the disposal capacity available at public filling areas, it is small. Due to the inert nature of most C&D material and the availability of public filling areas, disposal is not likely to raise long term environmental concerns. |
Chemical Waste |
A small volume of chemical waste, as well as asbestos containing roofing materials and weather cladding (estimate., up to 8,000m2) will be produced. Temporary storage on site, handling, transport and disposal must be in accordance with the Code of Practice on the Handling, Transportation and disposal of Asbestos Waste. Provided that this occurs, and chemical wastes are disposed of at a licensed facility, and there will be little environmental impact. |
General Refuse |
If good practice is adhered to and all feasible avoidance, reuse and recycling opportunities are taken, including minimising over ordering, there should be minimal impact. |
Introduction
Waste Management Hierarchy
· Avoidance and minimisation by not generating waste through changing or improving practices and design;
· Reusing materials and therefore avoiding disposal (generally with only limited reprocessing);
· Recovery and recycling, avoiding disposal (although reprocessing may be required); and
· treatment and disposal, according to relevant laws, guidelines and good practice.
C&D material
Chemical Waste
· Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;
· Have a capacity of less than 450l unless the specifications have been approved by the EPD; and
· Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.
· Be clearly labelled and used solely for the storage of chemical waste;
· Be enclosed on at least 3 sides;
· Have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;
· Have adequate ventilation;
· Be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and
· Be arranged so that incompatible materials are adequately separated.
· Be via a licensed waste collector; and
· Be to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility which also offers a chemical waste collection service and can supply the necessary storage containers; or
· Be to a recycling or reprocessing facility licensed by EPD.
Protection of Site Workers
General Refuse
· Public fill (inert) for disposal at public filling areas;
· C&D waste (non-inert) for landfill;
· Chemical waste for treatment at licensed facilities; and
· General refuse for disposal at landfill.
· Wastes should be handled and stored in a manner which ensures that they are held securely without loss or leakage thereby minimising the potential for pollution;
· Only reputable waste collectors authorised to collect the specific category of waste concerned should be employed;
· Appropriate measures should be employed to minimise windblown litter and dust during transportation by either covering trucks or transporting wastes in enclosed containers;
· The necessary waste disposal permits should be obtained from the appropriate authorities, if they are required, in accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation and the Government Land Ordinance (Cap 28);
· Collection of general refuse should be carried out frequently, preferably daily;
· Waste should only be disposed of at licensed sites and site staff and the civil engineering Contractor should develop procedures to ensure that illegal disposal of wastes does not occur;
· Waste storage areas should be well maintained and cleaned regularly; and
· Records should be maintained of the quantities of wastes generated, recycled and disposed, determined by weighing each load.
EM&A Requirements
Table 6.1 Actions Required Post Demolition
Borehole |
Action
Required |
Remove
concrete surface and clear uncontaminated surface material and stockpile |
Proposed
depth of Material for Removal or Treatment |
Remedial
Action |
Estimate
quantity of contaminated material for Treatment |
Reassurance
/ Confirmatory Sampling |
Sampling
Strategy |
TB1 |
Yes |
Concrete down to
0.3m depth |
Immediately
below concrete 0.3m to 4.0m |
Immobilisation
for 0.3m to 2.0m and 3.0m to 4.0m* TCLP test
followed by removal of 2.0m to 3.0m to landfill. Immobilisation if TCLP tests exceed
criteria **. |
100 to be removed to landfill + 270 @ |
Yes, determine
extent of HM (Cd, Cu, Pb,
Zn and Hg) and TPH contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E ,W and base of borehole. |
TB2 |
Yes |
Concrete down to
0.5m depth |
Immediately
below concrete 0.5m to 1.5m |
Immobilisation* |
100 |
Yes, determine
extent of HM (As, Cu, Pb and Zn) contamination at
edge and base of excavated hole.* |
5 samples 5m N,
S, E ,W and base of borehole. |
TB3 |
Yes |
Concrete down to
2.5m depth |
2.5m to 3.5m |
Immobilisation * |
100 |
Yes, determine
extent of HM (Cu, Pb, Zn and Hg) contamination at
edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB4 |
Yes |
Down to 2.2m
depth |
2.2m to 4.2m |
Immobilisation * |
200 |
Yes, determine
extent of HM (As, Cu, Pb and Zn) contamination at
edge and base of excavated hole.* |
4 samples 5 m N,
S, E & W of borehole plus one at base of hole layer |
TB5 |
Yes |
Concrete down to
1.8m. Down to 2.5m depth |
2.5m to 4.0m |
Immobilisation* |
200 |
Yes, determine
extent of HM (Pb) contamination at edge and base of
excavated hole.* |
4 samples 5 m N,
S, E & W of borehole plus one at base of hole layer |
TB6 |
No |
N/A |
N/A |
N/A |
0 |
N/A |
N/A |
TB7 |
No |
N/A |
N/A |
N/A |
0 |
N/A |
N/A |
TB8 |
Yes |
Concrete down to 1m. Down to 2.5m |
2.5m to 3.5m |
TCLP test followed by removal of 2.5m to 3.5m to
landfill. Immobilisation if TCLP tests
exceed criteria **. |
100 to be removed to landfill @ |
Yes, determine
extent of PAH contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E ,W and base of borehole. |
TB9 |
Yes |
Concrete down to
1.0m depth |
1.0m to 2.0m |
Immobilisation* |
100 |
Yes, determine
extent of HM (Pb) contamination at edge and base of
excavated hole.* |
4 samples 5m N,
S, E & W and base of borehole. |
TB10 |
Yes |
Surface
rubble/ash and brick material (not soil) about 1.5m depth. |
1.5 m |
Clear Waste to landfill. Waste to be treated and tested to meet EPD
disposal criteria. |
Up to, say, 300m3 (surface material, not for
in-situ treatment) @ |
Yes, determine
extent of HM (As, Cd, Cu, Pb,
Zn) TPH and PCDD/PCDF contamination under surface contaminated materials.* |
4 samples 5 m N,
S, E & W of borehole plus one at bore hole |
TB10a |
No |
N/A |
N/A |
N/A |
0 |
N/A |
N/A |
TB11 |
Yes |
Down to 1.5m
depth |
1.5 m |
Clear Waste to landfill. Waste to be treated and tested to meet EPD
disposal criteria. |
(See TB10, for materials not for in-situ
treatment) |
Yes, determine extent
of HM (Cd, Cu, Pb, and
Zn) and PCDD/PCDF contamination under surface contaminated materials.* |
5 samples 5m N,
S, E & W of borehole plus one at borehole |
TB11 |
Yes |
Below hardstanding surface (soil materials) |
1.5 to 4.0m |
Immobilisation* |
200 (for in-situ treatment) |
Yes, to
determine extent of HM (Pb) contamination at edge
and base of excavated hole. |
5 samples 5m N,
S, E & W of borehole plus one at base of hole layer |
TB12 |
Yes |
Concrete down to
0.5m |
0.5 to 1.5m |
Immobilisation* |
100 |
Yes, determine
extent of HM (Cd, Cu, Pb
and Zn) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB13 |
Yes |
Down to 2.5m |
2.5m to 3.5m |
Immobilisation* |
100 |
Yes, determine extent
of HM (Pb, Zn, Hg)
contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB14 |
No |
N/A |
N/A |
N/A |
0 |
N/A |
N/A |
TB15 |
Yes |
Concrete down to
0.4m |
0.4 to 2.4m |
TCLP test followed
by removal of 0.4m to 2.4m to landfill.
Immobilisation if TCLP tests exceed criteria **. |
200 to be removed to landfill @ |
Yes, determine
extent of HM (As, Cu, Pb, Hg and Zn) and PAH
contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB16 |
Yes |
Concrete down to
0.8m |
0.8 to 4.3m |
Immobilisation * |
350 |
Yes, determine
extent of HM (Cu, Pb and Zn) contamination at edge
and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB17 |
Yes |
Concrete down to
0.4m |
0.4 to 2.4m |
Immobilisation * |
200 |
Yes, determine
extent of HM (Pb and Hg) contamination at edge and
base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB18 |
Yes |
Concrete down to
1.0m |
1.0m to 2.0m |
Immobilisation * |
100 |
Yes, determine
extent of HM (Pb) contamination at edge and base of
excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB19 |
Yes |
Concrete down to
0.6m |
0.6m to 4.0m |
Immobilisation * |
375 |
Yes, determine
extent of HM (Pb and Hg) contamination at edge and
base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB20 |
Yes |
Concrete down to
0.3m |
0.3m to 2.3m |
TCLP test followed
by removal of 0.3m to 2.3m to landfill.
