13.              CONSTRUCTION METHODS, PROGRAMME AND USAGE OF NEW TECHNOLOGIES

 

13.1          Section 3.1 (xv) of the Particular Scope of the EIA Brief requires an assessment of: the details of the construction programme, the construction methodologies and an assessment of the extent to which the technologies to be employed are proven technologies.

 

13.2          The permanent work to construct the Spur Line can be summarised as the construction of the following major elements:

 

(i)                  East Rail diversion,

(ii)                Diversion of the Dong Jiang watermains,

(iii)               The ramps down to the cut and cover sections of tunnel,

(iv)              The cut and cover sections of the tunnel,

(v)                The bored tunnel,

(vi)              The launching shaft, retrieval shafts, Kwu Tung station box, EAP structures, and ventilation buildings,

(vii)             The ramp up to the viaduct,

(viii)           The viaduct,

(ix)              Lok Ma Chau station vehicular access

(x)                Lok Ma Chau station,

(xi)              The enhancement of the fishponds at Lok Ma Chau,

(xii)             The construction of the footbridge crossing the Shenzhen River.

 

13.3          Associated with the permanent works are a number of significant temporary works:

 

(i)                  The jetties in the Shenzhen river for unloading materials,

(ii)                Access roads,

(iii)               Contractors compounds.

 

13.4          A summary project programme for the whole of the Spur Line is attached as Appendix A13.1

 

13.5          Each of the above major features are broken down into their constituent elements in the Table 13.1 below. The construction methods, programme durations, and commentary on the extent to which proven technology is adopted are shown. The programme durations shown below are for concurrent activities in many cases. The technologies to be used in construction have been discussed in detail in Section 2 - Description of the Works; and in other individual sections such as Chapter 3 – Hydrology, in respect of the usage of the Earth Pressure Balance technology in the tunnel boring work.

 


Table 13.1

Construction Methods, Programme and Degree to Which the Technology is Proven

 

Ref.

Feature/element

Method

Prog. Duration

Previous use

1a

Diversion of East Rail – temporary

Construct new formation for ballasted track.

 2.5 years

Pak Shek Kok realignment

1a.1

Removal of planters in San Wan Road

Tree transplanting, tree felling, excavation.

6 months

Commonplace

1a.2

Construction of a new 2.4m diameter sewer

Diversion and reconnection of existing drainage by cut and cover techniques.

6 months

Commonplace

Drive sheet piles and excavate by machine for the sewer and manholes.

6 months

Commonplace

Construction of new in-situ reinforced concrete catchpits.

3 weeks each in phase with the excavation

Commonplace

Lay granular bedding and precast pipes, backfill and compact.

3 months

Commonplace

1a.3

Prepare the trackbed formation

Breakout the road surface by machine. Excavate 600mm soil by machine and replace with granular fill, compacted. Lay track ballast to underside of sleeper, imported by road.

2 months

Commonplace techniques

1a.4

Installation of railway systems

Lay the sleepers – import by road and use mobile crane. Offload rails from a train and lift onto sleepers by mobile crane. Fill between sleepers with ballast, imported by road.

2 months

Commonplace methods

Erect over headline mast by excavating for the base by machine and casting concrete around the prefabricated steel mast.

3 days each.

Commonplace methods

Lay precast concrete troughs for control and communications signals by importing by road and laying by hand.

1 month

Commonplace methods

Construct protective barrier by excavating for the base by machine and casting concrete around the prefabricated steel sections.

2 months

Commonplace methods

1a.5

Construct impact protection to Po Shek Wu Road Bridge

Construct 900 mm diameter reinforced concrete bored piles by piling rig using fluid to maintain stability.

1 month

Commonplace methods

 

 

Excavate by machine using sheet piles to expose the pile heads. Construct in-situ reinforced concrete pilecap and upstand.

1 month

Commonplace methods

1b.

Final diversion of East Rail

Construct new formation for ballasted track and connect to existing operating East Rail without disruption to service.

1 year

Pak Shek Kok realignment with identical o’night placement and commissioning of turnouts.

1b.1

Formation works

Place granular fill to formation, imported by truck and spread and compacted.

2 months

Commonplace methods

Import ballast by truck and lay to underside of sleeper.

