APPENDIX A
Introduction
A1
One of the Hong Kong Government's
overall policy objectives on environmental planning, as outlined in the 1989 White Paper on Pollution in Hong Kong,
is "to avoid creating new environmental problems by ensuring the
consequences for the environment are properly taken into account in site
selection, planning and design of all new developments".
A2
This
section highlights the relevant environmental legislation and guidelines which
are currently applicable to the proposed project. The EIA Ordinance and its associated Technical Memorandum is of particular relevance and was enacted in
April, 1998.
EIA Ordinance and its Associated Technical Memorandum
A3
The
Technical Memorandum on the Environmental Impact Assessment Process (TMEIA) is
issued under section 16 of the Environmental Impact Assessment Ordinance (Cap
499). The TM sets out the principles, procedures, guidelines, requirements and
criteria for:
(a)
the
technical content of a project profile;
(b)
the
technical content of an environmental impact assessment study brief or
environmental impact assessment report;
(c)
deciding
whether a designated project is environmentally acceptable;
(d)
deciding
whether an environmental impact assessment report meets the requirements of the
environmental impact assessment study brief;
(e)
deciding
whether the Director will permit an applicant to apply directly for an
environmental permit under section 5(9), (10) or (11) of the Ordinance;
(f)
resolving
conflicts on the content of the environmental impact assessment study brief and
the environmental impact assessment report;
(g)
taking
advice from other authorities;
(h)
deciding
what is a material change, addition or alteration to an environmental impact or
to a designated project;
(i)
the
issue of environmental permits;
(j)
the
imposition of environmental monitoring and audit requirements for designated
projects as conditions in environmental permits.
A4
The TM
provides criteria and guidelines for each aspect of the environmental impact
assessment by which to identify and evaluate activities which have the
potential to adversely impact the environment. The details of these are given
in the following relevant sections.
Hong
Kong Planning Standards and Guidelines
A5
The Hong Kong Planning Standards and Guidelines
(HKPSG) Chapter 9: Environment provides guidance for including environmental
considerations in the planning of both public and private developments. The
environmental suitability of a site for a certain land use is governed by such
factors as:
(i) natural
environmental characteristics including topography, climate, hydrological and
hydrographical characteristics, vegetation, wildlife and habitat, and soil
conditions;
(ii) the
nature, distribution and consequences of the residuals including aerial
emissions, wastes, sewage or noise generated by land uses in the development
area;
(iii) the capacity of the environment
to receive additional developments; and
(iv) existing
land uses.
A6
The HKPSG specifies the Government's overall
policy objective for environmental planning to be:
“to avoid creating new environmental
problems by ensuring the consequences for the environment are properly taken
into account in site selection, planning and design of all new developments;
and
"to seize opportunities for
environmental improvement as they arise in the course of urban
redevelopment"; and to ensure that,
"adequate and suitably sited environmental
facilities are provided to ensure proper handling and disposal of all wastes
and waste water arising from proposed developments."
Conservation
A7
HKPSG Chapter 10: Conservation states that the following four
principles should be adopted for the practical pursuit of conservation in land
use planning:
(i)
retain
significant landscapes and ecological attributes and heritage features as
conservation zones;
(ii) restrict
uses within conservation zones to those which sustain particular landscapes and
ecological attributes and heritage features;
(iii) control
adjoining use to minimise adverse impacts on conservation zones and optimise
their conservation value; and
(iv) create,
where possible, new conservation zones in compensation for areas of
conservation value which are lost to development.
Items of value which merit
conservation are identified in territorial, sub-regional and district planning
exercises, special surveys undertaken by other departments or as the result of
public views. However, plans which include conservation use have to be seen in
a wider context and take into account the need to provide adequate space for
development needs. The challenge is to combine these different uses into
acceptable and realistic plans which take account of territorial growth and
principles of sustainable development.
Protecting Natural Landscapes and Habitats
A8
Natural
landscapes and habitats may be gazetted as Country Parks or Special Areas (Country Parks Ordinance Cap 208),
Restricted Areas (Wild Animals Protection
Ordinance Cap 170), Water Gathering Grounds (Waterworks Ordinance Cap 102), conservation zones (Town Planning Ordinance Cap 131) or
listed as Sites of Special Scientific Interest (SSSIs).
A9
Country
Parks and Special Areas are designated under the Country Parks Ordinance and managed by the Agriculture and
Fisheries Department (AFD) on the advice of the Country Parks Board. At present
there are 21 Country Parks (area 40, 833 ha) and 14 Special Areas (area 1,639 ha),
11 of which are within Country Parks. Country Parks are designated for the
purposes of nature conservation, countryside recreation and education; Special
Areas are areas of government land with special interest and importance by
reason of their flora, fauna, geological, cultural or archaeological features.
The Country Parks Authority has established criteria for determining whether or
not a particular location is suitable for designation as a Country Park or
Special Area. The criteria include landscape quality, recreation potential,
conservation value, size, land status and the practicality of management.
A10
The Wild Animals Protection Ordinance
restricts access to designated areas of wildlife habitat. Restricted Areas
under the Ordinance are implemented by the AFD although certain site management
activities may be shared by others. Two Restricted Areas have been designated,
the Mai Po Marshes and the Yim Tso Ha Egretry. In addition, the Ordinance
protects local wildlife through both the prohibition of hunting territory-wide
and the possession of scheduled protected wild animals or hunting appliances.
A11
Areas
of conservation use may be declared as conservation zones under clause 4(1)(g)
of the Town Planning Ordinance. These
zones are shown on statutory plans which are approved by the Town Planning
Board and this process is further discussed in the subsequent section on
preparing plans to conserve natural landscapes and habitats.
A12
In
April 1999, a Wetland Conservation Area and Wetland Buffer Area was recommended
as a result of the findings of the Fishpond Study, and subsequently adopted by
the Town Planning Board Guidelines in the Town Planning Board for Application
for Developments within Deep Bay Area under Section 16 of the Town Planning
Ordinance (TPB. PG – No. 12B 1999).
A13
SSSIs
may be land based or marine sites which are of special interest because of
their flora, fauna, geographical, geological or physiographic features. SSSIs
are identified by the AFD and the Planning Department maintains a register of
sites. Once identified, SSSIs are shown on statutory and departmental plans
prepared by the Planning Department. Inter-relationships between land uses can
be quite subtle. An SSSI declared as a wildlife habitat may only be sustainable
if the wider surroundings remain rural so as to provide feeding grounds.
Similarly, a wetland site may only be sustained if a particular water source is
protected.
A14
The
Government recognises the need to protect marine and wetland habitats. AFD is
responsible for the implementation of future marine parks/reserves. Important
wetlands may be declared as being of international importance under the Convention on Wetlands of International
Importance Especially as Waterfowl Habitat (known as the `Ramsar' Convention). Parties to the Convention
may designate sites for inclusion in the List
of Wetlands of International Importance which is administered by the Bureau
of the Convention. The Ramsar Convention
states that "wetlands should be selected for the List on account of their
international significance in terms of ecology, botany, zoology, limnology or
hydrology. In the first instance, wetlands of international importance to
waterfowl at any season should be included". The Mai Po Marshes (a
restricted area and a SSSI) the intertidal mudflat at Inner Deep Bay and the
fishponds in Buffer Zone 1 have been designated as a Ramsar Site since
September 1995.
Statutory
Plans
A15
The Town Planning Ordinance permits
statutory land use zones under clause 4(1)(g) for `country parks, coastal
protection areas, sites of special scientific interest, green belts or other
specified uses that promote conservation or protection of the environment'.
Conservation zones for statutory plans are:
(i) SSSI to
conserve and to protect fauna and flora and other natural features with special
scientific value.
(ii) Country
Park to
encourage recreation and tourism, protect vegetation and wildlife, preserve and
maintain buildings and sites of historical or cultural significance within
country parks and to provide facilities and services for the public enjoyment
of the country.
(Note: The term `Country Parks'
includes `Special Areas' designated under the Country Parks Ordinance.)
(iii) Coastal Protection Area to
retain natural coastline.
(iv) Conservation
Area to
retain existing natural features and rural use.
(v) Green
Belt to
define the limits of urban development areas by conserving landscape features.
Visual Assessment and Landscaping, and Impacts on Sites of Cultural
Heritage
A16
The
current legislation relating to landscape and visual impacts of development in
Hong Kong is the Environmental Impact Assessment Ordinance [Cap. 499] enacted
in April 1998. Other than EIAO, the older HKPSG Chapter 10: Landscape and
Conservation also contains recommendations about developments in agricultural
areas, woodlands, water gathering grounds, areas of freshwater fish culture,
scenic and potential recreation areas, also provided guidelines for reducing
adverse environmental effects of development in rural areas. Landscape and
Visual Assessment is assessed according to the criteria and methods stated in
Annex 3, 10 and 18 of TMEIA and recommendations of HKPSG. Recommendations
covered include:
(i) Topography and site information:
Developments on hill tops, scenic
ridges and prominent positions should be avoided wherever possible. Site
layout, road alignments, etc. should follow and relate to the natural contours.
Overall, formation work and site disturbance should be minimised.
In scenic areas, opportunities
should be taken to use local landform and any excavated material available to
`fit' the development into the ground form, soften the geometric outline of
buildings, and screen ancillary features from view.
Developments should be sited and
planned to minimise long term visual impact.
(ii) Retention
of existing vegetation:
Developments should be sited so as
to retain existing woodlands, groups of trees and feature trees wherever
possible.
Retention of trees on development
sites is made easier if non-building areas are specified to include all
significant tree features and suitable conditions to ensure these areas are
protected and included in development proposals.
Advice should be sought from
Agriculture, Fisheries and Conservation Department, Buildings Department, Architectural
Services Department, Food and Environmental Hygiene Department and Leisure and
Cultural Services Department, on regulations governing the felling of trees,
the suitability of trees for retention and the possible occurrence of important
flora and fauna.
(iii) Site
layout, overhead services alignments, etc.:
The appropriate siting and design of
development is often crucial for the maintenance of the landscape in rural
areas. Building layouts that avoid regular repetitive or geometric forms and that
relate well to natural landforms are preferred.
Views from surrounding areas should
be taken into account.
Overhead services should be aligned
to minimise visual impact and below ground routes should be preferred in
sensitive areas.
(iv) Building design and landscape treatment:
In areas of scenic importance,
building design should be sympathetic with the surrounding landscape and the
general rural environment.
The preparation and implementation of landscape
plans should be a requirement on all major developments and, as a general rule,
for developments in scenic areas. Landscape Plans should include all or most of
the following:
(a) A
framework of tree planting to separate, screen and complement buildings;
(b) Shrub
and ground cover on the periphery of the site where this is open to public
view;
(c)
Re-vegetation
of excavated areas and formed slopes not built upon, consistent with
geotechnical requirements; and
(d) Proposals
to ensure that the vegetation to be established is maintained or self-sustaining.
A17
HKPSG also provides the following guidelines for
roadside planting which are applicable in both the urban and rural context:
(i) Wherever
possible, existing trees and woodlands are to be retained. Where this proves
impractical, all possible efforts should be made to transplant suitable healthy
trees either elsewhere on site or in the near vicinity.
