13.
CONSTRUCTION
METHODS, PROGRAMME AND USAGE OF NEW TECHNOLOGIES
13.1
Section 3.1 (xv) of the Particular Scope of the EIA Brief requires an
assessment of: the details of the
construction programme, the construction methodologies and an assessment of the
extent to which the technologies to be employed are proven technologies.
13.2
The permanent work to construct the Spur Line can be summarised as the
construction of the following major elements:
(i)
East Rail diversion,
(ii)
Diversion of the Dong Jiang watermains,
(iii)
The ramps down to the cut and cover sections of tunnel,
(iv)
The cut and cover sections of the tunnel,
(v)
The bored tunnel,
(vi)
The launching shaft, retrieval shafts, Kwu Tung station box, EAP
structures, and ventilation buildings,
(vii)
The ramp up to the viaduct,
(viii)
The viaduct,
(ix)
Lok Ma Chau station vehicular access
(x)
Lok Ma Chau station,
(xi)
The enhancement of the fishponds at Lok Ma Chau,
(xii)
The construction of the footbridge crossing the Shenzhen River.
13.3
Associated with the permanent works are a number of significant
temporary works:
(i)
The jetties in the Shenzhen river for unloading materials,
(ii)
Access roads,
(iii)
Contractors compounds.
13.4
A summary project programme for the whole of the Spur Line is attached
as Appendix A13.1
13.5
Each of the above major features are broken down into their constituent
elements in the Table 13.1 below. The construction methods, programme
durations, and commentary on the extent to which proven technology is adopted
are shown. The programme durations shown below are for concurrent activities in
many cases. The technologies to be used in construction have been discussed in
detail in Section 2 - Description of the Works; and in other individual
sections such as Chapter 3 – Hydrology, in respect of the usage of the Earth
Pressure Balance technology in the tunnel boring work.
Construction Methods, Programme and Degree to Which the Technology is Proven
Ref. |
Feature/element |
Method |
Prog. Duration |
Previous use |
1a |
Diversion of East Rail – temporary
|
Construct new formation for ballasted track. |
2.5 years |
Pak Shek Kok realignment |
1a.1 |
Removal of planters in San Wan Road |
Tree transplanting, tree felling, excavation. |
6 months |
Commonplace |
1a.2 |
Construction of a new 2.4m diameter sewer |
Diversion and reconnection of existing drainage by cut and cover techniques. |
6 months |
Commonplace |
Drive sheet piles and excavate by machine for the sewer and manholes. |
6 months |
Commonplace |
||
Construction of new in-situ reinforced concrete catchpits. |
3 weeks each in phase with the excavation |
Commonplace |
||
Lay granular bedding and precast pipes, backfill and compact. |
3 months |
Commonplace |
||
1a.3 |
Prepare the trackbed formation |
Breakout the road surface by machine. Excavate 600mm soil by machine and replace with granular fill, compacted. Lay track ballast to underside of sleeper, imported by road. |
2 months |
Commonplace techniques |
1a.4 |
Installation of railway systems |
Lay the sleepers – import by road and use mobile crane. Offload rails from a train and lift onto sleepers by mobile crane. Fill between sleepers with ballast, imported by road. |
2 months |
Commonplace methods |
Erect over headline mast by excavating for the base by machine and casting concrete around the prefabricated steel mast. |
3 days each. |
Commonplace methods |
||
Lay precast concrete troughs for control and communications signals by importing by road and laying by hand. |
1 month |
Commonplace methods |
||
Construct protective barrier by excavating for the base by machine and casting concrete around the prefabricated steel sections. |
2 months |
Commonplace methods |
||
1a.5 |
Construct impact protection to Po Shek Wu Road Bridge |
Construct 900 mm diameter reinforced concrete bored piles by piling rig using fluid to maintain stability. |
1 month |
Commonplace methods |
|
|
Excavate by machine using sheet piles to expose the pile heads. Construct in-situ reinforced concrete pilecap and upstand. |
1 month |
Commonplace methods |
1b. |
Final diversion of East Rail |
Construct new formation for ballasted track and connect to existing operating East Rail without disruption to service. |
1 year |
