This section outlines the
potential impacts associated with the proposed cable laying activities between
Chi Ma Wan Peninsula and Cheung Chau via Pui O on receiving water quality. The potential water
quality impacts associated with the Project have been considered. These include
impacts from cable laying, general construction works and runoff., and tThe environmental
acceptability of the impacts on receiving water quality wereas determined and
mitigation measures recommended where necessary..
In
order to define the nature and quantify the extent of the potential impacts
associated with the marine based works, sediment plume modelling was undertaken
using an approved and calibrated mathematical model which simulated various
likely scenarios in accordance with the requirements of the Study Brief. Other water quality
assessments have been undertaken using qualitative assessments and are based on
practical experience of similar projects in Hong Kong (such as “Focussed Environmental
Impact Assessment Study : Laying a Second 132kV Submarine Cable Transmission
link from Lau Fau Shan to Shekou”, ERM 1996)..
The potential water quality impacts associated with
the Project have been considered. These include impacts from dredging, general
construction works and runoff, and the environmental acceptability of the
impacts on receiving water quality were determined and mitigation measures
recommended.
The water quality
assessment has followed the guidelines given in Annexes 6 and 14 of the EIA-TM and has focussed on assessing the
construction impacts associated with implementing the project and provides
details of any mitigation measures and monitoring requirements which may be
necessary to ensure residual impacts are acceptable and comply with current
standards and guidelines.
The Water Pollution Control Ordinance (WPCO) (Cap. 358) enacted in 1980 is the principal legislation controlling water quality in Hong Kong along with Annexes 6 and 14 of the Technical Memorandum on Environmental Impact Assessment Process (EIA-TM). Under the WPCO, Hong Kong waters are classified into 10 Water Control Zones (WCZs) and statutory Water Quality Objectives (WQOs) are specified for each WCZ.
This cable laying project will take place in the Southern Water Control Zone which was gazetted in L.N. 204 of 1988. The WQOs for this WCZ are the evaluation criteria for assessing the water quality impacts during dredging or jet ploughing activities. The WQOs also apply to the protection of water quality with respect to the potential off-site discharges from construction sites, and disposal of sewage from the construction work force.
WQOs have been
established in terms of the physical, chemical and biological water quality in
the specific Water Control Zone to achieve the level of protection required for
each beneficial use. For the current
situation beneficial uses are:
·
human health; and
·
aquatic life
Relevant WQOs for this assignment are included in Table 4-1 which indicate the ambient value and the compliance level.
Table 4-1 Water
Quality Objectives (WQOs) for Southern Water Control Zone
Water
Quality Objective |
Part or Parts of Zone |
A.
AESTHETIC APPEARANCE (a) Waste discharges shall cause no objectionable odours
or discolouration of the water. (b) Tarry residues, floating wood, articles made of
glass, plastic, rubber or of any other substance should be absent. (c) Mineral oil should not be visible on the surface.
Surfactants should not give rise to a lasting foam. (d) There should be no recognisable sewage-derived
debris. (e) Floating, submerged and semi-submerged object at a
size likely to interfere with the free movement of vessels, or cause damage
to vessels, should be absent. Waste discharges shall not
cause the water to contain substance which settle to form objectionable
deposits. |
Whole Zone Whole Zone Whole Zone Whole Zone Whole Zone Whole Zone |
B.
BACTERIA (a) The level of Escherichia
coli should not exceed 610 per 100 ml, calculated as the geometric mean
of all samples collected in one calendar year. (b) The level of Escherichia
coli should not exceed 180 per 100 ml, calculated as the geometric mean
of all samples collected from March to October inclusive in one calendar
year. Samples should be taken 3 times in a calendar month at intervals of
between 3 and 14 days. |
Secondary Contact Recreation Subzones and Fish Culture Subzones Bathing Beach Subzones |
C. DISSOLVED
OXYGEN (a) Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 milligrams per litre for 90% of the sampling
occasions during the year, values should be calculated as the water column
average (arithmetic mean of at least 3 measurements at 1 metre below surface,
mid-depth, and 1 metre above seabed). In addition, the concentration of
dissolved oxygen should not be less than 2 milligrams per litre within 2
metres of the seabed for 90% of the sampling occasions during the year. (b) The dissolved oxygen level should not be less than 5
milligrams per litre for 90% of the sampling occasions during the year;
values should be calculated as water column average (arithmetic mean of at
least 3 measurements at 1 metre below surface, mid-depth and 1 metre above
seabed). In addition, the concentration of dissolved oxygen should not be less
than 2 milligrams per litre within 2 metres of the seabed for 90% of the
sampling occasions during the year. (c) Waste discharges shall not cause the level of
dissolved oxygen to be less than 4 milligrams per litre. |
Marine waters excepting Fish Culture Subzones Fish Culture Subzones Inland waters of the Zone |
D.
(a) The pH of the water should be within the range of
6.5-8.5 units. In addition, waste discharges shall not cause the natural pH
range to be extended by more than 0.2 units. (b) The pH of the water should be within the range of
6.0-9.0 units. (c) The pH of the water should be within the range of
6.0-9.0 units for 95% of samples. In addition, waste discharges shall not
cause the natural pH range to be extended by more than 0.5 units. |
Marine waters excepting Bathing Beach Subzones; Mui Wo (A), Mui Wo
(B), Mui Wo (C), Mui Wo (E) and Mui Wo (F) Subzones. Mui Wo (D) Subzones and other inland waters. Bathing Beach Subzones |
E.
TEMPERATURE (a) Waste
discharges shall not cause the natural daily temperature range to change by
more than 2.0 degree Celsius. |
Whole Zone |
F.
SALINITY (a) Waste
discharges shall not cause the natural ambient salinity level to change by
more than 10%. |
Whole Zone |
G.
SUSPENDED SOLIDS (a) Waste discharges shall neither cause the natural ambient
level to be raised by 30% nor give rise to accumulation of suspended solids
which may adversely affect aquatic communities. (b) Waste discharges shall not cause the annual median
of suspended solids to exceed 20 milligrams per litre. (c) Waste discharges shall not cause the annual median
of suspended solids to exceed 25 milligrams per litre. |
Marine waters Mui Wo (A), Mui Wo (B), Mui Wo (C), Mui Wo (E) and Mui Wo (F)
Subzones. Mui Wo (D) Subzones and other inland waters. |
H.
AMMONIA (a) The
ammonia nitrogen level should not be more than 0.021 milligram per litre,
calculated as the annual average (arithmetic mean), as unionised form. |
Whole Zone |
I.
NUTRIENTS (a) Nutrients shall not be present in quantities
sufficient to cause excessive or nuisance growth of algae or other aquatic
plants. (b) Without limiting the generality of objective (a)
above, the level of inorganic nitrogen should not exceed 0.1 milligram per
litre, expressed as annual water column average (arithmetic mean of at least
3 measurements at 1 metre below surface, mid-depth and 1 metre above seabed). |
Marine waters |
J.
5-DAY BIOCHEMICAL
OXYGEN DEMAND (a) Waste
discharges shall not cause the 5-day biochemical oxygen demand to exceed 5
milligrams per litre. |
Inland waters of the Zone |
K.
CHEMICAL OXYGEN DEMAND (a) Waste
discharges shall not cause the chemical oxygen demand to exceed 30 milligrams
per litre. |
Inland waters of the Zone |
L.
DANGEROUS SUBSTANCES (a) Waste discharges shall not cause the concentration
of dangerous substances in marine water to attain such levels as to produce
significant toxic effects in humans, fish or any other aquatic organisms,
with due regard to biologically cumulative effects in food chains and to
toxicant interactions with each other. (b) Waste discharges of dangerous substances shall not
put a risk to any beneficial uses o the aquatic environment. |
Whole Zone Whole Zone |
(Source: Adopted from CAP. 358, section 5, 1988 and
L.N. 453 of 91)
The Technical Memorandum (TM), “Standards for Effluent Discharge into Drainage and Sewerage Systems, Inland and Coastal Waters”, issued under Section 21 of the WPCO defines acceptable effluent discharge limits to different types of receiving waters. With regard to inland waters, there is no distinction between different zones and the beneficial use of the inland waters is the only factor governing the quality and quantity of the effluent that should be met. Under the TM, inland waters are classified into four groups. These are given below in Table 4-2.
Table 4-2 Different Groups of Inland Water Specified
in the TM
Inland
Water Grouping |
Beneficial use |
Group A |
Abstraction for potable
water supply |
Group B |
Irrigation |
Group C |
Pond fish culture |
Group D |
General amenity and
secondary contact recreation |
(Source: Adopted from Technical Memorandum of Standards for Effluents Discharged into
Drainage and Sewerage Systems, Inland and Coastal Waters)
For this Project Group D waters
prevail for the
inland waters the :-.
The WQOs
which prevail for this Project with discharge standards for Group
D waters are given in Table 4-3.
Table
4-3 Standards for Effluents Discharged into
Group D Inland Waters
(All
units in mg/L unless otherwise stated; all figures are upper limits unless
otherwise indicated)
Flow
rate (m3/day) Determinand |
£200 |
>200
and £400 |
>400
and £600 |
>600
and £800 |
>800
and £1000 |
>1000
and £1500 |
>1500
and £2000 |
>2000
and £3000 |
pH (pH units) |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
6-10 |
Temperature (oC) |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
Colour (lovibond
units) (25mm cell length) |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Suspended solids |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
BOD |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
COD |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
Oil & Grease |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
Iron |
10 |
8 |
7 |
5 |
4 |
2.7 |
2 |
1.3 |
Boron |
5 |
4 |
3.5 |
2.5 |
2 |
1.5 |
1 |
0.7 |
Barium |
5 |
4 |
3.5 |
2.5 |
2 |
1.5 |
1 |
0.7 |
Mercury |
0.1 |
0.05 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.1 |
0.05 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Other toxic metals
individually |
1 |
1 |
0.8 |
0.8 |
0.5 |
0.5 |
0.2 |
0.2 |
Total toxic metals |
2 |
2 |
1.6 |
1.6 |
1 |
1 |
0.5 |
0.4 |
Cyanide |
0.4 |
0.4 |
0.3 |
0.3 |
0.21 |
0.1 |
0.1 |
0.05 |
Phenols |
0.4 |
0.3 |
0.2 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Sulphide |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Sulphate |
800 |
600 |
600 |
600 |
600 |
400 |
400 |
400 |
Chloride |
1000 |
800 |
800 |
800 |
600 |
600 |
400 |
400 |
Fluoride |
10 |
8 |
8 |
8 |
5 |
5 |
3 |
3 |
Total phosphorus |
10 |
10 |
10 |
8 |
8 |
8 |
5 |
5 |
Ammonia nitrogen |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
10 |
Nitrate + nitrite
nitrogen |
50 |
50 |
50 |
30 |
30 |
30 |
30 |
20 |
Surfactants (total) |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
15 |
E. coli
(count/100ml) |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
1000 |
(Source: Adopted from Technical Memorandum of Standards for Effluents Discharged into
Drainage and Sewerage Systems, Inland and Coastal Waters)
The potential
sources of water quality impacts are from:As identified
in Section 2 there are various activities taking place in the marine
environment which could adversely affect water quality and impact on the marine sensitive
receivers.
These are primarily :
The main
aspects of the
project which have the potential to impact water quality and thus potentially
sensitive receivers these are:
·
Cable laying which is described in section 2 detail in section ___ and may take place using dredging or direct burying
methods although it is recognised that the method favoured method (by the the
Client) is theis direct
burying method as
it is shorter, has fewer environmental impacts to address and is generally more
in keeping with the approach of
minimising at source the environmental impacts of projects (through choice of
method or plant);
·
Formation of the temporary workings platform at the tunnel portal at Pui O; and
·
Laying the cable in the typhoon shelter at Cheung
Chau.
The methods considered for cable
laying have been subjected to detailed modelling using a sediment plume model. For the pther
aspects of the work, qualitative assessments have ben adopted. Justifications
for this are given in the form of the construction method as described below.
