Civil
Engineering Department
The
Government of the
Special
Administrative Region
Agreement No. CE
15/99
Demolition of Buildings and
Structures
in the
Proposed
Comprehensive Development Area Site
Environmental
Impact Assessment (Final Report)
September
2001
Atkins China Ltd
Client
: Civil Engineering Department |
Contract
No. (if any) : - CE 15/99 |
||||
Project
Title : Environmental Impact
Assessment for Demolition of Kwai Chung Incinerator Plant and Kennedy Town
CDA |
Project No. : 2996 |
||||
Document No. : 2996-OR025-05 |
Controlled Copy No. : |
||||
Document Title : Final Environmental Impact
Assessment |
|||||
Covering Letter / Transmittal Ref. No. : 2996/15.40/ |
Date of Issue : September
2001 |
||||
Revision, Review
and Approval/Authorisation Records |
|||||
05 |
6th Issue |
Various/ |
JWS/ |
DG/ |
|
04 |
5th Issue |
Various/ |
JWS/ |
DG/ |
|
03 |
4th Issue |
Various/ |
JWS/ |
DG/ |
|
02 |
3rd Issue |
Various/ |
JWS/ |
DG/ |
|
01 |
2nd Issue |
Various/ |
WD/ |
DG/ |
|
00 |
1st Issue |
Various/ |
JWS/ |
WD/ |
|
Revision |
Description |
Prepared by / date |
Reviewed by / date |
App. or Auth. By /
date |
|
Distribution
(if insufficient space, please use separate paper)
Controlled
Copy No. |
Issued
to |
1-45 |
Civil
Engineering Department |
46-47 |
ACL
– ELAN |
|
|
Note : App. and Auth. mean “Approved” and “Authorised” respectively.
Table of Contents
Executive
Summary
1.2 Purpose and Objectives of the Assignment
2. Study Area, Sensitive Receivers,
Constraints and General Approach to Demolition
2.4 General Approach to Demolition of Buildings and
Structures at KTCDA
2.5 Principles of Chimney Demolition at KTCDA
3.1 Site Location and Description
3.2 Asbestos Investigation Methodology
3.6 Programme for Asbestos Removal
3.7 Regulations, Codes of Practice and Local Requirements
4.1 Requirement for Land Contamination Assessment
4.5 Sampling Locations and Analysis of Results
4.8 Procedures for Management of Contaminated Rubble / Ash
Waste Material
4.9 Management of Contaminated Soil Material
4.10 Protection of Site Workers During Excavation and
Treatment of Soils
5.2 Government Legislation and Standards
5.5 Potential Sources of Impact
6.2 Government Legislation and Standards
7.2 Assessment Criteria and Methodology
7.4 Waste Disposal (Chemical Waste) (General) Regulation
7.6 Land (Miscellaneous Provisions) Ordinance
7.7 Public Cleansing and Prevention of Nuisance Regulation
7.9 Impacts of Wastes Generated from Demolition
7.11 Waste Management Planning
8. Environmental Monitoring and Audit
8.2 Environmental Monitoring and Audit
8.3 Event Contingency Plans (ECPs)
9. Conclusions and Recommendations
9.4 Land Contamination and Remediation
9.8 Environmental Monitoring and Audit.
List of Tables
Table 2.1 Structures to be demolished at KTCDA
Table 3.1 Main Locations for ACM Investigation at KTCDA
Table 3.2 Areas of ACM Identified by Functional Zone
Table 3.3 Estimate of Amount of ACM Weather Cladding
Table 4.1 Summary of Analytical Results – Soil Samples
Table 4.2 Summary of Analytical Results – Groundwater Samples
Table 4.3 Actions Required Post Demolition
Table 5.1 Noise Standards for Daytime Construction Work
Table 5.2 Representative Noise Sensitive Receivers
Table 5.3 Estimated Distances from Chimneys
Table 5.4 Base Suite of Demolition/Construction Plant
Table 5.5 Base Suite of Soil Remediation Construction Plant
Table 5.6 Predicted Unmitigated Noise Levels from Demolition
Table 5.8 Revised Suite of Demolition and Ground Remediation Plant
Table 5.9 Predicted Mitigated Noise Levels from Demolition of
Buildings other than Chimneys
Table 5.10 Predicted Mitigated Noise Levels from Demolition of
Chimneys Only
Table 5.11 Predicted Mitigated Noise Levels (Ground Remediation)
Table 6.1 Representative Air Sensitive Receivers
Table 6.2 Hong Kong Air Quality Objectives (mg/m3) (a)
Table 7.1 KTCDA Principal Demolition Products
Table 7.2 Summary of Waste Management Impacts
Table 8.1 Schedule of Impacts and Mitigation Measures
List of
Figures
Figure 1.1 Kennedy Town CDA Locality Plan
Figure 2.1 Kennedy Town CDA Sensitive Receivers
& Constraints
Figure 2.2 Kennedy Town CDA Outline Zoning Plan
Figure 2.3 Typical Perimeter Noise Barrier
Figure 2.4 External Working Platforms
KTCDA Chimneys
Figure 4.1 Kennedy Town CDA Borehole Locations
Figure 4.2 Contaminated Locations Requiring Clean
Up
List of
Appendices
Appendix A Preferred
Demolition Methodology (Extracted From WP1 Originally Presented November 1999)
Appendix B Criteria for Soil Contamination and Landfill Disposal of Contaminated Soil
Appendix C Water Quality Standards
Appendix D Hazards & Safety Requirements
Appendix E Environmental Outcome Profile
List of
Abbreviations
AAP |
Asbestos Abatement Plan |
ACE |
Advisory Council on Environment |
ACM |
Asbestos Containing Material |
AIR |
Asbestos Investigation Report |
AP |
Authorised Person |
APCO |
Air Pollution Control Ordinance |
AQO |
Air Quality Objective |
ASR |
Air Sensitive Receivers |
ASTM |
American Society for Testing Materials |
BTEX |
Benzene, Toluene, Ethylbenzene and Xylene |
BOO |
Building Ordinance Office |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CED |
Civil Engineering Department |
CP |
Car Park |
CPLD |
Committee on Planning & Land Development |
CSTG |
|
CSL |
Registered Asbestos Consultant |
DCDB |
Draft Code of Practice for Demolition of Buildings
|
DSD |
Drainage Services Department |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EM&A |
Environmental Monitoring & Audit |
EMSD |
Electrical & Mechanical Services Department |
EPD |
Environmental Protection Department |
FEHD |
Food and Environmental Hygiene Department |
G I/C |
Government, Institutional/Community |
GDBL |
Gin Drinker’s Bay Landfill |
HEC |
Hong Kong Electric |
HOKLAS |
|
IAR |
Initial Assessment Report |
KTA |
|
KTCDA |
|
KTIP |
|
MTIA |
Marine Traffic Impact Assessment |
NCO |
Noise Control Ordinance |
NSR |
Noise Sensititve Receiver |
NWFB |
|
PCDD / PCDF |
Dioxins and Furans |
PCWA |
Public Cargo Working Area |
PFBP |
Public Fill Barging Point |
PAC / PAH |
Poly Aromatic Hydrocarbons |
PME |
Powered Mechanical Equipment |
PPFS |
Preliminary Project Feasibility Study |
PQA |
Preliminary Quantitative Assessment |
RAC |
Registered Asbestos Contractor |
RAP |
Remediation Action Plan |
R7 |
Route 7 |
RCP |
Refuse Collection Point |
RSE |
Resident Site Engineer |
SB |
Study Brief |
SR |
Sensitive Receiver |
TMEIA |
Technical Memorandum on the EIA Ordinance |
TM |
Technical Memorandum |
TPH |
Total Petroleum Hydrocarbons |
URA |
Urban Renewal Authority |
WDO |
Waste Disposal Ordinance |
WP1 |
Working Paper 1 |
a) the
overall acceptability of any adverse environmental consequences that are likely
to arise as a result of the proposed Project;
b) the
conditions and requirements for the detailed design and/or demolition of the
proposed project to mitigate against adverse environmental consequences and
potential safety and health hazards wherever practicable;
c) the
acceptability of residual impacts after the proposed mitigation measures are
implemented.
a)
to describe the proposed
project and associated works together with the requirements for carrying out
the proposed project;
b)
to identify and describe the
elements of the community and environment likely to be affected by the proposed
project and/or likely to cause adverse impacts to the proposed project,
including both the natural and man-made environment;
c)
to identify and qualify
emission sources and determine the significance of impacts on sensitive
receivers and potential affected uses;
d)
to propose the provision of infrastructure
or mitigation measures so as to minimise pollution, environmental disturbance
and nuisance during demolition;
e)
to identify, predict and
evaluate the residual (i.e. after practicable mitigation) environmental impacts
and the cumulative effects expected to arise during the demolition of the
facilities in relation to the sensitive receivers and potential affected uses;
f)
to identify, assesses and
specify methods, measures and standards, to be included in the detailed design
and demolition of the project which are necessary to mitigate these
environmental impacts and reducing them to acceptable levels;
g)
to investigate the extent of
side-effects of proposed mitigation measures that may lead to other forms of
impacts;
h)
to identify constraints
associated with the mitigation measures recommended in the EIA study; and
i)
to design and specify the
environmental monitoring and audit requirements, if required, to ensure the
implementation and the effectiveness of the environmental protection and
pollution control measures adopted.
· Section 2 Study Area, Sensitive Receivers, Constraints and General Approach to Demolition.
· Section 3 Asbestos Control.
· Section 4 Land Contamination.
· Section 5 Noise.
· Section 6 Air Quality.
· Section 7 Waste Management.
· Section 8 Environmental Monitoring and Audit.
·
Section 9 Conclusions and Recommendations.
·
·
·
· Car / lorry park (CP);
·
FEHD Refuse
Collection Point (RCP); and USD
·
Table
2.1 Structures to be demolished at
KTCDA
Building |
Brief Description |
KTIP Chimneys |
Two reinforced concrete chimneys, 60m high, 3.5m in diameter. |
|
Reinforced concrete structure of approximately 3,025m² on plan Refuse Pier |
|
5-storey reinforced concrete structures of approximately 9,500m² on plan, including, Reception Pier |
|
Boiler House
and One reinforced concrete chimney, 25m high, 3m in diameter. |
|
Offices and
Vehicle Inspection Bays. Overall size is approximately 600m² on plan. Diesel storage
tank and lubrication oil store |
|
Single Storey Transformer House (adjacent to lairage) |
|
Open landscaped area with street lighting and sitting areas |
Sai See Street Refuse Collection Point |
Prefabricated steel and concrete structure, single storey. * |
*See Section 2.2
Residential, Government, Institutional and Community
· Kennedy Town Police Married Quarters currently overlooks the Site. The premises are scheduled to be vacated but parts of the buildings will potentially be occupied up to March 2002.
· The Mount Davis Cottage Area has been vacated.
·
The Housing
Society development at .mid
·
There are
occupied residential buildings at
Other Sensitivities near KTCDA
NWFB
RCP
Road Traffic
Marine Traffic
Other Issues
·
Top down methods by jack
hammer, percussive or hydraulic breakers;
·
Wrecking Ball;
·
Implosion;
·
Saw Cutting and Drilling;
·
Non
explosive demolition agents (NEDA);
·
Thermal lance; and
· Water jet.
Reception Piers
Preferred Methodology
Marine Barges
Road Traffic
· Typical perimeter noise barriers are shown in the indicative hoarding plan (Figure 2.3).
· Portable barricades will be used to cordon off different work zones within the Site.
· All structures are totally within the proposed Project Site and access would be controlled by security guards.
· No members of the public or unauthorised person would be allowed entry to the Site.
· Only contractors’ personnel and Government officials would be allowed within the Contractor’s working area.
· Demolition of building and structures would generally be in the reverse order to that of construction, progressive, storey by storey, having regard to type of construction.
· Wherever possible, external non-load bearing cladding should be removed first.
· All asbestos containing materials (ACM, particularly any ACM weather cladding, would be removed prior to commencement of demolition works where ever possible. Other ACM may need to be removed as access is gained to particular areas and as the demolition progresses (see also Section 3).
· Overloading of any parts of the remaining structure with debris or other materials should be avoided.
· All debris to be removed at frequent intervals and stockpiles should not be allowed to build up. Waste to be removed on a daily basis.
· Reinforced concrete structural members to be cut into appropriate lengths before being lowered. Crane and lifting gear should support beams and columns whilst being cut and lowered.
· Brick walls to be removed top to bottom in horizontal runs (<300mm deep).
· Determine where temporary support will be needed upon advice of the Site Engineer/AP/RSE.
Upper Chimneys
Lower Chimneys
· The same sequence of work above would be repeated until the chimney had been lowered down to approximately 10metres, a level within the reach of mobile hydraulic breakers at ground level. The lower portion would be removed by these means.
Access
Table
3.1 Main Locations for ACM
Investigation at KTCDA
Building |
Brief Description |
KTIP Chimneys |
Bases of two reinforced concrete chimneys, 60m high, 3.5m in diameter. |
|
Reinforced concrete structure of approximately 3,025m² on plan ACM Cladding Refuse Pier. |
|
5-storey reinforced concrete structures of approximately 9,500m² on plan, including, Blood and
Bone House ( Reception Pier. |
|
Boiler House
and One reinforced concrete chimney, 25m high, 3m in diameter. Other Buildings. |
|
Offices and Vehicle Inspection Bays. No potential ACM on walkthrough inspection . |
|
Single Storey Transformer House (requires checking) |
|
(All
structures removed previously by Government. No ACM Suspected) |
Sai See
Street Refuse Collection Point |
(New Construction.
No ACM Suspected.) |
Table 3.2 Areas of ACM Identified by Functional Zone
Functional
Space |
Homogenous
Material |
Location |
Removal prior
to main civil demolition * |
Homo-genous
Area |
Estimated
Quantity Approx. |
Friability |
Condition |
Use |
Accessibility |
Asbestos
Material |
|
Corrugated Metal Sheeting |
Throughout |
No* |
Weather Cladding |
Total 1000m3 (see Table 3.3) |
No |
Fair to Good |
Weather Protection |
Low |
Type 1 |
KTIP Chimneys |
Asbestos containing deposits |
Deposits at base of Chimneys A and B |
Yes |
Heterogeneous deposits |
Two 30cm deep 3m diameter circular areas chimney base Total <3m3 |
Yes |
Poor but compacted |
Debris (source unknown) |
Low |
Type 3 |
KTIP Office Block |
Floor Tile / Adhesive |
Offices |
Yes |
Floor Tile |
20m x 6m |
No |
Fair to Good |
Flooring |
Low |
Type 1 |
|
Floor Tile / Adhesive |
Offices |
Yes |
Floor Tile |
50m x 10m |
No |
Fair to Good |
Flooring |
Low |
Type 1 |
KTA (lairage roof) |
Asbestos Cloth |
Fuse Boxes |
Yes |
Asbestos Arc Shute |
5cm x 3cm wide cloth pieces. Total <2.m3 |
Yes |
Good |
Arc Shute |
Low |
Type 2 |
KTA Cattle Reception Area |
Asbestos Cement Roof |
Parts of roofing at waterfront. |
Yes |
Roofing |
3m wide x 5m long. Total <20m3 |
No |
Good |
Weather Protection |
Low |
Type 1 |
KTA Liarage Canteen Office |
Asbestos Blackboard |
Office. |
Yes |
Blackboard |
1m wide x 3m long. Total <5m3 |
No |
Good |
Blackboard |
Low |
Type 1 |
KTA Chimney Flues |
ACM in Bituminous Asphalt Coating |
Tops of five flues. |
No* |
Weather Protection |
2m x 1m x 5mm deep coating on each flue. Total <2.m3 |
No |
Fair |
Weather Protection |
Low |
Type 1 |
KTA By-Products Plant |
Asbestos Woven Gasket |
Meat Cookers and Blood Boilers |
Yes |
Asbestos Gasket |
5cm wide x 3m long (sixteen circular pieces). Total <2.m3 |
Yes |
Good |
Sealing Material |
Low |
Type 2 |
KTA Animal Carcass Incinerator |
Asbestos milboard |
Animal Carcass Incinerator |
Yes |
Insulation |
5m wide x 3m long (six sides of incinerator). Total <5.m3 |
Yes |
Poor |
Insulation |
Low |
Type 3 |
* Where
ACM not to be removed immediately prior to civil demolition it is assumed that
the main civil demolition contractor will provide access / scaffolds etc to
high level to facilitate ACM abatement and avoid duplication of effort for
building scaffold etc.