Pak Shek Kok realignment with identical o’night placement and commissioning of turnouts. |
1b.1 |
Formation works |
Place granular fill to formation, imported by truck and spread and compacted. |
2 months |
Commonplace methods |
Import ballast by truck and lay to underside of sleeper. |
1 month |
Commonplace methods |
||
1b.2 |
Railway Systems Installation |
Lay the sleepers – import by road and use mobile crane. Offload rails from a train and lift onto sleepers by mobile crane. Fill between sleepers with ballast, imported by road. |
2 months |
Commonplace methods |
Erect over headline mast by excavating for the base by machine and casting concrete around the prefabricated steel mast. |
3 days each. |
Commonplace methods |
||
Lay precast concrete troughs for control and communications signals by importing by road and laying by hand. |
1 month |
Commonplace methods |
||
1b.3 |
Remove temporary track |
Cut rails and load onto a train by mobile crane. Excavate ballast by machine and load onto trucks for disposal. |
1 month |
Commonplace methods |
Construct road side gullies and connect to the storm drains. Install planter irrigation pipes. |
1 month |
Commonplace methods |
||
Lay road pavement – import materials by truck and roll to compact. |
2 weeks |
Commonplace methods |
||
Reconstruct planter in reinforced concrete, cast in-situ, with stone facing. Complete irrigation installation. |
2 months |
Commonplace methods |
||
2 |
Diversion
of the Dong Jiang watermains |
Earthworks, foundations and new pipework to create a diversion of the mains. |
18 months |
Commonplace thrustblock and mainlaying methods |
2.1 |
Earthworks |
Excavate by machine. Load to trucks for disposal. |
2 months |
Commonplace methods |
2.2 |
Construct thrust blocks |
Bore minipiles and grout. |
1 day for each pile, working progressively with the diversions |
Commonplace methods |
|
|
Excavate to expose the heads of the minipiles and cast reinforced concrete thrust block. |
1 week for each phase, working progressively with the diversions |
Fan Kam Rd diversion of 1.2m diam main. |
2.3 |
Lay pipes |
Install minipile foundations, and cast a pipe support around the head in reinforced concrete. |
2 weeks for each support |
Commonplace methods |
Import new pipes by truck. String out on the new supports as far as possible using a mobile crane, and joint by welding. |
1 month for each main |
Commonplace methods |
||
2.4 |
Tie-in to existing mains |
Cut a section from the existing pipe and bring prefabricated joint section to site by truck. Weld joints. |
1 month for each main |
Commonplace methods |
Remove existing mains by flame cutting or unbolting as appropriate, load to a truck by mobile crane and dispose off site. |
1 week for each main |
Commonplace methods |
||
3 |
Ramps down to the cut and cover
sections |
Reinforced concrete structures. |
6 months for each ramp |
Commonplace methods |
3.1 |
Ramp walls |
Install contiguous bored piles, 1m diameter, in reinforced concrete, using fluid for excavation support. |
4 months |
Commonplace methods |
3.2 |
Base slab |
Excavate soil by machine and remove by truck. Cast the reinforced concrete base slab. |
2 months |
Commonplace methods |
3.3 |
Adjacent drainage channels |
Excavate by machine open cut for the channel and dispose material off site. Arrange so that temporary drainage is always available – see DIA for details agreed with DSD. |
2 weeks |
Commonplace methods |
Cast channel walls and base in reinforced concrete. |
3 months |
Commonplace methods |
||
Backfill and compact fill imported by truck. |
2 weeks |
Commonplace methods |
||
4 |
Cut and
cover sections of tunnel |
Diaphragm wall with reinforced concrete slabs. |
12 months |
Commonplace methods |
4.1 |
Diaphragm wall construction |
Install reinforced concrete lead trench. |
1 month |
Standard for all diaphragm walling jobs |
Set up plant for slurry stabilisation, including materials silos, settlement lagoons and pumps and pipes for circulation of slurry. |
3 months |
Ditto, but tunnel contractor will continue to use this plant for tunnelling. DB320 is most recent combined example. |
||
Mobilise rigs and excavate 800mm thick wall. Dispose of material off site by truck. Excavate every fourth or fifth panel approximately 1.8m in length. |
2 days for each panel |
