12
LANDSCAPE
AND VISUAL IMPACT ASSESSMENT
12.1 Introduction
12.1.1
The aim of this section of the
report is to outline the landscape baseline conditions, planning and
development control framework, and the visually sensitive receivers (VSRs). It
identifies the impacts that would occur during the construction of the KCRC
Spur Line between Sheung Shui and Lok Ma Chau Project; and its operational
phase, recommends mitigation measures and identifies residual effects apparent
after mitigation. This section also outlines any cumulative impacts that could
be attributed to the Project.
12.2
Standards
and Legislation
12.2.1
The methodology for undertaking the
landscape and visual impact assessment is in accordance with Annex 18 of the
Technical Memorandum to the Environmental Impact Assessment Ordinance (EIAO).
The assessment has been completed in accordance with Clause 3.13 of the Study
Brief. The main factors influencing the assessment are given below.
12.2.2
The landscape and visual impacts
are considered as follows:
·
landscape impact assessment shall
assess the source and magnitude of developmental effects on the existing
landscape elements, character and quality in the context of the site and its
environs; and,
·
visual impact assessment shall
assess the source and magnitude of effects caused by the proposed development
on the existing views, visual amenity, character and quality of the visually
sensitive receivers within the context of the site and its environs.
12.2.3
The significance thresholds for the
landscape and visual impacts are assessed for the construction phase and
operational phase both with and without mitigation measures.
12.2.4
In order to illustrate these
landscape and visual impacts and to demonstrate the effectiveness of the
proposed landscape and visual mitigation measures, photomontages at selected
representative viewpoints have been prepared to illustrate:
·
existing conditions;
·
unmitigated impacts;
·
partially mitigated impacts after
implementation of the proposed mitigation measures on day 1 of the operational
phase; and,
·
residual impact during year 10 of
the operational phase.
12.2.5
These residual impacts are then
evaluated in accordance with Annex 10 of the Technical Memorandum to the EIAO.
12.3
Landscape
Impact Assessment Methodology
12.3.1
The assessment of the potential
impacts of a proposed scheme on the existing landscape comprises two distinct
sections:
·
baseline survey; and,
·
potential landscape impacts
assessment.
12.3.2
For the Landscape Impact Assessment
(LIA) the assessment area is taken to include all areas within 500m of the
gazetted project limit.
12.3.3
A baseline survey of the existing
landscape character and quality has been undertaken from site inspections and
desktop surveys. Landscape elements considered include:
·
local topography;
·
woodland extent and type;
·
other vegetation types;
·
built form;
·
patterns of settlement;
·
land use;
·
scenic spots;
·
details of local materials, styles,
streetscapes, etc.;
·
prominent watercourses; and,
·
cultural and religious identity.
12.3.4
Planned developments either within
the study area or adjacent to it are also considered. The baseline survey will
form the basis of the landscape context by describing broadly homogenous units
of similar character. The individual landscape character areas (LCA) and
resources are rated using low, medium or high depending not only on the quality
of elements present but also their sensitivity to change and local or regional
importance. The quality of the landscape is not only related to its visual
amenity. The magnitude of change arising from the implementation of the scheme
proposals is rated as negligible, small, intermediate or large.
12.3.5
The assessment of the potential
landscape impacts of the proposals will result from:
·
identification of the sources of
impact, and their magnitude, that would be generated during construction and
operation of the scheme; and,
·
identification of the principal
landscape impacts, primarily in consideration of the degree of change to the
baseline conditions. The impacts are considered systematically in terms of the
landscape elements, the site and its context.
12.3.6
Factors affecting the magnitude of
change for assessing landscape impacts:
·
compatibility of the project with
the surrounding landscape;
·
duration of impacts under
construction and operational phases;
·
scale of the development; and,
·
reversibility of change.
12.3.7
Factors affecting the sensitivity
of for evaluation of landscape impacts:
·
quality of landscape characters /
resources;
·
importance and rarity of special
landscape elements;
·
ability of the landscape to
accommodate change;
·
significance of the change in local
and regional context, and;
·
maturity of the landscape.
12.3.8
The significance threshold for
impacts to landscape character and resources is rated as significant, moderate,
slight or negligible. The impacts may be beneficial or adverse.
12.3.9
The impact is a product of the
magnitude of change, which the proposals will cause to the existing landscape
context, and it's ability to tolerate the change, i.e. its quality and
sensitivity. The significance threshold is derived from the following matrix:
Magnitude of Change caused
by Proposals |
Large |
Moderate Impact |
Moderate / Significant
Impact |
Significant Impact |
Intermediate |
Slight / Moderate Impact |
Moderate Impact |
Moderate / Significant
Impact |
|
Small |
Slight Impact |
Slight / Moderate Impact |
Moderate Impact |
|
Negligible |
Negligible |
Negligible |
Negligible |
|
|
Low |
Medium |
High |
|
|
Sensitivity of Landscape to Change |
12.3.10
The above matrix will apply in the
assessment of the majority of situations, however, in certain cases a deviation
from this may occur, e.g. the impact may be so major that a significant impact
may occur to a landscape character or resource with a low sensitivity to
change.
12.3.11
The significance threshold is
considered as follows:
Negative / Beneficial Impacts |
|||
Significant: adverse/beneficial impact where the proposal would cause significant deterioration or improvement in existing landscape quality |
Moderate: adverse/beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing landscape quality |
Slight: adverse/beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in the existing landscape quality |
Negligible impact: no discernible change in the existing landscape quality. |
12.3.12
A review of the existing planning
studies and documents will be undertaken as part of the assessment to gain an
insight into the planned role of the site, its context and to help determine
the projects fit into the wider existing and future landscape context. The
review is taken from Sheung Shui to Lok Ma Chau. This review considered Outline
Zoning Plan numbers S/NE-KTN/3 – Kwu Tung South and S/YL-ST/4 – San Tin, and
the Recommended Outline Development Plan (RODP) for the Kwu Tung North NDA,
October 1999 which would form the basis for subsequent land use zoning
amendments for the Kwu Tung North area.
Tree Survey
Methodology
12.3.13
To minimise conflicts with existing
vegetation, a full tree survey will be completed in accordance with Planning
Environment and Lands Branch Technical Circular No. 3/94 (Works Branch
Technical Circular No.24/94, Tree Preservation). This will allow the fine
tuning of the proposed detail design for the proposed scheme and ensure that
any significant trees, will where possible, be protected during both the design
and construction periods. The methodology and scope including the programme for
the tree survey and felling application is subject to the approval of the
relevant authorities namely LCSD and AFCD. This section of the report contains
a preliminary assessment of the impact to existing trees and recommendations
for their treatment. The figures contained in this report are subject to the
findings of the detailed Tree Survey Report and Tree Felling Application
currently being undertaken.
Visual
Impact Assessment Methodology
12.3.14
The assessment of the potential
visual impact of the scheme comprises two distinct parts:
·
Baseline survey; and,
·
Visual impact assessment.
12.3.15
For the Visual Impact Assessment
(VIA), the assessment area is taken to include the visual envelope, which
includes all areas from which the scheme proposals can be seen. This area forms
the view shed formed by natural / manmade features such as existing ridgelines,
built development and for example areas of woodland / large trees.
12.3.16
The baseline survey of all views towards
the proposals is undertaken by identifying:
·
The visual envelope as has been
described above and may contain both open and partial views of the proposals.
This must also include indirect effects such as offsite construction
activities; and,
·
The visually sensitive receivers
(VSRs) within the visual envelope whose views will be affected by the scheme.
The potential receivers are considered as three groups:
a)
Views from residences - the most
sensitive of receivers due to the high potential of intrusion on the visual
amenity and quality of life,
b)
View from workplaces - less
sensitive than above due to visual amenity being less important within the work
environment, and;
c)
Views from public areas - including
all areas apart from the above, e.g., public parks, recreation grounds,
footpaths, roads, cultural sites, etc. Sensitivity of this group depends on the
transitory nature of the receiver, e.g. sitting in a park or travelling on a
highway. Also considered is the degree of view or glimpsed views.
12.3.17
However the assessment of
sensitivity has also been based on the quality and extent of the existing view.
Therefore a view from a residential property, which would normally be
considered the most sensitive view, may be less so if, for example, it is
degraded by existing development or partially screened by intervening visual
obstacles such as existing vegetation.
12.3.18
The location and direction of its’
view relative to the scheme also influences the sensitivity of each group.
Typical viewpoints from within each of the visually sensitive groups are
identified and their views described. Both present and future visually
sensitive receivers are considered.
12.3.19
The baseline survey will form the
basis of the visual character and quality of the site. The assessment of the
potential visual impacts will result from:
·
identification of the sources of
visual impacts, and their magnitude, that would be generated during
construction and operation of the scheme; and,
·
identification of the principal
visual impacts primarily in consideration of the degree of change to the
baseline conditions.
12.3.20
The impact assessment will relate
to the typical viewpoints within the visual receiver group, as identified
previously, and their existing and potential views subsequent to the scheme
development. The factors affecting the magnitude of change for assessing the
visual impacts include the following:
·
compatibility of the project with
the surrounding landscape forming the view;
·
duration of impacts under
construction and operational phases;
·
scale of the development;
·
reversibility of change;
·
viewing distance; and,
·
potential blockage of the view.
12.3.21
Factors affecting the sensitivity
of receivers for evaluation of visual impacts:
·
value and quality of existing
views;
·
availability and amenity of
alternative views;
·
type and estimated number of
receiver population;
·
duration or frequency of view; and,
·
degree of visibility.
12.3.22
The views available to the
identified VSRs are rated according to their sensitivity to change using low,
medium or high. Whilst the magnitude of change arising from the implementation
of the proposed scheme is rated as negligible, small, intermediate or large.
The significance threshold for visual impact is rated in a similar fashion to
the landscape impact, i.e. significant, moderate, slight and negligible. The
impacts may be beneficial or adverse.
12.3.23
Therefore the impact is a product
of the magnitude of change, which the proposals will cause to the existing
landscape context, and it's ability to tolerate the change, i.e. its quality
and sensitivity. The significance threshold is derived from the following
matrix:
Magnitude of Change
caused by Proposals |
Large |
Moderate Impact |
Moderate / Significant
Impact |
Significant Impact |
Intermediate |
Slight / Moderate Impact |
Moderate Impact |
Moderate / Significant
Impact |
|
Small |
Slight Impact |
Slight / Moderate Impact |
Moderate Impact |
|
Negligible |
Negligible |
Negligible |
Negligible |
|
|
Low |
Medium |
High |
|
|
Sensitivity of View to Change |
12.3.24
The above matrix will apply in the
assessment of the majority of situations, however, in certain cases a deviation
from this may occur, e.g. the impact may be so major that a significant impact
may occur to a view with a low sensitivity to change.
12.3.25
The significance threshold is
considered as follows:
Negative / Beneficial Impacts |
|||
Significant: adverse/beneficial impact where the proposal would cause significant deterioration or improvement in existing landscape quality |
Moderate: adverse/beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing landscape quality |
Slight: adverse/beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in the existing landscape quality |
Negligible impact: no discernible change in the existing landscape quality. |
Residual
Impacts
12.3.26
The residual impacts are those,
which remain after the proposed mitigation measures have been successfully
implemented. This is assessed both during the construction period and during
the design year, which is often taken to be 10 to 15 years after the proposed
scheme has been opened to normal operation. During the design year the soft
landscape mitigation measures are deemed to have reached a level of maturity,
which allows them to perform their original design objectives.
12.3.27
As has been described above the
level of impact is a product of the magnitude of change, which the proposals
will cause to the landscape character, landscape resource or visual amenity,
and their sensitivity to change. It is a comparison of the future landscape
modified by the proposals with the landscape, which would have existed during
this period if the proposed scheme had not been constructed. This assessment
also considers the ability of the landscape character, landscape resource or
visual amenity to tolerate change, i.e. its quality and sensitivity taking into
account the beneficial effects of the proposed mitigation. The significance
threshold is derived from the matrices described separately above for the
landscape and visual impacts.
12.3.28
In accordance with Annex 10 of the
EIAO TM an overall assessment is also made of the residual landscape and visual
impacts attributable to the proposed scheme. The degree of residual impact is
considered as follows:
Beneficial |
Acceptable |
Acceptable with mitigation |
Unacceptable |
Undetermined |
The project will complement the landscape
and visual character of its setting, will follow the relevant planning
objectives and will improve overall and visual quality. |
There will be no significant effects on the
landscape and no significant visual effects caused by the appearance of the
project, or no interference with key views. |
There some adverse effects, but these can be
eliminated, reduced or offset to a large extent by specific measures. |
The adverse affects are considered too
excessive and would not be reduced to an acceptable level by mitigation. |
Significant adverse effects are likely but
the extent to which they may occur or may be mitigated cannot be determined
from the study. Further detailed study will be required for the specific
effects in question. |
12.4
Mitigation
Measures
12.4.1
The identification of the landscape
and visual impacts will highlight those sources of conflict requiring design
solutions or modifications to reduce the impacts, and, if possible, blend the
development and associated activities in with the surrounding landscape. These
mitigation measures should take into account factors including:
·
woodland, tree and shrub planting
of new or disturbed slopes, amenity strips and areas, central reservations and
adjacent to any new structures;
·
consideration of the contouring of
new slopes in order to blend them in with the existing topography;
·
earth mounding and screening,
structural or vegetated;
·
highlighting unacceptable impacts
and considering alternative scheme proposals;
·
treatment of structural forms;
·
hard landscape, furniture and other
landscape; and,
·
significant landscape elements.
12.4.2
This will result in the formation
of landscape mitigation proposals, which will alleviate the previously
identified landscape and visual impacts as far as possible.
12.5
Existing
Landscape Context and Landscape Impacts
Existing
Landscape Context
12.5.1
The proposed Spur Line alignment is
located in the northern New Territories of Hong Kong between the town of Sheung
Shui and the border crossing at Lok Ma Chau (refer to Figure
12.1). There are several distinct LCAs within the Study Area (refer to
Figures 12.3a-b). These
include the high-rise urban areas of Sheung Shui, the low lying agricultural
areas of the River Beas plain including the Long Valley area, the natural
uplands including mountains, cottage type developments, villages and the fish
pond areas adjacent to Lok Ma Chau.
12.5.2
The proposed Spur Line alignment
arises from the existing KCR East Rail line north of Sheung Shui Station and
follows the existing rail alignment before turning west into a tunnel section
below the River Beas floodplain, the Long Valley area. Immediately north of
Sheung Shui Station the existing and proposed track alignments will be enclosed
by noise barriers (300m long and 5m high to the east and 300m long, 5.8m high
with a 3.6m cantilever to the west of the track alignment). The proposed
alignment will enter the tunnel approach and tunnel portal to the north of Po
Shek Wu Road with a Ventilation Building (75m long, 30m wide and 12.7m high)
being located on the initial tunnel section. The
scheme proposals also include a temporary narrowing of San
Wan Road to the east of the track alignment. The above ground structure of an
Emergency Access Point (EAP) (21m long, 12.5m wide and 10.8m high) will be
located to the south of the proposed alignment on the eastern bank of the River
Sutlej MDC. The construction of the tunnel below the River Sutlej MDC will
require a temporary disturbance of the riverbed. The Long Valley area primarily
comprises agricultural fields, which are generally active, although some areas
are abandoned and have reverted to rough grassland, together with several large
fishponds. Long Valley is bounded on the west by the River Beas, which flows
from south to north. This is currently being improved as part of the overall
flood prevention programme of the New Territories and will be constructed as a
wide concrete trapezoidal channel. The above ground structure of a second EAP
(21m long, 12m wide and 10.8m high) will be located on the western bank of the
River Beas to the south of the alignment.
12.5.3
Beyond the River Beas the Spur Line
alignment continues in tunnel to the south of Ho Sheung Heung village and
through an extensive area of cottage development including Tong Kok, Fung Kong
and Tung Fong. Two temples are located in the south of Ho Sheung Heung. This is
an area characterised by low-rise housing and light workshop/industrial
activities interspersed with tree groups. Within this area the Spur Line tunnel
alignment passes to the north of the Dill’s Corner Camp, the former military
base. Beyond the cottage areas to the south is the dual-3 Fanling Highway
(NTCR) that forms a distinctive landscape character area running east to west
along the southern periphery of the study area. A third EAP (21m long, 12.5m
wide and 10.8m high) with its associated above ground
structure is located to the north west of the Dills Corner Camp. The scheme
will also feature the above ground services cluster associated with the station
box for the future Kwu Tung Station (48m long, 29.2m wide and at the highest
point some 17.3m high although the main part of the structure will be 5.3m
high).
12.5.4
As the Spur Line alignment proceeds
through the cottage areas of the central section of the Study Area its turns south
to avoid the natural lower slopes of the Tit Hang hills. The western tunnel
portal where the vertical alignment rises onto viaduct is located to the south
of Chau Tau. A forth EAP (21m long, 12.5m wide and 10.8m high) with associated
above ground structure is located to the north west of Pak Shek Au and a
ventilation building (15m long, 15m wide and 11m high) located to the south of
Chau Tau at the western end of the tunnel. The hillsides that form the main
enclosure for the valley floor in this area are relatively undisturbed and
comprise a mix of grass and scrub vegetation. The Chau Tau Grenade Range is
located on the upper slopes. The proposed alignment then ascends onto viaduct
(ranging in height between 16 and 20m above the existing ground level) passing
the hillside, through the cottage and agricultural area of Chau Tau. Along this
section the Spur Line runs parallel to Fanling Highway (NTCR), approximately
100m to the north. The remainder of the alignment will be constructed on
viaduct leading to the proposed Lok Ma Chau Terminus. The scheme proposals also
include the widening of Lok Ma Chau Road (the proposed access road for EVA
access and station access) to the west of Chau Tau, and Pun Uk Tsuen. This
emergency access extends to the Sam Chun River before following the southern
riverbank to the proposed Lok Ma Chau Terminus.
12.5.5
Adjacent to the Fanling Highway /
San Sham Road Interchange the Spur Line turns to the north to run parallel to,
and east of, San Sham Road and the Lok Ma Chau Border Crossing facilities. This
is an area comprising a mix of active and inactive fishponds. Some of the ponds
have been filled and now form rough grassland. The Lok Ma Chau border crossing
to the west is characterised by a large area of hard standing and includes built
structures such as kiosks and low-rise administration buildings. The crossing
is currently undergoing an extension to increase capacity requiring the
construction of additional kiosks and waiting areas.
12.5.6
To the north of the border
crossing, the Spur Line turns east, crossing San Sham Road and into an
extensive area of fishponds south of the Sham Chun River. The Spur Line
terminates at this point with the proposed Lok Ma Chau Terminus. It is proposed
that the Terminus will be a four-storey building, approximately 27m high with a
total site area of approximately 1250m by 500m, will contain border-crossing
facilities with a double deck pedestrian bridge over the Shan Chun River to the
Peoples Republic of China. A second station complex, Huanggang Station, will be
constructed on the northern side of the Shan Chun River connected to the Lok Ma
Chau Terminus by the proposed pedestrian link or footbridge. Beyond the river
is the large and visually prominent high-rise city of Shenzhen. The
construction of the viaduct for the station approach will also require a
diversion of the existing CLP 132kV power lines.
12.5.7
The existing landscape quality and
sensitivity of the study area, which varies along the proposed Spur Line alignment,
is shown on Figures 12.3a-b.
The hills of Tit Hang and Fung Kong Shan are of a high landscape quality and
sensitivity due to their undisturbed and natural character. The fishpond areas
to the west of the hills at Tit Hang are considered to be of high landscape
quality and hence highly sensitive to construction works of this type. The
agricultural areas are of a high to medium quality due to their low level
of disturbance and relatively open nature and as a landscape resource, although
the retraining of the River Beas will detract from the landscape quality of
Long Valley. Cottage and village areas are generally considered as being of
a medium quality due to the presence of the local landscape features such
as the temples at Ho Sheung Heung and the extent of the existing mature tree
groups although this quality is degraded in locations due to the level of
disturbance. Areas of low quality landscape character include Sheung Shui,
the road corridor along the Fanling Highway (NTCR) due to the high levels
of disturbance and lack of landscape features, and the urban area north of
the Shan Chun River due to the level of built development. Tables 12.1 and
12.2 give a brief description of the landscape resources and landscape character
areas found within the study area.
Unmitigated
Impacts on Landscape Character, Quality and Resources
12.5.8
The works include, as has been
described above, the construction of a tunnel section from Sheung Shui to the
village of Chau Tau extending west below Long Valley, the River Beas, Kwu Tung
and Pak Shek Au. Beyond this point the Spur Line vertical alignment rises onto
viaduct as the alignment turns north and runs through the road corridor and
open storage areas adjacent to San Sham Road, before proceeding over the
fishponds at Lok Ma Chau. The Spur Line alignment then continues west crossing
the border crossing before terminating at the proposed Lok Ma Chau Terminus on
the Sam Po Shue fishponds. The pedestrian link across the Shan Chun River north
of the station complex, which provides a physical connection to the proposed Huanggang
Station, would have little perceivable impact on the landscape character and
quality of the study area.