1 month

Commonplace methods

1b.2

Railway Systems Installation

Lay the sleepers – import by road and use mobile crane. Offload rails from a train and lift onto sleepers by mobile crane. Fill between sleepers with ballast, imported by road.

2 months

Commonplace methods

Erect over headline mast by excavating for the base by machine and casting concrete around the prefabricated steel mast.

3 days each.

Commonplace methods

Lay precast concrete troughs for control and communications signals by importing by road and laying by hand.

1 month

Commonplace methods

1b.3

Remove temporary track

Cut rails and load onto a train by mobile crane. Excavate ballast by machine and load onto trucks for disposal.

1 month

Commonplace methods

Construct road side gullies and connect to the storm drains. Install planter irrigation pipes.

1 month

Commonplace methods

Lay road pavement – import materials by truck and roll to compact.

2 weeks

Commonplace methods

Reconstruct planter in reinforced concrete, cast in-situ, with stone facing. Complete irrigation installation.

2 months

Commonplace methods

2

Diversion of the Dong Jiang watermains

Earthworks, foundations and new pipework to create a diversion of the mains.

18 months

Commonplace thrustblock and mainlaying methods

2.1

Earthworks

Excavate by machine. Load to trucks for disposal.

2 months

Commonplace methods

2.2

Construct thrust blocks

Bore minipiles and grout.

1 day for each pile, working progressively with the diversions

Commonplace methods

 

 

Excavate to expose the heads of the minipiles and cast reinforced concrete thrust block.

1 week for each phase, working progressively with the diversions

Fan Kam Rd diversion of 1.2m diam main.

2.3

Lay pipes

Install minipile foundations, and cast a pipe support around the head in reinforced concrete.

2 weeks for each support

Commonplace methods

Import new pipes by truck. String out on the new supports as far as possible using a mobile crane, and joint by welding.

1 month for each main

Commonplace methods

2.4

Tie-in to existing mains

Cut a section from the existing pipe and bring prefabricated joint section to site by truck. Weld joints.

1 month for each main

Commonplace methods

Remove existing mains by flame cutting or unbolting as appropriate, load to a truck by mobile crane and dispose off site.

1 week for each main

Commonplace methods

3

Ramps down to the cut and cover sections

Reinforced concrete structures.

6 months for each ramp

Commonplace methods

3.1

Ramp walls

Install contiguous bored piles, 1m diameter, in reinforced concrete, using fluid for excavation support.

4 months

Commonplace methods

3.2

Base slab

Excavate soil by machine and remove by truck. Cast the reinforced concrete base slab.

2 months

Commonplace methods

3.3

Adjacent drainage channels

Excavate by machine open cut for the channel and dispose material off site. Arrange so that temporary drainage is always available – see DIA for details agreed with DSD.

2 weeks

Commonplace methods

Cast channel walls and base in reinforced concrete.

3 months

Commonplace methods

Backfill and compact fill imported by truck.

2 weeks

Commonplace methods

4

Cut and cover sections of tunnel

Diaphragm wall with reinforced concrete slabs.

12 months

Commonplace methods

4.1

Diaphragm wall construction

Install reinforced concrete lead trench.

1 month

Standard for all diaphragm walling jobs

Set up plant for slurry stabilisation, including materials silos, settlement lagoons and pumps and pipes for circulation of slurry.

3 months

Ditto, but tunnel contractor will continue to use this plant for tunnelling. DB320 is most recent combined example.

 

Mobilise rigs and excavate 800mm thick wall. Dispose of material off site by truck. Excavate every fourth or fifth panel approximately 1.8m in length.

2 days for each panel

Standard procedures

Install reinforcement cage by crane and pour concrete into the panel.

2 days for each panel

Standard procedures

4.2

Roof and floor slab

Excavate between walls by machine and remove materials by truck.

3 months

Standard procedures

Cast the slabs in reinforced concrete.

3 months

Commonplace

Backfill on top of the roof slab with granular fill imported by truck, and compact.

1 month

Commonplace, eg all service reservoirs

4.3

Adjacent drainage channels

Excavate by machine open cut for the channel and dispose material off site. Arrange so that temporary drainage is always available – see DIA for details agreed with DSD.

2 weeks

Commonplace methods

Cast channel walls and base in reinforced concrete.