Standard procedures |
||
Install reinforcement cage by crane and pour concrete into the panel. |
2 days for each panel |
Standard procedures |
||
4.2 |
Roof and floor slab |
Excavate between walls by machine and remove materials by truck. |
3 months |
Standard procedures |
Cast the slabs in reinforced concrete. |
3 months |
Commonplace |
||
Backfill on top of the roof slab with granular fill imported by truck, and compact. |
1 month |
Commonplace, eg all service reservoirs |
||
4.3 |
Adjacent drainage channels |
Excavate by machine open cut for the channel and dispose material off site. Arrange so that temporary drainage is always available – see DIA for details agreed with DSD. |
2 weeks |
Commonplace methods |
Cast channel walls and base in reinforced concrete. |
3 months |
Commonplace methods |
||
Backfill and compact fill imported by truck. |
2 weeks |
Commonplace methods |
||
5. |
The bored tunnel |
Two no. bores by Earth Pressure Balance boring machine. All items are placed or removed from the launching shaft by a purpose installed gantry crane. |
11 months for each bore + 3 months transit |
KCRC Contrct DB320. Highly successful and no public complaint |
5.1 |
Boring through soil |
Using earth pressure balance mode, excavate soil under pressure in the head and remove from the bore. Allow to settle and treat supernatant to neutralise pH, remove oils and coagulate fines for complete removal of solids. Remove solids by truck for disposal. |
300m/month |
KCRC DB320 Contract. Very successful. |
Import precast segments by truck and place in the bore immediately behind the face shield. Grout annulus with cementitious mix, batched and mixed within the tunnel from materials brought to site by truck. |
300m/month |
DB320 Contract Standard tunneling procedures and completed tunnel is waterproof. |
||
5a.2 |
Construct cross passages outside Long Valley |
Establish rig on the ground and bore a 150mm diameter shaft to the cross passage level. Mix grout from materials brought to site by truck and inject into the ground on a grid basis, moving the rig for adequate coverage. |
2 weeks/cross passage |
Common construction technique |
Excavate by hand or small machine from inside the tunnel. Place the lining by spraying concrete, by mixing the materials inside the tunnel, brought to site by truck. |
3 weeks/cross passage |
Common construction technique |
||
5b.2 |
Construct cross passages under Long Valley |
Drill horizontally from within the tunnel to introduce cold fluid to freeze the ground. |
3 weeks/cross passage |
Regular Construction technique adopted where conditions dictate |
Excavate by hand or small machine from inside the tunnel. Place the lining by spraying concrete, by mixing the materials inside the tunnel, brought to site by truck. |
3 weeks/cross passage |
Common construction technique |
||
5.3 |
Installation of the TBM |
Face shield and the following train are brought to site on a series of trucks and lowered into the launching shaft for re-assembly. |
3 months total |
DB320 times two drives |
5.4 |
Relocation of the TBM for the second bore |
Face shield is lifted out in pieces from the retrieval shaft and transported back to the launching shaft on a series of trucks. The train goes back through the tunnel. |
3 months |
DB320 times two drives |
5.5 |
Removal of the TBM |
The face shield and supporting train are taken from the retrieval shaft in pieces and removed from the site on a series of trucks. |
1 month |
DB320 times two drives |
5.6 |
Installation of railway systems |
The track is LVT, which is a combination of reinforced concrete cast in-situ brought to the site by truck, and precast items. The rails are brought to site in long lengths by train, transported along the tunnel and welded in-situ. |
8 months |
DB320 and Airport Railway |
Overhead line supports are brought to the site by truck and fixed in place in the tunnel. |
4 months |
All existing KCRC East Rail Tunnels and DB320 |
||
Cabling is laid out by large drums brought to the site by truck, running along the rails to install. |
4 months |
DB320 |
||
6. |
The launching shafts, retrieval
shafts, EAP shafts, Kwu Tung Station Box, and vent buildings |
Diaphragm wall construction below ground, internal structure is reinforced concrete, above ground structures are reinforced concrete. |
