Table 15.6
IMPLEMENTATION
SCHEDULE (See Notes at End of Table for Codes)
EIA Ref. |
Environment Protection Measures |
Location/Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
|
|||||
|
|
|
|
|
|
|
|
|
Section 3 |
Hydrology |
|
|
|
|
|
|
|
|
Prior
to be start of construction, a suite of piezometers should be installed at locations
specified in the EIA. Baseline measurements of groundwater shall be made in
the year preceeding tunnel construction. Wet/Dry season, Spring/Neap tides. |
Specified locations/C |
DDE/KCRC |
3 |
3 |
|
BOO Std groundwater Issues |
|
|
Construction |
|
|
|
|
|
|
|
|
Monitoring
of ground water levels and surface settlement at defined locations and
frequencies as specified in the EIA report. |
Specified locations/C |
CC |
|
3 |
|
BOO Std groundwater Issues |
|
|
The
contractor shall make appropriate remediation for recovery of settlement of
bunds along the mid-Long Valley watercourse, in consultation with farmers
using the irrigation flows. |
Specified locations/C |
CC |
|
3 |
|
|
|
|
Negotiation
with WSD and AFCD to establish management protocols for any necessary
operation of sluices and inflatable dams within the main Channels and the
Long Valley watercourses to facilitate a timely response to unacceptable
changes in LV groundwater levels. |
Long Valley/C |
KCRC/CC |
|
3 |
|
|
|
|
Incorporation
of compensatory cross-over drainage shall be installed in the lean-mix plug
to promote drainage subsurface flow in floor of River Sutlej channel. |
River Sutlej/Des & C |
DDE/CC |
3 |
3 |
|
|
|
|
Operation |
|
|
|
|
|
|
|
|
Measurements
shall be continued in Long Valley piezometers after tunnel construction is
complete, at a frequency specified in the EIA report. The pre-existing
hydrological envelope of wet/dry season, spring and neap tide shall be
re-confirmed. |
Long Valley/O |
KCRC/DDE |
|
3 |
3 |
|
|
Section 4 |
Ecology Construction mitigation measures Wetland habitats should be
designed to achieve the specified compensation objectives for habitats and
species. The design of the wetlands should conform with the description in
the EIA report. An overall area of 27.1 ha fishponds will be enhanced for wildlife as compensation for ecological impacts due to Spur Line. A further 9.9 ha will be used to create marsh and reedbed. A further 1 ha will be planted with bamboo to reduce visual impacts from the station building. An area of fishponds west of the Lok Ma Chau station, as specified in the EIA report, will be established before construction starts through water level management and fish stocking. During construction additional ponds within the ecological compensation area will be used as a water resource and for fish stocking. Reprofiling of pond levels will create shallow feeding habitats as required for target species. Modification of ponds and reprofiling of bunds should be carried out in accordance with the EIA requirements. |
Specified locations Specified locations/Des & C Lok Ma Chau/ Des, C & O |
DDE/CC DDE/CC/ KCRC DDE/CC/ KCRC |
3 3 3 |
3 3 3 |
3 |
-- |
|
|
Design must ensure that suitable hydrological
conditions for target wetland habitats are provided in the long-term and that
appropriate plant species and establishment methods are used to enhance /
create target vegetation communities. |
Lok Ma Chau/Des, C & O |
DDE/CC/ KCRC |
3 |
3 |
|
-- |
|
Section 4 |
The Habitat Creation and Management Plan (HCMP) should be prepared before the operation of the fishponds begins. Regular review of the HCMP is required during operation of the wetland enhancement area. Areas of reed bed and marshland habitat will
be created alongside the LMC station buildings for both ecological and water
cleanup proposes. They will be shallow sloping basins to produced zoned
wetland habitat. Construction works will be minimal and consist
of reprofiling adjacent fishpond bunds. The reedbed should be established before
construction of the sewage treatment plant is complete. |
Lok Ma Chau/Des, C & O Lok Ma Chau/ Des, C and O Lok Ma Chau/ Construction stage |
KCRC DDE/CC/ KCRC |
3 3 |
3 3 3 |
3 3 |
|
|
|
The design of Lok Ma Chau Station should
minimise areas of reflective materials (including glass) on outer surfaces of
the station and footbridge. |
LMC station & footbridge Des&C |
DDE/CC |
3 |
3 |
|
|
|
|
Contractor access should be limited to the
area required for working along the whole alignment and particularly at Lok
Ma Chau and San Tin where work is required in fishponds. Impacted ponds that
will not be used for mitigation or structures shall be reinstated after
construction is completed. |
|
|
|
|
|
|
|
|
The designated noise reduction system shall be
appropriately incorporated throughout the alignment |
Whole alignment/Des & C |
DDE/CC |
3 |
3 |
3 |
|
|
Section 4 |
Operation
mitigation measures Maintenance of the ecological compensation
areas should be carried out according to the Habitat Creation and Management
Plans for the Lok Ma Chau Station mitigation area. |