12.5.9
The use of the proposed tunnel
section from Sheung Shui to Chau Tau means that for a large part of the scheme
the predicted landscape impacts will be generally centred around the proposed
above ground structures. These include a Ventilation Building at the eastern
tunnel portal, an EAP Shaft on the eastern bank of the River Sutlej, an EAP
structure on the western bank of the River Beas, entrances to Kwu Tung Station
including the proposed services cluster with an adjacent EAP shaft and a final
EAP shaft to the north of Pak Shek Au. There would also be a ventilation
building to the east of the western tunnel portal. These above ground
structures would lead to the loss of landscape resources, and disturbance to
the existing and future landscape character in the immediate however these
impacts would be largely localised due to the enclosed nature of the existing
landscape context.
12.5.10
For the remainder of the alignment
west of Chau Tau, impacts from the above ground section of the alignment, which
is built on viaduct, will be generally being confined to areas adjacent to the
alignment. The use of the tunnel section will avoid impact to the sensitive
agricultural areas in the River Beas Plain / Long Valley area. The main
predicted impacts on existing landscape character will occur in the areas west
of Chau Tau, together with the fishpond areas at Lok Ma Chau and Sam Po Shue.
However, the direct impacts on specific landscape elements have been minimised
as much as a possible though the design of the viaduct alignment for the Spur
Line. There would be a small loss to the existing Fung Shui woodlands near Lok
Ma Chau Road (approximately 0.02 hectares), other woodlands within the study
area would not be subject to lose due to the selection of a route alignment,
which avoids contact with these culturally sensitive landscape resources. The
location of these Fung Shui woodlands is shown in the Ecology Chapter of this
report.
12.5.11
The proposed widening of Lok Ma
Chau Road would lead to the temporary loss of the existing mature trees lining
the road. This would have a temporary significant adverse impact on the
landscape character of the area adjacent to the existing road corridor. However
as with the impacts described above the landscape of the area west of Chau Tau
and Pun Uk Tsuen is enclosed by existing vegetation and built development and
so the impacts would be largely localised. The construction of the proposed access
road for EVA access and station access to the west of Ha Wan Tsuen although
crossing an area of existing fishponds is located adjacent to the Lok Ma Chau
Border Crossing and so disturbance to the existing landscape resources and
character is minimised as far as possible.
The proposed western section of the road on the southern bank of the
Sham Chun River is located in area already degraded by the highly engineered
form of the river and so impacts to the existing landscape resources and
character would be minimal.
12.5.12
The proposed alteration to the
existing CLP 132kV power line to the east of the Lok Ma Chau Border Crossing
would have a beneficial impact on the landscape character of the area through
the proposed burying of the cable in this area up to a location near to the
Fanling Highway.
Impacts on
Existing Landscape Resources
12.5.13
An important determinant of the landscape
character within a Study Area, which is largely rural, is the type and extent
of its landscape resources both natural and cultivated. These landscape resources
are shown on Figure 12.2a
- b. For the purposes of this
assessment the landscape resources are represented by the existing land cover.
The condition of these landscape resources is also important in determining
the landscape quality of the Study Area and its sensitivity to change. Therefore
the preservation and enhancement of these landscape resources is important
to the successful integration of the proposals into the landscape of the Study
Area. Table 12.1 below describes the abundance of a landscape resource within
the Study Area, the loss of this resource due to the proposals and the predicted
impact of this loss on the resource and the landscape character of the Study
Area.
Impacts on
Existing Trees Identified in the Tree Survey Report
Existing Trees
12.5.14
There are approximately 3,200 trees
within the Gazettal Boundary for the proposed scheme. These are mainly
concentrated in the central and western sections of the Study Area.
Tree Retention
12.5.15
Generally any trees or tree groups
on the fringes of the proposed track construction would be maintained where
possible. The extensive construction of the embankments and viaduct structures
would involve in some cases partial removal of tree groups. Where possible, the
proposed earthwork slopes both in cutting and on embankment would be feathered
at the edge of the slopes to allow trees to be retained. However, where it is
not possible to retain trees it is recommended that these trees be felled or
transplanted.
12.5.16
Approximately 1,150 of the trees surveyed
would be retained under the current proposals, these include roadside trees not
affected by the proposed realignment.
Tree Transplantation Proposals
12.5.17
In terms of assessing the
feasibility of transplanting the trees, the following factors were taken into
account:
·
Trees were to have above average
form, health and amenity value.
·
Trees assessed as having a high or
at least medium amenity value and predicted survival rate.
·
Trees should be native or rare
species.
·
Ease of access - In some cases
transplantation would be difficult and dangerous due to the physical
characteristics of the site and the inaccessibility of their situations.
·
The physical characteristics of the
specimen trees - For example, the trees on steep slopes respond to the existing
gradient with a higher proportion of roots on the downhill side and the root
ball usually forms itself to the angle of slope. It is often difficult to find
a similar location that is suitable for the transplantation of these trees. In
addition, these trees often have an unbalanced crown that would make them
unstable if transplanted to another location.
·
Transplantation back onto a slope
is often not practicable due to the difficulty of gaining safe access due to a
combination of the nature of the slopes, the gradients involved and the
stability of the machinery used.
·
The survival rate of trees would be
improved if a permanent location could be found immediately after being lifted
as opposed to the use of a temporary holding nursery.
12.5.18
Taking all these factors into account
the tree survey report recommends that approximately 250 trees could be
transplanted. These are mainly trees surveyed individually and are accessible
to the road. The trees to be transplanted include those situated along San Wan
Road and those lining Lok Ma Chau
Road. The tree survey report recommends that the trees identified as being
appropriate for transplantation are relocated in locations identified through
consultation with LCSD, HyD and / or AFCD. It is not recommended that the trees
be transplanted to a temporary holding nursery for the duration of the railway
construction contracts due to the potential damage that the trees will suffer
if they are moved twice and the likely costs involved in setting up a holding
nursery.
Tree Felling Proposals
12.5.19
The Tree Survey Report concludes
that it would not be feasible to retain or transplant approximately 1,800 of
the existing trees for the following reasons:
·
In some locations the scope of the
proposed works and site formation precludes any opportunities to retain
existing trees.
·
The slopes are too steep to enable
machinery access to transplant them.
·
The necessary excavation and
cutting into slopes, means it is technically unfeasible to retain the trees.
·
The trees are of poor quality in
terms of form or health.
·
The tree if retained in a solitary
position would become unstable and dangerous in windy conditions.
·
Trees, which are too large or
mature to be transplanted successfully.
Table 12.1: Existing Landscape Resources and Predicted Impacts (Refer to Figures 12.2a-b)
The table below presents the
unmitigated and mitigated (residual) impacts arising from the scheme proposals
during the construction and operational phases of the project. The mitigated
residual impacts are assessed during the design year which for the purposes of
this study is taken as being between 10 and 15 years after the schemes opening
when the proposed mitigation planting is deemed to have reached a level of
maturity, which is sufficient for it to perform the design objectives.
Landscape
Resource |
Total
Area of Resource / Total Loss of Area (Ha) / % Loss |
Sens. |
Mag
of Change (Con / Oper phase) |
Impact
on Landscape Character resulting from the loss of the Existing Landscape
Resources. |
Significance Threshold (Unmitigated) |
Mitigation Measures |
Significance Threshold (Mitigated) |
||
Con |
Oper |
Con |
Oper |
||||||
Fung Shui Woodland |
17.81/
0.02 / 0.1% |
High |
Small to Negligible Small / Small to Negligible |
The main area of woodland lost would result from the Lok
Ma Chau Road widening required as part of the Spur Line proposals. This loss
would not have a significant adverse impact on the landscape character of the
Study Area as the existing Lok Ma Chau Road already severs this area of
woodland. Also the area lost forms a small percentage of the total area of
Fung Shui woodland. |
Slight adverse |
Slight adverse |
Reinstatement
of planting along trackside where lost. The design
of noise mitigation measures to be responsive to the existing landscape and
minimise impacts on the existing landscape character. |
Slight adverse |
Slight adverse |
Woodland (including secondary forest and plantation
forest) |
48.00
/ 0.16 / 0.3% |
Medium |
Intermediate / Small |
These areas form an important landscape and visual
resource within the Study Area and include for the purposes of this
assessment those trees lining San Wan and Lok Ma Chau Roads. Although these
temporary impacts would be significant in these locations generally the
overall impact would be minimal in terms of the impact on the overall
existing resource and thus would not have a significant impact on the
landscape character of the Study Area. Also a large proportion of the area
lost is in the central section of the route alignment, which now forms the
site for the future Kwu Tung North NDA. |
Moderate adverse |
Moderate adverse |
Reinstatement
of naturalistic planting adjacent to the periphery of the proposed station
complex and the more formal landscape treatment of the complex site. The
footbridge has been designed to be a visually light structure through the use
a large transparent sections. Replanting
of trees lining San Wan and Lok Ma Chau Roads. |
Moderate adverse |
Slight adverse |
Orchard |
10.91
/ 0.52 / 4.8% |
Medium |
Small / Small |
The loss of these areas of orchard mainly situated in the
central section of the proposed Spur Line alignment, adjacent to the above
ground structures, would not have a significant adverse impact on the future
landscape character area which will be the site for the Kwu Tung North NDA.
The landscape character of the NDA will be very different to that which
currently exists. The landscape mitigation proposed for this area has been
designed to screen the Spur Line in low and medium level views whilst
visually integrating the form of the proposed earthworks and track in more
elevated views from the proposed high-rise residential development associated
with the NDA. |
Slight adverse |
Slight adverse |
Compensatory
planting for the loss of this resource would not be appropriate due to the
future landscape character of the Kwu Tung North NDA. Also the proposed
planting lining the track has been designed to screen low and medium level
views of the Spur Line proposals from the proposed NDA residential
development. |
Slight adverse |
Slight adverse to negligible impact |
Agricultural
Land (Dry) |
34.41
/ 0.09 / 0.26% |
Medium |
Negligible / Negligible |
None of
the existing resource within the important landscape area of Long Valley will
be lost due to the adoption of the tunnel option. |
Negligible Impact |
Negligible Impact |
None
required |
Negligible Impact |
Negligible Impact |
Agricultural Land (Wet) |
14.25
/ 0.0 / 0.0% |
Medium |
Negligible / Negligible |
None of
the existing resource within the important landscape area of Long Valley will
be lost due to the adoption of the tunnel option. |
Negligible Impact |
Negligible impact |
None required |
Negligible impact |
Negligible impact |
Agricultural Land (not currently cultivated) |
20.06
/ 0.55 / 2.3% |
High |
Small / Small |
The loss
of 2.3% of this agricultural land. None of the existing resource within the
important landscape area of Long Valley will be lost due to the adoption of
the tunnel option. |
Slight adverse |
Slight adverse |
None
required |
Slight adverse |
Slight adverse |
Fishpond Areas |
92.15
/ 9.6 / 10.4% |
High |
Small / Small |
The loss of approximately 10.4% of the fishponds in the
study area would have moderate impact on the overall resource in terms of
landscape character. A large part of the fish pond areas lost would be due to
the proposed Lok Ma Chau Station complex, and although the loss of this area
would represent the erosion of a limited resource in the HK SAR, the location
of the area is contiguous with existing development and so its loss would not
significantly affect the landscape character of this area. |
Moderate adverse |
Moderate adverse |
The existing fishponds within the Study Area affected by
the Spur Line proposals would for a large part be restored following the
construction period. A comprehensive mitigation scheme is proposed for
ecological impacts and this would enhance the ecological function of an area
of approximately 36ha fishponds and marsh. |
Moderate adverse |
Negligible impact |
Marsh |
1.67
/ 0.00 / 0% |
Medium |
Small / Small to Negligible |
None of
the existing resource within the important landscape area of Long Valley will
be lost due to the adoption of the tunnel option. |
Moderate adverse |
Moderate adverse |
Although a
relatively large area of marshland and reed beds would be created as part of
the ecological mitigation for Lok Ma Chau Station it would not be necessary
from landscape impact perspective. |
Moderate adverse |
Slight adverse |
Watercourses |
56.97
/ 0.04 / 0.1% |
Medium |
Small to negligible/ Small to negligible |
Many of the larger existing watercourses
within the Study Area, which influence its perceived landscape character,
have been modified by man; these include the retrained river channels to the
east the River Beas, Shek Sheung River and Shan Chun River. Therefore any
further modifications made as a result of the Spur Line proposals would have
no significant impact on the existing resource. In terms of smaller watercourses the main
types are the man made ditches which are characteristic of the long Valley
area. These are characterised by their earth banks, whilst some are
constructed of artificial materials. These would not be affected by the
proposals. |
Slight adverse |
Slight adverse |
Compensatory
mitigation measures for the minor loss of this resource should focus on the
improvement of the existing landscape character of the watercourses affected.
|
Slight adverse |
Slight adverse |
Grass / Shrub Mosaic |
8.05
/ 0.02 / 0.2% |
Medium |
Small / Small to Negligible |
The main
areas of this resource are situated on the hill slopes of the mountains to
the north of the Study Area and would not be affected by the Spur Line
proposals. |
Slight adverse |
Slight adverse |
Compensatory
mitigation measures for the modest loss of this resource were not thought
appropriate, as the main area of loss would be adjacent to Tong Kok, which
forms part of the future Kwu Tung North NDA. |
Slight adverse |
Slight adverse to negligible impact |
Key: Sensitivity of Resource (Sens): Low, Medium or High
Magnitude of Change (Mag): Negligible, Small, Intermediate or Large
Significance Threshold: Negligible, Slight, Moderate and Significant (adverse or beneficial)
Impacts: Refer to matrix and table in the introductory section of the LVIA
Con – Construction Phase
Oper – Operational
Table 12.2: Existing Landscape Character
and Landscape Impacts (Refer to Figures
12.3a-b)
The following table presents the
predicted unmitigated and mitigated (residual) impacts for the proposed scheme
during the construction and operational phases of the project. The mitigated
residual impacts are assessed during the design year which for the purposes of
this study is taken as being between 10 and 15 years after the schemes opening
when the proposed mitigation planting is deemed to have reached a level of
maturity, which is sufficient for it to perform the design objectives. It
should be noted that, with the exception of the area immediately north of the
existing Sheung Shui Station, noise barriers were not considered necessary for
this scheme.
Landscape
Character Area (LCA) |
Sens |
Mag
of Change (Con
/ Oper phase) |
Main
Impacts on Landscape Character Area |
Impact Significance Threshold (Unmitigated) |
Mitigation Measures |
Impact Significance Threshold (Mitigated) |
|||
Con |
Oper |
Con |
Oper |
||||||
Major Urban Development |
|
|
|
|
|
|
|
|
|
MUD 1: Sheung Shui Sheung Shui is located at the eastern end of the study area and
bounded by Fanling Highway (NTCR) to the south. The conurbation is dominated
by a mix of low, medium and high-rise buildings in dense clusters separated
by open space, amenity and undeveloped areas. The southern part of the LCA
contains the more modern developments of the new town areas comprising the
high-rise residential estates. Included within this unit is a former
Temporary Housing Area, which is now under redevelopment and the Sheung Shui
Sewage Treatment Works. The existing KCR East Rail line is a major feature of
the area. The high level of disturbance and lack of key landscape features
result in a landscape value of low quality and sensitivity to further change. |
Low |
Intermediate / Intermediate |
Relatively minor disturbance to
vegetative buffer along existing KCR line (R & C) Introduction of noise attenuation
barriers to east (160m long and 4m high) and west (160m long, 4.4m high with
a 2.5m cantilever) of existing KCR East Rail north of Sheung Shui station (C) Introduction
of additional rail infrastructure within urban areas and adjacent to new
developments including ventilation building (75m long, 30m wide and 12.7m
high) (C) Introduction
of EAP Structure east of the River Sutlej MDC (21m long, 12.5m wide and 10.8m
high) (C) |
Moderate adverse |
Moderate adverse |
Reinstatement
of planting along trackside where lost including the restoration of the soft
landscape areas lining San Wan Road. The design
of noise barriers to be responsive to the existing landscape and minimise
impacts on the existing landscape character. Careful
design of the facades of the proposed above ground structures associated with
the tunnel section and screen planting within the project limit. |
Moderate adverse |
Moderate adverse |
|
MUD 2 Kwu Tung North New
Development Area The NDA is
conceived as a high-rise residential, commercial, business use and government
/ institutional development which will replace the existing largely cottage
type development in the valley situated south of the Fung Kong Knolls and
north of the NTCR. The central area of the new town will be characterised by
the Town Park and the railway reserve above the proposed Spur Line Tunnel
section. It is proposed that these measures in addition to the proposed
landscape framework and urban design concept to create a high quality urban
environment for the future residents of Kwu Tung North. |
Medium |
Negligible /
Small to Negligible |
Spur Line, constructed in tunnel, will be in place prior to the first
population intake of the Kwu Tung North NDA. However the proposed above
ground structure including the station entrances and the EAP will be visible
to future VSRs. The introduction of the proposed above ground services cluster 48m
long, 29.2m wide and at the highest point some 17.3m high although the main
part of the structure is 5.3m high) (C). The introduction of EAP Structure north of Pak Shek Au (21m long,
12.5m wide and 10.8m high) (C). |
Negligible as
the Spur Line proposals will be completed prior to the first population
intake. |
Slight adverse
to negligible impact |
The
proposed railway will be constructed in tunnel and so for the large part no
landscape mitigation will be required. However there will be a number of
above ground structures such as the EAP and station entrances, which will
require sensitive landscape treatment in order to minimise impact. This
treatment includes the use of screen planting and the finishes of the
proposed structures. |
Negligible as
the Spur Line proposals will be completed prior to the first population
intake. |
Slight adverse
to negligible impact |
|
Lowland Agricultural Areas |
|
|
|
|
|
|
|
|
|
L1 North of Sheung Shui A large area of active agriculture to the east of the study area.
Tree groups, primarily comprising fruit species and concentrated around the
sporadic housing. The occasional fishpond is also present. The relatively low
level of disturbance, together with the area's intervisibility with
surrounding landscape together with its role as a buffer adjacent to Sheung
Shui has imbued this area with a relatively high sensitivity to change. |
High to medium |
Negligible / Negligible |
Area remote from works resulting in no impact |
Negligible impact |
Negligible impact |
None
required. |
Negligible impact |
Negligible impact |
|
L2 River Beas Plain / Long
Valley and Fung Kong This is a large area located to the east of the study area in the
lower lying areas adjacent to the River Beas and the villages of Fung Kong
and Tong Kok. The field pattern is complex and mature with most of the fields
being actively cultivated, although there are several areas, which are unused
and have reverted to rough grassland. Several fishponds are present to the
west. Tree vegetation is generally sparse and restricted to field boundaries,
adjacent to local houses and, together with bamboo clumps, along the banks of
the River Beas. The river is part of a separate strategy for flood
alleviation in the New Territories. The retrained river channel when complete
will be approximately 20m, trapezoidal section concrete channel with planted
external embankments. This channel will detract from the overall character of
the area. As part of the mitigation for the project areas of wetland will be
created in several of the remnant meanders. The agricultural areas are of
importance due to their relatively low level of disturbance, their role as a
landscape buffer to Sheung Shui although the proposed channel detracts from
the overall quality. |
High |
Small to negligible / Negligible |
No direct impact
to the Long Valley area. Introduction of the proposed emergency vehicle access / escape
staircase / assembly area adjacent to the River Beas MDC works. The EAP
Structure (21m long, 12m wide and 10.8m high) on the western bank of the
River Beas MDC. Adjacent to this structure will be an area of hard standing
for car parking and to provide an assembly area (C). Introduction of
EAP Structure east of the River Sutlej MDC (21m long, 12.5m wide and 10.8m
high) (C). |
Slight adverse |
Negligible impact |
Proposed
soft landscape mitigation measures on the periphery of the sites for the EAP
structure west of the River Beas, and the EAP structure and ventilation
building east of the River Sutlej. This
treatment also includes the design of the finishes for the proposed
structures. |
Slight adverse |
Negligible impact |
|
L3 North of Ki Lun Shan A small area to the south of Fanling Highway dominated by agriculture
although several areas are unused and are being developed reducing their
perceived landscape quality and sensitivity to further change. |
High |
Negligible /
Negligible |
Area remote from works resulting in no impact |
Negligible impact |
Negligible impact |
None
required. |
Negligible impact |
Negligible impact |
|
L4 Chau Tau This is a smaller area located towards the west of the study area
adjacent to the Fanling / San Sham Road Interchange. The area comprises
fields, which are generally still cultivated and have a complex and mature
field pattern. They form an important buffer between the local roads and the
villages and are of importance due to their relatively undisturbed nature and
sensitivity to change. |
Medium |
Large to Intermediate /
Intermediate to Small |
Disturbance to field
patterns and vegetation including trees. (C & R) Construction of the proposed
tunnel portal, tunnel approach ramp and viaduct sections. (C) Introduction
of the proposed ventilation building and hard standing south of the village
of Cha Tau and north of Castle Peak Road. (15m long, 15m wide and 11m high)
(C). Introduction
of tunnel portal and approach ramped viaduct ascending to maximum height of
approximately 16m above the existing ground level) (C). |
Significant adverse |
Moderate adverse |
Screen
planting adjacent to above ground structures and restoration of disturbed
areas. This treatment also includes the design of the finishes for the
proposed structures. |
Moderate adverse |
Slight adverse |
|
Natural
Upland Areas |
|
|
|
|
|
|
|
|
|
NUA
1 Tai Shek Mo and Tung Kong Shan These areas are located to the
east of the study area, north of the Spur Line and comprise of the natural
slopes of Tai Shek Mo and Tung Kong Shan. The lower slopes are vegetated with
trees with the upper levels dominated by scrub and grassland. The upland
areas are of high quality and a major natural resource locally providing a
major buffer to the sprawl around the villages of Tong Kok and Fong Kong.