The temporary
working
platforms area
at Pui O will be formed by placing a seawall in the location shown in Figure 3.3. Material excavated from the tunnel will be
used to form the works platform and by adopting a strategy of filling behind the forward
formed seawall, no “fines” will be released
to the receiving marine waters.. The method of construction which is designed for pollution prevention, will be to place concrete
blocks as an outer seawall (within no gaps) and fill behind the seawall with
excavated material from the tunnel.
Tunnel spoil will largely be large fraction rock and rubble. Notwithstanding this there will
be no opportunity for any small fraction materials (“fines”) to be released to the
receiving waters as there will be no gaps permitted in the seawall. Once the tunnelling works have been
completed the fill material will be excavated, disposed of off-site and the
seawall dismantled, thus reinstating the beach to its original state. No detailed modelling was undertaken as the
impacts are temporary and very minor. and transient.
When laying the cables in the
typhoon shelter, an opening will need to be made by dismantling the area shown
in Figure 4.21. The cast concrete sleeve will then be placed
in the seawall, which shall be reconstructed and divers deployed to “lay” the cables
through the sleeve to rest in the cable trough. The “U” shaped sleeve is 4.9m (long) x
0.75m (high) for each circuit which passes through the breakwater. Only two circuits are placed through the
breakwater according to the current design proposed.
It is estimated
that the
diver would
need around 10 days to lay each circuit in the typhoon shelter (by hand). This work will
have minimal impact on the sediments in the bottom of the typhoon shelter and no
detailed assessment has been carried out. As a precaution the Contractor should be prepared to provide a silt screen
for the diver to work within should this be required. Reference should be made to section 4.6 which
details mitigation measures.
Other potential
impacts include the off-site runoff during land based construction activities and
dewatering of slurry generated during the driving of the
tunnel,
and .
Other
issues include the liquid waste
(sewage and greywater) generated by the construction workers. which is discussed in Section 9 under the solid and liquid
wastes section.
For the assessment of off-site spillage the focus
was on qualitative assessments and definition of mitigation measures to be
included in the Contract Documents.
Guidelines following ProPECC Note PN1/924 “Construction”, “Site Drainage” would be used as a
reference guide. Mitigation measures are also described in
Section 4.6.
For the
treatment of wastewater generated by the tunnel construction, it is likely that
this would need to focus on removal of sediment. This could be by sedimentation tank or by the use of a mobile
microfiltration plant, should the required discharge standard not be met by
conventional sedimentation techniques. The standards to achieve are set out in the Technical Memorandum
on “Standards for Effluents Discharged into Drainage and Sewerage Systems,
Inland and Coastal Waters”. Further discussion of this waste is described in
Section 9.
Dredging for and/or laying of cables;
·Reclamation works at Pui O Beach;
·Construction runoff; and
·Sewage generated by the workforce.
The
water quality assessment has followed the guidelines given in Annexes 6 and 14 of
the EIA-TM. The water quality assessment h
and has focussed on assessing the construction and operational impacts
associated with implementing the project and provides details of any mitigation
measures and monitoring requirements which may be necessary to ensure residual
impacts are acceptable and comply with current standards and guidelines.
It should be noted
that as the working platform at Pui O is temporary there will be no potential
impediment to tidal flows
following completion of the works, therefore no post construction assessment is
required.
For the remaining
assessments, attention has focussed on the cable laying works.
In accordance
with the requirements of the EIA-TM, the assessments
given in the following sections are, as far as practical, quantitative..
Marine
Water Quality
The Study Area is
located within Southern Waters in a water body
where oceanic and estuarine waters interchange. The Southern Water Control
Zone which
is the second largest water control zone (WCZ) with a marine mud disposal
area to the south of Cheung Chau. The
WCZ also covers a statutory marine reserve in Cape D’Aguilar which is of great
scientific interest and conservationversation significance but which is remote from the subject site. The major land areas in the zone include the
southern part of Lantau Island, all outlaying
islands in the southern territorial waters of Hong Kong Island.
and the southern part of Hong Kong Island.
There are fFour
maricultural zones are located within this WCZ at Cheung Sha Wan, Po
Toi Island, Cheung Sha Wan (southeast coast of Lantau Island), Sok
Kwu Wan and Lo Tik Wan of Lamma Island.
Apart
from Chi Ma WanCheung Sha Wan all other fish
culture zones are remote from the influence of the proposed cable layingmarine works. Moreover, a
navigation fairway is running through The Adamasta Channel is a designated
navigation fairway which is used by high speed vessels plying to and from
Macau, inter-island ferries and
fishing vessels . Consequently
water movements are complex with seasonal variations observed with estuarine or
oceanic influences dominating at different times of the year.
Based on the data
obtained from Marine Water Quality in
Hong Kong in 1999 published by the Environmental Protection Department
(EPD), the closest monitoring stations to the project are at SM11, SM12 and
SM13 within the WCZ to the north and the west of Cheung Chau and to the
southeast of Lantau Island. Locations of the indicating representative
water sampling stations in the Southern WCZ (in the current
context) are shown in Figure 4.12. Water
quality statistics for the representative stations are presented in Table 4-4.
Table 4-4 Marine Water Quality in the Southern Water
Control Zone at Selected Stations
Determinand |
SM11 |
SM12 |
SM13 |
Temperature (oC) |
23.5 (17.5 – 27.2) |
23.7 (18.5 – 27.5) |
23.8 (18.6 – 27.3) |
Salinity (psu) |
30.3 (25.4 – 32.7) |
30.5 (25.8 – 33.4) |
30.4 (24.7 – 33.4) |
Dissolved Oxygen (mg/L) |
6.5 (5.0 – 9.3) |
6.6 (5.3 – 9.6) |
6.3 (4.7 – 8.0) |
Dissolved Oxygen Bottom (mg/L) |
6.5 (4.9 – 8.9) |
6.5 (5.3 – 9.4) |
6.4 (5.2 – 8.2) |
Dissolved Oxygen (% Saturation) |
91 (70 – 118) |
92 (75 – 125) |
88 (67 – 104) |
Dissolved Oxygen Bottom (% Saturation) |
91 (70 – 112) |
91 (76 – 123) |
89 (74 – 107) |
|
8.0 (7.8 – 8.3) |
8.0 (7.8 – 8.4) |
8.0 (7.9 – 8.4) |
Secchi Disc Depth (m) |
2.0 (1.0 – 3.5) |
1.8 (1.0 – 3.0) |
1.8 (1.0 – 3.5) |
Turbidity (NTU) |
8.2 (3.7 – 10.7) |
9.2 (4.0 – 13.6) |
12.7 (3.8 – 22.4) |
Suspended Solids (mg/L) |
6.4 (2.5 – 11.3) |
8.0 (2.8 – 12.7) |
9.7 (2.0 – 20.7) |
5-day Biochemical Oxygen Demand (mg/L) |
0.7 (0.3 – 1.2) |
0.8 (0.3 – 1.3) |
0.7 (0.3 – 1.2) |
Ammonia Nitrogen (mg/L) |
0.06 (0.04 – 0.11) |
0.04 (0.01 – 0.05) |
0.03 (0.01 – 0.05) |
Unionized Ammonia (mg/L) |
0.003 (0.001 – 0.006) |
0.002 (0.001 – 0.003) |
0.002 (<0.001 – 0.004) |
Nitrite Nitrogen (mg/L) |
0.03 (0.01 – 0.05) |
0.02 (<0.01 – 0.04) |
0.02 (<0.01 – 0.04) |
Nitrate Nitrogen (mg/L) |
0.14 (0.02 – 0.29) |
0.14 (0.01 – 0.30) |
0.13 (<0.01 – 0.32) |
Total Inorganic Nitrogen (mg/L) |
0.23 (0.08 – 0.38) |
0.19 (0.04 – 0.35) |
0.19 (0.02 – 0.37) |
Total Kjeldahl Nitrogen (mg/L) |
0.2 (0.12 – 0.36) |
0.22 (0.13 – 0.35) |
0.21 (0.08 – 0.33) |
Total Nitrogen (mg/L) |
0.41 (0.28 – 0.51) |
0.38 (0.24 – 0.55) |
0.36 (0.18 – 0.52) |
|
|
|
|
Ortho-phosphate (mg/L) |
0.02 (0.01 – 0.04) |
0.02 (0.01 – 0.03) |
0.02 (0.01 – 0.03) |
Total-Phosphorus (mg/L) |
0.04 (0.02 – 0.05) |
0.03 (0.02 – 0.04) |
0.03 (0.02 – 0.04) |
Silica (as SiO2) (mg/L) |
0.9 (0.1 – 3.0) |
1.0 (0.1 – 2.8) |
1.1 (0.1 – 3.0) |
Chlorophyll-a (mg/L) |
3.3 (1.0 – 6.6) |
3.2 (1.2 – 6.0) |
2.4 (0.6 – 5.4) |
Phaeo-pigment (mg/L) |
1.0 (0.4 – 1.6) |
1.0 (0.5 – 2.0) |
0.8 (0.2 – 1.9) |
E.coli (cfu/100mL) |
4 (1 – 120) |
12 (2 – 200) |
2 (1 – 15) |
Faecal Coliforms (cfu/100mL) |
9 (1 – 350) |
28 (4 – 510) |
5 (1 – 90) |
Note: 1. Except as specified,
data presented are depth-averaged results.
2. Depth-averaged results at each station are calculated as arithmetic
means of measurements at all available depths (i.e. S, M, B) except for E.coli
and faecal coliforms which are geometric means.
3. Data presented are annual arithmetic means except for E.coli and
faecal coliforms which are annual geometric means.
4. Data enclosed in brackets indicate the ranges.
5. Shaded cells indicate non-compliance with the WQOs.
(Source: Adopted from EPD Marine Water Quality for
1999)
The wWater
quality at the representative stations was generally good with a low level of sewage bacteria (indicative of
faecal organismsations)
being present and with . Aall the
parameters,
of water quality except for total
inorganic nitrogen (TIN), complying with the relevant WQOs. As these representative monitoring stations are shielded by
Lantau Island, the influence of the Pearl River flow is insignificant, which is . This can
be reflected by the relatively small range of in the salinity (25 to 33 psu).
With reference
to the report entitled of the
project “Focussed Environmental
Impact Assessment (EIA) Study : Laying a second 132kV Submarine Cable
Transmission Link from Lau Fau Shan to Shekou” it was noted that the . The
ambient level of suspended solids wais assumed to be the 90th
percentile of the reported concentrations. Using this precedent case the , and the predicted values of 90th
percentiles at SM11, SM12 and SM13 were calculated to be are 9.1,
12.2 and 17.8 mg/L respectively. The
mean ambient value is calculated to be 13.0 mg/L.
As the WQO is defined as
130% of the ambient, the WQO compliance threshold is set (for this
assessment) at 16.9 mg/L. Therefore, the maximum allowable elevated level
for suspended
sediment is due to the proposed works is 3.9 mg/L. It should be
stressed that this compliance level acceptability
level should be confirmed through
the baseline monitoring to be carreid carried out by the Contractor
prior to commencing marine works. This baseline monitoring will provide athe more accurate level of suspended solids which can be released into the
water column while still complying with the Water Quality Objectives – as it
will represent the situation at the
time of the works.
Analysis of dDissolved
oxygen is defined both in terms of concentration (mg/L) and saturation
(%). According to the WQO compliance
evaluation, only DO concentration is concerned and the ambient level of
dissolved oxygen is assumed to be the 10th percentile of the
reported concentrations. The ranges and
mean values at the representative sampling stations are presented in Table 4-4. The 10th percentiles at SM11, SM12 and SM13 are predicted
to be 5.4, 5.4 and 5.1 mg/L respectively.
The mean ambient value is estimated to be 5.3 mg/L. For the DO saturation, the 10th
percentiles at SM11, SM12 and SM13 are predicted to be 78.2%, 77.9% and 74.1%
respectively and the mean ambient level is estimated to be 76.7%. These ambient values indicate a
well-oxygenated baseline environment.