3 months

Commonplace methods

Backfill and compact fill imported by truck.

2 weeks

Commonplace methods

5.

The bored tunnel

Two no. bores by Earth Pressure Balance boring machine. All items are placed or removed from the launching shaft by a purpose installed gantry crane.

11 months for each bore + 3 months transit

KCRC Contrct DB320. Highly successful and no public complaint

5.1

Boring through soil

Using earth pressure balance mode, excavate soil under pressure in the head and remove from the bore. Allow to settle and treat supernatant to neutralise pH, remove oils and coagulate fines for complete removal of solids. Remove solids by truck for disposal.

300m/month

KCRC DB320 Contract. Very successful.

Import precast segments by truck and place in the bore immediately behind the face shield. Grout annulus with cementitious mix, batched and mixed within the tunnel from materials brought to site by truck.

300m/month

DB320 Contract

Standard tunneling procedures and completed tunnel is waterproof.

5a.2

Construct cross passages outside Long Valley

Establish rig on the ground and bore a 150mm diameter shaft to the cross passage level. Mix grout from materials brought to site by truck and inject into the ground on a grid basis, moving the rig for adequate coverage.

2 weeks/cross passage

Common construction technique

Excavate by hand or small machine from inside the tunnel. Place the lining by spraying concrete, by mixing the materials inside the tunnel, brought to site by truck.

3 weeks/cross passage

Common construction technique

5b.2

Construct cross passages under Long Valley

Drill horizontally from within the tunnel to introduce cold fluid to freeze the ground.

3 weeks/cross passage

Regular Construction technique adopted where conditions dictate

Excavate by hand or small machine from inside the tunnel. Place the lining by spraying concrete, by mixing the materials inside the tunnel, brought to site by truck.

3 weeks/cross passage

Common construction technique

5.3

Installation of the TBM

Face shield and the following train are brought to site on a series of trucks and lowered into the launching shaft for re-assembly.

3 months total

DB320 times two drives

5.4

Relocation of the TBM for the second bore

Face shield is lifted out in pieces from the retrieval shaft and transported back to the launching shaft on a series of trucks. The train goes back through the tunnel.

3 months

DB320 times two drives

5.5

Removal of the TBM

The face shield and supporting train are taken from the retrieval shaft in pieces and removed from the site on a series of trucks.

1 month

DB320 times two drives

5.6

Installation of railway systems

The track is LVT, which is a combination of reinforced concrete cast in-situ brought to the site by truck, and precast items. The rails are brought to site in long lengths by train, transported along the tunnel and welded in-situ.

8 months

DB320 and Airport Railway

Overhead line supports are brought to the site by truck and fixed in place in the tunnel.

4 months

All existing KCRC East Rail Tunnels and DB320

Cabling is laid out by large drums brought to the site by truck, running along the rails to install.

4 months

DB320

6.

The launching shafts, retrieval shafts, EAP shafts, Kwu Tung Station Box, and vent buildings

Diaphragm wall construction below ground, internal structure is reinforced concrete, above ground structures are reinforced concrete.

18months for each structure, but before tunnel boring is carried out at that location.

Common construction technique

6.1

Diaphragm wall construction

Install reinforced concrete lead trench.

1 month

Common construction technique

Set up plant for slurry stabilisation, including materials silos, settlement lagoons and pumps and pipes for circulation of slurry.

3 months

Common construction technique

Mobilise rigs and excavate 800mm thick wall. Dispose of material off site by truck. Excavate alternate panels approximately 1.8m in length.

2 days for each panel

Common construction technique

Install reinforcement cage by crane and pour concrete into the panel.

2 days for each panel

Common construction technique

6.2

Internal slabs, walls and superstructure

Cast in reinforced concrete brought to site by truck, materials placed by mobile crane and skip.

12 months for each structure

Common construction technique

7

Ramp up to the viaduct

A piled structure with a reinforced concrete superstructure.

6 months

Common construction technique

7.1

Bored Piles

Install prebored H piles, with material excavated using a down-the-hole hammer. Materials for grouting to be brought to site for batching and mixing on site.

4 days/pile

Common construction technique

7.2

Superstructure

Cast in reinforced concrete brought to site by truck, materials placed by mobile crane and skip.

