The Study Brief specifically requires an
assessment of the water quality, fisheries, cultural heritage, ecological
(terrestrial and aquatic), landscape and visual impacts, hazard to health and
waste management arising from the project along with an assessment of the waste
arisings. However it is recognised that
during construction there may be some impacts arising from the construction
activities such as construction dusts
and noise. This section has therefore been included to address the potential
environmental impacts including air quality and noise during the construction
phase, identify any mitigation measures necessary and to define any special
requirements during the construction phase such as monitoring and auditing or
provision of special pollution control measures. Reference is also made to the potential
issues of loss of yield relating to the Shap Long Reservoir.
Sensitive receivers (SRs) for both air
quality and noise, which have been identified within the study area of the
Project, are illustrated on Figure 3.1.
These include a few scattered village houses at Ham Tin Tsuen and Pui O Lo Wai
Tsuen on Chi- Ma- Wan Peninsula as
well as the residential buildings of Cheung Kwai Estate, Greenery Crest, village houses and the
institution of Buddhist Wai Yan Memorial College along the west coast of Cheung
Chau Island. No sensitive receiver was
identified within an area of 500m radius in the vicinity of the Tai Long Wan tunnel
portal. Descriptions of the representative
sensitive receivers are presented in Table 3-1.
Table 3-1 Summary
of the Representative Sensitive Receivers (Air and Noise)
SRs |
Location |
Usage |
Closest
Distance (m) |
Pui O, Lantau |
|||
SR1 |
Pui O Lo Wai Tsuen |
Village House |
20 |
SR2 |
Ham Tin Tsuen |
Village House |
10 |
SR3 |
Ham Tin Tsuen |
Village House |
20 |
SR4 |
Hostel (Lot No. 27) in the
vicinity of Pui O tunnel portal |
Hostel |
40 |
Cheung Chau |
|||
SR5 |
Greenery Crest |
Residential |
30 |
SR6 |
Buddhist Wai Yan Memorial College |
Institution |
10 |
SR7 |
Village house at Pak She Praya
Street |
Village House |
10 |
SR8 |
Cheung Kwai Estate |
Residential |
50 |
The
potential air quality impacts associated with the installation of the 3 x 132 kV
circuits from Pui -O
via Chi -Ma -Wan
Peninsula via the
Adamasta Channelsea crossing towards Cheung Chau have
been considered for the land based section of the works only although they
are not required under the Study Brief. For the section of submarine cables,
construction dust impact will not be expected.
For the remaining section, dust generation as a result of earth
excavation is the major source of air pollution during the construction phase. Following completion of construction works
there will be no adverse environmental impact. Suitable mitigation measures,
where necessary, are recommended to protect the ASRs and to ensure that the
legislative criteria and guidelines are satisfied.
The principal legislation that is
relevant to air pollution from construction sites is the Air Pollution Control
Ordinance (APCO) (Cap. 311). Relevant
Air Quality Objectives for Total Suspended Particulates (TSP) and Respirable
Suspended Particulates (RSP) extracted from EIA-TM are tabulated presented below in Table 3-2 below.
For construction dust, EIA-TM also recommends a maximum hourly level of 500
µg/m3 for TSP at nearby Air Sensitive Receivers (ASRs).
Table 3-2 Hong Kong Air Quality Objectives
Averaging
Time |
Pollution
Concentration Level (µg/m3 ) |
|
TSP |
RSP |
|
1 hour1 |
500* |
N.A. |
24 hour2 |
260 |
180 |
Annual3 |
80 |
55 |
Notes:
(1) Not to be exceeded more than
three times per year.
(2) Not to be exceeded more than
once per year.
(3) Arithmetic means.
N.A. Not Available
* Maximum allowable dust levels at
ASRs provided in the EIA-TM.
The existing environment of the proposed cable alignment is primarily affected by the traffic on Pui O such as South Lantau Road and Chi Ma Wan Road, as well as on Cheung Chau such as Cheung Chau Sai Tai Road, Tai Hing Tai Road, Praya Street and Pak She Praya Street. No industrial source has been identified in the area. As such, the local traffic is considered to be the dominant source affecting the ambient air quality.
As tThe
proposed project is on Lantau Island and the , there
is currently one fixed
air quality monitoring station is currently operated by EPD in Tung Chung, which is the closest monitoring
station to this Project, has been used to obtain dlocated
in Tung Chung. ata reported
for the year 1999. These
data are contained in Table
3-3 for The key
parameters for pollutants – Total Suspended Particulates (TSP) and Respirable
Suspended Particulates (RSP) data reported
for the year 1999 at this station is givendemonstrated in Table 3-3.
Table
3-3 Annual Average of TSP and RSP
Monitored at Tung Chung in 1999
Air Pollutants |
Annual Average (µg/m3) |
TSP |
75 |
RSP |
48 |
Dust, in relation to the construction of
underground cable, cable tunnel and submarine cable, will be generated from
blasting, reclamation, excavation, filling, material handling and vehicular
movements on unpaved work sites and found to be are the
main sources of dust. No batching plant
will be is required
to be established on-site. Major worksites have been identified along the
alignment and shown in Figure 3.2. Activities to be undertaken at the worksites
are discussed below.
Construction of Underground Cable
Dust
generation during the construction of the underground cable is mainly
arisesd
from the excavation of
the trench along the routeworksite.
Construction of Cable Tunnel
The
Chi -Ma -Wan
cable tunnel is expected towill
be excavated by drill and blast method or tunnel boring machine (TBM) over a period of
3480
weeks with 25,000 Mm3
of spoil being generated, or by drill and blast technique (alternative
method). Two possible worksites, the
northern portal area in Pui O Wan and southern portal area in Tai Long Wan
East, have been identified for the tunneling works. At both end portals in
Pui O Wan and Tai Long Wan East, theThe excavated spoils from thePui O tunnel portal are expected to
will be transported
away by trucks. trucks while
those extracted from Tai Long Wan tunnel portal are expected towill be disposed by
barges using the temporary landing area after the
tunnel has been drivlled throughn.