Lok Ma Chau/O |
KCRC |
|
|
3 |
-- |
|
|
Monitoring The detailed
design of the wetland mitigation area should be checked and the establishment
of the wetland area monitored by qualified ecologists and landscaping
professionals. |
Lok Ma Chau compensation area/Des, C & O |
KCRC |
3 |
3 |
3 |
-- |
|
Section
5 |
Fisheries Reinstatement of temporarily impacted
fishponds below the viaduct, after construction is completed. |
Lok Ma Chau |
CC |
3 |
3 |
|
-- |
|
Section
6 |
Air Quality Dust Mitigation Measures The following dust control measures as part of good construction site practice should be incorporated in the Contract Specification and implemented to minimize dust nuisance arising from the works to within acceptable levels: |
|
|
|
|
|
|
|
|
(i)
The Contractor shall
undertake at all times to prevent dust nuisance as a result of his
activities. Effective dust suppression measures, as necessary, should be
installed to minimize air quality impacts, at the boundary of the site and at
any sensitive receivers. |
Whole
construction site/whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
(ii)
The
Contractor shall frequently clean and water the site to minimize fugitive
dust emissions. |
Whole
construction site/whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
Section
6 |
(iii)
Effective
water sprays shall be used during the delivery and handling of all raw sand,
aggregate and other similar materials, when dust is likely to be created, to
dampen all stored materials during dry and windy weather. |
Whole
construction site/whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
(iv)
Watering
of exposed surfaces shall be conducted as often as possible depending on the
circumstances. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
(v)
Areas
within the site where there is a regular movement of vehicles shall have an
approved hard surface, be kept clear of loose surface materials and / or
regularly watered. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
(vi)
Where
dusty materials are being discharged to vehicle from a conveying system at
fixed transfer point, a three-sided roofed enclosure with a flexible curtain
across the entry shall be provided. Exhaust fans shall be provided for this
enclosure and vented to a suitable fabric filter system. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
(vii)
The
Contractor shall confine haulage and delivery vehicles to designated roadways
inside the site. If in the opinion of the Engineer, any motorised vehicle is
causing dust nuisance, the Engineer may require that the vehicle be
restricted to a maximum speed of 15 km per hour while within the site area. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
Section
6 |
(viii)
Wheel
cleaning facilities shall be installed and used by all vehicles leaving the
site. No earth, mud, debris, dust and the like shall be deposited on public
roads. Water in the wheel cleaning facility shall be changed at frequent
intervals and sediments shall be removed regularly. The Contractor shall
submit details of proposals for the wheel cleaning facilities to the Engineer
prior to construction of the facility. Such wheel cleaning facilities shall
be usable prior to any earthwork excavation activity on site. The Contractor
shall provide a hard-surfaced road between any cleaning facility and the
public road. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
(ix)
Stockpiles
of sand and aggregate greater than 20 m3 shall be enclosed on
three sides, with walls extending above the pile and 2 m beyond the front of
the pile. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
(x)
Chemical
wetting agents shall only be used on completed cuts and fills to reduce wind
erosion. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
(xi)
All
site vehicular exhausts should be directed vertically upwards or directed
away from ground to minimize dust nuisance. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
Section
6 |
(xii)
Ventilation
system, equipped with proprietary filters, should be provided to ensure the
safe working environment inside the tunnel. Particular attention should be
paid to the location and direction of the ventilation exhausts. The exhausts
should not be allowed to face any sensitive receivers directly. Consideration
should also be given to the location of windows, doors and direction of
prevailing winds in relation to the nearby sensitive receivers. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
In addition, based on the Air Pollution
Control (Construction Dust) Regulation, any works involved regulatory work,
such as stockpiling, loading and unloading of dusty materials, shall take
precautions to suppress dust nuisance. Examples of dust suppression methods
are: |
|
|
|
|
|
|
|
|
• The working area of any
excavation or earthmoving operation shall spray with water or a dust
suppression chemical immediately before, during and immediately after the