Sediment Quality
Marine
sediment quality data is collected by EPD in the vicinity of the sStudy aArea. has revealed that the sediments are classified as The “Classification
of Dredged Sediment for Marine Disposal” under Work Bureau Technical Circular
(WBTC) No. 3/2000 is summarised in. The
sediment quality criteria for the classification of sediment is summarised as
shown in Table 4-5. This defines the level of further testing
(if any) which
needs
to be carried out before disposal routes can be defined assuming that
disposal of material is required. It should be noted that only if
dredging is undertaken will disposal of marine deposits be requiriedd. The direct burying
method does not generate waste for off-site disposal which is another reason why it is a favoured construction
method..
Table
4-5 Sediment Quality Criteria for
the Classification of Sediment
Contaminants |
Lower
Chemical Exceedance Level (LCEL) |
Upper
Chemical Exceedance Level (UCEL) |
Metals (mg/kg dry wt.) |
|
|
Cadmium (Cd) |
1.5 |
4 |
Chromium (Cr) |
80 |
160 |
Copper (Cu) |
65 |
110 |
Lead (Pb) |
75 |
100 |
Mercury (Hg) |
0.5 |
1 |
Nickel (Ni)* |
40 |
40 |
Zinc (Zn) |
200 |
270 |
Metalloid (mg/kg dry wt.) |
|
|
Arsenic (As) |
12 |
42 |
Organic-non-PAHs (mg/kg dry
wt.) |
|
|
PCBs |
23 |
180 |
Organic-PAHs (mg/kg dry wt.) |
|
|
Low Molecular Weight PAHs |
550 |
3160 |
High Molecular Weight PAHs |
1700 |
9600 |
* The contaminant level is considered to
have exceeded the UCEL if it is greater than the value shown.
SS5 and SS6 are
the two closest sediment monitoring stations to the proposed submarine cable
across the Adamasta Channel. In
addition, the proposed submarine cable will pass through Cheung Chau typhoon
shelter albeit
using divers
to lay the cables in this final section rather than direct burying or dredging techniques. Therefore, the quality of typhoon shelter
sediments at SS7 iswas also taken into account. The routine
sediment quality monitoring data at SS5, SS6 and SS7 collected by EPD are
summarised in Table 4-6.
Table
4-6 Monitoring Results of Sediment
Quality between 1995 and 1999
Parameter |
Average Concentrations |
Unit
|
||
SS5 |
SS6 |
SS7 |
||
Cadmium |
0 - 0.9 |
0 - 0.9 |
0 - 0.9 |
(mg/kg dry
wt.) |
Chromium |
0 – 49 |
0 - 49 |
0 - 49 |
|
Copper |
0 - 54 |
0 - 54 |
³65 |
|
Lead |
0 - 64 |
0 - 64 |
65 - 74 |
|
Mercury |
0 - 0.7 |
0 - 0.7 |
0 - 0.7 |
|
Nickel |
0 - 34 |
0 - 34 |
0 - 34 |
|
Zinc |
0 - 140 |
0 - 140 |
150 - 190 |
|
Arsenic |
0 - 14 |
0 - 14 |
0 - 14 |
|
PCBs |
6 - 10 |
0 - 5 |
11 - 20 |
(mg/kg dry wt.) |
PAHs |
51 - 100 |
0 - 50 |
101 - 200 |
|
Note: 1. Data presented are
in annual medians of monthly samples
2. Shaded cells indicate non-compliance
with exceedance of the LCEL.
(Source: Adopted from EPD Marine Water Quality in
Hong Kong for 1999)
Based on the
above monitoring results, the qualities
of the sediment quality is relatively similar for the three
locations except for Zn in SS7.samples
collected at the marine sediment monitoring locations are similar. The average concentrations of the heavy
metals in the marine sediments at SS5 and SS6 fall within the same range while
the typhoon shelter sediments at SS7 hasve
higher
average concentrations of copper, lead
and zinc. The results show that the
contents of Mercury and Arsenic exceed the Lower Chemical Exceedance Level
(LCEL) but
complies with the Upper Chemical Exceedance Level (UCEL). Therefore
no contamination of sediment is considered.
The average
concentrations of polychlorinated biphenyls (PCBs) and polycyclic aromatic
hydrocarbons (PAHs) are different at the three monitoring stations. The tendency of increasing concentrations is
in the sequence of SS6, SS5 and SS7.
The high PAHs at Cheung Chau typhoon shelter may be related to the combustion use of of petrol eum ion the fishing boats.
Beneficial uses
have been defined in accordance with the requirements of the Hong Kong Planning Standards and Guidelines
(HKPSG), which have been transposed into the EIA-TM. As required under the Study Brief all water bodies, water and
stream courses, groundwater systems and other sensitive or beneficial uses have
been identified within a
6km radius from the project sites. The
study area of the water quality impact assessment is presented in Figure 4.3.
In some cases however
the effects of the works cannot be discerned so far from the site and thus these sensitive receivers may
be discounted. Potentially sensitive
receivers include :include: These
include Adamasta Channel, Cheung
Chau Typhoon Shelter, Hei Ling Chau Typhoon Shelter, Silver Mine Bay, Cheung
Sha Lower Beach, Pui O Beach and other gazetted and non-gazetted beaches within
the Study.. y Area.
Monitoring locations within the Study Area are
illustrated on Figure
4.23. Monitoring
locations for beneficial uses have been identified in accordance with the
requirements of the EIA-TM. These include:
· Marine life;
· Mariculture;
· Beaches and other recreational areas;
· Fish spawning grounds and fish culture zones; and
· Areas for navigation/shipping including typhoon shelters, marinas and boat parks.
The project
essentially requires
cable
laying across the Adamasta Channel and the potential impacts relate to
elevation of suspended solids in the water column. Taking these factors
into account only two of the potentially sensitive receivers within the 6km
radius have the potential to be adversely affected during the course of the
cable laying works. These are the Cheung Sha Wan Fish Culture Zone (shown as
station R1 on Figure
4.4) and Tai Kwai Wan beach on Cheung Chau (shown as R13 on Figure 4.4).
Other potentially sensitive receivers
such as Pui O Wan are too far away from the works area and the effects of tidal
currents would disperse any sediment plumes before reaching this area and for
this reason Pui O Wan has
been discounted from any further assessment relating to sediment
plume modelling. Similarly the beach at Tung Wan (R7) has been
discounted as it is on the east of Cheung Chau whereas the works will take place on the
west of the island.
In order to assess
the extent of the impacts of sediment release to the water column a series of
assessment stations were selected which include the two sensitive receivers as
indicated above. Although the results from all other assessment points shown on Figure 4.4
have been
included to assist in the interpretation of the data, attention is
focussed upon the impacts of the works on the sensitive receivers R1 and R13.
Sensitive receivers Those which could be potentially affected include:
·Adamasta
Channel
·Cheung
Chau Typhoon Shelter
·Pui
O Beach
·Tai
Kwai Wan
·Tai
Long Wan
·Yi
Long Wan
·Sai
Wan
·Po
Yue Wan
·Pak
Tso Wan
·Tung
Wan Tsai
Those which arwe outsidewith the area of influence of the works are not
considered further and include:
·Cheung Sha Wan Fish
Culture Zone
·Fish
Fry Nursery Area
·Hei
Ling Chau Typhoon Shelter
·Silver
Mine Bay
·Cheung
Sha Lower Beach
·Tung
Wan
Chai
·Sai Wan Typhoon
Shelter
·Kwun
Yam Wan
·Mong
Tung Wan
Of
the foregoing identified sensitive receivers within the six km radius of the
works, some have been identified as being outside the area of influence of the
work. Some of
the sensitive receivers have not been ascribed specific assessment points. These include the Cheung
Sha Wan Fish Culture
Zone is outwith the main tidal flows and sediment plumes are expected to disperse before reaching this area. Hei Ling Chau and Sai Wan are typhoon
shelters both have impediments to flow and ingress of pollutants due to the breakwaters and Pui O beach was not included as the landmass of
the Chi Ma Wan Peninsula and the tidal regime in
the area were considered to be
impediments to the migration of sediments from the main stream of the Adamasta
Channel.
For the water quality
impact assessment, 38 monitoring locations for beneficial
uses have been selected as
part of the assessment process. 27
monitoring locations represent the water sensitive receivers of beneficial uses
and the rest of 11 are used for assess ing
purposeThe assessment points indicated on Figur. Locations of these WSRs and assessment points are presented in Figure 4.42., with aare included with a
brief description in Table 4-.7. A brief description of the WSRs is summarised given
in Table 4-7
and 4-8
respectively.
Location |
|
Assessment Point |
Easting |
Northing |
Cheung Sha Wan Fish Culture Zone |
Sensitive Receiver |
R1* |
810 687.330 |
818 743.944 |
Tai Kwai Wan |
Sensitive Receiver (Non-gazetted
Beach) |
R13* |
808 727.202 |
820 715.976 |
Tung Wan |
Sensitive Receiver Gazetted Beach |
R7* |
808 103.527 |
821 798.480 |
Nam Tam Wan |
Rugged Coast |
R8* |
806 894.147 |
821 408.058 |
Po Yue Wan |
Rugged Coast |
R24** |
806 725.004 |
819 775.129 |
Pak Tso Wan |
Non-gazetted Beach |
R25* |
806 385.343 |
820 077.863 |
Tai Long Wan |
Non-gazetted Beach |
R26** |
808 794.506 |
817 867.812 |
Tai Long Wan |
Non-gazetted Beach |
R27** |
808 789.923 |
817 679.750 |
Yi Long Wan |
Non-gazetted Beach |
R28** |
808 374.320 |
817 346.308 |
Yi Long Wan |
Non-gazetted Beach |
R29** |
808 478.223 |
817 170.606 |
Yi Long Pai |
Non-gazetted Beach |
R30* |
808 262.784 |
817 069.695 |
Mong Tung Wan |
Non-gazetted Beach |
R38* |
809 440.312 |
815 880.115 |
Cheung Chau Typhoon Shelter |
Typhoon Shelter |
R18** |
808 108.111 |
820 693.041 |
|
|
R19** |
807 906.423 |
820 885.690 |
|
|
R20** |
807 584.012 |
820 871.393 |
|
|
R21** |
807 474.000 |
820 605.354 |
|
|
R22** |
807 498.292 |
820 453.979 |
|
|
R23** |
807 194.387 |
820 265.925 |
Adamasta Channel |
Navigation Fairway |
R2* |
810 458.139 |
820 129.182 |
|
|
R3* |
810 052.929 |
821 064.905 |
|
|
R4* |
809 792.935 |
821 551.115 |
|
|
R5* |
809 791.652 |
820 500.719 |
|
|
R6* |
809 559.160 |
821 055.732 |
|
|
R9* |
809 515.618 |
820 009.596 |
|
|
R10* |
809 272.676 |
820 560.022 |
|
|
R11** |
809 067.820 |
819 542.974 |
|
|
R12* |
808 887.635 |
820 165.550 |
|
|
R14** |
808 466.217 |
820 569.500 |
|
|
R15** |
808 648.422 |
819 138.386 |
|
|
R16** |
808 442.957 |
819 774.439 |
|
|
R31** |
808 131.778 |
818 010.005 |
|
|
R32** |
808 035.518 |
817 505.448 |
|
|
R33* |
807 966.761 |
817 005.478 |
|
|
R34* |
807 499.947 |
816 504.704 |
|
|
R35** |
807 687.148 |
818 339.435 |
|
|
R36** |
807 572.552 |
817 784.422 |
|
|
R37* |
807 471.708 |
817 253.170 |
Note: * Monitoring locationsWater
sensitive receivers lie outside the area of
100m away from the submarine cables.
** Monitoring locationsWater
sensitive receivers fall within the
area100m in the vicinity of the submarine cables.
Note: * Assessment
Points
lie outside the area of 100m away from the submarine cables.
** Assessment Points fall within
the area100m in the vicinity of the submarine cables.
The
identified sensitive receivers include a fish culturale zone and a fish fery
nursery area, nine non-gazetted
and on gazetted beaches and the
navigation fairway. The existing water
quality at these sensitive receivers can be represented by the closest EPD’s
monitoring station, SM12, as discussed in the previous section 4.3.2.
Cheung Sha Wan Fish Cultural Zone and the fish fry
nursery area located toon the east side of Chi Ma Wan Peninsula and a.