3 months

Common construction technique

7.3

Parapet

Concrete precast off site, brought to site by truck, lifted and placed by mobile crane, fixed into place by casting a stitch of reinforced concrete.

3 days for each panel, 1 month total

Common construction technique

7.4

Adjacent drainage channels

Excavate by machine open cut for the channel and dispose material off site. Arrange so that temporary drainage is always available – see DIA for details agreed with DSD.

2 weeks

Commonplace methods

Cast channel walls and base in reinforced concrete.

3 months

Commonplace methods

Backfill and compact fill imported by truck.

2 weeks

Commonplace methods

7.5

Installation of railway systems

The track is LVT, which is a combination of reinforced concrete cast in-situ brought to the site by truck, and precast items. The rails are brought to site in long lengths by train, transported along the tunnel and welded in-situ.

2 months

Common construction technique

Overhead line supports are brought to the site by truck and fixed in place in the tunnel.

2 weeks

Common construction technique

Cabling is laid out by large drums brought to the site by truck, running along the rails to install.

Cables laid with the rest of the alignment.

Common construction technique

8

Viaduct

A simply supported twin-cell precast prestressed concrete deck erected on falsework, supported by reinforced concrete piers and bored piled foundations.

18 months

Common construction technique

 

Most of West Rail

8.1

Foundations

Install bored piles, 1.8m diameter, in reinforced concrete brought to site by truck and placed by crane and skip, using fluid for excavation support.

6 days for each pile

Common construction technique for last 30 years

Open cut excavation to expose the pileheads, cast the pilecap in reinforced concrete brought to site by truck and placed by crane and skip.

7 days; 1 month for each foundation

Common construction technique

8.2

Pier

A single stem in reinforced concrete brought to site by truck and placed by crane and skip, using purpose designed steel formwork.

20 days for three pours

Common construction technique

8.3

Deck

Erect purpose designed falsework on the pilecaps at the end of each span using a mobile crane. Transport the falsework by truck.

3 days

Common construction technique

Bring one cell precast concrete segments to site by truck and erect onto the falsework using a mobile crane. Stress together stage one.

1 day/span

Common construction technique

Lower onto temporary bearings and repeat for the second cells for the span.

1 day/span

Common construction technique

Cast the end diaphragms in reinforced concrete brought to site by truck, placed by crane and skip, and transfer load to the permanent bearings.

2 days/span

Common construction technique

Grout the ducts for the tensioning strands by lifting materials onto the deck by crane, mixing and pumping materials on the deck.

0.5 days/ span

Common construction technique

Place the parapets which are concrete precast off site, brought to site by truck, lifted and placed by mobile crane, fixed into place by casting a stitch of reinforced concrete.

3 days/span

Common construction technique

Carry out stage 2 of the prestressing.

0.5 day

Common construction technique

Remove the falsework using a crane, transport by truck and re-erect further on.

3 days

Common construction technique

8.4

Installation of railway systems

The track is LVT, which is a combination of reinforced concrete cast in-situ brought to the site by truck, and precast items. The rails are brought to site in long lengths by train, transported along the tunnel and welded in-situ.

2 months

Common construction technique

Overhead line supports are brought to the site by truck and fixed in place in the tunnel.

2 weeks

Common construction technique

Cabling is laid out by large drums brought to the site by truck, running along the rails to install.

Cables laid with the rest of the alignment.

Common construction technique

9

Lok Ma Chau Station Vehicular Access

Comprises a widening of the existing road and a realignment where it passes over the Spur Line.

3 years 4 months

Common construction technique

9.1

Formation works

Tree transplanting and felling.

6 months

Common construction technique

 

 

Excavation of soft materials near the ground surface by machine, disposed off site by truck.

8 months

Common construction technique

 

 

Deposition of granular materials brought to site by truck, and compacted by vibrating roller.

2 months

Common construction technique

 

 

Installation of precast kerbs, road gullies and drainpipes by excavator brought to ite by truck, backfilled by granular materials and compacted.

2 months

Common construction technique

 

 

Laying and rolling pavement materials brought to site by truck.

1 month

Common construction technique

10

Lok Ma Chau Station

Ground formation works by filling ponds, followed by piling and superstructure works.