18months for each structure, but before tunnel boring is carried out at that location. |
Common construction technique |
6.1 |
Diaphragm wall construction |
Install reinforced concrete lead trench. |
1 month |
Common construction technique |
Set up plant for slurry stabilisation, including materials silos, settlement lagoons and pumps and pipes for circulation of slurry. |
3 months |
Common construction technique |
||
Mobilise rigs and excavate 800mm thick wall. Dispose of material off site by truck. Excavate alternate panels approximately 1.8m in length. |
2 days for each panel |
Common construction technique |
||
Install reinforcement cage by crane and pour concrete into the panel. |
2 days for each panel |
Common construction technique |
||
6.2 |
Internal slabs, walls and superstructure |
Cast in reinforced concrete brought to site by truck, materials placed by mobile crane and skip. |
12 months for each structure |
Common construction technique |
7 |
Ramp up
to the viaduct |
A piled structure with a reinforced concrete superstructure. |
6 months |
Common construction technique |
7.1 |
Bored Piles |
Install prebored H piles, with material excavated using a down-the-hole hammer. Materials for grouting to be brought to site for batching and mixing on site. |
4 days/pile |
Common construction technique |
7.2 |
Superstructure |
Cast in reinforced concrete brought to site by truck, materials placed by mobile crane and skip. |
3 months |
Common construction technique |
7.3 |
Parapet |
Concrete precast off site, brought to site by truck, lifted and placed by mobile crane, fixed into place by casting a stitch of reinforced concrete. |
3 days for each panel, 1 month total |
Common construction technique |
7.4 |
Adjacent drainage channels |
Excavate by machine open cut for the channel and dispose material off site. Arrange so that temporary drainage is always available – see DIA for details agreed with DSD. |
2 weeks |
Commonplace methods |
Cast channel walls and base in reinforced concrete. |
3 months |
Commonplace methods |
||
Backfill and compact fill imported by truck. |
2 weeks |
Commonplace methods |
||
7.5 |
Installation of railway systems |
The track is LVT, which is a combination of reinforced concrete cast in-situ brought to the site by truck, and precast items. The rails are brought to site in long lengths by train, transported along the tunnel and welded in-situ. |
2 months |
Common construction technique |
Overhead line supports are brought to the site by truck and fixed in place in the tunnel. |
2 weeks |
Common construction technique |
||
Cabling is laid out by large drums brought to the site by truck, running along the rails to install. |
Cables laid with the rest of the alignment. |
Common construction technique |
||
8 |
Viaduct |
A simply supported twin-cell precast prestressed concrete deck erected on falsework, supported by reinforced concrete piers and bored piled foundations. |
18 months |
Common construction technique Most of West Rail |
8.1 |
Foundations |
Install bored piles, 1.8m diameter, in reinforced concrete brought to site by truck and placed by crane and skip, using fluid for excavation support. |
6 days for each pile |
Common construction technique for last 30 years |
Open cut excavation to expose the pileheads, cast the pilecap in reinforced concrete brought to site by truck and placed by crane and skip. |
7 days; 1 month for each foundation |
Common construction technique |
||
8.2 |
Pier |
A single stem in reinforced concrete brought to site by truck and placed by crane and skip, using purpose designed steel formwork. |
20 days for three pours |
Common construction technique |
8.3 |
Deck |
Erect purpose designed falsework on the pilecaps at the end of each span using a mobile crane. Transport the falsework by truck. |
3 days |
Common construction technique |
Bring one cell precast concrete segments to site by truck and erect onto the falsework using a mobile crane. Stress together stage one. |
1 day/span |
Common construction technique |
||
Lower onto temporary bearings and repeat for the second cells for the span. |
1 day/span |
Common construction technique |
||
Cast the end diaphragms in reinforced concrete brought to site by truck, placed by crane and skip, and transfer load to the permanent bearings. |