Table 3.3 Estimate of Amount of ACM Weather Cladding
Functional Space |
Area |
Location |
Area on Plan |
Estimated
Quantity Approx. |
Estimated Quantity Rounded Up to nearest 50 m² |
|
|
Roof and Walls |
30m x 50m |
1500 |
1500 |
|
South Side |
Roof and Walls |
30m x 70m |
2100 |
2100 |
|
North Side |
Roof and Walls |
30m x 70m |
2100 |
2100 |
|
|
Roof and Walls |
30m x 50m |
1500 |
1500 |
|
TOTAL |
|
|
|
7200 |
Statutory Obligations and Codes of Practice, etc.
· oil installations (e.g. oil depots and oil filling stations);
· power plant;
· chemical manufacture and processing plant; and
· car repairing / dismantling workshops.
· describe previous and current land uses within the study area;
· report the results of Site inspections from the perspective of potential land contamination; and
· present the results of the soil contamination investigation and recommendations for soil remediation or further work with respect to intrusive investigations for soil testing.
Description of Existing KTCDA Compound
Site Activities
· maintenance and repair of vehicles;
· storage of fuel;
· vehicle refuelling;
·
vehicle parking; and
·
sitting out area; and
·
refuse collection point and access (.
· waste incineration;
· abattoir;
· electrical and mechanical equipment maintenance;
· wholesale marketing;
· coal yard;
· sawmill; and
· distillery.
Car Park
Kennedy Town Incinerator Plant
Fuel Tanks
Refuse Reception Area
Refuse Bunkers
Exit Ramp and Refuse Reception Ground Floor
Switchgear Room
Generator Room
Plant Room
Transformer Areas
Exhaust and Transfer House Areas
Main Hall
Dangerous Goods Store
Dust and Grit Collection
Dust Bunker
Ash Hopper
Kennedy Town Abattoir
Entrance, Dispatch Bank & Parking
Lairage Entrance Unit and Transformer Chamber
Manure Chute Refuse Collection Ground Floor
Lairage and Reception Area
Water Treatment Plant
Pump Room
Animal Carcass Incinerator
Chimney
Boiler House
Diesel Fuel Tanks
By-Product Plant
Car Park Area
Meat Dispatch Area
New World First Bus Depot (NWFB)
Fuel Tanks
Lubrication Storage
Battery and Chemical Waste Storage
Car Park
Cadogan Street Temporary Garden (CSTG)
Kennedy Town Abattoir/Incineration Plant (KTA/KTIP)
Bus Maintenance and Refuelling Depot (NWFB)
Other Areas
· removal of the former incineration plant;
· removal of the former abattoir compounds;
· removal of the dangerous goods store;
· removal of the existing bus maintenance depot;
· removal of the flammable materials storage area; and
·
removal of existing overground
diesel and oil storage tanks and underground pipework or other substructures, such as inspection pits Rat
NWFB.diesel and oil storage tanks
· total petroleum hydrocarbons (TPH); (USEPA 8015)
· polycyclic aromatic compounds (PAC/PAH-16); (USEPA 8270)
· dioxins and furans (PCDD/PCDF); (USEPA8290&1616)
· benzene, toluene, ethlybenzene and xylene (BTEX); (USEPA 8260)
· polychlorinated biphenyls (PCB); (EP066)
· heavy metals (HM, including Ag, As, Cd, Cr, Cu, Hg, Ni, Pb, Zn); (USEPA 6020)
· inorganic parameters pH (EA002) cyanide (EK026) ammonia (EK055) phosphorus (EKO&!A) sulphate (ED041).
· [inorganic parameters analysed by HOKLAS accredited in house laboratory methods indicated by prefix E]
Table 4.1 Summary of Analytical Results – Soil Samples
Method |
USEPA 8015 |
USEPA 8260 |
USEPA 8270 |
EP066 |
USEPA 8290 |
USEPA 6020 |
EK026 |
EK055 |
EK071A |
EA002 |
USEPA |
Analysis Description |
TPH |
BTEX |
PAH |
PCB |
PCDD / PCDF |
METALS |
Total Cyanide |
Ammonia as N |
Reactive Phosphorus as P |
pH Value @ 25'C |
Moisture |
Unit |
mg/kg |
mg/kg |
mg/kg |
mg/kg |
pg/g |
mg/g |
mg/kg |
mg/kg |
mg/kg |
|
% |
Dutch B |
1000 |
0.5 to 5.0 |
1 to 10 |
1 |
n/a |
5 to 500 |
10 |
1000 |
200 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TSB1 S0.3 |
<B |
<B |
<B |
|
|
>C (Cu, Pb, Zn) >B<C (Cd) |
<B |
<B |
<B |
8.0 |
13.8 |
TSB1 M1.3 |
<B |
<B |
<B |
|
|
>C (Cu, Pb, Zn) >B<C (Cd, Hg) |
<B |
<B |
<B |
8.3 |
16.1 |
TSB1 X2.5 |
>B<C |
<B |
<B |
|
|
>B<C (Cu, Pb, Zn) |
<B |
<B |
<B |
9.5 |
17.1 |
TSB1 B3.2 |
<B |
<B |
<B |
|
|
>B<C (Pb) |
<B |
<B |
<B |
8.8 |
14.1 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB2 S0.5 |
<B |
<B |
<B |
<B |
|
>C (Pb, Cu) >B<C (As, Zn) |
<B |
<B |
<B |
9.0 |
18.1 |
TSB2 M1.5 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.4 |
13.5 |
TSB2 B3.0 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.4 |
13.8 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB3 M2.5 |
<B |
<B |
<B |
<B |
|
>B<C (Cu, Pb, Zn, Hg) |
<B |
<B |
<B |
11.3 |
13.6 |
TSB3 B3.8 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
7.8 |
16.9 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB4 S0.5 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.1 |
13.7 |
TSB4 M2.7 |
<B |
<B |
<B |
|
<U |
>B<C (Cu, Pb, Zn) |
<B |
<B |
<B |
9.5 |
15.1 |
TSB4 B3.9 |
<B |
<B |
<B |
|
<U |
>B<C (As, Cu, Pb, Zn) |
<B |
<B |
<B |
8.7 |
21.3 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB5 S1.8 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
10.5 |
24.3 |
TSB5 M2.5 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.8 |
19.4 |
TSB5 B3.4 |
<B |
<B |
<B |
|
<U |
>B<C (Pb) |
<B |
<B |
<B |
9.4 |
18.6 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB6 S0.6 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.1 |
17.1 |
TSB6 M2.2 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
8.7 |
13.5 |
TSB6 B3.3 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.2 |
14.6 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB7 S1.5 |
<B |
<B |
<B |
<B |
<U |
<B |
<B |
<B |
<B |
8.6 |
24.0 |
TSB7 M2.7 |
<B |
<B |
<B |
<B |
<U |
<B |
<B |
<B |
<B |
9.2 |
18.7 |
TSB7 B3.3 |
<B |
<B |
<B |
<B |
<U |
<B |
<B |
<B |
<B |
8.8 |
17.0 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB8 S1.1 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.7 |
13.6 |
TSB8 M2.6 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
8.5 |
13.6 |
TSB8 B3.1 |
<B |
<B |
>B<C (benzopyrene) |
|
<U |
<B |
<B |
<B |
<B |
8.9 |
13.8 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB9 S1.0 |
<B |
<B |
<B |
|
<U |
>B<C (Pb) |
<B |
<B |
<B |
9.7 |
17.0 |
TSB9 M2.4 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
8.3 |
17.7 |
TSB9 B3.3 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
10.8 |
14.7 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB10 S0.4 |
>B <C |
<B |
<B |
|
<U |
>C (Pb) >B<C (Cd, Cu, Zn) |
<B |
<B |
<B |
7.3 |
31.6 |
TSB10 M1.2 |
<B |
<B |
<B |
|
>U |
>C (As, Cd, Cu, Pb, Zn) |
<B |
<B |
<B |
8.3 |
35.2 |
TSB10 B1.8 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
10.5 |
29.6 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB10A M2.6 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
10.4 |
13.2 |
TSB10A B3.9 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.0 |
14.9 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB11 S0.5 |
<B |
<B |
<B |
|
>U |
>C (Pb) >B<C (Cd, Cu, Zn) |
<B |
<B |
<B |
11.0 |
21.3 |
TSB11 M2.4 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.0 |
18.4 |
TSB11 B3.8 |
<B |
<B |
<B |
|
<U |
>B<C (Pb) |
<B |
<B |
<B |
9.2 |
20.3 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB12 S0.5 |
<B |
<B |
<B |
|
<U |
>B<C (Cd, Cu, Pb, Zn) |
<B |
<B |
<B |
9.0 |
12.9 |
TSB12 M2.5 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.0 |
11.4 |
TSB12 B3.5 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
8.5 |
15.3 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB13 S0.5 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.1 |
7.8 |
TSB13 M1.5 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.5 |
15.9 |
TSB13 B3.0 |
<B |
<B |
<B |
|
<U |
>B<C (Pb, Zn, Hg) |
<B |
<B |
<B |
8.4 |
24.5 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB14 S0.4 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.6 |
10.3 |
TSB14 M2.5 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.3 |
12.0 |
TSB14 B3.5 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.3 |
18.8 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB15 S0.4 |
<B |
<B |
>B<C (benzopyrene) |
<B |
|
>C (Cu, Pb, Zn) >B<C (As, Hg) |
<B |
<B |
<B |
8.8 |
12.9 |
TSB15 M2.3 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.3 |
23.6 |
TSB15 B3.5 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.3 |
12.9 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB16 S0.8 |
<B |
<B |
<B |
|
|
>B<C (Cu, Pb, Zn) |
<B |
<B |
<B |
7.8 |
14.0 |
TSB16 M2.3 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
9.0 |
17.2 |
TSB16 B3.6 |
<B |
<B |
<B |
|
|
>B<C (Pb) |
<B |
<B |
<B |
8.4 |
20.3 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB17 S0.4 |
<B |
<B |
<B |
|
|
>B<C (Hg) |
<B |
<B |
<B |
10.4 |
15.3 |
TSB17 M2.3 |
<B |
<B |
<B |
|
|
>B<C (Pb) |
<B |
<B |
<B |
8.5 |
26.3 |
TSB17 B3.0 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
8.7 |
9.1 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB18 S1.0 |
<B |
<B |
<B |
<B |
|
>B<C (Pb) |
<B |
<B |
<B |
8.6 |
18.6 |
TSB18 M2.4 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
9.2 |
13.2 |
TSB18 B3.8 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
9.3 |
21.7 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB19 S0.6 |
<B |
<B |
<B |
|
|
>B<C (Pb) |
<B |
<B |
<B |
7.5 |
12.2 |
TSB19 M2.3 |
<B |
<B |
<B |
|
|
>B<C (Pb, Hg) |
<B |
<B |
<B |
7.6 |
21.6 |
TSB19 B3.5 |
<B |
<B |
<B |
|
|
>B<C (Hg) |
<B |
<B |
<B |
7.8 |
18.8 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB20 S0.3 |
<B |
<B |
>B<C (pyrene, benzopyrene) |
<B |
|
>C (Pb) >B<C (As, Cd, Cu, Zn, Hg) |
<B |
<B |
<B |
9.4 |
26.6 |
TSB20 M1.5 |
>C |
<B |
>C (pyrene, benzopyrene) >B<C (fluoranthene) |
<B |
|
>B<C (Cu) |
<B |
<B |
<B |
8.3 |
28.6 |
TSB20 B3.2 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.6 |
10.9 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB21 S0.5 |
<B |
<B |
<B |
|
|
>C (Cu, Pb, Zn) >B<C (Hg) |
<B |
<B |
<B |
8.8 |
14.8 |
TSB21 M2.4 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
8.6 |
8.1 |
TSB21 X3.5 |
>B<C |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
7.7 |
12.3 |
TSB21 B4.9 |
<B |
<B |
<B |
|
|
>B<C (Pb, Hg) |
<B |
<B |
<B |
8.5 |
12.9 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB22 S0.5 |
<B |
<B |
<B |
|
|
>B<C (Pb) |
<B |
<B |
<B |
9.1 |
14.4 |
TSB22 M1.8 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
8.6 |
11.1 |
TSB22 B2.9 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
8.9 |
15.3 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB23 S0.5 |
<B |
<B |
<B |
|
|
>B<C (Pb) |
<B |
<B |
<B |
8.2 |
9.5 |
TSB23 M1.9 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
10.9 |
10.3 |
TSB23 B3.4 |
<B |
<B |
<B |
|
|
>B<C (Pb) |
<B |
<B |
<B |
8.8 |
17.1 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB24 S1.2 |
<B |
<B |
<B |
<B |
<U |
>B<C (Pb, Hg) |
<B |
<B |
<B |
7.9 |
6.9 |
TSB24 M2.0 |
<B |
<B |
<B |
<B |
<U |
>B<C (Pb, Hg) |
<B |
<B |
<B |
7.9 |
15.9 |
TSB24 X3.0 |
<B |
<B |
<B |
<B |
<U |
>B<C (Pb) |
<B |
<B |
<B |
8.4 |
18.8 |
TSB24 B4.0 |
<B |
<B |
<B |
<B |
<U |
>B<C (Cu, Pb) |
<B |
<B |
<B |
8.4 |
17.7 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB25 S0.9 |
<B |
<B |
<B |
<B |
<U |
<B |
<B |
<B |
<B |
8.1 |
14.4 |
TSB25 M1.6 |
<B |
<B |
>B<C (benzopyrene) |
<B |
<U |
<B |
<B |
<B |
<B |
10.0 |
19.2 |
TSB25 X2.9 |
<B |
<B |
<B |
<B |
<U |
>B<C (Pb) |
<B |
<B |
<B |
8.1 |
13.8 |
TSB25 B3.9 |
<B |
<B |
<B |
<B |
<U |
>B<C (Pb, Hg) |
<B |
<B |
<B |
8.4 |
12.4 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB26 S0.8 |
>B<C |
<B |
<B |
|
|
>B<C (Pb) |
<B |
<B |
<B |
9.2 |
15.2 |
TSB26 M1.8 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
9.9 |
13.3 |
TSB26 X2.7 |
>C |
<B |
<B |
|
|
>B<C (Cu, Pb, Zn, Hg) |
<B |
<B |
<B |
9.0 |
12.7 |
TSB26 B3.4 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
8.6 |
12.3 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB27 S0.5 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
8.3 |
13.6 |
TSB27 M2.0 |
<B |
<B |
<B |
|
|
<B |
<B |
<B |
<B |
8.1 |
13.8 |
TSB27 B3.4 |
<B |
<B |
>B<C (benzopyrene) |
|
|
>C (Pb) >B<C (Cu) |
<B |
<B |
<B |
8.3 |
18.4 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB28 S0.4 |
<B |
<B |
<B |
|
<U |
>C (Pb) >B<C (Cd, Cu, Zn) |
<B |
<B |
<B |
9.5 |
18.3 |
TSB28 M2.1 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
9.6 |
16.8 |
TSB28 B3.6 |
<B |
<B |
<B |
|
<U |
>C (Pb, Cu) >B<C (As, Zn) |
<B |
<B |
<B |
10.7 |
16.9 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB29 S0.5 |
<B |
<B |
<B |
<B |
|
>B<C (Cu, Pb, Zn) |
<B |
<B |
<B |
8.0 |
21.2 |
TSB29 X1.0 |
<B |
<B |
<B |
<B |
|
<B |
<B |
<B |
<B |
8.1 |
12.1 |
TSB29 M1.3 |
<B |
<B |
<B |
<B |
|
>B<C (Cu, Zn, Hg) |
<B |
<B |
<B |
8.3 |
17.7 |
TSB29 X2.0 |
<B |
<B |
<B |
<B |
|
>C (Pb) >B<C (Zn) |
<B |
<B |
<B |
9.0 |
20.3 |
TSB29 B3.0 |
<B |
<B |
<B |
<B |
|
>C (Pb) |
<B |
<B |
<B |
9.2 |
22.6 |
|
|
|
|
|
|
|
|
|
|
|
|
TSB30 S0.6 |
<B |
<B |
<B |
|
<U |
>B<C (Pb) |
<B |
<B |
<B |
10.1 |
9.3 |
TSB30 M2.4 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
7.6 |
15.4 |
TSB30 B3.5 |
<B |
<B |
<B |
|
<U |
<B |
<B |
<B |
<B |
8.7 |
23.8 |
N.B. B and C refer to Dutch B and C criteria. U refers to USEPA criteria.