(ii) Wherever
possible, footways, median strips and road side areas should be designed to
accommodate planting. Transport Department, Highways Department and Fire
Services Department should be consulted. In areas where planting is intended,
special consideration to the location of utility services may be required.
(iii) Roadside
and median plantings can also temper the environment, reduce vehicle pollution
to a degree and screen traffic and other uses.
(iv) Major
planting belts (structure plantings) should be wide enough to be usable for
recreation and be heavily planted. Where a buffer for polluting uses is
intended a wide planting is needed (say 45 m).
(v) Intersections
(especially grade separated) occupy large areas and present scope for heavy
planting and contouring. Care must be taken with sight lines, and the Territory
Development Department should be consulted.
(vi) Always
consult with future maintenance authorities (Urban Services Department,
Regional Services Department).
Noise
A18
HKPSG states that "The basic role of planning
against noise is to provide an environment whereby noise impacts on sensitive
uses are maintained at acceptable levels."
A19
For
Designated Projects noise is assessed according to the criteria and methods in
Annexes 5 and 13 of the TMEIAO. Evening and night time construction works, as
well as commercial/industrial noise is controlled under the Noise Control Ordinance [Cap 400] of
1988 regulations and associated Technical Memoranda (TM). The following TM have
been issued on:
(i)
The Assessment of Noise from Places other than
Construction Sites, Domestic Premises or Public Places (1997)
(ii) Noise
from Construction Work other than Percussive Piling (2nd Ed. 1997)
(iii) Noise
from Percussive Piling (1997)
(iv) Noise
from Construction Works in Designated Area (1997)
A20
Noise
Sensitive Receivers (NSRs) are defined by the EIAO TM and the Noise Control Ordinance (NCO TM) as
follows:
(i) all
domestic premises, including temporary housing accommodation;
(ii) hotels
and hostels;
(iii) offices;
(iv) educational
institutions, including kindergartens, nurseries and all others where unaided
voice communication is required;
(v) places
of public worship and courts of law;
(vi) hospitals,
clinics, convalescences and homes for the aged, diagnostic rooms and wards;
(vii) amphitheatres and
auditoria, libraries, performing arts centres and Country Parks.
A21
The
appropriate Acceptable Noise Level (ANL) for a particular NSR is dependent on
the character of the area in which the NSR is located, and the time of day
under consideration. The Area Sensitivity Rating (ASR) is a function of the
type of area within which the NSR is located and the degree of the effect on
the NSR of particular Influencing Factors (IFs). IFs include any industrial
area, major roads (ie. those with a heavy and generally continuous flow of
vehicular traffic) and the area within the boundary of Hong Kong International
Airport. Table A.1 shows the Area Sensitivity Ratings given by the Noise Control Ordinance.
Table A.1
Area Sensitivity Ratings
Degree
to which NSR is
affected Type of by
IF Area containing NSR |
Not Affected |
Indirectly Affected |
Directly Affected |
(i) Rural
area, including Country Parks or village type developments |
A |
B |
B |
(ii) Low
density residential area consisting of low-rise or isolated high-rise
developments |
A |
B |
C |
(iii) Urban
area |
B |
C |
C |
(iv) Area
other than above |
B |
B |
C |
Notes:
`Country
Park' means an area that is designated as a country park pursuant to section 14
of the Country Parks Ordinance.
`Directly
Affected' means that the NSR is at such a location that noise generated by the
IF is readily noticeable by the NSR and is a dominant feature of the noise
climate of the NSR.
`Indirectly
Affected' means that the NSR is at such a location that noise generated by the
IF, whilst noticeable at the NSR, is not a dominant feature of the noise
climate of the NSR.
`Not
Affected' means that the NSR is at such a location that noise generated by the
IF is not noticeable at the NSR.
`Urban
Area' means and area of high density, diverse development including a mixture
of such elements as industrial activities, major trade or commercial activities
and residential premises.
Construction
Noise
A22
TM
EIAO specifies criteria for assessing noise from daytime construction noise
standards for 0100 to 1900 hours on any day not being a Sunday or general
holiday, in Leq (30 mins) are:
• 75
dB(A) for all domestic premises including temporary housing accommodation,
hotels and hostels
• 70
dB(A) for all educational institutions, including kindergartens, and nurseries
These
levels assume that the premises utilizes open windows for ventilation.
A23 Despite any description or assessment made in the subsequent paragraphs, the Noise Authority will be guided by the relevant Technical Memorandum (Memoranda) in assessing an application, once filed for a Construction Noise Permit. He will consider all the factors affecting his decision taking contemporary situations / conditions into account. Nothing in this Report shall bind the Authority in making his decision. There is no guarantee that a Construction Noise Permit will be issued, if a permit is to be issued, the Authority shall include any condition he thinks fit and such conditions are to be followed while the works covered by the permit are being carried out. Failing which will lead to cancellation of the permit and prosecution action under the NCO.
A24
Noise
restrictions are imposed during the evenings (19:00-23:00), night-time
(23:00-07:00) and all day on Sunday and public holidays. For construction
activities during these hours, a Construction Noise Permit (CNP) is required
from the Environmental Protection Department (EPD). The CNP application will be
assessed in accordance with the Basic Noise Levels (BNLs) given in the TM on Noise from Construction Works other
than Percussive Piling. For construction work within a designated area
involving the use of Specific Powered Mechanical Equipment (SPME) other than
percussive piling and/or carrying out of prescribed construction works (PCW)
the CNP application will be assessed in accordance with the BNLs given in the TM on Noise from Construction Work in
Designated Area. These BNLs are shown in Table A.2.
Table A.2
Basic Noise Levels for
General Construction Noise
ASR Time Period |
A |
B |
C |
All days during
the evening (19:00-23:00), and general holidays (including Sundays) during
the daytime and evening (07:00-23:00) |
60* 45** |
65* 50** |
70* 55** |
All days during
the night-time (23:00-07:00) |
45* 30** |
50* 35** |
55* 40** |
* Construction work other
than percussive piling in areas, and the construction work does not involve the
use of SPME nor the carrying out of PCW.
** Construction work within a designated area
involving the use of SPME other than percussive piling and/or carrying out of
PCW.
A25
The
PCW and SMPE are:-
(i) use
of all handheld breakers
(ii) use
of all bulldozers
(iii) use of all
concrete lorry mixers
(iv) use of all
dump trucks
(v) use
of all vibratory hand held pokers
(vi) erection or
dismantling of formwork or scaffolding
(vii) loading,
unloading or handling of rubble, wooden boars, steel bars, wood or scaffolding
material
(viii) hammering
A26
Noise
criteria applied to control the noise from percussive piling is detailed in the
TM on Noise from Percussive Piling.
Any percussive piling requires a CNP from EPD. When considering the issue of a
CNP, EPD compares the corrected noise level (CNL) with the Acceptable Noise
Level (ANL) for the area. Table A.3 shows the ANLs for percussive piling.
Table A.3
Acceptable Noise Levels for Percussive Piling
NSR Window Type or Means of Ventilation |
ANL (dB(A)) |
(i) NSR
(or part of NSR) with no windows or other openings |
100 |
(ii) NSR
with central air conditioning system |
90 |
(iii) NSR
with windows or other openings but without central air conditioning system |
85 |
Note: 10 dB(A) is
deducted from the ANLs shown above for NSRs such as hospitals, medical clinics,
education and other NSRs considered to be particularly sensitive to noise.
A27
The
CNL relates to the tonality, impulsiveness and intermittency of the noise. In
the event that the CNL exceeds the ANL, EPD will impose restrictions on the
permitted hours of piling operation in accordance with Table A.4.
Table A.4
Permitted Hours of Percussive Piling
Operation on or after 01.10.99
|
Permitted hours of operation on any day not being a
general holiday |
CNL is less than
10 dB(A) below ANL |
Nil |
CNL is more than
10 dB(A) below ANL |
07:00-19:00 |
A28
A
Construction Noise Permit (CNP) must be applied for any kind of percussive
piling carried out in the territory. Table A.5 lists the maximum permitted
hours which can be obtained under the latest legislation not involving the use
of diesel, pneumatic and/or steam hammer. By 2000, the use of diesel, pneumatic
and/or steam hammers will be effectively phased out by stringent standards
lowering acceptable no. 34 to less than 10 dB(A) below ANL. It is a summary of
the information given in the Technical
Memorandum On Noise From Percussive Piling, 1997, issued by the EPD under
the NCO.
Table A5
Permitted Hours of
Operation for the Carrying Out of Piling Work
Not Involving the Use of Diesel, Pneumatic and/or Steam Hammers
Amount by which Corrected
Noise Level (CNL) exceeds Acceptable Noise Level (ANL), CNL-ANL |
Permitted hours of operation on any day not being a general holiday |
10 dB(A) < CNL
– ANL |
0800 to 0900 AND 1230 to
1330 AND 1700 to 1800 |
0 dB(A) < CNL
- ANL £ 10 dB(A) |
0800 to 0930 AND 1200 to
1400 AND 1630 to 1800 |
CNL - ANL £ 0 dB(A) |
0700 to 1900 |
A29
The
information required in an application for a CNP includes:
• a
map (preferably 1:1000 scale) showing precise details of the site location,
site limits and nearby noise sensitive receivers, e.g. residential buildings,
schools, hospitals;
• location
of any stationary powered mechanical equipment on site or, in the case of an
application for a percussive piling permit, the piling zone or actual pile
locations;
• details
of time period (time of day, duration in days/weeks/months) for which the CNP
is required;
• a
description, including two photographs and identification codes, and number of
units of each item of powered mechanical equipment to be used or, in the case
of piling, details of the piling method and pile type including number of
units; and
• details
of any particularly quiet items of equipment or piling methods, special noise
control measures to be employed on site, or any other information thought to be
relevant.
A30
Despite
any description or assessment made in the subsequent paragraphs, the Noise
Control Authority will be guided by the relevant Technical Memorandum
(Memoranda) in assessing an application, once filed, for a Construction Noise
Permit. He will consider all the factors affecting his decision taking
contemporary situations/conditions into account. Nothing in this Report shall
bind the Authority in making his decision. There is no guarantee that a
Construction Noise Permit will be issued. If a permit is to be issued, the
Authority shall include any condition he thinks fit and such conditions are to
be followed while the works covered by the permit are being carried out.
Failing which will lead to cancellation of the permit and prosecution action
under the NCO.
A31
During
daytime works, EPD recommends that the advice in EPD's TM EIAO on construction
noise abatement practice is followed.
Operational
Noise
A32
Table
1A of Annex 3, TMEIA, states that noise levels from a new fixed source should
be 5 dB(A) below the relevant ANL presented in the TM on The Assessment of Noise from Places other than Construction
Sites, Domestic Premises or Public Places or the prevailing background
noise level, whichever is lower. The ANL from the TM for a given NSR is
presented in dB(A) in Table A.6 below.