2 days/span |
Common construction technique |
||
Grout the ducts for the tensioning strands by lifting materials onto the deck by crane, mixing and pumping materials on the deck. |
0.5 days/ span |
Common construction technique |
||
Place the parapets which are concrete precast off site, brought to site by truck, lifted and placed by mobile crane, fixed into place by casting a stitch of reinforced concrete. |
3 days/span |
Common construction technique |
||
Carry out stage 2 of the prestressing. |
0.5 day |
Common construction technique |
||
Remove the falsework using a crane, transport by truck and re-erect further on. |
3 days |
Common construction technique |
||
8.4 |
Installation of railway systems |
The track is LVT, which is a combination of reinforced concrete cast in-situ brought to the site by truck, and precast items. The rails are brought to site in long lengths by train, transported along the tunnel and welded in-situ. |
2 months |
Common construction technique |
Overhead line supports are brought to the site by truck and fixed in place in the tunnel. |
2 weeks |
Common construction technique |
||
Cabling is laid out by large drums brought to the site by truck, running along the rails to install. |
Cables laid with the rest of the alignment. |
Common construction technique |
||
9 |
Lok Ma Chau Station Vehicular
Access |
Comprises a widening of the existing road and a realignment where it passes over the Spur Line. |
3 years 4 months |
Common construction technique |
9.1 |
Formation works |
Tree transplanting and felling. |
6 months |
Common construction technique |
|
|
Excavation of soft materials near the ground surface by machine, disposed off site by truck. |
8 months |
Common construction technique |
|
|
Deposition of granular materials brought to site by truck, and compacted by vibrating roller. |
2 months |
Common construction technique |
|
|
Installation of precast kerbs, road gullies and drainpipes by excavator brought to ite by truck, backfilled by granular materials and compacted. |
2 months |
Common construction technique |
|
|
Laying and rolling pavement materials brought to site by truck. |
1 month |
Common construction technique |
10 |
Lok Ma Chau Station |
Ground formation works by filling ponds, followed by piling and superstructure works. |
3 years 9 months |
Common construction techniques. See LMC Boundar Crossing |
10.1 |
Formation works |
The tops of the bunds forming the ponds in the station footprint are lowered by excavator, and the material placed in the area to be made a marshland. Geogrid and Wick drains, surcharge. |
1 month |
Common construction technique. See LMC Boundary Crossing |
Diversion of an existing watercourse by placing fill by machine, compacting it and forming the channel in grasscrete (precast conrete). Construction of a weir in reinforced concrete and excavation by machine for additional pipes to upgrade the existing outfall. |
3 months |
Common construction technique. See LMC Boundary crossing |
||
Sand fill is brought to the site by barge and placed in the ponds by a conveyor, displacing the remaining water in the ponds to neighbouring ponds. |
6 months |
Common construction technique. See Tin Shui Wai and River Trade Terminal |
||
Excavate trenches by machine using trench sheets for support, and place drain pipes. |
4 months |
Common construction technique |
||
10.2 |
Piling |
Install bored piles, 2.1m diameter, in reinforced concrete brought to site by barge and placed by crane and skip, using fluid for excavation support. |
6 days for each pile |
Common construction technique. See NTCR and LMC Boundary crossing |
Open cut excavation to expose the pileheads, cast the pilecap in reinforced concrete brought to site by barge and placed by crane and skip. |
7 days; 6 months for foundation works |
Common construction technique |
||
10.3 |
Superstructure |
Reinforced concrete brought to site by barge is placed using a crane and skip. Other materials such as cladding will be brought to site by barge and erected using a crane. |
18 months |
Common construction technique |
10.4 |
Finishes and fit out |
Materials will be brought to site by truck and lifted using crane. |
18 months |