They are not directly affected by the proposed
installation of submarine cables.
Tai Long Wan, Yi Long Wan, Yi Long Pai and Mong
Tung Wan are locateds along the south-west coast of Chi Ma Wan
Peninsula while Tai Kwai Wan, Po Yue Wan, Pak Tso Wan, Nam Tam Wan and Tung Wan
are on Cheung Chau. Only Tung Wan is a gazetted beach.
The
proposed submarine cables are running extend
across the Adamasta Channel. As ships and ferries
travel through this fairway regularly and transverse
the alignment of the submarine cables, the dispersion of the water pollutants may be
complicated. It should be noted that the assessment has not
taken account of propeller wash
as this was deemed to be minor compared to other natural hydrodynamic
forces.
Construction activities include land-based works
for the installation of the underground cable.
Construction activities may cause adverse impacts on the water quality
of the receiving waters due to silt laden runoff, and direct contamination of
waters during construction works.
Potential impacts associated with
the cable laying activities include the physico-chemical changes to the water
column due to the release of suspended solids and the hitherto bound
contaminant. s.
The nature and extent of the impacts depend on the quality of the sediments as well as:
· Dispersion characteristics within the receiving waters
· Method of cable laying
· Rate of cable laying
· Proximity and nature of the sensitive receivers
Environmental impacts
associated with dredging can be subdivided as follows:
·physical effects :
resuspension and redeposition of particles during the dredging operations and
changes in physical habitat due to smothering of benthos.
·chemical effects :
oxidation of released sediments, potential proliferation of bacteria which feed
on resuspended organic matter.
·biological effects :
short term alteration in phytoplankton productivity as a result of decreased
light penetration or proliferation of some species at the expense of others due
to overabundance of nutrients, and adverse impacts of silt and clay particles
on the branchiae of fish, and abrasive effects on crustaceans.
·social implications :
visual impacts of dredging in terms of the recreational use of waters, damage
to commercial fishing grounds or high levels of suspended solids at seawater
intake points.
Key issues which were addressed through this assessment include:
(i) the definition of the extent of the potential sediment contaminationplume; and
(ii) determination of the response of the marine
environment to the potential release into the water column of trace metals and
organic micropollutants from the material being dredged; and
(iii) definition of the mitigation measures
which will minimise the impacts of dredging release of
sediments to the lowest acceptable level.
The geochemical form of trace
metals within sediment samples plays a significant role in determining the
potential impacts on the marine environment.
Although bulk chemical analyses provides an indication of the total
contaminant levels within a sediment sample, the mere presence of a contaminant
does not necessarily infer that it will either have an adverse impact on water
quality or be available for uptake by aquatic organisms.
Metals may be :
(i) bound tightly within the crystalline lattice
structure of the minerals within sediments and are not thus release except
through the weathering process. Such
metals, including aluminium and magnesium, are usually inert and are thus
biologically unavailable;
(ii) bound through a variety of ionic interactions,
involving negatively charged surfaces of minerals or large organic molecules
and positively charged cations including trace metals. Substances in this form, often termed
exchangeable cations, are relatively easily mobilised particularly under acidic
conditions; or
(iii) dissolved in interstitial waters (pores) and
although this fraction is generally relatively small these contaminants are
comparatively easily mobilised and are often available to biota. Contaminants in interstitial waters exist as
free ions, in various organic and inorganic complexes, and their concentration
is independent of the total contaminant level.
Metals, nutrients and organic
materials which are bound into the sediment interstitial waters or adsorbed to
the cation exchange complex, are the most mobile and potentially available
contaminants in dredged material.
Anoxic sediments will frequently contain trace elements which are
readily mobilised.
Contaminants, such as PCBs and
chlorinated hydrocarbons are more complicated than organo-metals as they are
not bound within mineral lattices, they do not occupy positions in clays or
form sulphides or other insoluble compounds, nor are they part of the
exchangeable fraction. Instead,
synthetic organics are almost exclusively found in the adsorbed form, usually
associated with dissolved and particulate organic pollutants and carbon in
sediments, connected to various organic molecules by Van der Waals forces.
Only a fraction of the PCBs
and chlorinated hydrocarbons which are bound to the sediments are available in
the interstitial water of sediments, and therefore it may be concluded that
only a very small percentage of the overall contaminant load will be
bioavailable.
Redox potential (Eh) is one of
the most important factors influencing the remobilization of metals from
sediments. Anoxic sediments which are
characterised by an Eh of -100 mV or less, while well oxygenated waters will,
in contrast, have an Eh of >400mV.
If anoxic sediments are dredged from or disposed of in well oxygenated
waters (i.e. dissolved oxygen levels greater than 4 mg/L), the physio-chemical
state of metals within the sediments may be affected and some metals will
become more mobile.
In addition to redox
potential, the pH of both the sediments and the receiving waters can also
affect the availability of some metals with a consequential increase in the
amount of metal released initially to the water column.
In addition to the increase in
suspended solids to the water column potential impacts also relate to the
possible smothering of benthic biota and marine organisms through irritation of
the gills or other membranes. A change in the deposition layer may result in
the disturbance to the benthic infauna although recent survey data has shown
that the rate of reworking of the seabed is much more rapid than previously
considered and this should not be such a problem as formerly considered.
Another aspect which
has often been considered in assessments of dredging impacts is the change in
dissolved oxygen levels due to the release of suspended solids into the water
column (during dredging). This is a
particular issue if the sediments are heavily contaminated especially with
organic matter. In this regard
however cognisance should be given to the actual field survey data collected by
CLP on another project which involved monitoring of the dissolved oxygen levels
during the dredging works.
During
construction there is the potential for erosion and sediments to be washed into
receiving waters. The potential sources
of these impacts and the potential effects have also been assessed.
Another aspect which has often been considered in
assessments of dredging impacts is the change in dissolved oxygen levels due to
the release of suspended solids into the water column (especially during dredging).
The effects of the resuspension of sediments in
terms of dissolved oxygen depletion has been may be estimated using athe standard relationship relating the
sediment oxygen demand and daily oxygen uptake rate with concentration of
sediment release during dredging. : However such
DOdep = C x SOD x K x 0.001
where DOdep = reduction in dissolved oxygen level in mg/l
C = tidal average suspended solids concentration in
kg/m3
SOD = sediment oxygen demand in mg/kg sediment
K = daily oxygen uptake rate, 0.23
This Such equations provides very conservative results which need
to be subsequently verified during onsite monitoringby collecting sediment samples
from the dredging location and conducting laboratory analyses for SOD. It should be stressed that the sediments in
the area to be disturbed are not generally dredged would
not be expected to be highly
polluted and coupled with a relatively low dredging rate, it would be sediment
release, it is expected
that DO depletion would be negligible and a very transient, situationshort term impact. This has
not in this regard however cognisance should be given
to the actual field survey data collected by CLP on another project which
involved monitoring of the dissolved oxygen levels during the works and
confirmed that the level of dissolved oxygen depletion was negligible.
4.5.3 Modelling Assumptions
Hydrodynamic Regime
As tThe reclamation area on formation
of the temporary working platforms area to the east side of
Pui O beach is small (18055180
m2) and temporary, no and will be
formed behind a seawall with no dredging work will be
involved. Thus As noted
previously, the
water quality impact caused by construction of this temporary working platformreclamation
area is expected to be minimal and negligible when comparing with the laying of submarine cables.
The
temporary working platform was not refore, the
construction of this reclamation was not included in the modelsin the
hydrodynamic models as this facility will be
dismantled following excavation of the tunnel.. The tidal flow
models used for this assessment were therefore not modified to take account of
any potential impediment to flow associated with this project. The model used
was that set up under EPD contract No WP00-84 using the local fine
grid model with a coastline representing the coastline .for the year
2000.
The dredging modelling scenarios
focussed
on disturbance due to laying the submarine cables and used have been modelled using DELFT3D-PART
with the following parameters values:
· settling velocity = 1.28 x 10-4 m/s (based on the fact that sandy marine deposits prevail in the Study Area)
· critical shear stress for sedimentation = 0.05 Pa
· critical shear stress for erosion = 0.1 Pa
· vertical dispersion coefficient in wet season = 10-6 m2/s
· vertical dispersion coefficient in dry season = 10-3 m2/s
·assuming a
release of 400,000 particles to the model
A total of
400,000 particles were The amount quantity of sediment released to the water
column by a dredger is commonly represented by the ‘S’
factor, which is expressed in terms of the total quantity of sediment released
by the dredger per cubic metre dredged, can be used as a reasonable estimate of
the to simulate the quantity of sediment being released resuspended
withininto the water column. According to the “Contaminated Spoil
Management Study, October 1991, undertaken by MCL (then known as Mott MacDonald
Hong Kong Limited), EPD”, the upper limit
of the S factor among the various dredge types a dredger, 30% of sediment loss rate of
30% is the upper level of losses to the water column as a result of
dredging. This was used in the model to
is assumed. This represents a conservative worst
case scenarioeee.vv
For the simulation of the direct burying technique
it was assumed that 100 % of the sediment would be released to the lowest layer in
the water
column (as a worst case assumption). This assumption was
made is because
the direct burying technique essentially
ploughs through the seabed creating a trench and laying a cable at the same
time. It should be stressed that the
material being ploughed is essentially fluidised mud which is not available for
dispersion in the water column. However in order to simulate the worst case
scenario the 100% release rate was used and the assumption made that the effects would be
confined to the bottom layer of the
model (ie the lowest 20% of the water
columniAlso, it is assumed
that 100% of sediment will be resuspended for direct burying. This
allows aIt demonstrates
the worst scenario to
be simulate).
According to the
“Contaminated Spoil Management Study, October 1991, undertaken by MCL (then
known as Mott MacDonald Hong Kong Limited), EPD”, a sediment loss rate of 30%
is the upper level of losses to the water column as a result of dredging. This was used in the model to represent a
conservative worst case scenario and does not allow for any mitigation measures
such as good operational control or control of the rate of lifting of material
or even the effects of using sealed or at least closed grabs. The modelling
assumption made was that the sediment would be released over the extent of the
water column for the dredging scenario to simulate the worst case effects and
also to represent the spillage from grabs during the lifting process.d..
During dredging or other disturbance to the bottom
sediments, materials will be resuspended,
and in accordance with the foregoing the loss rate this
has been assumed to be 30%.
Sediment release rates were calculated using the
following assumptions:
for dredging
·
‘s’ factors taken from the contaminated Spoil Management Study, October 1991
assumed for a bucket type dredger s = 15-30
·
assumed release of sediment was over extent of water column to represent worst case
·
assumed dredging rate was 547m3/day
· 12 hours working day was assumed
·
sandy marine deposits would be dredged and not clay
·
dry density of sediment was 488kg/m3
for direct buying
·
thewo fastest advancing rates wasere assumed to be 150 m/hr and
represented the worst case scenario for the model scenarios to simulate different rates of workassumed
in the model although note however an
assessment to be made a assumption to
be made assumed S=100
(reference to previous report)thereafter
the two rates are referred to as ‘slow’ and ‘fast’ direct buryi ieng; 150m/hr and 400m/hr. Although for the purposes of the assessment the
two rates were used, in
practice the rate of work on-site
is closer to 150m/hr and thus the
focus of attention for the assessment has been placed on the results of
scenarios simulating 150m/hr;
·
the “trench” was assumed to be 3m deep
and 0.3m wide;
·
release of sediment was all assumed to be to the bottom layer of
the model (ie 20% of water column).
The direct burying
method will cover the distance between the two shorelines in a
shorter period of time than
the dredging works. (referred to as the ‘fast’ rate). tTmeans infers
that multitriple A period of 13 weeks
in total has been identified in the progamme given in Section 2 for the direct burying method. The direct burying
simulations have been carried out with releases during a spring and a neap tide assuming one
cable (or multi-core) laid at one time over a seven day period. The model also
assumes releases
of sediment at various points across the channel. This approximates the time varying releases into the water column
as the DELFT3D-PART was not designed to deal with
continuously moving discharge locations.
The progress for dredging is considerably slower
with an advance rate of approximately 4 m/h.