Construction of
Submarine Cable
For the section
of submarine section,cables, no adverse dust impacts are expected.
Dispersion Model
The
extent of dust impacts arising from the construction of project has been
predicted using the USEPA approved model Fugitive Dust Model (FDM) in
conjunction with the construction programme. The Compilation of Air Pollutant Emission Factors, 5th Edition, US
Environmental Protection Agency, 19956, (AP-42)
was used to determine the various fugitive dust sources.
Meteorological Data Input
Sequential meteorological data for 1999 from Cheung Chau and King’s Park weather stations, operated by Hong Kong Observatory, was used as input to the model to obtain 1-hour and 24-hour average TSP concentration at the identified ASRs. Data obtained from Cheung Chau and King’s Park stations used as input to the model includes wind direction and speed together with atmospheric Pasquill stability class, mixing heights and air temperature.
Emission Factors
Emission factors, for various fugitive dust
sources have been determined based on the USPEPA Compilation of
Air Pollution Emission Factors, 5thth Edition
(AP-42). Emission factor for typical construction operations given in the USPEPA is 1.2 tons per
acre of construction per month of activity (296.5 g/m2/month). The emission factors used for carrying out
the modelling are summarised in Table
3-4. Dust emission factor of 3.2 x
10-4 g s-1 m-2 was obtained by converting the
above emission factor based on 26 working day per month and 10 operation hours
per day. Calculations of the emission factors are given in Appendix A.
The dust emission from the construction of underground cable and cable tunnel is associated with blasting, excavation, material handling and vehicle movement on unpaved road. The emission factor for general construction is illustrated in Table 3-4 below.
Table 3-4 Emission
Factors for General Construction Activities
Activities |
Emission Factors |
Remarks |
General Construction |
3.2 x 10-4 g s-1 m-2 |
Based on USEPA AP-42 Vol. 1 5th Edition, Section 13.2.3 |
Prediction of 1-hour TSP Levels
It
was assumed that construction would take place over ten hours per day. The corresponding meteorological data has
thus been used as input to the FDM. The highest predicted TSP levels were
obtained and compared with the recommended 1-hour limit of 500 mgm-3.
Prediction
of 24-hour TSP Levels
As the time variation of dust emissions is not considered in the FDM, the daily TSP levels for daytime construction activities are therefore determined by simulating the model with the default option of an 8-hour averaging period. Meteorological data was used for the period 0900 – 1700 hours. The 24-hour TSP level was then estimated by multiplying the modeled results by a conversion factor (8 hours out of 24 hours = 1/3) to take account of the 8-hour construction period, i.e. one-third of the 8-hour TSP levels predicted from the model. The predicted 24-hour TSP levels from daytime activities and the background daily TSP level were added together and compared with the AQO of 260 mgm-3.
Construction dust impacts were modelled using the Fugitive Dust Model (FDM) with worst case assumptions as input data and at ground level. Predicted hourly and daily TSP levels at the identified ASRs are shown in Table 3-5 below. The background annual average TSP levels of 75 mgm-3 extracted from EPD’s Tung Chung Air Quality Monitoring Station has been added to the predicted hourly and daily results to provide the cumulative impact.
Table 3-5 Predicted
Hourly and Daily TSP Levels (mmgm-3) – Without Mitigation
ASR |
Area |
Location |
|
|
|
Pui O, Lantau |
Pui O Lo Wai Tsuen |
161 |
83 |
SR2 |
|
Ham Tin Tsuen |
184 |
83 |
|
|
Ham Tin Tsuen |
254 |
87 |
|
|
Hostel (Lot No. 27) |
591 |
98 |
|
Cheung Chau |
Greenery Crest |
154 |
82 |
SR6 |
|
Buddhist Wai Yan Memorial
College |
212 |
83 |
SR7 |
|
Village House along Pak She
Praya Street |
226 |
86 |
SR8 |
|
Cheung Kwai Estate |
169 |
79 |
Dust Criteria |
500 |
260 |
||
Notes: (1)
Background
TSP level is included in the results. (2) |
As
indicated in Table 3-5, the
predicted 24-hourly and daily1-hour TSP concentration levels
at all the ASRs except
for SR4 are complyied with
the AQO criteria of 500260
mmgm-3 and 260500
mmgm-3
respectively duringusing
underground cable and cable tunnel construction.
Owing to the close proximity of the hostels (approx.
70m) to the Pui O tunnel portal
area and the temporary working platform, exceedance of hourly TSP at SR4 was predicted. In
order to reduce the adverse dust impact during construction, dust suppression
control measures such as regular watering are recommended. A dust
reduction efficiency of 50% can be practically achieved by applying watering twice a day.
With the implementation of the recommended
mitigation measures, the mitigated hourly and daily TSP concentration levels
were
predicted and the results are presented in Table 3-6.
Table 3-6 Predicted
Hourly and Daily TSP Levels (mgm-3) – With
Mitigation
ASR |
Area |
Location |
Hourly Average TSP
Level(1) |
Daily Average TSP
Level(1) |
SR1 |
Pui O, Lantau |
Pui O Lo Wai Tsuen |
118 |
79 |
SR2 |
|
Ham Tin Tsuen |
130 |
79 |
SR3 |
|
Ham Tin Tsuen |
164 |
81 |
SR4 |
|
Hostel (Lot No. 27) |
333 |
87 |
SR5 |
Cheung Chau |
Greenery Crest |
115 |
79 |
SR6 |
|
Buddhist Wai Yan
Memorial College |
144 |
79 |
SR7 |
|
Village House along
Pak She Praya Street |
151 |
81 |
SR8 |
|
Cheung Kwai Estate |
122 |
77 |
Dust Criteria |
500 |
260 |
||
Notes: (1) Background TSP level is included in the
results. |
In Table 3-6, the predicted hourly and daily TSP concentration levels
at all the ASRs are well below the AQO criteria.
In addition,
According to the contour plots of mitigated 1-Hhourly and daily TSP concentrations are
presented as
shown in Figures 3.4
and 3.5
respectively., Nno exceedances of
AQO
criteria at the sensitive uses are identified. Therefore, no residualadverse construction
dust impacts areis
expected.