Table A.6
Acceptable Noise
Levels during Operations
ASR Time Period |
A |
B |
C |
Day (07:00-19:00)
and Evening (19:00-23:00) |
60 |
65 |
70 |
Night
(23:00-07:00) |
50 |
55 |
60 |
Rail
Noise
A33
For
rail noise, the TM EIAO specifies the acceptable noise limit at the facades of
all noise sensitive buildings, as Lmax (2300 - 0700 hours) of 85 dB(A),
and to comply with the Acceptable Noise Levels laid down in the Technical
Memorandum for the Assessment of Noise from Places other than Domestic
Premises, Public Places or Construction Sites as given in Table A.6.
Air
Quality
A34
The
principal legislation regulating air emissions in Hong Kong is the Air Pollution Control Ordinance (APCO) [Cap
311] of 1983 and its subsidiary regulations.
A35
The
whole of the Territory has been divided into Air Control Zones. The study
basically falls within the topographically confined Deep Bay Airshed.
A36
HKPSG states that "Air quality is affected by
such factors as the emission rate of air pollutants, the separation distance
between emission sources and receptors, topography, height and width of
buildings as well as meteorology."
A37
The Air Pollution Control (Construction Dust)
Regulations has been implemented in 1997. These regulations are to control
the dust emission from construction sites by a notification and permit
procedure.
Operational
Emissions
A38
The
Hong Kong Air Quality Objectives (AQOs) state the maximum acceptable
concentration of air pollutants. The AQOs for one and 24 hour
concentrations of five major pollutants are shown in Table A.9. The Government
aims to achieve the AQOs throughout the Territory as soon as `reasonably
practicable'. Efforts are being made to control and reduce air pollution
emitters in areas where the AQOs are already exceeded, eg. by controlling new
developments. The AQOs will apply to the operational phases of the project.
Construction
Dust
A39
During
the construction phase of the project, an hourly average TSP limit of 500 μg/m3 is recommended by EPD for assessing construction dust
impacts. This limit is not statutory, but nonetheless has been used in many
construction works in Hong Kong as a contractual requirement.
A40
The HKPSG recommends that any open storage
areas should be located at least 100 m from any air sensitive receiver.
Cement
and Concrete
A41
Cement
works in which the total silo capacity exceeds 50 tonnes and in which cement is
handled fall under the Specified Processes under the Air Pollution Control Ordinance. A licence from EPD is required to
operate such a works.
A42
Technical
Memoranda have been issued on:
(i) Specifying
Air Quality Objectives for Hong Kong (Table A.9);
(ii) Issuing
Air Pollution Abatement Notices to Control Air Pollution from Stationary
Pollution Processes.
Other subsidiary regulations issued
are as follows:
A1 - Furnaces,
Ovens and Chimneys (Installation and Alteration) Regulations.
B1 - Dust
and Grit Emission Regulations.
C1 - Smoke
Regulations.
D1 - Appeal
Board.
E1 - Air
Control Zones (Declaration and Consideration) Order.
F1 - Specified
Processes.
G1 - Specification
of Required Particulars and Information.
H1 - Consolidation
Statement of Air Quality Objectives.
I1 - Fuel
Restriction
J1 - Vehicle
Design Standards (Emission) Regulations.
Table A.9
Air Quality Objectives
Pollutant |
Concentration (μg)m3 |
Health effects of pollutant at elevated
ambient levels |
||||
|
Average Time |
|
||||
|
1hr |
8hrs |
24hrs |
3mths |
1yr |
|
Sulphur Dioxide |
800² |
|
3503 |
|
80 |
Respiratory illness; reduced lung function; morbidity and mortality
rates increase at higher levels. |
Total Suspended Particulate |
|
|
2603 |
|
80 |
Respirable fraction has effects on health. |
Respirable Suspended Particulates |
|
|
1803 |
|
55 |
Respiratory illness; reduced lung function; cancer risk for certain
particles; morbidity and mortality rates increase at higher levels. |
Nitrogen Dioxide |
300² |
|
1503 |
|
80 |
Respiratory irritation; increased susceptibility to respiratory
infection; lung development impairment. |
Carbon Monoxide |
30000² |
100003 |
|
|
|
Impairment of co-ordination; deleterious to pregnant women and those
with heart and circulatory conditions. |
Photochemical Oxidants as ozone |
240² |
|
|
|
|
Eye irritation; cough; reduced athletic performance; possible
chromosome damage. |
Lead |
|
|
|
1.5 |
|
Affects cell and body processes; likely neuro-psychological effects,
particularly in children; likely effects on rates of incidence of heart
attacks, strokes and hypertension. |
Notes: Concentrations
measured at 298°K (25°C) and 101.325 kPA
1 Suspended
particles in air with a nominal aerodynamic diameter of 10 μm or smaller
2 Criteria
not to be exceeded more than 3 times per year
3 Criteria
not to be exceeded more than once per year
A43
In
order to obtain a licence to conduct a Specified Process, EPD may require the
applicant to submit an air pollution control plan for the process. This will
include:
(i) a
description and technical particulars of the plant or equipment that may evolve
an air pollutant;
(ii)
details
of pollution control equipment or measures proposed to minimise emissions and
comply with the requirement to use the best practicable means of controlling air
pollution;
(iii) a
description (with maps) to identify sensitive receivers, eg. residential
buildings, schools, hospitals;
(iv) an
assessment of the resulting air quality and risk to human health, including
supporting calculations and information;
(v) a
statement that the best practicable means of controlling air pollution has been
adopted or is proposed, including supporting calculations and information;
(vi) a plan for,
or scheme of, monitoring the emission at source or the ambient concentration of
any air pollutant.
A44
The HKPSG recommends that any concrete
batching plants and open storage areas should be located at least 100 m
from any air sensitive receiver.
Water
Quality
A45
The
TMEIA specifies criteria for evaluating water pollution to be:
·
water
quality, in terms of compliance with Water Quality Objectives for the water
body under study;
·
hydrology,
in relation to mixing zone criteria;
·
bottom
sediments and ecology;
·
stress
status of water body; and
·
cumulative
impacts from other projects.
A46
Project
specific criteria which need to be evaluated include:
·
waste
discharges;
·
dumping
of wastes;
·
stormwater
runoff; and
·
release
of toxic or prohibited substances.
A47
In the
assessment of the significance of identified impacts, the existing water
quality of the water bodies must be determined and the assimilative capacity of
the receiving water body evaluated to identify the need for mitigation of
impacts.
A48
Particular
attention must be paid to activities which involve discharges containing toxic
components, and the adequacy of existing treatment systems assessed. The
presence of reclamations, or other works which affect water flow must be taken
into account in assessing impacts. Non-point pollution sources and stormwater
discharges must be considered for all new developments, and devices to control
pollution incorporated into the drainage system.
A49
The
principal legislation for controlling water pollution in Hong Kong is the Water Pollution Control Ordinance (WPCO)
[Cap 358] of 1981 which allows for gazette of Water Control Zones (WCZ)
within which the discharge of liquid effluents and the deposit of matter into
any water bodies, public sewers and drains are controlled. The WPCO is
applicable for construction site discharges as well as for discharges during
the operational phase.
A50
The
Study Area falls within the Deep Bay Water Control Zone, which was declared on
1 December 1990. Deep Bay (Hau Hoi Wan) is affected by pollution from various
sources both within and outside Hong Kong. The water quality objectives for Deep
Bay are presented in Table A.10.
Table A.10
Statement of Water
Quality Objectives
(Deep Bay Water
Control Zone)
Sections relevant to
the Project
Water Quality Objective |
Part or Parts of Zone |
|
A. |
AESTHETIC
APPEARANCE |
|
|
(a) Waste
discharges shall cause no objectionable odours or discolouration of the
water. |
Whole Zone |
|
(b) Tarry
residues, floating wood, articles made of glass, plastic, rubber or of any
other substances should be absent. |
Whole Zone |
|
(c) Mineral
oil should not be visible on the surface. Surfactants should not give rise to
a lasting foam. |
Whole Zone |
|
(d) There
should be no recognisable sewage-derived debris. |
Whole Zone |
|
(e) Floating,
submerged and semi-submerged objects of a size likely to interfere with the
free movement of vessels, or cause damage to vessels, should be absent. |
Whole Zone |
|
(f) Waste
discharges shall not cause the water to contain substances which settle to
form objectionable deposits. |
Whole Zone |
B. |
BACTERIA |
|
|
(a) The
level of Escherichia coli should
not exceed 610 per 100 mL, calculated as the geometric mean of all
samples collected in one calendar year. |
Secondary Contact Recreation Subzone and Mariculture
Subzone (L.N. 455 of 1991) |
|
(b) The
level of Escherichia coli should be
zero per 100 mL, calculated as the running median of the most recent 5
consecutive samples taken at intervals of between 7 and 21 days. |
Yuen Long &
Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and
Water Gathering Ground Sub-zones |
C. |
COLOUR |
|
|
(a) Waste
discharges shall not cause the colour of water to exceed 30 Hazen units. |
Yuen Long &
Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and
Water Gathering Ground Subzones |
D. |
DISSOLVED OXYGEN |
|
|
(a) Waste
discharges shall not cause the level of dissolved oxygen to fall below 4
milligrams per litre for 90% of the sampling occasions during the year;
values should be taken at 1 metre below surface. |
Inner Marine
Subzone excepting Mariculture Subzone |
|
(c) The
dissolved oxygen level should not be less than 5 milligrams per litre for 90%
of the sampling occasions during the year; values should be taken at
1 metre below surface. |
Mariculture
Subzone |
|
(d) Waste
discharges shall not cause the level of dissolved oxygen to be less than 4
milligrams per litre. |
Yuen Long &
Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges
Subzone, Water Gathering Ground Subzones and other inland waters of the Zone |
E. |
PH |
|
|
(a) The
pH of the water should be within the range of 6.5-8.5 units. In addition,
waste discharges shall not cause the natural pH range to be extended by more
than 0.2 units. |
Marine waters
excepting Yuen Long Bathing Beach Subzone |
|
(b) Waste
discharges shall not cause the pH of the water to exceed the range of 6.5-8.5
units. |
Yuen Long &
Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges
Subzone and Water Gathering Ground Subzones |
F. |
TEMPERATURE |
|
|
Waste discharges
shall not cause the natural daily temperature range to change by more than
2.0oC. |
Whole Zone |
G. |
SALINITY |
|
|
Waste discharges
shall not cause the natural ambient salinity level to change by more than
10%. |
Whole Zone |
H. |
SUSPENDED SOLIDS |
|
|
(a) Waste
discharges shall neither cause the natural ambient level to be raised by 30%
nor give rise to accumulation of suspended solids which may adversely affect
aquatic communities. |
Marine waters |
|
(b) Waste
discharges shall not cause the annual median of suspended solids to exceed 20
milligrams per litre. |
Yuen Long &
Kam Tin (Upper and Lower) Subzones, Beas Subzone, Ganges Subzone, Indus
Subzone, Water Gathering Ground Subzones and other inland waters |
I. |
AMMONIA |
|
|
The un-ionized
ammonical nitrogen level should not be more than 0.021 milligram per litre,
calculated as the annual average (arithmetic mean). |
Whole Zone. |
J. |
NUTRIENTS |
|
|
(a) Nutrients
shall not be present in quantities sufficient to cause excessive or nuisance
growth of algae or other aquatic plants. |
Inner and Outer
Marine Subzones |
|
(b) Without
limiting the generality of objective (a) above, the level of inorganic
nitrogen should not exceed 0.7 milligram per litre, expressed as annual mean. |
Inner Marine
Subzone |
K. |
5-DAY BIOCHEMICAL OXYGEN DEMAND |
|
|
(a) Waste
discharges shall not cause the 5-day biochemical oxygen demand to exceed 3
milligrams per litre. |
Yuen Long &
Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and
Water Gathering Ground Subzones |
L. |
CHEMICAL OXYGEN
DEMAND |
|
|
(a) Waste
discharges shall not cause the chemical oxygen demand to exceed 15 milligrams
per litre. |
Yuen Long &
Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and
Water Gathering Ground Subzones. |
M. |
TOXINS |
|
|
(a) Waste
discharges shall not cause the toxins in water to attain such level as to
produce significant toxic carcinogenic, mutagenic or teratogenic effects in
humans, fish or any other aquatic organisms, with due regard to biologically
cumulative effects in food chains and to toxicant interactions with each
other. |
Whole Zone |
|
(b) Waste
discharges shall not cause a risk to any beneficial uses of the aquatic
environment. |
Whole Zone |
A51
The TM on Standards for Effluents Discharged
into Drainage and Sewerage Systems, Inland and Coastal Waters was issued in
1991. Under the provisions of this TM, all discharges must be licensed. Tables
included within the document identify standards related to effluent flow rates
ranging from <200 m3/day to 3,000 m3/day,
providing guidance on a case-by-case basis. To illustrate this, standards for
Group B inland water discharges are shown in Table A.11.