Immobilisation if TCLP tests exceed criteria **. |
200 to be removed to landfill @ |
Yes, determine
extent of HM (As, Cu, Pb, Hg, Cd
and Zn) PAH and TPH contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB21 |
Yes |
Concrete down to
0.5m |
0.5m to 5.0m |
TCLP test
followed by removal of 0.5m to 3.5m to landfill. Immobilisation if TCLP tests exceed criteria **. Remaining depth to be immobilised to 5m * |
300 to be removed to landfill + 150 @ |
Yes, determine
extent of HM (Cu, Pb, Hg and Zn) and TPH
contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB22 |
Yes |
Concrete down to
0.5m |
0.5 to 1.5m |
Immobilisation *
|
100 |
Yes, determine
extent of HM (Pb) contamination at edge and base of
excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB23 |
Yes |
Concrete down to
0.5m |
0.5 to 4m |
Immobilisation* |
350 |
Yes, determine extent
of HM (Pb) contamination at edge and base of
excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB24 |
Yes |
Concrete down to
1.2m |
1.2 to 4.2m |
Immobilisation* |
300 |
Yes, determine
extent of HM (Cu, Pb and Hg) contamination at edge and base of
excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB25 |
Yes |
Concrete down to
0.9m. Down to 1.0m |
Depth 1.0m – 4.4m |
TCLP test
followed by removal of 1.0m to 2.9m to landfill. Immobilisation if TCLP tests exceed
criteria **. Immobilisation
for remaining 2.9m to 4.4m* |
100 to be removed to landfill + 240 @ |
Yes, to
determine extent of HM (Pb, Hg) and PAH
contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB26 |
Yes |
Concrete down to
0.8m |
Depth 0.8m – 3.0m |
TCLP test
followed by removal of 0.8m to 3.0m to landfill. Immobilisation if TCLP tests exceed
criteria **. |
220 to be removed to landfill.@ |
Yes, to determine
extent of HM (Pb, Cu, Zn, Hg) and TPH
contamination.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB27 |
Yes |
Concrete down to
0.5m and clean soil down to 2.0m |
2.0 to 4.0m |
TCLP test followed by removal of 2.0m to 4.0m to
landfill. Immobilisation if TCLP tests
exceed criteria **. |
200 |
Yes, determine
extent of HM (Cu and Pb) and PAH contamination at
edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB28 |
Yes |
Concrete down to
0.4m |
0.4 to 4.4m |
Immobilisation* |
400 |
Yes, determine
extent of HM (As, Cd, Cu, Pb,
and Zn) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB29 |
Yes |
Concrete down to
0.5m |
0.5 to 3.5m |
Immobilisation* |
300 |
Yes, determine
extent of HM (Cu, Pb, Hg and Zn) contamination at
edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB30 |
Yes |
Concrete down to
0.6m |
0.6 to 1.6m |
Immobilisation* |
100 |
Yes, determine
extent of HM (Pb) contamination at edge and base of
excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
Refuse Bunkers |
Yes |
N/A |
N/A |
Landfill
disposal * |
To be determined
after inspection of bunkers |
Examine bunker refuse
prior to demolition. |
Consider
analysis depending on bunker contents. |
* If contamination
confirmed by reassurance sampling extract a further 1m into the soil,
immobilise and resample.
** TCLP test for all metals identified
in Table E1 in EPD Contaminated Sites Investigation and Remediation Guidance
Notes
# Broad brush estimate based on
depths to which materials >Dutch B are identified by current round of sampling
and all material within 5m (10m x 10m square hole) to that depth (rounded up to
nearest 10m3. (Total 6055 m3. requiring confirmation). According to the quantity of contaminated
material estimated for each borehole location, the total quantity of
contaminated soil should be about 6055m3 . About 4635m3.
of the total volume
is estimated to require treatment on site by immobilisation.
@ Broad brush estimate of materials
to be transferred to landfill rounded up to nearest 10m3 about 1,420m3, requiring
confirmation).
· the EIA Report recommendations on environmental protection and pollution control mitigation measures;
· works progress and programme;
· individual works methodology proposals (which shall include proposals on associated pollution control measures);
· the contract specifications on environmental protection;
· the relevant environmental protection and pollution control laws; and
· previous site inspection results.
· log complaint and date of receipt onto the complaint database;
· investigate the complaint to determine its validity, and to assess whether the source of the problem is due to works activities;
· if a complaint is valid and due to works, identify mitigation measures;
· if mitigation measures are required, advise the Contractor accordingly;
· review the Contractor’s response on the identified mitigation measures, and the updated situation;
· if the complaint is submitted by EPD, submit interim report to EPD on status of the complaint investigation and follow-up action within the time frame agreed between the ER and relevant Government Departments;
· undertake additional monitoring and audit to verify the situation if necessary, and review that any valid reason for complaint does not recur;
· report the investigation results and the subsequent actions to the source of the complaint for responding to the complainant (if the source of complaint is EPD, the results should be reported within the time frame agreed with the ER and relevant Government Departments); and;
· record the complaint, investigation, the subsequent actions and the results in the monthly EM&A reports.
Table 7.1 Event Contingency Plan for Environmental Complaints
Step |
Day |
Action |
Contractor |
ER |
ET |
IC(E) |
1 |
1 |
Party receiving
complaint shall create a new complaint record. If the Contractor receives a
complaint, he shall pass the information to the ER. |
¨ |
¨ |
¨ |
|
2 |
1 |
ER to ensure
details of complaint provided to Contractor (if complaint not originally
received by the Contractor), ET and IC(E) |
|
¨ |
|
|
3 |
2 |
Within 1 working
day after the receipt of the Notification of Complaint, provide ER relevant
works site information, e.g. types and locations of construction works. |
¨ |
|
|
à |
4 |
2 |
Investigate the
complaint to determine its validity, and to assess whether the source of the
problem is due to the works activities.
Report the validity of the complaint to ER. |
|
|
|
¨à |
5 |
2 |
If complaint is
valid and due to works, ER shall notify the Contractor. If complaint is invalid or not due to
works, Go to Step 12. |
|
¨ |
|
|
6 |
2 |
Propose
mitigation measures to ER within 1 working day of the receipt of the
Notification. |
¨ |
|
|
à |
7 |
2 |
Review and agree
with the proposed mitigation measures and make recommendations where
necessary. |
|
¨à |
|
¨à |
8 |
2 |
Implement the
mitigation measures once they have been agreed. |
¨ |
|
|
|
9 |
4 |
Audit the
implementation of the proposed mitigation measures on site within 2 working
days after measures have been agreed. |
|
¨à |
|
¨à |
10 |
- |
Undertake
additional monitoring to verify the situation where necessary. |
|
|
¨ |
|
11 |
4 |
Report the
investigation results and subsequent actions taken to ER within 2 working
days after the implementation of mitigation measures. |
¨ |
|
¨ |
|
12 |
5 |
Respond to the
complainant within 1 working day after receiving the investigation report. |
|
¨ |
|
|
13 |
25 |
If no further
comments or complaints are received from the complainant within 20 working
days after responding to the complainant, close the complaint record. If the complainant has further comments or
complaints on the same issue, notify other parties on the same day and go to
step 2. |
|
¨ |
|
¨à |
¨ action party
à enter comments/proposals into appropriate complaint record where applicable
· a 1-2 page executive summary;
· brief project background information;
· drawings showing locations of the baseline monitoring station;
· monitoring results (in both hard and diskette copies) together with the following information:
- monitoring methodology;
- equipment used and calibration details;
- parameters monitored;
- monitoring locations; and
- monitoring date, time, frequency and duration.
· details on influencing factors, including:
- major activities, if any, being carried out on the site during the period;
- weather conditions during the period; and
- other factors which might affect the results.
· determination of the Action and Limit Levels for each monitoring parameter and statistical analysis of the baseline data;
· revisions for inclusion in the EM&A Manual; and
· comments and conclusions.