operation so as to maintain the entire surface wet; |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
• Exposed earth shall be properly treated by
compaction, turfing, hydroseeding, vegetation planting or sealing with latex,
vinyl, bitumen or other suitable surface stabiliser within six months after
the last construction activity on the construction site or part of the
construction site where the exposed earth lies; and |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
•
Any stockpile of dusty materials shall be either covered entirely by
impervious sheeting or placed in an area sheltered on the top and three
sides; and sprayed with water or a dust suppression chemical so as to
maintain the entire surface wet. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
Section
6 |
• Regular watering of haul roads to
maintain surface wet. In order to meet this requirement, watering should be
carried out at least twice a day and a water refilling system should be
installed so that the water refilling time should be less than ten minutes. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
• All stockpile of excavated material
shall be either covered entirely by impervious sheeting or sprayed with water
so as to maintain it in a damp condition. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
• Any conveyor system used for transfer
of dusty materials should be fitted with wind boards on all sides, enclosures
at conveyor transfer points and hopper discharge areas, three sided roofed
enclosure with flexible curtain across the entry, conveyor belt cleaners and
exhaust fans with suitable fabric cleaner. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
• Where a site boundary adjoins a road,
street service lane or other area accessible to the public, hoarding of not
less than 2.4 m above ground level shall be provided along the entire
length of that portion of the site boundary except for any site entrances or
exits. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
• Sites used for the storage of cement
or dry pulverised fuel ash shall not be overfilled. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
|
According
to the Air Pollution Control (Specified
Processes) Regulations, concrete plants with a site capacity greater than
50 tonnes will be considered as a specified process and require a licence to
be operated. Under this regulation, an Air Pollution Control Plan for the
batching plant will be prepared in an effort to control the fugitive dust.
Thus, operation of plant must comply with the strict dust controls so as to
reduce the potential dust impact on the nearby sensitive receivers. |
Whole construction site / whole construction period |
CC |
|
3 |
|
Air Pollution Control Ordinance (APCO) |
|
Section
6 |
EM
& A Requirements The assessment of air quality impacts has
concluded that it is unlikely that there will be any significant impacts
along the Spur Line alignment during both construction and operation phases.
Routine environmental monitoring of air quality during construction is
considered unnecessary. However, the specified mitigation measures should be
written into contract documents. |
whole alignment/all times |
CC |
|
3 |
|
-- |
|
|
Routine audit of the implementation status of
specified mitigation measures during the construction and operation phases
should be undertaken by the project proponent or his representative. Such
audits should be well documented and include action procedures in the case of
non-compliance. |
whole alignment/all times |
CC |
|
3 |
|
-- |
|
Section 7 |
Noise Construction mitigation
measures |
|
|
|
|
|
|
|
|
The Contractor shall comply with the Noise Control Ordinance (Cap 400) and
with any regulations made under the Ordinance, including restrictions placed
on noise from construction work and the requirements to seek Construction Noise
Permits. Before commencing work which requires Construction Noise Permits,
the Contractor should obtain such permits and display these appropriately. |
whole alignment/all times |
CC |
|
3 |
|
NCO (Cap 400) |
|
|
The Contractor shall devise, arrange methods
of working and carry out the works in such a manner as to minimise noise
impacts on the surrounding environment, and shall provide experienced
personnel with suitable training to ensure that these methods are
implemented. |
whole alignment/all times |
CC |
|
3 |
|
-- |
|
Section 7 |
In general, the Contractor is required to
minimize or avoid potential construction noise impact by imposing a
combination of the following mitigation measures: |
whole alignment/all times |
CC |
|
3 |
|
|
|
|
Noisy equipment and activities should be
sited by the Contractor as far from close-proximity sensitive receivers as
practical. Prolonged operation of noisy equipment close to dwellings should
be avoided. |
whole alignment/all times |
CC |
|
3 |
|
|
|
|
The Contractor should minimise construction noise exposure
to the schools (especially during examination periods) as much as possible.