The input and output files of the FDM Model for the dust assessment during construction phase are provided in Appendix B.
The construction works
at the Pui O tunnel portal are likely to cause Construction dust
impact on the nearby
ASR if no mitigation measures are in place from the above limited
construction works would unlikely to be of a concern. However, the construction dust
impact can be reduced to an acceptable level with the implementation of dust
control measures. Both general and specific mitigation measures are recommended to
ensure no adverse air quality impact during construction phase.
Specific
Dust suppression efficiency
of 50% can be
achieved by applying watering twice a day.
General
Nevertheless,
tThe following control measures are stipulated in the
Air Pollution
Control (Construction
Dust) Regulation and should be implemented to minimise the dust nuisance.
·
the stockpile should be properly treated
and sealed with latex, vinyl, bitumen or other suitable surface stabiliser if a
stockpile of dusty materials is more than 1.2m but lessmore than 1.2m
high and lies within 50m from any site boundary that adjoins a road, street, or
other area accessible to the public;
·
effective dust
screens, sheeting or netting should be provided to enclose the scaffolding from
the ground floor level of the
building or if a canopy is provided at the first floor level, from the first
floor level, up to the highest level of the scaffolding where a scaffolding is
erected around the perimeter of a building under construction;
·
dump truckskip hoist for material transport should be
totally enclosed by impervious sheeting;
·
any excavated dusty
materials or stockpile of dusty materials should be covered entirely by
impervious sheeting or sprayed with water so as to maintain the entire surface
wet, and recovered or backfilled
or reinstated within 24 hours of the excavation or unloading;
·
stockpile of dusty
materials should not extend beyond the pedestrian barriers, fencing or traffic
cones;
·
dusty materials
remaining after a stockpile is removed should be wetted with water and cleared
from the surface of roads;
·
vehicle washing
facilities should be provided at every vehicle exit point;
·
the area where
vehicle washing takes place and the section of the road between the washing
facilities and the exit point should be paved
with concrete, bituminous materials or hardcores;
·
where a site
boundary adjoins a road, streets or other area accessible to the public,
hoarding of not less than 2.4m high from ground level should be provided along
the entire length except for a site entrance
or exit;
·
every main haul road
should be scaled with concrete and kept clear of dusty materials or sprayed
with water so as to maintain the entire road surface wet;
·
the portion of road
leading only to a construction site that is within 30m of a designated vehicle
entrance or exit should be kept clear of dusty materials;
·
every stock of more
than 20 bags of cement should be covered entirely by impervious sheeting or
placed in an area sheltered on the top and the 3 sides;
·
cement delivered in
bulk should be
stored in a closed silo fitted with an audible high level alarm which is
interlocked with the material filling line such that, in the event of the silo
approaching an overfilling condition, an audible alarm is triggered and the
material filling stops
within one minutes;
·
silo used for the
storage of cement not be overfilled;
·
loading, unloading,
transfer, handing or storage of bulk cement or any cement during or after the
de-bagging process should be carried out in a totally enclosed system or facility, and any vent
or exhaust should be fitted with an effective fabric or equivalent air
pollution control system or equipment;
·
cement, or any other
dusty materials collected by fabric filters or other air pollution control
system or equipment should be disposed
of in totally enclosed containers;
·
stockpile of dusty
materials should be either covered entirely by impervious sheeting, placed in
an area sheltered on the top and the 3 sides; or sprayed with water so as to
maintain the entire surface wet;
·
all dusty materials
should be sprayed with water prior to any loading, unloading or transfer
operation so as to maintain the dusty material wet;
·
vehicle speed should
be limited to 10 kph except on completed access roads;
·
every vehicle should
be washed to remove
any dusty materials from its body and wheels before leaving the construction
sites;
·
the load of dusty
materials carried by vehicle leaving a construction site should be covered
entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the
vehicle;
·
the working area of
excavation should be sprayed with water immediately before, during and
immediately after the operations so as to maintain the entire surface wet;
The following control measures are recommended during blasting of works:
·
the area within 30m
from the blasting area shall be wetted with water
prior to blasting;
·
blasting shall not be carried out
when the strong wind signal or tropical cyclone warning signal No. 3 or higher
is hoisted unless prior permission of
the Commissioner of Mines is obtained.
·
wire mesh, gunny sacks and sandbags should be used on
top of the blast area at each shot to prevent flying rock and dust;
·
water the surface of the blast area to increase its
moisture content;
·
dust filters should be fitted to the tunnel
construction ventilation systems;
·
vents of all silos and weighing scale shall be fitted
with fabric filtering system; and
·
seating of pressure relief valves of all silos shall be
checked, and the valves resealed if necessary, before each delivery.
Material Handling
·The height from
which fill materials are dropped should be controlled to a minimum practical
height to limit fugitive dust generation from unloading;
·Any stockpiles
of aggregate or spoil should be covered and water applied;
·Water spray
should be used during the handling of excavated and fill material where dust is
likely to be created; and
·All dusty
materials should be sprayed with water immediately prior to any loading,
unloading or transfer operation so as to maintain moisture content of the dusty
materials.
Earthworks
·The amount of
exposed soil should be kept in minimal by re-vegetation of completed
earthworks.
No residual air quality impact is
expected.
Full compliance with the AQOs during construction will likely achieved at all air sensitive receivers without the requirements of mitigation measures. Therefore, routine dust monitoring during construction is not required but regular site audits are recommended to be conducted to ensure the implementation of good site practice and appropriate mitigation measures.
A quantitative
assessment on the construction dust impacts has identified that fugitive dust
is the primary potential air pollutant during the proposed works. The
assessments have demonstrated that apredicted an exceedance of hourly TSP
dust criteria
at the hostel, SR4, was predictedimpact
will be minimal. for the
situation where no mitigation measures were in place. Wwith the
application of the established and practical dust
suppression techniques such as regular watering twice a day, covering/dampening any
stockpiles and dampening dusty materials before transportation and the control
measures stipulated in the Air Pollution Control (Construction Dust) Regulation, the construction dust impacts can be reduced by more than
50% to an
acceptable level. No residual air quality
impact Through the proper implementation of the
recommended mitigation measures, dust generation will be further controlled and
exceedance of the acceptable criteria is not expected. As a result, no routine air quality
monitoring is recommended.
that
baseline dust monitoring and dust impact monitoring is carried out prior to and
during the construction works.