· 1-2 pages executive summary;
· basic project information including a synopsis of the project organisation, programme and management structure, and the work undertaken during the month;
· a brief summary of EM&A requirement including :
- all monitoring parameters;
- environmental quality performance limits (Action and Limit levels);
- Event-Action Plans;
- environmental mitigation measures, as recommended in the project EIA study final report;
- environmental requirements in contract documents;
· advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA study report, summarised in the updated implementation schedule;
· drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
· monitoring results (in both hard and diskette copies) together with the following information:
·
monitoring methodology;
·
equipment used and calibration details
·
parameters monitored
·
monitoring locations
·
monitoring date, time, frequency, and duration;
·
major activities being carried out on site during the
period;
·
weather conditions during the period; and
·
any other factors which might affect the monitoring
results;
·
advice on the solid and liquid waste management status;
·
a summary of non-compliance (exceedances)
of the environmental quality performance limits (Action and Limit levels);
·
a review of the reasons for and the implications of
non-compliance and deficiency reporting and any follow-up procedures;
·
a description of the actions taken in the event of
non-compliance and deficiency reporting and any follow-up procedures related to
earlier non-compliance;
·
a summary record of all complaints received (written
or verbal) for each media, including locations and nature of complaints,
liaison and consultation undertaken, actions and follow-up procedures taken and
summary of complaints; and
·
an account of the future key issues as
reviewed form the works programme and work method statements.
· title page;
· Executive Summary (1-2 pages);
-
breaches of
- complaint Log;
- reporting Changes; and
- future key issues.
· contents page;
· environmental status;
- drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
- summary of non-compliance with the environmental quality performance limits; and
- summary of complaints.
· environmental issues and actions;
- review issues carried forward and any follow-up procedures related to earlier non-compliance (complaints and deficiencies);
- description of the actions taken in the event of non-compliance and deficiency reporting;
- recommendations (should be specific and target the appropriate party for action); and
- implementation status of the mitigation measures and the corresponding effectiveness of the measures.
· future key issues;
· appendices;
-
- graphical plots of trends of monitored parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:
i. major activities being carried out site during the period;
ii. weather conditions during the period; and
iii. any other factors which might affect the monitoring results.
- monitoring schedule for the present and next reporting periods;
- cumulative complaints statistics; and
- details of complaints, outstanding issues and deficiencies.
· all reports issued;
· site inspection forms and reports;
· monitoring field and laboratory records;
· complaints and related follow-up action information; and
· revised mitigation measures proposals adopted during the course of the works programme.
Table 8.1 Sample Template for Interim Notifications of Environmental Quality Limits Exceedances
Project |
|
Date |
|
Time |
|
Monitoring Location |
|
Parameter |
|
Action & Limit Levels |
|
Measured Level |
|
Possible reason for Action or Limit Level Non-compliance |
|
Actions taken / to be taken |
|
Remarks |
|
|
|
|
|
Location Plan |
Prepared by : |
|
|
|
|
Designation : |
|
|
|
|
Signature : |
|
|
|
|
Date : |
|
|
|
|
Table 9.1 Schedule of Impacts and Mitigation Measures
No. |
Activity |
Mitigation/EIA
Recommendations |
Respons-ibility for Implemen-tation |
Location Duration
completion Of measures |
Implemen-tation Stage |
Relevant
Guidelines Legislation |
1 |
Ash
Disposal |
|
|
|
|
|
I |
Treatment |
Reconfirm extent of
contaminated ash deposits by sampling for dioxins and furans. Handling, transportation and disposal of the
ash waste in line with relevant regulations.
Collection, immobilisation and testing of waste for disposal to
landfill shall be carried out according to the relevant regulations and
recommendations of the EIA including immobilisation by collection and mixing
the ash material with cement. Pilot
mixing and TCLP tests should establish the ratio of cement to ash to the
satisfaction of EPD. Ash waste to be
treated and placed into steel drums lined with plastic sheeting. The drums should be adequately sealed and
in new or good condition. Prior
agreement of the disposal criteria from EPD and agreement to disposal from
the landfill operator must be obtained. |
CED’s Contractor |
KTCDA work areas. Duration of the ash removal |
A@ |
1, 10, EIA |
II |
Disposal |
To monitor the disposal of waste at landfills, a
“trip-ticket” system (WBTC No. 5/99) for all solid waste transfer/disposal
operations should be implemented. The
system should be included as a contractual requirement, and monitored by the
Environmental Team and audited by the Independent Checker (Environment). |
CED’s Contractor |
As above |
A |
1, 5, 9 |
III |
Asbestos
Removal |
An asbestos abatement programme should be submitted to
EPD for approval prior to the commencement of the asbestos abatement work. |
CED and
Contractor |
As above |
A |
4 |
2 |
Demolition |
|
|
|
|
|
A |
Non-blasting
Methodology |
Waste
Management Plan to be submitted to EPD.
Demolition by Non-Blasting Methodology Only. All structures and buildings should be
demolished and removed prior to demolition of chimneys |
CED |
KTCDA work areas. Duration of the demolition |
C# |
8 |
B |
Material
Storage |
Covers for dusty stockpiles and control of dust emissions from construction
(demolition) works requires appropriate dust control measures to be
implemented in accordance with the requirements in the Air Pollution Control
(Construction Dust) Regulation. |
CED’s Contractor |
As above |
C |
4 |
C |
Vehicle
movement |
Haul road
watering, vehicle wheel wash prior to exit.
Where practical, access roads should be protected with crushed gravel. |
CED’s Contractor |
As above |
C |
4 |
D |
Plant
maintenance |
All plant
shall be maintained to prevent any undue air emissions. |
CED’s Contractor |
As above |
Prior to start of works |
4 |
E |
Improved
Site Hoarding |
Boundary hoarding to be modified in form of noise barrier to provide
effective noise screening and made of panels with a superficial surface
density of at least 10 kg/m3 |
CED’s Contract`or |
As above |
C |
Env. Permit |
F |
Demolition
Sequence |
Include
careful consideration and positioning of portable noise barriers to allow
noise attenuation. |
CED’s Contractor |
As above |
C |
8 |
G |
Portable
Noise Barriers |
Moveable noise barriers shall be provided close to PME in cases
where, in the opinion of the Engineer, such PME has the potential to cause
noise nuisance to sensitive receivers and where a benefit will result. Such barriers shall be made of panels with
superficial surface density not less than 10 kg/m3. |
CED’s Contractor |
As above |
C |
Env. Permit |
H |
Plant
Operation |
Modify
continuous operational periods for noisy plant to comply with noise criteria.
|
CED’s Contractor |
As above |
C |
Env Permit |
I |
Demolition
Techniques |
Selection
of non-blasting demolition techniques to minimise noise and vibration. |
CED’s Contractor |
As above |
C |
8 |
J |
Plant
maintenance |
All plant
shall be maintained to prevent any undue noise nuisance. |
CED’s Contractor |
As above |
C |
2, 3 |
K |
Wheel wash |
All wheel
wash water shall be diverted to a sediment pit. |
CED’s Contractor |
As above |
C |
5 |
L |
Sediment
control |
Sediment
removal facilities shall provided and be maintained and excavated as
necessary to prevent sedimentation of channels. Perimeter channels should be provided.
Works should be programmed for the dry season where feasible. Environmental guidelines for the handling and
disposal of discharges from construction sites, as stipulated in the Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94)
to be followed. |
CED’s Contractor |
As above |
C |
5, 12 |
M |
Surface
water diversion |
All clean
surface water shall be diverted around the site. |
CED’s Contractor |
As above |
C |
5, 12 |
N |
Fuel can
storage |
All fuel
cans shall be placed within a bunded area. Any fuel
spills shall be mopped up as necessary. |
CED’s Contractor |
As above |
C |
5,6 |
O |
Material,
plant move-ment & fuel can filling. |
Any fuel or
oil spills shall be excavated and disposed of. |
CED’s Contractor |
As above |
C |
6,7 |
P |
Generators
|
All
generators shall be placed within a bunded area.