Table 4.2 Summary of Analytical Results – Groundwater Samples
Method |
USEPA 8015 |
USEPA 8260 |
USEPA 8270 |
EP066 |
USEPA 8290 |
USEPA 6020 |
EK026 |
EK071A |
EA002 |
Analysis Description |
TPH |
BTEX |
PAH |
PCB |
PCDD / PCDF |
METALS |
Total Cyanide |
Reactive Phosphorus as P |
pH Value @ 25'C |
Unit |
ug/l |
ug/l |
ug/l |
ug/l |
|
ug/l |
ug/l |
ug/l |
|
Dutch B |
200 |
30 |
10 |
0.2 |
|
50 |
50 |
200 |
|
TSB1 |
IS |
IS |
IS |
- |
- |
IS |
IS |
IS |
IS |
TSB2 |
IS |
IS |
IS |
IS |
- |
IS |
IS |
IS |
IS |
TSB3 |
>B<C |
<B |
>B<C (Phenanthrene) |
<B |
- |
<B |
<B |
<B |
8.2 |
TSB4 |
>C |
<B |
<B |
- |
IS |
IS |
IS |
IS |
IS |
TSB5 |
<B |
|
<B |
- |
<U |
>C (Cd,
Cu, Pb, Zn) |
<B |
IS |
IS |
TSB6 |
IS |
<B |
IS |
- |
IS |
IS |
IS |
IS |
IS |
TSB7 |
IS |
IS |
IS |
- |
IS |
IS |
IS |
IS |
IS |
TSB8 |
IS |
IS |
IS |
- |
<U |
IS |
IS |
IS |
IS |
TSB9 |
IS |
<B |
IS |
- |
<U |
IS |
<B |
IS |
IS |
TSB10 |
IS |
IS |
IS |
- |
<U |
IS |
IS |
IS |
IS |
TSB10A |
IS |
IS |
IS |
- |
<U |
IS |
IS |
IS |
IS |
TSB11 |
IS |
IS |
IS |
- |
<U |
IS |
IS |
IS |
IS |
TSB12 |
IS |
IS |
IS |
- |
IS |
IS |
IS |
IS |
IS |
TSB13 |
<B |
<B |
<B |
- |
<U |
>C(Cd)
>B(Cu,Pb) |
<B |
<B |
7.8 |
TSB14 |
IS |
IS |
IS |
IS |
- |
IS |
IS |
IS |
IS |
TSB15 |
>C |
<B |
>B (various) |
>B<C |
- |
<B |
<B |
<B |
9.8 |
TSB16 |
>B<C |
<B |
<B |
- |
<U |
>B (As) |
<B |
<B |
7.3 |
TSB17 |
>B<C |
<B |
<B |
- |
- |
>C
(Cu, Pb, Zn) |
<B |
<B |
7.2 |
TSB18 |
>B<C |
<B |
<B |
<B |
- |
>C (Cd,
Cu, Pb, Zn) |
<B |
<B |
7.5 |
TSB19 |
>B<C |
<B |
<B |
- |
- |
>C (Cu,
Pb, Zn) |
<B |
<B |
7.3 |
TSB20 |
<B |
<B |
>C |
<B |
- |
<B |
<B |
<B |
7.5 |
TSB21 |
>C |
IS |
>B<C (Pyrene) |
- |
- |
>C (Cd,
Cu, Pb, Zn) |
<B |
<B |
10.7 |
TSB22 |
>C |
<B |
>B<C (Fluoranthene,
Pyrene) |
- |
- |
IS |
IS |
IS |
IS |
TSB23 |
IS |
IS |
IS |
- |
- |
IS |
IS |
IS |
IS |
TSB24 |
IS |
IS |
IS |
IS |
IS |
IS |
IS |
IS |
IS |
TSB25 |
>B<C |
<B |
<B |
<B |
<U |
<B |
<B |
>B |
7.2 |
TSB26 |
IS |
IS |
IS |
- |
- |
IS |
IS |
IS |
IS |
TSB27 |
IS |
IS |
IS |
- |
- |
IS |
IS |
IS |
IS |
TSB28 |
IS |
<B |
IS |
- |
<U |
>C (Cd,
Cu, Pb, Zn) |
<B |
<B |
8.6 |
TSB29 |
<B |
<B |
<B |
- |
- |
<B |
<B |
<B |
7.6 |
TSB30 |
IS |
<B |
>B<C (Fluoranthene, Pyrene, Benzopyrene) |
- |
<U |
>C (Cd ),>B (Zn) |
<B |
<B |
7.6 |
Table 4.3 Actions Required Post Demolition
Action
Required |
Remove
concrete surface and clear uncontaminated surface material and stockpile |
Proposed
depth of Material for Removal or Treatment |
Remedial
Action |
Estimate
quantity of contaminated material for Treatment (m3, #) |
Sampling
Strategy |
||
TB1 |
Yes |
Concrete down to
0.3m depth |
Immediately below
concrete 0.3m to 4.0m |
Immobilisation
for 0.3m to 2.0m and 3.0m to 4.0m* TCLP test
followed by removal of 2.0m to 3.0m to landfill. Immobilisation if TCLP tests exceed
criteria **. |
100 to be removed to landfill + 270 @ |
Yes, determine
extent of HM (Cd, Cu, Pb, Zn and Hg) and TPH contamination at edge and base
of excavated hole.* |
5 samples 5m N,
S, E ,W and base of borehole. |
TB2 |
Yes |
Concrete down to
0.5m depth |
Immediately
below concrete 0.5m to 1.5m |
Immobilisation* |
100 |
Yes, determine
extent of HM (As, Cu, Pb and Zn) contamination at edge and base of excavated
hole.* |
5 samples 5m N,
S, E ,W and base of borehole. |
TB3 |
Yes |
Concrete down to
2.5m depth |
2.5m to 3.5m |
Immobilisation * |
100 |
Yes, determine extent
of HM (Cu, Pb, Zn and Hg) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB4 |
Yes |
Down to 2.2m
depth |
2.2m to 4.2m |
Immobilisation * |
200 |
Yes, determine extent
of HM (As, Cu, Pb and Zn) contamination at edge and base of excavated hole.* |
4 samples 5 m N,
S, E & W of borehole plus one at base of hole layer |
TB5 |
Yes |
Concrete down to
1.8m. Down to 2.5m depth |
2.5m to 4.0m |
Immobilisation* |
200 |
Yes, determine
extent of HM (Pb) contamination at edge and base of excavated hole.* |
4 samples 5 m N,
S, E & W of borehole plus one at base of hole layer |
TB6 |
No |
N/A |
N/A |
N/A |
0 |
N/A |
N/A |
TB7 |
No |
N/A |
N/A |
N/A |
0 |
N/A |
N/A |
TB8 |
Yes |
Concrete down to 1m. Down to 2.5m |
2.5m to 3.5m |
TCLP test followed by removal of 2.5m to 3.5m to
landfill. Immobilisation if TCLP tests
exceed criteria **. |
100 to be removed to landfill @ |
Yes, determine extent
of PAH contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E ,W and base of borehole. |
TB9 |
Yes |
Concrete down to
1.0m depth |
1.0m to 2.0m |
Immobilisation* |
100 |
Yes, determine extent
of HM (Pb) contamination at edge and base of excavated hole.* |
4 samples 5m N,
S, E & W and base of borehole. |
TB10 |
Yes |
Surface
rubble/ash and brick material (not soil) about 1.5m depth. |
1.5 m |
Clear Waste to landfill. Waste to be treated and tested to meet EPD
disposal criteria. |
Up to, say, 300m3 (surface material, not for
in-situ treatment) @ |
Yes, determine
extent of HM (As, Cd, Cu, Pb, Zn) TPH and PCDD/PCDF contamination under
surface contaminated materials.* |
4 samples 5 m N,
S, E & W of borehole plus one at bore hole |
TB10a |
No |
N/A |
N/A |
N/A |
0 |
N/A |
N/A |
TB11 |
Yes |
Down to 1.5m
depth |
1.5 m |
Clear Waste to landfill. Waste to be treated and tested to meet EPD
disposal criteria. |
(See TB10, for materials not for in-situ
treatment) |
Yes, determine
extent of HM (Cd, Cu, Pb, and Zn) and PCDD/PCDF contamination under surface
contaminated materials.* |
5 samples 5m N,
S, E & W of borehole plus one at borehole |
TB11 |
Yes |
Below hardstanding
surface (soil materials) |
1.5 to 4.0m |
Immobilisation*
|
200 (for in-situ treatment) |
Yes, to
determine extent of HM (Pb) contamination at edge and base of excavated hole. |
5 samples 5m N,
S, E & W of borehole plus one at base of hole layer |
TB12 |
Yes |
Concrete down to
0.5m |
0.5 to 1.5m |
Immobilisation* |
100 |
Yes, determine
extent of HM (Cd, Cu, Pb and Zn) contamination at edge and base of excavated
hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB13 |
Yes |
Down to 2.5m |
2.5m to 3.5m |
Immobilisation* |
100 |
Yes, determine
extent of HM (Pb, Zn, Hg) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB14 |
No |
N/A |
N/A |
N/A |
0 |
N/A |
N/A |
TB15 |
Yes |
Concrete down to
0.4m |
0.4 to 2.4m |
TCLP test
followed by removal of 0.4m to 2.4m to landfill. Immobilisation if TCLP tests exceed
criteria **. |
200 to be removed to landfill @ |
Yes, determine
extent of HM (As, Cu, Pb, Hg and Zn) and PAH contamination at edge and base
of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB16 |
Yes |
Concrete down to
0.8m |
0.8 to 4.3m |
Immobilisation * |
350 |
Yes, determine
extent of HM (Cu, Pb and Zn) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB17 |
Yes |
Concrete down to
0.4m |
0.4 to 2.4m |
Immobilisation * |
200 |
Yes, determine
extent of HM (Pb and Hg) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB18 |
Yes |
Concrete down to
1.0m |
1.0m to 2.0m |
Immobilisation * |
100 |
Yes, determine
extent of HM (Pb) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB19 |
Yes |
Concrete down to
0.6m |
0.6m to 4.0m |
Immobilisation * |
375 |
Yes, determine
extent of HM (Pb and Hg) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB20 |
Yes |
Concrete down to
0.3m |
0.3m to 2.3m |
TCLP test
followed by removal of 0.3m to 2.3m to landfill. Immobilisation if TCLP tests exceed
criteria **. |
200 to be removed to landfill @ |
Yes, determine
extent of HM (As, Cu, Pb, Hg, Cd and Zn) PAH and TPH contamination at edge
and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB21 |
Yes |
Concrete down to
0.5m |
0.5m to 5.0m |
TCLP test
followed by removal of 0.5m to 3.5m to landfill. Immobilisation if TCLP tests exceed
criteria **. Remaining depth to be immobilised to 5m * |
300 to be removed to landfill + 150 @ |
Yes, determine
extent of HM (Cu, Pb, Hg and Zn) and TPH contamination at edge and base of
excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB22 |
Yes |
Concrete down to
0.5m |
0.5 to 1.5m |
Immobilisation *
|
100 |
Yes, determine
extent of HM (Pb) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB23 |
Yes |
Concrete down to
0.5m |
0.5 to 4m |
Immobilisation* |
350 |
Yes, determine
extent of HM (Pb) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB24 |
Yes |
Concrete down to
1.2m |
1.2 to 4.2m |
Immobilisation* |
300 |
Yes, determine extent
of HM (Cu, Pb and Hg) contamination at
edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB25 |
Yes |
Concrete down to
0.9m. Down to 1.0m |
Depth 1.0m – 4.4m |
TCLP test followed
by removal of 1.0m to 2.9m to landfill.
Immobilisation if TCLP tests exceed criteria **. Immobilisation
for remaining 2.9m to 4.4m* |
100 to be removed to landfill + 240 @ |
Yes, to determine
extent of HM (Pb, Hg) and PAH contamination at edge and base of excavated
hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB26 |
Yes |
Concrete down to
0.8m |
Depth 0.8m – 3.0m |
TCLP test followed
by removal of 0.8m to 3.0m to landfill.
Immobilisation if TCLP tests exceed criteria **. |
220 to be removed to landfill.@ |
Yes, to
determine extent of HM (Pb, Cu, Zn, Hg) and TPH contamination.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB27 |
Yes |
Concrete down to
0.5m and clean soil down to 2.0m |
2.0 to 4.0m |
TCLP test followed by removal of 2.0m to 4.0m to
landfill. Immobilisation if TCLP tests
exceed criteria **. |
200 |
Yes, determine extent
of HM (Cu and Pb) and PAH contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB28 |
Yes |
Concrete down to
0.4m |
0.4 to 4.4m |
Immobilisation* |
400 |
Yes, determine extent
of HM (As, Cd, Cu, Pb, and Zn) contamination at edge and base of excavated
hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB29 |
Yes |
Concrete down to
0.5m |
0.5 to 3.5m |
Immobilisation* |
300 |
Yes, determine extent
of HM (Cu, Pb, Hg and Zn) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
TB30 |
Yes |
Concrete down to
0.6m |
0.6 to 1.6m |
Immobilisation* |
100 |
Yes, determine extent
of HM (Pb) contamination at edge and base of excavated hole.* |
5 samples 5m N,
S, E & W and base of borehole. |
Refuse Bunkers |
Yes |
N/A |
N/A |
Landfill
disposal * |
To be determined
after inspection of bunkers |
Examine bunker refuse
prior to demolition. |
Consider
analysis depending on bunker contents. |
* If contamination confirmed by
reassurance sampling extract a further 1m into the soil, immobilise and
resample.
** TCLP test for all metals identified
in Table E1 in EPD Contaminated Sites Investigation and Remediation Guidance
Notes
# Broad brush estimate based on
depths to which materials >Dutch B are identified by current round of sampling
and all material within 5m (10m x 10m square hole) to that depth (rounded up to
nearest 10m3. (Total 6055 m3.
requiring confirmation). According
to the quantity of contaminated material estimated for each borehole location,
the total quantity of contaminated soil should be about 6055m3 .
About 4635m3. of the total volume is estimated to require
treatment on site by immobilisation.
@ Broad brush estimate of materials
to be transferred to landfill rounded up to nearest 10m3 about 1,420m3, requiring
confirmation).
Control of Surface Water
Demolition Site Run-off and Surface Water Drainage
· The use of sediment traps, where appropriate; and
· The adequate maintenance of drainage systems to prevent flooding and overflow.