Table A.11
Standards for
Effluents discharged into Group B inland waters
Flow
rate (m³/day) Determinant |
£200 |
>200 and £400 |
>400 and £600 |
>600 and £800 |
>800 and £1000 |
>1000 and £1500 |
>1500 and £2000 |
>2000 and £3000 |
pH (pH units) |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
Temperature (oC) |
35 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
Colour (lovibound units) (25 mm cell length) |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
Suspended solids |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
30 |
BOD |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
20 |
COD |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
80 |
Oil & Grease |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
10 |
Iron |
10 |
8 |
7 |
5 |
4 |
3 |
2 |
1 |
Boron |
5 |
4 |
3 |
2.5 |
2 |
1.5 |
1 |
0.5 |
Barium |
5 |
4 |
3 |
2.5 |
2 |
1.5 |
1 |
0.5 |
Mercury |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
0.0001 |
0.001 |
0.001 |
Selenium |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
0.1 |
0.1 |
0.1 |
Other toxic metals individually |
0.5 |
0.5 |
0.2 |
0.2 |
0.2 |
0.1 |
0.1 |
0.1 |
Total toxic metals |
2 |
1.5 |
1 |
0.5 |
0.5 |
0.2 |
0.2 |
0.2 |
Cyanide |
0.1 |
0.1 |
0.1 |
0.08 |
0.08 |
0.05 |
0.05 |
0.03 |
Phenols |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Sulphide |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
0.2 |
Fluoride |
10 |
10 |
10 |
8 |
8 |
8 |
5 |
3 |
Sulphate |
800 |
800 |
600 |
600 |
600 |
400 |
400 |
400 |
Chloride |
1000 |
1000 |
800 |
800 |
800 |
600 |
600 |
400 |
Total phosphorus |
10 |
10 |
10 |
8 |
8 |
8 |
5 |
5 |
Ammonia nitrogen |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
Nitrate + nitrite nitrogen |
30 |
30 |
30 |
20 |
20 |
20 |
10 |
10 |
Surfactants (total) |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
E-coli (count/100 ml) |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
Note: All units in mg/L
unless otherwise indicated; all figures are upper limits unless otherwise
indicated.
Water Pollution Control (Sewerage) Regulation
A52
The Water Pollution Control (Sewerage) Regulation
was enacted in June 1994 to require owners of ancyroid properties to connect
their discharge of wastewater to the public sewerage system and to provide
control over operation and maintenance of private treatment facilities. This
regulation specifies the gazetted procedures for infrastructure works. This
legislation will reduce wastewater discharges direct to environment and lead to
water quality improvements in areas served by the public sewerage system. The
requirements have been defined in a Technical Circular issued by EPD, ProPECC PN 1/94 on Construction Site
Drainage.
Construction Site Discharges
A53
Advice
on the handling and disposal of construction site discharges, including site
runoff and contaminated wastewaters, is provided in the ProPECC Paper (PN1/94) on Construction
Site Drainage.
A54
The Livestock Waste Control Scheme (LWCS) to
the Waste Disposal (Livestock Waste)
Regulations was implemented on 24th June 1988 under the Waste Disposal Ordinance (Cap. 354). The
LWCS was reviewed and a new implementation programme was adopted in April 1994
under the Amendment of the Waste Disposal
(Livestock Waste) Regulations.
Discharge Standards
Restriction Area |
Phased Implementation of Discharge Standards@ |
||
250:250 |
100:100 |
50:50 |
|
10R, 13R & 14R |
1 Jul 1995 |
1 Jul 1996 |
1 Jul 1997 |
11R |
1 Jul 1994* |
1 Jul 1996 |
1 Jul 1997 |
16R, 18R, 19R, 21R, 23R-25R |
1 Jan 1996 |
1 Jan 1997 |
1 Jan 1998 |
Control Area |
|
|
|
10, 12-14 |
1 Jul 1995 |
1 Jul 1996 |
1 Jul 1997 |
11 |
1 Jul 1994 |
1 Jul 1996 |
1 Jul 1997 |
15-17 |
1 Jul 1996 |
1 Jul 1997 |
1 Jul 1998 |
18-25 |
1 Jul 1997 |
1 Jul 1998 |
1 Jul 1999 |
Important Note:
@ in addition to meeting the
above phased implementation programme, any farm that is new or restarts
business after acceptance of the ex-gratia allowance must immediately comply
with the discharge standard of 250:250 as soon as it starts ore restarts its
business. Any failure to comply fully with the control requirements would
result in enforcement and prosecution action.
1 July 1995
for farms on Lantau Island other than in Mui Wo Environs.
Waste Oil
A55
The
disposal of waste oil and other chemicals is controlled by the regulations for
chemical waste control under the Waste
Disposal Ordinance. Chemical wastes must be disposed of at a licensed
chemical waste disposal facilities. The Chemical Waste Treatment Centre (CWTC)
at Tsing Yi is one of the facilities licensed to allow disposal of waste oil.
Waste oil may also be disposed of at other licensed disposal sites.
Zero Discharge Policy
A56 EPD operates a policy of “zero discharge” for new developments discharging into the Deep Bay Water Control Zone. Under this policy, measures must be put in place to ensure that there is no net increase in pollution load as a result of the development.
Solid Waste
A57 In the TMEIA, the criteria for assessing waste management implications are listed as follows:
(a)
provide
adequate, environmentally acceptable waste handling, storage, collection,
transfer, treatment and disposal facilities to deal with waste arising from the
development;
(b)
meet all
the relevant requirements under the Waste Disposal Ordinance and its
Regulations;
(c)
provide
proper handling, storage, collection and disposal of waste generated during
construction phase in accordance with the requirements of the Waste Disposal
Ordinance and the Dumping at Sea Ordinance;
(d)
provide
adequate facilities to facilitate waste reduction and explore beneficial use of
waste generated, taking into account:
-
the
quantity of waste arising;
-
the
physical and chemical nature of the waste materials;
-
all
practicable on site measures to render the waste acceptable for beneficial use;
-
the
availability of outlets for beneficial use of the waste in Hong Kong;
-
the
environmental effect in any waste reduction practice and additional handling of
waste for beneficial use;
(e)
explore
alternatives which generate minimal amount of waste through design
modifications and programming of works; and
(f)
for
residential and community developments cost to existing landfills, adequate
safety and precautionary measures to avoid or minimise the risks due to landfill
gas (LFG) migration or leachate contamination. In particular, for development
or re-development that is within 250 m of the edge of waste, a landfill gas
hazard assessment is typically required to assess the risk associated with LFG
and, where necessary, design adequate precautionary/protection measures to
render the proposed development as safe as reasonably practicable.
A58 In assessing the potential waste impacts from a proposed project, specific activities or industries must be considered, particularly if they have special requirements for disposal. Such activities include:
·
Offensive
Trades
·
Chemical
Waste Producing Industries
·
Livestock
rearing
·
Community
Facilities with special waste disposal requirements
A59 A waste management plan must be prepared describing methods for reducing wastes, recycling and re-using wastes, and, if they require disposal, techniques need to be included for collecting, handling and transporting the waste materials, and identifying facilities for disposal.
A60 Chapter 9 of HKPSG states, in Section 6 - Waste Management that "The Government's overall objectives for waste management planning are to ensure:
(a) the
adequate provision of facilities for cost-effective and environmentally
satisfactory disposal of all wastes; and
(b) the
availability of and proper enforcement of legislation on storage, collection,
transport, treatment and disposal of wastes, to safeguard the health and
welfare of the community from any adverse environmental effects."
A61 Disposal of chemical, household, street, trade and livestock waste is controlled by the Waste Disposal Ordinance [Cap 354] of 1980. This legislation covers all aspects of the production, storage, collection and disposal, including the treatment, reprocessing and recycling of waste. In 1989, the formulation of a strategic Waste Disposal Plan for Hong Kong was founded on this legislation.
A62 Construction waste generated during the construction phase should be sorted on site into inert and non-inert fraction for reuse and recycling as far as practical. The non-inert fraction containing no more than 30% by weight of inert content can be disposed of at landfills, whilst the inert fraction should be delivered to public dumps or other reclamation sites. Inert material means soil, rock, asphalt, concrete, brick, cement plaster/mortar, building debris, aggregates, etc.
A63 Handling and disposal of chemical wastes including oils and grease are covered by the Waste Disposal (Chemical Waste) (General) Regulations. Design of oil/fuel storage facilities is covered by the Code of Practice for Oil Storage Installations, 1992 issued by the Building Authority and the handling of chemical spillages on land is regulated by the Fire Services Department.
A64 Dredging and dumping for land formation is controlled under the Foreshore and Sea Bed Reclamations Ordinance [Cap 127] (1985) and the Dumping at Sea Act (1974) Overseas Territories Order (1975) respectively. The former provides for the control of reclamation and use of foreshore and seabed. The latter prohibits dumping at sea without a licence.
A65 Guidelines and Standards on Contaminated Sediments are currently subject to review and may soon be changed. The current classification system is given below.
Table
A.12
Classification
of Sediments by Metal Content (mg/kg dry weight)
|
Cd |
Cr |
Cu |
Hg |
Ni |
Pb |
Zn |
Class A |
0.0-0.9 |
0-49 |
0-54 |
0.0-0.7 |
0-34 |
0-64 |
0-140 |
Class B |
1.0-1.4 |
50-79 |
55-64 |
0.8-0.9 |
35-39 |
65-74 |
150-190 |
Class C |
1.5 or more |
80 or more |
65 or more |
1.0 or more |
40 or more |
75 or more |
200 or more |
Note: Tests results should be rounded off to
two significant figures before comparing with the table, e.g. Cd to the nearest
0.1 mg/kg, Cr to the nearest 1 mg/kg, and Zn to the nearest
10 mg/kg, etc.