This section presents an assessment of the potential noise impact
associated with the installation of the 3 x 132 kV circuit
from Pui -O
via Chi -Ma -Wan
Peninsula via Sea Crossing towards Cheung Chau. The quantitative assessment
methodology which has been adopted is presented and control measures, to ensure
the effective protection of the identified sensitive receivers, are
recommended.
General Construction Works
In Hong Kong, construction noise within
“restricted hours” (i.e. between 19:00 to 07:00 hours from Monday to Saturday
and any time on public holidays) is controlled under the Noise Control
Ordinance (NCO) (Cap. 400) and the relevant Technical Memoranda (TMs) issued by
the Environmental Protection Department (EPD) through a Construction Noise
Permit (CNP) system.
If construction works are carried out
during “restricted hours”, a CNP has to be obtained from EPD allowing 28 days
for the application to be processed. In addition, any percussive piling work
can only be carried out with a valid CNP issued by the Authority. The TMs classify a variety of uses including
domestic premises, hostel and place of public worship as noise sensitive
receivers (NSRs).
The Noise Control Authority will consider a
well-justified CNP application, once fielde, for construction works within
restricted hours as guided by the relevant Technical Memorandum issued under
the Noise Control Ordinance. The Noise
Control Authority will take into account of contemporary conditions/situations
of adjoining land uses and any previous complaints against construction
activities at the site before making his decision in granting a CNP. Nothing in this EIA Report shall bind the
Noise Control Authority in making his decision. If a CNP is to be issued, the Noise Control Authority shall
include in it any condition he thinks fit.
Failure to comply with any such conditions will lead to cancellation of
the CNP and prosecution action under the NCO.
Although the
TMs do not provide any statutory control over construction noise during the
“non-restricted hours”, a limit of Leq(30min) 75 dB(A) is proposed
for all domestic premises including temporary housing accommodation in the
“Practice Note for Professional Person, PN2/93” issued by the Professional
Persons Environmental Consultative Committee in June 1993. For schools, the recommended noise levels
during normal schools days is Leq(30min) 70 dB(A) and is lowered to
Leq 65 dB(A) during examination periods. These limits have been
applied on major construction projects and are now widely accepted in Hong
Kong. The same noise criteria are stipulatedcan be found
in Table 1B Noise Standards for Daytime Construction Activities in the gazetted
Technical Memorandum on EIA Process issued under Section 16 of the EIA
Ordinance which also specify the relevant noise standards for hotels and
hostels as shown in Table 3-76.
Table 3-76 Noise
Standards for Daytime Construction Activities
Uses |
0700 to 1900
Hours on Any Day Not Being a Sunday or General Holiday Leq
(30 mins) dB(A) |
1900
to 0700 Hours or Any Time on Sundays or General Holidays |
All
domestic premises including temporary housing accommodation |
75 |
See Note (iii) |
Hotels
and hostels |
75 |
|
Educational
institutions including kindergartens, nurseries and all others where unaided
voice communication is required |
70 65 (during examinations) |
|
Notes
:
(i)
The above standards apply to uses which rely on
opened windows for ventilation;
(ii)
The above standards shall be viewed as the
maximum permissible noise levels assessed at 1m from the external facade;
(iii)
The criteria laid down in the relevant technical
memorandum under the Noise Control Ordinance for designated areas and
construction works other than percussive piling may be used for planning
purpose. A Construction Noise Permit
(CNP) shall be required for the carrying out of the construction work during
the period.
(Source : Table 1B of Technical Memorandum on EIA Process.)
The existing noise environment is dominated by road
traffic. Pui O such as South Lantau
Road and Chi Ma Wan Road, as well as Cheung Chau such as Cheung Chau Sai Tai
Road, Tai Hing Tai Road, Praya Street and Pak She Praya Street are the major
sources of road traffic noise. No industrial
source has been identified in the area and noise from traffic mainly
contributes to the daytime and nighttime background noise levels in the area.
The existing noise environment at
Pui O, Lantau is dominated by road traffic. South Lantau Road and Chi Ma Wan
Road are the major sources of road traffic noise. Sometimes
the sea wave may generate a high background noise level.
In Cheung Chau, there isare no vehicular roads for
automobiles so the
major noise sources come
from commercial activities and the community. During holidays, the background noise is always
higher as many tourists
visit Cheung Chau hosts many visitors.
Various construction activities have been identified which could cause elevations in noise levels at the nearby NSRs. A typical construction programme for Pui O via Chi Ma Wan via Sea Crossing towards Cheung Chau, has been developed which is shown in Figure 2.4. It is recognised that the Contractor may develop a different construction programme and construction method from the one presented in this report, however it will be his responsibility to demonstrate that his methods ensure compliance with the criteria stipulated in the preceding sections.
As indicated in the preliminary construction programme, the main construction activities comprise:
·
installationconstruction of underground cable;
· construction of cable tunnel; and
· laying of submarine cable.
Installation of Underground
Cable
The main construction activities include road breaking, trench excavation, cable laying, backfilling, removal of debris and road paving.
Construction activities at this project are expected to operate during normal daytime working hours (i.e. 0700 to 1900 hours on any day but not being a Sunday or public holiday).
A plant
inventory has been established based on previous relevant highway project
experience and is presented in Table 3-87.