Any fuel spills shall be mopped up as necessary. |
CED’s Contractor |
As above |
C |
5,6,7 |
Q |
Material
containers |
All empty
bags and containers shall be collected for disposal. |
CED’s Contractor |
As above |
C |
6,7 |
R |
Worker
generated litter and Waste |
Litter
receptacles shall be placed around the site. Litter shall be taken regularly
to the refuse collection points. Chemical toilets (or suitable equivalent)
should be provided for workers. Any canteens should have grease traps. |
CED’s Contractor |
As above |
C |
6 |
S |
Neighbourhood
nuisance |
All
complaints regarding construction works shall be relayed to the environmental
team. |
CED’s Contractor |
As above |
C |
1, 6 |
T |
Legal
requirements |
Different
types of waste should be segregated, stored, transported and disposed of in
accordance with the relevant legislative requirements and guidelines |
CED’s Contractor |
As above |
C |
1,6 |
U |
On-site
separation |
On-site
separation of municipal solid waste and construction/demolition wastes shall
be conducted in order to minimise the amount of solid waste to be disposed to
landfill. |
CED’s Contractor |
As above |
C |
1, 11 |
V |
Temporary
storage area |
Separated
wastes should be stored in different containers, skips, or stockpiles to
enhance reuse or recycling of materials and encourage their proper disposal. |
CED’s Contractor |
As above |
C |
1, 11 |
W |
Record of
wastes |
Records of
quantities of wastes generated, recycled and disposed (with locations) shall
be kept. |
CED’s Contractor |
As above |
C |
1, 9 |
X |
Trip-ticket
system |
To monitor
the disposal of waste at landfills and control fly-tipping, a “trip-ticket”
system under WBTC N0.5/99 for all solid waste transfer/disposal operations
should be implemented. The system
should be included as a contractual requirement, and monitored by the
Environmental Team and audited by the Independent Checker (Environment). |
CED’s Contractor |
As above |
C |
1, 9 |
|
|
|
|
|
|
|
3 |
Soil
Remediation Phase |
|
|
|
|
|
AA |
B, C, D,
E, F, G, H, I, J, K, L, M, N, O, P, Q, R, S, T U, V, W and X as above |
As above
(see W for soil remediation). |
CED’s Contractor |
KTCDA work areas. Duration of the soil remediation |
R |
As above |
BB |
De-watering |
Collect
and recycle extracted groundwater and leachate by
mixing with cement for soil remediation.
Environmental guidelines
for the handling and disposal of discharges from construction sites, as
stipulated in the Practice Note for Professional Persons, Construction Site
Drainage (ProPECC PN 1/94) to be followed.
Any surplus groundwate and leachate requiring disposal to be disposed
of under the relevant legislation or treated to meet the standards given in
Table 9a of the WPCO TM and any other parameters to be agreed with EPD prior
to any consent being given to discharge. |
CED’s Contractor |
As above |
|
5 |
CC |
Immobilisation |
Immobilisation and testing
of waste soil shall be carried out according to the relevant regulations and
recommendations of the EIA including immobilisation by collection and mixing
the contaminated soil material with cement.
Pilot mixing and TCLP tests should verify the effectiveness and
establish the ratio of cement to soil to the satisfaction of EPD. Such activities shall take place in a
covered area with a concrete paved floor.
Reassurance confirmatory sampling shall be carried out to confirm the
extent of contamination. Soil waste to
be cast in blocks and replaced in the ground.
Extracted soils and materials and
stabilisation/solidification to be conducted in bunded
area to prevent surface run-off. See
also item 2(H) above. Final soil
decontamination report to be submitted to EPD. |
CED’s Contractor |
As above |
|
1, 10 |
4 |
Monitoring
and Audit |
To be
carried out in accordance with the Schedule in the EM&A Manual. |
CED*/
Contractor/ RSS |
KTCDA works areas During demolition and at end of demolition throughout
execution of Remediation Action Plan |
C |
1 |
* Normally undertaken by a
specialist monitoring team employed directly by the proponent and audited by
the Independent Checker(Environment)
@ A = during ash removal (before
demolition)
# C = during construction (i.e.
demolition phase).
* R = during soil remediation phase
(after demolition)
1.
Environmental Impact
Assessment Ordinance Technical Memorandum (EIAO)
2.
Noise Control Ordinance
3.
The ProPECC
Note PN2/93 (Construction Noise daytime limits)
4.
Air Pollution Control
Ordinance (APCO)
5.
Water Pollution Control
Ordinance (WPCO)(Cap. 358)
6.
Waste Disposal Ordinance (Cap
354)
7.
Waste Disposal (Chemical
Waste)(General) Regulation (Cap 354)
8.
Draft Code of Practice on
Demolition of Buildings (BD, 1998)
9.
Works Bureau Technical
Circular No. 5/99, Trip-ticket System for Disposal of Construction and
Demolition Material
10. Guidance
Notes for Investigation and Remediation of Contaminated Sites
11. Works
Bureau Technical Circular No. 5/98, On Site Sorting of Construction Waste on
Demolition Sites
12.
ProPECC Note PN 1/94Construction Site Drainage
Attachment
A Preferred Demolition Methodology
(Extracted From WP1 Originally Presented November 1999)
List of Abbreviations
AAP |
Asbestos Abatement Plan |
ACE |
Advisory
Committee on Environment |
ACM |
Asbestos Containing Material |
AIR |
Asbestos Investigation Report |
AP |
Authorised Person |
APCO |
Air Pollution Control Ordinance |
BOO |
Building Ordinance Office |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CED |
Civil Engineering Department |
CPLD |
Committee on Planning & Land Development |
CSTG |
|
DSD |
Drainage Services Department |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EM&A |
Environmental Monitoring & Audit |
EMSD |
Electrical & Mechanical Services Department |
EPD |
Environmental Protection Department |
G I/C |
Government, Institutional/Community |
KTA |
|
KTCDA |
|
KTIP |
|
LDC |
Land Development Corporation |
LGHAGN |
Landfill Gas Hazard Assessment Guidance Note |
MTIA |
Marine Traffic Impact Assessment |
NWFB |
|
PCWA |
Public Cargo Working Area |
PFBP |
Public Fill Barging Point |
PQA |
Preliminary Quantitative Assessment |
RAC |
Registered Asbestos Consultant |
R7 |
Route 7 |
RCP |
Refuse Collection Point |
RSE |
Resident Site Engineer |
SR |
Sensitive Receiver |
TIA |
Traffic Impact Assessment |
TM |
Technical Memorandum |
USD |
Urban Services Department |
I.
The contents
of this Attachment A to the EIA for the Demolition of the Kennedy Town Comprehensive Development Area was originally presented to
Government Departments. The contents of this paper was endorsed at the First Study
Management Group Meeting for the study Environmental Impact Assessment Study
for Demolition of Kwai Chung Incineration Plant and
Kennedy Town Comprehensive Development Area, CE 15/99.
II.
The preferred demolition
methods were endorsed as a basis for defining the activities to be addressed
within the environmental impact assessment and the analysis of the alternative
demolition options and the major conclusions regarding demolition methods are
presented. The Working Paper also presents the major
constraints associated with the Projects.
For purposes of presenting supporting material to the EIA
for the Demolition of the Kennedy Town Comprehensive Development Area the text referring
to Kwai Chung Incineration Plant has been deleted.
III.
The PPFS for KTCDA concluded that the
preferred method of demolition was by traditional top down methods utilising
manual tools and mechanical plant but that the possibility of
demolition by implosion for two chimneys (one at the incineration plant and one
at the abattoir) could not be ruled out.
The PPFS recommended that the feasibility of demolition of the chimneys by implosion
or other unconventional techniques be further investigated in the EIA.
IV.
Consultation with Government Departments has confirmed
the concerns regarding implosive demolition identified in the PPFS for KTCDA
and the preference for top down demolition methods. Investigations have shown
that ACM is present in the abattoir chimney and the incinerator chimneys and at
other location in the KTCDA. The weather
cladding of the KTIP buildings is also ACM.
This dictates that a non-blasting approach is required in order that the
ACM can be removed in line with statutory requirements.
V.
The KTCDA is surrounded by
residential development and other sensitive uses. The risks, hidden costs and knock on effects
of implementing any proposal which includes blasting techniques for the felling
of the chimneys or the main building structures also makes such options
unattractive.
VI.
The details of the
constraints to demolition are presented and a conceptual demolition method has
been developed which avoids most of the complications associated with blasting
and provides flexibility for the implementation stages of the works.
VII.
The conclusion is that non-explosive demolition
methods should be used for the demolition of the Kennedy Town Comprehensive
Development Area.
A1.1.1 The Civil Engineering Department (CED) has appointed Atkins China Ltd. (ACL) to undertake the Environmental Impact Assessment (EIA) for the Demolition of the Kwai Chung Incineration Plant and the Kennedy Town Comprehensive Development Area (Agreement No. CE 15/99). The Kennedy Town Incineration Plant (KTIP) is within the boundary of the KTCDA and ceased to operate March 1993 and has been decommissioned and the facilities require demolition. The demolition of the remaining facilities constitutes the Project as defined under the requirements of the Environmental Impact Assessment Ordinance (EIAO).
