2                    PROJECT DESCRIPTION

 

2.7.1  Key Project Requirements

 

CLP proposes to establish 3 x 132 kV supply circuit from the existing Pui O Substation on south Lantau Island, via Chi Ma Wan Peninsula via Adamasta Channel towards Cheung Chau North and Cheung Chau South Substations as shown in Figure 2.1. The preferred option of circuit alignment includes the following five sections:

 

(i)  Section 1: Pui O Substation to Pui O Beach using underground cable (3 x 132kV circuits of approximate length 2350m);

(i)  Section 2: Pui O Beach to Tai Long Wan east using cable tunnel (3 x 132kV circuits of approximate length 3000m), including a reclamation area of 180 m2 by the side of Pui O Wan for the works area of the proposed tunnel portal;

(i)  Section 3: Tai Long Wan to Cheung Chau Sai Tai Road using submarine cable (3 x 132kV circuits, each cable of approximate length 2300m);

(i)  Section 4: Cheung Chau Sai Tai Road to Cheung Chau South Station using underground cable (2 x 132kV circuits of approximate length 100m); and

(i)  Section 5: Cheung Chau Sai Tai Road to Cheung Chau North Station using underground cable (1 x 132kV circuit of approximate length 1250m).

 

2.1  Site LocationSite Location and Route Selection

 

The Study Area covers Pui O, Chi Ma Wan Peninsula, Cheung Chau and Adamasta Channel. Outline Zoning Plan (OZP) No. S/SLC/8S/SLC/11 for the South Lantau Coast shows the different zonings of the Study Area on Lantau Island (Part print of the OZP is shown in Figure 2.2). Encroachments ofreproduced as Figure 2.1). Encroachment by the potential cable routes on the Lantau South Country Park, coastal protection area, green belt,belt and village type development are expected. Particular concerns are in Pui O area, Cheung Chau, Shap Long Kau Tsuen, Yim Tin Kong Tsuen, Ham Tin Tsuen and Tai Long Wan where residential developments exist.

In Cheung Chau, the 3 x 132kV circuits will be connected to the substations located in Cheung Chau north and south. The potential cable routes will impinge on the following areas.

·proposed underground cables will be laid in Sai Wan Promenade and Cheung Chau Typhoon Shelter in Cheung Chau south and along Cheung Chau Sai Tai Road, Tai Hing Tai Road, Praya Street and Pak She Praya Street in Cheung Chau central; and

·Sai Wan Promenade and Cheung Chau Typhoon Shelter in Cheung Chau south.

central.

Prior to conducting this EIA Study, a detailed Route Options Assessment was carried out by MCL. Four options for the cable routes were investigated and the evaluations, merits and demerits of each are given in the Final Report for “132kV Supply to Cheung Chau - Route Options Assessment”, April 2000.  The four options essentially were:

 

Option I:     Overhead transmission lines in Pui O and Chi Ma Wan Peninsula; submarine cables across Adamasta Channel; underground cables in Cheung Chau.

 

Option IIa: Overhead transmission lines in Pui O; submarine cables from Pui O to Cheung Chau; underground cables and overhead transmission lines in Cheung Chau.

 

Option IIb: Underground cables in Pui O; submarine cables from Pui O Beach to Cheung Chau; underground cables in Cheung Chau.

 

Option III:   Underground cables in Pui O; cable tunnel in Chi Ma Wan Peninsula; submarine cables across Adamasta Channel; underground cables in Cheung Chau.

 

In the aforementioned Route Options Assessment, a number of factors including environmental and ecological impacts, landscape and visual character, statutory requirements, land requirements and ease of maintenance were considered in the evaluation process to allow a decision to be made on the optimum alignment option. In addition to which the alignment options were circulated to various Government departments including Environmental Protection Department, Agricultural, Fisheries and Conservation Department, Planning Department, Lands Department, Electrical & Mechanical Services Department, Civil Engineering Department for comment.

 

A set of evaluation criteria covering environmental issues, statutory requirements, traffic impacts, programme, cost, etc. were established taking into account the comments received from various Government departments. The evaluation process identified Option III, which included a cable tunnel across the Chi Ma Wan peninsula, as the preferred option.