Table 3-78 Powered Mechanical Equipment Used (Underground Cable)
Activity |
PME
Employed |
Identification
Code |
Sound
Power Level dB(A) |
Road Breaking |
Air Compressor |
CNP 001 |
100 |
Hand-held Breaker |
CNP 023 |
108 |
|
Dump Truck |
CNP 067 |
117 |
|
Backhoe |
CNP 081 |
112 |
|
Trench Excavation |
Backhoe |
CNP 081 |
112 |
Road Reinstatement |
Compactor |
CNP 050 |
105 |
Concrete Lorry Mixer |
CNP 044 |
109 |
|
Vibratory Poker |
CNP 170 |
113 |
As mentioned previously, Cheung Chau does not
possess vehicular access for automobiles, no dump trucks and or backhoes are expected to be used for
installing underground cables. Trolleys areis expected to
be employed for transporting the excavated materials.
ConstructionInstallation of
Cable Tunnel
The Chi Ma Wan Peninsula cable Ttunnel areis expected willto be excavated preferably by
a tunnel boring machine or possibly using or the
drill and blast method. Temporary works areas The tunnel portals will be located at
two possible worksites will locate at, the northern
portal area in Pui O Wan and the
southern portal area in Tai Long Wan East respectively.
Tunnel excavation works are expected to take place during normal daytime
working hours (i.e. 0700 to 1900 hours on any day not being a Sunday or public
holiday) for the first 100m. Beyond
this initial length, 24-hour working is expected which is normal practice in
tunnel construction and provides optimal programming and use of resources.
During restricted hours the construction activities will be contained within the tunnel and tunnel portal blast doors will be closed. All materials excavated during restricted hours will be stockpiled within the tunnel or at the tunnel portal and will be removed only during normal working hours. These measures will significantly reduce noise emissions associated with construction of the tunnel therefore no noise impacts from the nighttime construction of the tunnel are anticipated.
In Pui O Wan, the excavated spoil from the tunnel
will be transported away by trucks. At the
southern portal area in Tai Long Wan East, about 25,000 Mm3 of spoil will be excavated and transported
off-site by truck.barges.
A plant
inventory has been established by the tunnel designer and is presented in Table 3-98.
Table 3-98 Powered Mechanical Equipment Used
for Tunnel Construction
Activity |
PME
Employed |
Identification
Code |
Sound
Power Level dB(A) |
General |
Loader |
CNP 081 |
112 |
Backhoe / Muck Car |
CNP 081 |
112 |
|
Concrete Lorry Mixer |
CNP 044 |
109 |
|
Mobile Crane |
CNP 048 |
112 |
|
Dump Trucks |
CNP 067 |
117 |
|
Concrete Pump |
CNP 047 |
109 |
|
Mobile generator |
CNP 101 |
108 |
|
Compressor |
CNP 002 |
102 |
|
Water Pump |
CNP 281 |
88 |
|
Ventilation Fan |
|
|
|
Site Formation |
Rock Drill (Hydraulic) |
CNP 182 |
123 |
Shotcrete Vehicle |
CNP 047 |
109 |
|
Explosive Delivery Vehicle |
CNP 141 |
112 |
|
TBM Tunnel Construction ( |
Tunnel Boring Machine |
- |
88 |
Conveyor Belt System |
CNP 041 |
90 |
|
Drill & Blast Tunnel Construction
(Alternative |
Rock Drill (Hydraulic) |
CNP 182 |
123 |
Conveyor Belt System |
CNP 041 |
90 |
|
Shotcrete Vehicle |
CNP 047 |
109 |
|
Explosive Delivery Vehicle |
CNP 141 |
112 |
|
Lining Construction |
Concrete Delivery Truck |
CNP 141 |
112 |
Pumping Plant |
CNP 047 |
109 |
TAs Tthe
lining construction
of the tunnel will take place inside behind the tunnel so the noise impact for this activity does
not needs
to be assessed.“portal”, no noise impact is expected and therefore
this activity has not been assessed.
As there is no noise
sensitive receiver at Tai Long Wan, the noise impact
for delivery by barge does not need to be assessed.
construction will take place inside the tunnel so
the noise impact for this activity is required to be assessed.
LayingInstallation of Submarine Line
The major vessels that will be employed for laying
the submarine cables including lay barge, tugb
boat, warning boat, pontoon barge and floating crane, etc. The proposed PMEs
will be used for the installation of submarine cables are given in Table 3-10.
Table 3-10 Powered
Mechanical Equipment Used (Submarine Cable)
Activity |
PME Employed |
Identification Code |
Sound Power Level dB(A) |
Laying
Submarine Cable |
Lay Barge |
CNP 061 |
104 |
Tub Boat |
CNP 221 |
110 |
|
Warning Boat |
CNP 061 |
104 |
|
Pontoon Barge |
CNP 061 |
104 |
|
Floating Crane |
CNP 048 |
112 |
Construction
works under water, an adverse noise impact on the nearby village houses would
not be expected. Therefore, no detailed assessment is required.
The major
vessels that will be employed for laying the submarine cables including lay
barge, tugb boat, warning
boat, pontoon barge and floating crane, etc. The proposed PMEs will be used for
the installation of submarine cables are given in Table 3-109.
Table 3-109 Powered
Mechanical Equipment Used (Submarine Cable)
According to
the GW-TM, the notional source postionposition of the employed PME
for laying the submarine cables will be taken to be a
point 50m from the promenatepromenade at Cheung Chau.
Therefore, the distance between the PME and the closest noise sensitive
receiver is expected to be over 100m and any noise
generated will be attenuated by distance.
It should also be noted that in the typhoon shelter, the laying of
cables will be completed by divers due to the physical constraints of walking
within this confined area.As stated in Section
2 the cables will be laid by diver in the typhoon shelter and PME is not
expected to be used. The distance
between the PME and the closest noise sensitive receiver is expected to be over
300m
and thus as noise will be attenuated to acceptable levels. No further assessments of the noise from
laying submarine cables has been carried out.
A methodology for assessing construction noise other than percussive piling has followed the guidelines set out in the Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM). The methodology is as follows:
·
identify
the likely type, sequence and duration of principal noisy construction
activities required for the implementation of the proposed project;
·
identify a
list of plant inventory likely to be required for each construction activity;
·
calculate
the maximum total sound power level (SWL) for each construction activity using
the plant list and SWL data given for each plant in the technical memorandum;
·
·representative
NSRs as defined by the EIAO-TM have been identified, based on
existing and committed landuses in the study area that may be affected by the
worksite. For the purposes of this
study, NSRs have been identified up to a distance of 300m from the
alignment. However, this distance may
be reduced, subject to the first layer of NSRs providing adequate acoustic
shielding;
·
calculate
the distance attenuation and barrier corrections to NSRs from worksite notional
noise source point; and
·
predict
construction noise levels at NSRs in the absence of any mitigation measures.