3 years 9 months

Common construction techniques. See LMC Boundar Crossing

10.1

Formation works

The tops of the bunds forming the ponds in the station footprint are lowered by excavator, and the material placed in the area to be made a marshland. Geogrid and Wick drains, surcharge.

1 month

Common construction technique. See LMC Boundary Crossing

Diversion of an existing watercourse by placing fill by machine, compacting it and forming the channel in grasscrete (precast conrete). Construction of a weir in reinforced concrete and excavation by machine for additional pipes to upgrade the existing outfall.

3 months

Common construction technique. See LMC Boundary crossing

Sand fill is brought to the site by barge and placed in the ponds by a conveyor, displacing the remaining water in the ponds to neighbouring ponds.

6 months

Common construction technique. See Tin Shui Wai and River Trade Terminal

Excavate trenches by machine using trench sheets for support, and place drain pipes.

4 months

Common construction technique

10.2

Piling

Install bored piles, 2.1m diameter, in reinforced concrete brought to site by barge and placed by crane and skip, using fluid for excavation support.

6 days for each pile

Common construction technique. See NTCR and LMC Boundary crossing

Open cut excavation to expose the pileheads, cast the pilecap in reinforced concrete brought to site by barge and placed by crane and skip.

7 days; 6 months for foundation works

Common construction technique

10.3

Superstructure

Reinforced concrete brought to site by barge is placed using a crane and skip. Other materials such as cladding will be brought to site by barge and erected using a crane.

18 months

Common construction technique

10.4

Finishes and fit out

Materials will be brought to site by truck and lifted using crane.

18 months

Common construction technique

11

Enhancement of the fishponds at Lok Ma Chau

A water management system comprising an arterial pipe is to be installed, together with some modifications to the pond bunds to form the required habitat.

3 years

Common construction technique. Uses traditional labour, farming methods and equipment

11.1

Formation of the marsh

Reworking by machine of the bund material placed during station formation.

2 months

Common farming technique

11.2

Installation of the water control measures

Installation of steel sheet piles, installed by vibrating in to position, and excavation of the bunds by machine.

2 weeks for each location

Common construction technique

Bring to site by truck precast concrete catchpits, culverts, channels, lifted into position by small crane.

2 weeks for each location

Common construction technique

Laying of uPVC pipes into the ponds by hand.

1 week for each location

Common construction technique

Backfill around catchpits with bund material, compacting by machine, and withdrawal of sheetpiles by vibrator.

1 week for each location

Common construction technique

Excavation by machine of a shallow trench to install uPVC pipes forming the arterial system, backfilling with bund material.

1 month in each half

Common construction technique

11.3

Modifications to the bunds

Use of an excavator to lower the bunds, spreading to one side as required.

3 days for each location

Common farming and construction technique

Import of 10mm aggregate by truck, placed by machine on a geotextile.

1 day for 100m

Common construction technique

11.4

Construction of the pipe bridge

Installation of gabions in the pond, with materials brought to site by truck and placed by machine.

1 week

Common construction technique

 

 

Installation of timber piles brought to site by truck, by vibrating in to position by machine.

1 week

Common construction technique

 

 

Installation of timber walings, and backfill by grade 200 fill brought to site by truck and placed by machine.

1 week

Common construction technique

 

 

Installation of steel sheet piles, installed by vibrating in to position, and excavation of the bunds by machine.

2 weeks for each abutment

Common construction technique

 

 

Installation of precast concrete bankseats, brought to site by truck and lifted by machine. Backfilled with bund material and compacted by machine.

1 week

Common construction technique

 

 

Fabrication of the timber deck off site, brought to site by truck and lifted into position by crane.

1 week

Common construction technique

12

Shenzhen River Footbridge

(Anticipated form of Construction)

This is a cable stayed structure design and built by the Mainland Authorities, with bored pile foundations in the river bed.

2 Years 9 months

Common construction technique. See KaiTak footbridge

12.1

Foundations

Install a cofferdam in the river by sheet piles, working from a pontoon moored in the river. Dewater the cofferdam by pumping.

3 months

A combination of usual methods and practices. LMC Boundary crossing used same cofferdam

Erect a platform on the cofferdam and place a bored pile rig on it. Moor a pontoon alongside as support

1 month

A combination of usual methods and practices

Construct the piles in reinforced concrete brought to site by barge.