 

Detailed evaluation of alignment options as given in the previously approved Route Options Assessment is given in Annex 1.

 

Justifications for selecting the cable tunnel option as given in the previously approved Route Options Assessment Report are summarised below:

 


Visual Impact

 

It was identified there would be no visual impacts resulting from the majority of the preferred alignment which is either underground, under water or inside a cable tunnel.  The only visual impact would be from the tunnel portals on the two sides of Chi Ma Wan Peninsula.  For the construction of the northern portal located on the south side of Pui O Beach, a temporary works area will be required for the construction of the portal. The southern portal will be facing Adamasta Channel on the rocky coast of Chi Ma Wan Peninsula. The visual impact of the portal to the public is insignificant.

 

Landscape and Ecology

 

Similar to visual impacts, the only areas along the proposed alignment which cause landscape and ecological impacts are at the two tunnel portals.  As the areas involved are relatively small, the landscape and ecological impacts were considered to be minimal.

 

Construction Impacts

 

The potential construction impacts in environmental terms are air and noise both of which will only be short term and non-persistent.  During the operational phase, effects of the electricity circuits on adjacent areas along the alignment will be minimal.

 

Marine Traffic

 

The construction of the submarine cables across Adamasta Channel will create the least hazard to the marine traffic using the Channel among all other alternatives.  Moreover, the duration of the cable laying work is not expected to be long.  With proper scheduling of the work the associated risk could be kept well within an acceptable limit.

 

Fisheries

 

The proposed alignment will have the minimum disturbance on fisheries among all other alternatives and the duration of the works is expected to be short.

 

Statutory Requirements and Procedures

 

The construction of the submarine cables across Adamasta Channel and the small scale temporary works area at the northern portal will require gazetting of the work under Foreshore and Seabed (Reclamation) Ordinance. The coverage of this temporary works area is the smallest amongst the options considered.

 

Land Requirements

 

The cable route is either aligned in public roads or government lands and thus no resumption or clearance of land is required.

 

Summary

 

The selected option has demonstrated that it is the optimum for upgrading the existing supply circuits from Pui O to Cheung Chau. In this EIA Study, the environmental impacts have been assessed to show the project can be constructed with no residual impacts.

 


 

2.2       Project Description

 

CLP proposes to establish 3 x 132 kV supply circuit from the existing Pui O Substation on south Lantau Island, via Chi Ma Wan Peninsula via Adamasta Channel towards Cheung Chau North and Cheung Chau South Substations. The proposed circuit alignment includes the following five sections as shown in Figure 2.2:

 

(i)                  Section 1: Pui O Substation to Pui O Beach using underground cable (3 x 132kV circuits of approximate length 2350m);

(ii)                Section 2: Pui O Beach to Tai Long Wan east using cable tunnel (3 x 132kV circuits of approximate length 3000m), including a small temporary works platform of 550180 m2 by the side of Pui O Wan to be used as the works area for the proposed tunnel portal;

(iii)               Section 3: Tai Long Wan to Cheung Chau Sai Tai Road using submarine cable (3 x 132kV circuits, each cable of approximate length 2300m), including a temporary landing area of about 200 m2 by the side of Tai Long Wan for transporting the tunnel boring machine off-site at once the excavation works are completed;

(iv)              Section 4: Cheung Chau Sai Tai Road to Cheung Chau South Station using underground cable (2 x 132kV circuits of approximate length 100m); and

(v)                Section 5: Cheung Chau Sai Tai Road to Cheung Chau North Station using underground cable (1 x 132kV circuit of approximate length 1250m).

 

The proposed alignment will start from Pui O Substation with underground cables along South Lantau Road and Chi Ma Wan Road to the proposed tunnel portal on the south side of Pui O Beach. The alignment will continue in a cable tunnel leading to the other end at Tai Long Wan East. The cables will be spread out by means of a number of small sections of underground cables in the Tai Long Wan portal area. 