Operational
Waste
A66 Furthermore, waste reception and transfer facilities should be sited so that any adjacent development is very well buffered. For facilities handling the reception and disposal of dusty or odoriferous wastes, special precautions should be taken to avoid nuisance to surrounding areas. Note should be taken of prevailing wind direction and subsequent potential for nuisance.
HKPSG,
Chapter 9, Section 6
Refuse
Collection Points (Municipal Councils)
Provision
in Urban and New Town Areas
A67 A refuse collection point (RCP) is required to serve the needs of each population of 20,000 persons or areas within 500 m. In industrial or commercial areas, or in areas where adequate private facilities are, or will be available, this level of provision may need to be adjusted to suit anticipated needs. The Director of Urban Services and the Director of Regional Services should be consulted on detailed requirements.
A68 For road safety reasons, new RCPs should be planned to allow head-in-head-out movements of refuse collection vehicles (RCVs). A gross site area of not less than 294 m2 with a minimum width of 14 m) is required in the case of island or corner sites.
General
Location and Design Guidelines
A69 RCPs should be sited so as to minimise disruption to traffic or the creation of traffic safety hazards. RCPs should therefore not be located on trunk or primary distributor roads, on steep roads, or locations where turning trucks may create traffic problems.
A70 Adequate provision of off-street (enclosed) parking of bulk collection vehicles and separate access for the public and private refuse collectors should be provided where appropriate.
A71 The location and design of RCPs should aim to minimise nuisance to the public and people living and working nearby, where appropriate, by enclosing the whole facility and if necessary, through the provision of odour control equipment and ventilation. Water points should be a minimum requirement for all RCPs for cleaning purposes, design features such as air/exhaust cleaning, high-pressure water cleaning and leachate drainage and disposal should be incorporated. Architectural design of RCPs should also incorporate landscaping wherever possible as visual screening to, and as a buffer from adjacent sensitive land uses.
A72 Due to difficulties in finding suitable sites for RCPs especially in the built-up areas, RCPs should be incorporated in large-scale developments of both public and private sectors. To reduce the need for waste handling and minimise potential nuisance problems, appropriate waste collection and handling facilities should be included in these large-scale developments and redevelopments.
Provision
of Refuse Collection Facilities in Private Residential, Commercial and
Composite Building Developments
A73 The provision of refuse collection facilities in private residential, commercial and composite commercial/residential building developments should comply with the Building (Refuse Storage Chambers and Chutes) Regulations. The two Municipal Councils may stipulate certain conditions regarding the removal of household waste from premises under the Public Cleansing and Prevention of Nuisances (Urban Council/Regional Council) By-laws.
A74 The floor space and vehicular requirements of refuse storage chambers under the Building (Refuse Storage Chambers and Chutes) Regulations are summarised in Table A.13.
Table A.13
Summary of
Requirements of Refuse Storage Chambers
in Private
Residential, Commercial and Composite Building Developments
Description of Building |
Total Usable Floor Space
(UFS) (m2) |
Description of Storage
Chamber |
Minimum Floor Space of
Storage Chamber |
Residential
Building |
>1,320 to
<13,200 |
Storage chamber |
Total UFS in m2
divided by 440 |
|
>13,200 |
Storage chamber
with vehicular access |
|
Commercial
Building |
>3,960 to
<39,600 |
Storage chamber |
Total UFS in m2
divided by 1,320 |
|
>39,600 |
Storage chamber
with vehicular access |
|
Composite
Commercial/ Residential Building |
Aggregate of
>1,320 to <13,200 |
Storage chamber |
Aggregate of the
total UFS of the residential building component in m2 divided by
440 |
|
Aggregate of
>13,200 |
Storage chamber
with vehicular access |
Aggregate of the
commercial building component in m2 divided by 1,320 |
Provision in Public Housing Estates
A75 Whilst the above standards and guidelines are related to provision of RCPs in urban, new town and rural areas, they do not apply to public housing estates which are subject to separate provision standard and design criteria for refuse collection. The present and proposed refuse collection systems within public housing estates are outlined in the "Guidelines for Refuse Collection in Public Housing Estates" included in this Appendix and described below:
a) Refuse
Storage Chambers: standard provision incorporated in each domestic block which
provides sufficient daily storage. Depending on the size of the individual
block, one refuse bin with a minimum area allowance of 2.0 m2 should
be provided for every 35 flats.
b) Refuse
Storage Areas: temporary holding areas designed to accommodate the storage of
refuse bins awaiting collection. The location should aim to minimise nuisance
to the public and the estate tenants living nearby and should be within the
shortest distance practicable from the domestic blocks they serve. The minimum
allowance should be 2.5 m2 per bin.
c) RCPs
in Buildings: a totally enclosed structure which allows entry of RCVs for collection
of refuse generally associated with commercial centres. They are normally built
as part of the commercial centres provision. One centralised RCP should be
provided for an estate of 3,000 flats or less.
d) Junk
Collection Points: a separate storage area for those items which cannot be
handled by the normal refuse collection service. They should be an
independently designed structure apart from with the refuse storage chamber or
refuse storage area. Normally, an estate with 2,500 flats or less would require
one junk collection point of 20 m2 minimum. An estate of 2,500
flats or more would require two junk points of 20 m2, or one of
40 m2 minimum.
Guidelines
for Community Facilities with Special Requirements for Waste Disposal
A76 When planning these community facilities, allowance should be made for adequate space provision for the storage, collection and disposal of solid wastes. This should be in the form of a refuse storage area on the ground floor (or any floor with direct vehicular access). The area should be close to the goods lift and there should be adequate provision for off-street vehicular access for loading of RCVs. The refuse storage chambers should be built to similar standards as those required for residential developments under the Building (Refuse Storage Chambers and Chutes) Regulations.
Markets
and Cooked Food Stalls
A77 Many of the wastes produced by these facilities are highly putrescible. Adequate refuse storage area should be provided and located so as to minimise potential nuisance to the public and people living and working nearby. Animal carcasses, commonly generated by the activities within these facilities, should be segregated from other waste streams and separate temporary storage and collection facilities be provided. The facilities should preferably be confined in covered areas and grease traps should be provided to prevent chokage of sewers.
Hospitals/Clinics
A78 All clinical wastes should be separately collected from other municipal wastes. All clinical wastes must be disposed of in specially designed pathological incinerators.
Refuse
Transfer Stations
A79 A refuse transfer station (RTS) provides a regional and sub-regional destination for unloading of refuse collection vehicles, where the waste is containerised for haulage in bulk to a final disposal facility. A RTS aims primarily at reducing the cost of transporting waste and minimising environmental nuisance by better containment of waste. Consideration should be given to providing such a facility for handling 500-2,000 tonnes a day of waste in the Urban Area, equivalent to 500,000 - 2 million population, or 100 ‑ 1,000 tonnes in the NT, equivalent to 100,000 - 1 million population. A site area of between 1 and 2 hectares is required for each such facility.
A80 A RTS should be centrally located in the waste catchment it serves, preferably on the water front, with barge access. To minimise incompatibility with adjacent sensitive land uses, a RTS should be sited in an industrial or other non-sensitive area or, if possible, underground. Sufficient space should be provided for reception and queuing of refuse collection vehicles (RCVs). Short vehicular access from and to major transport routes is preferred, to avoid traffic congestion and delays to RCVs. The adequacy of adjoining road capacities for the RCVs should be determined. Considerations should be given to the provision of fully enclosed stations and/or suitable barriers for odour and dust control. Adequate control measures should be provided to minimise the impacts and may include provisions for noise control of the machinery and the structure, leachate treatment/ disposal systems and installation of air/exhaust cleaning systems.
Ecology
Sites
of Special Scientific Interest
A81 There are various legislative and regulatory controls in place for the conservation of species and protection of the environment. Table 1.2 from HKPSG's Chapter 9: Environment highlights "ecologically sensitive areas such as Sites of Special Scientific Interest (SSSI) and areas with other particular vegetation and wildlife habitat characteristics" as Environmental Factors influencing Land Use Planning, and states that Nature Reserves and SSSI should be adequately protected from the effects of pollution and from the diversion of natural flows.
TM for EIA
A82
The TM
for EIA Process provides criteria for evaluating ecological importance as well
as assessment and mitigation guidelines. Criteria for evaluating ecological
impacts and general criteria for evaluating ecological importance of a site or
species is given in Annex 8, and for assessment and mitigation in Annex 16.
Criteria for Evaluating Ecological Impact
A83
Annex
8 provides examples of important habitats in the Territory, and criteria for
evaluating a site or species. These criteria are listed in Table A.6 below.
Assessment and Mitigation Guidelines
A84
Annex
16 gives the guidelines for ecological assessment and mitigation. The need for
an ecological assessment for this project is stated in the brief.
The
five parts of an ecological assessment are given in the TM (Annex 16 (4)) as:
(1) Provision
of comprehensive and accurate information of the baseline environment;
(2) Identification
and prediction of potential ecological impacts;
(3) Evaluation
of the significance of the impacts identified;
(4) Recommendations
of effective and practicable alternatives and mitigation measures; and
(5) Recommendations
of the need for and the scope of an appropriate monitoring and audit programme.
Important habitats include
Recognized Sites of Conservation Interest (Annex 16, Appendix A, Note 1), as
well as other habitats. The criteria for important habitats requiring
assessment are partly based on their size, and are given in Table A14.
Table A.14
Minimum Size of
Habitats Requiring Assessment or Considered to be Important
Habitat Type |
TM
on EIA Process Annex
8.2 Table (1) Note: examples of important habitat types |
TM
on EIA Process Annex
16, Appendix A, Note 2: important habitats where an ecological assessment is
necessary |
PELB Technical
Circular No. 1/97& WBTC 4/97: Guidelines for Implementing the Policy on
Off-site Ecological Mitigation Measures: examples of important habitat types |
Woodland |
mature native > 1 ha |
> 1 ha |
mature native > 1 ha |
Undisturbed
Natural Coast |
> 1 ha or 500 metres long |
> 1 ha or 500 metres long |
> 1 ha or 500 metres long |
Intertidal
Mudflats |
> 1 ha |
> 0.5 ha |
> 1 ha |
Established
Mangrove stands |
any size |
any size |
any size |
Freshwater or
Brackish Marshes |
> 1 ha |
> 0.5 ha |
> 1 ha |
Established
Seagrass Bed |
any size |
any size |
any size |
Natural Stream
Courses and Rivers of Significant Length |
> 500 metres long |
> 100 metres |
Unpolluted
natural stream courses > 500 metres
long |
Other Wetlands
defined by Ramsar but not Mentioned Above |
(not included) |
> 1 ha |
(not included) |
Established Coral
Communities |
any size |
any size |
any size |
Other Habitats
Considered to Have Special Conservation Importance by Documented Scientific
Studies |
no size criteria |
no size criteria |
no size criteria |
A85
Annex
16 of the TM states that there is a general policy for mitigating impacts on
important habitats and wildlife. The importance is established in the
assessment process criteria given in the Table above. The policy for mitigation
(Annex 16 (5.4.1 a-c)), in order of priority, is:
(1) Avoidance:
adopting suitable alternatives, e.g. design;
(2) Minimize
unavoidable impacts through relocation, programming, or restoration;
(3) Impacts
that cannot be avoided or minimized may be compensated.