These areas also have an important role in forming the landscape setting for
the valley and have a strong influence on the areas landscape character. Low
levels of disturbance resulting in high sensitivity. |
High |
Negligible / negligible |
Area remote from works resulting in no impact |
Negligible Impact |
Negligible Impact |
None
required |
Negligible impact |
Negligible impact |
|
NUA
2 Ki Lun Shan Located to the south of the Spur
Line and Fanling Highway, this is an extensive are of the natural Ki Lun Shan
hillside. Woodland belts fringe lower slopes with the upland areas dominated
by shrub and grassland. The hill provides containment and is a landscape
buffer to the Fanling Highway. Low levels of disturbance and natural
character result in high quality and sensitivity. |
High |
Negligible / negligible |
Area remote from works
resulting in no impact |
Negligible impact |
Negligible impact |
None
required |
Negligible impact |
Negligible impact |
|
NUA
3 Lok Ma Chau Located to the north of the Spur
Line this area comprises the hillsides of Lok Ma Chau and a lower knoll to
the east. These are primarily natural slopes and important local landscape
features providing a buffer to the cottage sprawl to the south and forming
the landscape setting of this area. The lower slopes are vegetated with tree
groups with the upper levels being characterised by scrub and grassland. The
slopes are generally undisturbed and, despite the presence of the power
lines, are of high quality and sensitivity to further change. |
High |
Negligible / negligible |
Area unaffected by works
resulting in no impact |
Negligible impact |
Negligible impact |
None
required |
Negligible impact |
Negligible impact |
|
Village Areas |
|
|
|
|
|
|
|
|
|
V1 Sheung Shui This cluster of villages is located at the eastern end of the study
area and comprise the following: Man Hang Tsuen; Po Sheung Tsuen; Wai Lai Tsuen; Heung Yat Tsuen; Tai Yue Tsuen; Cheung Sum Tsuen; Ha Pak Tsuen; and, Sheung Pak Tsuen. These villages are definable as separate in terms of their landscape
character and perceived landscape quality, although their proximity results
in a visual coalescence forming what is perceived as a single settlement
overall. The villages are low-rise and comprise generally modern village
houses in a regimented layout orientated to the southwest. Liu Man Shek Tong
(Ancestral Hall) is present to the north of the settlements. Tree planting is
present. |
Medium |
Negligible / Negligible |
Area largely remote from works resulting in no impact with the
exception of the areas contiguous with the existing track to Lo Wu where
there would be temporary adverse impacts from the relocation of existing
facilities such as footpaths, cycle park, trackside roads and footbridges
crossing the proposed alignment. There would also be some temporary adverse
impacts from the proposed temporary works area east of Cambridge Plaza. |
Negligible
Impact |
Negligible
Impact |
None
required |
Negligible impact |
Negligible impact |
|
V2 Tai Tau Leng A small village to the east of the study area comprising low-rise
houses. Trees are present, primarily on the outskirts. |
Medium |
Negligible / negligible |
Area remote from works resulting in no impact |
Negligible impact |
Negligible impact |
None
required |
Negligible impact |
Negligible impact |
|
V3 Tsung Pak Long Located at the eastern end of the study area to the south of the Spur
Line. The village primarily comprises modern houses; however, several
traditional vernacular buildings and structures are present including the
original village wall, which encloses a section of the village to the south.
This results in a higher landscape quality and sensitivity. |
High |
Negligible / negligible |
Area remote from works resulting in no impact |
Negligible impact |
Negligible impact |
None
required |
Negligible impact |
Negligible impact |
|
V4 Ho Sheung Heung A medium sized village with a more open layout located to the north
of the Spur Line. In general, the houses are modern although two temples are
also present to the south, together with several ruins of more traditional
buildings and structures. The presence of the temples and the village’s
proximity to the open expanse of Long Valley results in a high landscape
quality and sensitivity to change. However the existing storage areas to the
south east of the village have lead to erosion of both the landscape quality
and its sensitivity to further change. |
High to medium |
Small to negligible / Small to negligible |
Area largely remote from
works resulting in minor indirect impacts due to the above ground structure
of the proposed EAP. Introduction of the proposed emergency vehicle access / escape
staircase / assembly area adjacent to the River Beas MDC works. The EAP
Structure (21m long, 12m wide and 10.8m high) on the western bank of the
River Beas MDC. Adjacent to this structure will be an area of hard standing
for car parking and to provide an assembly area (C). |
Slight adverse
to negligible impact |
Slight adverse
to negligible impact |
None
required |
Slight adverse
to negligible impact |
Slight adverse
to negligible impact |
|
V5 Pun Uk Tsuen and Chau
Tau Two small villages to the west of the study area comprising low-rise
housing with clusters of trees. |
Medium |
Negligible / negligible |
Area remote from works resulting in no impact |
Negligible
Impact |
Negligible
Impact |
None
required |
Negligible impact |
Negligible impact |
|
Cottage Areas |
|
|
|
|
|
|
|
|
|
C1 Ho Heung Sheung This is located to the east of the Ho Heung Sheung village and
comprises a broad mix of land use and development including open storage,
sporadic agriculture, fish ponds, workshops and houses. Tree groups of
primarily native and fruit trees are present. The perceived landscape quality
and the areas sensitivity to further change would have been high due to
features such as the fishponds and areas of mature fruit trees has been
eroded by the presence of existing storage areas. Therefore this area has a
medium level of perceived landscape quality and sensitivity to further
change. |
Medium |
Small to negligible / Small to negligible |
Area largely remote from
works resulting in minor impacts due to the above ground structure associated
with the proposed EAP. Introduction of the proposed emergency vehicle access / escape
staircase / assembly area adjacent to the River Beas MDC works. The EAP
Structure (21m long, 12m wide and 10.8m high) on the western bank of the
River Beas MDC. Adjacent to this structure will be an area of hard standing
for car parking and to provide an assembly area (C). |
Slight adverse
to negligible impact |
Slight adverse
to negligible impact |
Landscape
planting adjacent to the proposed EAP structures to screen the development
from the remainder of the LCA and integrate it into the existing landscape
framework. The
external appearance of the structure should also be carefully considered. |
Slight adverse
to negligible impact |
Slight adverse
to negligible impact |
|
C2 Tung Fong This is a large area of cottage development central to the study area
and comprises a mix of development and land uses including low-rise housing,
open storage, workshops, and small areas of agriculture, warehousing, graves
and Dill’s Corner Camp. Remnant tree groups are present with species varying
from native to fruit trees and with more ornamental amenity species. There
are also areas of high-disturbance and platform formation reducing the
overall landscape quality and the character areas sensitivity to further
change. |
Low |
Intermediate / Small to negligible |
Disturbance to the overall
mixed development Construction
of the proposed Kwu Tung Station (please refer to the dimensions described
under MUD 2 Kwu Tung North New Development Area above) with excavation and
temporary works area causing disruption to the existing landscape character. Introduction of the
proposed emergency vehicle access / escape staircase / assembly area north of
Po Lau Road and the EAP above ground structures. Disturbance to several tree groups and temporary adverse
impact from the temporary works areas, located in the former military base at
Dills Corner Camp. |
Moderate adverse
|
Slight adverse
to negligible impact |
Restoration
of works areas and screening planting adjacent to the above ground structures
associated with the Kwu Tung North station entrances and the EAP. This
treatment also includes the design of the finishes for the proposed
structures. |
Moderate to
slight adverse |
Negligible
impact |
|
C3 Chau Tau A large area adjacent to the villages of Chau Tau and Pun Uk Tsuen
and comprises a mix of houses, workshops, several fishponds and small
agricultural areas. Several areas also comprise orchards in the north. The
relatively low level of disturbance compared to other cottage areas result in
a medium quality |
Medium |
Intermediate /
Intermediate to Small |
Introduction of the proposed viaduct structure as a new
infrastructure element within the landscape with localised impacts.
Introduction of the proposed ventilation building and hard standing south of
the village of Cha Tau and north of Castle Peak Road. (15m long, 15m wide and
11m high) (C). Introduction of tunnel portal and approach ramped viaduct
ascending to maximum height of approximately 16m above the existing ground
level) (C). Main part of the area largely unaffected by works with the exception
of the widening of Lok Ma Chau Road for emergency vehicle access and station
access leading to the loss of roadside trees. |
Moderate adverse |
Moderate adverse |
The
protection of existing trees during the construction period and compensatory
tree planting to replace those trees lost. This treatment also includes the
design of the finishes for the proposed structures. |
Moderate to slight adverse |
Slight adverse to negligible impact |
|
Road
Corridor and Linear Development |
|
|
|
|
|
|
|
|
|
RC1 Fanling Highway The road corridor, comprising the Fanling Highway, runs east west
through the southern part of the study area. This is a dual-3 road and is
generally vegetated along the roadside with a mix of trees, shrubs and grass.
Tree species present include Acacia
confusa and Melaleuca leucadendron. Adjacent to the road is
local development including open storage, some residential development and
workshop areas. The high level of disturbance and lack of features result in
an overall low landscape quality and sensitivity to further change although
the roadside planting are an important landscape element both from within and
without the character area. |
Low |
Negligible / negligible |
Area remote from works
resulting in no impact and screened by existing roadside trees. |
Negligible
Impact |
Negligible
Impact |
None
required |
Negligible impact |
Negligible impact |
|
RC2 Lok Ma Chau Border
Crossing This area is located to the west of the study area and includes the
border crossing and San Sham Road. This is a large area of hard standing and
includes the kiosks and low-rise administration buildings. Several areas of
young Casuarina equisetifolia
planting is present which screens the crossing from external views, together
with some ornamental planting within the kiosk area. The crossing is
currently undergoing extension to increase capacity requiring additional
kiosks and waiting areas. Areas of open storage are adjacent to the road to
the south. |
Low |
Negligible / negligible |
Area remote from works
resulting in no impact and screened by existing roadside trees. |
Negligible
Impact |
Negligible
Impact |
None
required |
Negligible impact |
Negligible impact |
|
Fishponds |
|
|
|
|
|
|
|
|
|
F1 River Beas Plain Located to the north east of the study area and north of the Spur
Line adjacent to the River Beas. The ponds are generally in active use
although several areas are used for agriculture. Several isolated low-rise
buildings are also present. The low level of disturbance and susceptibility
to change result in a high landscape quality and sensitivity to further
change. |
High |
Negligible / Negligible |
Area unaffected by works resulting in no impact |
Negligible
Impact |
Negligible
Impact |
None
required |
Negligible impact |
Negligible impact |
|
F2 Lok Ma Chau A smaller area of fishponds between the Lok Ma Chau village and Shan
Chun River, and also the border crossing, generally in active use. Several
isolated buildings are also present |
High. |
Large / Large |
Disturbance to the existing
fishponds requiring temporary filling during works, although this is
localised to the alignment Introduction of the
proposed emergency vehicle access / escape staircase / assembly area north of
Lok Ma Chau Control Point Introduction of viaduct
section ranging in height from 16 to 20m above the existing ground level (C). |
Significant adverse localised to the alignment |
Significant adverse localised to the alignment |
Replacement
of fishponds below viaduct Screen
planting along the boundary of the proposed station complex and emergency
area. |
Significant adverse localised to the alignment |
Significant adverse localised to the alignment |
|
F3 Sam So Shue This is an extensive area of fishponds to the west of the study area,
which are generally in active use. Isolated buildings are also present. The
extent and sensitivity of the ponds results in a high level of landscape
quality and sensitivity to further change despite the proximity of the Shenzhen
Strategic Economic Zone to the west of the border. |
High |
Large / Large |
Disturbance to, and loss of the existing fishponds to the north due
to the construction of the station complex. Introduction of viaduct
section ranging in height from 16 to 20m above the existing ground level (C). Introduction of the
Terminus complex with a total site area of approximately 1250m by 500m. The
main building would rise approximately 27m above the surrounding ground
level. (C & R). |
Significant
adverse localised to the station area |
Significant
adverse localised to the station area |
Replacement
of wetland areas adjacent to site. |
Significant
adverse localised to the station area |
Significant
adverse localised to the station area |
|
Key: Landscape
Sensitivity (Sens): Low,
Medium or High
Magnitude of Change (Mag): Negligible,
Small, Intermediate and Large
Significance Threshold: Negligible,
Slight, Moderate and Significant (adverse or beneficial)
Residual
Impacts: Refer
to matrix and table in methodology section
Con
– Construction Phase
Oper
– Operational
Summary
12.5.20
The existing landscape context of
the study area is a diverse range of landscape character from the high-rise
urban areas of Sheung Shui to the natural uplands of the surrounding hillsides
and agriculture of the low-lying areas. The corresponding quality of these
areas also varies with a combination of high, medium and low landscape quality.
The sensitivity to change of these landscape character areas varies from a high
sensitivity in the River Beas Plain / Long Valley areas and the Sam So Shue
fishpond areas, to the low sensitivity of the Sheung Shui, Tung Fong and Lok Ma
Chau Border Crossing areas.
12.5.21
The nature of the project including
the proposed use of a tunnel section, and a construction method, which
restricts the works to a working corridor close to the proposed route
alignment, would minimise and localise the impacts. However, the proposals
would lead to significant adverse in the areas of higher quality, namely the
fishpond and agricultural areas at the western end of the route alignment.
Within the other areas, primarily the cottage areas, the impacts would be
reduced to moderate adverse, as these areas would be less sensitivity to the
proposed works. Whilst in Long Valley and Kwu Tung the impacts would range
between slight adverse and negligible due to the use of a tunnel section.
12.5.22
The implementation of the Spur Line
proposals would lead to the loss of 0.02 hectares of Fung Shui woodland (0.1%
of the total resource in the Study Area), 0.16 hectares of woodland (0.3% of
the total resource in the Study Area), 0.52 hectares of orchard (4.8% of the
total resource in the Study Area), 0.55 hectares of agricultural land not
currently cultivated (2.3% of the total resource in the Study Area), 0.09 hectares
of active dry agricultural land (0.26% of the total resource in the Study
Area), 9.6 hectares of fishponds
(10.4% of the total resources in the Study Area), 0.04 hectares of watercourses
(0.1% of the total resource in the Study Area) and 0.02 hectares of grass /
shrub mosaic (0.2% of the total resource in the Study Area). No wet
agricultural land or marsh will be impacted by the alignment.
12.5.23
With the exception of the existing
orchard areas and the fishpond areas, these losses represent a small percentage
of the total area of the respective landscape resources within the study area,
typically less than one percent. The most significant losses from a landscape
character perspective are those of the fishponds, which represent a limited
resource in the context of the HKSAR. The impact on the landscape character of
these remaining fishpond areas has been minimised to an extent through the
location of the Lok Ma Chau Terminus complex in a situation contiguous to
existing development such as the Lok Ma Chau Border Control Point. The use of
the proposed tunnel section will largely avoid losses to the existing landscape
resources in the eastern and central section of the alignment with the
exception of the footprints of the above ground structures.
12.5.24
A total of approximate
3,200 trees have been identified in the survey within the Gazettal Boundary,
1,150 can be retained in situ and 2,050 will be affected by the works. Of these 2,050 affected trees, it is proposed that approximate 250
are transplanted and the remaining approximate 1,800 are felled.
12.5.25
The planned developments that will
form the future landscape context are identified in the Review of Planning and
Development Control Framework below.
12.6
Review
of Planning and Development Control Framework
Existing
Planning Context and Impacts
12.6.1
A review of the existing planning
studies and documents was undertaken to gain an insight into the planned role
of the site, its context and to help determine the projects fit into the wider
existing and future landscape context. This review considers areas that will be
physically affected by the proposals that is where the implementation of the
development proposals would lead to the actual loss of an area. The assessment
also considers the potential degradation of the landscape setting of an area
which might affect the viability of its’ landscape planning designation but not
result in a loss of land area. A review of the existing planning and
development control framework is presented as Table 12.3 below. The details
presented in this table form the basis of a separate chapter on Land Use
(Chapter 14) as required by the Study Brief Clause 3.1 (xvi).
Table 12.3: Review of Existing Planning and Development Control
Framework (Refer
to Figures 12.4a-b)
The information
shown in this table and that shown on Figure
12.4a–b has been obtained
from Outline Zoning Plan numbers S/NE-KTN/3 – Kwu Tung South and S/YL-ST/4
– San Tin. The Recommended Outline Development Plan (RODP) for the Kwu Tung
North New Development Area (NDA) was released to the public in October 1999.
It will form the basis of the subsequent land use zoning amendments for the
NDA. Reference has been made to the RODP to gauge the impact of the proposed
Spur Line within the planning context of this new urban development. The review
is taken from Sheung Shui to Lok Ma Chau. The table presents the predicted
unmitigated and mitigated (residual) impacts arising from the proposed scheme
during the construction and operational phases of the project. The mitigated
residual impacts are assessed during the design year, which for the purposes
of this study is taken as being between 10 and 15 years after the schemes
opening. During the design year the proposed mitigation planting is deemed
to have reached a level of maturity, which is sufficient for it to perform
the design objectives.
Planning Designation /
Location |
Approx. Area Affected by
the Proposals |
Sens |
Mag of Change (Con /
Oper Phase) |
Planning Intention of Zoning / Primary Source of
Impact |
Impact Significance Threshold
(Unmitigated) |
Mitigation Measures |
Impact Significance Threshold
(Mitigated) |
||
Con |
Oper |
Con |
Oper |
||||||
Kwu Tung North Strategic Growth Area (NDA)
Recommended Outline Development Plan (RODP) October 1999. |
|||||||||
1. Sheung Shui to Lok Ma Chau Spur Line |
0.5Ha |
Low |
Large beneficial / Large beneficial |
The proposed
Spur Line alignment has been safeguarded within these proposals; the track
would bisect the proposed residential development, physically separating the
two areas. There would be no loss of land to the areas identified under the
RODP. The RODP allows for an approximately 84 metre corridor for the proposed
Spur Line to pass through however following the initial construction period a
large part of the land would be available for alternative land uses. The NDA
has been designed to accommodate the proposed rail corridor, and the future
design would consider the potential use of this area. Therefore based
on the NDA proposals shown in the RODP the proposed Spur Line would not
affect the planning designation for the NDA area. In fact the construction of
the proposed railway would facilitate the development of a ‘rail-based
development’ for Kwu Tung North NDA one of the basic premises of its
sustainable planning principles. |
Moderate beneficial in that the scheme would facilitate the Spur Line
proposals. |
Moderate beneficial |
The mitigation
measures for the Spur Line have been described in detail in section 12.8
below. However the use of the proposed tunnel section will be the primary
mitigation measure. Other measures include the restoration of disturbed
landscapes, the implementation of planting proposals adjacent to structures
particularly the above ground structures associated with the tunnel section
and the extensive planting on the periphery of the Lok Ma Cha Terminus
complex. The railway reserve above the tunnel section in Kwu Tung North NDA
would also allow the implementation of a large landscape area through the
centre of the new town. |
Moderate beneficial |
Moderate beneficial |
2.
Other Specified Uses ( Wetland Conservation Area) (West
of Sheung Shui and north of Yin Kong) |
0.0Ha |
High |
Negligible / Negligible |
The planning
intention of this designation is to safeguard good quality agricultural land.
This area of agricultural land would be bisected by the proposed Spur Line
alignment, although the use of a tunnel section would avoid any potential
adverse impact of the proposed scheme and ensure that it remains a viable
agricultural area. |
Negligible Impact |
Negligible Impact |
None required. |
Negligible Impact |
Negligible Impact |
3. Government / Institution or Community (Area D8 north of the proposed Spur
Line) |
0.0Ha |
High |
Negligible / Negligible |
The planning
intention of this designation is to provide sites for Government, Institution
or Community facilities serving the needs of the local as well as district
population. The proposed alignment would be contained within a tunnel section
and so it would not have an adverse impact on potential users of this site
although the viability of the planning designation would not be affected by
the proposals. |
Negligible Impact |
Negligible Impact |
None required,
however the proposed railway reserve will provide an opportunity as part of
the NDA proposals to create a central landscaped area, which will contribute
to the quality of the future urban environment. |
Negligible Impact |
Negligible Impact |
4. RS, (Area D7 Residential site with a plot
ratio of 6.5) |
0.0Ha |
High |
Small to Negligible / Small to Negligible |
The planning
intention of this zone is to provide low-density housing and so future
residents would form VSRs. The proposed Spur Line alignment to the south of
this site would be contained in tunnel and so there would be negligible
landscape and visual impacts. The planning
intention of this zone is to provide housing and so future residents would
form VSRs. The proposed Spur Line alignment to the south of this site would
be in tunnel and so not visible to future residents. However there would be
some above ground structures such as the proposed station entrances and EAP
structure. The design of these structures to be responsive to the future
landscape of the proposed Town Park and the use of tree and shrub planting
would serve to visually soften the form of the structures. |
Negligible Impact |
Negligible Impact |
The Spur Line
proposals will be completed prior to the first population intake for the NDA.