 

For the worst case scenario 9a total of nine number of submarine cables will could be laid to Cheung Chau south across the navigation fairway of the Adamasta Channel.  It is more likely that the cables will be laid using 3 triple-core cables. The minimum distance between the cables is 50m in the worst in the worst case where nine9 separate cables are laid and will be 150m when three3 triple-core cables are laid. The selection factors forthat governs the selection of using 3 triple-core orf 9 single cables depend oninclude weight of cables, capital cost of cables, installation works and the allowance for the bending radius. The distance across the channel between the landfalls in the deepest section on Tai Long Wan and Cheung Chau is about 2300m and the water depth is around 10m. Two 132kV circuits will be connected to Cheung Chau South Substation via underground cables laid along Sai Wan Promenade.

 

The remaining single 132 kV circuit will be laid underground along Chueng Chau Sai Tai Road, Tai Hing Tai Road, Praya Street, Pak She Praya Street and connected to Cheung Chau North Substation.

 

In accordance with the definitions given in the EIAO Technical Memorandum, this project is a Designated Project under Part 1 Schedule 2, Q1.

 

2.3       Transmission Methods for the Proposedand Alternative Route Considerations

 

DifferentAs indicated in the foregoing section, as part of the Route Options Assessment, different transmission methods and alternative route optionshave been established giving due considerations to land use, technical feasibility, safety, health and environmental aspects. The preliminary route proposal as stated below had been circulated to Environmental Protection Department, Agricultural, Fisheries and Conservation Department,Planning Department,  Lands Department, Territory Development Departments and other relevant government departments and concerned parties including District Office/Islands and Green Lantau Association for comments.

 

 The following are thewere evaluated and tThe following subsection provides general descriptions of the implementation works required for constructing the proposed route. options and transmission methods being considered.

 

2.3.1  Overhead Transmission Lines

 

‘Overhead transmission lines’ is one of the most common transmission methodsare commonly used for land cables. For the proposed 3 x 132kV circuits, overhead transmission lines can be used inare proposed for the section of the route on the Chi Ma Wan Peninsula on thefor those sections from Pui O Substation to Tai Long Wan East and Ha Keng.

.

 


The overhead lines will be supported on 18m high H-poles at maximum intervals of 180m. The poles will be provided at closer distancewith a maximum interval of 180m between two poles. The poles may be closer to suit the topography and at locations where the alignment changes direction. The required horizontal separation between two 132 kV circuits is 30m. Conductors will be installed at 11.7m above ground on the H-H-poles. The transmission lines between poles, including the sag at 75°C, shallwill maintain a minimum of 6.7m above ground and 3.7m above any existing vegetation.

 

The foundations for the H-poles are generally 1.2m x 1.2m (plan) by 3m deep concrete footings. Access roads leading to the support locations for the construction of the foundations and erection of the poles can be eliminated if helicopters are employed for carrying out the works. The extent of vegetation and tree clearance required is therefore Trees to be cleared will therefore be limited to those atlimited to any trees at the site of support locations. Notwithstanding, pole locations will be selected to avoid mature trees wherever possible.Wherever possible, the design tenet will be to select pole locations which avoid mature trees.

 

2.3.12     Underground Cables

 

Electricity cables laid underground by means of open excavation are also widely used in Hong Kong. Trenches from 800 towill be either 800mm or 1200mm wide and approximately 1000 mm deep arewill be required for layingto lay the proposed 132kV cables.

 

Typically, the first two sets of cables to be laid underground will require a minimum horizontal spacing of 600mm, whilst the required separation offor the third set of cables to the first two sets is approximately 2 to 3m.

 

Other trenchless techniques such as directional drilling for laying underground cables are also practicable. These methods can apply to areas where existing underground utilities are thoroughly investigated and identified as not conflicting with the proposed cable alignments.commonly adopted. With these methods, the disturbance to residents and existing traffic to residents and existing traffic caused by the associated construction work will be reduced to the a minimum.

 

2.3.23     Cable Tunnel

 

Using tunnel to accommodateBy accommodating the transmission lines in a tunnel through the Chi Ma Wan Peninsulawill minimise the encroachmentof the cable routes on Lantau South Country Park. However, its construction costPark will be minimised.  Construction costs when compared to other options, such as overhead transmission lines and underground cables is more expensive.are greater, although environmental benefits and visual impacts are reduced.