Site Run-off during Soil Remediation
General Demolition Activities
Sewage Effluent
· All the recommended mitigation measures including appropriate drainage and silty run-off collection facilities are incorporated in accordance with the recommendations of ProPEC PN 1/94;
· All temporary drainage diversions will be reinstated to the original condition after the demolition works are completed and implemented properly, in accordance with the recommendations of ProPECC PN 1/94; and
· All demolition works area discharges shall comply with the TM standards of the WPCO. Any practical options for the diversion and re-alignment of drainage should comply with both engineering and environmental requirements. It is considered that controls on discharges from land based demolition activities and proper site management procedures, as referenced above, will minimise residual water quality impacts to the acceptable levels stipulated in the WPCO criteria.
Table 5.1 Noise Standards for Daytime Construction Work
Land Use |
0700 to 1900 hours on any day not being a
Sunday or general holiday |
· All domestic premises including temporary housing accommodation |
75 |
· Hotels and hostels |
75 |
· Educational institutions including kindergartens, nurseries and all others where voice communication is required |
70 65 (During examinations) |
Notes: The above standards apply to uses which rely on opened windows for ventilation.
The above standards shall be viewed as the maximum permissible noise levels assessed at 1 m from the external façade.
·
·
The
·
The new Housing
Society development (Cayman Rise) at
·
Residential
buildings at
·
· Government, Institutional and Community uses at St Lukes Church School, St Lukes Settlement, Jockey Club Clinic, Victoria Mortuary and the Bayanihan Centre.
Table 5.2 Representative Noise Sensitive Receivers
NSR |
Building |
Horizontal Distance from notional noise source (m) |
Use |
KT-N1 |
|
75 |
25-storey high residential block |
KT-N2 |
Sai Wan New Mansion |
75 |
12-storey high residential block |
KT-N3 |
|
75 |
27-storey high residential block above 4-storey high podium |
KT-N4 |
Cayman
Rise |
75 |
31-storey
high residential block above 5-storey high podium |
KT-N5 |
|
100 |
Philippine overseas worker training school |
KT-N6 |
Jockey Club Clinic |
75 |
3-storey high building |
KT-N7 |
St. Luke's |
100 |
6-storey high school |
Table 5.3 Estimated Distances from Chimneys
NSR |
Building |
Horizontal Distance from Chimney A (m) |
Horizontal Distance from Chimney B (m) |
Horizontal Distance from Chimney C (m) |
KT-N1 |
|
300 |
250 |
150 |
KT-N2 |
Sai Wan New Mansion |
288 |
238 |
138 |
KT-N3 |
|
250 |
200 |
138 |
KT-N4 |
Cayman
Rise |
163 |
138 |
163 |
KT-N5 |
|
113 |
138 |
250 |
KT-N6 |
Jockey Club Clinic |
113 |
100 |
175 |
KT-N7 |
St. Luke's |
150 |
138 |
200 |
· Sound Power Level - The sound power level of each item of Powered Mechanical Equipment (PME) as listed in the Technical Memorandum.
· Distance Attenuation - All items of PME have been considered to be grouped at the notional source position, which is a point mid-way between the approximate geographical centre of the construction Site and its boundary nearest to the NSR. The distance between the NSR and the notional source position attenuates the noise level. The corresponding correction factors are set out in the Technical Memorandum. However, for the demolition of chimneys, all items of PME was assumed at the location of the nearest chimney to the concerned NSR.
· Barrier Effect - According to the Technical Memorandum, a negative correction of 5 dB(A) or 10 dB(A) can be applied to the predicted noise levels depending on the situation stipulated in the TMCW.
· Façade Correction - A positive correction of 3dB(A) has been applied to consider the effect of reflection from facades.
Table 5.4 Base Suite of Demolition/Construction Plant
Construction
Plant |
CNP No. |
SWL, dB(A) |
Quantity |
||
Months 1-2 |
Months 3-4 |
Months 5-9 |
|||
Generator, silenced |
CNP102 |
100 |
2 |
2 |
2 |
Air Compressor |
CNP003 |
104 |
1 |
3 |
3 |
Crawler Mounted Hydraulic Breaker |
CNP028 |
122 |
1 |
4 |
4 |
Excavator/Backhoe |
CNP081 |
112 |
1 |
3 |
3 |
Crawler/Mobile Crane |
CNP048 |
112 |
1 |
4 |
4 |
Lorry/Dump Truck |
CNP067 |
117 |
2 |
5 |
10 |
Pneumatic Breaker |
CNP026 |
114 |
1 |
5 |
5 |
Chain Saw |
CNP203 |
115 |
1 |
3 |
3 |
Cutter |
CNP021 |
90 |
1 |
2 |
2 |
Water Pump |
CNP281 |
88 |
8 |
8 |
8 |
Crane Shaft and Derrick* |
CNP049 |
95 |
1 |
3 |
3 |
Total SWL per month dB(A) |
125 |
131 |
132 |
* to lift large sections of
cladding or reinforced concrete to ground level.
Table 5.5 Base Suite of Soil Remediation Construction Plant
Construction Plant |
CNP No. |
SWL, dB(A) |
Quantity |
||
Months 10-11 |
Months 12-15 |
Months 16-17 |
|||
Generator, silenced |
CNP102 |
100 |
2 |
2 |
2 |
Air Compressor |
CNP003 |
104 |
2 |
2 |
2 |
Excavator/Backhoe |
CNP081 |
112 |
2 |
2 |
2 |
Lorry/Dump Truck |
CNP067 |
117 |
2 |
3 |
3 |
Pneumatic Breaker |
CNP026 |
114 |
2 |
2 |
2 |
Water Pump |
CNP281 |
88 |
4 |
4 |
4 |
Ballast Tamper |
CNP029 |
105 |
1 |
1 |
1 |
Concrete Mixer |
CNP045/046 |
96 |
2 |
2 |
2 |
Vibratory Compactor |
CNP050 |
105 |
2 |
2 |
2 |
Total SWL, dB(A) per month
|
123 |
124 |
124 |
Table 5.6 Predicted Unmitigated Noise Levels from Demolition
NSR |
Period |
SWL, dB(A) |
DA, dB(A) |
FC, Db(A) |
PNL, dB(A) |
KT-N1 |
Months 1-2 |
125 |
-46 |
3 |
82 |
Months 3-4 |
131 |
-46 |
3 |
88 |
|
Months 5-9 |
132 |
-46 |
3 |
89 |
|
KT-N2 |
Months 1-2 |
125 |
-46 |
3 |
82 |
Months 3-4 |
131 |
-46 |
3 |
88 |
|
Months 5-9 |
132 |
-46 |
3 |
89 |
|
KT-N3 |
Months 1-2 |
125 |
-46 |
3 |
82 |
Months 3-4 |
131 |
-46 |
3 |
88 |
|
Months 5-9 |
132 |
-46 |
3 |
89 |
|
KT-N4 |
Months 1-2 |
125 |
-46 |
3 |
82 |
Months 3-4 |
131 |
-46 |
3 |
88 |
|
Months 5-9 |
132 |
-46 |
3 |
89 |
|
KT-N5 |
Months 1-2 |
125 |
-48 |
3 |
80 |
Months 3-4 |
131 |
-48 |
3 |
86 |
|
Months 5-9 |
132 |
-48 |
3 |
87 |
|
KT-N6 * |
Months 1-2 |
125 |
-46 |
3 |
82 |
Months 3-4 |
131 |
-46 |
3 |
88 |
|
Months 5-9 |
132 |
-46 |
3 |
89 |
|
KT-N7 |
Months 1-2 |
125 |
-48 |
3 |
80 |
Months 3-4 |
131 |
-48 |
3 |
86 |
|
Months 5-9 |
132 |
-48 |
3 |
87 |
Note: SWL denotes sound power level
DA denotes
distance attenuation and distance referred to Table 5.2
FC denotes
façade correction
PNL denotes
predicted noise level
* The Jockey Club Clinic (KT-N6) is provided
with window insulation and air-conditioning and does not rely on operable
windows for ventilation. Predicted Noise
Levels at this locations are for indication only.
Table 5.7 Predicted Unmitigated Noise Levels from Ground Remediation
NSR |
Period |
Total SWL, dB(A) |
DA, dB(A) |
FC, dB(A) |
PNL, dB(A) |
KT-N1 |
Months 10-11 |
123 |
-46 |
3 |
80 |
|
Months 12-15 |
124 |
-46 |
3 |
81 |
|
Months 16-17 |
124 |
-46 |
3 |
81 |
KT-N2 |
Months 10-11 |
123 |
-46 |
3 |
80 |
Sai Wan New Mansion |
Months 12-15 |
124 |
-46 |
3 |
81 |
|
Months 16-17 |
124 |
-46 |
3 |
81 |
KT-N3 |
Months 10-11 |
123 |
-46 |
3 |
80 |
|
Months 12-15 |
124 |
-46 |
3 |
81 |
|
Months 16-17 |
124 |
-46 |
3 |
81 |
KT-N4 |
Months 10-11 |
123 |
-46 |
3 |
80 |
Cayman Rise |
Months 12-15 |
124 |
-46 |
3 |
81 |
|
Months 16-17 |
124 |
-46 |
3 |
81 |
KT-N5 |
Months 10-11 |
123 |
-48 |
3 |
78 |
|
Months 12-15 |
124 |
-48 |
3 |
79 |
|
Months 16-17 |
124 |
-48 |
3 |
79 |
KT-N6 |
Months 10-11 |
123 |
-46 |
3 |
80 |
Jockey Club Clinic |
Months 12-15 |
124 |
-46 |
3 |
81 |
|
Months 16-17 |
124 |
-46 |
3 |
81 |
KT-N7 |
Months 10-11 |
123 |
-48 |
3 |
78 |
St. Luke's |
Months 12-15 |
124 |
-48 |
3 |
79 |
|
Months 16-17 |
124 |
-48 |
3 |
79 |
Note : SWL denotes
sound power level
DA denotes distance attenuation
FC denotes façade correction
PNL denotes predicted noise level
* The Jockey Club Clinic (KT-N6) is
provided with window insulation and air-conditioning and do not rely on
operable windows for ventilation.
Predicted Noise Levels at these locations are for indication only.
· Silenced and super silenced type equipment;
· Reduction in number of plant operating simultaneously;
· Movable barriers as noise shields;
· Use of modified site hoarding to a perimeter noise barrier as a noise shield; and
· Re-scheduling and restricting hours of operation of noisy tasks.
Table 5.8 Revised Suite of Demolition and Ground Remediation Plant
Construction Plant |
CNP No. / BS5228 Ref. No. |
SWL, dB(A) |
Quantity |
Demolition of Buildings other
than Chimneys |
|||
Crawler Mounted Hydraulic Breaker |
Table
C8/13 |
110 |
2 |
Excavator/Backhoe |
Table
C3/97 |
105 |
2 |
Lorry/Dump Truck |
Table
C9/27 |
105 |
2 |
Water Pump |
CNP281 |
88 |
4 |
Total SWL, dB(A)
for demolition of Buildings other than Chimneys |
115 dB(A) |
||
|
|||
Demolition of Chimneys Only |
|||
Pneumatic Breaker |
Table
C2/10 |
110 |
3 |
Cutter |
CNP021 |
90 |
3 |
Air Compressor |
CNP003 |
104 |
3 |
Generator, silenced |
CNP102 |
100 |
3 |
Excavator/Backhoe |
Table
C3/97 |
105 |
3 |
Lorry/Dump Truck |
Table
C9/27 |
105 |
4 |
Water Pump |
CNP281 |
88 |
3 |
Mobile Crane |
Table
C7/114 |
101 |
1 |
Total SWL, dB(A)
for demolition of Chimneys Only[1] |
118 dB(A) |
||
|
|||
Ground Remediation |
|||
Generator, silenced |
CNP102 |
100 |
2 |
Air Compressor |
CNP003 |
104 |
1 |
Excavator/Backhoe |
Table
C3/97 |
105 |
1 |
Lorry/Dump Truck |
Table
C9/27 |
105 |
2 |
Pneumatic Breaker |
Table
C2/10 |
110 |
1 |
Water Pump |
CNP281 |
88 |
4 |
Ballast Tamper |
CNP029 |
105 |
1 |
Concrete Mixer |
CNP045/046 |
96 |
2 |
Vibratory Compactor |
CNP050 |
105 |
2 |
Total SWL, dB(A)
for Ground Remediation |
115 dB(A) |
Note : [1] The
quantity of equipment was assumed for demolition
of three chimneys simultaneously.
Table 5.9 Predicted Mitigated Noise Levels from Demolition of Buildings other than Chimneys
NSR |
SWL, dB(A) |
DA, dB(A) |
FC, dB(A) |
PNL, dB(A) |
KT-N1 |
115 |
-46 |
3 |
72 |
KT-N2 |
115 |
-46 |
3 |
72 |
KT-N3 |
115 |
-46 |
3 |
72 |
KT-N4 |
115 |
-46 |
3 |
72 |
KT-N5 |
115 |
-48 |
3 |
70 |
KT-N6 * |
115 |
-46 |
3 |
72 |
KT-N7 |
115 |
-48 |
3 |
70 |
Note: SW denotes sound power level
DA denotes distance attenuation and distance referred to Table 5.2
FC denotes façade correction
PN denotes predicted noise level
* The Jockey Club Clinic (KT-N6) is provided with window insulation and air-conditioning and does not rely on operable windows for ventilation. Predicted Noise Levels at these locations are for indication only.
Table 5.10 Predicted Mitigated Noise Levels from Demolition of Chimneys Only
NSR |
SWL, dB(A) |
DA, dB(A) |
FC, dB(A) |
PNL, dB(A) |
KT-N1 |
118 |
-52 |
3 |
69 |
KT-N2 |
118 |
-51 |
3 |
70 |
KT-N3 |
118 |
-51 |
3 |
70 |
KT-N4 |
118 |
-51 |
3 |
70 |
KT-N5 |
118 |
-49 |
3 |
72 |
KT-N6 * |
118 |
-48 |
3 |
73 |
KT-N7 |
118 |
-51 |
3 |
70 |
Note: SW denotes sound power level
DA denotes distance attenuation and distance referred to the shortest distance in Table 5.3
FC denotes façade correction
PN denotes predicted noise level
* The Jockey Club Clinic (KT-N6) is provided with window insulation and air-conditioning and does not rely on operable windows for ventilation. Predicted Noise Levels at these locations are for indication only.
Table 5.11 Predicted Mitigated Noise Levels (Ground Remediation)
NSR |
SWL, dB(A) |
DA, dB(A) |
FC, dB(A) |
PNL, dB(A) |
KT-N1 |
115 |
-46 |
3 |
72 |
KT-N2 |
115 |
-46 |
3 |
72 |
KT-N3 |
115 |
-46 |
3 |
72 |
KT-N4 |
115 |
-46 |
3 |
72 |
KT-N5 |
115 |
-48 |
3 |
70 |
KT-N6 * |
115 |
-46 |
3 |
72 |
KT-N7 |
115 |
-48 |
3 |
70 |
Note: SW denotes sound power level
DA denotes distance attenuation and distance referred to Table 5.2
FC denotes façade correction
PN denotes predicted noise level
* The Jockey Club Clinic (KT-N6) is provided with window insulation
and air-conditioning and does not rely on operable windows for
ventilation. Predicted Noise Levels at
this locations is for indication only.