If the noise assessment criteria are exceeded at NSRs, mitigation measures must be considered. A re-evaluation of the total SWL for each construction activity will be made assuming the use of practical mitigation measure such as “quiet” equipment and movable noise barriers. If the criteria were still exceeded, further mitigation measures such as reduction in noisy plant working simultaneously would be considered.
As there is no noise sensitive receiver within 300m from the work site at Tai Long Wan tunnel portal, no construction noise impact generated from this work site is required to be assessed.
The unmitigated noise levels associated with the installation of 3 x
132kV supply circuit from Pui O via Chi Ma Wan Peninsula via sea crossing
towards Cheung Chau has been predicted for the worst case representative NSRs
for each construction activities and the results are summarised in Table 3-11.. Details and of the calculation are summarised in Table 11 as well as
contained provided in
Tables C-1 and C-2 of Appendix C, and takinge into account of
noise attenuation over distance.
Table 3-11C-2 in Appendix
C indicates that the cumulative construction
noise impact of unmitigated construction activities associated with
installation of underground cable and construction of cable tunnel would cause
exceedance of the daytime construction noise criterion at majority of the NSRs,
up to 8892dB(A) at SR2, Pui O Lo Wai Tsuen. Mitigation
measures are therefore required for these NSRs in order to alleviate the noise
impacts generated from installation of the underground cable and
construction of cable tunnel during the construction phase.
Table 3-11 Predicted Noise Level at Representative Noise
Sensitive Receivers -– Without Mitigation (Leq30min
dB(A))Unmitigated
i(
|
Predicted
Noise Level,
|
|||||||
NSR(s) |
Pui
O, Lantau |
Cheung
C |
||||||
|
SR1 |
SR2 |
SR3 |
SR4 |
SR5 |
SR6 |
SR7 |
SR8 |
Daytime Construction Noise Criteria
dB(A) |
75 |
75 |
75 |
75 |
75 |
70 |
75 |
75 |
1. Installation of Underground Cable |
||||||||
Road Breaking |
8 |
92 |
86 |
80 |
|
|
|
70 |
Trench |
8 |
87 |
81 |
75 |
N.A. |
N.A. |
N.A. |
N.A. |
Road Reinstatement |
8 |
88 |
82 |
76 |
78 |
88 |
88 |
74 |
2. Construction of Cable Tunnel |
||||||||
General |
N.A. |
N.A. |
N.A. |
79 |
N.A. |
N.A. |
N.A. |
N.A. |
Site
Formation |
N.A. |
N.A. |
N.A. |
82 |
N.A. |
N.A. |
N.A. |
N.A. |
TBM |
N.A. |
N.A. |
N.A. |
50 |
N.A. |
N.A. |
N.A. |
N.A. |
Drill
& Blast |
N.A. |
N.A. |
N.A. |
82 |
N.A. |
N.A. |
N.A. |
N.A. |
Tunnel Lining |
N.A. |
N.A. |
N.A. |
72 |
N.A. |
N.A. |
N.A. |
N.A. |
General
+ Site Formation/Drill &
Blast |
N.A. |
N.A. |
N.A. |
84 |
N.A. |
N.A. |
N.A. |
N.A. |
3. Cumulative Impact |
86 |
92 |
86 |
85 |
78 |
88 |
88 |
74 |
* Bolded value means PNL exceeds the daytime
construction noise criteria
* Bolded
value means PNL exceeds the daytime construction noise criteria
Mitigation measures for each construction site are detailed below, and the following forms of mitigation measures are recommended and should be incorporated into the Contract Specifications:
·
good site
practice to limit noise emissions at source
·
selection
of quieter plant and working methods
While it is recognised that the Contractor may develop a different package of mitigation measures to meet the required noise standards, the following suite of practical and implementable measures demonstrate an approach that would be feasible to reduce noise to acceptable levels.
Good
Site Practice
Good site
practice and noise management can significantly reduce the impact of
construction site activities on nearby NSRs.
The following package of measures should be followed during each phase
of construction :
·
only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction works;
·
machines
and plant that may be in intermittent use should be shut down between work
periods or should be throttled down to a minimum;
·
plant known
to emit noise strongly in one direction, should, where possible, be orientated
to direct noise away from the NSRs;
·
mobile
plant should be sited as far away from NSRs as possible; and
·
material
stockpiles and other structures should be effectively utilised, where
practicable, to screen noise from on-site construction activities.
Selecting Quieter Plant and
Working Methods
The Contractor
may be able to obtain particular models of plant that are quieter than
standards given in GW-TM. Benefits
which can be achieved through this approach will depend on the details of the
Contractor chosen methods of working.
As it is considered too restrictive to define specific items of plant
for the construction operations, it is more practical to specify an overall
plant noise performance specification to apply to the total SWL of all plant on
the site so that the Contractor is allowed some flexibility to select plant to
suit his needs.
The nature of the construction noise
sources of the project allows the introduction of a wide range of possible
mitigation measures. Commonly used
noise mitigation measures include:
·
Application
of properly designed silencers, mufflers, acoustically dampened panels and
acoustic sheds or shields, etc.;
·
Use of
electric-powered equipment where applicable instead of diesel-powered or
pneumatic-powered equipment;
·
Erecting
noise enclosures around noisy plants;
·
Location of
noise emitting plants at maximum possible distances from sensitive receivers;
·
Contractual
clauses for construction works;
·
Schedule of
noisy operations during non-restricted hours;
·
Regular
maintenance of site plant/ equipment; and
·
A temporary
cantilevered barriers of 4m high is proposed to be erected at the tunnel portal
area in order to alleviate the construction noise impact by blocking the line
of view from the nearby receivers. The
material needs to have a surface density (>7 kg/m2) to provide
sufficient screening effect (approx. 10 dB(A)).