It will take therefore
take
about
13-18 weeks, assuming 12 hour working day, which is considerably more than
a spring-neap cycle. The dredging
scenarios have therefore been carried out for a spring neap cycle.
4.5.4 Assessment Methodology
Once in suspension, fine sediment will be carried by
the tidal currents and dispersedd,
possibly over a large area depending on tidal conditions and the point
of release in the tidal cycles.
During transport by the tidal currents, the fine sediment will tend to
flocculate forming larger particles which will settle under gravity on the
seabed. The rate of settling for
cohesive sediments will depend on the concentration and on the local tidal currents. Once the tidal currents become sufficiently
weak, the sediment will settle to the seabed and begin to consolidate. If the tidal currents become large enough,
the settled material will be eroded and put back into suspension for further
transport by the tidal currents where the rate of erosion will depend on the
tidal currents and the degree of consolidation which may have taken place.
Sediment release rates were calculated using the
following assumptions:
for
dredging
·‘s’
factors taken from the contaminated spoil management study, October 1991
assumed for a bucket type dredger s = 15-30
·assumed
release of sediment was to upper layer of water column to represent worst case
·assumed
dredging rate was 547m3/day
·12
hours working day was assumed
·dry
density of sediment was 488kg/m3
for
direct buying
·advancing
rates of 150 or 400m/hr were used on advise from Contractors as being
achievable rates for undertaking this type of work using available equipment
·assumed
S=100 (reference to previous report)
·trench
assumed to be 3m deep, 0.3m wide
·release
of sediment
The
direct burying methods cover the distance between the shorelines in a short
period. It will take approximately 15
hours to cover the distance of 2300m when using the 150 m/h. Therefore, the direct burying simulations
have been carried out with releases during a spring and a neap tide.
The
progress for dredging is considerably slower with an advance rate of
approximately 4 m/h. It will take
therefore about 13-18 weeks, assuming 8 hour working days, which is
considerably more than a spring-neap cycle.
The dredging scenarios have therefore been carried out for a spring neap
cycle.The DELFT3D-PART model is a
particle tracking model which releases discrete particles that represent the
released sediments. Each released
particle in the model represents a certain mass of sediments. Settling and resuspension are included in
the model, although its main purpose is to simulate the extent of the sediment
plumes. The DELFT3D-PART model is
driven by the hydrodynamic model results from a previous study carried out by
Delft Hydraulics on behalf of the EPD (Local Fine Grid Model of the
North-Western Waters and Western Harbour - WP00-084). The results of the
particle tracking model are based on a grid with cells of 50*50m. All runs were carried out for both the wet
as well as the dry season periods.
Assessments
have been carried out by mathematical models. These are described in details in
Section 4.7.
Assessments of the potential impacts associated
with the off-site discharges have been addressed using a qualitative
approach. Domestic sewage arisings have been considered in
terms of potential waste arisings, location and disposal arrangements.
The maximum
number of construction workers on-site is estimated to be 50 employees. According to the Sewerage Manual (Part 1),
Drainage Services Department, 1995, the flow and loads caused by the
construction workforce can be estimated and the results are presented in Table 4-8.
Table 4-8 Estimated
Flow and Loads Caused by the Construction Workforce
This estimate of liquid waste arisings has not been
included in the model input file as it is not expected to represent a direct
discharge to receiving waters. Rather the wastes will
be treated prior to disposal.
The DELFT3D-PART model was set up
to represent the coastline which was present at the time of the flow
measurements in 20001996. The model validation was carried out for the
two representative tide types – spring and neap during the wet season by using
the Fine Grid Model (FGM). Graphical
presentations of the computational grid and depth schematisation of the FGM are
provided in Appendix D. The simulated results of water level,
depth-averaged current magnitude, salinity and temperature are validated with
update 1997 model results. The
graphical plots are also presented in Appendix D.
For the study of the effects of cable laying between the Chi
Ma Wan Peninsula and
Cheung Chautowards Cheung Chau, a number of (DELFT3D-PART) simulations
of the sediment plumes
plumes that will be generated were
carried out.
The sediment plume model has
been used to simulate the following scenarios which are based on the two previously
definedfollowing cable laying methods. Sediment and associated release rates for each scenario
have been calculated as follows:
·
Direct burying at 150m/hr, with a slow
speed of 150 m/h,
sediment release rate 24.4 kg/s
Iie 150 m per hour
x 0.4 m wide x 3 m deep trench = 180 m3 per hour
180/3600 m3/s
x 488 kg/m3 = 24.4kg/s (removal)
·Direct burying at 400m/hrwith
a fast speed of
400 m/h, sediment release rate 65.1 kg/s
Ie 400 m
per hour x 0.4 m wide x 3 m deep trench = 480 m3 per hour
480/3600
m3/s x 488 kg/m3 = 65.1kg/s (removal)
·
Dredging with a single trench, sediment
release rate 2.8 kg/s
Iie Volume of sediment being disturbed during
dredging = 17.1m2 x 4m per hour
= 68.4 m3 per
hour
Spill rate =
68.4/3600 m3/s x 488kg/m3 x 0.3 = 2.8 kg/s
·
Dredging with three
trenches, sediment release rate 8.34
kg/s
Iie Volume of sediment being disturbed during
dredging = 17.1m2 x 4m per hour x 3 = 205.2 m3 per hour
Spill rate =
205.2/3600 m3/s x 488kg/m3 x 0.3 = 8.3 kg/s
Sediment release rates were calculated using the
following assumptions:
for dredging
·‘s’ factors taken
from the contaminated spoil management study, October 1991 assumed for a bucket
type dredger s = 15-30
·assumed release
of sediment was to upper layer of water column to represent worst case
·assumed
dredging rate was 547m3/day
·12 hours
working day was assumed
·dry density of
sediment was 488kg/m3
for direct
buying
·advancing rates
of 150 or 400m/hr were used on advise from Contractors as being achievable
rates
·assumed S=100
(reference to previous report)
·trench assumed
to be 3m deep, 0.3m wide
·release of
sediment
The direct burying methods cover the distance between the
shorelines in a short period. It will
take approximately 15 hours to cover the distance of 2300m when using the 150
m/h. Therefore, the direct burying
simulations have been carried out with releases during a spring and a neap
tide.
The progress
for dredging is considerably slower with an advance rate of approximately 4
m/h. It will take therefore about 13-18
weeks, assuming 8 hour working days, which is considerably more than a
spring-neap cycle. The dredging
scenarios have therefore been carried out for a spring neap cycle.
The PART model
is a particle tracking model which releases discrete particles that represent
the released sediments. Each released
particle in the model represents a certain mass of sediments. Settling and resuspension are included in
the model, although its main purpose is to simulate the extent of the sediment
plumes. The PART model is driven by the
hydrodynamic model results from a previous study carried out by Delft
Hydraulics on behalf of the EPD (Local Fine Grid Model of the North-Western
Waters and Western Harbour - WP00-084). The results of the particle tracking
model are based on a grid with cells of 50*50m. All runs were carried out for both the wet as well as the dry season
periods.
The following eighttwelve
scenarios were investigated:
·
direct burying, dry season, neap tide @ 150 m/hslow
speed150m/hr
·
direct burying, dry season, spring tide @ 150m/hrslow
speed150 m/h
·
direct burying, wet season, neap tide @ 150m/hrslow
speed150 m/h
·
direct burying, wet season, spring tide @ 150m/hrslow
speed150 m/h
·
direct burying, dry
season, neap tide @ 400m/hr400 m/hfast
speed
·
direct burying, dry
season, spring tide @ 400m/hrfast
speed400 m/h
·
direct burying, wet
season, neap tide @ 400m/hrfast
speed400 m/h
·
direct burying, wet
season, spring tide @ 400m/hr400 m/h
· dredging, single trench, dry season
· dredging, single trench, wet season
· dredging, three trenches, dry season
· dredging, three trenches, wet season
In each scenario, the operation
is assumed to start at Cheung Chau and the location of the installation
activities then moves during the simulation towards Tai Long Wan. Only one cable (or multitriple-core) is assumred to be laid at any given time. Results of the
simulations are presented as numerical values, colour contour plots which are
snapshots of concentrations are a given time and time histories which
illustrate the concentration of suspended solids at a defined location over
time. All
these data are contained in Appendix E with and the results of the itme histories given
in Appendix E indicate the length of time for the status quo to be restored
following a peak concentration.a summary of the peak concentrations
predicted at the sensitive receivers given in Appendix F. A summary of the peak
concentrations is given in Tables 4-.8 and 4-.9 for direct burying
and dredging respectively.
For the direct burying method, each
cale (or triple-core ie 3 ‘strands’) being laid at 150
metres per hour day
will take 15 hours days
and 400 metres per hour will take 6 hours daysfor the operation to traverse the 2300
metres of the Adamasta Channel. The
operators of the cable laying vessels indicate that the faster rate is around 450m/day.
However the assumption made for the model was that if laying the cable of say 10x
the usual speed was acceptable, then the slower speed would also be acce
ptable.
The
specialists who built the model also confirm that the total
amount of sediments released during the direct burying simulations is the same
as derived during the study. This is
because it directly related to the size of the trench, density of the sediments
and loss rate of the method. If the
advance rate is 24 times slower than used in the study, and the total of
released sediments remains as it is, then the release rates for these runs
would be 1/24th of what was prviouslypreviouslyused,
over a period that is 24 times longer. These are considerable differences with what was used in the study. What will be clear is that the peak concentrations as indicated
in the plots that were submitted at the time will overestimate the
concentrations. They can probably be scaled by a factor of 24, although this will not be
exact because there are some non-linear effects for which scaling would not be
valid. Scaling the peaks of the
time-histories will give you an indication of the increases in concentrationse . However, because of the essentially
different nature of the conditions, and the much longer duration of the operation,
the approach of the
modelling should look very similar to the dredging scenarios, which also cover
a longer period.
These spreading of these
sediment releases
plumes
will bewill be affected by the time of ir timing in release into the
tidal cycle. For the spring tide simulations, the cable laying has been assumed
to start a few hours before low-low-water spring. For the neap tide
simulations, the operation has been assumed to start a few hours after
low-low-water neap. The simulations for direct burying last for 7 days.
For Using the traditional dredging techniques at a rate of 4
metres per hour, it will take a period of 575
hours will
be required to traverse the Adamasta Channel. Since, the total dredging
operation will extend well over several spring/neap tidal cycles (~ 15 days), it
make
little does not make much difference when the
dredging starts in the tidal cycle. All of these simulations thus start at
low-low-water spring and continue for 36 days (12 hours/day, 6 days of dredging
followed by 1 day of rest).
Although direct
burying is the preferred option for installing the submarine cables, the actual
installation method employed will depend on the Contractor’s choice. In
addition, a normal advancing rate in the range between 400 and 450 m/day will
be applied for direct burying method. Therefore, the modelling results
demonstrate the worst scenario for direct burying.
Due to the generic nature of the simulations and for the purposes of the presentation of the output time series, the starting date and time of the dredging has been made equivalent to 01 January, at 00:00:00h. The contour plot outputs (as shown in Appendix E) have been presented in terms of the number of hours or days that have elapsed since the start of the dredging.
The resulting sediment
concentrations calculated by DELFT3D-PART represent only the increase in
sediment concentrations above the background concentrations already present.
DELFT3D-PART does not calculate the background concentrations. The background
concentrations have been assumed to be average values using the data provided
by EPD in
their published routine water quality monitoring data as described in t ehe foregoing sections.
This allows the acceptability or otherwise of the marine works to be assessed
using the WQO as the criteria.
Graphical Presentations and Contour Plots
Graphical presentations and the
contour plots of the depth average concentrations of sediments for
comparing the results between extreme
cases (such as dredging 1 trench and
3 trenches on the same plot, two speeds for direct burying ie
“150 m/h slow” and
“400 m/hfast on
the same plot, etc.) are provided in Appendix E. General observations are that the direct burying
method generates a more elongated and distinctive plume compared to the
dredging .