Conclusions
Table 6.1 Representative Air Sensitive Receivers
ASR |
Building |
Horizontal Distance from nearest dust source (m) |
Use |
KT-A1 |
|
25 |
25-storey high residential block |
KT-A2 |
Sai Wan New Mansion |
25 |
12-storey high residential block |
KT-A3 |
|
25 |
27-storey high residential block above 4-storey high podium |
KT-A4 |
Cayman Rise |
40 |
High-rise residential block |
KT-A5 |
|
50 |
Philippine overseas worker training school |
KT-A6 |
Jockey Club Clinic |
15 |
3-storey high building |
KT-A7 |
|
50 |
6-storey high school |
N.B. Notional dust source is the nearest site boundary
Table 6.2
Pollutant |
Averaging Time |
|||
|
1 Hour (b) |
8 Hour (c) |
24 Hour (c) |
1 Year (d) |
Total Suspended Particulates (TSP) |
(500) (f) |
- |
260 |
80 |
Respirable Suspended Particulates (e) (RSP) |
- |
- |
180 |
55 |
Nitrogen Dioxide (NO2) |
300 |
- |
150 |
80 |
|
800 |
- |
350 |
80 |
Carbon Monoxide (CO) |
30,000 |
10,000 |
- |
- |
Note: a) Measured at 298K (25oC) and 101.325 kPa (one atmosphere). b) Not to be exceeded more than three times per year. c) Not to be exceeded more than once per year. d) Arithmetic means. e) Respirable suspended particulates are defined as particles suspended in the air with a nominal aerodynamic diameter of 10 mm and smaller. f) Technical Memorandum of Environmental Impact Assessment Process (TMEIA) stipulates a maximum TSP level of 500 mg m-3 (1-hour averaging time). |
· Adoption of good site practices;
· Avoid practices likely to raise dust level;
· Frequent cleaning and damping down of stockpiles and dusty areas of the Site;
· Reducing drop height during material handling or wall felling;
· Imposing a vehicle speed restriction of 15 km/hr within the Site;
· Provision of wheel washes facilities for Site vehicles leaving the Site;
· Regular plant maintenance to minimise exhaust emission; and
· Sweep up dust and debris at the end of each shift.
Assessment Criteria
· Waste Disposal Ordinance (Cap 354);
· Waste Disposal (Chemical Waste) (General) Regulation (Cap 354);
· Dumping at Sea Ordinance (Cap 466);
· Land (Miscellaneous Provisions) Ordinance (Cap 28); and
· Public Health and Municipal Services Ordinance (Cap 132) –Public Cleansing and Prevention of Nuisances Regulation.
· Waste Disposal Plan for Hong Kong Planning, Environment and Lands Branch, December 1989;
·
· New Disposal Arrangements for Construction Waste, Environmental Protection Department & Civil Engineering Department, 1992;
· Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, Environmental Protection Department 1992;
· A Guide to the Control on Import and Export of Waste, Environmental Protection Department, 1996; and
· Code of Practice on the Handling, Transportation and Disposal of Asbestos Waste, Environmental Protection Department, 1993.
· Works Bureau Technical Circular No. 5/98, On Site Sorting of Construction Waste on Demolition Sites;
· Works Bureau Technical Circular No. 5/99, Trip-ticket System for Disposal of Construction and Demolition Material;
· Works Bureau Technical Circular No. 19/99, Metallic Site Hoardings and Signboards; and
· Works Bureau Technical Circular No. 25/99, Incorporation of Information on Construction and Demolition Material Management in Public Works Subcommittee Papers.
· Works Bureau Technical Circular No. 29/2000 – Waste Management Plan
· Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards and Car Repair/Dismantling Workshops (EPD/TR1/99)
Assessment Methodology
· The type of waste generated;
· The amount of the principal waste types generated; and
· The proposed reuse, recycling, storage, transport, treatment and disposal methods, and the impacts of these methods.
Potential Sources of Impact
General
·
Construction and
Demolition (C&D) Demolition materials;waste
· Chemical waste; and
· General refuse.
C&D Demolition MaterialsWaste
· bricks / masonry*;
· mortar*;
· concrete*;
· dirt / soil / mud*;
· reinforced concrete*;
· asphalt (roads, parking lots)*;
· mastic (roofs / screeding)
· plaster (drywalls) *;
· ceramic / ceiling tiles*;
· steel (girders, steel mesh, reinforcement bar, joists, trusses, window frames, railings, banisters);
· other metal (e.g. aluminium frame);
· sheet plastics (e.g. protective covers);
· other plastics (e.g. pipes, stair handles, scaffolding ties);
· glass (e.g. window, doors);
· wood (e.g. door frame, doors, office partitioning);
· trimmings from bamboo scaffolding;
· wiring;
· white goods (appliances);
· fixtures (various material types);
· fibre (from insulation); and
· contaminants (e.g. lead based paints).
Table 7.1 KTCDA Principal Demolition Products
Buildings |
Concrete Volume (m3) |
Weight of Rebar (kg) |
Refrigeration Block |
2,800 |
50,000 |
Slaughterhouse Block |
4,000 |
72,000 |
Lairage Block |
10,000 |
177,000 |
Incineration Plant |
1,200 |
16,000 |
Chimneys |
1,000 |
13,000 |
Total |
19,000 |
328,000 |
Chemical Waste
General Refuse
Prediction and Evaluation of Impacts
General
C&D MaterialsDemolition
Waste
Chemical Waste
· Toxic effects to workers;
· Adverse effects on air, water and land from spills;
· Fire hazards; and
· Disruption to sewage treatment works where waste enters the sewage system through damage to the sewage biological treatment systems.
General Refuse
Table 7.2 Summary of Waste Management Impacts
Waste Type |
General Evaluation |
|
The total quantities of |
Chemical Waste |
A small volume of chemical waste, including up to 1,000m3 of asbestos containing roofing materials and louvres, will be produced. Temporary storage on site, handling, transport and disposal must be in accordance with the Code of Practice on the Handling, Transportation and disposal of Asbestos Waste. Provided that this occurs, and chemical wastes are disposed of at a licensed facility, and there will be little environmental impact. |
General Refuse |
If good practice is adhered to and all feasible avoidance, reuse and recycling opportunities are taken, including minimising over ordering, there should be minimal impact. |
Introduction
Waste Management Hierarchy
· Avoidance and minimisation by not generating waste through changing or improving practices and design;
· Reusing materials and therefore avoiding disposal (generally with only limited reprocessing);
· Recovery and recycling, avoiding disposal (although reprocessing may be required); and
· Treatment and disposal, according to relevant laws, guidelines and good practice.
C&D MaterialsDemolition Waste
Chemical Waste
· Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;
· Have a capacity of less than 450 l unless the specifications have been approved by the EPD; and
· Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.
· Be clearly labelled and used solely for the storage of chemical waste;
· Be enclosed on at least 3 sides;
· Have an impermeable floor and bunding, of capacity to accommodate 100% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;
· Have adequate ventilation;
· Be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and
· Be arranged so that incompatible materials are adequately separated.
· Be via a licensed waste collector; and
· Be to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility which also offers a chemical waste collection service and can supply the necessary storage containers; or
· Be to a recycling or reprocessing facility licensed by EPD.
General Refuse
· Wastes should be handled and stored in a manner which ensures that they are held securely without loss or leakage thereby minimising the potential for pollution;
· Only reputable waste collectors authorised to collect the specific category of waste concerned should be employed;
· Appropriate measures should be employed to minimise windblown litter and dust during transportation by either covering trucks or transporting wastes in enclosed containers;
· The necessary waste disposal permits should be obtained from the appropriate authorities, if they are required, in accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation (Cap 354) and the Government Land Ordinance (Cap 28);
· Collection of general refuse should be carried out frequently, preferably daily;
· Waste should only be disposed of at licensed sites and site staff and the civil engineering Contractor should develop procedures to ensure that illegal disposal of wastes does not occur;
· Waste storage areas should be well maintained and cleaned regularly; and
· Records should be maintained of the quantities of wastes generated, recycled and disposed, determined by weighing each load.
· reference to statutory waste management requirements and obligations;
· reference to waste management requirements as determined under the EIA and Environmental Permit;
· clarification of responsibilities within the environmental management structure;
· clarification of the types, quantities, disposal methods and likely timing of waste arising;
· provisions for sorting facilities on site to facilitate sorting of C&D material;
· proposals for recycling, reuse and return of C&D material;
· details of waste handling procedures;
· details of waste transportation procedures;
· details of waste disposal procedures; and
· details of auditing and other checking requirements.
EM&A Requirements
· To monitor the performance of the project and to provide an early indication if any of the environmental mitigation measures, identified in this report and/or implemented by the Contractor, fail to meet the established standards and guidelines;
· To take remedial action if unexpected problems or unacceptable impact arise;
· To provide data to enable an environmental audit to be undertaken;
· To provide a data base against which the short or long term environmental effects associated with the demolition works may be determined; and
· To verify the environmental impacts predicted in the EIA.
· 1-hour and 24-hour TSP monitoring at three locations on the Site boundary facing ASRs KT1, KT3 and KT5;
· noise monitoring at three locations near the Site boundary facing the Site at KT1, KT3 and KT5; and
· as appropriate, the removal and disposal of contaminated material and surplus groundwater, (at this stage underground tank cleaning and backfilling are not thought to be required).
· Action Level, beyond which appropriate remedial actions may be necessary to prevent environmental quality deteriorating further ; and
· Limit Level, the limits stipulated in the relevant Hong Kong statutes and guidelines, if these are exceeded, works should not proceed without appropriate remedial action, including a critical review of plant and working methods.
Table 8.1 Schedule of Impacts and Mitigation Measures
No. |
Activity |
Respons-ibility for Implemen-tation |
Location Duration completion Of measures |
Implemen-tation Stage |
Relevant Guidelines Legislation |
|
1 |
Ash Disposal |
|
|
|
|
|
I |
Treatment |
Reconfirm extent of contaminated ash deposits by sampling for dioxins
and furans. Handling, transportation
and disposal of the ash waste in line with relevant regulations. Collection, immobilisation and testing of
waste for disposal to landfill shall be carried out according to the relevant
regulations and recommendations of the EIA including immobilisation by
collection and mixing the ash material with cement. Pilot mixing and TCLP tests should
establish the ratio of cement to ash to the satisfaction of EPD. Ash waste to be treated and placed into
steel drums lined with plastic sheeting.
The drums should be adequately sealed and in new or good condition. Prior agreement of the disposal criteria
from EPD and agreement to disposal from the landfill operator must be
obtained. |
CED’s Contractor |
KTCDA work areas. Duration of
the ash removal |
A@ |
1, 10, EIA |
II |
Disposal |
To monitor
the disposal of waste at landfills, a “trip-ticket” system (WBTC No. 5/99)
for all solid waste transfer/disposal operations should be implemented. The system should be included as a
contractual requirement, and monitored by the Environmental Team and audited
by the Independent Checker (Environment). |
CED’s Contractor |
As above |
A |
1, 5, 9 |
III |
Asbestos Removal |
An
asbestos abatement programme should be submitted to EPD for approval prior to
the commencement of the asbestos abatement work. |
CED and Contractor |
As above |
A |
4 |
2 |
Demolition |
|
|
|
|
|
A |
Non-blasting Methodology |
Waste Management Plan to be submitted to EPD. Demolition by Non-Blasting Methodology
Only. All structures and buildings
should be demolished and removed prior to demolition of chimneys |
CED |
KTCDA work areas. Duration of
the demolition |
C# |
8 |
B |
Material Storage |
Covers for
dusty stockpiles and control of dust emissions from construction
(demolition) works requires appropriate dust control measures to be
implemented in accordance with the requirements in the Air Pollution Control
(Construction Dust) Regulation. |
CED’s Contractor |
As above |
C |
4 |
C |
Vehicle movement |
Haul road watering, vehicle wheel wash prior to exit. Where practical, access roads should be protected
with crushed gravel. |
CED’s Contractor |
As above |
C |
4 |
D |
Plant maintenance |
All plant shall be maintained to prevent any undue air
emissions. |
CED’s Contractor |
As above |
Prior to start of works |
4 |
E |
Improved Site Hoarding |
Boundary hoarding to be modified in form of
noise barrier to provide effective noise screening and made of panels with a
superficial surface density of at least 10 kg/m3 |
CED’s Contract`or |
As above |
C |
Env. Permit |
F |
Demolition Sequence |
Include careful consideration and positioning of portable
noise barriers to allow noise attenuation.
|
CED’s Contractor |
As above |
C |
8 |
G |
Portable Noise Barriers |
Moveable noise barriers shall be provided close
to PME in cases where, in the opinion of the Engineer, such PME has the
potential to cause noise nuisance to sensitive receivers and where a benefit
will result. Such barriers shall be
made of panels with superficial surface density not less than 10 kg/m3. |
CED’s Contractor |
As above |
C |
Env. Permit |
H |
Plant Operation |
Modify continuous operational periods for noisy plant to
comply with noise criteria. |
CED’s Contractor |
As above |
C |
Env Permit |
I |
Demolition Techniques |
Selection of non-blasting demolition techniques to minimise
noise and vibration. |
CED’s Contractor |
As above |
C |
8 |
J |
Plant maintenance |
All plant shall be maintained to prevent any undue noise
nuisance. |
CED’s Contractor |
As above |
C |
2, 3 |
K |
Wheel wash |
All wheel wash water shall be diverted to a sediment pit. |
CED’s Contractor |
As above |
C |
5 |
L |
Sediment control |
Sediment removal facilities shall provided and be maintained
and excavated as necessary to prevent sedimentation of channels. Perimeter channels should be provided
before demolition starts. Works should
be programmed for the dry season where feasible. Environmental guidelines for
the handling and disposal of discharges from construction sites, as
stipulated in the Practice Note for Professional Persons, Construction Site
Drainage (ProPECC PN 1/94) to be followed. |
CED’s Contractor |
As above |
C |
5, 12 |
M |
Surface water diversion |
All clean surface water shall be diverted around the site. |
CED’s Contractor |
As above |
C |
5, 12 |
N |
Fuel can storage |
All fuel cans shall be placed within a bunded area. Any fuel
spills shall be mopped up as necessary. |
CED’s Contractor |
As above |
C |
5,6 |
O |
Material, plant move-ment & fuel can filling. |
Any fuel or oil spills shall be excavated and disposed of. |
CED’s Contractor |
As above |
C |
6,7 |
P |
Generators |
All generators shall be placed within a bunded area. Any fuel
spills shall be mopped up as necessary. |
CED’s Contractor |
As above |
C |
5,6,7 |
Q |
Material containers |
All empty bags and containers shall be collected for
disposal. |
CED’s Contractor |
As above |
C |
6,7 |
R |
Worker generated litter and Waste |
Litter receptacles shall be placed around the site. Litter
shall be taken regularly to the refuse collection points. Chemical toilets
(or suitable equivalent) should be provided for workers. Any canteens should have
grease traps. |
CED’s Contractor |
As above |
C |
6 |
S |
Neighbourhood nuisance |
All complaints regarding construction works shall be relayed
to the environmental team. |
CED’s Contractor |
As above |
C |
1, 6 |
T |
Legal requirements |
Different types of waste should be segregated, stored,
transported and disposed of in accordance with the relevant legislative
requirements and guidelines |
CED’s Contractor |
As above |
C |
1,6 |
U |
On-site separation |
On-site separation of municipal solid waste and
construction/demolition wastes shall be conducted in order to minimise the
amount of solid waste to be disposed to landfill. |
CED’s Contractor |
As above |
C |
1, 11 |
V |
Temporary storage area |
Separated wastes should be stored in different containers,
skips, or stockpiles to enhance reuse or recycling of materials and encourage
their proper disposal. |
CED’s Contractor |
As above |
C |
1, 11 |
W |
Record of wastes |
Records of quantities of wastes generated, recycled and
disposed (with locations) shall be kept. |
CED’s Contractor |
As above |
C |
1, 9 |
X |
Trip-ticket system |
To monitor the disposal of waste at landfills and control fly-tipping,
a “trip-ticket” system under WBTC N0.5/99 for all solid waste
transfer/disposal operations should be implemented. The system should be included as a
contractual requirement, and monitored by the Environmental Team and audited
by the Independent Checker (Environment). |
CED’s Contractor |
As above |
C |
1, 9 |
|
|
|
|
|
|
|
3 |
Soil
Remediation Phase |
|
|
|
|
|
AA |
B, C, D, E, F, G, H, I, J, K,
L, M, N, O, P, Q, R, S, T U, V, W and X as above |
Submit supplementary CAP and conduct
additional sampling to determine more accurately the extent of
contamination. As above (see W for
soil remediation). |
CED’s Contractor |
KTCDA work areas. Duration of
the soil remediation |
R |
As above |
BB |
De-watering |
Collect and recycle extracted groundwater and leachate by
mixing with cement for soil remediation.