A86
The TM
states a preference for on-site mitigation rather than off site (Annex 16,
5.4.3). Off-site compensation will only be considered when all other mitigation
measures have been investigated and exhausted in the EIA process, and
significant residual impacts (according to the criteria in Annexes 8 and 16)
persist.
Guidelines for Implementing the Policy on Off-site Ecological Mitigation
Measures - PELB Technical Circular No. 1/97
A87
Ecological
impact is a product of the magnitude and scale of an impact and the asserted
importance of the species or habitat(s) likely to be affected (TM Annex
16,5.3.1). Criteria for implementing policy on off-site mitigation found in
PELB Technical Circular 1/97 give examples of important sizes of habitats.
These are compared to the TM criteria in Table A14.
A88
The
PELB Technical Circular provides guidelines for funding arrangements and
implementation of off-site ecological measures.
Sites of Special Scientific Interest
A89
There
are various legislative and regulatory controls in place for the conservation
of species and protection of the environment. Table 1.2 from HKPSG's Chapter 9: Environment
highlights "ecologically sensitive areas such as Sites of Special
Scientific Interest (SSSI) and areas with other particular vegetation and
wildlife habitat characteristics" as Environmental Factors influencing
Land Use Planning, and states that Nature Reserves and SSSI should be
adequately protected from the effects of pollution and from the diversion of
natural flows.
A90
The HKPSG also highlight the need for care
to be taken in planning and implementation of civil engineering construction
works to avoid, minimise or ameliorate the occurrence of pollution from silt,
oil and other sources on water bodies in unspoilt areas designated for
conservation and in SSSIs.
Wild Animals
A91
Wild
animals are protected by the Wild Animals
Protection Ordinance [Cap 170] (1980), which fall under the authority of
the Director of Agriculture and Fisheries. The latest version of Cap 170 is the
Second Schedule of the Wild Animals
Protection Ordinance [Cap 170] which has been reviewed in 1996. Protected
wild animals listed under the Schedule include mammals, all wild birds,
reptiles, amphibians and Troides helena
(a butterfly).
A92
The Animals and Plants (Protection of Endangered
Species) Ordinance (Cap. 187) controls the possession of any endangered
species and is designed to prohibit collection, import and export. In addition
there are measures which cover the retention, removal and replacement of trees
on development sites. The Wild Animals
Protection Ordinance (Cap. 170) is aimed mainly at hunters and collectors,
but does apply to this case under Section 5, "No person shall, except
in accordance with a special permit, take, remove, injure, destroy or wilfully
disturb a nest or egg of any protected wild animal."
Rare and Endangered Plant Species
A93
Various
species of plants are protected under the Forestry Regulations of the Forestry and Countryside Ordinance [Cap 96]
(1950) and Animals and Plants (Protection
of Endangered Species) Ordinance [Cap 187] (1976). The Forestry and Countryside Ordinance [Cap 96] and Forestry Regulations [Cap 96 Sub.
leg. A] were revised in 1993. The Animals
and Plants (Protection of Endangered Species) Ordinance [Cap 187] has been
revised in 1999.
A94
Regarding
the specific protection laws, all forests on government land are protected
under Hong Kong's Forests &
Countryside Ordinance. The law (Cap. 96, section 21), states that:
"Any person who, without lawful
authority or excuse, in any forest or plantation:-
(b) plucks
or damages any bud, blossom or leaf of any tree, shrub or plant;
(d) fells,
cuts, burns or otherwise destroys any trees or growing plants,
shall be guilty of an offence."
The law defines "forest"
to mean, "any area of Crown land covered with selfgrown trees."
Section 3 of the subsidiary Forestry Regulation is more specific and
provides a list of plants which are protected.
A95
Convention on Wetlands of International
Importance especially as Waterfowl Habitat - Ramsar, 2.2.1971 as amended by the
Protocol of 3.12.1982 and the Regina Amendments of 28.5.1987
"The Contracting Parties, recognising
the interdependence of Man and his environment; considering the fundamental
ecological functions of wetlands as regulators of water regimes and habitats
supporting a characteristic flora and fauna, especially waterfowl; being
convinced that wetlands constitute a resource of great economic, cultural,
scientific, and recreational value, the loss of which would be irreparable;
desiring to stem the progressive encroachment on and loss of wetlands now and
in the future; recognising that waterfowl in their seasonal migrations may
transcend frontiers and so should be regarded as an international resource;
being confident that the conservation of wetlands and their flora can be
ensured by combining far-sighted national policies with co-ordinated international
action; have agreed as follows:
Article 2 - 5. "Any Contracting
Party shall have the right ... because of its urgent national interests, to
delete or restrict the boundaries of wetlands already included by it in the
List and shall, at the earliest possible time, inform the organisation or
government responsible for the continuing bureau duties specified in Article 8
of any such changes."
Article 2 - 6. "Each
Contracting Party shall consider its international responsibilities for the
conservation, management and wise use of migratory stocks of waterfowl, both
when designating entries for the List and when exercising its right to change
entries in the List relating to wetlands in their territory."
Article 3 - 1. "The Contracting
Parties shall formulate and implement their planning so as to promote the
conservation of the wetlands included in the List, and as far as possible the
wise use*
of wetlands in their territory."
Article 3 - 2. "Each
Contracting Party shall arrange to be informed at the earliest possible time if
the ecological character or any wetland in its territory and included in the
List has changed, is changing or is likely to change as the result of
technological developments, pollution or other human interference."
Article 4 - 2. "Where a
Contracting Party in its urgent national interest, deletes or restricts the
boundaries of a wetland included in the List, it should as far as possible
compensate for any loss of wetland resources, and in particular it should
create additional nature reserves for waterfowl and for the protection, either
in the same area or elsewhere, of an adequate portion of the original
habitat."
Article 5. "The Contracting
Parties shall consult with each other about implementing obligations arising
from the Convention especially in the case of a wetland extending over the
territories of more than one Contracting Party or where a water system is
shared by Contracting Parties. They shall at the same time endeavour to
co-ordinate and support present and future policies and regulations concerning
the conversation of wetlands and their flora and fauna."
Bonn Convention
A96
Also
through the PRC, Hong Kong is a Party to the Convention on the Conservation of
Migratory Species of Wild animals (the Bonn
Convention). The Bonn Convention has two major objectives:
• to
provide strict protection for species listed in Appendix 1 of the
Convention (migratory species in danger of extinction throughout all or a
significant portion of their range); and
• to
encourage Range States for such species to conclude agreements for the
conservation and management of Appendix II species (migratory species
which have an unfavourable conservation status and require international
agreements for their conservation, or which have a conservation status which
would significantly benefit from international cooperation).
Tree Preservation
A97
Works Branch Technical Circular 24/94
(Planning, Environment and Lands Branch Circular 3/94) on Tree Preservation states that:
"The need to preserve trees
must be borne in mind particularly by those in charge of engineering,
architectural and landscape projects ..... There are many projects such as ...
service reservoirs, formation works and the like where virtually all trees and
shrubs within the works area boundary may have to be destroyed. In these cases
care should be taken to minimise the extent of the works area and thereby
maximise the number of trees to be preserved."
A98
The
most recent regulations and guidelines for tree preservation are contained in WBTC No. 24/94. Every effort should be
made to preserve trees in the planning, design and construction of development
projects (WBTC No. 24/94 para (4))
and, in general, permission to lop or cut down any tree will not be granted
unless good cause is shown (WBTC No.
24/94 Appendix A, para (3)).
A99
The
Director of Urban Services is the authority for felling or maintenance of trees
located within 5 m of the edge of a roadway. The Director of Lands is the Land
Authority, therefore applications for felling are submitted through the DLO.
For government projects, a tree felling application shall be submitted to DLO
after D of A&F or DUS has expressed no objection to felling (WBTC No. 24/94 Appendix B, para E(2)).
Whenever possible, permission should be sought 12 months in advance so that
root systems can be prepared for transplant if appropriate (WBTC No. 24/94 Appendix A, para E(3)).
Trees that are less than 95 mm DBH presumably are protected under Forestry and Countryside Ordinance, and
felling requires permission from D of A&F.
A100
The relevant
guidelines for felling permission for this project are as follows (paraphrased
from WBTC No. 24/94 Appendix B para
(C)):
1. irreplaceable
rare tree species are not involved;
2. felling
would not cause serious environmental impact;
3. genuine
development need to fell exists, which cannot be reasonably overcome;
4. compensatory
landscaping/replanting to Government's satisfaction will be undertaken;
5. the
tree is not an unusually large or fine example;
6. the
tree is in poor condition.
Felling Application Procedure
A101
After
D of AF&C or D of LCS has expressed no objection to felling, works
department shall submit tree feeling application to DLO.
A102
Applications
shall be accompanied by:
1. two
copies of a tree survey plan, showing accurate location of the tree(s), height,
circumference, tree spread to scale. Plans should include trees to be retained,
transplanted, and felled, existing levels in the vicinity of each tree, and
future proposals (outline of road, formation and finished levels);
A103
2. a
tree schedule, including botanical name, height, circumference of the trunk,
tree spread, and condition;
3. photographs
4. compensatory
landscaping/replanting plan to which an undertaking will be tied.
Replanting Plans
A104
Tree
species selected for replanting in areas where felling cannot be avoided should
retain the amenity value as well as improve the ecological value of the
affected area if possible. Amenity value is increased with trees that provide
shade, ability to screen out poor views, fragrance or colour of leaves or
blossoms. Ecological value can be improved in several ways. One improvement is
to plant native species of trees with fruit or seeds useful as food for birds.
Another is to increase the diversity of an area by planting a variety of native
species. Diversity can be similarly increased by planting trees that will
attain various heights, giving a multi-layered canopy.
A105
Some
factors to be considered in the selection of roadside trees in urban areas of
Hong Kong (Webb 1991) are:
a) pollution
tolerance;
b) drought
tolerance;
c) tolerant
of compacted or heavy soil;
d) resistant
to typhoon damage (no brittle branches);
e) straight
trunk to 3-4 m; and
f) non-toxic
fruit or leaves.
Conservation Area - Buffer Zones
A106
In 1995 the Government created
two Buffer Zones around Deep Bay. Buffer Zone 1 occupied an area of 948
ha and new development within this zone was not allowed unless it was required
to support the conservation of the area's natural features and scenic qualities.
In Buffer Zone 2 (1027 ha), new development was not considered unless
the applicant could demonstrate the proposed development would have insignificant
impact on environment, ecology, drainage, sewerage and traffic in the area
including the MPNR and Inner Deep Bay. Any development is also subject to
the more detailed Outline Zoning Plans (1994)
[1]
. More recently, these buffer zones have been modified
through the recommendation of the “Study on the Geological Value of Fish Ponds
in the Deep Bay Area”, resulting in the creation of the Wetland Conservation
Area (WCA) and Wetland Buffer Area (WBA). These are shown in Figure
A1.1. The planning intention of the WCA is to conserve the ecological
value of the fishpond area which forms an integral part of the wetland system
in the Deep Bay Area.