2 months

A combination of usual methods and practices

12.2

Tower

Construct the tower in reinforced concrete by self climbing formwork with materials brought in by barge, to tower top level.

4 months

A combination of usual methods and practices

12.3

Deck erection

Pre-fabricate the deck segments and bring to site by barge. Lift into place from a tower top anchorage using strand jacks. Secure in position.

2 months

Common construction technique

Lift successive segments of the deck using strand jacks mounted on the deck already constructed, securing to the permanent tower top anchorage.

2 weeks for a pair of segments

Common construction technique

12.4

Ship Impact Protection

Install ship impact protection and remove the temporary cofferdam.

3 months

Common construction . See Ting Kau Bridge.

13

Temporary Jetties in the Shenzhen River

Temporary piles with a steel deck.

4 months

See Shenzhen and Tuen Mun developments

13.1

Foundations and deck

Establish a mooring for a pontoon. Mount the piling rig on the pontoon and construct bored piles with permanent casing filled with reinforced concrete to river bed level. All materials will be brought to site by barge. Install the deck by welding supports to the pile top casing and attaching the decking by welding.

4 months

A combination of usual methods and practices

13.2

Dismantling

Remove the deck by flame cutting, lifting the detached parts onto a pontoon moored at the jetty. Cut of the steel casings at river bed level and remove by pontoon.

1 month

A combination of usual methods and practices

14

Temporary access roads

These will be aggregate laid on a geotextile if necessary

 

 

14.1

Temporary access roads on cleared land

The road will be 7m in width, comprising 500mm stone brought to site by truck, tipped and pushed into place by an excavator. A geotextile will be placed if ground conditions warrant this.

100m/day

Common construction technique

 

 

To avoid impacting overland flow, the road will be either depressed into the ground, which will require the removal of existing soil, or placed on the existing ground and arrangements made to allow the overland flow to traverse the road. This could be pipes through, or a cut-off trench alongside the road. These measures are as stated in the DIA, and agreed by DSD.

 

Common construction technique

14.2

Access roads through ponds

The pond will first be drained. A geogrid will be placed and stone brought by truck and placed to the required level.

30m/day

Common construction technique LMC Boundary crossing site

 

 

On completion of the works, where there is no requirement for a permanent bund, the temporary bund will be removed.

 

LMC Boundary Crossing sets precedent

15

Contractors Compounds

Compounds are required at various locations.

 

Common to all sites

15.1

Formation

The compounds will be graded to the required level, covered in a geotextile and stone placed to form a relatively flat competent surface.

2 months

Common construction technique

15.2

Compound Facilities

Temporary site offices for staff and containers for storage of materials will be erected. An electrical supply from either the network or a generator will be made, and a water supply will be laid. There will be latrine and washing facilities.

 

Common construction technique

Plant maintenance and repair facilities will be put in place.

 

Common construction technique

A precasting yard for smaller concrete items may be set up.

 

Common construction technique

 

 

13.6          Sundry structures and features for which piling, excavation or concreting works will be required are necessary will be carried out according to the principles of he major elements described above.

 

13.7          None of the technologies to be used in the construction of the Spur Line are un proven. The three major elements of the works have directly relevant comparable projects in Hong Kong, namely:

 

·                     the DB 320 bored tunnel contract for West Rail, for which the equipment and personnel will migrate to the Spur Line. Groundwater is not an issue for the TBM in earth pressure balance mode and fail safe measures in the form of an existing WSD inflatable dam are available to guarantee that the agriculture and wetlands in Long Valley will not be compromised;

 

·                     the station platform will have to be constructed over very soft ground at Lok Ma Chau. The Lok Ma Chau Boundary crossing platform and Boundary Crossing Facilities constructed in 1988 – 1992 successfully used blanket drainage, 2000km of vertical wick drains and reinforced earth technology and embankment surcharging to prepare the platform;

 

·                     the station and immigration facilities to be constructed on this platform have numerous comparable examples constructed in Hong Kong over the last 25 years; and

·                     the KCRC West Rail project has constructed the entire length of viaduct from Ho Pui to Tuen Mun, including a high level crossing of the Kam Tin channel.

 

13.8          The programme, construction methods and technology to be used in the construction of the Spur Line are all well proven in Hong Kong.

Back to Content