Environmental guidelines for the handling and disposal of discharges
from construction sites, as stipulated in the Practice Note for Professional
Persons, Construction Site Drainage (ProPECC PN 1/94) to be followed. Any surplus groundwate and leachate
requiring disposal to be disposed of under the relevant legislation or
treated to meet the standards given in Table 9a of the WPCO TM and any other
parameters to be agreed with EPD prior to any consent being given to
discharge. |
CED’s Contractor |
As above |
|
5 |
CC |
Immobilisation |
Immobilisation and testing of waste soil shall be carried out
according to the relevant regulations and recommendations of the EIA
including immobilisation by collection and mixing the contaminated soil
material with cement. Pilot mixing and
TCLP tests should verify the effectiveness and establish the ratio of cement
to soil to the satisfaction of EPD.
Such activities shall take place in a covered area with a concrete
paved floor. Reassurance confirmatory
sampling shall be carried out to confirm the extent of contamination. Soil waste to be cast in blocks and
replaced in the ground. Extracted soils and materials and
stabilisation/solidification to be conducted in bunded area to prevent
surface run-off. See also item 2(H)
above. Final soil decontamination report
to be submitted to EPD. |
CED’s Contractor |
As above |
|
1, 10 |
4 |
Monitoring and Audit |
To be carried out in accordance with the Schedule in the
EM&A Manual. |
CED*/ Contractor/ RSS |
KTCDA works areas During demolition and at end
of demolition throughout execution of Remediation Action Plan |
C |
1 |
* Normally undertaken
by a specialist monitoring team employed directly by the proponent and audited
by the Independent Checker(Environment)
@ A = during ash
removal (before demolition)
# C
= during construction (i.e. demolition phase).
* R
= during soil remediation phase (after demolition)
1 Environmental
Impact Assessment Ordinance Technical Memorandum (EIAO)
3 The
ProPECC Note PN2/93 (Construction Noise daytime limits)
4 Air
Pollution Control Ordinance (APCO)
5 Water
Pollution Control Ordinance (WPCO)(Cap. 358)
6 Waste
Disposal Ordinance (Cap 354)
7 Waste
Disposal (Chemical Waste)(General) Regulation (Cap 354)
8 Draft
Code of Practice on Demolition of Buildings (BD, 1998)
9 Works
Bureau Technical Circular No. 5/99, Trip-ticket System for Disposal of
Construction and Demolition Material
10
Guidance Notes for
Investigation and Remediation of of Contaminated Sites
11
Works Bureau Technical
Circular No. 5/98, On Site Sorting of Construction Waste on Demolition Sites
12
ProPECC Note PN
1/94Construction Site Drainage
Attachment A Preferred Demolition Methodology (Extracted
From WP1 Originally Presented November 1999)
List of Abbreviations
AAP |
|
ACE |
Advisory Committee on Environment |
ACM |
Asbestos Containing
Material |
AIR |
Asbestos Investigation
Report |
AP |
Authorised Person |
APCO |
Air Pollution Control
Ordinance |
BOO |
Building Ordinance Office |
CAP |
Contamination Assessment
Plan |
CAR |
Contamination Assessment
Report |
CED |
Civil Engineering
Department |
CPLD |
Committee on Planning
& Land Development |
CSTG |
Cadogan Street Temporary
Garden |
DSD |
Drainage Services
Department |
EIA |
Environmental Impact
Assessment |
EIAO |
Environmental Impact
Assessment Ordinance |
EM&A |
Environmental Monitoring
& Audit |
EMSD |
Electrical &
Mechanical Services Department |
EPD |
Environmental Protection
Department |
G I/C |
Government,
Institutional/Community |
KTA |
Kennedy Town Abattoir |
KTCDA |
Kennedy Town Comprehensive
Development Area |
KTIP |
Kennedy Town Incineration
Plant |
LDC |
Land Development
Corporation |
LGHAGN |
Landfill Gas Hazard
Assessment Guidance Note |
MTIA |
Marine Traffic Impact
Assessment |
NWFB |
New World First Bus Depot |
PCWA |
Public Cargo Working Area |
PFBP |
Public Fill Barging Point |
PQA |
Preliminary Quantitative
Assessment |
RAC |
Registered Asbestos
Consultant |
R7 |
Route 7 |
RCP |
Refuse Collection Point |
RSE |
Resident Site Engineer |
SR |
Sensitive Receiver |
TIA |
Traffic Impact Assessment |
TM |
Technical Memorandum |
USD |
Urban Services Department |
I.
The contents of this
Attachment A to the EIA for the Demolition of the Kennedy Town Comprehensive
Development Area was originally presented to Government
Departments. The contents of this paper
was endorsed at the First Study Management Group Meeting for the study
Environmental Impact Assessment Study for Demolition of Kwai Chung Incineration
Plant and Kennedy Town Comprehensive Development Area, CE 15/99.
II.
The preferred demolition
methods were endorsed as a basis for defining the activities to be addressed
within the environmental impact assessment and the analysis of the alternative
demolition options and the major conclusions regarding demolition methods are
presented. The Working Paper also presents the major
constraints associated with the Projects. For purposes of presenting supporting
material to the EIA for the Demolition of the Kennedy Town
Comprehensive Development Area the text referring to Kwai Chung Incineration
Plant has been deleted.
III.
The PPFS for KTCDA concluded that the
preferred method of demolition was by traditional top down methods utilising
manual tools and mechanical plant but that the possibility of
demolition by implosion for two chimneys (one at the incineration plant and one
at the abattoir) could not be ruled out.
The PPFS recommended that the feasibility of demolition of the chimneys by
implosion or other unconventional techniques be further investigated in the
EIA.
IV.
Consultation with Government Departments has confirmed
the concerns regarding implosive demolition identified in the PPFS for KTCDA
and the preference for top down demolition methods. Investigations have shown
that ACM is present in the abattoir chimney and the incinerator chimneys and at
other location in the KTCDA. The weather
cladding of the KTIP buildings is also ACM.
This dictates that a non-blasting approach is required in order that the
ACM can be removed in line with statutory requirements.
V.
The KTCDA is surrounded by
residential development and other sensitive uses. The risks, hidden costs and knock on effects
of implementing any proposal which includes blasting techniques for the felling
of the chimneys or the main building structures also makes such options
unattractive.
VI.
The details of the
constraints to demolition are presented and a conceptual demolition method has
been developed which avoids most of the complications associated with blasting
and provides flexibility for the implementation stages of the works.
VII.
The conclusion is that non-explosive demolition methods
should be used for the demolition of the Kennedy Town Comprehensive Development
Area.
A1.1.1 The Civil Engineering Department (CED) has
appointed Atkins China Ltd. (ACL) to undertake the Environmental Impact
Assessment (EIA) for the Demolition of the Kwai Chung Incineration Plant and
the Kennedy Town Comprehensive Development Area (Agreement No. CE 15/99). The Kennedy Town Incineration Plant (KTIP) is
within the boundary of the KTCDA and ceased to operate March 1993 and has been
decommissioned and the facilities require demolition. The demolition of the
remaining facilities constitutes the Project as defined under the requirements
of the Environmental Impact Assessment Ordinance (EIAO).
A1.1.2 The primary aim of this
paper is to establish a conceptual demolition method and to define the major
constraints that must be considered in the final demolition process. The paper presents
information that facilitated decisions on acceptable conceptual demolition
methods for both Project as a basis for the remainder of the Study.
A1.1.3 To satisfy the requirements of the EIA it
is necessary to define clearly the nature of the works involved in the
demolition process. The development of a
conceptual scheme for the demolition process in turn requires detailed analysis
of the facilities and those surrounding uses and activities which might
influence decisions on demolition. This
paper presents this analysis. The
conceptual scheme for demolition of the facilities has been developed based on
practical experience and current demolition practice in Hong Kong as well as
internationally.
A1.1.4 A description of the
elements of the community and environment, likely to be affected by the
proposed demolition activities is provided to ensure that any potential
constraints on demolition works due to the need to protect sensitive receivers,
surrounding infrastructure or facilities are considered. Such requirements may constrain the way the
proposed Project is executed and affect the methods that can be used so as to
influence the choice of demolition methods.
A1.2 Structure of the Report
A1.2.1 In addition to this introduction Working
Paper 1 Report includes sections covering the following:
·
Section 2 Project
and Study Area
·
Section 3 Appreciation
and Understanding of Constraints to Demolition.
·
Section 3 General
Approach to Demolition of Buildings and Structures.
·
Section 4 Conceptual
Demolition Method for Chimneys at KTCDA.
·
Section 5 Conclusions.
A2.1 Kennedy Town Comprehensive Development
Area (KTCDA)
A2.1.1 The proposed Kennedy Town Comprehensive
Development Area (KTCDA) is situated next to Victoria Road and Cadogan Street,
Kennedy Town, and adjacent to Victoria Harbour, with a site area of about 34,000
square metres.
A2.1.2 The KTCDA comprises several elements as
well as the Kennedy Town Incineration Plant (KTIP). The main operations at the Kennedy Town
Abattoir (KTA) ceased and relocated to new facilities at Sheung Shui in the
autumn of 1999. The KTA includes an
incinerator for disposal of animal carcasses and waste that is managed by
EPD. The KTA plant remains in place.
A2.1.3 Part of the former EMSD Depot that forms
part of the KTCDA has been leased to New World First Bus (NWFB) for bus maintenance
and refuelling, under a short-term tenancy.
The remainder is leased as a car / lorry park. These facilities will remain in operation for
the time being.
A2.1.4 The former Kennedy Town Wholesale Market
has been relocated and this area has been remodelled as a park and sitting out
area adjacent to Victoria Road. This is
known as the Cadogan Street Temporary Garden (CSTG).
A2.1.5 Food and Environmental Hygiene Department
have recently constructed a Refuse Collection Point (RCP) between the park and
the Abattoir at Sai See Street.
A2.1.6 The KTCDA includes:
·
the Kennedy Town Incineration Plant (KTIP);
·
the Kennedy Town Abattoir (KTA);
·
the New World First Bus Depot (NWFB);
·
car / lorry park (CP);
·
FEHD Refuse Collection Point (RCP); and
·
the Cadogan St Temporary Garden (CSTG).
A2.1.7 The structures to be demolished are
summarised in Table A2.1.
A2.1.8 The KTCDA was recommended for future
private housing development in the “Planning and Engineering Study for the
Redevelopment of Mount Davis Cottage Area and Kennedy Town Police Married
Quarters” (Agreement No. CE 52/97), completed in May1999. The Open Space and Refuse Collection Point
were proposed to be permanently relocated within the redevelopment.
A2.1.9 The proposed Green Island Reclamation and
Route 7 (R7), a strategic road link between Kennedy Town and Aberdeen, are
located just to the north of the KTCDA site although the exact alignment of R7
is not yet confirmed. A further planning
and engineering study to address some major issues, including the Green Island
Development and alternative road alignments of Route 7, is currently being
considered by the government. The
findings from this further study may alter the future land use of the KTCDA.
Table
A2.1 Structures to be
demolished at KTCDA
Building |
Brief Description |
KTIP Chimneys |
Two reinforced concrete chimneys, 60m high, 3.5m in diameter. |
KTIP Building |
Reinforced concrete structure of approximately 3,025m² on plan, Refuse Pier |
Kennedy Town Abattoir |
5-storey reinforced concrete structures of approximately 9,500m² on plan, Reception Pier |
Former EMSD Building |
Boiler House and Animal Carcass Incinerator Building. One reinforced concrete chimney, 25m high, 3m in diameter. |
New World First Bus Depot |
Offices and Vehicle Inspection Bays. Overall size is approximately 600m² on plan. |
Hong Kong Electric Sub Station |
Single Storey Transformer House (adjacent to KTA lairage) |
Cadogan Street Temporary Garden |
(Inclusion / Exclusion / Programme
Requires Decision.) |
Sai See Street Refuse Collection Point |
(Inclusion / Exclusion / Programme
Requires Decision.) |
A3. Appreciation
and Understanding of Constraints to Demolition
A3.1.1 This section identifies the sensitive
receives (SRs) affected by the Project as defined in the EIAO and discusses the
implications of these and other nearby sensitive engineering projects and
infrastructure with respect to the constraints they will place on demolition
methods. Where relevant we have also
noted the implications such sensitive locations may have on the potential for
explosive demolition.
A3.1.2 It has been assumed that the demolition for
KTCDA will take place as soon as possible in order to allow future developments
on and near the site. The earliest start
date will be in 2002 with demolition works lasting about one year.
A3.2 Sensitive Receivers at KTCDA
Residential, Government, Institutional and Community
A3.2.1 Residential, Government, Institutional and
Community uses surround the KTCDA site and many are elevated and overlook the
site. The nearest rank of sensitive
receivers is discussed below.
·
Kennedy Town Police Married Quarters currently
overlooks the site. The premises are
scheduled to be vacated but parts of the buildings will potentially be occupied
up to March 2002.
·
The Mount Davis Cottage Area has already been
partially vacated and the remaining premises will be vacated up to March 2001.
·
The new Housing Society development at Ka Wai Man Road
is scheduled for occupation by mid 2000.
·
There are occupied residential building at Cadogan
Street including Centenary Mansion.
A3.2.2 Other premises in the low rise blocks at
Cadogan Street are scheduled for demolition in preparation for the Land
Development Corporation’s urban renewal project. Whereas many of the ground floor commercial
premises remain in operation temporarily, the residential units above have been
vacated or are scheduled to be vacated by the time demolition of KTCDA takes
place.
A3.2.3 Manhattan Heights high rise development at
Kennedy Town New Praya overlooks the site. Residential units will be occupied
by the time demolition of KTCDA takes place.
A3.2.4 There are Government, Institutional and
Community uses at St Lukes Church School, St Lukes Settlement, Jockey Club
Clinic, Victoria Mortuary and the Bayanihan Centre.
A3.2.5 St Lukes Church School on Ka Wai Man Road
and the, St Lukes Settlement and Jockey Club Clinic will remain in operation at
the time of demolition for KTCDA.
A3.2.6 The Bayanihan Centre on Victoria Road is a
training and support facility for Philippine overseas workers which is open
seven days per week and it is assumed this will remain in operation at the time
demolition of KTCDA takes place.
A3.3 Implications of Demolition by Implosion at KTCDA
A3.3.1 Non-explosive demolition methods used the
EIA will lead to the recommendation recommend of a series of mitigation
measures to protect the residential, government, institutional and community
uses and all other sensitive receivers that surround the KTCDA.
A3.3.2 If explosive demolition methods were to be
used, the EIA would include a comprehensive Risk Assessment Report covering the
effects of the affected neighbourhood would be required. The assessment would be undertaken within
this Study and one of the results would be to recommend risk reduction measures
to ensure that explosive demolition would be carried out within the Hong Kong
Risk Guidelines. These requirements
would be included in the Environmental Permit.
A3.3.3 One such likely requirement is the
inclusion of an exclusion zone to minimise the chance of ejecta or debris
hitting any spectators. Whereas the
exclusion zone cannot be determined at this stage, it is possible to identify
the likely size of such a zone by reference to other studies. Recent requirements for the minimisation of
risks from ejecta, included in the Environmental Permit (EP-002/1998) for the
Felling of Five Power Station Chimneys at Tsing Yi Power Station Chimneys by
explosion, included an exclusion zone equivalent to three times the chimney
heights.