The proposed railway reserve above the tunnel section will not be landscaped
as part of these proposals. However the
design of the future NDA should consider this area ‘s potential for enhancing
the open space framework with the future urban environment. |
Negligible Impact |
Negligible Impact |
5. PSPS / HOS D4 |
0.0Ha |
High |
Small to Negligible / Small to Negligible |
The planning
intention of this zone is to provide low-density housing and so future
residents would form VSRs. The proposed Spur Line alignment to the south of
this site would be contained in tunnel and so there would be negligible
landscape and visual impacts. The planning
intention of this zone is to provide housing and so future residents would
form VSRs. The proposed Spur Line alignment to the south of this site would
be in tunnel and so not visible to future residents. However there would be
some above ground structures such as the proposed station entrances and EAP
structure. The design of these structures to be responsive to the future
landscape of the proposed Town Park and the use of tree and shrub planting
would serve to visually soften the form of the structures. |
Negligible Impact |
Negligible Impact |
The Spur Line
proposals will be completed prior to the first population intake for the NDA.
The proposed railway reserve above the tunnel section will not be landscaped
as part of these proposals. However the
design of the future NDA should consider this area ‘s potential for enhancing
the open space framework with the future urban environment. |
Negligible Impact |
Negligible Impact |
6/7. District Open Space D3/B6 |
0.0Ha |
High |
Negligible / Intermediate beneficial |
The planning
intention of this zone is to designate existing and proposed open spaces so
as to provide active and passive recreational opportunities to serve the
district population. The proposed Spur Line alignment to the south of this
area would be largely contained in tunnel with the proposed station entrances
and EAP structure being above ground. The design of
these structures to be responsive to the future landscape of the proposed
Town Park and the use of tree and shrub planting would serve to visually
soften the form of the structures. The 84 metre wide rail corridor through
the NDA would be available for alternate land uses such as augmenting the
proposed Town Park District Open Space although these details will be
established in the NENT Study. |
Negligible Impact |
Moderate beneficial impact |
As 4 above. |
Negligible Impact |
Moderate beneficial impact |
8. RS / PSPS / HOS B4 (Private Sector Participation Scheme /
Home Ownership Scheme Site with a plot ratio of 6.5) |
0.0Ha |
High |
Negligible / Small to negligible |
The planning
intention of this zone is to provide housing and so future residents would
form VSRs. The proposed Spur Line alignment to the south of this site would
be in tunnel and so not visible to future residents. However there would be
some above ground structures such as the proposed station entrances and EAP
structure. The design of these structures to be responsive to the future
landscape of the proposed Town Park and the use of tree and shrub planting
would serve to visually soften the form of the structures. |
Negligible Impact |
Slight adverse to negligible |
As 4 above. |
Negligible Impact |
Slight adverse to negligible |
9. RS B3 (Residential site with a plot ratio of 5.0) |
0.0Ha |
High |
Negligible / Small to negligible |
The planning
intention of this zone is to provide housing. The proposed Spur Line
alignment to the south of this site would be would be largely contained
within the proposed tunnel section with the above ground structures of the
station entrances and EAP being visible. The design of these structures to be
responsive to the future landscape of the proposed Town Park and the use of
tree and shrub planting would serve to visually soften the form of the
structures. |
Negligible Impact |
Slight adverse to negligible |
As 4 above. |
Negligible Impact |
Slight adverse to negligible |
10. R (2) F3 (Residential site with a plot ratio of 5.0) |
0.0Ha |
High |
Negligible / Small to negligible |
The planning
intention of this zone is to provide housing. The proposed Spur Line
alignment to the north of this site would be would be largely contained
within the proposed tunnel section with the above ground structures of the
station entrances and EAP being visible. The design of these structures to be
responsive to the future landscape of the proposed Town Park and the use of
tree and shrub planting would serve to visually soften the form of the
structures. There would be a residual negligible impact due to the Spur
Line proposals. |
Negligible Impact |
Slight adverse to negligible |
As 4 above. |
Negligible Impact |
Slight adverse to negligible |
11. R (1) F2 (Residential site with a plot ratio of 6.5) |
0.0Ha |
High |
Negligible / Small to negligible |
The planning
intention of this zone is to provide housing and so future residents would
form VSRs. The proposed Spur Line alignment to the south of this site would
be in tunnel and so not visible to future residents. However there would be
some above ground structures such as the proposed station entrances and EAP
structure. The design of these structures to be responsive to the future
landscape of the proposed Town Park and the use of tree and shrub planting would
serve to visually soften the form of the structures. |
Negligible Impact |
Slight adverse to negligible |
As 4 above. |
Negligible Impact |
Slight adverse to negligible |
12. R (1) F1 (Residential site with a plot ratio of 6.5) |
0.0Ha |
High |
Negligible / Small to negligible |
The planning
intention of this zone is to provide housing and so future residents would
form VSRs. The proposed Spur Line alignment to the south of this site would
be in tunnel and so not visible to future residents. However there would be
some above ground structures such as the proposed station entrances and EAP
structure. The design of these structures to be responsive to the future
landscape of the proposed Town Park and the use of tree and shrub planting
would serve to visually soften the form of the structures. |
Negligible Impact |
Slight adverse to negligible |
As 4 above. |
Negligible Impact |
Slight adverse to negligible |
13. R (2) F4 (Residential site with a plot ratio of 5.0) |
0.0Ha |
High |
Negligible / Small to negligible |
The planning
intention of this zone is to provide housing. The proposed Spur Line
alignment to the north of this site would be would be largely contained
within the proposed tunnel section with the above ground structures of the
station entrances and EAP being visible. The design of these structures to be
responsive to the future landscape of the proposed Town Park and the use of
tree and shrub planting would serve to visually soften the form of the
structures. |
Negligible Impact |
Slight adverse to negligible |
As 4 above. |
Negligible Impact |
Slight adverse to negligible |
14 / 15. OU Business Uses E3 (Other Specified Uses) |
0.0Ha |
High |
Negligible / Small to negligible |
The planning
intention of this area is to provide a flexible zoning catering for uses such
as distribution and logistics. The proposed Spur Line alignment to the north
of this site would be in tunnel although there may be views of the proposed
EAP structure to the northwest. |
Negligible Impact |
Slight adverse to negligible |
As 4 above. |
Negligible Impact |
Slight adverse to negligible |
16.
Green Belt
(East of Tit Hang) |
0.0Ha |
High |
Negligible / Negligible |
The planning
intention of this area is to define the limits of urban development areas
through the use of natural features, to contain urban sprawl and provide
passive recreational areas. The proposed track alignment would be contained
in a tunnel section and with the exception of the proposed EAP structure
would not impact on the Green Belt area. Therefore although this area is
important to the existing landscape character, and will be more so when the
NDA proposals are implemented, the predicted residual impacts would be negligible
in significance. |
Negligible Impact |
Negligible Impact |
None required. |
Negligible Impact |
Negligible Impact |
Outline Zoning
Plan S/YL- ST/4 – San Tin |
|||||||||
17. Green Belt (West of Tit Hang) |
5.0Ha |
High |
Small / Small to Negligible |
The planning
intention of this area has been described above. The proposed track alignment
would pass through the southern lowland part of this designated area. The
eastern part of the alignment within this Green Belt area is characterised by
existing cottage areas with a disturbed landscape character and an inherent
low landscape quality, therefore losses to this area would not affect the
viability of the Green Belt designation. The eastern
section of the Spur Line rising from the tunnel section onto viaduct to the
south west of Chau Tau would cross the remnant agricultural field areas south
of the village; this area currently provides a landscape buffer between the
village and the Open Storage areas west of Lok Ma Chau Road. This is an
important landscape resource for the area and so the direct loss or indirect
disturbance of a large part of this section of the Green Belt would have a
moderate adverse impact on the landscape setting of the village. The main
area of loss will occur due to the proposed above ground structures
associated with Ventilation Building, EAP structure and tunnel portal at the
western end of the tunnel section. However in
general terms the main landscape resources for which this area is currently
important and will be more so during the future following the implementation
of the Kwu Tung North NDA proposals are the wooded hill slopes to the north
of Pun Uk Tsuen. There would be no direct impacts on these hill slopes
however there may be some slight adverse impacts on the visual amenity and
the landscape character of the area. Although a more pronounced impact on the
landscape character of this area will occur due to the implementation of the
proposed Kwu Tung North NDA. |
Moderate adverse |
Slight to moderate adverse |
The design of
the structures including the tunnel portal, retaining walls, and the
ventilation building should be responsive to the existing landscape
character. Soft landscape measures including tree planting will be utilised
to soften the form of the structures and provide visual screening where
possible. |
Moderate adverse |
Slight to moderate adverse |
Planning
Designation / Location |
Approx. Area Affected by the Proposals |
Sens |
Mag of Change (Con / Oper Phase) |
Planning Intention of
Zoning / Primary Source of Impact |
Impact
Significance Threshold (Unmitigated) |
Mitigation
Measures |
Impact
Significance Threshold (Mitigated) |
|
|||||||
Con |
Oper |
Con |
Oper |
|
|||||||||||
18. Undetermined (Between San Sham and Lok Ma Chau Roads) |
6.37Ha |
Low |
Small / Small |
This area is
currently characterised by container trailer parks, warehouses, agricultural
land and some village houses. It has been designated as ‘undetermined’ due to
its existing land uses and plans for the proposed Spur Line. An area to the
north of Castle Peak Road would also be utilised as a proposed emergency
vehicle access / escape staircase and assembly area. As such, this areas
current designation would not be affected by the proposed track alignment.
The degraded landscape character of this area and its’ inherent low level of
quality would not be significantly affected by the Spur Line proposals. |
Slight adverse |
Slight adverse |
The design of the proposed viaduct structure
should be graceful in terms of its’ horizontal alignment and touch the ground
as lightly as possible in terms of having a low visual mass when viewed in
elevation. |
Slight adverse |
Slight adverse |
|
|||||
19. Government / Institution or Community (Lok Ma Chau Control Point) |
0.5Ha |
Low |
Small / Small |
The planning
intention of this area is to provide sites for Government, Institution or
Community facilities serving the needs of the local as well as the district
population. Its actual role is that of a border control checkpoint and as
such it is characterised by its vehicular routes and waiting areas together
with the security booths. This area has a degraded level of landscape
character and landscape quality. |
Slight adverse |
Slight adverse |
The design of the proposed viaduct structure
should be graceful in terms of its’ horizontal alignment and touch the ground
as lightly as possible in terms of having a low visual mass when viewed in
elevation. Also disturbed landscape resources such as
the existing woodland buffer should be restored following the construction
phase. |
Slight adverse |
Slight adverse |
|
|||||
20. Green Belt (South of Lok Ma Chau lookout point) |
0Ha |
High |
Intermediate to
small / Small to negligible |
The planning intention of this
area has been described in general terms above. Although there is a general presumption
against development in these areas some limited development may be permitted
where there are strong planning grounds. This area covers the valley sides
south of Tai Law Hau from Tit Hang to Lok Ma Chau. It also forms the
landscape setting for a number of small settlements such as Pun Uk Tsuen and
Chau Tau. The proposed route alignment, which would be built on viaduct,
would sever the southern section of the Green Belt. This landscape is
currently characterised by village areas, agricultural fields and small
fishpond areas. The proposed track would lead to the loss of amenity in the
area to the south and west of Chau Tau although the main landscape resources
for which the area is designated would remain intact and so this area would
remain viable as Green Belt. Therefore although the proposed rail alignment
would lead to the physical loss of part of this important landscape
designated area and the loss of some amenity. |
Moderate to
slight adverse |
Slight adverse |
The design of the proposed viaduct structure
should be graceful in terms of its’ horizontal alignment and touch the ground
as lightly as possible in terms of having a low visual mass when viewed in
elevation. Also disturbed landscape resources such as
the existing woodland buffer should be restored following the construction
phase. |
Moderate to
slight adverse |
Slight adverse |
||||||
21. Conservation Area (San Sham
Road to Ping Hang) |
11.00Ha |
High |
Large /
Intermediate |
The
Conservation Area designation is intended to protect the existing natural
characteristics of the area, and has particular importance for the Mai Po
Nature Reserve. The section of the conservation area through which the
proposed route would pass is characterised by small pond areas. During the
construction phase approximately 11 hectares of this area would fall within
the scheme boundary. However following the completion of the construction
period much of this area would be restored as fishponds. The proposed track
alignment, which is built on viaduct, would sever the western section of this
fishpond area leaving much of the area to the east intact. A comprehensive
package of ecological mitigation measures has been formulated to compensate
for the potential degradation of this ecological resource. These measures
these are described in the ecological impact assessment section of this
report. The hills of Tai Law Hau and Ping Hang, which also form part of the
Conservation Area, would be unchanged by the proposals. Therefore the main
resources for which this area was designated would remain largely intact and
any potential losses would be compensated for in the proposed mitigation
strategy. |
Significant
adverse |
Moderate adverse |
The design of the proposed viaduct structure
should be graceful in terms of its’ horizontal alignment and touch the ground
as lightly as possible in terms of having a low visual mass when viewed in
elevation. Also disturbed landscape resources such as
the existing woodland buffer should be restored following the construction
phase. |
Significant
adverse |
Moderate adverse |
||||||
22. Major Road (San Sham Road) |
0Ha |
Low |
Negligible /
Negligible |
The Shan Sham
Road is a major link between Hong Kong and China. The proposed track
alignment would traverse the road section from Lok Ma Chau Control point to
the Shenzhen Economic Zone.
At
this point the proposed track alignment would be built on viaduct and so
there would be no permanent impact upon vehicular access. Therefore the
planning designation for this area would remain unchanged by the proposals. |
Negligible
Impact |
Negligible Impact |
The design of the proposed viaduct structure
should be graceful in terms of its’ horizontal alignment and touch the ground
as lightly as possible in terms of having a low visual mass when viewed in
elevation. Also disturbed landscape resources such as the
existing woodland buffer should be restored following the construction phase. |
Negligible
Impact |
Negligible
Impact |
||||||
23. Drainage Reserve (Parallel to San Sham Road) |
0Ha |
Low |
Negligible /
Negligible |
The proposed
track alignment, which would be built on viaduct in this location, would
cross this area currently safeguarded for future drainage improvement
measures. This would have no direct impact upon the designation of this area,
as there would be no loss of land.
The
Spur Line proposals would have a negligible impact on the perceived future
landscape of an area, which will be largely characterised by its engineered
form. |
Negligible
Impact |
Negligible
Impact |
As 22 above. |
Negligible
Impact |
Negligible
Impact |
||||||
Planning Designation /
Location |
Approx. Area Affected by the Proposals |
Sens |
Mag of Change (Con / Oper Phase) |
Planning Intention of
Zoning / Primary Source of Impact |
Impact
Significance Threshold (Unmitigated) |
Mitigation
Measures |
Impact
Significance Threshold (Mitigated) |
|||
Con |
Oper |
Con |
Oper |
|||||||
24. Conservation Area (Sam Po Shue) |
9.90Ha plus 8.9 Ha for the proposed marshland / reedbed ecological mitigation
area and a further 27.1 Ha for the fishpond mitigation area. Total 45.9 Ha |
High |
Large /
Intermediate |
The Conservation
Area designation is intended to protect the existing natural characteristics
of the area, and has particular importance for the Mai Po Nature Reserve
which is situated approximately 2500 metres to the west of the Lok Ma Chau
Terminus proposals. The section of the conservation area through which the
proposed route would pass is characterised by fishponds. The designation of
part of this existing fishpond area north of the existing village areas such
as Yan Shau Wai and On Lung Tsuen as container back-up uses would lead to degradation
in the amenity of this area. The proposed
track alignment, which is built on viaduct, would sever the north eastern
section of this fishpond area leaving much of the area to the west intact. A
comprehensive package of ecological mitigation measures has been formulated
to compensate for the potential degradation of this ecological resource.
Therefore the main resources for which this area was designated would remain
largely intact and any potential losses would be compensated for in the
proposed mitigation strategy.
Therefore the
main resources for which this area was designated would remain largely intact
and any potential losses would be compensated for in the proposed mitigation
strategy. |
Significant
adverse |
Moderate adverse |
The design of the proposed viaduct structure
should be graceful in terms of its horizontal alignment and touch the ground
as lightly as possible in terms of having a low visual mass when viewed in
elevation. Also disturbed landscape resources such as
the existing woodland buffer should be restored following the construction
phase. The appearance of the proposed Lok Ma Chau
Terminus complex should be responsive to its landscape setting. The proposed
peripheral landscape planting will partially screen the Terminus structure,
fully screen the ground level activities and provide a measure of visual
integration into the landscape context |
Significant
adverse |
Moderate adverse |
|
Outline Zoning Plan
S/NE-KTN/3 – Kwu Tung South |
||||||||||
Generally |
0Ha |
High to low |
Intermediate /
Small to Negligible |
The planning
designations shown on this Outline Zoning Plan would not be directly affected
by the Spur Line proposals as they are not crossed by the proposed alignment
and so there would be no actual loss of land area. Also potential indirect
impacts would be largely mitigated by the level of landscape degradation
caused by existing, intervening development such as the Fanling Highway
(NTCR) and built development such as Dill’s Corner Camp. The future landscape
of the area will be dominated by the high-rise development associated with
the proposed Kwu Tung North NDA and so the Spur Line proposals will have a
negligible residual impact. |
Moderate adverse |
Negligible
Impact |
As 1 above. |
Moderate adverse |
Negligible
Impact |
|
Key: Landscape
Sensitivity (Sens): Low,
Medium or High
Magnitude of Change (Mag): Negligible,
Small, Intermediate and Large
Significance Threshold: Negligible,
Slight, Moderate and Significant (adverse or beneficial)
Con – Construction Phase
Oper
– Operational
Residual Impacts: Refer to matrix and table in methodology section
Summary
12.6.2
The Spur Line proposals would
generally result in a negligible level of impact on the designated planning
zones within the Study Area. Due in large part to the utilisation of the
proposed tunnel section. Most of the area affected would comprise agricultural
land, although there would be losses to areas of Conservation Area, and smaller
losses to areas designated as Industrial (Group D), Open storage and Open
Space. The potential losses to zones designated Conservation Areas would be
mitigated through the use of the proposed ecological mitigation measures refer
to the ecology section of this report. There would be a loss of approximately
5.0 hectares of the existing Green Belt to the east of Tit Hang, whilst there
would be no direct loss to the area of Green Belt adjacent to Lok Ma Chau Look
Out Point. This loss of Green Belt is largely due to the above ground
structures associated with the western end of the tunnel section and
approximately 1.7 hectares of this area will be utilised for the proposed soft
landscape mitigation measures. Whilst this is a significant area and despite
the general presumption against development in these Green Belt areas the
presence of the existing infrastructure projects and the level of existing
development including in the Lok Ma Chau Border Crossing has degraded the
existing landscape. The Spur Line proposals would leave the landscape framework
of these areas largely intact. With the exception of the field area to the
south and west of Chau Tau the overall residual adverse impact on the Green
Belt resource of the Study Area would range from slight to moderate in
significance.
12.6.3
The proposed Spur Line would not
have a direct impact upon the proposed Kwu Tung North NDA in terms of the
physical loss of land or the impacts on the viability of the planning
designations. The proposed alignment is safeguarded within the proposals in the
form of a rail corridor approximately 84 metres in width, and its construction
would facilitate some of the planning principles central to the NDA such as the
promotion of a ‘rail based development’. The proposed use of the tunnel section
would leave the railway reserve relatively intact following the completion of
the construction phase of the project. With the exception of the mitigation
measures for the above ground structures and the restoration of any areas
disturbed during the construction period no landscaping is proposed for this
area as part of the Spur Line proposals. The residual area is now subject to a
separate assessment under the NENT Study.
12.6.4
The review of the
existing planning and development control framework found that the Spur Line proposals would not conflict with the published land use
plans for the Study Area and so no amendment is required as a result of the
proposals.
12.7
Existing
Visual Context and Visual Impacts
Visual
Envelope
12.7.1
The alignment would run through a
landscape formed of lowlands, uplands, urban and cottage areas resulting in
a visual envelope, which in some sections open and others more enclosed. The
extent of the visual envelope is shown on Figures
12.5a-b. To the north
of the Spur Line the visual envelope is generally confined by the ridgelines
of hills at Lok Ma Chau, Tit Hang, Fung Kong Shan and Tai Shek Mo. For the
section between Sheung Shui and Chau Tau the utilisation of the tunnel section
would mean that for the large part of the visual envelope will be confined
to areas in close proximity to he proposed above ground structures. However,
at western end of the proposed alignment the envelope extends further across
the open fishpond and agricultural areas. To the east the visual envelope
for the above ground section prior to the tunnel would be visually contained
by the developments in north Sheung Shui.
12.7.2
South of the proposed Spur Line,
the visual envelope varies due to the differing levels of development. In the
eastern parts it extends over the open agricultural fields and is generally
contained by the local villages and roadside planting of the Fanling Highway.
Centrally, the visual envelope is contained at lower levels by the local
buildings and planting within the cottage areas; however, at upper levels the
envelope extends to the ridgeline of Ki Lun Shan. In the west the envelope
extends over Sam Po Shue to the villages at San Tin.