The Contractor should liaise with the school and the Examination Authority to
ascertain the exact dates and times of all examination periods during the
course of the contract and to avoid noisy activities during these periods. |
whole alignment/all times |
CC |
|
3 |
|
- |
|
|
Noisy plant or processes should be
replaced by quieter alternatives where possible. Silenced diesel and gasoline
generators and power units, as well as silenced and super-silenced air
compressors, can be readily obtained. |
whole alignment/all times |
CC |
|
3 |
|
- |
|
|
Noisy activities should
be scheduled to minimise exposure of nearby sensitive receivers to high
levels of construction noise. For example, noisy activities can be scheduled
for midday, or at times coinciding with periods of high background noise
(such as during peak traffic hours). |
whole alignment/all times |
CC |
|
3 |
|
- |
|
|
Idle equipment should be
turned off or throttled down. Noisy equipment should be properly maintained
and used no more often than is necessary. |
whole alignment/all times |
CC |
|
3 |
|
- |
|
Section 7 |
The power units of
non-electric stationary plant and earth-moving plant should be quietened by
vibration isolation and partial or full acoustic enclosures for individual
noise-generating components. |
whole alignment/all times |
CC |
|
3 |
|
- |
|
|
Construction activities should be planned so that parallel operation
of several sets of equipment close to a given receiver is avoided, thus
reducing the cumulative impacts between operations. The numbers of operating
items of powered mechanical equipment should be minimised. Noise can be
reduced by increasing the distance between the operating equipment and the
NSRs or by reducing the number of items of equipment and/or construction
activity in the area at any one time. Quiet and/or
silenced models PME should be employed as far as practicable. |
whole alignment/c Whole alignment/all times |
CC CC |
|
3 3 |
|
- |
|
|
For site specific
construction noise measures, refer to Section 7.2. |
|
CC |
|
3 |
|
TMEIAO/NCO |
|
|
Operational
Noise The contractor shall ensure that the measures
proposed shall meet the required standard defined in the Noise Control Ordinance at all locations along the Alignment. |
whole alignment/all times |
CC |
|
3 |
|
|
|
|
Viaduct Structure The Sound Reduction Plenum System will be used
on all elevated sections of the alignment on viaduct |
All elevated sections of alignment on viaduct |
DDE/CC |
3 |
3 |
|
NCO and EIAOTM |
|
Section 7 |
Ventilation Buildings Refer to Section 7.3 for design noise limits
for ventilation buildings |
|
DDE/CC |
3 |
3 |
|
NCO |
|
|
Track Form Design Floating mini-slab track (FST) at a resonant frequency of 16 Hz and low stiffness shear type baseplates of 13 kN/mm shall be used in the track form design throughout the section of the railway within Kwu Tung North NDA. Low Vibration Track (LVT) will be used through the tunnel and viaduct sections of the alignment except for within Kwu Tung North NDA. Noise Barriers. |
Kwu Tung North NDA/operational stage North of Sheung Shui Station |
DDE/CC DDE/CC |
3 3 |
3 3 |
|
NCO and EIAOTM NCO and EIAOTM |
|
|
Air-conditioning Limits The noise specification of
air-conditioning units mounted on the roof of new skirted trains shall not
exceed a noise level of 57 dB(A) at a distance of 15 m from the
train. |
All trains/whole operational
stage |
DDE/CC |
3 |
3 |
|
NCO and EIAOTM |
|
Section 7 |
Monitoring The assessment of noise impacts
has concluded that if the recommended mitigation measures are incorporated
into the design, it is unlikely that there will be any prolonged impacts at
any of the sites during construction phase. Routine environmental monitoring
of noise during construction will be carried out at RNSRs specified in Chapter
15 of the EIA report. Additional and hoc monitoring should be carried out if
complaints arise. Specified mitigation measures should be written into
contract documents. |
RNSRs as listed in EIA report |
CC |
|
3 |
|
-- |
|
|
Routine audit of the implementation
status of specified mitigation measures during the construction and operation
phases should be undertaken by the project proponent or his representative.