 

  The construction methods forTwo methods for constructing the tunnel in the anticipated hard rock conditions can could be considered as both are practical.  These are:-

 

·         Drill and Blast Method; and

·         Tunnel Boring Machine (TBM) Construction

 

Drill and blast is the traditional, though relatively slow, method of constructing tunnels in rock. The vibration and noise disturbance would result in severe limitations on the extent and power permitted for the blasting. This could reduce progress rates toas slow as 30m per week.

 

TheBy Ccomparingson on the performance of TBMs to drill and blast, the former is usually considered to be better although this is governed by the hardness and mass of the rock, the power of the machine and the layout of the cutting tools. A review of similar tunnels work wide isconstruction requirements has shown that a rate of around 90m per week can be achieved once the crews have become familiar with the operation of the machine and to associated ancillary equipment.

 

The proposedsize of the tunnel is approximately 3m in diameter as shown in Figure 2.3.It will be divided longitudinally into two compartments by a partition wall.  Each compartment will be linked together by emergency access provided in every 50m. Apart fromIn addition to the major electrical and mechanical installation, the tunnel will be equipped with a ventilation system to provide cooling for the cables and to the atmosphere within the tunnel.  Fire detection systems will also be provided to detect the presence of fire in the tunnel so that for safety reasons.

 

evacuation of the tunnel can be initiated.

 

It is recommended that cables within the tunnel should be maintained with an appropriate separation to avoid the inter-circuit thermal effect.  This would be:

 

·         Typical cable to cable horizontal axial spacing: 300mm (cables in air or in stabilized sand);

·         Typical circuit to circuit horizontal axial spacing: 900mm (cables in air or in stabilized sand); and

·         Typical circuit to circuit vertical spacing: 300mm.

 

2.3.34     Submarine Cables

 

For submarine cables, the key essential issues will beissues to be addressed are the method of laying the cables, connections to landfall, the depth of burial and nature of fill. Submarine cables areIt is understood that for protection to the cables (from hazards such as anchor drag) submarine cables will normally be laid at depths of at least 3 metres below seabed. For 132kV cables, each single cable will need(or triple-core cable) needs a separation distance of approximately 50m. The depth of burial shouldmust bein a sufficient cushion thickness to give adequate protection to the cables against damage. The thicknessdamage and should be designed with consideration ofgiving due regard to vulnerability to damage, chance and consequences of damage.

 

The permanent protection for the submarine cables will depend on assessment of the chances andthe potential consequences of the load and the cost of protection. Man–made hazards such as anchor drop, anchor drag, and sunken vessels, grounding vessels and trawl boards; natural hazards such as seabed movements; waves, currents and vortex induced oscillations shouldwill need to be considered in the assessment. by the contractor.  The permanent protection proposed for this section of the route is concrete slabs, 2m x 3m x 0.3mTo indicate the location of the cables and to avoid damage during maintenance dredging a layer of concrete slabs, 2m x 3m x 0.3m will be laid over the alignment.  These will be placed either by crane from a barge (using GPS) or by diver and will eventually be covered by natural sedimentation patterns.

 

There are various methods available for laying submarine cables.  One advanced technique is by using a ‘burying machine’ which will excavate a trench and at the same time leave a cable in it.lay the cable. The cables are fed from a barge towed along the cable alignment by steel wires.  There will be no joints in the cables laid by this technique.

technique and no need for digging trenches or backfilling.

 

Prior to laying the submarine cables, detailed investigations arewill be required by the cContractor to determine seabed levels, rock head levels, mud thickness, existing utility alignments in seabed, object protrusions above the seabed such as sunken vessels and or metal objects.Hydrographic surveys are required to collect data of waves, tidal patterns, currents, winds etc.  

 

2.4              Preferred Route Option and Construction Method

 

2.4.1  Preferred Route Option

 

The Study of the Route Options Assessment has assessed four different alignment options with a mixture of transmission methods including overhead transmission lines, underground cables, submarine cables and cable tunnel for the installation of 3 x 132kV electricity circuits from Pui O Substation at Lantau south to Cheung Chau (refer to Figure 2.1).