12.7.3
To the west the visual envelope
extends a considerable distance over the fishponds and wetlands of Mai Po,
however, there are few visually sensitive receivers in the area.
Existing
Visually Sensitive Receivers
12.7.4
In broad terms, there are three distinct
characters to the visual amenity along the study area, which largely coincide
with the existing landscape character designations. To the east the high-rise
conurbation of Sheung Shui and Fanling dominates the views. The openness of
the landscape and the extent of the views, together with the low level of
existing disturbance and high degree of vegetation result in views in this
area being of a high value. Many low level views are subject to screening,
and hence are less sensitive, due to intermediate buildings and trees. The
location of the VSRs identified in this assessment are shown on Figures
12.6a-b.
12.7.5
The cottage areas dominate the
central section of the study area, with views being dominated by the local mix
of buildings, workshops, open storage and mature tree groups with the upland
areas of Tit Hang and Ki Lun Shan in the background. In general, views are
confined to areas adjacent to the proposed above ground structures as the
intermediate features screen many lower level views. The former military
facility at Dill’s Corner Camp would be utilised as a temporary works area
during the construction phase of the project. Also an area of the existing
light industrial /cottage area, and some designated open space to the north of
the camp would be used for temporary works areas. The visual quality is
relatively low due to this mix of visual features although the sensitivity is
higher due to proximity of the VSRs.
12.7.6
For the purposes of this study the
Kwu Tung North NDA will be considered as a committed development. It will be characterised by a core of high-rise development, which
is graded towards the periphery of the NDA utilising the stepped building
height principle, with the peripheral blocks ranging from 10 to 20 blocks in
height. The proposed railway corridor would be lined on the
northern and southern sides by largely high-rise residential development. In
general views for VSRs facing the Spur Line will be dominated by the opposing
high-rise development with the upland areas beyond forming a green backdrop.
The predicted visual impact of the Spur Line will be assessed against a
situation whereby the NDA is constructed in its absence.
12.7.7
In the western section of the study
area the visual amenity varies. Views to the east comprise of the Lok Ma Chau
Border Crossing, together with the local cottage areas with the Lok Ma Chau
natural hillside in the background. The views to the west and south are open
over the Sam So Shue fishponds. To the north views are dominated by the high-rise
urban developments of Shenzhen and Huanggang.
12.7.8
For simplicity, the VSRs are generally
grouped by village or development. The VSRs are shown on Figures
12.6a-b and described
in Table 12.4 below.
Visual
Impacts
12.7.9
The primary visual impacts arise
from the construction of the viaduct across the open low-lying areas at the
western end of the alignment, which will introduce a major elevated linear
element into the existing landscape context. In particular, the local villages
within these areas will suffer the most significant adverse visual impacts. The
VSRs, their views and visual impacts are summarised in Table 12.4 below.
12.7.10
The central section of the Spur
Line will utilise a tunnel section as has been described above. The local
buildings, structures and tree planting screen many of the views of the
proposed above ground structures, although those VSRs in close proximity to the
alignment would suffer adverse visual impacts, with those further away being
subject to lower levels of visual intrusion. The proposed tree and shrub
planting adjacent to the above ground structures will reduce the perceived
level of visual impact.
12.7.11
The former military facility at
Dills Corner Camp and area located between Chau Tau and the NTCR would be
utilised as a temporary works areas during the construction phase of the
project. However these areas area enclosed by high fences and mature tree
planting, which would largely screen construction activity from adjacent VSRs.
The temporary works area to the north of Dills Corner Camp is situated in a
visually enclosed landscape, which has been degraded by light industrial
development. Much of the predicted temporary adverse impact could be mitigated
through the use of temporary hoarding.
12.7.12
The proposed Kwu Tung North NDA
will eventually absorb a large proportion of this central section of the study
area leading to fundamental changes in the visual amenity of the area, and the
range and number of the potential VSRs. As has been described above the visual
amenity of these new VSRs will be largely characterised by high-rise
development with the upland areas beyond forming a green backdrop. These VSRs
would be subject to slight adverse to negligible impacts due to the proximity
of the above ground structures. Under the Spur Line proposals with the
exception of the above ground structures no landscape treatment is proposed for
the area of the railway reserve above the tunnel section. The construction
phase of the Spur Line proposals will occur prior to the first population
intake within the Kwu Tung North NDA.
Table 12.4: Visually Sensitive
Receivers and Visual Impacts (Refer to Figure
12.6 a- b)
The following table presents the
predicted unmitigated and mitigated (residual) impacts for the proposed scheme
during the construction and operational phases of the project. The mitigated
residual impacts are assessed during the design year which for the purposes of
this study is taken as being between 10 and 15 years after the schemes opening
when the proposed mitigation planting is deemed to have reached a level of
maturity, which is sufficient for it to perform the design objectives. It
should be noted that, with the exception of the area immediately north of the
existing Sheung Shui Station, noise attenuation measures are not considered
necessary for this scheme. For the purposes of this assessment low rise was
taken as 0-4 floors, medium rise as 5-10 floors and high-rise as 11+ floors.
Visually Sensitive Receiver / Type / Approx Viewing Distance |
Existing View |
Sens |
Mag of
Change (Con / Oper phase) |
Primary Source of Impact |
Impact Significance
Threshold (Unmitigated) |
Mitigation Measures |
Impact Significance
Threshold (Mitigated) |
||
Con |
Oper |
Con |
Oper |
||||||
1. Choi Po Court
High-rise Residential / 250m |
Views are open and northwest over a mix of
the urban areas of Sheung Shui, the local villages and the River Beas plain
towards Tia Mo Shek. Sensitivity reduced due to distance to site |
Medium |
Intermediate /
Intermediate to Small |
Construction: Disturbance to landscape
particularly vegetated character of area Operational: Introduction of proposed noise
barriers adjacent to Sheung Shui station would only be partially visible from
this location. East of KCR East Rail (300m long and 5m high) and west (300m
long, 5.8m high with a 3.6m cantilever).
|
Moderate adverse |
Moderate adverse |
Design of the noise barriers to minimise
visual impacts and integrate with the urban context of high-rise residential
development and large commercial / storage warehouses. |
Moderate to
slight adverse |
Slight adverse |
2. Sheung Shui Sewage
Treatment Works Industrial / 200m |
Views are east towards the open agricultural
areas of the River Beas plain. Sensitivity reduced due to the partial
screening by the tree planting adjacent to the KCR East Rail line and the
industrial nature of the VSRs |
Low |
Small / Small to
Negligible |
Construction: Disturbance to the landscape
particularly the vegetated character of area Operational: no visible structure. |
Slight adverse |
Negligible
Impact |
None required. |
Slight adverse |
Negligible
Impact |
3. Other Uses Ongoing light industrial / commercial / 20m |
Views are north and west over the
agricultural and fishpond areas of the River Beas plain with the cottage
areas of Fung Kong and the hillsides of Tai Mo Shek and Tung Kong Shan in the
background. The view to the north also contains the KCR line and sewage
treatment works. |
Low |
Intermediate /
Small to negligible |
Construction: Disturbance to the landscape
particularly the vegetated character of area Operational:
Introduction of the proposed ventilation building (75m long, 30m wide and
12.7m high) and EAP Structure east of the River Sutlej MDC (21m long, 12.5m
wide and 10.8m high). |
Slight adverse |
Slight adverse
to negligible impact |
The visual appearance of the ventilation
building should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its’ visual form and
integrate the structure into the existing landscape context. |
Slight adverse |
Slight adverse
to negligible impact |
4. Tsung Pak Long Low-rise development / 20m |
Views are north and west over the open
agricultural areas of the River Beas plain with Tai Mo Shek and the high-rise
conurbation of Shenzhen in the background. Several views are partially screened
by intermediate trees and vegetation. Sensitivity reduced due to screening
and distance. |
Medium |
Small to
negligible / Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed EAP structure. Operational: Introduction of EAP structure
into the rural landscape however this impact will be largely negated through
the implementation of the proposed Kwu Tung North NDA proposals. Ventilation
building (75m long, 30m wide and 12.7m high) and EAP Structure east of the
River Sutlej MDC (21m long, 12.5m wide and 10.8m high). |
Slight adverse |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Slight adverse
negligible Impact |
Negligible
Impact |
5. Yin Kong Low-rise development / 400m |
Views from the sporadic are north over the
open agricultural areas of the River Beas plain with Tai Mo Shek and the
high-rise conurbation of Shenzhen in the background. Several views are
partially screened by intermediate trees and vegetation. Sensitivity reduced
due to screening and distance. |
Medium |
Small to Negligible
/ Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed EAP structure. Operational: Introduction of EAP structure
into the rural landscape however this impact will be largely negated through
the implementation of the proposed Kwu Tung North NDA proposals. Proposed EAP structure on the western
bank of the River Beas MDC (21m long, 12m wide and 10.8m high). Adjacent to
this structure will be an area of hard standing for car parking and to
provide an assembly area |
Slight adverse
negligible Impact |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Slight adverse
negligible Impact |
Negligible
Impact |
6. Fanling Highway East Vehicle travellers / 500m |
Views are north over the agricultural fields
of the River Beas plain with Tai Mo Shek and the high-rise conurbation of
Shenzhen. Sensitivity reduced due to distance, 500m, and screening by
roadside vegetation. |
Low |
Negligible /
Negligible |
Construction: Visible construction activity
confined to the temporary works areas. Operational: Not visible above ground
structures. |
Slight adverse
to negligible Impact |
Negligible
Impact |
Retention of
existing trees on the periphery of the development site and hoarding where
this is not possible. |
Negligible
Impact |
Negligible
Impact |
7. Ho Sheung Heung Low-rise residential / 250m |
Views are south over the agricultural fields
of the River Beas plain towards the villages and cottage areas to the south.
Beyond this views are contained by the roadside planting of Fanling Highway.
The quality of views is reduced by the presence and partial screening by the
open storage areas. |
Medium |
Small to
Negligible / Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed EAP structure. Operational: Introduction of EAP structure
into the rural landscape however this impact will be largely negated through
the implementation of the proposed Kwu Tung North NDA proposals. Proposed EAP
structure on the western bank of the River Beas MDC (21m long, 12m wide and
10.8m high). Adjacent to this structure will be an area of hard standing for
car parking and to provide an assembly area |
Slight adverse
negligible Impact |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Slight adverse
negligible Impact |
Negligible
Impact |
8. Fung Kong Low-rise residential / 300m |
Views are south over the adjacent
agricultural areas towards the cottage areas of Tong Kok and the roadside
vegetation of Fanling Highway. Partial screening is given by local tree
planting and intermediate buildings reducing sensitivity. |
Medium |
Negligible /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the
excavation required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be
largely negated through the implementation of the proposed Kwu Tung North NDA
proposals. Main visible structure the proposed above ground services cluster
48m long, 29.2m wide and at the highest point some 17.3m high although the
main part of the structure is 5.3m high). |
Negligible
Impact |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Negligible
Impact |
Negligible
Impact |
9. Tung Fong
South Low-rise residential and industrial / 30m |
Views are south through the cottage area
towards the site and comprise a mix of houses, workshops, and storage and
tree groups with the natural Ki Lun Shan in the background. Many views are
partially screened by the local features, reducing sensitivity. |
Medium |
Intermediate /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the
excavation required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be
largely negated through the implementation of the proposed Kwu Tung North NDA
proposals. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
10. Tung Fong
North Low-rise residential and industrial / 300m |
Views are south through the cottage area
towards the site and comprise a mix of houses, workshops, and storage and
tree groups with the natural Ki Lun Shan in the background. Views are
primarily from industrial buildings and partially screened by the local
features, reducing sensitivity. |
Low |
Intermediate /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the
excavation required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be largely
negated through the implementation of the proposed Kwu Tung North NDA
proposals. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
11. Shek Tsai
Leng Low-rise residential and industrial / 150m |
Views are north through the cottage area
including houses, workshops and tree groups with the natural Tit Hang
hillside in the background. Views are partially screened by the local
features reducing sensitivity. |
Low |
Intermediate /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the
excavation required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be
largely negated through the implementation of the proposed Kwu Tung North NDA
proposals. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
12. Dill’s Corner Camp Low-rise residential / 50m |
Views are north through the cottage area
including houses, workshops and tree groups with Tit Hang hillsides in the
background. Views are partially screened by the local features reducing
sensitivity. |
Medium |
Large /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the
excavation required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be
largely negated through the implementation of the proposed Kwu Tung North NDA
proposals. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
13. Pak Shek Au East Low-rise residential and industrial / 20m |
Views are north through the cottage area
including houses, workshops and tree groups with Tit Hang hillsides in the
background. Views are partially screened by the local features reducing
sensitivity. |
Medium |
Large /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the excavation
required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be
largely negated through the implementation of the proposed Kwu Tung North NDA
proposals. The EAP Structure will be 21m long, 12.5m wide and 10.8m high. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
14. Pak Shek Au West Low-rise residential and industrial / 20m |
Views are south through the cottage area
including houses, workshops and tree groups with Ki Lun Shan hillsides in the
background. Views are partially screened by the local features reducing
sensitivity. |
Medium |
Large /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the
excavation required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be
largely negated through the implementation of the proposed Kwu Tung North NDA
proposals. The EAP Structure will be 21m long, 12.5m wide and 10.8m high. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
The visual appearance of the EAP structure
should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Moderate adverse
(VSRS adjacent
to the proposed station area and the proposed works area). |
Negligible
Impact |
15. Footpath – Lok Ma Chau
East Walking trial / 400m |
Views are elevated and south over the
cottage area and Fanling Highway corridor to the natural Ki Lun Shan.
Although views are open, they are of reduced quality due to the level of
development in the valley. |
Medium |
Small /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the
excavation required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be
largely negated through the implementation of the proposed Kwu Tung North NDA
proposals. |
Slight adverse |
Negligible
Impact |
The visual appearance of the EAP and station
entrance structures should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Slight adverse |
Negligible
Impact |
16. Footpath – Ki Lun Shan
East Walking trial / 500m |
Views are elevated and north over the
cottage area and Fanling Highway corridor to the natural Lok Ma Chau
hillsides. Although views are open, they are of reduced quality due to the
level of development in the valley. |
Medium |
Small /
Negligible |
Construction: Disturbance to the landscape
due to the construction of the proposed above ground structures and the
excavation required for the proposed station box. Operational: Introduction of EAP structure
and station entrances into the rural landscape however this impact will be
largely negated through the implementation of the proposed Kwu Tung North NDA
proposals. |
Slight adverse |
Negligible
Impact |
The visual appearance of the EAP and station
entrance structures should be responsive to the landscape context. Tree and shrub planting will be introduced
around the periphery of the building footprint to soften its visual form and
integrate the structure into the existing landscape context. |
Slight adverse |
Negligible
Impact |
17. Footpath – Lok Ma Chau
Central Walking trial / 500m |
Views are elevated and south over the
cottage areas, Chau Tau village and Fanling Highway corridor and interchange
to the natural Ki Lun Shan. Although views are open, they are of reduced
quality due to the level of development in the valley. |
Medium |
Small /
Negligible |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel boring, temporary
works sites and the construction of the proposed viaduct section. Operational: Introduction of proposed tunnel
portal and viaduct section into the existing landscape context. The movement
of trains would also lead to adverse visual impact. However from this vantage
point the existing landscape is highly disturbed due to the existing
development and infrastructure, and there are alternative views available. |
Slight adverse |
Negligible
Impact |
Design of above ground structures and
viaduct sections. Compensatory tree and shrub planting along
the proposed track alignment where feasible as a visual buffer |
Slight adverse |
Negligible
Impact |
18. Chau Tau East Low-rise residential and industrial / 40m |
View is south through the local houses,
workshops and tree groups with Fanling Highway and Ki Lun Shan in the
background. Sensitivity and quality of views is reduced due to presence of
and screening by poor features. |
Medium |
Large to
Intermediate / Large to Intermediate |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel boring, temporary
works sites and the construction of the proposed viaduct section. Operational:
Introduction of proposed viaduct section and ventilation building into the
existing landscape context. The movement of trains would also lead to adverse
visual impact. Ventilation building 15m long, 15m wide and 11m high. Introduction of tunnel portal and
approach ramped viaduct ascending to maximum height of approximately 16m
above the existing ground level. |
Moderate adverse |
Moderate adverse |
Design of above ground structures and
viaduct sections. Compensatory tree and shrub planting along
the proposed track alignment where feasible as a visual buffer |
Moderate adverse |
Moderate adverse |
19. Chau Tau
West Low–rise residential / 300m |
Views are south and west. To the south they
are across the local agricultural fields, local open storage to the Fanling
Highway Interchange with Ki Lun Shan in the background. To the west views are
similar over the agricultural fields and open storage to San Sham Road.
Quality and sensitivity of views is reduced due to the presence of and
partial screening by the open storage and local tree groups. |
Medium |
Large / Large |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel boring, temporary
works sites and the construction of the proposed viaduct section. Operational: Introduction of proposed
viaduct section and ventilation building into the existing landscape context.
The movement of trains would also lead to adverse visual impact. Viaduct
section approximately 16m above the existing ground level. |
Significant
adverse |
Significant
adverse |
Design of above ground structures and
viaduct sections to integrate into the rural setting. Compensatory tree and shrub planting along
the proposed track alignment where feasible as a visual buffer |
Significant
adverse |
Significant to
moderate adverse |
20. Footpath –
Ki Lun Shan West Walking trial / 500m |
Views are north over the Fanling Highway and
along San Sham Road to Lok Ma Chau border crossing and ongoing construction
works with the high-rise conurbation in the background. To the east of the
road are the mixed areas of open storage and fishponds, to the west the views
are open over the local fishponds to Shenzhen. Quality and sensitivity are
reduced due to distance and the level of development in the low-lying areas. |
Medium |
Small /
Negligible |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel boring, temporary
works sites and the construction of the proposed viaduct section. Operational: Introduction of proposed tunnel
portal and viaduct section into the existing landscape context. The movement
of trains would also lead to adverse visual impact. However from this vantage
point the existing landscape is highly disturbed due to the existing
development and infrastructure, and there are alternative views available. |
Slight adverse |
Negligible
Impact |
Design of above ground structures and
viaduct sections. Compensatory tree and shrub planting along
the proposed track alignment where feasible as a visual buffer |
Slight adverse |
Negligible
Impact |
21. Fanling
Highway West Vehicle travellers / 300m |
Views are north variously over the open
stage areas and fishponds at Sam Po Shue, along San Sham Road and the open
storage and cottage areas of Chau Tau and Pak Shek Au. Views are also
partially screened by the roadside vegetation. |
Low |
Small / Small to
Negligible |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel boring, temporary
works sites and the construction of the proposed viaduct section. Disturbance
to vegetation and loss of tree groups as visual buffer Operational: Introduction of proposed
viaduct section into the existing landscape context. The movement of trains
would also lead to adverse visual impact. |
Slight adverse |
Negligible
Impact |
Design of above ground structures and
viaduct sections. Compensatory tree and shrub planting along
the proposed track alignment where feasible as a visual buffer |
Slight adverse |
Negligible
Impact |
22.
Tung Chan Wai and San Lung Tsuen Low-rise residential / 1600m |
Views are north over the fishponds of Sam Po
Shue towards San Sham Road, the border crossing and the high-ride conurbation
of Shenzhen. Sensitivity of views to northwest reduced due to presence of the
road and border crossing. Sensitivity of views to northern part of site
reduced due to distance. |
Medium |
Intermediate /
Intermediate |
Construction: Disturbance to the landscape
due to the construction activity associated with the proposed viaduct section
and Lok Ma Chau Terminus complex. Disturbance to vegetation and loss of tree
groups as visual buffer Operational: Introduction of proposed
viaduct section and Terminus complex into the existing landscape context. The
movement of trains would also lead to adverse visual impact. Although the station complex would be viewed
against the high-rise urban background of Shenzhen. |
Moderate adverse |
Moderate adverse |
Design of Terminus and viaduct structures to
be responsive to existing rural context. Tree and shrub planting on the periphery of
the Terminus complex to soften the visual form of the structure and screen
low-level activities. |
Moderate adverse |
Moderate adverse |
23. Pun Uk Tsuen
Low-rise residential / 450m |
Views are south and west over the local
agricultural field’s open storage to San Sham Road with local tree groups.
Sensitivity of views is reduced due to the poor quality of the feature and
partial screening by adjacent storage and woodland strips. |
Medium |
Large /
Intermediate |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel boring, temporary
works sites and the construction of the proposed viaduct section. Operational: Introduction of proposed
viaduct section and ventilation building into the existing landscape context.
The movement of trains would also lead to adverse visual impact. Widening of
Lok Ma Chau Road (proposed access road for EVA and station access). |
Significant
adverse |
Significant to
moderate adverse |
Design of above ground structures and
viaduct sections to integrate into the rural setting. Compensatory tree and shrub planting along
the proposed track alignment where feasible as a visual buffer. Restoration of roadside landscape along Lok
Ma Chau Road. |
Significant
adverse |
Significant to
moderate adverse |
24.