A3.3.4 The “Draft Code of Practice for Demolition
of Buildings (Buildings Department) requires that all residents or inhabitants
within an exclusion zone be evacuated during blasting. The radius of a typical exclusion zone is not
less than 2.5 times the height of the structure to be demolished. The highest structures at the KTCDA are the
KTIP chimneys at 60m. Experience
therefore suggests that an exclusion zone of two and a half (150m) to three
times (180m) the height of the structures to be demolished would be required at
the KTCDA. The possible limits of
exclusion with respect to the chimneys at KTCDA are shown on Figure 2.1.
A3.3.5 The PPFS for the demolition of KTCDA noted
that, due the short distance between Chimney “A” and other buildings to the
west, it would be a high risk option to demolish using explosives. The PPFS also noted that the possibility of
demolition of Chimneys B and C using explosives could not be ruled out at that
stage. However the PPFS did not make
reference to any other buildings in the vicinity. The Kennedy Town Police Married Quarters, St
Lukes Settlement, Jockey Club Clinic, Victoria Mortuary, Bayanihan Centre, St
Lukes Church School, Hosing Society Residential Development, Cadogan Street
Temporary Garden, China Merchants Wharf, Industrial Buildings in Victoria Road
and Public Piers at Cadogan Street would all be within a 2.5 times exclusion
zone for evacuation for Chimney “B”.
A3.3.6 The PPFS report also notes that the Cadogan
Street Temporary Garden (GLA-THK 10550), RCP (GLA-THK 1054) and the New World
First Bus Depot are subject to leases requiring one month notice for
termination. The FEHD RCP at Sai See Street
is subject to a lease requiring three months notice for termination. The reprovision of the Cadogan Street
Temporary Garden and the Temporary RCP have been planned to be within the
Kennedy Town CDA redevelopment. The
location for an alternative site for the New World First Bus Depot has been
proposed to lie within the Green Island Development. In the event that these locations cannot be
closed for operational reasons, they may also have to be temporarily closed or
evacuated during demolition by implosion, if they are not already handed back
to Government by the time of demolition.
A3.3.7 USD have indicated that there is no
programme identified to relocate the newly developed RCP and CSTG. Whereas these sites would require protection
during the demolition, regardless of the demolition method, there would be more
opportunity for a flexible approach to the phasing of demolition if
non-blasting methods are used and exclusion zones are not required.
A3.3.8 The New World First Bus Depot also includes
diesel fuel storage tanks and other lubrication oil storage. Experience also suggests that such tanks in
reasonably close proximity to demolitions by implosion would be required to be
emptied and sterilised for the duration of the felling by implosion in order to
reduce risk.
A3.4 Other Sensitivities near KTCDA
Road Traffic
A3.4.1 Road traffic access must be maintained for
residential and commercial uses at Kennedy Town. There are general concerns about the
potential impact of traffic to and from the demolition site on the local
network.
A3.4.2 Access must be maintained for commercial
uses at China Merchants Wharf and Godowns, the Kennedy Town public transport
terminus Victoria Public Mortuary, industrial buildings, residences on Victoria
Road, the petrol station on Victoria Road and the Island West Refuse Transfer
Station.
A3.4.3 Whereas the exact volume of waste to be
disposed of has not yet been determined, preliminary estimates indicate that
about forty lorries per day would be required.
Therefore it is estimated that during the peak of demolition process
fewer than ten heavy vehicles per hour would be required to remove waste from
the Site. Traffic Impact Assessments
carried out for the “Planning and Engineering Study for the Redevelopment of
Mount Davis Cottage Area and Kennedy Town Police Married Quarters” (Agreement
No. CE 52/97) indicate that this level of additional traffic could be absorbed
into the surrounding network without significant impacts.
A3.4.4 In addition the impact of potential road
closures needed to allow blasting techniques, such an approach would require
additional studies which are outside of the Brief and may delay the EIA
programme. Transport Department have
indicated a general presumption that a road closure would be unacceptable unless
it can be proven that traffic impacts can be mitigated to acceptable
levels. A full traffic impact assessment
(TIA) would be required to assess impacts on all roads in the exclusion zone and the public transport system and a
feasible traffic diversion scheme would need to be developed. Emergency plans would also be required.
Marine Traffic
A3.4.5 Access must be maintained for vessels
accessing the pier at China Merchants Wharf and Cadogan Street and interference
to the Victoria Harbour marine traffic must be minimised. Although local assessments indicate that
additional waste disposal vehicles could be absorbed into the surrounding road
network, it has been suggested that barges could be used to remove waste in
order to reduce overall road traffic impacts.
Such a proposal may also require a Marine Traffic Impact Assessments
(MTIA).
A3.4.6 The exclusion zone for blasting would also
be applied to marine vessels in the area and together with the requirement to
evacuate the China Merchants Wharf and Godown, this may require compensation to
the operators and the hidden cost organising and patrolling such an evacuation
in the busy harbour.
Weather
A3.4.7 The KTCDA is close to the slopes of Mt.
Davis which have been prone to landslides in the past. Blasting restrictions may be necessary and
initiation of blasts may need to be prevented following periods of heavy rain
as this may increase the likelihood and effect distance of landsides. Likewise blasting demolition would not be
allowed in periods of high or gusting winds to avoid the possibility of
chimneys falling in unplanned directions or at an unplanned time. Both considerations introduce uncertainty to
the programme but in particular add to the difficulties in co-ordination of
evacuation of the exclusion zone.
Other Issues
A3.4.8 The revised alignment for Route 7 and
extent of the Green Island Developments are currently under review but at
present the programme of these developments is unlikely to be advanced before
2002 and after the target completion date for demolition of KTCDA. These development proposals should therefore
have no impact on the Project.
A3.5 Implications of the Presence of Asbestos
Containing Materials
A3.5.1 An Asbestos Investigation Report (AIR) and
Asbestos Abatement Plan are required under the Air Pollution Control Ordinance
(APCO) prior to the commencement of any asbestos abatement work. Reports and plans prepared by Registered
Asbestos Consultants (EPD register RACs 1014 and 1019) indicate asbestos
containing materials (ACM) are present at the Site.
A3.5.2 The Brief assumes that any
asbestos containing materials (ACM) present in the chimneys and superstructures
within the two sites will be removed before commencement of the demolition
works. However, experience suggests that
in practice the asbestos abatement processes will run more smoothly if both
asbestos contractors and civil demolition contractors work in tandem, as has
been the case with the civil demolition of the remaining buildings and structures
at other large industrial locations in Hong Kong. This is generally due to the convenience of
the main civil demolition contractors providing access (scaffolding etc.) to
the ACM, for the asbestos contractor. In
other cases it may be necessary for the civil demolition contractor to remove
large sections of materials for the asbestos contractor to gain access to the
ACM. Further details are presented in the
dedicated Asbestos Study Report.
A3.5.3 Records show that bulk asbestos removals of
ACM from the KTIP was undertaken prior to the removal of main plant and
machinery some years ago. Site surveys
and inspection of the plans for the KTA suggest that asbestos containing
materials (ACM) are present in the chimney of the KTA. Drawings indicate that an asbestos rope was
used to seal joints between the sections of the chimney. Such materials may only be accessible as the
sections of the chimney are dismantled.
Blasting could result in the uncontrolled release of asbestos
fibre. Therefore blasting will not be an
option. Other areas which will require
investigation but which have to date not been accessed include the insulation
to the carcass incinerator, the blood boilers and chimney duct insulation. However, the presence of ACM in these locations
will not have a significant bearing on the choice of demolition method as they
can be removed as soon as the relevant plant is decommissioned.
A3.5.4 Investigations have confirmed the presence
of a typical low risk asbestos containing material (ACM) on the superstructures
of the KTIP incinerator building. This
is in the form of corrugated metal weather cladding with an asbestos type
mastic protective paint coating. This is
identical to ACM typically found at other industrial sites in Hong Kong, built
in the 1960s and 1970s. Other ACM has
also been identified at KTIP.
A3.5.5 Site visits did not reveal any potential
ACM in the New World Bus Depot or the other parts of the Site. Other areas have been investigated but no
potential ACM has been identified.
Details are presented in the dedicated Asbestos Study Report (Asbestos
Investigation Report and Asbestos Abatement Plan).
A3.6.1 Based on the information presented in
Section 3 the consultants believe that sufficient information has been gathered
to recommend that the preferred method of demolition should adopt a top-down,
non-explosive approach for the demolition of Kennedy Town Comprehensive
Development Area.
A4. General
Approach to Demolition of Buildings and Structures at KTCDA
A4.1 General Approach
A4.1.1 This section seeks to illustrate some of
the more general procedures for demolition that would apply to KTCDA. The intention in this and section 5 is not to
prescribe a precise method or provide a work specification or a demolition plan
but to indicate the approach which should be taken, in sufficient detail to
facilitate broad agreement on the methodology and progress Environmental Impact
Assessment.
A4.1.2 Whereas the eventual detailed demolition
plan of the selected demolition contractor(s) may not necessarily adopt the
precise methodology proposed in this working paper, the consultants believe
that general characteristics of the methods are appropriate. The methods are sufficiently effective and
applicable for the tasks and where possible methods that will help reduce noise
and dust nuisances have been indicated.
The options selected are also broadly in line with the Draft Code of
Practice for Demolition of Buildings (Buildings Department 1998) which will
also need to be observed at the detailed design stage.
A4.1.3 The overriding concerns for the demolition
Projects will be safety and minimisation of environmental impacts. This will include the safety of the
operatives, safety of the other workers on the site and safety of the general
public as well as protection of adjacent facilities and minimisation of
nuisances.
A4.1.4 The Contractor should during the course of
demolition, ensure and verify that all utilities and services have been
rendered safe.
A4.2 Hoarding and Site Access
A4.2.1 Typical hoardings would to be provided
along the site boundaries. Portable
barricades will be used to cordon off different work zones where demolition is
in progress. Where conditions warrant
the Contractor should seek opinion and advice from the Site Engineer/AP/RSE in
order to modify such plans accordingly.
A4.2.2 The buildings and chimneys are totally
within the proposed Project site and access would be controlled by security
guards. No members of the public or
unauthorised person would be allowed to enter the sites.
A4.2.3 Only contractors’ personnel and Government
officials concerned with the demolition would be allowed within the contractors
working area.
A4.3 Demolition Principles
A4.3.1 Building and other structures should
generally be demolished in the reverse order to that of their
construction. The order of demolition
for building would be progressive, storey by storey, having regard to the type
of construction.
A4.3.2 As a general rule, wherever possible,
external non-loading bearing cladding or any non-structural work should be
removed first. All asbestos containing
materials (ACM, particularly any ACM panels, would be removed prior to
commencement of demolition works where ever possible. Other ACM may need to be removed as access is
gained to particular areas and as the demolition progresses (see also section
3).
A4.3.3 Overloading of any parts of the remaining
structure with debris or other materials should be avoided. Where materials and debris and are lowered
from higher levels, care should be taken to prevent the material from swinging
in such a manner that it creates a danger to the workers on site or the
surrounding structures. Larger pieces of
debris should be broken down into manageable sizes, subject to a maximum of
1.0m x 1.0m. The weight of loaded
buckets for unloading debris would be limited to say, 200 kg.
A4.3.4 All debris would be removed at frequent
intervals preferable on a daily basis and stockpiles should not be allowed to
build up. In general it is anticipated
that demolition waste would be removed on a daily basis with several tens of
lorries leaving either site each day at the peak of demolition activities.
A4.3.5 Reinforced concrete structural members
should be cut into lengths appropriate to the weight and size of member before
being lowered to the ground. Where
possible, crane and lifting gear should be used to support beams and columns
whilst they are being cut and lowered to the ground.
A4.3.6 Removal of bricks walls should be from top
to bottom in horizontal runs of not more that 300mm wide.
A4.3.7 Before and during demolition, the
Contractor should pay attention to the nature and condition of the concrete,
the condition and position of reinforcement, and the possibility of lack of
continuity of reinforcement should be ascertained. Attention should also be paid to the
principles of the structural design to identify parts of the structure, which
cannot be removed in isolation. If
uncertainties exist then advice of the Site Engineer/AP/RSE’s advice should be
sought.
A4.3.8 During demolition works, if anomalies or
irregularities are discovered in structural elements, regarding reinforcement
bar details, alteration and addition works, unauthorised building works, etc,
demolition works should stop immediately.
AP/RSE should be informed and works will commence only after AP/RSE
approval is obtained.
A4.3.9 If the Contractor discovers that the
removal of certain parts of the buildings or structure during demolition would
result in other parts becoming unsafe, it would be necessary to determine where
temporary support will be needed and the advice of the Site Engineer/AP/RSE
should be sought.
A4.4.1 The Contractor will need to carry out works
in accordance with the Factories and Industrial Undertakings Ordinance,
particularly the Construction Site (Safety) Regulations and the Code of
Practice for Scaffold Safety, as well as all other statutory requirements and
guidelines covering health and safety issues.
A4.4.2 All contractor and sub-contractors should
be competent and qualified in demolition works.
Site Engineer/AP/RSE(s) will need to ensure that all levels of
Contractor(s) and his subordinates are fully conversant with the demolition
plans, method statements and procedures.
A4.4.3 Where scaffolding is used, the Contractor
should arrange for a competent scaffolder to visit site and inspect the
scaffolding work, and to make any adjustments required to the scaffolding as
the work proceeds, to ensure its stability.
A4.4.4 The Contractor shall also appoint a
competent person, experienced or trained in the type of operation being
performed at that particular time, to supervise and control the work on site.
A4.4.5 The Contractor should ensure that every
work place, approach and opening, which may pose a danger to persons employed
and others should be properly illuminated and protected.
A4.4.6 The use of all mobile cranes must be
strictly controlled to ensure that cranes of adequate capacity will be used for
lifting under different loading conditions.
A5. Principles
of Chimney Demolition at KTCDA
A5.1 Access
A5.1.1 The main site would be protected by
security personnel and a high hoarding such that the public would be totally
excluded from the Project.
A5.1.2 The area beneath the chimneys would be
cordoned off and only authorised staff involved in the demolition of the
chimneys would be allowed admission into the vicinity of the chimney
structures.
A5.2 General Approach
A5.2.1 The principle of the demolition procedure
for the upper portion of the chimneys (i.e. say 10meters from ground level or
greater) is that the chimneys will be broken into small pieces on the spot by
operatives using hand held tools. They
would work from working platforms external to the chimney (Figure 5.1). Hydraulic breakers would be used for the
remaining lower portions of the chimneys.
A5.2.2 Prior to the commencement of the demolition
work, loose sand will be placed on top of the existing ground around the
chimneys to receive small pieces of light debris that may fall. To facilitate the access of the excavators
for the removal of debris, an access ramp will be formed. The vertical opening (former fan duct
connection point) near the base of the stack would be blocked when demolition
is in progress. This portal would be
opened for removal of debris after completion of daily demolition work. The above mentioned method of removal of
debris is only applicable to the demolition of the upper portion of the
chimneys.
A5.2.3 For demolition of the lower portion, the
demolished debris would be formed as an access ramp for the hydraulic breaker
to ascend to a height sufficient to gain access and demolish the remaining
portion of the chimney.
A5.2.4 The demolished debris would be broken down
and removed by hydraulic excavators and loaded on to trucks for transportation
to the designated disposal site. During
the demolition work, water sprays will be used to suppress excessive dust
generated by the processes.
A5.3 Preparation
A5.3.1 The area surrounding the chimney will be
secured and all necessary barricades erected.
Only authorised personnel will be allowed into the area. A steel external working platform system will
be erected to surround the upper portion of the chimney, i.e. greater than 10
meters above ground level. The maximum
distance between the floor levels of the working platforms will be two
meters. Access steel ladders will be
constructed from ground level to the top of each chimney, with proper handrails
(Figure 5.1).