A1.1.2 The primary aim of this paper is to establish a conceptual demolition
method and to define the major constraints that must be considered in the final
demolition process. The paper presents information
that facilitated decisions on acceptable conceptual demolition methods for both
Project as a basis for the remainder of the Study.
A1.1.3 To
satisfy the requirements of the EIA it is necessary to define clearly the
nature of the works involved in the demolition process. The development of a conceptual scheme for
the demolition process in turn requires detailed analysis of the facilities and
those surrounding uses and activities which might influence decisions on
demolition. This paper presents this
analysis. The conceptual scheme for
demolition of the facilities has been developed based on practical experience
and current demolition practice in Hong Kong as well as internationally.
A1.2.1 In addition to this introduction Working Paper 1 Report includes sections covering the following:
· Section 2 Project and Study Area
· Section 3 Appreciation and Understanding of Constraints to Demolition.
· Section 3 General Approach to Demolition of Buildings and Structures.
· Section 4 Conceptual Demolition Method for Chimneys at KTCDA.
· Section 5 Conclusions.
A2.1
A2.1.1 The
proposed Kennedy Town Comprehensive Development Area (KTCDA) is situated next
to
A2.1.2 The KTCDA comprises several elements as well as the Kennedy Town Incineration Plant (KTIP). The main operations at the Kennedy Town Abattoir (KTA) ceased and relocated to new facilities at Sheung Shui in the autumn of 1999. The KTA includes an incinerator for disposal of animal carcasses and waste that is managed by EPD. The KTA plant remains in place.
A2.1.3 Part of the former EMSD Depot that forms part of the KTCDA has been leased to New World First Bus (NWFB) for bus maintenance and refuelling, under a short-term tenancy. The remainder is leased as a car / lorry park. These facilities will remain in operation for the time being.
A2.1.4 The
former Kennedy Town Wholesale Market has been relocated and this area has been
remodelled as a park and sitting out area adjacent to
A2.1.5 Food
and Environmental Hygiene Department have recently constructed a Refuse
Collection Point (RCP) between the park and the Abattoir at
A2.1.6 The KTCDA includes:
·
the
·
the
·
the
· car / lorry park (CP);
· FEHD Refuse Collection Point (RCP); and
·
the
A2.1.7 The structures to be demolished are summarised in Table A2.1.
A2.1.8 The KTCDA was recommended for future private housing development in the “Planning and Engineering Study for the Redevelopment of Mount Davis Cottage Area and Kennedy Town Police Married Quarters” (Agreement No. CE 52/97), completed in May1999. The Open Space and Refuse Collection Point were proposed to be permanently relocated within the redevelopment.
A2.1.9 The
proposed Green Island Reclamation and Route 7 (R7), a strategic road link
between
Table A2.1 Structures to be
demolished at KTCDA
Building |
Brief
Description |
KTIP Chimneys |
Two reinforced concrete
chimneys, 60m high, 3.5m in diameter. |
|
Reinforced concrete
structure of approximately 3,025m² on plan, Refuse Pier |
|
5-storey reinforced
concrete structures of approximately 9,500m² on plan, Reception Pier |
|
Boiler House and One reinforced concrete
chimney, 25m high, 3m in diameter. |
|
Offices and Vehicle
Inspection Bays. Overall size is approximately 600m² on plan. |
|
Single Storey Transformer
House (adjacent to KTA lairage) |
|
(Inclusion / Exclusion /
Programme Requires Decision.) |
Sai See Street Refuse Collection Point |
(Inclusion / Exclusion /
Programme Requires Decision.) |
A3. Appreciation
and Understanding of Constraints to Demolition
A3.1.1 This section identifies the sensitive receives (SRs) affected by the Project as defined in the EIAO and discusses the implications of these and other nearby sensitive engineering projects and infrastructure with respect to the constraints they will place on demolition methods. Where relevant we have also noted the implications such sensitive locations may have on the potential for explosive demolition.
A3.1.2 It has been assumed that the demolition for KTCDA will take place as soon as possible in order to allow future developments on and near the site. The earliest start date will be in 2002 with demolition works lasting about one year.
A3.2 Sensitive Receivers at
KTCDA
Residential, Government, Institutional and Community
A3.2.1 Residential, Government, Institutional and Community uses surround the KTCDA site and many are elevated and overlook the site. The nearest rank of sensitive receivers is discussed below.
· Kennedy Town Police Married Quarters currently overlooks the site. The premises are scheduled to be vacated but parts of the buildings will potentially be occupied up to March 2002.
· The Mount Davis Cottage Area has already been partially vacated and the remaining premises will be vacated up to March 2001.
·
The new Housing
Society development at
·
There are occupied residential building at
A3.2.2 Other
premises in the low rise blocks at
A3.2.3
A3.2.4 There are Government, Institutional and Community uses at St Lukes Church School, St Lukes Settlement, Jockey Club Clinic, Victoria Mortuary and the Bayanihan Centre.
A3.2.6 The
Bayanihan Centre on
A3.3 Implications of Demolition by Implosion
at KTCDA
A3.3.1 Non-explosive demolition methods used the EIA will lead to the recommendation recommend of a series of mitigation measures to protect the residential, government, institutional and community uses and all other sensitive receivers that surround the KTCDA.
A3.3.2 If explosive demolition methods were to be used, the EIA would include a comprehensive Risk Assessment Report covering the effects of the affected neighbourhood would be required. The assessment would be undertaken within this Study and one of the results would be to recommend risk reduction measures to ensure that explosive demolition would be carried out within the Hong Kong Risk Guidelines. These requirements would be included in the Environmental Permit.
A3.3.3 One such likely requirement is the inclusion of an exclusion zone to minimise the chance of ejecta or debris hitting any spectators. Whereas the exclusion zone cannot be determined at this stage, it is possible to identify the likely size of such a zone by reference to other studies. Recent requirements for the minimisation of risks from ejecta, included in the Environmental Permit (EP-002/1998) for the Felling of Five Power Station Chimneys at Tsing Yi Power Station Chimneys by explosion, included an exclusion zone equivalent to three times the chimney heights.
A3.3.4 The “Draft Code of Practice for Demolition of Buildings (Buildings Department) requires that all residents or inhabitants within an exclusion zone be evacuated during blasting. The radius of a typical exclusion zone is not less than 2.5 times the height of the structure to be demolished. The highest structures at the KTCDA are the KTIP chimneys at 60m. Experience therefore suggests that an exclusion zone of two and a half (150m) to three times (180m) the height of the structures to be demolished would be required at the KTCDA. The possible limits of exclusion with respect to the chimneys at KTCDA are shown on Figure 2.1.
A3.3.5 The PPFS for the demolition of KTCDA noted that, due the short distance between Chimney “A” and other buildings to the west, it would be a high risk option to demolish using explosives. The PPFS also noted that the possibility of demolition of Chimneys B and C using explosives could not be ruled out at that stage. However the PPFS did not make reference to any other buildings in the vicinity. The Kennedy Town Police Married Quarters, St Lukes Settlement, Jockey Club Clinic, Victoria Mortuary, Bayanihan Centre, St Lukes Church School, Hosing Society Residential Development, Cadogan Street Temporary Garden, China Merchants Wharf, Industrial Buildings in Victoria Road and Public Piers at Cadogan Street would all be within a 2.5 times exclusion zone for evacuation for Chimney “B”.
A3.3.6 The
PPFS report also notes that the Cadogan Street
Temporary Garden (GLA-THK 10550), RCP (GLA-THK 1054) and the New World First
Bus Depot are subject to leases requiring one month notice for
termination. The FEHD RCP at
A3.3.7 USD have indicated that there is no programme identified to relocate the newly developed RCP and CSTG. Whereas these sites would require protection during the demolition, regardless of the demolition method, there would be more opportunity for a flexible approach to the phasing of demolition if non-blasting methods are used and exclusion zones are not required.
A3.3.8 The New World First Bus Depot also includes diesel fuel storage tanks and other lubrication oil storage. Experience also suggests that such tanks in reasonably close proximity to demolitions by implosion would be required to be emptied and sterilised for the duration of the felling by implosion in order to reduce risk.
A3.4 Other Sensitivities near
KTCDA
Road Traffic
A3.4.1 Road
traffic access must be maintained for residential and commercial uses at
A3.4.2 Access
must be maintained for commercial uses at
A3.4.3 Whereas the exact volume of waste to be disposed of has not yet been determined, preliminary estimates indicate that about forty lorries per day would be required. Therefore it is estimated that during the peak of demolition process fewer than ten heavy vehicles per hour would be required to remove waste from the Site. Traffic Impact Assessments carried out for the “Planning and Engineering Study for the Redevelopment of Mount Davis Cottage Area and Kennedy Town Police Married Quarters” (Agreement No. CE 52/97) indicate that this level of additional traffic could be absorbed into the surrounding network without significant impacts.