The main features of the scenarios that will
determine the elevated suspended solids concentration is the release rate and
the release period. The
direct burying methods produce significantly higher
release rates, but for shorter periods than compared
to the dredging method. The results of the
dredging simulations also show that when dredging three trenches simultaneously
the results
are of the order of three times that for dredging one trench. The difference between
the methods is directly visible in the results of the simulations. When examining the time-histories of the
model results for the monitoring locations it can be noted that the maximum
concentrations of the direct burying (at 150)) m/h) and the dredging
scenario have the same order of magnitude. with the direct burying being more defined as
a “plume”. The one trench
approach shows concentrations at about one third of the three trench scenarios. whilst the slow150
m/h direct burying results in higher concentrations
than the fast400
m/h rate of advance.
The highest concentrations tend
to be observed within the typhoon shelter of Cheung Chau Wan, which is a
semi-enclosed waterbody with relatively little exchange with surrounding
waters. This
over-exaggerates the potential impacts, because, as indicated in Section 2 the
work carried out in the typhoon shelter will be by hand, by divers and thus the
impacts will be significantly less than predicted by the model.
Here the difference between the direct burying and
the dredging is immediately visible with significantly higher concentrations
for the direct burying methods.
The sediment plumes
from the direct
Although the sediment
plumes for the direct burying method appear to be burying are well defined plumes, which extend
for several kilometers, in particular for the spring tide, in which the
concentrations are simulated to be between 10 and 50 mg/L
for the fast rate of direct burying for a few hours after commencement of the
dredging.and show high concentrations (10-50mg/l) at the centre of the
plume, the
plumes do not impinge on any of the defined sensitive receivers, and noNo exceedancess of
the WQO’s are observed aAt the Cheung Sha Wan Fish Culture Zone (R1) and concentrations of around 1 mg/l were predicted on the spring tide during the
wet season, while at R13 (Tai
Kwai Wan (R13)were likely to be observedconcentrations of around 5mg/l were predicted on the spring tide of the dry
season. The results need to be further examined to
determine whether they exceed the WQO’s and reference is made to the peak values
contained in Table
4.8. This peak concentration only lasts
about four hours for condition
simulated and affects in general the Adamasta Channel and the non-gazetted
beach at Tai Long Wan. The concentrations
drop significantly once the activities are complete,. which, for each
cable, takes about 15 hours (150 m/h). In
about 5-6 hours after cessation of activities, the concentrations in the plume
have reduced to significantly less
than 5 mg/L and from the time histories it is apparent that
restoration to comply with WQO generally takes 2-4 hours. An exception is the station at Po Yue Wan
which is rugged coastline and
not a water
sensitive receiver
where the duration for restoration is slightly longer (except for the wet
season spring tide scenario). For the
spring tide this will last somewhat longer due to the higher current
velocities. The
plumes for the spring tide cover a larger area and are more elongated than for
the neap tide which is a reflection of the tidal excursions and
defines the extent of the impacts in the shorte. term.
It has been demonstrated by the models that by
application of the direct burying method significantly more sediments could be
resuspended compared to dredging, therefore leading to significantly higher concentrations
near the activity with a sediment plume of the order of 1 km or less in which
concentrations may exceed about 50 mg/L as peak values which only last 2-4 hours. The extent of the plume with concentrations
between 10-15 mg/L can be several km in length and confined to the Adamasta Channel and Tai Long Wan non-gazetted
beach. No fish culture zones or fish fry areas are adversely affected.
The plumes ofgenerated as a
result of the
dredging are less well defined, with significantly
lower
concentrations in the vicinity of the dredging activities than for the direct
burying. This
is due to the assumed release rate. Concentrations
exceeding 10 mg/L only occur occasionally and for a few stations and for
relatively short periods. Examples of such behaviour are the monitoring
locations nearest the dredging activities (R11, R12, R15 and R16). These
monitoring locations are all located within all represent the the
Adamasta Channel Some potential
excedances are evident during the wet season at Tai Kwia Wan and as a result further
investigation of the actual peak values is required for which reference is made to Table 4.9..
Numerical Data
According to the results,
it was noted that in some of the contour plots and time series plots, sudden
peaks in the suspended
sediment concentration could be are observed at various
locations away from the actual dredging location. This effect is due to the
resuspension of sediment particles that have settled at these locations at
earlier times. When the shear stress at
a given location exceeds the critical shear stress for erosion, the
resuspension routine in DELFT3D-PART causes all of the settled particles to
instantaneously go back into suspension at this location. Subsequently, the
resulting concentrations probably represent
an over-estimation of the actual values that could be expected at these
locations particularly in the lower layers, but indeed affecting the overall
depth-averaged concentrations.
It
has been demonstrated by the models that by application of the direct burying method
significantly more sediments could be resuspended compared to dredging, and
therefore leads to significantly higher
concentrations near the activity with a sediment plume of the order of 1 km or
less in which concentrations may exceed
about 50 mg/L. The extent of the plume with concentrations between 10-15 mg/L
can be several km in length. However, tThe effects of direct
burying are visible for significantly shorter periods than dredging. The plumes from the dredging method show general concentrations increases concentrations ofin between 5-10 mg/L over
an area of the order of 1-2 km (wet season, 1 trench), but last for the entire
dredging period, which will be in the order of 3 months.
Modelling ResultsNumerical
Data
The results of the Ttwelve scenarios of the water quality assessment for laying the
submarine cables for the Project have been predicted. Details of the predicted
modelling results are given in Appendix F
with the average concentration of .
The 90 percentiles of
suspended solids at the representative monitoring locations for direct burying
and dredging are summarised
in Tables 4-9
&
4-10
and Tables
4-110
& 4-12,
respectively. These results present the impacts predicted for
the release into the water column of a predefined volume of sediment (ie
400,000 particles) using the direct burying technique over a seven day periods4-8… Table
4-9…
.
TAs indicated earlier in this section the WQO’s for SS requires that thatany elevation must be less
than 30% above the natural ambient level which in this case has
been taken to be . For
subzones the annual median is used. Following a review of the contour plots the raw
data were used to
determine whether the elevation of
SS is acceptable due to direct burying.
First the average values of suspended solids, over the seven day period
(as the duration of the works is around
6 days and the models were run for 7 day cycles), were related to the increment
“allowed” in accordance with the WQO (3.9mg/l). Secondly the time history plots were
interpreted to determine the extent and duration of the peak concentrations and
to identify whether, using this and the contour plots together, there would be
breaches of WQO’s at the sensitive receivers.
Table 4-9 Summary of Average
Concentration 90%-ile of Suspended
Solids at the Representative Sensitive ReceiversMonitoring
Locations (Direct Burying)
(All units in mg/L unless otherwise stated; all
figures are upper limits unless otherwise indicated)
Note: Boldfaced
value represents the elevated level of suspended solid exceeding the WQO.
Table 4-10 Summary
of Average Concentration Suspended Solids at the Representative Assessment Points (Direct Burying)
By comparing the predicted results in Table 4-9
with the maximum allowable elevated level (3.9 mg/L), the depth average
concentration of the suspended solids over the seven days cycles at
all the representative monitoring locations except for R24 comply with the
relevant WQO. However Exceedances of the elevated SS occur at R24 (Po Yue
Wan) for both advancing rates (150 and 400
m/h) during the wet season only. Since it is a rugged
coast but not a gazetted beach, it is not a water sensitive receiver. Ppeak
values may be observed which exceed the WQO’s (in Appendix F) but these are
short duration (~ 2-4 hours) and do
not directly affect water sensitive receivers.
It
should also be noted that the model assumed 100% release of sediment to the
water column, which is conservative and thus the results predicted are more
severe than would be expected even under the worst case scenario. Therefore,
the water quality impact is expected to be acceptable. Moreover, with the
implementation of general mitigation measures and pollution prevention
measures, the water quality impact caused by the direct burying method will be
minimal.
It is observed that the elevated SS levels at the
Cheung Sha Wan Fishery Culturale Zone and fish fry
nursery area are predicted to be in the range between 0.0 to 0.57
mg/L so the water quality impacts at these sensitive receivers are may
be surprised surmised to
be minimal for both advancing rates of
work..
The highest average
elevated SS levels at Tung Wan (a gazetted beach) are only 0.1 and 0.2 mg/L for
“slow” and “fast” modelling rates respectively. Therefore, the water quality
impact is expected to be minimal. Some
differences occur in the predicted peak values of the “slow” and “fast” rates
which suggest that the model is exhibiting the effects of longer release times in a grid cell therefore
the peak is more exaggerated in some cases for the “slow” rate of burying combined with flow factors and re-suspension
rates.
For
all other non-gazetted beaches in Table
4-10, the highest predicted average elevated SS levels are 1.9 and 2.2 mg/L
for “slow” and “fast” advancing rates so the water quality impacts are
acceptable.
Anomalies in the results predicted for the For the Cheung Chau typhoon
shelter, the predicted results show
that the advancing rate of 150 m/h generated higher
elevated SS levels than that that 400 m/h ddid.
However, the range of the results is between 0.0 and 30.8
mg/L so the water quality impact at the typhoon shelter is also
falls
within the requirements of WQOminimal. The reason is probably due to the complex
hydrodynamic regime in the vicinity of the breakwater and the influence of
resuspension during the slow advancing rate.
The predicted
SS levels at the gazetted beach, Tung Wan, are well below the acceptable levels
and the predicted results at all other monitoring locations along the coast
except for Po Yue Wan are well within the WQO requirement.
The
predicted elevated SS levels at the Adamasta Channel vary between 0.0 and 1.54
mg/L for “slow” advancing rate of 150 m/h and between 0.0 and 2.01.9
mg/L for the “fast” advancing rate 400 m/h. No exceedance of
elevated SS levels is expected.
For all other non-gazetted beaches in Table 4-10, the highest predicted
average elevated SS levels are 1.9 and 2.2 mg/L for “slow” and
“fast” advancing rates so the water quality impacts are acceptable.
Table 4-10 Summary of Average
Concentration 90%-ile of Suspended
Solids at the Representative Monitoring Locations
(Dredging)
(All
units in mg/L unless otherwise stated; all figures are upper limits unless
otherwise indicated)
Note: Boldfaced value represents the elevated
level of suspended solid exceeding the WQO.
Table 4-12 Summary of Average Concentration Suspended
Solids at the Representative Assessment Points (Dredging)
(All units in mg/L
unless otherwise stated; all figures are upper limits unless otherwise indicated)
In Table 4-10, it
is observed that no exceedances of SS occur at any of the monitoring locations
for dredging one trench. However, there are
predicted exceedances at Cheung Chau typhoon shelter (R22 and R23), Po Yue Wan
(R24) and Adamasta Channel (R11, R15 and R16) for dredging three trenches
simultaneously during the wet season. The exceedances are only slightly above
the maximum allowable elevated level (3.9 mg/L) based on background data which
needs to be confirmed by baseline monitoring before marine works commencing on
this contract so the water quality impacts are not substantially adverse. On
this basis, general mitigation measures and pollution prevention measures are thus would
be recommended in order to reduce the SS level
complying with the WQO requirement. Should dredging three trenches
simultaneously be the option selected by the contractor.
·
Direct Burying
Peak concentrations of SS predicted at the
sensitive receivers for each tide and season are given in Table 4-.8 from which it can be
observed that full compliance with the WQO’s can be achieved regardless of the time of year
the direct
burying works
take place. Interpretation
of the data given in the time histories which illustrates the peak
concentrations, the duration and significance in relation to impacts on water
sensitive receivers are discussed in the following paragraphs.
Using the raw data given
in the time histories contained in Appendix F, it is evident that the peak values
occur mostly in the Adamasta Channel (R9, R10, R15, R32, R36 and R37) with a duration of generally between 2 and 4 hours although up to 8 hours has been simulated.
Predicted peak values in
Cheung Chau Typhoon Shelter can be
discounted because although the model simulated the effects of direct burying
in this typhoon shelter the work will be carried out by hand by divers which
will be significantly less disruptive to the seabed conditions.
At R24 (Po Yue Wan) two peak exceedances of up to 24 mg/l for 2 hours and 14
mg/l for up to 2 hours were predicted.