 

These alternative alignments have been circulated to various Government departments for comments.  A set of evaluation criteria covering environmental issues, statutory requirements, traffic impacts, programme, costs etc. are established taking into account the comments received.  The evaluation process has identified the adoption of cable tunnel to cross Chi Ma Wan as the preferred option.

 

2.4.1    

Construction Method

 

(a)    Underground cables willare expected to be laid using open trench excavation method. The length of each trench is assumed not exceed 50m and no other trenches will be dug simultaneously within a 150m distance along the same road;

 

(b)    CableThe cable tunnel willbe preferably be constructed using a TBM as this is faster, has less environmental impact in terms of vibration and noise.  It does not require large volume of water to cool the working face, according to the tunnel designer as the preferred form of TBM uses recirculation of water and chillers to cool the cutting face.  This minimises the by TBM method.volume of wastewater generated which requires treatment prior to disposal. The choice of TBMmethod or the conventional drill & blast technique wouldwill depend on the final decision of the project cContractor.TBM is the favoured option (although the Contractor may choose an alternative) for excavating the tunnel. An initial tunnel drive (approx. 100m long) would be excavated from the portal using blasting or machine breaking for the erection of the TBM. Restrictions on the blasting, if blasting was adopted, would be similar to the blasting for the portal formation. NIn addition to which it should be noted that the form of construction does not require o storage of explosives overnight but rather daily delivery is expected for this Project, but rather daily delivery. The control on the use of explosives is under the Dangerous Goods Ordinance (Cap. 295) and n No further assessment has been carried out for this aspect of construction.

 

 

(c)    Submarine cables towill be laid byare expected to be laid using the direct burying method and only one submarine cable will bewith only one single cable (or triple-core cable) being laid during each operation. Thenumber of submarine power cables for this project shall be either 9 or 3 but it cannot be confirmed at this stage. It will depend on the recommendation of the submarine cable supplier. However, the worst case scenario of 9 numbers of nine separate submarine cables has been investigated in this EIA Report. The submarine cables will be covered by concrete slabs of approximate dimensions Dredging may2m(W) x 3m(L) x 0.3m(D) to indicate the location of the cable and to provide protection during dredgingas an indication of the location of the cablesas an indication protection layer.  They will be placed close to the surface of the seabed. The concrete slabs will gradually be affected by natural sedimentation patterns in the area and covered, thereby re-establishing the base stratum. Manual excavation by divers will be required at both landfalls whenwhere the water istoo shallow.

 

At the Cheung Chau Typhoon Shelter the cables will need to be passed through the breakwater which will require a section of 4.9m wide and 0.75m high to be broken out, a concrete sleeve put in place and the breakwater reinstated.  The level of the concrete sleeve is expected to be at the same level of the submarine cables (ie 3m below seabed).  The proposed partial demolition of the northern end of the South Breakwater of Cheung Chau Typhoon Shelter has been circulated to CED during the route options assessments.preliminary design of the concrete sleeve at the breakwater has been discussed with CED and Specific procedures for the partial demolition of the Pthe roceduredetails of the partial demolition of the breakwater will need to be be agreed by the contractor with with CED (although agreement in principle has been given) during the detailed design stage prior to the works commenceing on-site.  The cables can will then be passed through the breakwater from the submarine section to typhoon shelter section, by hand using qualified qualified divers for such work.

 

2.5              Schedule Programme

 

The construction programme for the proposed project has been outlined in Table 2-1 below and depicted in Figure 2.4.  The level of the concrete sleeve is expected to be at the same level of the submarine cables (ie 3m below seabed).  The preliminary design of the concrete sleeve at the breakwater has been discussed with CED and the details of the design will be agreed with CED during the detailed design stage.


 

Table 2-1         Outline Construction Programme for the Proposed Project

 

Task

No. of Weeks

Period

Tunnel Section

120

Jul 02 – Oct 04

Mobilisation and Site Clearance

4

Jul 02 – Aug 02

Site Formation at Pui O and Tai Long Wan

20

Aug 02 – Dec 02

Tunnelling

37

Dec 02 – Sep 03

Lining, Ancillary Building etc.