A3.4.4 In addition the impact of potential road closures needed to allow blasting techniques, such an approach would require additional studies which are outside of the Brief and may delay the EIA programme. Transport Department have indicated a general presumption that a road closure would be unacceptable unless it can be proven that traffic impacts can be mitigated to acceptable levels. A full traffic impact assessment (TIA) would be required to assess impacts on all roads in the exclusion zone and the public transport system and a feasible traffic diversion scheme would need to be developed. Emergency plans would also be required.
Marine Traffic
A3.4.5 Access
must be maintained for vessels accessing the pier at
A3.4.6 The
exclusion zone for blasting would also be applied to marine vessels in the area
and together with the requirement to evacuate the
Weather
A3.4.7 The
KTCDA is close to the slopes of
Other Issues
A3.4.8 The revised alignment for Route 7 and extent of the Green Island Developments are currently under review but at present the programme of these developments is unlikely to be advanced before 2002 and after the target completion date for demolition of KTCDA. These development proposals should therefore have no impact on the Project.
A3.5 Implications of the Presence of Asbestos
Containing Materials
A3.5.1 An Asbestos Investigation Report (AIR) and Asbestos Abatement Plan are required under the Air Pollution Control Ordinance (APCO) prior to the commencement of any asbestos abatement work. Reports and plans prepared by Registered Asbestos Consultants (EPD register RACs 1014 and 1019) indicate asbestos containing materials (ACM) are present at the Site.
A3.5.2 The
Brief assumes that any asbestos containing materials (ACM) present in the chimneys and
superstructures within the two sites will be removed before commencement of the
demolition works. However, experience
suggests that in practice the asbestos abatement processes will run more
smoothly if both asbestos contractors and civil demolition contractors work in
tandem, as has been the case with the civil demolition of the remaining
buildings and structures at other large industrial locations in
A3.5.3 Records show that bulk asbestos removals of ACM from the KTIP was undertaken prior to the removal of main plant and machinery some years ago. Site surveys and inspection of the plans for the KTA suggest that asbestos containing materials (ACM) are present in the chimney of the KTA. Drawings indicate that an asbestos rope was used to seal joints between the sections of the chimney. Such materials may only be accessible as the sections of the chimney are dismantled. Blasting could result in the uncontrolled release of asbestos fibre. Therefore blasting will not be an option. Other areas which will require investigation but which have to date not been accessed include the insulation to the carcass incinerator, the blood boilers and chimney duct insulation. However, the presence of ACM in these locations will not have a significant bearing on the choice of demolition method as they can be removed as soon as the relevant plant is decommissioned.
A3.5.4 Investigations
have confirmed the presence of a typical low risk asbestos containing material
(ACM) on the superstructures of the KTIP incinerator building. This is in the form of corrugated metal
weather cladding with an asbestos type mastic protective paint coating. This is identical to ACM typically found at
other industrial sites in
A3.5.5 Site visits did not reveal any potential ACM in the New World Bus Depot or the other parts of the Site. Other areas have been investigated but no potential ACM has been identified. Details are presented in the dedicated Asbestos Study Report (Asbestos Investigation Report and Asbestos Abatement Plan).
A3.6.1 Based on the information presented in Section 3 the consultants believe that sufficient information has been gathered to recommend that the preferred method of demolition should adopt a top-down, non-explosive approach for the demolition of Kennedy Town Comprehensive Development Area.
A4. General Approach to Demolition of
Buildings and Structures at KTCDA
A4.1 General Approach
A4.1.1 This section seeks to illustrate some of the more general procedures for demolition that would apply to KTCDA. The intention in this and section 5 is not to prescribe a precise method or provide a work specification or a demolition plan but to indicate the approach which should be taken, in sufficient detail to facilitate broad agreement on the methodology and progress Environmental Impact Assessment.
A4.1.2 Whereas the eventual detailed demolition plan of the selected demolition contractor(s) may not necessarily adopt the precise methodology proposed in this working paper, the consultants believe that general characteristics of the methods are appropriate. The methods are sufficiently effective and applicable for the tasks and where possible methods that will help reduce noise and dust nuisances have been indicated. The options selected are also broadly in line with the Draft Code of Practice for Demolition of Buildings (Buildings Department 1998) which will also need to be observed at the detailed design stage.
A4.1.3 The overriding concerns for the demolition Projects will be safety and minimisation of environmental impacts. This will include the safety of the operatives, safety of the other workers on the site and safety of the general public as well as protection of adjacent facilities and minimisation of nuisances.
A4.1.4 The Contractor should during the course of demolition, ensure and verify that all utilities and services have been rendered safe.
A4.2 Hoarding and Site Access
A4.2.1 Typical hoardings would to be provided along the site boundaries. Portable barricades will be used to cordon off different work zones where demolition is in progress. Where conditions warrant the Contractor should seek opinion and advice from the Site Engineer/AP/RSE in order to modify such plans accordingly.
A4.2.2 The buildings and chimneys are totally within the proposed Project site and access would be controlled by security guards. No members of the public or unauthorised person would be allowed to enter the sites.
A4.2.3 Only contractors’ personnel and Government officials concerned with the demolition would be allowed within the contractors working area.
A4.3 Demolition Principles
A4.3.1 Building and other structures should generally be demolished in the reverse order to that of their construction. The order of demolition for building would be progressive, storey by storey, having regard to the type of construction.
A4.3.2 As a general rule, wherever possible, external non-loading bearing cladding or any non-structural work should be removed first. All asbestos containing materials (ACM, particularly any ACM panels, would be removed prior to commencement of demolition works where ever possible. Other ACM may need to be removed as access is gained to particular areas and as the demolition progresses (see also section 3).
A4.3.3 Overloading of any parts of the remaining structure with debris or other materials should be avoided. Where materials and debris and are lowered from higher levels, care should be taken to prevent the material from swinging in such a manner that it creates a danger to the workers on site or the surrounding structures. Larger pieces of debris should be broken down into manageable sizes, subject to a maximum of 1.0m x 1.0m. The weight of loaded buckets for unloading debris would be limited to say, 200 kg.
A4.3.4 All debris would be removed at frequent intervals preferable on a daily basis and stockpiles should not be allowed to build up. In general it is anticipated that demolition waste would be removed on a daily basis with several tens of lorries leaving either site each day at the peak of demolition activities.
A4.3.5 Reinforced concrete structural members should be cut into lengths appropriate to the weight and size of member before being lowered to the ground. Where possible, crane and lifting gear should be used to support beams and columns whilst they are being cut and lowered to the ground.
A4.3.6 Removal of bricks walls should be from top to bottom in horizontal runs of not more that 300mm wide.
A4.3.7 Before and during demolition, the Contractor should pay attention to the nature and condition of the concrete, the condition and position of reinforcement, and the possibility of lack of continuity of reinforcement should be ascertained. Attention should also be paid to the principles of the structural design to identify parts of the structure, which cannot be removed in isolation. If uncertainties exist then advice of the Site Engineer/AP/RSE’s advice should be sought.
A4.3.8 During demolition works, if anomalies or irregularities are discovered in structural elements, regarding reinforcement bar details, alteration and addition works, unauthorised building works, etc, demolition works should stop immediately. AP/RSE should be informed and works will commence only after AP/RSE approval is obtained.
A4.3.9 If the Contractor discovers that the removal of certain parts of the buildings or structure during demolition would result in other parts becoming unsafe, it would be necessary to determine where temporary support will be needed and the advice of the Site Engineer/AP/RSE should be sought.
A4.4 General Safety Measures
A4.4.1 The Contractor will need to carry out works in accordance with the Factories and Industrial Undertakings Ordinance, particularly the Construction Site (Safety) Regulations and the Code of Practice for Scaffold Safety, as well as all other statutory requirements and guidelines covering health and safety issues.
A4.4.2 All contractor and sub-contractors should be competent and qualified in demolition works. Site Engineer/AP/RSE(s) will need to ensure that all levels of Contractor(s) and his subordinates are fully conversant with the demolition plans, method statements and procedures.
A4.4.3 Where scaffolding is used, the Contractor should arrange for a competent scaffolder to visit site and inspect the scaffolding work, and to make any adjustments required to the scaffolding as the work proceeds, to ensure its stability.