Footpath and Viewpoint – Lok Ma Chau Viewpoint / 500m |
Views are east over the local cottage areas,
fishpond and border crossing and ongoing construction works, to the open
areas of Sam Po Shue to Mai Po. The viewpoint is a local feature, however,
the level of disturbance in views reduces sensitivity. |
Medium |
Intermediate /
Intermediate |
Construction: Disturbance to the landscape
due to the construction activity associated with the proposed viaduct section
and Lok Ma Chau Terminus complex. Disturbance to vegetation and loss of tree
groups as visual buffer Operational: Introduction of proposed
viaduct section and Terminus complex into the existing landscape context. The
movement of trains would also lead to adverse visual impact. Although the
viaduct would be seen against the backdrop of the Lok Ma Chau Border Crossing
and the Terminus against the high-rise urban background of Shenzhen. Widening of Lok Ma Chau Road (proposed
access road for EVA and station access). |
Moderate adverse |
Moderate adverse |
Design of Terminus and viaduct structures to
be responsive to existing rural context. Tree and shrub planting on the periphery of
the Terminus complex to soften the visual form of the structure and screen
low-level activities. Restoration of roadside landscape along Lok
Ma Chau Road. |
Moderate adverse |
Moderate adverse |
25. Lok Ma Chau Low-rise residential / 600m |
Views are east over the local fishponds and
agricultural fields towards the Lok Ma Chau Border Crossing and ongoing
construction works. Sensitivity reduced due to distance. |
Medium |
Large to
Intermediate / Intermediate |
Construction: Disturbance to the landscape
due to the construction activity associated with the proposed viaduct section
and Lok Ma Chau Terminus complex. Disturbance to vegetation and loss of tree
groups as visual buffer Operational: Introduction of proposed
viaduct section (ranging from 16 to 20m above the existing ground level) and
Terminus complex (approximately 27m high) into the existing landscape
context. The movement of trains would also lead to adverse visual impact.
Although the viaduct would be seen against the backdrop of the Lok Ma Chau
Border Crossing and the Terminus against the high-rise urban background of
Shenzhen. Widening of Lok Ma Chau Road (proposed
access road for EVA and station access). |
Significant to
moderate adverse |
Significant to
moderate adverse |
Design of Terminus and viaduct structures to
be responsive to existing rural context. Tree and shrub planting on the periphery of
the Terminus complex to soften the visual form of the structure and screen
low-level activities. Re-instatement of wetlands elsewhere on site Restoration of roadside landscape along Lok
Ma Chau Road. |
Significant to
moderate adverse |
Moderate adverse |
26. Ha Wan Tsuen
Low-rise residential / 200m |
Views are east and south over local
fishponds to the Border Crossing and ongoing construction works. |
Medium |
Intermediate /
Intermediate |
Construction: Disturbance to the landscape
due to the construction activity associated with the proposed viaduct
section. Disturbance to fishponds, vegetation and loss of tree groups as
visual buffer Operational: Introduction of viaduct
(ranging from 16 to 20m above the existing ground level) as a major feature
of views. The movement of trains would also lead to adverse visual impact.
Alternative views available. Introduction of proposed access road for EVA
and station access road through area currently characterised by fishponds. |
Moderate adverse |
Moderate adverse |
Re-instatement
of planting below viaduct where appropriate Design of viaduct to integrate with rural
context. Tree planting lining the proposed access
road for EVA and station access road. |
Moderate adverse |
Moderate adverse |
27. San Sham Road and Lok
Ma Chau Border Crossing Vehicle travellers / 200m |
Views are to the east and west. To the east
the views are partially screened and over the local fishpond and open storage
to Lok Ma Chau hillsides. To the west the views are over the fishponds of Sam
Po Shue with Shenzhen in the background. |
Low |
Small / Small |
Construction: Disturbance to the
landscape due to the construction activity associated with the proposed
viaduct section. Disturbance to vegetation and loss of tree groups as visual
buffer Operational: Introduction of viaduct
(ranging in height from 16 to 20m above the existing ground level) as a major
feature of views. The movement of trains would also lead to adverse visual
impact. Alternative views available. |
Slight adverse |
Slight adverse |
Compensatory
planting to soften viaduct form Design of
viaduct to integrate with rural context |
Slight adverse |
Slight adverse |
28. KCR East
Rail Train passengers / 20m |
Views are west over the agricultural fields
and fishponds of the River Beas plain and along the valley with the local
natural hillsides to the north and south. |
Low |
Intermediate /
Negligible |
Construction: Disturbance to the
landscape due to the construction activity associated with the proposed
tunnel portal with approach track and noise barriers at Sheung Shui Station.
Disturbance to vegetation and loss of tree groups as visual buffer Operational: Introduction of the noise
barriers and the tunnel portal as a major feature of views. Although the
existing view is characterised by the structure associated with the existing
East Rail track. |
Slight adverse |
Negligible
Impact |
Compensatory
tree and shrub planting where possible. Design of new structures including noise barriers
to be responsive to the existing landscape context. |
Slight adverse |
Negligible
Impact |
29. Europa
Gardens Medium–rise residential / 500m |
Views to the north and east are
characterised by the existing Fanling Highway with the cottage areas
extending to Long Valley beyond it. The highway is lined with existing tree
planting and there is a framework of mature trees within the cottage areas to
the north. Views extend to the ridgeline extending east from Lok Ma Chau. |
Low |
Small /
Negligible |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel boring, temporary
works sites and the construction of the proposed tunnel section above ground
structure. However existing view is degraded to an extent due to the proximity
of the NTCR. Operational: no visible structure from this
location due to the intervening vegetation and in the future the
implementation of the proposed Kwu Tung North NDA. |
Slight adverse
to Negligible |
Negligible
impact |
Restoration of works areas however the
implementation of the proposed Kwu Tung North NDA proposals will negate any
residual impacts arsing from the Spur Line proposals. |
Slight adverse
to Negligible |
Negligible
impact |
30. Choi Ping
House High – rise residential / 150m |
The upper storeys of this building enjoy
commanding views over the railway tracks although at lower levels the mature
tree planting lining Choi Yuen Road screens much of the available views.
Views to the north east where available are characterised by the a landscape
of high rise residential property in the background, large commercial
premises in the middle ground and the existing KCR East Rail with associated
structures in the foreground. The mature trees lining San Wan Road provide
further greenery in a view, which is otherwise of hard urban landscape. |
Medium to low |
Intermediate /
Intermediate |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel approach and the
proposed Construction activity associated with the noise barriers. However
existing view is degraded to an extent due to the proximity of the existing
infrastructure. Operational: Introduction of proposed noise
barriers as new linear elements within the urban landscape. East of KCR East
Rail (300m long and 5m high) and west (300m long, 5.6m high with a 3.6m
cantilever). |
Moderate adverse |
Slight adverse |
Reinstatement of planting along trackside
where lost and as additional landscape buffer. The design of noise barriers to be
responsive to the existing landscape and minimise impacts on the existing
landscape character. |
Moderate adverse |
Slight adverse |
31. 134 to 140
San Fung Road Medium – rise commercial / 100m |
Views to the south west are at an acute
angle and restricted by the existing mature trees lining San Wan Road
although there are filtered views of the existing KCR track to Lo Wu and of
the high rise development of Choi Yuen Estate beyond. |
Medium to low |
Large /
Intermediate |
Construction: Disturbance to the landscape
due to the construction activity associated with the tunnel approach and the
proposed Construction activity associated with the noise barriers. However
existing view is degraded to an extent due to the proximity of the existing
infrastructure. Loss of existing roadside trees. Operational: Introduction of proposed noise
barriers as new linear elements within the urban landscape. East of KCR East
Rail (300m long and 5m high) and west (300m long, 5.8m high with a 3.6m
cantilever). |
Significant to
moderate adverse |
Moderate adverse |
Reinstatement of planting along trackside
where possible and as additional landscape buffer. The design of noise barriers to be
responsive to the existing landscape and minimise impacts on the existing
landscape character. |
Significant to
moderate adverse |
Moderate adverse |
32. High Rise
Residential Development, Kwu Tung North NDA (north of the Spur Line) High-rise residential / 30m |
Views to the south will be dominated by the
proposed high-rise development associated with the NDA with the natural hill
slopes of the Kai Kung Leng forming a green backdrop. There will also be
filtered views of the New Territories Circular Road (Fanling Highway). |
High |
Negligible /
Small to negligible |
Construction: no
activity visible as the spur proposals will be completed prior to the first
population intake. Operational: Introduction of proposed
station entrance and EAP above ground structures. |
Negligible
Impact |
Slight adverse
to negligible |
The Spur Line proposals will be completed
prior to the first population intake. With the exception of the mitigation
measures proposed for the above ground structures and the restoration of
areas disturbed due to the construction phase activity no landscape measures
are proposed for the railway reserve above the tunnel section. |
Negligible
Impact |
Slight adverse
to negligible |
33. Low-rise
Development, Kwu Tung North NDA (north of the Spur Line) Low and medium-rise business use and
Government / Institutional Uses / 30m |
Views to the south will be dominated by the
proposed high-rise development associated with the NDA with the natural hill
slopes of the Kai Kung Leng forming a green backdrop. Views of the New
Territories Circular Road will be screened by the proposed development. |
Medium to low |
Negligible /
Small to negligible |
Construction: no
activity visible as the spur proposals will be completed prior to the first
population intake. Operational: Introduction of proposed
station entrance and EAP above ground structures. Main visible structure the
proposed above ground services cluster 48m long, 29.2m wide and at the
highest point some 17.3m high although the main part of the structure is 5.3m
high). |
Negligible
Impact |
Slight adverse
to negligible |
The Spur Line proposals will be completed
prior to the first population intake. With the exception of the mitigation
measures proposed for the above ground structures and the restoration of
areas disturbed due to the construction phase activity no landscape measures
are proposed for the railway reserve above the tunnel section. |
Negligible
Impact |
Slight adverse to
negligible |
34. High-rise
Residential Development, Kwu Tung North NDA (south of the Spur Line) High-rise residential / 30m |
Views to the south will be dominated by the
proposed high-rise development associated with the NDA with the natural hill
slopes of the Fung Kong Shan forming a green backdrop. |
High |
Negligible /
Small to negligible |
Construction: no
activity visible as the spur proposals will be completed prior to the first
population intake. Operational: Introduction of proposed
station entrance and EAP above ground structures. Main visible structure the
proposed above ground services cluster 48m long, 29.2m wide and at the
highest point some 17.3m high although the main part of the structure is 5.3m
high). |
Negligible
Impact |
Slight adverse
to negligible |
The Spur Line proposals will be completed
prior to the first population intake. With the exception of the mitigation
measures proposed for the above ground structures and the restoration of
areas disturbed due to the construction phase activity no landscape measures
are proposed for the railway reserve above the tunnel section. |
Negligible
Impact |
Slight adverse
to negligible |
35. Low-rise
Development, Kwu Tung North NDA (south of the Spur Line) Low-rise business use areas / 30m |
Views to the north will be dominated by the
proposed high rise development associated with the NDA with the natural hill
slopes of Fung Kong Shan forming a green backdrop. |
Low |
Negligible /
Small to negligible |
Construction: no
activity visible as the spur proposals will be completed prior to the first
population intake. Operational: Introduction of proposed
station entrance and EAP above ground structures. Main visible structure the
proposed above ground services cluster 48m long, 29.2m wide and at the
highest point some 17.3m high although the main part of the structure is 5.3m
high). |
Negligible
Impact |
Slight adverse
to negligible |
The Spur Line proposals will be completed
prior to the first population intake. With the exception of the mitigation
measures proposed for the above ground structures and the restoration of
areas disturbed due to the construction phase activity no landscape measures
are proposed for the railway reserve above the tunnel section. |
Negligible
Impact |
Slight adverse
to negligible |
Key: Landscape
Sensitivity (Sens): Low,
Medium or High
Magnitude of Change: Negligible,
Small, Intermediate or Large
Significance
Threshold: Negligible,
Slight, Moderate or Significant (adverse or beneficial)
Impacts: Con:
Construction phase impacts
Oper: Operational phase impacts
Note: The viewing distance is measured from the façade of the building or location that forms the Visually Sensitive Receiver to nearest visible part of the proposed scheme.
Summary
12.7.13
The existing visual amenity varies
in character and sensitivity along the Spur Line alignment from the open
agricultural and fishpond areas at each end to the developed cottage areas in
the middle. Although the agricultural and fishpond areas have open views over
low-lying areas, which have a high level of landscape quality, they also
contain several visually detracting features such as open storage and
infrastructure. This combined with the partial screening of the views by
existing buildings and vegetation, and the viewing distances of VSRs would result
in views, which have an overall medium to low sensitivity to change.
12.7.14
The primary source of visual impact
will be the introduction of the viaduct across the low-lying agricultural and
fishpond areas, together with the disturbance to the vegetation, at the western
end of the study area and the proposed noise barriers at the eastern end of the
alignment. These will cause significant to moderate adverse visual impacts to
the local, generally low-rise VSRs in the western section of the Study Area and
high-rise development in the eastern section.
12.7.15
For the central section the use of
the proposed tunnel will minimise potential impacts arising from the
construction and operational phases however VSRs in close proximity to the
alignment will be subject to the some limited impact due to the proposed above
ground structures. However these will be mitigated to a large extent through
the screening provided by the intermediate buildings and tree groups, and as a
result would be subject to largely slight adverse to negligible impacts.
Overall, these views are of a medium to low sensitivity to further change being
degraded by a number of visually detracting features.
12.7.16
Following the construction of the
proposed Kwu Tung North NDA there would be a large number of additional VSRs.
The view enjoyed by residents of the proposed high-rise development adjacent to
the Spur Line alignment would be characterised by other high rise development
on the opposite side of the alignment and filtered and partial views of the
green backdrop of the hills beyond. The residents would be subject to a slight
adverse to negligible level of impact arising from the presence of the proposed
above ground structures.
12.8
Consultation
12.8.1
The original
consultation exercise completed in September 2000 under the EIAO for the
previous EIA Report gave rise to no specific comments relating to the landscape
and visual aspects of the Spur Line proposals. The new scheme proposals
utilising the tunnel section have also formed part of an ongoing consultation
exercise with organisations such as World Wide Fund for Nature, Hong Kong Bird
Watching Society, Conservancy Association and Friends of the Earth in addition
to the relevant statutory and advisory bodies, however no adverse comments have
been received relating to the landscape and visual aspects of the project.
12.9
Cumulative
Impacts
12.9.1
In a number
of locations along the Spur Line alignment, current or future
works (by project proponents) will occur before the construction of the Spur
Line. These include the expansion of the Lok Ma Chau Boundary Crossing and the
construction of the Fanling, Sheung Shui and Hinterland Drainage Channels. The
San Tin Eastern Drainage Channel construction will start at a similar time to
the commencement of construction of the Spur Line, whilst the proposed San Tin
Western Drainage Channel would (if approved) probably also overlap with the
Spur Line construction programme. All of these projects will result in
landscape and visual impacts including the degradation of landscape character
and visual amenity, and the loss of landscape resources.
12.9.2
Mitigation measures to address
landscape and visual impacts have been incorporated into the design of each of
the approved projects. The resulting changes to the existing landscape
character, landscape resources and visual amenity have been taken into account
in the baseline assessment. Cumulative impacts from these projects are
therefore taken into account through their inclusion in the baseline conditions
for the Spur Line EIA. A summary of the likely implementation programme for the
works to be carried out in the area is shown below.
Table 12.5: Outline Implementation Programmes for Concurrent Projects
Project |
Period of Works |
Lok Ma Chau
Boundary Crossing |
May 1999 - 2003 |
Shan Chun River Training Phase III |
2001 - 2004 |
San Tin Eastern
Main Drainage Channel |
September 2002 -
2005 |
Fanling, Sheung
Shui and Hinterland Main Drainage Channels (Long Valley area) |
June 1999 - 2001
(some elements delayed) |
12.9.3
This indicates that there will be
some overlap between the Spur Line and other projects. This will be primarily
in the area of San Tin Eastern Drainage Channel, during construction works.
Impacts should be minimised through adherence to good site management practices
that will minimise adverse landscape and visual impacts.
Completed Projects with Mitigation Measures which may be
affected by the Spur Line Proposals
12.9.4
The Lok Ma Chau Boundary Crossing
project involves the establishment of new tree and shrub planting to screen the
proposals from adjacent VSRs and provide a measure of integration into the
existing landscape context. The Spur Line proposals will lead to a small loss
(less than 0.1 Ha) of this planting area due to the construction of the
proposed viaduct section over the crossing. However the proposed mitigation
landscape measures will restore this planting where possible and thus obviate
any long-term adverse impacts.
Concurrent Projects with Potential for Cumulative Impacts
12.9.5
Table 12.6 lists major projects that
will be conducted concurrently with the construction of the Spur Line. Each
of these projects will have a potential adverse impact on the landscape and
visual amenity within the Study Area. The locations of these projects in relation
to the Spur Line Alignment are shown on Figure
2.3. Projects of particular significance, due to their proximity to the
proposed Lok Ma Chau Terminus include the construction of the San Tin Eastern
Main Drainage Channel, and expansion of the Lok Ma Chau Boundary Crossing.
12.9.6
The San Tin Eastern Main Drainage
Channel which will be constructed to the west of the Lok Ma Chau Boundary
Crossing will be crossed by the elevated section of the Spur Line. These
proposals will have an adverse impact on the existing landscape of the fishpond
area through the introduction of an engineered channel. The section of the
channel affected will have grasscrete banks and include an adjoining area of
wetland to be provided in mitigation for the predicted ecological impacts of
the proposals. Direct landscape and visual impacts to these proposals arising
from the Spur Line at its crossing point will be negligible with the formation
of one or possibly two columns for the viaduct, resulting in direct loss of
grasscrete bank and/or wetland of 25-50 square metres. The cumulative impact of
these concurrent proposals will lead to a further degradation of the landscape
character of the F2 Lok Ma Chau and F3 Sam So Shue fishpond areas.
Possible Future Projects with Potential for Cumulative
Impacts
12.9.7
Subsequent projects should avoid
direct adverse impacts on mitigation areas that are already designated through
this or any other project. This applies, in particular, to the proposed San Tin
Western Drainage Channel. Should a decision be made to proceed with this
project, its’ alignment must be designed so that they have no adverse impact on
the landscape mitigation proposals for the Spur Line and / or compensate for
any direct or indirect adverse effects.
Table 12.6: Summary of Major
Committed Projects Adjacent to the Spur Line
Project
Description |
Potential
Impacts |
Commencement
Date |
Completion Date |
Shan Chun River Training Phase III involves the
realignment of the Shan Chun River to improve drainage efficiency and prevent
flooding. |
Significant and permanent adverse landscape and visual impacts. This
is largely due to the scale of the proposals, their inability to relate to
the existing landscape character, scale and pattern, and the lack of
landscape and visual impact mitigation measures. |
Mid 2001 |
Late 2004 |
San Tin Eastern Main Drainage Channels – drainage
improvement works to alleviate flooding in the San Tin area and provide flood
storage ponds for Chau Tau and Pun Uk Tsuen. |
Significant and permanent adverse
landscape and visual impacts. This is largely due to the scale of the
proposals, their inability to relate to the existing landscape character,
scale and pattern, and the lack of landscape and visual impact mitigation
measures. |
September
2002 |
2005 |
Fanling, Sheung Shui & Hinterland Main Drainage
Channels – drainage improvement works to alleviate flooding in the Fanling,
Sheung Shui & Hinterland areas. |
Significant and permanent adverse
landscape and visual impacts. This is largely due to the scale of the
proposals, their inability to relate to the existing landscape character,
scale and pattern, and the lack of landscape and visual impact mitigation
measures. |
1999 |
2001 |
Planning & Development Study on Northeast New
Territories involves examination of the scope and feasibility of accommodating
strategic growth development needs in the NENT. |
The NENT Study that includes the proposed
Kwu Tung North NDA and Fanling Bypass will also have a considerable impact on
the landscape character and visual amenity of the Study Area including
indirect impacts on the Long Valley area. The NDA will result in significant
and permanent adverse landscape and visual impacts to the central section of
the Study Area and so largely negate predicted impact of the above ground
structures associated with the proposed tunnel in this part of the Study
Area. |
(Programme not yet confirmed) |
- |
Lok Ma Chau Control Point Expansion Project – kiosk expansion
and works to improve vehicle and passenger throughput and circulation. |
Significant and permanent adverse
landscape and visual impacts. This is largely due to the scale of the
proposals, their inability to relate to the existing landscape character,
scale and pattern, and the lack of landscape and visual impact mitigation
measures. |
Mid 1999 |
2003 |
12.10
Opportunities
for Mitigation Measures
12.10.1
The landscape mitigation measures
are described in this report so to a level of detail which both demonstrates
their ability to alleviate the potential landscape and visual impacts
identified in the assessment and also to allow the proposals to be carried
forward during the detailed design stage. More detailed landscape proposals
will be developed during the completion of the Design and Construction phase of
this project following the proposed detailed tree survey.
12.10.2
Within this report the mitigation
has been described for broad areas of similarity cross referenced to the appropriate
figures. Figures 12.7a, b,
c, d,
e, f,
g, h,
i, j,
k, l,
m, n,
o show the proposed landscape
mitigation measures. It is recommended that the Environmental, Monitoring
and Audit Requirements (EM&A) for landscape and visual resources described
in Chapter 15 of this report is undertaken during both the construction and
operational phases of the project.