41

Sep 03 – Jun 04

Fitting Out and Statutory Submission

18

Jun 04 – Oct 04

Submarine Section

48

May 03 – Apr 04

Seabed Survey

10

May 03 – Aug 03

Mobilisation

13

May 03 – Aug 03

Removal of Breakwater

10

Aug 03 – Oct 03

Cable Laying

13

Nov 03 – Jan 04

Testing and Commissioning

8

Feb 04 – Mar 04

Reinstate Breakwater

8

Mar 04 – Apr 04

Underground Section

133

Feb 02 – Aug 04

South Lantau Road

26

Jul 02 – Jan 03

Chi Ma Wan Road

133

Feb 02 – Aug 04

Cheung Chau Island

26

Jan 03 – Jul 03

Testing & Commissioning for the Whole Route

8

Aug 04 – Oct 04

Testing and Commissioning

8

Aug 04 – Oct 04

Works Completed

0

Oct 04 – Oct 04

 

Installation of the proposed 132kV supply circuit from Pui O to Cheung Chau is planned to commence in mid 2002 for completion inby the end of 2004.

 

2.6       Cumulative Impacts

 

Based on the available information, it is understood that the following projects could potentially interface with this proposed 3 x 132kV supply circuits installation depending on the timing and phasing of the projects:Assignment.  These include:

 


·Highways Department’s Contract Agreement No. CE 47/96 – RPIS Minor Rural Improvement Works Package 5 IS-032 Improvement of Chi Ma Wan Road, Lantau Island (Phase I);

 

·         Highways Department’s Contract Agreement No. CE 47/96 – RPIS Minor Rural Improvement Works Package 5 IS-032 Improvement of Chi Ma Wan Road, Lantau Island (Phase I);

 and

·         Reclamation of Sai Wan Typhoon Shelter and Associated Engineering Works at Cheung Chau by Territory Development Department; and

Reclamation of Sai Wan Typhoon Shelter and Associated Engineering Works at Cheung Chau by Territory Development Department

 Department; and

 

·         220DS – Outlying Islands Sewerage Stage 1 Phase 1B - Outfall Replacement and Sewage Sludge Dewatering Facilities Upgrading at Cheung Chau Sewage Treatment Plant;

 

As this installation of the proposed underground cables will be executed under the project “RPIS Minor Rural Improvement Works Package 5 IS-032 Improvement of Chi Ma Wan Road, Lantau Island (Phase I)”, the construction activities of the Chi Ma Wan Road widening will not be implemented simultaneously at the same location as that of laying the power cables. In addition, the tunnel portal at Pui O is located over 500m from the section of Chi Ma Wan Road to be widened. As a result, no cumulative impacts are anticipated.

 

Territory Development Department (TDD) has submitted a project profile for a Study Brief fromto EPD for the project “Reclamation of Sai Wan Typhoon Shelter and Associated Engineering Works at Cheung Chau”. The tentative construction programme for this project will commence in early 2003 and be completed in 2005. However, the EIA Study is atChau (CE 66/2000)”. The construction works are expected to commence in mid 2004 for completion in 2006. This means that there will be no the preliminary stage and it is thus more appropriate that the EIA study for the reclamation works at Sai Wan takes on board the findings of this EIA Report with respect to cumulative impacts.interface with the cable laying of this Project which is scheduled to be constructed between November 2003 and January 2004. Therefore, no cumulative impact with the project CE 66/2000 is expected.

 

For the project of 220DS, it has been confirmed that the completion date for the construction works will be in early May 2002. Therefore, no cumulative impacts are expected.

 

As there is no fixed schedule fFor the maintenance dredging for Cheung Chau typhoon shelter, it is recommended confirmed that the Phase 1 maintenance works is planned to commence in December 2001 for completion in April 2002 and the Phase 2 maintenance works is planned to commence in late 2002 for completion in early 2003 (say December 2002 to April 2003).consideration be given to programming any such works to avoid overlap with the cable laying works.   After these two maintenance works, no further works are planned in the next few years.  Therefore there is no interface with this Project and no cumulative impacts are expected.

 

 

No other concurrent projects in the vicinity of the project area have been identified during the construction programme for this Project and as such no cumulative impacts are anticipated.