Such audits should be well documented and include action procedures in the
case of non-compliance. |
whole alignment/all times |
CC |
|
3 |
|
-- |
|
Section 8 |
Water Construction
mitigation measures With reference to Section 8 of the EIA report,
the Contractor shall provide mitigation measures to meet environmental
protection requirements as described below. |
|
|
3 |
3 |
|
|
|
Section 8 |
(a)
At the start of site establishment perimeter
cut-off drains shall be constructed to direct off-site water around the site,
and internal drainage works and erosion and sedimentation control facilities
shall be implemented. Channels, earth bunds or sand bag barriers shall be
provided on site to direct storm water to silt removal facilities. The design
of efficient silt removal facilities should be based on the guidelines in
Appendix A1 of ProPECC PN 1/94. All the surface runoff or extracted ground
water contaminated by silt and suspended solids should be collected by the
on-site drainage system and diverted through the silt traps prior to
discharge. |
Whole alignment / C |
CC |
|
3 |
|
ProPECC PN 1/94 WPCO |
|
|
(b)
The overall slope of the site shall be kept to
a minimum to reduce the erosive potential of surface water flows , and all
trafficked areas and access roads shall be protected by coarse stone ballast. |
Whole alignment / C |
CC |
|
3 |
|
WPCO |
|
|
(c)
The Contractor shall ensure that works take place
in the dry season as far as practicable or else additional temporary works
such as cofferdam or temporary earth bund will be required to minimise runoff
and pollution from the works entering the water column. Water collecting
behind the cofferdam shall be either pumped onto the land-bank or collected,
settled and pH adjusted to 6.0 to 8.5 before being allowed to enter the
channels. Concrete works on the footbridge across Shenzhen River should
implement appropriate drainage to prevent concrete washings entering the
environment. |
Whole alignment/C |
CC |
|
3 |
|
ProPECC PN 1/94 |
|
Section 8 |
(d)
Works in River Sutlej and for diversion of
Chau Tau Channel should be carried out in the dry season and provision made
for diversion of the low flow channel to avoid impacts on water quality from
the works. |
River Sutlej and Chau Tau/C |
|
|
3 |
|
|
|
|
(e)
Moist spoil from the tunnel boring operation
shall be transported to the launching shaft on a conveyer belt, covered if
necessary to reduce runoff during the wet season, and the spoil shall be
settled on-site to reduce spoil moisture before disposal. The remaining water
will be treated to removal solids and other pollutants to ensure compliance
with WPCO before discharge. A licence shall be obtained from EPD (LCO) before
the start of any works involving discharges. |
Launching shaft/C |
CC |
|
3 |
|
|
|
|
(f)
Wheel washing facilities and sediment traps
shall be provided at each site exit. |
All site/C |
CC |
|
3 |
|
|
|
|
(g)
Open stockpiles of construction materials
(e.g. aggregates, sand and fill material) on site shall be protected from
erosion during rainstorms. Measures shall be taken to prevent the washing
away of construction materials, soil, silt or debris into any drainage
system. Hydroseeding should be used where practical. |
Whole alignment/C |
CC |
|
3 |
|
ProPECC PN 1/94 |
|
Section 8 |
(h)
All vehicles and plant shall be cleaned before
leaving the construction site to ensure no earth, mud or debris is deposited
by them on roads. A wheel washing bay shall be provided at every site exit.
The wheel washing bay shall be designed and sited to accommodate the
predicted through put of vehicles and shall have an associated sedimentation
facility that is capable of removing the sand and silt from the wash-water.