Standards, Legislation and Guidelines
12.10.3
The landscape and visual mitigation
design aspects of this project shall be undertaken in accordance with the
following guidelines:
·
Hong Kong Planning Standards and
Guidelines, particularly Chapter 4;
·
Planning Environment and Lands
Branch Technical Circular No. 3/94 (WBTC No.24/94, Tree Preservation);
·
Management & Maintenance of
both Natural Vegetation & Landscape Works (Works Branch), WBTC No. 18/94;
·
Management & Maintenance of
Landscape Works along Public Roads. Aug 1996 (HyD. Guidance Notes), LU/GN/001;
·
Visibility of Directional Signs,
HyDTC 6/98;
·
Control of Visual Impact of Slopes
(Works Branch), WBTC 25/93;
·
Improvement to the Appearance of
Slopes (Works Branch), WBTC no. 17/2000;
·
Technical Guidelines on Landscape
Treatment and Bio-engineering for Manmade Slopes and Retaining Walls (GEO Publication No. 1/2000)
·
KCRC West Rail
Design Guidelines;
·
The Advisory Committee on the
Appearance of Bridges and Associated Structures (ACABAS), WBTC No. 19/98;
·
Allocation of Space for Urban
Street Trees (Works Branch), WBTC; and,
·
Appearance of Structures. Lands and
Works Branch Technical Circular No. 11/89.
Primary Mitigation Measures
12.10.4
In accordance with the EIAO TM, the hierarchy for landscape and
visual impact mitigation is first avoidance of impact, then minimisation of
impact and finally compensation of impact. The
Spur Line alignment has been selected based on engineering, operational safety
and environmental grounds. The rationale for the combination of a viaduct in
the western section and a bored tunnel in the eastern section has been
explained in Chapter 2 of this report. Various options of the alignment were
examined in detail from the environmental point of view, in the PPFS, the
previous EIA study and were also considered by the Appeal Board.
12.10.5
In terms of the avoidance and
minimisation of impact to the existing landscape and visual amenity, the Spur
Line alignment seeks to fulfil the following objectives:
·
Minimisation of the cumulative
impact, as far as possible, to the landscape through for example the selection
of an alignment, which is adjacent in the western section to an existing
transport corridor, characterised by the Fanling Highway (NTCR) and the Lok Ma
Chau Border Crossing. In this area the current alignment has been fine tuned
for engineering reasons and so is in closer proximity to the existing
infrastructure;
·
Protection of areas of high
landscape quality such as Long Valley through the utilisation of the proposed
tunnel section;
·
Maintenance of the unique landscape
character of the Study Area as a resource for the HK SAR, this is apparent in
the proposed mitigation measures for the LMC Terminus whereby impacts to the
large part of the existing fishpond area have been avoided through the location
of the complex on the northern periphery of the area contiguous to the existing
Lok Ma Chau Border Crossing; and,
·
Rehabilitation of existing
landscapes following the completion of the construction phase of the project,
this will be apparent in the restoration of the fishpond areas below the
proposed viaduct section in the western section of the alignment and the
restoration of temporary works areas.
12.10.6
In accordance with the EIAO TM, mitigation measures for the
construction and operational phases of the development have been designed to
minimise predicted landscape and visual impacts, and to compensate for lost
landscape resources as far as is possible given the project constraints.
Secondary Mitigation Measures
12.10.7
A series of mitigation measures
designed to alleviate impact and where possible compensate for loss of
landscape resources for the construction and operational phases of the project
are described below.
Construction
Phase
Preservation of Existing Vegetation
12.10.8
An important mitigation for both
the landscape and visual impacts is the retention of existing planting,
particularly trees. The design of the project has considered the avoidance of
disturbance to the existing trees as far as is practicable.
12.10.9
A full tree survey is currently
being undertaken and this will be submitted for approval to the relevant
government departments in accordance with Planning Environment and Lands Branch
Technical Circular No 3/94 (WBTC 24/94, Tree Preservation). Full details of the
existing of the existing trees on site will be given in the Tree Survey Report
and Tree Felling Application. This document also includes recommendations for,
where appropriate, their retention in situ, transplantation to a new location
and felling. The fundamental tenet of this study is that trees will be
retained, where possible, with particular regard given to the retention of tree
groups. Where it is not possible to retain trees due to the construction of the
Spur Line proposals the trees have been considered for their suitability for
transplanting. Trees identified for retention will be adequately protected
during the construction phase. Trees identified for retention within the
project limit would be protected during the works with these protection
measures being written into the contract documents. These measures for the
protection of existing trees will be described in detail in the tree survey
report Appendix 1: Particular Specification for Tree Protection, Tree Pruning
and Tree Transplanting and includes the following provisions:
·
The use of sturdy protective
fencing located at the edge of the tree canopy (100mm outside the crown spread)
and not around the trunk. The fencing, which will be in accordance with the
Highways Department’s standard drawings numbered H6120, and will be erected
prior to the commencement of the construction phase operations;
·
prohibition of the storage of
materials, the movement of construction vehicles, refuelling and the washing of
equipment including concrete mixers beneath the tree canopy;
·
the watering of existing vegetation
particularly during periods of excavation when the water table beneath the
existing vegetation is lowered;
·
the rectification and repair of
damaged vegetation to it’s original condition prior to the commencement of the
works;
·
the specifications for the
treatment of trees identified for transplantation should include the following:
·
treatments prior to uplifting
operations including crown and root pruning;
·
treatments during lifting
operations where the specification should include details of root cutting and
root ball treatment;
·
the preparation of recipient sites;
·
the timing and methods of planting
and aftercare of the transplanted trees, and;
·
the preparation of photographic
records for existing retained and transplanted trees throughout the
establishment period to monitor their health.
12.10.10
The tree transplanting and planting
works would be implemented by approved Landscape Contractors and inspected and
approved on site by a qualified Landscape Architect or Aboriculturalist. A tree
protection and transplanting specification based on the provisions of the tree
survey report will be included within the contract documents. The extent of the
works area will be regularly checked during the construction phase to avoid
trespass onto areas outside the works area and so minimise damage to existing
trees and woodland.
Temporary Works Areas
12.10.11
A number of locations have been identified
for temporary works areas (refer to Figure
12.7a–b), these include
an area west of the intersection of San Wan Road and Po Shek Wu Road in Sheung
Shui, a section of the former military base Dill’s Corner Camp and an south
of Chau Tau. The temporary works area also include the proposed Tunnel Boring
Machine (TBM) launching shaft to the east of the River Sutlej MDC and the
TBM extraction shaft to the south of Chau Tau, and will include facilities
for the extraction of excavated materials including conveyor belt system.
These sites are contiguous to the proposed track alignment. Construction site
controls would be enforced where possible to ensure that the landscape and
visual impacts arising from the construction phase activities are minimised,
these are as follows:
·
Temporary works area would be
screened using hoarding and existing vegetation would be retained;
·
The careful design of site lighting
to prevent light spillage;
·
Structures such as offices should
be painted in muted and recessive colours;
·
Hydro seeding should be applied to
temporary works areas, and;
·
Temporary construction sites shall
be restored to standards accepted by the concerned government departments, or
better than the original condition.
Hoarding
12.10.12
A temporary hoarding would be
erected along the edge of the works to screen the construction operations from
the local VSRs. However, as parts of the Spur Line are elevated on viaduct
sections, hoarding may not be a practicable solution in all locations Those
locations where hoarding would be appropriate include the following:
·
the area north of Sheung Shui
Station where hoarding would screen the works area in low level views open to
pedestrians and vehicular travellers;
·
the boundary of the temporary works
areas identified above;
·
the central section of the route
alignment adjacent to Chau Tau, which is characterised by cottage areas and
villages. The hoarding would screen low-level views of the construction
activity from the local VSRs; and,
·
the project limit for the proposed
widening of Lok Ma Chau Road to screen low-level views from adjacent
residential development.
12.10.13
Further locations for hoarding will
be identified during the detailed design stage of the project when the full
detail of the construction activity is known.
Topsoils
12.10.14
The works will result in
disturbance to extensive areas of topsoil. This topsoil, if following standard
soil horticultural testing techniques is found to be worthy of retention,
should be stockpiled to a maximum height of 2 metres. The stock piled topsoil
should be either temporarily vegetated with hydroseeded grass during the
construction phase and turned over on a regular basis to avoid degradation of
the organic material. This material should be re-used following the completion
of the main rail related construction phase activities. Alternatively, if this
is not practicable, it should be considered for use elsewhere, including other
projects. Excavated material from the pond bunds should be used as topsoil, if
suitable as a growing medium, for the establishment or re-instatement of
vegetation.
Operational
Phase (after construction)
Landscape Mitigation Measures including Compensatory Planting
Proposals
12.10.15
The compensatory planting proposals
would be considered in greater detail during the later stage of the project. At
this stage the landscape mitigation measures for the proposed scheme have been
considered in four sections which are as follows:
North of Sheung Shui Station (refer to Figure
12.7a, b, c,
d)
12.10.16
The limited area available due to
the proximity of existing development would restrict the scope for landscape
mitigation beyond the reprovision of paved areas and the treatment of the
proposed noise barriers to the east of the existing KCRC East Rail alignment as
described below. However the existing tree planting lining San Wan Road would
be reprovisioned where space allows.
Tunnel Section (refer to Figure
12.7d, e,
f, g, h,
i)
12.10.17
The proposed scheme would be
constructed in tunnel from the existing KCR East Rail to the area south of the
village of Chau Tau. For this section of the alignment there would be generally
no visible structure above ground with the exception of the proposed EAP
structures, ventilation buildings and the station entrances in the future Kwu
Tung North NDA. Therefore the important landscape of the Long Valley area would
be left intact.
12.10.18
These elements of the scheme would
comprise as has been described above low-rise structures ranging in height up
to 10.8m for the EAP Structures, 12.7m for the ventilation buildings and 17.3m
for the proposed above ground service cluster associated with the proposed Kwu
Tung Station. The landscape mitigation will follow a dual approach. The first
will be through the careful design of the form and finishes to the proposed
structures. This will extend to the colour of the main buildings, which should
match the tonal qualities of the landscape context and through the use of
colour massing to break up the visual form of the structure. This massing may
involve the use of blocks of colour or tone, which provide a subtle variation
and reduce the apparent visual mass of the structure. Although generalisations
are unwise earth colours with warm tones usually fit in to the landscape best.
The surface treatment of the proposed structures is also important and
reflective surfaces should be avoided.
12.10.19
The second approach to the mitigation
of these structures should be through the introduction of woodland buffer
planting on peripheries of the gazetted areas for each element forming where
possible a visual continuum with the existing woodland structure of the Study
Area.
Western Viaduct Section (refer to Figure
12.7j, k, l,
m, n)
12.10.20
In general this section would be
viaduct over an existing area of fishponds. These fishponds would be reinstated
below the viaduct. Where planting is required it would be concentrated on
disturbed soil areas or areas adjacent to the bases of the viaduct columns and
would comprise woodland and shrub planting, particularly adjacent Chau Tau. The
selection of tree and shrub those species selection would include species
native to Hong Kong and would provide aesthetic interest. The loss of existing
vegetation would be a primary source of both the landscape and visual impacts.
The following principles would be considered during the design of these
planting areas:
·
A corridor would be identified
separate from the utility corridors which impedes landscape works;
·
Where appropriate, woodland
planting would be established, with species types reflecting those affected
combined with species suitable for screening the proposed scheme in views from
future VSRs. The long-term objective would be to create native woodland. The
immediate objective of the planting on the disturbed areas would be to create a
fast vegetative cover for quick visual effect. The nurse species would be
selectively felled following the successful establishment of the target
indigenous species and to allow for native species to become dominant in the
long term;
·
A higher proportion of ornamental
species would be introduced into areas adjacent to residential developments or
along some sections of the alignment for visual effect; and,
·
The planting would be designed to
avoid emphasising the engineered form and linearity of the proposed track
alignment. This would be achieved using a number of methods such as varying the
type and height of vegetation along the trackside.
Emergency Vehicle Access and General Vehicular Access Road to
the Lok Ma Chau Station Complex (refer to Figure
12.7 l, m, n,
o)
12.10.21
The eastern part of this Emergency
Access Road (EVA) would involve the widening of the existing single lane Lok Ma
Chau Road resulting in the loss of an existing row of mature trees which
currently line the road. As has been described above a full tree survey will be
carried out in accordance with WBTC 24/94. These trees would be retained, where
possible. However, where this is not feasible the suitability of these trees
for transplantation would be considered. Trees identified for retention will be
adequately protected during the works as has been described above, this will be
detailed in the Tree Survey Report. The roadside trees would be replaced to
reproduce and enhance the landscape character of the existing roadside
landscape.
12.10.22
The western section of the EVA and
general access road would involve the widening of the existing carriageway into
an area of fishponds. These fishpond areas would be restored following the
construction phase. Roadside planting would include grass species to stabilise
the embankment sides and occasional specimen trees to mirror the existing
landscape character of the area through which the access road would pass.
Lok Ma Chau Terminus Complex (refer to
Figure 12.7o)
12.10.23
The landscape associated with the
station complex would fall into two main categories, the first a landscape
framework of woodland planting which would form the landscape and visual context
into which the built development would fit, the second would compliment the
building and provide a signature landscape as a gateway to Hong Kong. Detailed
proposals for the station complex would be formulated during the detailed
design stage of the project.
12.10.24
Woodland planting using native
species would be established on the boundary of the proposed station complex to
soften the built form, visually integrate the development into the landscape of
this existing rural setting and provide a buffer or transitional zone between
the proposed development and the proposed ecological mitigation areas. The
character of this landscape treatment would be one that provides a
naturalistic, soft form, which is responsive to the attributes of a landscape
of fishpond areas and small clumps of trees. The ecological impact assessment
has identified several areas adjacent to the station as potential sites for
wetland mitigation including marsh and reedbed areas (refer to the Ecology
Chapter 4 for details). A co-ordinated approach has been undertaken between the
ecology and landscape teams to produce a comprehensive package of mitigation
measures that fulfil both the ecological, and landscape and visual imperatives.
12.10.25
The proposed tree and shrub
planting design would be guided by the principles described under the proposed
soft landscape mitigation for the central section of the proposed scheme.
12.10.26
The more formal landscape treatment
of the areas immediately adjacent to the station complex, largely visually
contained by the peripheral woodland planting, would be more contemporary in
nature reflecting the modernity of the proposed station complex. This concept
would be realised through the contemporary design and use of both hard and soft
landscape elements providing a gateway for travellers to the Hong Kong Special
Administrative Region. The species selection for the design of this area would
perform a number of roles including contributing to the passenger landscape
milieu in an aesthetic sense, the formation and containment of space, the
highlight and framing of the architectural features or focal points of the main
station buildings and the screening of ancillary structures.
Tree Planting Strategy
12.10.27
The landscape mitigation described
above would incorporate the proposals to be described in Chapter 2 of the Tree
Survey Report (currently being prepared), which contains compensatory tree
planting proposals for the overall Spur Line scheme. These proposals are based
on the findings of this report and those of the Tree Survey Report. The
strategy proposes that in order to compensate for the large number of trees
lost as a result of the railway construction, the opportunities for tree
planting should be maximised wherever possible. This dense woodland planting
would find a resonance in the existing visually enclosed and well vegetated
landscape of the central section of the Study Area. .
12.10.28
The tree planting strategy also
gives guidance on the planting of trees in close proximity to structures such
as the viaducts. It proposes that two height bands are used, below 6 metres in
height for locations in close proximity to the viaducts and trees above 6
metres in height for other locations. The proposals list species appropriate
for both bands including species with narrow crowns suitable for planting in
close proximity to the viaduct structures.
12.10.29
The tree planting proposals include
some 4 hectares of compensatory tree planting within the project limit for
the Spur Line would compensate for the loss of specimen trees, small woodland
copses and woodlands resulting from the scheme. This equates to approximately
30,000 new trees based on the planting of whips at 1.5 m centres within the
Gazzetal Boundary (this figure assumes the implementation of the mitigation
measures described above and presented as Figures
12.7a, b, c,
d, e,
f, g,
h, i,
j, k,
l, m,
n, o). The final density of the proposed
tree planting areas would be significantly lower than the number described
above due to the thinning of the stand in order to allow the growth to maturity
of the woodland trees. However if the target of a mature woodland stand is
to be achieved the final density should be around 5 - 10 metre centres (approximately
4,500 to 9,000 trees). This compares favourably with the report’s assertion
that some 1,800 trees would be felled or
transplanted due to the Spur Line proposals. Following the successful establishment
of newly planted trees and assuming that the transplanted trees are retained
on site, the project’s Gazettal Boundary will contain between 5,900 and 10,400
trees.
Major Engineering Structures
12.10.30
Particular attention would be given
to the design, appearance and construction methods of the structures which form
part of these proposals, these would include the following:
·
the noise barriers north of Sheung
Shui;
·
the viaduct sections which would
form the main visible structures within the proposed scheme;
·
the ventilation buildings to the
west of Sheung Shui and south of Chau Tau, the EAP structures located west of
the River Beas, north of Dill’s Corner Camp, north of Lok Ma Chau transport
interchange on Fanling Highway and north of the Lok Ma Chau Control point; and,
·
the retaining structures which
would be located along the proposed alignment particularly along the approaches
to the tunnel portals.
12.10.31
The landscape consultants have
worked in unison with the engineers on the aesthetic aspects of the structures
and their relationship with the landscape. The major engineering structures
will be submitted to ACABAS for their comment and advice. This will then inform
the design and visual appearance of the proposed structures in the detailed
design phase of the project. However overall the designs would consider the
following principles:
·
The structures would aim to “touch”
the ground as lightly as possible in order to minimise disturbance to the
existing landscape and vegetation below the structures. This would be achieved
by designing slender, rounded columns spaced the maximum distance apart. The
viaducts would be constructed using pre-cast methods and launched from columns
rather than scaffolding. The viaduct should be designed to achieve where
appropriate a graceful, curving alignment;
·
Landform and vegetation in areas
disturbed by construction works would be reinstated to blend with the existing
landscape patterns or as discussed above;
·
Wherever light levels, the water
regime and the requirements of the ecological mitigation measures permit,
vegetation would be reinstated below the structures. Irrigation may be required
in some locations and hard landscape solutions considered where the clearance
is low. Planting would be used wherever possible to minimise the apparent
height of structures and to soften their appearance in medium and long distance
views;
·
The design of the proposed
structures should avoid unnecessary visual clutter, this would be achieved through
the co-ordination of the various engineering disciplines involved to arrive at
innovative design solutions;
·
Fair faced concrete would not be
used for parapets to minimise glare from the structure and to avoid the
visually detracting effect of staining; and,
·
Drainage structures would where
possible be concealed within the structure of the proposed viaducts.
Noise Mitigation Structures
12.10.32
Under the current proposals the
requirement for noise barriers would be limited to an area north of Sheung Shui
station. An approximately 300 m long and 5 m high noise barrier on the eastern
side of the existing KCR East Rail alignment would stretch from the existing
station complex north. A 300 m long, 5.8 m vertical noise barrier with 3.6 m
cantilever at 60 degrees would be constructed on the western side of the KCR
East Rail alignment. The design of these structures would be responsive to the
landscape through which the track would pass which is essentially an urban
environment characterised by high-rise residential property and commercial /
warehouse premises. The barriers would also pick up on existing design themes
in the station complex to ensure that the new structure would be visually
compatible with existing ones.
12.10.33
The design criteria for the noise
mitigation structures installed along the trackside should not be limited to
the functional requirements of mitigating train noise. It should also include a
requirement that these structures make a positive contribution to the urban
landscape character of this area and by doing so improve the perceived
landscape quality of the area. These barriers would be visible from some VSRs
identified in the study.
12.10.34
The design criteria should seek to:
·
Promote the innovative use of
materials, such as Plexiglas, fibreglass, reinforced concrete etc, whilst
remaining aware of the design life span of each of the elements incorporated in
the design;
·
Reduce the visual effect of the
structure through the use of form, materials, textures colours and tones;
·
Reflect the chromatic context of
the surrounding urban landscape; and,
·
Utilise materials, which are
non-reflective avoiding glare from incident sunlight.
12.11
Mitigation
Measures and Operational (Residual) Impacts
12.11.1
The mitigation measures have been
developed to alleviate the identified landscape and visual impacts, these
will eventually form the basis for the landscape proposals. Figures
12.7a, b, c,
d, e,
f, g,
h, i,
j, k,
l, m,
n, o shows the broad landscape treatment
proposed to mitigate the effects predicted during the EIA, whilst Figures
12.8a, b, c
show how these mitigation measures would be implemented through the use of
a number of typical sections.
12.11.2
A series of computer generated images
or photomontages are shown on Figure
12.10 a, b, c,
d, e,
f, g,
h, i,
j, k,
l, m,
n, o,
p, the location of which
are identified on Figure 12.9.
The photomontages of the proposed scheme show the existing conditions, unmitigated
impacts, partially mitigated impacts during the opening year (Year 1) and
those residual impacts which would exist in the design year during the operational
phase (Year 10-15).
12.11.3
Figures
12.10 a and b show the
existing view from Lok Ma Chau Lookout Point towards the proposed Terminus
Building. The post construction view as presented shows the proposed viaduct
crossing the pond area to the east of Lok Ma Chau Boundary Crossing control
point before crossing San Sham Road and joining the proposed Terminus Building.