A5.4 Sequence of Operations
A5.4.1 The demolition sequence would involve the
construction of a series of working platforms around the outside of a
chimney. Workers would work from the top
most platform to remove the chimney structure with the debris directed into the
lower portion of the remaining chimney.
This would involve the following steps.
a)
All required preparation work and safety measures
would be installed. The area surrounding
the chimney would be made secure and all necessary barricades erected.
b)
Safety netting and tarpaulins would be installed to
enclose the location at which demolition work is in progress (i.e. the external
boundary of the steel working platform from platform floor level to one meter
above the top edge of the remaining chimney wall). Checks would be made to ensure no gaps were
present between floor boards and between the front edge of platform and the
external surface of the chimney, so as to avoid falling of broken pieces out
beyond the netted working platform.
c)
The portion of the wall from say 0.3m above the floor level
of the working on the platform to the top of the chimney will be demolished by
operatives working on the platform using hand held pneumatic breaking tools to
break the existing chimney concrete into small pieces. Work would proceed from top working towards
the lower level. The steel reinforcement
exposed in the process would be cut by flame and lowered to ground.
d)
After completing the work at one level operatives
would descend to the working platform just below and remove the components of
the upper platform carefully. Demolition
at the lower platform level would then proceed safety nets will be installed in
the same manner as described in procedure (b) above.
e)
The debris would be cleaned out from the platform
daily (each evening) to avoid accumulation of debris.
f)
The same sequence of work from procedure (b) to (d)
would be repeated until the chimney had been lowered down to approximately 10m
chimney height, a level within the reach of mobile hydraulic breakers at ground
level. The lower portion will be removed
by these means.
A5.5.1 The buildings and chimneys at KTCDA can be
demolished and removed by the conventional top down demolition using hand held
tools and mechanical breaking methods.
In order to avoid hazards caused to the adjacent areas, all the
structures and other buildings near to the chimneys would be demolished and
removed prior to the demolition of the chimneys.
A5.5.2 The estimated time for the completion of
these works included in the PPFS was 12months which would appear to be ample
time for demolition based on the above methodology.
A6.1.1 This paper presented information concerning
the difficulties associated with the demolition of the Kennedy Town
Comprehensive Development Area (the Project).
In order to facilitate the progress the EIA process as a whole it is
necessary to define the Projects in sufficient detail in line with the
objectives of the Study.
A6.1.2 The primary aim of this
paper is to establish a conceptual demolition method in order to facilitate
progress the EIAs. During the
preliminary investigations the consultants have taken note of the work
conducted previously and also initiated discussions with relevant Government
departments, many of whom have expressed severe concerns with the proposals to
include any form of blasting techniques for the felling of the chimneys or the
main building structures at the site.
A6.1.3 In the selection of an appropriate
demolition method the physical effects on local sensitive receivers and adjacent
structures are very important. There are
also hidden costs arising from the need to carefully co-ordinate demolition by
implosion. The effect on marine and road
transport systems and the complexity of implementing controls is also an
important factor. The cumulative impacts
of the surrounding interfaces on the project methods have been assessed and
make demolition by implosion at either site a potentially costly and a very
high risk proposal.
A6.1.4 The preferred demolition methodology
presumes that a variety of top down methods would be used and various articles
from a suite of powered mechanical equipment has been assumed to be in use at
various locations across the site throughout the demolition. The use of jack-hammers and hydraulic
breakers is efficient and noise and dust impacts can potentially be controlled
by a range of mitigation measures (e.g. noise barriers, dust control) familiar
to the construction industry in Hong Kong.
In addition the statutory provisions under the Noise Control Ordinance
and Air Pollution Control Ordinance control noise and dust from such
operations. Due to the presence of ACM
the preferred method of demolition must adopt non-explosive approach. The asbestos investigation and abatement
plans are described in detail in the dedicated Asbestos Study Report.
A6.1.5 In order to facilitate the progress of the
Environmental Impact Assessment the consultants sought and gained endorsement
of the content of this paper. Whereas
the eventual detailed demolition plan of the selected demolition contractor(s)
may not necessarily adopt the precise methodology proposed in this working
paper, the methods used shall adopt top-down, non-explosive methods for the
demolition of Kennedy Town Comprehensive Development Area.
Attachment
B
Landfill Disposal Criteria for Contaminated
Land
Metals
Parameter |
TCLP
Limit (ppm) |
Cadmium |
10 |
Chromium |
50 |
Copper |
250 |
Nickel |
250 |
Lead |
50 |
Zinc |
250 |
Mercury |
1 |
Tin |
250 |
Silver |
50 |
Antimony |
150 |
Arsenic |
50 |
Beryllium |
10 |
Thallium |
50 |
Vanadium |
250 |
Selenium |
1 |
Barium |
1000 |
Source : Guidance Notes for Investigation
and Remediation of Contaminated Sites (EPD TR1 / 99).
Metals
Toxicity
Characteristics Leaching Procedure (TCLP) test for materials contaminated with
heavy metals needs to be carried out in accordance with the testing frequency
and requirements as stipulated in EPD’s Guidance Notes for Investigation and
Remediation of Contaminated Sites.
TPH
and PAH
Toxicity
Characteristic Leachate Testing Procedure (TCLP) tests for TPH, PAH and BTEX
contaminated materials have to be carried out according to the testing
frequency and requirements as stipulated in EPD’s “Guidance Notes for
Investigation and Remediation of Contaminated Sites. Pre-treatment is required to bring levels of
TPH to below the TCLP limit of 2,500ppm PAH/BTEX to below the TCLP limit
1,000ppm.
Dioxins
and Furans (PCDD/PCDF)
Toxicity
Characteristic Leachate Testing Procedure (TCLP) tests for PCDD/PCDF
contaminated materials have to be carried out with reference to the
requirements as stipulated in EPD’s Guidance Notes for Investigation and
Remediation of Contaminated Sites.
Pre-treatment is required to bring levels of PCDD/PCDF to below the TCLP
limit of 1ppb PCDD/PCDF (TEQ), subject to TCLP confirmation at a frequency of 1
sample per 100 tonnes of stabilised materials.
N.B.
TEQ =toxicity equivalent units.
ppm = mg/kg (miligrams
/ kilogram)
ppm = mg/g (micrograms
/ gram)
ppb = ng/g (nanograms
/ gram)
ppb = 1000pg/g (picograms / gram)
Appendix C
(Source: Standards for Effluents Discharged into
Drainage and Sewerage Systems Inland and Coastal Waters, EPD)
1. Hazards and Safety Precautions
1.1 Introduction
1.1.1 Hazards which may arise
at KCIP generally be classified under the following headings:
· General Hazards
· Groundwater / Soil leachate
Operators
1.2.1 Operators should be
experienced and licensed drivers. Where
possible, all operators should be required to demonstrate their driving ability
in the equipment they will be operating and under actual job conditions before
recruitment.
1.2.2 Only personnel with
valid driving licences are permitted to drive any site cars or vehicles. In the case of vehicles which are not
intended for road use, the driver should hold a licence for the nearest
comparable class of road vehicle.
1.2.3 For operators employed,
a photocopy of their driving licence should be obtained. Their validity and the class of vehicle
licences to drive should be checked.
1.2.4 The site office should
keep an up to date list of names and copies of driving licences of drivers of
motor vehicles and plant.
Equipment
1.2.5 Drivers should make a daily inspection of their vehicles. The check should include steering, brakes, mirrors, lights, horn, tires and windshield wipers. Reverse alarms which must be installed on all trucks and lorries should also be checked to ensure safe operation. Drivers are required to report all defects to the plant mechanic foreman, and repairs should be made promptly.
Roads
1.2.6 Site roads should be
maintained in safe operating condition at all times. Roads should be built to provide adequate
drainage and width and should avoid sharp curves, abrupt changes in gradient
and excessive gradients. The use of
one-way traffic roads is recommended wherever possible. Site roads must have clearly visible signs in
both Chinese and English.
Transporting Personnel
1.2.7 Personnel should only
ride in vehicles designed for the purposes.
It is forbidden for personnel to take rides with operations where no specific
sear has been provided for passengers.
Loading Lorries
1.2.8 Materials loaded onto
lorries should be within the permitted safe weight limit and should not project
beyond the lorry body or be placed in an unsafe pile in such a manner as to
present a hazard to other vehicles, pedestrians or structures.
General Requirements
1.2.9 Drivers leaving the
driver leaves the driving seat of a vehicle shall ensure the engine shall is
switched off, the gear engaged and parking brakes applied. The wheels shall be chocked on slopes.
1.2.10 Lorries should only be
backed under the direction of a marshal or spotter. In dumping areas, the marshal and spotters
should be identified by a reflective vests.
1.2.11 All operators and drivers
are required to observe speed limits at all times.
1.2.12 All pedestrians requiring
to pass close to an operating machine shall ensure that the machine operator
has been them and has stopped operation prior to proceeding.
1.2.13 All personnel working on
site roads or directing traffic shall wear reflective vests.
Plant Noise
1.2.14 The foreman shall ensure
that noise assessments are carried out on all noisy plant used on site. Any plant that creates noise exceeding the
first action level stated in the Factories and Industrial Undertakings (Noise
at Work) Regulations should be identified, with notices fixed to the plant and
appropriate action should be taken as described in the Regulations to avoid
exposure to the noise. Attention shall
also be paid to the recommended Environmental Monitoring and Audit plan for the
site.
1.3.1 The reclamation under
the site may exude leachate originating from soil which may be contaminated or
toxic and the following rules should therefore be observed:
· If leachate has to be handled, or groundwater samples, ensure that the operatives wear protective clothing and gloves. If any operatives come into contact with contaminated leachate, they should be immediately wash the affected area with clean fresh water.
· Ensure that any broken skin, cuts, graze and the like do not come into contact with waste or leachate. All cuts etc should be covered prior to working on the site.
· Safety boots should be worn on the site.
· All operatives should keep a lookout for sharp objects on the site such as broken glass, syringe needles, nails in pieces of wood and the such like.
· If any operative receives any cuts or grazes whilst he is at work, he should report this immediately to his supervisor who will arrange for medical attention.
1.4.1 All operational and
supervisory staff’s attention shall be drawn to the hazards of potentiall
contaminated ground.
1.4.2 No fires shall be
permitted on the site. Operational and
supervisory staff shall immediately extinguish any fires within the site.
1.4.3 Confined spaces and
excavation, where entry is required shall be treated as described under Section
1.5.
1.4.4 Fire fighting facilities
shall be maintained on the site, and shall be property housed and kept readily
available for instant use.
1.4.5 The site designated
emergency co-ordinator shall liaise with the Fire Services Department to ensure
that they are in a position to respond quickly to any fire or explosion which
may occur. The emergency co-ordinator
shall notify the Fire Services Department immediately in the event of any such
emergency.
1.4.6 The site agent shall
carry out the following:
· Prepare detailed working procedures and safety precautions for the work being carried out.
· Instruct the workmen and other staff in the working procedures and safety precautions to be followed.
· Record in writing that the workmen and other staff have been so instructed.
· Provided sufficient equipment so the working procedures and safety precautions can be followed.
· Ensure the working procedures and safety precautions are adhered to.
1.5 Working in Confined Spaces
1.5.1 The Site contractor
shall ensure that any work in a confined space, as defined in the Factories and
Industrial Undertakings (Confined Spaces) Regulations, complies with the
requirements of the Regulations and is in accordance with the Guide to the
Regulations published by the Labour Department.
1.5.2 All entries into
confined spaces will be subject to a written detailed safe working procedure
and a permit to work procedure. The
written safe working procedure will include, but may not be limited to, details
of the following: -
· arrangements for detecting toxic or explosive gas or oxygen deficiency, and the detection equipment to be used.
· supervision arrangements
· safety and emergency rescue equipment to be used, including breathing apparatus, safety harness and safety ropes
· permit to work procedures
1.5.3 All persons entering a
confined space shall have received appropriate training from authorised bodies.
1.5.4 All written safe working procedures and completed “Permit-To-Work Certificate” shall be kept in the site office.
Environmental Outcome
Profile
The Project
Total Project Cost :~HK$112 million
Cost of Environmental
Component (EIA, Study and Mitigation Measures) say HK$31.0million.
Road works = N/A
Railway =N/A
Reclamation / dredging
=N/A
Power station =N/A
Drainage work =N/A
Development Study = N/A
Others: Demolition
a) Demolition
of the Main Plant Kennedy Town Incineration Plant Building (60m x 70m x 30m
high) office building, loading jetty and refuse pier;
b) Demolition
of two 60m high chimneys and a 25m high chimney;
c) Demolition
of Kennedy Town Abattoir and cattle reception pier;
d)
Demolition of former EMSD
Depot; and
e)
Ground remediation.
An application Reference (No. ESB-023/1998) for an Environmental Impact
Assessment (EIA) Study Brief under section 5(1)(a) of the Environmental Impact
Assessment Ordinance.
Key Outcomes :
Population Protected :
During demolition of the
incineration plant and soil remediation, dwellings within 500m of the project
boundary would contain a population of approximately 42,000. In addition there would be workers accessing
the work sites adjacent as well as occupants of the 10,000 or so vehicles using
the adjacent highways on a daily basis.
The residents would be
potentially affected by cumulative noise from the demolition. The EIA has demonstrated that, using the
recommended demolition methodology the population would not be subject to
exceedances of the relevant construction noise criteria under the EIAO TM.
During the demolition, the
population of approximately 42,000 within 500m of the project boundary would
potentially be affected by cumulative dust.
Implementing effective and adequate dust suppression will include
measures such as the dampimg down of all stockpiles and wheel washing
facilities to ensure vehicles moving to and from the site and around the site
would not create any significant increase to dust in the area. Therefore, the avoidance of nuisances can be
ensured during the whole demolition period by the adoption of measures to
ensure compliance with the Air Pollution Control (Construction Dust)
Regulations.
Problems Avoided :
During the demolition phase
the recommendation of non-blasting methods will avoid the need to evacuate
several sites and temporary closure of major road traffic arteries in the
vicinity. Remediation of contaminated
soil on site will avoid the use of valuable landfill space, ensure that the
site is suitable for all possible future uses.
The use of dust mitigation
measures will avoid nuisances for the adjacent sensitive receivers, work sites
or vehicles on the highways. Water
quality impacts will be avoided by the treatment of surplus site run-off,
groundwater etc. The environmental
monitoring and audit programme will ensure that accepted environmental
standards are met.
Environmentally Friendly
Designs:
During the demolition phase
the recommendation for non-blasting methods will reduce noise, dust and
vibration and the use of other environmentally friendly methodologies and waste
disposal measures will minimise the impact on the receiving environment as
follows:
· Mitigation measures and monitoring and audit programmes are recommended for the demolition and soil remediation phase for dust and waste management to ensure that the waste disposal is in line with EIA recommendations to prevent adverse environmental impacts.
· Noise and air quality impacts at the sensitive receivers can be reduced to within accepted norms by the use of the methods recommended in the EIA.
· Environmental benefits from implementing this Project include the removal of unsightly and derelict buildings, decontamination of the soil underneath the site and removal of several tonnes of asbestos waste.
Others : A Pre EIAO EMSG meeting was held in EPD’s offices on
July 24, 2001.
[1] Site observations elsewhere have indicated that the noise nuisance caused by the demolition process using hydraulic crushers was minimal. Thus it is recommended that the use of hydraulic crushers should be considered as quieter alternative demolition methods. This alternative would be 15 to 20 dB(A) quieter than a conventional hydraulic breaker. Assuming the sound power level of hydraulic crusher is 107 dB(A), it has been calculated that four hydraulic crushers could be deployed without exceeding the appropriate criteria. However hydraulic crushers are relatively new to the local construction industry and efficiency is recorded as 50% lower than that of a conventional hydraulic breaker.