Common construction technique |
11 |
Enhancement of the fishponds at
Lok Ma Chau |
A water management system comprising an arterial pipe is to be installed, together with some modifications to the pond bunds to form the required habitat. |
3 years |
Common construction technique. Uses traditional labour, farming methods and equipment |
11.1 |
Formation of the marsh |
Reworking by machine of the bund material placed during station formation. |
2 months |
Common farming technique |
11.2 |
Installation of the water control measures |
Installation of steel sheet piles, installed by vibrating in to position, and excavation of the bunds by machine. |
2 weeks for each location |
Common construction technique |
Bring to site by truck precast concrete catchpits, culverts, channels, lifted into position by small crane. |
2 weeks for each location |
Common construction technique |
||
Laying of uPVC pipes into the ponds by hand. |
1 week for each location |
Common construction technique |
||
Backfill around catchpits with bund material, compacting by machine, and withdrawal of sheetpiles by vibrator. |
1 week for each location |
Common construction technique |
||
Excavation by machine of a shallow trench to install uPVC pipes forming the arterial system, backfilling with bund material. |
1 month in each half |
Common construction technique |
||
11.3 |
Modifications to the bunds |
Use of an excavator to lower the bunds, spreading to one side as required. |
3 days for each location |
Common farming and construction technique |
Import of 10mm aggregate by truck, placed by machine on a geotextile. |
1 day for 100m |
Common construction technique |
||
11.4 |
Construction of the pipe bridge |
Installation of gabions in the pond, with materials brought to site by truck and placed by machine. |
1 week |
Common construction technique |
|
|
Installation of timber piles brought to site by truck, by vibrating in to position by machine. |
1 week |
Common construction technique |
|
|
Installation of timber walings, and backfill by grade 200 fill brought to site by truck and placed by machine. |
1 week |
Common construction technique |
|
|
Installation of steel sheet piles, installed by vibrating in to position, and excavation of the bunds by machine. |
2 weeks for each abutment |
Common construction technique |
|
|
Installation of precast concrete bankseats, brought to site by truck and lifted by machine. Backfilled with bund material and compacted by machine. |
1 week |
Common construction technique |
|
|
Fabrication of the timber deck off site, brought to site by truck and lifted into position by crane. |
1 week |
Common construction technique |
12 |
Shenzhen River Footbridge (Anticipated form of Construction) |
This is a cable stayed structure design and built by the Mainland Authorities, with bored pile foundations in the river bed. |
2 Years 9 months |
Common construction technique. See KaiTak footbridge |
12.1 |
Foundations |
Install a cofferdam in the river by sheet piles, working from a pontoon moored in the river. Dewater the cofferdam by pumping. |
3 months |
A combination of usual methods and practices. LMC Boundary crossing used same cofferdam |
Erect a platform on the cofferdam and place a bored pile rig on it. Moor a pontoon alongside as support |
1 month |
A combination of usual methods and practices |
||
Construct the piles in reinforced concrete brought to site by barge. |
2 months |
A combination of usual methods and practices |
||
12.2 |
Tower |
Construct the tower in reinforced concrete by self climbing formwork with materials brought in by barge, to tower top level. |
4 months |
A combination of usual methods and practices |
12.3 |
Deck erection |
Pre-fabricate the deck segments and bring to site by barge. Lift into place from a tower top anchorage using strand jacks. Secure in position. |
2 months |
Common construction technique |
Lift successive segments of the deck using strand jacks mounted on the deck already constructed, securing to the permanent tower top anchorage. |
2 weeks for a pair of segments |
Common construction technique |
||
12.4 |
Ship Impact Protection |
Install ship impact protection and remove the temporary cofferdam. |
3 months |
Common construction . See Ting Kau Bridge. |
13 |
Temporary Jetties in the Shenzhen