This is not a water sensitive receiver but rather a rugged coastline. No exceedances of SS were predicted at the
sensitive receivers and with the exception of the predicted elevations at Po
Yue Wan and Pak Tso Wan the effects of direct burying are confined to the works
area in the Adamasta Channel.
However, Aas noted earlier in t hhis section, the actual rates for
direct burying are much slower than those simulated in the model. Taking into
account the various factors which affect the levels of suspended sediments in
the water coulumn it has been surmised that the actual if the
rate of work is slower than that simulated is the models, the actual average
concentrations of suspended solids would comply with the WQO’s (as the volume
of sediment released is the same, albeit
the
sediment is released over the same time but at a slaver rate). The peak concentrations can be divided
by however could
be divided by a factor which represents the slower rate of work ie 6 days
rather than say 6 hours.
Although
the results are not exactly linear, by decreasing the rate by 1/24th, the
peak results would be generally more
representative of those for a slaver rate of work. The model
over-predicts the rate of re-suspension
(apparent on slower rates)
and as such the submission of the peak values by say x 20 to get the revised
maximum concentrations arising from the direct
burying method would still be expected to be conservative. The focus of
attention has been placed on the “Fast” rate of direct burying as this is around 20
times the actual speed of the works to be undertaken. The
results given in Table
4.11
indicate that no
Even if the
average concentrations of suspended sediments of the
unadjusted sediment concentrations are considered,
as given in Tables … and … are used then it may be seen that the re are no
exceedances of the WQO’s (assuming 3.9mg/l is the compliance
threshold).
No exceedances are predicted at
the sensitive receivers even at these peak
concentrations..
Table 4-8 Summary
of Peak Concentration Suspended Solids at the Representative Sensitive
Receivers (Direct Burying)
Direct
Burying |
Advancing Rate = 150 m/hr (Worst Case Scenario) |
||||
Sensitive
Receiver |
Assessment
Point |
Dry Season |
Wet Season |
||
Neap |
Spring |
Neap |
Spring |
||
Cheung Sha Wan Fish Culture Zone |
R1 |
0.0 |
0.0 |
0.0 |
0.5 |
Tai Kwai Wan |
R13 |
1.0 |
3.9 |
0.0 |
0.5 |
The predicted peak elevated SS levels at Cheung
Chau typhoon shelter are in the range between 0.0 and 7.2 mg/L for “slow”
advancing rate and between 0.0 and 14.8 mg/L for “fast” rate. As stated
previously, the submarine cables within the typhoon shelter will be laid by
divers manually instead of using direct burying machine. Therefore, the predicted water quality impact
will be greatly reduced and the exceedances at the typhoon
shelter can be discounted.
The predicted peak elevated SS levels in
the Adamasta Channel are in the range of
0.0 and 8.2 mg/L for “slow” advancing rate and between 0.0 and 19.9 mg/L for the “fast”
rate. Generally Eexceedances of
elevated SS levels only occur
for a short period (~2-4 hours) and
as the average
results demonstrate compliance then water quality can be generally assumed to
be acceptable.
In Table 4-14,
no exceedances were identified at any
of the non-gazetted
beaches. The only exceedance
in the peak concentration is at Po
Yue Wan, which is rugged
coast and is not a
sensitive receiver. In
addition to which the average SS concentration complies with the WQO at this
location.
It should also be noted
that in addition to the fact the results represent the worst case it is not
believed that 100% of sediment would be put into suspension because the
sediments which are finalised and at the bottom on the trench do not enter the
water column and are not available for dispersion off-site.
Notwithstanding this, on
the basis the aim is to protect water quality and marine life, it is proposed
that a ‘rest’ period of contour
be used between finishing the burying operation (by boat) and commencing the
next cable laying operation. The work
done by divers (by hand) in the Cheung Chau typhoon shelter should be exempted
from this vest period as there will be minimal disturbance to the seabed during
hand operations. This rest period has
been assumed on the basis of the time taken for sediments to resettle in the
Adamasta Channel (refer to Appendix F). The time
taken for material to settle, as predicted by the model, is generally around 2-4 hours but as
some longer periods of peak concentrations are simulated it is considered that 6 hours would be an
appropriate rest period noting that in many cases it is apparent that the
settling rate is much faster.
·
Dredging
The predicted peak concentrations
of suspended solids for dredging are illustrated in Table 4-.9.
The dredging
method will not be used for laying the entire cable, but rather will be
used only at the ends of the cable where the water is too shallow to use the
direct burying technique.
Where a single trench
is dredged the model predictions indicate full compliance with the WQO’s (ie over the year) at the Cheung Sha Wan Fish
Culture Zone ( R1). At Tai Kwai Wan beach (R13) the dredging works
can be carried out without any non-compliance during the dry season, but exceed
the WQO’s
if dredging is carried out during the wet season.
No mitigation is therefore required if dredging takes place during
the dry season assuming only a single trench is dredged.
Where dredging is proposed to take place for a
single trench during the wet season the reduction in suspended solids
concentrations needs to be around 55% to ensure compliance with the WQO at the Tai Kwai
Wan beach.
In the event that
dredging is carried out for three trenches simultaneously, then according to the model
predictions breaches of the WQO’s may be expected during both wet and dry seasons at R13 (Tai Kwai
Wan). At the Cheung Sha Wan Fish Culture Zone (R1) the model predicts
compliance during the dry
season but excedance of the WQO’s during the wet season.
The most effective mitigation measures would
like be to limit the dredging in
dry season if the works programme allows.
For the situation where three trenches are proposed to be dredged simultaneously, a reduction of 30% of the suspended solids concentration is required during the dry season. During the wet season the mitigation measures need to effect a reduction of 85% (ie 21.6mg/l) to ensure full compliance with the WQO’s at the sensitive receivers.
No It
is found that all Only minor ’s, and these all take
place in the wet season. The current programme as shown in Section 2 is to
undertake the dredging works during the dry season therefore no problems are
anticipated. Should the Contractor
decide to alter his programme to undertake dredging during the dry season then mitiation measures would be required. As the
modelling scenario assumes no mitigation then it can be surmised that with the application
of the mitigation measures provided in Section 4.6 the impacts would eassily be
reduced by half. This would
ensure compliance. It should furthermore be noted that prior to consrtuction the
predicted exceedances are taking place during the wet season. One way to avoid
potential adverse water quality impacts is to install the submarine cables
during the dry season only. However, it may affect the construction programme.
Alternatively, the baseline at the wet season can be used to determine the WQO
compliance threshold. This may allow a higher ceiling for the elevated levels.
In fact, a baseline water quality monitoring will be carried
out prior to the commencement of the construction. This is more useful to
reflect the conditions of the marine environment. and thus the works
could be carried out either in the wet or dry .season should the
contractor decide to
adopt this method.
Table 4-9 Summary of AveragePeak Concentration Suspended
Solids at the Representative Sensitive Receivers (Dredging)
(All units in mg/L
unless otherwise stated; all figures are upper limits unless otherwise
indicated)
Dredging |
Single Trench |
Three Trenches |
|||
Beneficial Use |
Monitoring Station |
Dry |
Wet |
Dry |
Wet |
Cheung
Sha Wan Fish Culture Zone |
R1 |
0.8 |
2.3 |
2.4 |
6.8 |
Tai Kwai
Wan |
R13 |
1.8 |
8.5 |
5.4 |
25.5 |
Note: Boldfaced value represents the elevated
level of suspended solid exceeding the WQO.
Table 4-10 Summary
of Peak Concentration Suspended Solids at the Representative Sensitive
Receivers (Dredging with Mitigation Measures)
(All units in mg/L
unless otherwise stated; all figures are upper limits unless otherwise
indicated)
In addition, it is
anticipated that the conventional advancing rate for direct burying method will
be much slower (say 400 m/day) than what has
been assumed in the models. The predicted modelling results are based on an
accelerated advance rate which is ten times faster than the usual rate of work
which shows no exceedances of SS levels at the water sensitive receivers.
Direct Burying
Interpretation of the
model results indicates that no mitigation measures are required for direct
burying regardless of the tide and season. Full compliance with the WQO’s at the
sensitive receivers are predicted.
Dredging
It is recognised that although the majority
of the cables will be laid by direct burying, at either end minor dredging works may be required as the shallow depth of
water is unsuitable for the
direct burying machine to operate. Such minor dredging works would best be carried out during
the dry season with a single cable trench being dredged at any given time to ensure
compliance with the WQO’s.
In the event that dredging takes place
during the wet season then additional mitigation measures to be adopted include the
use of closed and sealed grabs. This will reduce the release of sediment by at
least 50% and coupled with a controlled rate of lifting (can be
up to 50% reduction in suspended solids release) of the dredged material will
be adequate to ensure compliance with the WQO’s will be achieved at the sensitive
receivers.
In the event that
dredging three trenches simultaneously is considered the use of closed and sealed grabs will be adequate to achieve
compliance with the WQO’s at the sensitive receivers during the dry season. During the
wet season the combined suite of mitigation measures such as closed and sealed
grabs, controlled lifting
rate and a
reduction in the rate of dredging (by 40%) will be needed to reduce the release of suspended solids to enable compliance
with the WQO’s.
IIn
Summary
The effects of applying mitigation measures to
dredging activities are shown in Table 4-.10 which illustrates that compliance with
the WQO’s can be achieved for both wet and dry seasons.
Simulated worst
possible cases to allow effect of mitigation (if required) were assessed. The
water qualityMitigation assessment has
concluded that mitigation measures may also be
required to minimise the effects of construction on receiving water quality.
These include the control of direct burying/dredging cable trenches, the through the control
of control of surface runoff from sites, during construction and the
provision of appropriate
collection, treatment and disposal facilities for the wastes (liquid and
solid) which are generated during the implementation of the works.
It should also be noted that the extent of mitigation measures will vary depending upon the nature of the contract. In order to provide a cost effective package of mitigation measures which can be included in the environmental requirements of each contract, a suite of general measures have been proposed for the protection of receiving water quality.
Table 4-10 Summary
of Peak Concentration Suspended Solids at the Representative Sensitive Receivers
(Dredging with Mitigation Measures)
(All units in mg/L
unless otherwise stated; all figures are upper limits unless otherwise
indicated)
Dredging |
Single Trench |
Three Trenches |
|||
Beneficial Use |
Monitoring Station |
Dry |
Wet |
Dry |
Wet |
Cheung
Sha Wan Fish Culture Zone |
R1 |
- |
- |
- |
3.4 |
Tai
Kwai Wan |
R13 |
- |
2.1 |
2.7 |
3.9 |
Remarks: -‘-’ complies
with WQO without mitigation measures being applied.
General
Mitigation Measures
·
All waste water generated on the Site shall be
collected, and rremoved from
Site via a suitable and properly designed temporary drainage system and
disposed of at a location and in a manner that will cause neither pollution nor
nuisance.
· The Contractor shall construct, maintain, remove and reinstate, as necessary, temporary drainage works and take all other precautions necessary for the avoidance of damage by flooding and silt washed down from the Works. He shall also provide adequate precautions to ensure that no spoil or debris of any kind is allowed to be pushed, washed down, fall or be deposited on land or on the seabed adjacent to the Site.
· The Contractor shall not permit any sewage, waste water or other effluent containing sand, cement, silt or any other suspended or dissolved material to flow from the Site onto any adjoining land or allow any solid waste to be deposited anywhere within the Site or onto any adjoining land and shall have all such materials removed from the Site.
· The Contractor shall be responsible for temporary drainage, diverting or conducting of open streams or drains intercepted by any works and for reinstating these to their original courses on completion of the Works.
· Any proposed temporary diversions to stream courses or nullahs shall be submitted to the Engineer for agreement one month prior to such diversion works being commenced. Diversions shall be constructed to allow the water flow to discharge without overflow, erosion or washout. The area through which the temporary diversion runs is to be reinstated to its original condition when the temporary diversion is no longer required.
· The Contractor shall not discharge directly or indirectly (by runoff) or cause or permit to be discharged into any public sewer, storm-water drain, channel, stream-course or sea, any effluent or foul or contaminated water or cooling water without the prior consent of the relevant Authority who may require the Contractor to provide, operate and maintain at the Contractor's own expense, within the premises or otherwise, suitable works for the treatment and disposal of such effluent or foul or contaminated or cooling or hot water.