A4.4.4 The Contractor shall also appoint a competent person, experienced or trained in the type of operation being performed at that particular time, to supervise and control the work on site.
A4.4.5 The Contractor should ensure that every work place, approach and opening, which may pose a danger to persons employed and others should be properly illuminated and protected.
A4.4.6 The use of all mobile cranes must be strictly controlled to ensure that cranes of adequate capacity will be used for lifting under different loading conditions.
A5. Principles
of Chimney Demolition at KTCDA
A5.1.1 The main site would be protected by security personnel and a high hoarding such that the public would be totally excluded from the Project.
A5.1.2 The area beneath the chimneys would be cordoned off and only authorised staff involved in the demolition of the chimneys would be allowed admission into the vicinity of the chimney structures.
A5.2.1 The principle of the demolition procedure for the upper portion of the chimneys (i.e. say 10meters from ground level or greater) is that the chimneys will be broken into small pieces on the spot by operatives using hand held tools. They would work from working platforms external to the chimney (Figure 5.1). Hydraulic breakers would be used for the remaining lower portions of the chimneys.
A5.2.2 Prior to the commencement of the demolition work, loose sand will be placed on top of the existing ground around the chimneys to receive small pieces of light debris that may fall. To facilitate the access of the excavators for the removal of debris, an access ramp will be formed. The vertical opening (former fan duct connection point) near the base of the stack would be blocked when demolition is in progress. This portal would be opened for removal of debris after completion of daily demolition work. The above mentioned method of removal of debris is only applicable to the demolition of the upper portion of the chimneys.
A5.2.3 For demolition of the lower portion, the demolished debris would be formed as an access ramp for the hydraulic breaker to ascend to a height sufficient to gain access and demolish the remaining portion of the chimney.
A5.2.4 The demolished debris would be broken down and removed by hydraulic excavators and loaded on to trucks for transportation to the designated disposal site. During the demolition work, water sprays will be used to suppress excessive dust generated by the processes.
A5.3.1 The area surrounding the chimney will be secured and all necessary barricades erected. Only authorised personnel will be allowed into the area. A steel external working platform system will be erected to surround the upper portion of the chimney, i.e. greater than 10 meters above ground level. The maximum distance between the floor levels of the working platforms will be two meters. Access steel ladders will be constructed from ground level to the top of each chimney, with proper handrails (Figure 5.1).
A5.4.1 The demolition sequence would involve the construction of a series of working platforms around the outside of a chimney. Workers would work from the top most platform to remove the chimney structure with the debris directed into the lower portion of the remaining chimney. This would involve the following steps.
d) After completing the work at
one level operatives would descend to the working platform just below and
remove the components of the upper platform carefully. Demolition at the lower platform level would
then proceed safety nets will be installed in the same
manner as described in procedure (b) above.
f)
The same sequence of work from procedure (b) to (d)
would be repeated until the chimney had been lowered down to approximately 10m
chimney height, a level within the reach of mobile hydraulic breakers at ground
level. The lower portion will be removed
by these means.
A5.5.1 The buildings and chimneys at KTCDA can be demolished and removed by the conventional top down demolition using hand held tools and mechanical breaking methods. In order to avoid hazards caused to the adjacent areas, all the structures and other buildings near to the chimneys would be demolished and removed prior to the demolition of the chimneys.
A5.5.2 The estimated time for the completion of these works included in the PPFS was 12months which would appear to be ample time for demolition based on the above methodology.
A6.1.1 This paper presented information concerning the difficulties associated with the demolition of the Kennedy Town Comprehensive Development Area (the Project). In order to facilitate the progress the EIA process as a whole it is necessary to define the Projects in sufficient detail in line with the objectives of the Study.
A6.1.2 The primary aim of this paper is to establish a conceptual
demolition method in order to facilitate progress the EIAs. During the preliminary investigations the
consultants have taken note of the work conducted previously and also initiated
discussions with relevant Government departments, many of whom have expressed
severe concerns with the proposals to include any form of blasting techniques
for the felling of the chimneys or the main building structures at the site.
A6.1.3 In the selection of an appropriate demolition method the physical effects on local sensitive receivers and adjacent structures are very important. There are also hidden costs arising from the need to carefully co-ordinate demolition by implosion. The effect on marine and road transport systems and the complexity of implementing controls is also an important factor. The cumulative impacts of the surrounding interfaces on the project methods have been assessed and make demolition by implosion at either site a potentially costly and a very high risk proposal.
A6.1.4 The preferred demolition methodology presumes that a variety of top down methods would be used and various articles from a suite of powered mechanical equipment has been assumed to be in use at various locations across the site throughout the demolition. The use of jack-hammers and hydraulic breakers is efficient and noise and dust impacts can potentially be controlled by a range of mitigation measures (e.g. noise barriers, dust control) familiar to the construction industry in Hong Kong. In addition the statutory provisions under the Noise Control Ordinance and Air Pollution Control Ordinance control noise and dust from such operations. Due to the presence of ACM the preferred method of demolition must adopt non-explosive approach. The asbestos investigation and abatement plans are described in detail in the dedicated Asbestos Study Report.
A6.1.5 In order to facilitate the progress of the Environmental Impact Assessment the consultants sought and gained endorsement of the content of this paper. Whereas the eventual detailed demolition plan of the selected demolition contractor(s) may not necessarily adopt the precise methodology proposed in this working paper, the methods used shall adopt top-down, non-explosive methods for the demolition of Kennedy Town Comprehensive Development Area.
Appendix B Role of Independent Checker (Environmental) IC(E)
B.1 Role
of IC(E)
B.1.1 The information in this section is advisory only and does not form part of the works contract. In addition to the specific duties identified, any additional advisory services between the IC(E), ER and the project proponent could be provided on an as needed basis, subject to agreement between the parties.
B.1.2 The role of the IC(E) shall be independent from the management of construction works; but the IC(E) shall be empowered to audit the environmental performance of construction. The IC(E) shall have a similar of level of experience as the ETL. The ER shall approve the proposed nominated IC(E).
B.1.3 The duties of the IC(E) are to:
· Review and audit all aspects of the EM&A programme
· Validate and confirm that monitoring is undertaken in accordance with the procedures, frequencies, equipment and locations specified in the EM&A Manual, and any other conditions imposed in the EP with regard to the EM&A programme.
· Conduct site inspections as considered necessary to verify site conditions.
· Audit EIA and EP construction phase mitigation requirements against the status of implementation.
· Review effectiveness of construction phase environmental mitigation and performance
· Approve alternative working methods proposed by the contractor where these reduce impacts. Audit working methods as instructed by the ER to determine if there are alternatives that can be adopted.
· Audit complaint cases to confirm follow up actions are in accordance with the EM&A Manual requirements
· Carry out any specific requirements in the EP specified for action by the IC(E).
B.1.4 With reference to Event and Action Plans, where an event requires the ET or contractor to inform the ER, the ER will have a duty to inform the IC(E). For contractual reasons this arrangement should be adopted, rather than contractual requirements for the ET or contractor to communicate with the IC(E) directly. Actions required by the IC(E) in verifying implementation of the Event Action Plans should be clearly defined in the Scope of Works for the construction phase of the project. This would either be defined through the duties of the Engineer, or through a separate agreement between the project proponent and a third party IC(E).
Landfill Disposal Criteria for Contaminated
Land
Metals
Parameter |
TCLP Limit (ppm) |
Cadmium |
10 |
Chromium |
50 |
Copper |
250 |
Nickel |
250 |
Lead |
50 |
Zinc |
250 |
Mercury |
1 |
Tin |
250 |
Silver |
50 |
Antimony |
150 |
Arsenic |
50 |
Beryllium |
10 |
Thallium |
50 |
Vanadium |
250 |
Selenium |
1 |
Barium |
1000 |
Source : Guidance Notes for Investigation and Remediation
of Contaminated Sites (EPD TR1 / 99).
Metals
Toxicity Characteristics Leaching
Procedure (TCLP) test for materials contaminated with heavy metals needs to be
carried out in accordance with the testing frequency and requirements as
stipulated in EPD’s Guidance Notes for Investigation
and Remediation of Contaminated Sites.
TPH and PAH
Toxicity Characteristic Leachate Testing
Procedure (TCLP) tests for TPH, PAH and BTEX contaminated materials have to be
carried out according to the testing frequency and requirenments
as stipulated in EPD’s “Guidance Notes for Investigation and Remediation of
Contaminated Sites. Pretreatment
is required to bring levels of TPH to below the TCLP limit of 2,500ppm PAH/BTEX
to below the TCLP limit 1,000ppm.