River |
Temporary piles with a steel deck. |
4 months |
See Shenzhen and Tuen Mun developments |
13.1 |
Foundations and deck |
Establish a mooring for a pontoon. Mount the piling rig on the pontoon and construct bored piles with permanent casing filled with reinforced concrete to river bed level. All materials will be brought to site by barge. Install the deck by welding supports to the pile top casing and attaching the decking by welding. |
4 months |
A combination of usual methods and practices |
13.2 |
Dismantling |
Remove the deck by flame cutting, lifting the detached parts onto a pontoon moored at the jetty. Cut of the steel casings at river bed level and remove by pontoon. |
1 month |
A combination of usual methods and practices |
14 |
Temporary access roads |
These will be aggregate laid on a geotextile if necessary |
|
|
14.1 |
Temporary access roads on cleared land |
The road will be 7m in width, comprising 500mm stone brought to site by truck, tipped and pushed into place by an excavator. A geotextile will be placed if ground conditions warrant this. |
100m/day |
Common construction technique |
|
|
To avoid impacting overland flow, the road will be either depressed into the ground, which will require the removal of existing soil, or placed on the existing ground and arrangements made to allow the overland flow to traverse the road. This could be pipes through, or a cut-off trench alongside the road. These measures are as stated in the DIA, and agreed by DSD. |
|
Common construction technique |
14.2 |
Access roads through ponds |
The pond will first be drained. A geogrid will be placed and stone brought by truck and placed to the required level. |
30m/day |
Common construction technique LMC Boundary crossing site |
|
|
On completion of the works, where there is no requirement for a permanent bund, the temporary bund will be removed. |
|
LMC Boundary Crossing sets precedent |
15 |
Contractors
Compounds |
Compounds are required at various locations. |
|
Common to all sites |
15.1 |
Formation |
The compounds will be graded to the required level, covered in a geotextile and stone placed to form a relatively flat competent surface. |
2 months |
Common construction technique |
15.2 |
Compound Facilities |
Temporary site offices for staff and containers for storage of materials will be erected. An electrical supply from either the network or a generator will be made, and a water supply will be laid. There will be latrine and washing facilities. |
|
Common construction technique |
Plant maintenance and repair facilities will be put in place. |
|
Common construction technique |
||
A precasting yard for smaller concrete items may be set up. |
|
Common construction technique |
13.6
Sundry structures and features for which piling, excavation or
concreting works will be required are necessary will be carried out according
to the principles of he major elements described above.
13.7
None of the technologies to be used in the construction of the Spur
Line are un proven. The three major elements of the works have directly
relevant comparable projects in Hong Kong, namely:
·
the DB 320 bored tunnel contract for West Rail, for which the equipment
and personnel will migrate to the Spur Line. Groundwater is not an issue for
the TBM in earth pressure balance
mode and fail safe measures in the form of an existing WSD inflatable dam are
available to guarantee that the agriculture and wetlands in Long Valley will
not be compromised;
·
the station platform will have to be constructed over very soft ground
at Lok Ma Chau. The Lok Ma Chau Boundary crossing platform and Boundary
Crossing Facilities constructed in 1988 – 1992 successfully used blanket
drainage, 2000km of vertical wick drains and reinforced earth technology and
embankment surcharging to prepare the platform;
·
the station and immigration facilities to be constructed on this
platform have numerous comparable examples constructed in Hong Kong over the
last 25 years; and
·
the KCRC West Rail project has constructed the entire length of viaduct
from Ho Pui to Tuen Mun, including a high level crossing of the Kam Tin
channel.
13.8
The programme, construction methods and technology to be used in the construction
of the Spur Line are all well proven in Hong Kong.