· The Contractor shall at all times ensure that all existing stream courses and drains within, and adjacent to the Site are kept safe and free from any debris and any excavated materials arising from the Works. The Contractor shall ensure that chemicals and concrete agitator washings are not deposited in watercourses.
· All Contractor's Equipment shall be designed and maintained to minimise the risk of silt and other contaminants being released into the water column or deposited in other than designated locations.
General
Pollution Prevention Measures to be Adopted During Dredging
mechanical grabs shall
be designed and maintained to avoid spillage and shall seal tightly while being
lifted; all vessels shall be sized such that adequate clearance is maintained
between vessels and the sea bed at all states of the tide to ensure that undue
turbidity is not generated by turbulence from vessel movement or propeller wash. ;
·
Dredging rate should not exceed 573cu.m/day
·
use of closed and sealed grabs to be used to reduce sediment release
rate by at least 50%;
·
mechanical grabs shall be designed and maintained
to avoid spillage and shall seal tightly while being lifted; all vessels shall
be sized such that adequate clearance is maintained between vessels and the sea
bed at all states of the tide to ensure that undue turbidity is not generated
by turbulence from vessel movement or propeller wash;
·
.d Dredging
rate must be lower than 54784 m3/day during dry season
·
dredging rate must be lower than 3218wet season and shall
not exceed 1094 m3/day
during wetdry
season
(if three trenches
dredged simultaneously);;
·
dredging should preferably be carried out during
the dry season. In the event that
simultaneous dredging of three trenches is proposed then the sediment losses to
the water column must be reduced by 40%;
Dredging should
preferably be carried out during the dry season. In the
event that simultaneous dredging of three trenches is proposed then the
sediment losses to the water column must be reduced by 40%If rescheduled to be carried out during the wet
season then mitigation measures may need to be put in place to reduce the rate
of release of sediment to the water
column by 50%
·
the marine works
shall cause no visible foam, oil, grease, scum, litter or other objectionable
matter to be present on the water within the Site or dumping grounds;
· all barges shall be fitted with tight fitting seals to their bottom openings to prevent leakage of material;
· excess material shall be cleaned from the decks and exposed fittings of barges before the vessel is moved;
·
loading of barges and hoppers shall be controlled
to prevent splashing of dredged material to the surrounding water and barges or
hoppers shall not be filled to a level which will cause overflowing of material
or polluted water during loading or transportation;
;
loading
of barges and hoppers shall be controlled to prevent splashing of dredged
material to the surrounding water and barges or hoppers shall not be filled to
a level which will cause overflowing of material or polluted water during
loading or transportation;
· the Engineer may monitor any or all vessels transporting material to ensure that no dumping outside the approved location takes place. The Contractor shall provide all reasonable assistance to the Engineer for this purpose;
· all vessels used for marine works must be currently registered as such with the marine department; and
·
water quality monitoring shall be carried out by the
Contractor during the dredging.
Requirements and extent of monitoring will be agreed with DEP and the
Engineer.
Specifically: In addition to the
foregoing general protection measures the following control
measures for dredging may also apply in the event that dredging of three trenches is proposedwhen
exceedances of SS levels
at the monitoring locations are identified:
·
use of closed and
sealed grabs to reduce release rate by at least 50%;
·
if programme permits
schedule dredging works during dry season;
·
control release of
suspended sediments to achieve 50% reduction; anduse of closed and sealed
grabs to reduce release rate by at least 50%;
·
dredging works should be scheduled
to take place during the dry season wherever possible; and
·
dredging rate should be lower than 32218 m3/day during wet season.
dredging rate should be
lower than 218down 84achieve 50% reduction. and and
·dredging one trench at a
time.
Specifically;
if dredging one trench at a time is proposed then the following control
measures are proposed:
·use of closed and sealed
grabs to reduce
sediment release rate by at
least 50%;
·the dredger or when dredging works during wet seasone.;
if
programme permits schedule dredging works during dry season..
General Pollution Prevention Measures to be Applied During
Direct Burying
·
other than exerting due care when carrying out the
works, direct burying can be carried out without any special mitigation
measures being required to protect sensitive receivers regardless of the tide
or season.
·other than exerting due
care when carrying out the works, direct burying can be carried out without any
special mitigation measures being required to protect sensitive receivers
regardless of the tide or season.direct
burying techniques should be carried out with a result period of 6 hours
between completion of one cable and laying the next.
·Rr
·between
completing one direct burying activity and commencing the next a rest
period of 6 hours
should be observed to allow the sediment levels to reduce to pre-works levels.
in the event that direct burying techniques generate
suspended solids levels greater than 30% above ambient (to be defined in the
baseline survey Ll)
consideration may need to be given to working within a shield over the face of the
direct burying machine as illustrated on Figure _____.. This is a proprietary piece of equipment
which is essentially a hood placed over the face of the works, it suppresses
the release of suspended solids into the water column by acting as a mobile “barrier” between the seabed and water column
above.
General Pollution Prevention Measures to be
Applied During Placing of Cables in Cheung Chau Typhoon Shelter
·use of silt
screens may be required, either side of the cable laying iof the placing of cables causes elevation in
suspended solids in excess of 30% above the ambient level as defined through the
baseline water quality monitoring data. For the purposes of this assessment
this is assumed to be 3.9 mg/Ll.._____.General Water
Pollution Prevention Measures to be Applied if Drill and Blast Techniques are
Used
·all
wastewater generated must be treated to the appropriate standard given in the
TM on “Standards”.
General Water Pollution Prevention Measures to
be Applied if TBM’s Used
·
all wastewater generated must be treated to the
appropriate standard given in the TM on “Standards for Effluents
Discharged into DraiangeDrainage and Sewerage
Systems, Inland and Coastal Waters”.
·
in the event that conventional sedimentation
techniques are inadequate to treat wastewater
generated, consideration should be given to use of alternative techniques such
as mobile microfiltration plants.
·
all wastewater generated must be treated to the
appropriate standard given in the TM on “Standards for effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters”.
·
in the event that conventional sedimentation
techniques are inadequate to treat wastewater generated, consideration should
be given to use of alternative techniques such as mobile microfiltration
plants.
Residual water quality impact during construction is not expected with the implementation of the pollution control measures.
As discussed in Section 2.5 of
this Report, it has been
confirmed
with relevant Government Departments that tinued that no other works projects are scheduled to overlap with the current Project and as such no
cumulative impact assessment was carried out. t The EIA study for the
project “Reclamation of Sai
Wan Typhoon Shelter and Associated Engineering Works at Cheung Chau” is
at the preliminary stage and it is thus more appropriate that the EIA study for
the reclamation works at Sai Wan takes on board the findings of this EIA Report
with respect to cumulative impacts.
No water quality impact will be anticipated during the operational phase.
With
the implementation of the water quality mitigation measures, no exceedance of
WQO of suspended solids is anticipated at the monitoring locations. However, a
robustTo confirm compliance with the WQO’s it is proposed that
an environmental monitoring and audit programme is established. This will focus on
confirmatory monitoring for the direct burying option, and compliance
monitoring in the event dredging is proposed.
will
be implemented to ensure that the general mitigation measures are effective and
the actual water quality impacts during the installation of submarine cables
and the temporary
working platformreclamation works at
Pui O Beach are acceptable.
Five
wWater quality monitoring points should include
locations at including
Cheung Sha Wan Fish Culture Zone,
Cheung Chau Typhoon Shelter, Tai Kwai Wan, Tai Long Wan, South of Hei Ling Chau Typhoon
Shelter, and Pui O Beach and Adamasta Channel are proposed. The
locations and number of the monitoring points shall be agreed with EPD before
undertaking any works. Details of the water quality monitoring and their monitoring locations will be are presented in the section 4 of Environmental
Monitoring and Audit Manual. .
4.11 Conclusions
It may becan
concluded
that for direct burying method, short term exceedances of peak elevated SS
levels take place especially only at Po Yue Wan during
drywet
season season. At Po Yue Wan these occur on neap
tide for
both the “slow”
and “fast” advancing rates
although it should be noted that average results fully comply with the WQO’s. Since No short term
exceedances occurred any of the sensitive receivers rather they are,
not unexpectedly, observed in the Adamasta Channel and a Po
Yue Wan which
is not a water sensitive receiver, the
predicted SS levels at all the water sensitive receivers comply with the
relevant WQO. Therefore, .
Water quality impacts
associated with the implementation of this Project are acceptable.
The
construction programme has scheduled the cable laying work during the dry
season. The results of the assessment
confirm that cable laying work can be carried out without any adverse water
quality impact during the dry season.
Direct burying is the
preferred option for the cable laying as it is of shorter duration than
dredging, has lesser and acceptable impacts than dredging and can fully comply
with the WQO’s
at the sensitive receivers all year round.
Full compliance with the
WQO’s (throughout the year) has been predicted
for the direct burying option, although confirmatory monitoring is
proposed to ensure water quality at Tai Kwai Wan and Cheung Sha Wan Fish
Culture Zone is not impacted by the cable laying works.
Dredging will not
be carried out for laying the entire length of the cables. Instead, For the minor
dredging works which need
to be carried out for laying either end of the cables (due to the shallow depth
of water). tThe results indicate
that the
WQO’s can be achieved if the single trench dredging option is carried
out during the dry season.
In the event that
dredging needs to take place during the wet season (eg for reasons of
programming) then practical mitigation measures will be needed
to ensure compliance with the WQO’s. For the single trench option mitigation measures
including the use of closed and sealed grabs and through controlling
the rate of lifting will ensure the WQO’s can be achieved.
Although the water quality
impact is acceptable., it has been proposed that a “rest”
period of 6 hours should be observed between the completion of one cable
burying operation (by boat) and commencement of the next cable laying operation. The 6 hour period is based on the time taken
for the sediments to resettle to acceptable levels as shown in the time history
plots in Appendix F. Reference should
be made to these plots relating to the Adamasta Channel and Po Yue Wan where
peak concentrations are observed.
In the event that a
three trench dredging option is considered then mitigation measures would need
to reduce
the impacts by
40% during the dry season (through the use of closed grabs) and by 85% during the wet season (using closed grabs,
controlling the rate of lifting and reducing the dredging rate by a further 40%). All of the foregoing
are practical measures which can be adopted to ensure compliance with the WQO’s.
For the high concentration observed within the typhoon
shelter of Cheung Chau Wan the potential impacts are over-exaggerated because the work
carried out in the typhoon shelter will be carried out by hand using qualified divers. Therefore the impacts will be significantly less than
predicted by the model and no adverse water quality impact is expected.
The construction programme has scheduled the cable
laying work during the dry season. The
results of the assessment confirm that cable laying work can be carried out
without any adverse water quality impact during the dry season. Even cable
laying work is required during the wet season, the water quality can also comply with the
WQO with the implementation of the above-mentioned mitigation measures.
The potential impacts
from off-site runoff can be controlled to acceptable levels. There will be no adverse impact
on water quality arising from the temporary working platform at Pui O. The
facility is only required for the excavation of the tunnel. The working
platform is small (180m2) and will be formed behind a seawall of
concrete blocks with no gaps. Once the excavation has been completed the
working platform will be removed and the shoreline reinstated.Work at Pui O in respect of the
tunnel excavation will not have an adverse impact on water quality as the
working platform is small, a temporary facility and the area will be formed behind a No
exceedances of SS levels at all the monitoring locations are predicted with
dredging one trench or three trenches but
exceedances occur at Cheung Chau typhoon shelter, Po Yue Wan and Adamasta
Channel when three trenches are dredged simultaneously. With
the implementation of the general mitigation measures and pollution prevention
measures, the water quality impacts at the water sensitive
receivers are not expected.Therefore, the water quality impact is acceptable.seawall of concrete blocks with
no gaps.
An environmental monitoring and audit will be
implemented to ensure the general mitigation measures are effective and that
the actual water quality impacts are within the acceptable levels during the
installation of submarine cables and the reclamation temporary working
platformworks at
Pui O Beach.