Dioxins and Furans (PCDD/PCDF)
Toxicity Characteristic Leachate Testing
Procedure (TCLP) tests for PCDD/PCDF contaminated materials have to be carried
out according to the testing frequency and requirements as stipulated in EPD’s “Guidance Notes for Investigation and Remediation of
Contaminated Sites. Pretreatment
is required to bring levels of PCDD/PCDF to below the TCLP limit of 1ppb
PCDD/PCDF (TEQ). TCLP testing shall be
at a frequency of 1 sample per 100 tonnes of stabilised material.
N.B.
TEQ =toxicity
equivalent units.
ppm
= mg/kg (miligrams / kilogram)
ppm
= mg/g
(micrograms / gram)
ppb
= ng/g (nanograms
/ gram)
ppb
= 1000pg/g (picograms / gram)
1. Hazards and Safety Precautions
1.1 Introduction
1.1.1 Hazards which may arise at KCIP generally be classified under the following headings:
· General Hazards
· Gas hazards
· Landfill leachate
Operators
1.2.1 Operators should be experienced and licensed drivers. Where possible, all operators should be required to demonstrate their driving ability in the equipment they will be operating and under actual job conditions before recruitment.
1.2.2 Only personnel with valid driving licences are permitted to drive any site cars or vehicles. In the case of vehicles which are not intended for road use, the driver should hold a licence for the nearest comparable class of road vehicle.
1.2.3 For operators employed, a photocopy of their driving licence should be obtained. Their validity and the class of vehicle licences to drive should be checked.
1.2.4 The site office should keep an up to date list of names and copies of driving licences of drivers of motor vehicles and plant.
Equipment
1.2.5 Drivers should make a daily inspection of their vehicles. The check should include steering, brakes, mirrors, lights, horn, tires and windshield wipers. Reverse alarms which must be installed on all trucks and lorries should also be checked to ensure safe operation. Drivers are required to report all defects to the plant mechanic foreman, and repairs should be made promptly.
Roads
1.2.6 Site roads should be maintained in safe operating condition at all times. Roads should be built to provide adequate drainage and width and should avoid sharp curves, abrupt changes in gradient and excessive gradients. The use of one-way traffic roads is recommended wherever possible. Site roads must have clearly visible signs in both Chinese and English.
Transporting Personnel
1.2.7 Personnel should only ride in vehicles designed for the purposes. It is forbidden for personnel to take rides with operations where no specific sear has been provided for passengers.
Loading Lorries
1.2.8 Materials loaded onto lorries should be within the permitted safe weight limit and should not project beyond the lorry body or be placed in an unsafe pile in such a manner as to present a hazard to other vehicles, pedestrians or structures.
General Requirements
1.2.9 Drivers leaving the driver leaves the driving seat of a vehicle shall ensure the engine shall is switched off, the gear engaged and parking brakes applied. The wheels shall be chocked on slopes.
1.2.10 Lorries should only be backed under the direction of a marshal or spotter. In dumping areas, the marshal and spotters should be identified by a reflective vests.
1.2.11 All operators and drivers are required to observe speed limits at all times.
1.2.12 All pedestrians requiring to pass close to an operating machine shall ensure that the machine operator has been them and has stopped operation prior to proceeding.
1.2.13 All personnel working on site roads or directing traffic shall wear reflective vests.
Plant Noise
1.2.14 The foreman shall ensure that noise assessments are carried out on all noisy plant used on site. Any plant that creates noise exceeding the first action level stated in the Factories and Industrial Undertakings (Noise at Work) Regulations should be identified, with notices fixed to the plant and appropriate action should be taken as described in the Regulations to avoid exposure to the noise. Attention shall also be paid to the recommended Environmental Monitoring and Audit plan for the site.
1.3.1 Waste in the landfill emits a mixture of gases. The composition of gases at KCIP is not known however leachate gases of the following composition would not be untypical for such a site approximately as follow:
· 45-55% methane – Explosive.
· 44-54% Carbon Dioxide – Asphyxiant.
· 1% Other gases – mainly organic vapours.
1.3.2 The main danger from landfill gas is due to explosion of methane, however, if large concentrations of gas displace air there can be a danger of asphyxiation or poisoning. Gas concentrations are likely to be higher near the tops of gas wells and near exposed areas of leachate collection stone.
1.3.3 All personnel are advised to observe the following guidelines to avoid gas accidents:
· No smoking on the site.
· Do not enter trial pits unless the air quality has been tested (see 1.6)
· If any personnel has any of the following health symptoms while working at, in or near a trial pit on the Site he should move away from the area of the trial pit immediately:
- Headache,
- Dizziness / lightheadedness,
- Tingling or numbness,
- Nausea,
- Blue lips or bright red skin.
1.3.4 Once the affected person has moved to a position remote from the trail pit he should inform his supervisor who will evaluate the situation, decide whether other persons should be evacuated from the immediate area whether medical aid is required.
1.4 Landfill
Leachate
1.4.1 Solid waste in the reclamation under the site or leachate originating from GDBL may be toxic, the following rules should therefore be observed:
· If leachate has to be handled, or groundwater samples lotion ensure that the operatives wear protective clothing and gloves. If any operatives come into contact with leachate, should be immediately wash the affected area with clean fresh water.
· Ensure that any broken skin, cuts, graze and the like do not come into contact with waste or leachate. All cuts etc should be covered prior to working on the site.
· Safety boots should be worn on the site.
· All operatives should keep a lookout for sharp objects on the site such as broken glass, syringe needles, nails in pieces of wood and the such like.
· If any operative receives any cuts or grazes whilst he is on he landfill, he should report this immediately to his supervisor who will arrange for medical attention.
1.5.1 All operational and supervisory staff’s attention shall be drawn to the hazards of landfill gas generated by decaying refuse in the landfill which may have migrated to the KCIP Site. This gas can endanger the safety of workers, as the flammable gas it contains explosive potential once it is mixed with air. Attention shall also be given to other components of the gas which have the potential to cause asphyxiation or toxic effects under appropriate conditions.
1.5.2 Smoking and the use of naked lights and welding shall be prohibited in areas of the site where landfill gas likely to be present and can migrate. Warning signs designating “no smoking areas” shall be put up to remind workers of these restrictions.
1.5.3 Plant and mobile plant shall carry fire extinguishers, and shall be equipped with properly functioning spark arrestors and automatic air intake shut down valves. Wherever possible diesel operated plant shall be used.
1.5.4 No fires shall be permitted on the site. Operational and supervisory staff shall immediately extinguish any fires within the site.
1.5.5 Confined spaces and excavation where entry is required shall be treated as described under Section 1.6.
1.5.6 Temporary offices, huts and storage containers shall not be located where infiltration of gas could occur, and in any event shall be provided with simple gas protection measures and detection systems where appropriate.
1.5.7 Fire fighting facilities shall be maintained on the site, and shall be property housed and kept readily available for instant use.
1.5.8 The site designated emergency co-ordinator shall liaise with the Fire Services Department to ensure that they are in a position to respond quickly to any fire or explosion which may occur. The emergency co-ordinator shall notify the Fire Services Department immediately in the event of any such emergency.
1.5.9 The site agent shall carry out the following:
· Prepare detailed working procedures and safety precautions for the work being carried out.
· Instruct the workmen and other staff in the working procedures and safety precautions to be followed.
· Record in writing that the workmen and other staff have been so instructed.
· Provided sufficient equipment so the working procedures and safety precautions can be followed.
· Ensure the working procedures and safety precautions are adhered to.
1.6 Working
in Confined Spaces
1.6.1 The Site contractor shall ensure that any work in a confined space, as defined in the Factories and Industrial Undertakings (Confined Spaces) Regulations, complies with the requirements of the Regulations and is in accordance with the Guide to the Regulations published by the Labour Department.
1.6.2 All entries into confined spaces will be subject to a written detailed safe working procedure and a permit to work procedure. The written safe working procedure will include, but may not be limited to, details of the following: -
· arrangements for detecting toxic or explosive gas or oxygen deficiency, and the detection equipment to be used.
· supervision arrangements
· safety and emergency rescue equipment to be used, including breathing apparatus, safety harness and safety ropes
· permit to work procedures
1.6.3 All persons entering a confined space shall have received appropriate training from authorised bodies.
1.6.4 All written safe working procedures and completed “Permit-To-Work Certificate” shall be kept in the site office.