The settled out sand and silt shall be removed at least on a weekly basis to ensure
the continued efficiency of the process. The section of access road leading
to, and exiting from, the wheel-wash bay to the public road shall be paved
with sufficient backfill toward the wheel-wash bay to prevent vehicle
tracking soil and silty water to public roads and drains. |
Whole alignment/all times |
CC |
|
3 |
|
WPCO |
|
|
(i)
The transport of sediment to the environment
shall be minimised by the installation of appropriate sediment traps within
the drainage system. Sediment traps shall be designed with adequate capacity,
and shall be regularly maintained. |
whole alignment/all times |
CC |
|
3 |
|
ProPECC PN 1/94 |
|
|
(j)
Wastewater generated from the washing down of
mixer trucks and drum mixers and similar equipment should be recycled. The
discharge of wastewater should be kept to a minimum. |
whole alignment/all times |
CC |
|
3 |
|
-- |
|
|
(k)
Wastewater generated from construction
activities should be discharged into an excavated sedimentation pit prior to
discharge wherever possible. The pit should be unlined to allow for
infiltration of water into the ground if ground conditions allow. Settlement
of concrete washings in a sedimentation pit should allow for setting of
concrete before disposal. |
whole alignment/all times |
CC |
|
3 |
|
-- |
|
Section 8 |
(l)
In the case of an unlined pit for all types of
wastewater being settled out, water infiltration into the ground requires a
license from EPD under the WPCO regulations. Where a license cannot be
obtained, or if water re-use is practised, the pit may need to be lined,
which requires more frequent removal of the contents. |
whole alignment/all times |
CC |
|
3 |
|
WPCO |
|
|
(m)
Measures shall be taken to minimise the
ingress of site drainage into excavations. If the excavation of trenches in
wet periods is necessary, they shall be dug and backfilled in short sections wherever
practicable. Water pumped out from trenches or foundation excavations should
be discharged into storm drains via silt removal facilities. |
whole alignment / all times |
CC |
|
3 |
|
WPCO |
|
|
(n)
Oil interceptors shall be provided in Site
compounds and regularly emptied to prevent release of oils and grease into
the surface water drainage system after accidental spillages. The interceptor
shall have a bypass to prevent flushing during periods of heavy rain. Oil and
fuel bunkers shall be bunded to prevent discharge due to accidental spillages
or breaching of tanks. |
Whole alignment/all times |
CC |
|
3 |
|
ProPECC PN 1/94 |
|
Section 8 |
(o)
Any waters entering storm drains must have a
pH of between 6.0 and 8.5. Under normal circumstances, surplus wastewater may
be discharged into foul sewers after treatment in silt removal and pH
adjustment facilities (to within the pH range of 6 to 9). Disposal of
wastewater into storm drains will require more elaborate treatment. Surface
run-off should be segregated from the morter plant within the launching area
and diverted to the storm water drainage system. Surface run-off contaminated
by materials in a mortar plant or casting yard, if used, should be adequately
treated before disposal into storm water drains. |
Whole alignment/all times |
CC |
|
3 |
|
ProPECC PN 1/94 |
|
|
(p)
Runoff should be prevented from entering
adjacent ponds through construction of bunds between works areas and ponds. |
Whole alignment/all times |
CC |
|
3 |
|
-- |
|
|
(q)
The Contractor shall take all reasonable
measures to minimise adverse impacts resulting from construction activities
associated with the removal of sediments. These measures shall include
ensuring that all plant and equipment and working methods meet the following
criteria. • utilising
appropriate suspended solids containment screen while removing sediment; • minimise
disturbance of the channel base/pond bed while draining water and removing
sediment. |
Whole alignment/all times |
CC |
|
3 |
|
- |
|
Section 8 |
• minimise
leakage of excavated sediment during lifting; • prevent
the overflowing of any container used to contain removed sediments. |
|
|
|
|
|
|
|
|
• in
small scale works a barrier of sand bags should enclose the area; |
|
|
|
|
|
|
|
|
• sediment
removal should be undertaken during the dry season whenever possible; |
|
|
|
|
|
|
|
|
• sediments
should be removed from site immediately or stored away from the water course. |
|
|
|
|
|
|
|
|
During filling of ponds for Lok Ma Chau
Station formation, displaced water should be directed through selected bunds
to settle in defined fishponds within the contracts works area. The settled
water shall only been discharged when it meets discharge standards. |
Lok Ma Chau fishponds/all times |
CC |
|
3 |
|
|
|
|
(r)
The Contractor shall be responsible for
disposing of all dredged sediments at an appropriate location depending on