Mitigation
Measures during blasting of works (specific)
·
Tunnel
portal doors should be closed when the construction activities carried out
within the tunnel
1st
Level of Mitigation Measure
Tables C-3 and C-4 ofin Appendix C indicated that
wWith the use of quiet plant under the
installation of underground cable and construction of cable tunnel, the cumulative construction
noise impact at NSRs (i.e.
SR1, SR2, SR3, SR4 and SR7) would slightly still exceed
the daytime noise criterion (i.e. 75dB(A) for residential use) by up to 82 dB(A) as shown in Table
3-12 at NSRs (i.e. SR1, and SR2, SR3, SR4 and SR7).
Due to the close proximity to the construction works, SR5
the Buddhist Wai Yan Memorial College (SR6) would be adversely affected and the
predicted noise levels would exceed the daytime noise criterion (i.e. 70dB(A)
for schoolsinstitutional
use) by 133dB(A).
Additional mitigation measures are therefore required to further reduce noise
to acceptable levels. See Table
12.Details of the
calculation are provided in Tables C-3 and C-4 of Appendix C.
Table 3-12 Predicted Noise Level at Representative Noise Sensitive Receivers –
With Use of Quiet Plant (Leq30min dB(A))
|
Predicted Noise Level, dB(A) |
|||||||
NSR(s) |
Pui O, Lantau |
Cheung Chau |
||||||
|
SR1 |
SR2 |
SR3 |
SR4 |
SR5 |
SR6 |
SR7 |
SR8 |
Daytime
Construction Noise Criteria dB(A) |
75 |
75 |
75 |
75 |
75 |
70 |
75 |
75 |
1.
Installation of Underground Cable |
||||||||
Road
Breaking |
77 |
83 |
77 |
72 |
74 |
83 |
83 |
69 |
Trench
Excavation |
74 |
80 |
74 |
69 |
N.A. |
N.A. |
N.A. |
N.A. |
Road
Reinstatement |
74 |
80 |
74 |
69 |
70 |
80 |
80 |
66 |
|
||||||||
|
||||||||
2.
Construction of Cable Tunnel |
||||||||
General |
N.A. |
N.A. |
N.A. |
72 |
N.A. |
N.A. |
N.A. |
N.A. |
Site
Formation |
N.A. |
N.A. |
N.A. |
81 |
N.A. |
N.A. |
N.A. |
N.A. |
TBM |
N.A. |
N.A. |
N.A. |
50 |
N.A. |
N.A. |
N.A. |
N.A. |
Drill
& Blast |
N.A. |
N.A. |
N.A. |
81 |
N.A. |
N.A. |
N.A. |
N.A. |
Tunnel
Lining |
N.A. |
N.A. |
N.A. |
65 |
N.A. |
N.A. |
N.A. |
N.A. |
General
+ Site
Formation/Drill & Blast |
N.A. |
N.A. |
N.A. |
82 |
N.A. |
N.A. |
N.A. |
N.A. |
3.
Cumulative Impact |
77 |
83 |
77 |
82 |
74 |
83 |
83 |
69 |
2nd
Level of Mitigation Measure
In addition to the above mitigation measures,
a temporary vertical barriers is proposed to be erected at the tunnel portal
area in order to alleviate the construction noise impact by blocking the line
of view from the nearby receivers. The barrier material needs to have a surface
density (> 7 kg/m2) to provide sufficient screening effect (58 to 10 dB(A)
reduction). Moreover, the construction noise
level produced by
rock drill would be further reduced by
the shielding effect of topographical constraints of the tunnel portal area (5 to 10 dB(A) reduction).
Table
3-13C-5 and C-6 ofin Appendix C demonstrated that with incorporation of quiet plant and
the use of movable barrierconsideration of the effect of barrier,
the cumulative noise
impact at all NSRs would comply with the daytime construction noise criterion
except SR5. The predicted noise levels at SR65 would still exceed the noise
criterion by 58dB(A). See Table
13. Details of
the calculation are provided in Tables C-5 and C-6 of Appendix C.
Table 3-13 Predicted Noise Level at Representative Noise Sensitive Receivers –
With Use of Quiet Plant and
Use of Movable Noise Barriers (Leq30min dB(A))
|
Predicted Noise Level, dB(A) |
|||||||
NSR(s) |
Pui O, Lantau |
Cheung Chau |
||||||
|
SR1 |
SR2 |
SR3 |
SR4 |
SR5 |
SR6 |
SR7 |
SR8 |
Daytime
Construction Noise Criteria dB(A) |
75 |
75 |
75 |
75 |
75 |
70 |
75 |
75 |
1.
Installation of Underground Cable |
||||||||
Road
Breaking |
69 |
75 |
69 |
63 |
64 |
74 |
74 |
60 |
Trench
Excavation |
69 |
75 |
69 |
63 |
N.A. |
N.A. |
N.A. |
N.A. |
Road
Reinstatement |
69 |
75 |
69 |
63 |
65 |
75 |
75 |
61 |
2.
Construction of Cable Tunnel |
||||||||
General |
N.A. |
N.A. |
N.A. |
72 |
N.A. |
N.A. |
N.A. |
N.A. |
Site
Formation |
N.A. |
N.A. |
N.A. |
72 |
N.A. |
N.A. |
N.A. |
N.A. |
TBM |
N.A. |
N.A. |
N.A. |
50 |
N.A. |
N.A. |
N.A. |
N.A. |
Drill
& Blast |
N.A. |
N.A. |
N.A. |
72 |
N.A. |
N.A. |
N.A. |
N.A. |
Tunnel
Lining |
N.A. |
N.A. |
N.A. |
65 |
N.A. |
N.A. |
N.A. |
N.A. |
General
+ Site
Formation/Drill & Blast |
N.A. |
N.A. |
N.A. |
75 |
N.A. |
N.A. |
N.A. |
N.A. |
3.