The images show the proposed scheme integrated into a landscape characterised
by open storage areas, fishpond areas and the infrastructure associated with
the boundary crossing.
12.11.4
Figure
12.10 c, shows the existing view from the road south of Chau Tau towards
Ki Lung Shan. The works associated with the drainage works which form the
foreground in views from Chau Tau would obscure much of the available view
of the proposed above ground structure associated with the tunnel section,
therefore the view has been brought forward to the new road to the south of
the village. This allows a view of the worst-case scenario in terms of the
impacts arising from these structures. Figures
12.10 c and d show the
post construction view with the proposed ventilation building located at the
western end of the tunnel. The view demonstrates that the west Ventilation
Building will be largely be in scale with the other surrounding developments
and role of the proposed mitigation planting in further alleviating predicted
adverse impacts.
12.11.5
Figure
12.10 e shows the existing view from Yan Shau Wai north towards a skyline
dominated by the urban development of the Shenzhen Special Economic Zone.
Figures 12.10 e and f
show the proposed Terminus Building at Lok Ma Chau in a post construction
view with the proposed screen planting around the station complex and the
proposed finishes to the building superstructure. The image also shows the
viaduct crossing Lok Ma Chau Road and joining the proposed terminus.
12.11.6
Figure
12.10 g shows the existing view from the western bank of the river Beas
MDC north towards the village of Ho Sheung Heung and the summit of Tai Shek
Mo. The post construction views presented as Figures
12.10 g and h show the
proposed above structures associated with the proposed EAP. The image shows
the scale of the proposed structure in relation to the adjacent landscape.
The view also demonstrates the visual and landscape disturbance caused by
the existing MDC works and the role of the proposed landscape mitigation measures
in visually softening the form EAP structure.
12.11.7
Figure
12.10 i shows the existing view from the western bank of the River Sutlej
MDC north west towards the existing KCRC East Rail and Sheung Shui Abattoir.
The view clearly shows the poor quality of the existing landscape, which is
characterised by contained storage and construction activity. The post construction
views presented as figure 12.10
i and j show the proposed
ventilation building at the eastern end of the tunnel section with its relative
scale and visual appearance being in context with the existing landscape character.
The view also demonstrates the role of the proposed mitigation planting in
visually softening the form of the structure.
12.11.8
Figure
12.10 k shows the existing view from San Wan Road at the foot of the Po
Shek Wu Road Bridge looking south west. The post construction views presented
as Figures 12.10 k and l
show the proposed noise barrier extending north from Sheung Shui Station.
The image shows that the form and scale of the proposed noise barrier would
not be visually intrusive in the context of the urban environment.
12.11.9
Figure 12.10 m shows the existing view south east
from the temples to the south of the village of Ho Sheung Heung towards the
EAP Structure west of the River Beas MDC. The viewpoint is located on the
eastern edge of the hard standing adjacent to the temple buildings and thus
represents the worst case scenario in terms of the available views. The actual
view from the eastern façade of the temple buildings will be largely
screened by the mature woodland to the south of the temple site clearly visible
on the right of the images. The proposed EAP structure would have a negligible
impact on the views from this location.
12.11.10
Figure
12.10 o shows the existing view from the 14th floor of Choi Ping House
looking north over Sheung Shui Station and the existing KCR track. The post
construction views presented as figures
12.10 p and n show the
proposed noise barrier with cantilever extending north from Sheung Shui Station
on the western side of the existing KCR East Rail alignment. The existing
tree and shrub planting would be retained where possible to break up the horizontal
emphasis of the structure and reduce its apparent visual mass.
12.12
Environmental
Monitoring and Audit
12.12.1
The EIA has recommended the
EM&A for landscape and visual resources is undertaken during both the
construction and operational phases of the project. The implementation and
maintenance of the soft landscape mitigation and compensatory planting measures
are key aspects of this and should be checked to ensure that the proposals are
fully realised. The proposals for the EM&A Manual and Implementation
schedule are contained in Chapter 15 of this report.
12.13
Programme
for Landscape Works
12.13.1
The landscape works will closely
follow the completion of the civil engineering contracts, as is shown in Table
12.7 below. The Design Year is for the purposes of this study taken as
approximately 10 – 15 years after the scheme opening when the proposed soft
landscape mitigation is deemed to have reached a level of maturity commensurate
with the performance of the proposed mitigation objectives.
Table 12.7 Provisional
Programme for Landscape Works
Section of the Proposed
Scheme |
Approximate Time Scale |
||
Completion of the General
Civil Engineering Works |
Implementation of Landscape
Works* |
Design Year |
|
Track
from Sheung Shui Station to Lok Ma Chau Border Control Point |
June 2006 |
June 2006 to July 2007 |
2022 |
Track
from Lok Ma Chau Border Control Point up to and including the proposed Lok Ma
Chau Station |
June 2006 |
June 2006 to July 2007 |
2022 |
*Note: The
implementation of the soft landscape mitigation measures should be completed as
soon as possible following the completion of the engineering works. Where
possible a phased programme of implementation would ensure that the soft
landscape measures fulfil their mitigation role at the earliest possible
opportunity.
12.13.2
For the purposes of this report the
above programme has been simplified to give an indication of the proposed
design year for the soft landscape mitigation measures. At this stage the
programme is preliminary and subject to finalisation during the detail design
stages of the project. At the very latest the implementation of the landscape
works should be undertaken in the planting season immediately following the
sectional completion of the engineering works. Hydroseeding should however be
undertaken by the main contractor immediately following the completion of the
engineering works. The landscape maintenance for soft works are expected to
include:
·
Regular maintenance, including
irrigation, pruning, etc. for ornamental trees and shrubs. All ornamental areas
would be accessible to maintenance vehicles.
·
Informal maintenance for woodland
planting. The proposed woodland planting would be designed to be low
maintenance. However during the initial establishment period and the following
period until the stand reaches maturity the wooded areas would require an
active management and maintenance regime. This would include the selective
thinning of the woodland to remove the nurse species and achieve the optimal
distance between the trunks to allow the healthy growth of the individual
trees. Beyond these considerations the woodland areas would require little
maintenance inputs, an important considerations particularly where access is
difficult for example in track side locations and on steep slopes. In these
situations maintenance would be on an on-call basis only.
·
Regular clearance of refuse and debris
accumulation within the project limit.
12.14
Implementation,
Management and Maintenance of the Landscape Works
12.14.1
The objective of the management and
maintenance regime for the mitigation measures described above will be to
ensure that the landscape fulfils its role in mitigating the predicted adverse
landscape and visual impacts arising from the proposed scheme. Table 12.8
outlines the implementation, management and maintenance responsibilities for
the landscape works and items associated with this project both during the
construction and operational phases of the scheme.
Table
12.8 Implementation, Management and Maintenance of the Landscape Works
Landscape Item |
Proposed Implementation |
Management Department |
Maintenance Department |
All landscape works within KCRC
Reserve |
KCRC |
KCRC |
KCRC |
Roadside
planting (within 5m of a roadside)* |
KCRC |
LCSD |
LCSD |
Amenity Areas Noise mitigation measures |
KCRC KCRC |
LCSD KCRC |
LCSD / Arch S D KCRC |
*Note: The management / maintenance area of 5m falling
within the responsibility of LCSD is measured from the kerbside.
12.14.2
This has been based on the WBTC No.
18/94, Management and Maintenance of Natural Vegetation and Landscape Works.
The detail landscape design for the project will be submitted to the relevant
Government Departments for their approval during the detail design stage of the
Design and Construction phase of this project. This will also delineate the
final boundaries for responsibility. The landscape mitigation measures do not
include off-site mitigation.
12.15
Summary
12.15.1
After balancing the engineering,
operation, safety, environmental and other considerations, the alignment of
proposed Sheung Shui to Lok Ma Chau Spur Line has been determined as a tunnel
from Sheung Shui to Chau Tau followed by viaduct to the proposed Lok Ma Chau Terminus.
As has been described in Chapter 2, other alignments are either not technically
feasible or cannot be developed within the programmed time period. The
landscape and visual impact assessment has identified the existing landscape
and visual character of the site and study area. It varies from the open and
low lying agricultural and fishpond areas at the western and eastern ends of
the alignment to the more developed cottage areas and road corridor in the
valley between the Tit Hang and Ki Lun Shan hills. This is reflected in the
visual context with views at the ends being open and rural in character, and
the views in the central section being more enclosed and screened.
12.15.2
The primary landscape impacts would
result from the disturbance to vegetation, agricultural areas and fishponds,
together with the introduction of a major infrastructure element within the
landscape at the western section of the alignment. However the proposed
utilisation of a tunnel section bored using the TBM would leave the landscape
above largely intact at the eastern and central sections of the alignment.
There would however be some impacts from the proposed above ground structures
including the EAP, Ventilation Buildings and Kwu Tung Station development.
Table 12.9 below summarises the predicted loss of landscape resources resulting
from the Spur Line proposals and indicates the significance of these losses to
the landscape character of the Study Area. It also provides figures for the
compensatory planting measures designed to mitigate these impacts. These
proposed mitigation measures have been designed to integrate the proposals into
the existing landscape of fishponds, agricultural land, open storage and
cottage areas, and the future landscape represented by the Kwu Tung North NDA.
Table 12.9: Summary of Impact on Existing
Landscape Resources
Landscape
Resource |
Total Area of
Landscape Resource in the Study Area (Ha) |
Total Loss of
Area (Ha) |
% Loss with
the Study Area |
Residual
Impact |
Fung Shui Woodland |
17.81 |
0.02 |
0.1 |
Negligible |
Woodland (including secondary forest
and plantation forest) |
48.00 |
0.16 |
0.3 |
Negligible |
Orchard |
10.91 |
0.52 |
4.8 |
Slight adverse to negligible impact |
Agricultural Land (Dry) |
34.41 |
0.09 |
0.26 |
Negligible |
Agricultural Land (Wet) |
14.25 |
0.0 |
0.0 |
None |
Agricultural Land (not currently
cultivated) |
20.06 |
0.55 |
2.3 |
Negligible |
Fishpond Areas |
92.15 |
9.6 |
10.4 |
Slight adverse |
Marsh |
1.67 |
0.0 |
0.0 |
None |
Watercourses |
56.97 |
0.04 |
0.1 |
Negligible |
Grass / Shrub Mosaic |
8.05 |
0.02 |
0.2 |
Negligible |
*Note: The
provision of mitigation measures for Marsh, Watercourses, and Grass / Shrub
Mosaic forms part of the wetland compensation proposals and is therefore
quantified under the ecological impact assessment section of the report.
12.15.3
For the large part the predicted
impacts would not have a significant effect on the landscape resources found in
the Study Area. Although a small area of the culturally important Fung Shui
forest north of Lok Ma Chau Control Point would be lost, this would not have a
significant impact on either the existing resource or the character of the area
from a landscape perspective. The proposals would lead to the loss of some
1,800 trees within the project limit and a further 250 would be transplanted.
The proposed planting of some 4 hectares of compensatory tree planting within
the project limit for the Spur Line would compensate for the loss of specimen
trees, small woodland copses and woodlands resulting from the scheme. This
equates to approximately 30,000 trees in the proposed mitigation planting
areas, although the eventual number following management operations will be
between 4,500 and 9,000.
12.15.4
The most significant of the losses
would be that of the existing fishponds, which form an increasing scarce
landscape resource within the HKSAR. However the majority of these losses would
occur on the Lok Ma Chau Terminus site where the proximity of the scheme to the
existing Sham Chun River channel and the Lok Ma Chau Control Point, and the
proposed landscape mitigation measures would largely mitigate the schemes
impact on the existing landscape character.
12.15.5
The landscape character of the
study area would not be significantly affected by the Spur Line proposals, the
predicted impacts are summarised in Table 12.10 below.
Table
12.10: Summary of Impact on Landscape Character
Landscape Character Area |
Residual Impact |
L1 North of Sheung Shui L2 River Beas Plain
/ Long Valley and Fung Kong L3 North of Ki Lun
Shan NUA 1 Tai Shek Mo and Tung Kong
Shan NUA 2 Ki Lun Shan NUA 3 Lok Ma Chau V1 Sheung Shui V2 Tai Tau Leng V3 Tsung Pak Long V5 Pun Uk Tsuen and Chau Tau C2 Tung Fong RC1 Fanling Highway RC2 Lok Ma Chau Border
Crossing F1 River Beas Plain |
Negligible |
MUD 2 Kwu Tung North New
Development Area V4 Ho Sheung Heung C1 Ho Heung Sheung C3 Chau Tau |
Negligible to slight adverse |
L4 Chau Tau |
Slight adverse |
MUD 1: Sheung Shui |
Moderate adverse |
F2 Lok Ma Chau F3 Sam So Shue |
Significant adverse |
12.15.6
The utilisation of the proposed
tunnel section would leave the important landscape area of Long Valley intact.
12.15.7
The proposed viaducts would form a
new large-scale element in the landscape. The main thrust of the proposed
mitigation proposals has been to design a visually lightweight structure, which
exhibits a graceful curving alignment. The alignment has where possible been
selected to avoid high quality landscapes.
12.15.8
The proposed noise barriers at
Sheung Shui Station would also form new elements within the landscape although
the barriers would serve to screen some of the visual impacts arising from the
existing railway track and its associated structures. In addition to this the
barriers would be constructed in an area characterised by large-scale buildings
such as the station complex, high-rise residential development and large
warehouse type commercial premises, and so the scale of the development would
be in keeping with the existing landscape context. The detailed design of this
barriers would be carefully considered to minimise potential landscape impacts.
The existing tree planting lining Choi Yuen Road would also aid the structures’
integration into the existing landscape framework. In general terms, the
implementation of mitigation measures such as compensatory planting,
re-instatement of fishpond areas and design of the viaduct and noise barriers
should, where possible, integrate with the local landscape character thus
minimizing much of the residual adverse impact arising from the proposals.
12.15.9
The proposed utilisation of a
tunnel section would have a beneficial impact on the landscape of the Kwu Tung
North NDA in that it would minimise the impact on the future landscape and
visual amenity available to future residents. The predicted adverse impacts
arising from the location of the EAP structure and above ground station
structures would be minimised through the use of tree and shrub planting as
part of the landscape mitigation package. The design of this section of the NDA,
currently under review as part of the NENT Study, should seek incorporate where
appropriate the proposed landscape mitigation measures in this area.
12.15.10
The Spur Line proposals would
result in a negligible level of impact on designated planning zones within the
Study Area. Table 12.11 below summarises the predicted impacts on the existing
and future landscape planning framework of the Study Area.
Table 12.11: Summary of Impact on Existing and
Future Landscape Planning Framework
Landscape Planning Designation |
Residual Impact |
1. Sheung Shui to Lok Ma Chau Spur Line 6/7. District Open Space D3/B6 |
Moderate beneficial |
2. Other Specified Uses/WCA (West of
Sheung Shui and north of Yin Kong) 3. Government / Institution or Community (Area D8 north of the
proposed Spur Line) 4. RS, D7Reidential site
with a plot ratio of 6.5 5.PSPS / HOS D4 16. Green Belt (East of Tit Hang) 22. Major Road (San Sham Road) 23. Drainage Reserve (Parallel to San Sham Road) Outline Zoning Plan S/NE-KTN/3 – Kwu Tung South Generally |
Negligible Impact |
7. RS / PSPS / HOS B4 (Private Sector Participation
Scheme / Home Ownership Scheme Site with a plot ratio of 6.5) 8. RS / PSPS / HOS B4 9. RS B3 (Residential site with a plot ratio of 5.0) 10.
R(2) F3 (Residential site with a plot ratio of
5.0) 11.
R(1) F2 (Residential site with a plot ratio of
6.5) 12.
R(1) F1 (Residential site with a plot ratio of
6.5) 13.
R(2) F4 (Residential site with a plot ratio of
5.0) 14.
G/IC E4 (Government / Institution or Community
Uses; Fire station) 15. OU Business Uses E3 (Other Specified Uses) |
Negligible to slight adverse |
18. Undetermined (Between San Sham and Lok Ma Chau
Roads) 19. Government / Institution
or Community (Lok Ma Chau Control
Point) 20. Green
Belt (South
of Lok Ma Chau lookout point) |
Slight adverse |
17. Green Belt (West of Tit Hang) |
Slight to moderate adverse |
21. Conservation Area (San Sham Road to Ping Hang) 24. Conservation Area (Sam Po Shue) |
Moderate adverse |
12.15.11
Most of the area effected would
comprise agricultural land, although there would be losses to areas of
Conservation Area, and smaller losses to areas designated as Industrial (Group
D), Open storage and Open Space. The potential losses to areas designated as
Conservation Areas would be mitigated through the use of the proposed
ecological mitigation measures described in the ecological impact assessment
section of this report. There would be approximately 5.0 hectares of the
existing Green Belt at the western end of the proposed alignment and some
limited indirect impacts on the Green Belt adjacent to Lok Ma Chau lookout
Point. However approximately 1.7 hectares of the area of direct loss of Green
Belt would be used to accommodate the proposed soft landscape mitigation
measures. Although these impacts are not insignificant in terms of the area
affected, the landscape character of these areas has been degraded by existing
land uses. The proposals would leave the largely pristine hill slopes intact and
so it would not affect the landscape setting of the valley and the future NDA,
or the viability of these areas as Green Belt.
12.15.12
The proposed Spur Line would not
have a direct impact upon the proposed Kwu Tung North NDA, the proposed
alignment is safeguarded within the proposals and its construction would
facilitate some of the planning principles central to the NDA such as the
promotion of a ‘rail based development’.
12.15.13
The review of the existing planning
and development control framework found that the Spur Line proposals would not
conflict with the published land use plans for the Study Area and so no
amendment is required as a result of the proposals. The original Spur Line
alignment and the proposed tunnel option have been subject to consultation with
the general public and the relevant statutory and advisory bodies, and has thus
far received no specific comment concerning the acceptability of the predicted
landscape and visual impacts.
12.15.14
The main visual impacts would arise
from the disturbance to the existing vegetation, the introduction of the
viaduct in the low-lying areas, and in the introduction of the proposed noise
barriers adjacent to Sheung Shui station. The mitigation measures proposed for
the scheme have been outlined above. The predicted visual impacts are
summarised in Table 12.12 below.
Table 12.12: Summary of
Impact on Visually Sensitive Receivers
Visually Sensitive Receivers |
Residual Impact |
2. Sheung Shui Sewage Treatment Works 4. Tsung Pak Long 5. Yin Kong 6. Fanling Highway East 7. Ho Sheung Heung 8. Fung Kong 9. Tung Fong South 10. Tung Fong North 11. Shek Tsai Leng 12. Dill’s Corner Camp 13. Pak Shek Au East 14. Pak Shek Au West 15. Footpath – Lok Ma Chau East 16. Footpath – Ki Lun Shan East 17. Footpath – Lok Ma Chau Central 20. Footpath – Ki Lun Shan West 21. Fanling Highway West 28. KCR East Rail 29. Europa Gardens |
Negligible Impact |
3. Other Uses (ongoing light industrial / commercial development) 32. High Rise Residential Development,
Kwu Tung North NDA (north
of the Spur Line) 33. Low-rise Residential Development, Kwu
Tung North NDA (north of
the Spur Line) 34. High-rise Residential Development,
Kwu Tung North NDA (south
of the Spur Line) 35. Low-rise Development, Kwu Tung North
NDA (south of the Spur
Line) |
Negligible to slight adverse |
1. Choi Po Court 27. San Sham Road and Lok Ma Chau Border Crossing 30. Choi Ping House |
Slight adverse |
18. Chau Tau East 22. Tung
Chan Tai and San Lung Tsuen 24. Footpath and Viewpoint – Lok Ma Chau 25. Lok Ma Chau 26. Ha Wan Tsuen 31. 134 to 140 San Fung Road |
Moderate adverse |
19. Chau Tau West 23. Pun Uk Tsuen |
Moderate to significant adverse |
12.15.15
The visual impacts associated with
the proposed noise barriers situated to the north of Sheung Shui station would
not be significant as these structures would be located in an urban context
characterised by large buildings many of which have a warehouse type design.
The proposed colour and tonal treatment of the barriers would also serve to
minimise these predicted visual impacts. The utilisation of the proposed tunnel
section would alleviate much of the visual impacts arising from the central
section of the alignment.
12.15.16
At the western end there would be
limited opportunity for screen planting, with exception of Chau Tau, as the
fishponds would be reinstated below the viaduct in order to maintain the areas
landscape character. The viaduct would be in general context of the
infrastructure developments such as the existing Fanling Highway (NTCR) and the
Lok Ma Chau Control Point with its associated access roads and proposed vehicle
holding areas.
12.15.17
The proposed Terminus complex at
Lok Ma Chau would be viewed against the high-rise urban backdrop of Shenzhen
and so the existing level of visual intrusion caused by this development would
mitigate much of the resulting visual impact from the proposed scheme. The
proposed mitigation tree and shrub planting around the station complex and the
avoidance of finishes causing glare would also reduce the potential for visual
impact.
12.15.18
Overall the proposed Lok Ma Chau
Spur Line proposals would in terms of residual landscape and visual impacts be ‘acceptable with mitigation’ that is to
say ‘there would be some adverse effects,
but these can be eliminated, reduced or offset to a large extent by specific measures’.