A107
The
WCA and WBA have been adopted in the Town Planning Board Guidelines for
Application of Developments within Deep Bay Area under Section 16 of the Town
Planning Ordinance (TPB PG-No. 12B April 1999).
A108
In
considering development proposals in the Deep Bay Area, the Board adopts the
Fish Pond Study’s recommended principle of “no-net-loss in wetland” which
provides for the conservation of continuous and adjoining fish ponds. The
no-net-loss can refer to both loss in “area” and ‘function”.
A109
TPB PG
No 12B states that new development within the WCA should not be allowed unless
it is required to support the conservation of the ecological value of the area
or if the development is an essential infrastructural project with overriding
public interest. In the latter case, an ecological assessment is required to
demonstrate that it will not result in a net loss of wetland function or
negative disturbance impacts. Wetland compensation is required for any
development requiring pond filling and mitigation measures against disturbance
are also required.
PRC Relevant Statutes and Bilateral Migratory Bird Agreements
Wildlife Protection Law of the PRC
A110
According
to Chapter 2 Provision 12 an environmental impact assessment should be
submitted by the developer for construction projects which potentially result
in adverse impacts on wildlife habitat protected by national or local
regulations. In the approval process the Environmental Protection Department
should consult the wildlife protection agencies at the same administrative level.
PRC Wildlife Protection Implementation Regulations
A111
According
to Chapter 2 Provision 10 preventative measures should be taken by
relevant institutions and individuals to preclude potential risk of adverse
impacts on wildlife protected by national or local regulations.
PRC Guidelines for Nature Reserves for Forests and Wildlife Species
A112
According
to Provision 11 the natural environment and natural resources in nature
reserves should be managed solely by the administrative organization of nature
reserves. Without permission of the Ministry of Forestry or the provincial,
autonomous regional, or municipal administrative department of forests no
institution or individual is allowed to enter the nature conservation area to
establish institutions or construct facilities.
PRC Nature Reserve Regulations, Provision 32
A113
Any
construction facility is prohibited in core areas and buffer zones of nature
reserves. Construction facilities which may cause environmental pollution,
resource destruction, or landscape damage in the experimental areas are also
inhibited; pollutants discharged from other construction projects in the
experimental areas should obey national or local standards. Time tables should
be set up for effluent control for those existing facilities or in the
experimental area if the effluents discharged exceed national or local
standards; mitigation measures must be taken for any damage.
A114
Other
construction projects surrounding nature reserves should not damage the
environmental quality of nature reserves; any damage must be rectified within a
definite time.
A115
Time
tables for the rectification will be set up by appropriate administrations
authorized by relevant laws and regulations. The responsible enterprises and
institutions must accomplish rectification within the specified time.
The National Protection List of Important Wild Animals
A116
The
following mammals which occur in the Shenzhen River catchment and Deep Bay area
are listed among species to be protected in PRC (first class protection species
are marked with *).
Otter Lutra
lutra
Small Indian Civet Viverricula
indica
Chinese White Dolphin Sousa
chinesis
A117
The
following birds which occur in the Shenzhen River catchment and Deep Bay are
listed among species to be protected in PRC (first class protection species are
marked with *).
Black-necked Grebe Podiceps
nigricollis
Dalmatian Pelican Pelecanus
(philippensis) crispus
Reef Egret Egretta
sacra
Swinhoe's Egret Egretta
eulophotes
Oriental White Stork* Ciconia
(ciconia) boyciana
Black Stork* Ciconia
nigra
White Ibis Threskiornis
(aethiopicus)
melanocephalus
Glossy
Ibis Plegadis
falcinellus
White Spoonbill Platalea
leucorodia
Black-faced Spoonbill Platalea
minor
Swan Cygnus
sp.
Mandarin Duck Aix
galericulata
Common Crane Grus
grus
Imperial Eagle* Aquila
heliaca
Black-shouldered Kite Elanus
caeruleus
Black Kite Milvus
migrans
White-bellied Sea Eagle Haliaeetus
leucogaster
Crested Goshawk Accipiter
trivirgatus
Marsh Harrier Circus
aeruginosus
Hen Harrier Circus
cyaneus
Pied Harrier Circus
melanoleucos
Japanese Sparrowhawk Accipiter
gularis
Besra Accipiter
virgatus
Horsfield's Goshawk Accipiter
soloensis
Grey-faced Buzzard-eagle Butastur
indicus
Buzzard Buteo
buteo
Spotted Eagle Aquila
clanga
Bonelli's Eagle Hieraaetus
fasciatus
Crested Honey Buzzard Pernis
ptilorhnychus
Serpent Eagle Spilornis
cheela
Osprey Pandion
haliaetus
Kestrel Falco
tinnunculus
Peregrine Falco
peregrinus
Hobby Falco
subbuteo
Saker Falcon Falco
cherrug
Little Whimbrel Numenius
(borealis) minutus
Spotted Greenshank Tringa
guttifer
Relict Gull* Larus
relictus
Greater Coucal Centropus
sinensis
Lesser Coucal Centropus
bengalensis
Rose-ringed Parakeet Psittacula
krameri
Short-eared Owl Asio
flammeus
Grass Owl Tyto
capensis
White-vented Needletail Hirundapus
cochinchinensis
A118
The
following reptiles which occur in the Shenzhen River catchment and Deep Bay are
listed among species to be protected in PRC.
Water Monitor Varanus
salvator
Burmese Python Python
molurus
Bilateral Migratory Bird Agreements
`Agreement between the Government of Australia and the Government of the
People's Republic of China for the Protection of Migratory Birds and their
Environment'
and
`Agreement on the Protection of Migratory Birds and Their Habitats by
the Governments of Japan and the People's Republic of China'
A119
China
has entered into a number of bilateral agreements to protect migratory birds.
These include agreements with both Japan and Australia. Birds passing through
the Deep Bay area are known to migrate to/from both of these countries (see,
for example: Melville, D.S. and Galsworthy, A.C. 1993. Report on bird ringing
in Hong Kong in 1992. Hong Kong Bird
Report 1992:81-99) and thus these agreements are relevant in the context of
this study. A list of birds occurring in the Deep Bay area protected under
bilateral migratory bird agreements between China and Australia/Japan is given
below.
Birds occurring in the Deep Bay area
protected under bilateral migratory bird agreements between China and
Australia/Japan:
Black-necked
Grebe |
Podiceps nigricollis |
J |
|
|
Great Crested
Grebe |
Podiceps cristatus |
AJ |
|
|
Lesser
Frigatebird |
Fregata ariel |
AJ |
|
|
Bittern |
Botaurus stellaris |
J |
|
|
Cattle Egret |
Bubulcus ibis |
J |
|
|
Reef Egret |
Egretta sacra |
AJ |
|
|
Great Egret |
Egretta alba |
AJ |
|
|
Yellow Bittern |
Ixobrychus sinensis |
AJ |
|
|
Schrenck's
Bittern |
Ixobrychus eurhythmus |
J |
|
|
Little Green
Heron |
Butorides striatus |
J |
|
|
Intermediate
Egret |
Egretta intermedia |
J |
|
|
Night Heron |
Nycticorax nycticorax |
J |
|
|
Purple Heron |
Ardea purpurea |
J |
|
|
Black Stork |
Ciconia nigra |
J |
|
|
Glossy Ibis |
Plegadis falcinellus |
A |
|
|
White Spoonbill |
Platalea leucorodia |
J |
|
|
Black-faced
Spoonbill |
Platalea minor |
J |
|
|
Ruddy Shelduck |
Tadorna ferruginea |
J |
|
|
Shelduck |
Tadorna tadorna |
J |
|
|
Pintail |
Anas acuta |
J |
|
|
Teal |
Anas acrecca |
J |
|
|
Baikal Teal |
Anas formosa |
J |
|
|
Falcated Teal |
Anas falcata |
J |
|
|
Mallard |
Anas platyrhychos |
J |
|
|
Gadwall |
Anas strepera |
J |
|
|
Wigeon |
Anas penelope |
J |
|
|
Garganey |
Anas querquedula |
AJ |
|
|
Shoveler |
Anas clypeata |
J |
|
|
Common Pochard |
Aythya ferina |
J |
|
|
Baer's Pochard |
Aythya baeri |
J |
|
|
Tufted Duck |
Aythya fuligula |
J |
|
|
Scaup |
Aythya marila |
J |
|
|
Red-breasted
Merganser |
Mergus serrator |
J |
|
|
White-bellied
Sea-eagle |
Haliaeetus leucogaster |
A |
|
|
Marsh Harrier |
Circus japonica |
J |
|
|
Hobby |
Falco subbuteo |
J |
|
|
Watercock |
Gallicrex cinerea |
J |
|
|
Moorhen |
Gallinula chloropus |
J |
|
|
Pheasant-tailed
Jacana |
Hydrophasianus chirurgus |
A |
|
|
Painted Snipe |
Rostratula benghalensis |
AJ |
|
|
Little Ringed
Plover |
Charadrius dubius |
A |
|
|
Ringed Plover |
Charadrius hiaticula |
A |
|
|
Lesser Sand
Plover |
Charadrius mongolus |
AJ |
|
|
Greater Sand
Plover |
Charadrius leschenaultii |
AJ |
|
|
Oriental Plover |
Charadrius veredus |
A |
|
|
Lapwing |
Vanellus vanellus |
J |
|
|
Grey Plover |
Pluvialis squatarola |
A |
|
|
Pacific Golden
Plover |
Pluvialis fulva |
AJ |
|
|
Little Whimbrel |
Numenius (borealis) minutus |
A |
|
|
Whimbrel |
Numenius phaeopus |
J |
|
|
Curlew |
Numenius arquata |
AJ |
|
|
Australian Curlew |
Numenius madagascariensis |
AJ |
|
|
Black-tailed
Godwit |
Limosa limosa |
AJ |
|
|
Bar-tailed Godwit |
Limosa lapponica |
AJ |
|
|
Spotted Redshank |
Tringa erythropus |
J |
|
|
Redshank |
Tringa totanus |
AJ |
|
|
Marsh Sandpiper |
Tringa stagnatilis |
AJ |
|
|
Greenshank |
Tringa nebularia |
AJ |
|
|
Green Sandpiper |
Tringa ochropus |
J |
|
|
Wood Sandpiper |
Tringa glareola |
AJ |
|
|
Nordmann's
Greenshank |
Tringa guttifer |
J |
|
|
Common Sandpiper |
Tringa hypoleucos |
AJ |
|
|
Grey-rumped
Sandpiper |
Tringa brevipes |
AJ |
|
|
Terek Sandpiper |
Xenus cinereus |
AJ |
|
|
Turnstone |
Arenaria interpres |
AJ |
|
|
Swinhoe's Snipe |
Gallinago megala |
AJ |
|
|
Pintail Snipe |