Cumulative Impact |
69 |
75 |
69 |
75 |
65 |
75 |
75 |
61 |
* Bolded value means PNL exceeds the daytime
construction noise criteria
With the implementation of appropriate
and sufficient noise mitigation measures, it is envisaged that the potential
construction noise impact at all other NSRs can be substantially minimised.
Details of the noise mitigation measures shall be formulated based on the
conclusions of this EIA Report. The effectiveness and continuous implementation
of the noise mitigation measures shall be checked by an audit programme which
can help protecting the nearby NSRs through the provision of regular feedback
to the site contractors.
According to the predicted results of the
mitigated noise with two levels of mitigation measures as shown in Table 3-13C-5 and C-6 ofin Appendix C, there is still an
exceedance of noise level by 5dB(A) at SR65, the Buddhist Wai Yan Memorial
College. As the noisiest activity in front of SR65 is road breaking and road reinstatement,
the high noise level at this receiver only exists for a few days (2 to 3 days).
Short duration of this residual impact could be mitigated by scheduling the
construction works at SR65
on Saturday (non-teaching period) or school holidays.
Laying underground cables is a typical installation and CLP has established good trade practices for this work such that they minimise the construction noise and dust impacts. With the implementation of noise mitigation measures and scheduling the construction activities in front of the school, full compliance with the environmental criteria is expected to be achieved. Therefore, routine environmental monitoring for construction noise is not required during the construction phase. Regular site audits are however recommended to be conducted to ensure the effectiveness of these good site practices and appropriate mitigation measures.
The
unmitigated noise levels associated with the installation of underground cable and construction of cable tunnel, would cause exceedance
of the daytime construction noise criterion at the nearby NSRs. The most
seriously affected area is Ham
Tin Tsuen of Pui O, Lantauthe Buddhist Wai Yan Memorial College (SR5)
where unmitigated noise level of up to 9288 dB(A) is predicted. Therefore,
adequate control measures will be necessary for the installation of underground
cable and construction of
cable tunnel. Mitigation measures including the use of quiet plant and
consideration of barrier effect are proposed to substantially
minimise the noise level. Although the noise impact at all NSR would comply with the
daytime construction noise criterion (ie 75 dB(A) for domestic premises),mitigated noise
level reduces to 78 dB(A), it still exceeds the
noise criteria
the Buddhist Wai Yan Memorial College (ie SR6) would still exceed the noise
criteria (ie 70 dB(A)
for schools) by 5
dB(A). By considering the short
duration of this residual impact, re-scheduling the construction works at SR65 on Saturday
(non-teaching period) or school holidays could minimise the noise impacts.
Therefore, the residual noise impact could be alleviated.
For the
construction of the tunnel, numerous of noisy PMEs such as jumbo drilling
machine and rock bolt jumbo are involved. Construction noise
impact at the nearby NSRs is expected. With the erection of the temporary
vertical noise barrier at Pui O tunnel portal and adoption of quiet plants, the
construction noise impact can be alleviated. The predicted noise levels with
mitigation can comply with the noise criteria.
As noise exceedances during the construction phase are not predicted and the laying underground land cable is a trade practice well established by CLP, routine environmental noise monitoring is not required during construction. However regular site audits are recommended to be conducted to ensure the implementation of good site practice and appropriate mitigation measures.
By comparing the assessment results for construction of cable tunnel with TBM and drill & blast method, the construction noise impacts at the nearby sensitive receivers are acceptable for both methods with the implementation of mitigation measures. Although TBM is the envisaged option based on the finding, both TBM and the drill & blast method are also feasible and comply with the daytime noise criteria.
Site
investigations have been conducted to identify the ground condition in Chi Ma
Wan Peninsula along the proposed cable alignment. The investigation revealed
that the proposed tunnelling will have negligible effect on the water catchment yield and
is unlikely to cause any significant drawndown of the groundwater profile and
as a result it does not affect existing plantation within the study area.
However, as a preventive measure, monitoring points are proposed at appropriate
locations to monitor any change of the ground water profile during the
construction period.
The purpose of the groundwater monitoring is to:-
· monitor the existing ground water table, in case of any substantial change or abnormal loss of groundwater, mitigation measures could be implemented at the first instance; and
· implement mitigation measures wherever appropriate to prevent further groundwater inflow into the proposed cable tunnel and to alleviate the drawdown effect which although unlikely has the potential to affect the existing plantation.
The proposed tunnel is located approximately 120m below the ground surface in Chi Ma Wan Peninsula. The estimated catchment affected by the proposed tunnel will be approximately 390,000m2 based on a 400m zones of influence as described in McFeat et al, 1998. The water inflow into the proposed cable tunnel will depend on the amount of rock joints, types of joint infill and aperture thickness. Major water inflows occur where fracture zones and open joints are encountered. It is recommended that groundwater monitoring points are installed at shallow cover locations such as in Lung Mei and where fracture zones and open joints are anticipated.
3.5.1 Mitigation Measures
In case any substantial and abnormal changes in the ground water table are observed from the monitoring point as a result of groundwater inflow into the proposed cable tunnel, mitigation measures as outlined below are recommended to prevent further groundwater loss. The mitigation measures include:-
· traditional pre-injection systems using cement grout will be applied in the identified fault intersection zone to reduce the water inflow, if necessary; and
· apply 2mm thick typical high performance PVC waterproof membrane and geotextile fleece mats as suggested in the tunnel preliminary design report to ensure watertighteness of the tunnel.
In order to ensure no ground water loss during the cable tunnelling work, monitoring of ground water table as specified in section 4 of the EM&A Manual and the monitoring requirements as defined below will be specified in the Contract Document. The monitoring requirements during construction period include:-
· The contractor is required to submit a layout plan showing the proposed locations groundwater monitoring points to the satisfaction of EPD;
· The contractor is required to submit method statements for the proposed mitigation measures to prevent further ground water inflow into the proposed cable tunnel to the satisfaction of EPD, the mitigation measures are:-
(i) pre-injection system using approved cement grout and any equivalent approved methods and/or proprietary products which could achieve the same performance and purpose; and
(ii) lining and waterproof membrane for the cable tunnel.