the volume and composition of the material. |
whole alignment/all times |
CC |
|
3 |
|
-- |
|
|
(s)
If any office, works area canteen or toilet
facilities are erected, foul water effluent should be directed to a foul
sewer or to a sewage treatment facility either directly or indirectly by
means of pumping or other means approved by the Engineer. |
whole alignment/all times |
CC |
|
3 |
|
ProPECC PN 1/94 |
|
Section 8 |
(t)
Temporary on-site storage of excavated
materials from station and depot construction works shall be covered with
tarpaulin or similar fabric during rainstorms. Any washout of construction or
excavated materials should be diverted to the drainage system via sediment
traps. Stockpiling of the excavated material can be minimised by scheduling
the construction programme in a way that one section of the alignment can be
constructed and completed before the excavation works of the next. |
whole alignment / all times |
CC |
|
3 |
|
ProPECC PN 1/94 |
|
|
(u)
A cofferdam should be constructed during
footbridge construction at Shenzhen River. |
Shenzhen River/ during bridge construction. |
|
|
|
|
|
|
|
(v)
Regular maintenance of all drainage systems is
necessary. |
All drainage systems/all times |
|
|
|
|
|
|
|
(w)
Chemical wastes should be
collected, stored and disposed of in accordance with the Code of Practice on the Packing, Labelling and Storage of Chemical
Waste. |
Whole alignment/all times |
CC |
|
3 |
|
WDO (Cap 354) |
|
|
(x)
If contaminated material is excavated it shall
be treated and/or disposal of to WENT landfill. If excavated material is
heavily contaminated it may require disposal to SENT landfill. |
Excavation areas/all times |
CC |
|
3 |
|
|
|
|
(y)
Transfer of material onto barges should be
carried out slowly to prevent contamination. |
sand fill location/all times |
CC |
|
3 |
|
|
|
|
(z)
Transfer of materials onto the platform should
be carried out slowly to avoid sand falling off the conveyor. |
Platforms/all times |
CC |
|
3 |
|
|
|
Section 8 |
Operational
mitigation measures The following measures should be adopted for
the operation of the Spur Line alignment: |
whole alignment Des, C & O stages |
DDE/CC |
3 |
3 |
3 |
|
|
|
A surface water drainage system shall be
provided to collect track runoff. Where oils and lubricating fluids could be
spilt, the track drainage channels discharge shall pass through oil
interceptors and sediment traps to remove oil, grease and sediment before
being diverted to the public storm water system or watercourse. |
whole alignment
Des, C & O stages |
DDE/CC |
3 |
3 |
3 |
|
|
|
Silt traps, sediment basins and oil
interceptors shall be designed to appropriate design standards, and whilst in
use, regularly cleaned and maintained in good working order. The efficiency
of these installations is dependent on regular cleaning and maintenance. |
whole alignment
Des, C & O stages |
DDE/CC |
3 |
3 |
3 |
ProPECC PN 5/93 |
|
|
On-site drainage shall focus on areas where
contaminated effluent may be generated and provide a clear segregation of
clean and contaminated effluents. |
whole alignment
Des, C & O stages |
DDE/CC |
3 |
3 |
3 |
ProPECC PN 5/93 |
|
|
Oily contents of oil interceptors shall be
collected for recycling, or transferred to an appropriate disposal facility |
whole alignment
Des, C & O stages |
DDE/KCRC |
3 |
3 |
3 |
|
|
|
The design of the footbridge should minimise
disturbance of the sediment through careful design of the size and shape of
pier supports. |
footbridge at LMC station/Des |
DDE (for footbridge) |
3 |
3 |
3 |
|
|
Section 8 |
Sewage Effluent from Station Works Force Water quality impacts caused by sewage
effluent generated by the work force at the station should be effectively
controlled through on-site waste water treatment facilities prior to
discharge to the reedbed system located to the east of Lok Ma Chau Station.
The reedbed system requires sufficient capacity to be able to polish the
sewage treatment plant effluent and a proportion of river water to comply
with ZDP. |
|
DDE/CC |
3 |
3 |
3 |
Technical Memorandum Standards for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters
(TM). |
|
|
Monitoring The assessment of water quality impacts has
concluded that routine environmental monitoring of water quality during
construction should be carried out as specified in the EIA report, to
minimise impacts on downstream water quality. The specified mitigation
measures should be written into contract documents. |
All sites/construction |
CC |
3 |
|
|
-- |
|
|
Routine audit of the implementation status of
specified mitigation measures during the construction and operation phases
should be undertaken by the project proponent or his representative. Such
audits should be well documented and include action procedures in the case of
non-compliance. |
All sites/ Construction |
CC |
|
3 |
|
|
|