Gallinago stenura |
A |
|
|
Common Snipe |
Gallinago gallinago |
J |
|
|
Woodcock |
Scolopax rusticola |
J |
|
|
Asiatic Dowitcher |
Limnodromus semipalmatus |
A |
|
|
Red Knot |
Calidris canutus |
AJ |
|
|
Great Knot |
Calidris tenuirostris |
AJ |
|
|
Red-necked Stint |
Calidris ruficollis |
AJ |
|
|
Long-toed Stint |
Calidris subminuta |
AJ |
|
|
Temminck's Stint |
Calidris temminckii |
J |
|
|
Sharp-tailed
Sandpiper |
Calidris acuminata |
AJ |
|
|
Dunlin |
Calidris alpina |
AJ |
|
|
Curlew Sandpiper |
Calidris ferruginea |
AJ |
|
|
Sanderling |
Calidris alba |
AJ |
|
|
Spoon-billed
Sandpiper |
Eurynorynchus pygmaeus |
J |
|
|
Broad-billed
Sandpiper |
Limicola falcinellus |
AJ |
|
|
Ruff |
Philomachus pugnax |
AJ |
|
|
Black-winged
Stilt |
Himantopus himantopus |
J |
|
|
Avocet |
Recurvirostra avosetta |
J |
|
|
Red-necked
Phalarope |
Phalaropus lobatus |
AJ |
|
|
Grey Phalarope |
Phalaropus fulicarius |
AJ |
|
|
Oriental
Pratincole |
Glareola maldivarum |
AJ |
|
|
Common Gull |
Larus canus |
J |
|
|
Herring Gull |
Larus argentatus |
J |
|
|
Slaty-backed Gull |
Larus schistisagus |
J |
|
|
Black-headed Gull |
Larus ridibundus |
J |
|
|
Black-legged
Kittiwake |
Rissa tridactyla |
J |
|
|
Common Tern |
Sterna hirundo |
AJ |
|
|
Little Tern |
Sterna albifrons |
AJ |
|
|
Ancient Auk |
Synthliboramphus antiquus |
J |
|
|
Oriental Cuckoo |
Cuculus saturatus |
AJ |
||
Short-eared Owl |
Asio flammeus |
J |
||
White-throated
Needletail |
Hirundapus caudacutus |
AJ |
||
Pacific Swift |
Apus pacificus |
AJ |
||
Little Swift |
Apus affinis |
J |
||
Sand Martin |
Riparia riparia |
J |
||
Barn Swallow |
Hirundo rustica |
AJ |
||
Red-rumped
Swallow |
Hirundo daurica |
AJ |
||
Asian House
Martin |
Delichon dasypus |
J |
||
Forest Wagtail |
Dendronanthus indicus |
J |
||
Yellow Wagtail |
Motacilla flava |
AJ |
||
Citrine Wagtail |
Motacilla citreola |
AJ |
||
White Wagtail |
Motacilla alba |
AJ |
||
Richard's Pipit |
Anthus richardi |
J |
||
Olive-backed
Pipit |
Anthus hodgsoni |
J |
||
Pechora Pipit |
Anthus gustavia |
J |
||
Red-throated
Pipit |
Anthus cervinus |
J |
||
Water Pipit |
Anthus spinoletta |
J |
||
Ashy Minivet |
Pericrocotus divaricatus |
J |
||
Tiger Shrike |
Lanius tigrinus |
J |
||
Brown Shrike |
Lanius cristatus |
J |
||
Black-naped
Oriole |
Oriolus chinensis |
J |
||
Chestnut-cheeked
Starling |
Sturnus philippensis |
J |
||
Red-tailed Robin |
Luscinia sibilans |
J |
||
Siberian
Rubythroat |
Luscinia calliope |
J |
||
Siberian Blue
Robin |
Luscinia cyane |
J |
||
Red-flanked
Bluetail |
Tarsiger cyanurus |
J |
||
Daurian Redstart |
Phoenicurus auroreus |
J |
||
Stonechat |
Saxiocola torquata |
J |
||
Siberian Thrush |
Zoothera sibiricus |
J |
||
White's Thrush |
Zoothera dauma |
J |
||
Grey-backed
Thrush |
Turdus hortulorum |
J |
||
Grey Thrush |
Turdus cardis |
J |
||
Pale Thrush |
Turdus pallidus |
J |
||
Eye-browed Thrush |
Turdus obscurus |
J |
||
Dusky Thrush |
Turdus naumanni |
J |
||
Short-tailed Bush
Warbler |
Urosphena squameiceps |
J |
||
Middendorf's
Grasshopper Warbler |
Locustella ochotensis |
J |
||
Lanceolated
Warbler |
Locustella lanceolata |
J |
||
Great Reed
Warbler |
Acrocephalus orientalis |
AJ |
||
Black-browed Reed
Warbler |
Acrocephalus bistrigiceps |
J |
||
Yellow-browed
Warbler |
Phylloscopus inornatus |
J |
||
Arctic Warbler |
Phylloscopus borealis |
AJ |
||
Pale-legged Leaf
Warbler |
Phylloscopus tenellipes |
J |
||
Eastern Crowned
Warbler |
Phylloscopus coronatus |
J |
||
Yellow-rumped
Flycatcher |
Ficedula zanthopygia |
J |
||
Narcissus Flycatcher |
Ficedula narcissina |
J |
||
Mugimaki
Flycatcher |
Ficedula mugimaki |
J |
||
Blue-and-White
Flycatcher |
Cyanoptila cyanomelana |
J |
||
Sooty Flycatcher |
Muscicapa sibirica |
J |
||
Grey-streaked
Flycatcher |
Muscicapa griseisticta |
J |
||
Brown Flycatcher |
Muscicapa latirostris |
J |
||
Japanese Paradise
Flycatcher |
Terpsiphone atrocaudata |
J |
||
Ruddy Sparrow |
Passer rutilans |
J |
||
Brambling |
Fringilla montifringilla |
J |
||
Siskin |
Carduelis spinus |
J |
||
Black-tailed
Hawfinch |
Eophona migratoria |
J |
||
Yellow-breasted
Bunting |
Emberiza aureola |
J |
||
Black-faced Bunting |
Emberiza spodocephala |
J |
||
Japanese Yellow
Bunting |
Emberiza sulphurata |
J |
||
Chestnut-eared
Bunting |
Emberiza fucata |
J |
||
Rustic Bunting |
Emberiza rustica |
J |
||
Little Bunting |
Emberiza pusilla |
J |
||
Tristram's
Bunting |
Emberiza tristrami |
J |
||
Pallas's Reed
Bunting |
Emberiza pallasi |
J |
||
Reed Bunting |
Emberiza schoeniclus |
J |
||
A120
These
species are listed under:
(A) Agreement
between the Government of Australia and the Government of the People's Republic
of China for the Protection of Migratory Birds and Their Environment, and
(J) Agreement
on the Protection of Migratory Birds and Their Habitats by the Governments of
Japan and the People's Republic of China.
The Management Measures for Forests of Guangdong Province, Section 26
A121
Natural
reserves should be protected. Permission of relevant authorities is required
for any special-aimed use of the resources within natural reserves.
The Environmental Management Regulations for Construction Projects in
Guangdong Province, Section 4
A122
Any
decision on construction projects including their identification, layout, and
siting should meet the environmental planning requirements. Consideration
should be given to protecting and to enhancing the environmental quality of the
whole area. Construction of projects which will cause environmental pollution
and ecological damage to water source protection zones, natural reserves, and
other special protection areas is prohibited.
Guangdong Provincial Implementary Detailed Regulations for Natural
Reserves of Forest and Wildlife Species, Section 12
A123
Natural
environment and resources within the natural reserves should be managed by the
administrative organization of nature reserves. Establishment of institutes or
facilities is prohibited without approval of the Ministry of Forestry or the
provincial authority of forest management.
Non
Statutory Guidelines
Deep Bay Guidelines for Dredging, Reclamation and Drainage Works
A124
The Deep Bay Guidelines for Dredging,
Reclamation and Drainage Works (DBG) published by ERL (Asia) Ltd in
association with Binnie Consultants Ltd for EPD in 1991, defines a large area
of Inner Deep Bay and its coastal regions as a Special Measures Zone (SMZ). It
encompasses the area within and bounded by Buffer Zone 2.
A125
Recommendations
on acceptable noise levels, sediment quality, water quality and air quality
were made for locations within this zone in order to protect the scientific,
educational and amenity interest of the SMZ.
A126
The
recommended guidelines for water quality, noise level and air quality within
the SMZ are given in the DBG. These guidelines, however, are non-statutory and
in some instances are now outdated. However, the spirit of the DBG should be
retained where construction works are undertaken close to Deep Bay as it was
designed to protect the sensitive ecology of the area.
A127
The
purpose of the DBG is to provide Government project sponsors and construction
contractors with general guidance on issues of:
• site
selection;
• work
methods;
• environmental
site investigation needs;
• environmental
constraints, criteria and monitoring requirements;
• design
procedures, including assessment of impacts and selection of mitigation
measures; and
• special
conditions of contract and performance specifications to be applied to Deep Bay
projects.
A128
Environmental
constraints contained in the Deep Bay Guidelines which may be relevant to this
project include:
• noise
level limits for construction work; and
• measures
for minimizing disturbance to wildlife in the area.
Table A.15
Deep Bay Guidelines -
Noise Level Limits for Construction Works Area,
Just Outside the Inner
Deep Bay Special Measures Zone
Time Period |
Acceptable Noise Level (dB(A))(1) |
Weekdays 0700-1900 hours (2) |
75 |
Weekdays 1900-2300 hours |
60 |
General Holidays (including
Sundays) 0700-2300 hours |
60 |
All Days, 2300-0700 hours |
45 |
(5 min.) Leq
measured at the building facade of a Noise Sensitive Receiver (NSR). (2) Alternative
limit for weekdays, 0700-1900 hours, is 10 dB(A) above the ambient noise
level (measured as 1-hour L90 dB(A)). |
Table A.16
Deep Bay Guidelines –
Noise Level Limits for Construction Works
within Inner Deep Bay
Special Measures Zone
Time Period |
Acceptable Noise Level (dB(A))(1) |
All Days, 0700-2300 hours(2) All Days, 2300-0700 hours |
60 45 |
Leq 5 min.
measured freefield, 100 m from the site boundary. (2) Alternative
limit for weekdays, 0700-1900 hours, is 5 dB(A) above the ambient noise level
(measured as 1-hour L90 dB(A)). |
Table A.17
Deep Bay Guidelines - Air Quality Objectives
for Deep Bay Catchment
Concentration (Fg/m3)
for Different Averaging Times (i) |
||||
|
1 hr (ii) |
8 hr (iii) |
24 hr (iii) |
1 yr (iv) |
SO2 |
350-500 |
|
150 |
80 |
TSP (v) |
|
|
180 |
80 |
RSP (v) |
|
|
110 |
55 |
NO2 |
300 |
|
150 |
80 |
CO |
30,000 |
10,000 |
|
|
O3 |
200 |
100-120 |
|
|
Lead |
|
|
1.5 |
|
Measured at 298oK
and 101.325 kPa (one atmos). Not to be
exceeded more than 3 times per year. Not to be
exceeded more than once per year. Arithmetic means. TSP = Total
Suspended Particulates RSP = Respirable
Suspended Particulates. |
* The
wise use of wetlands concept is defined, in Appendix 9 of the Ramsar Convention
Manual, as: "their sustainable utilisation for the benefit of human kind
in a way compatible with the maintenance of the natural properties of the
ecosystem".