3.                  Constraints on design

 

3.1              Engineering

 

The engineering design is principally the means to control water levels to close tolerances in this largely flat area, with a minimum of mechanical assistance. Construction must not be disruptive to the surrounding habitat. In addition, the ground in which the ponds are located comprises a significant depth of mud, such that moderate surcharge loads could cause significant short and long term settlement.  This must be guarded against in the construction of the mitigation area.

 

3.2              Hydrology / Drainage

 

3.2.1        The main constraint on the design of the wetland mitigation scheme is the highly seasonal rainfall in Hong Kong. Typically there is a period of water deficit (i.e. rainfall is exceeded by evapotranspiration) from September to March. Without an additional source of water it is not normally possible, to maintain permanent shallow wetlands, such as those required in the marshland mitigation area. Permanent wetlands may be retained by storing sufficient water to overcome the deficit period, but such wetlands are then inundated by water which is too deep for many of the wetland target species over the much of the annual cycle.

 

3.2.2        Potential water sources include the local watercourses, but these are highly polluted (see below) and / or underlying aquifers. Due to the presence of marble caverns in the underlying rocks in the Lok Ma Chau area, boreholes are not allowed in the area for engineering safety reasons. It is also possible that any underlying aquifers may be brackish.

 

3.2.3        There are no data currently available on groundwater levels within or nearby the mitigation areas. Therefore it is not known whether the proposed wetland areas would be potentially subject to water inputs or losses. Further site investigation data are awaited before this can be evaluated.

 

3.2.4        There are also potential constraints on the wetland design regarding drainage options as a result of the tidal conditions of the water courses and frequent local flooding. The top of the bunds in the area are generally at +3.5mPD and in periods of heavy rain there is flooding in the area. This will be alleviated with the construction of the San Tin Eastern Main Drainage Channel, which will protect the locality from upstream events. The ponds will not flood as frequently as has been the case to date. Rainfall intensities greater than that of the annual event will likely cause the ponds to be inundated due to high watercourse levels.

 


3.2.5        The outfall into the channel which receives run-off from the station roof must not cause this channel to be over capacity. The channel has been sized to allow for a 1 in 200 year event.

 

3.2.6        The outfall to the natural watercourse which provides drainage for the area is tidal. Constructing an outfall will be difficult, and the watercourse banks and bed would have to be protected from erosion. Any collapse of the bank or loss of cross section will make the area more susceptible to flooding. An outfall into this watercourse would require a flap valve. If this were to become wedged open with debris, the tidal range could send saline water into the pond system. In view of this all water will be need to be taken to the watercourse to the east of site (Watercourse B).

 

3.3              Soils

 

3.3.1        As described in Section 1.4 the soils present at the site consist of poorly drained marine clays. These are sufficiently impermeable to maintain wetland conditions or fish ponds over the site as demonstrated by the current presence of such habitats, which are in the main solely maintained by direct rainfall inputs.

 

3.3.2        The soils are, however, acid sulphate soils which can lead to highly acidic conditions when these are disturbed and dried. Nevertheless vegetation such as Phragmites does spontaneously recover on fishpond bunds and therefore the maintenance of basic vegetation cover is unlikely to be constrained. However, care with soil handling or remedial measures (e.g. application of lime) may be needed to establish more sensitive and diverse wetland vegetation of high ecological value within the marsh areas of the site.

 

3.4              Water Quality

 

3.4.1        Information on the water quality in the smaller channels flowing through or adjoining the site is not available. However, it is likely that these water courses contain water with highly polluted eutrophic water similar to other channels in the area.

 

3.4.2        The use of nutrient rich water in maintaining wetland conditions may be helpful in raising productivity levels in wetlands, thereby maintaining levels of food resource for target species. However, it is considered that the hyper-eutrophic conditions of the nearby water courses, especially during low flows, when the additional water supply is most critical, are too poor for these sources to be suitable for the target wetland habitats and many of the target species.

 

3.4.3        The maintenance of wetlands conditions and achievement of target water levels will therefore be dependent on the storage of direct rainfall.


3.5              Access

 

3.5.1        Access to the edge of the mitigation area may be gained by the service road to the Lok Ma Chau station. However, access to other areas of the fish ponds and other parts of the mitigation area will only be possible by the fish pond bund tracks. These vary in width and their capacity for supporting heavy or large vehicles such as earth moving plant.

 

3.5.2        The site is within the Closed Border Area.

 

3.6              Adjacent Habitats / Land-uses

 

3.6.1        The area is mostly surrounded by fish ponds that are contiguous with those of the Inner Deep Bay Ramsar site and MPNR. To the north the area is bounded by the Shenzhen River. These habitats / land uses provide no constraints on the proposed wetland mitigation.

 

 

4.                  Detailed design and construction methods

 

4.1              Overview

 

4.1.1        The mitigation area will consist of two main habitats: fishponds (most of which will be under active traditional fish pond management) and a new area of created marshland with a mixture of wetland vegetation and open water pools (see Figure 4.1).

 

4.1.2        The fish pond area currently consists of 22 existing fishponds, 7 of which will be joined to create larger ponds (because these are favoured by many water birds): Ponds 3, 6, 8, 9, 10, 13 and 14.

 

4.1.3        The ponds (1 – 15) within the fish pond compensation area will be managed as a mixture of active fish pond, shallow lakes, naturally regenerated marsh and reedbed.

 

§                     Ponds 1 and 2 will be managed to create moderate-shallow rain-fed lakes primarily as duck habitat.

 

§                     Pond 5 will be maintained as a reedbed with open pools.

 

§                     Pond 12 will be maintained as a shallow marsh, with managed naturally regenerated vegetation.

 

4.1.4        All other ponds will be used in a 3-year rotational sequence of fish farming  / shallow set-aside ponds (with no fish stocking). Thus approximately 1/3 of ponds will be set-aside from production  in any one year, one of which will be used as a contingency reservoir pond.


4.2              Land Form

 

Fish Ponds

 

4.2.1        As the area already consists of fish ponds the mitigation works would be restricted to the modification of existing ponds, rather than construction of new ponds. These modifications will consist of the joining of ponds to reduce enclosure effects and to provide shallow margins and islands (Figure 4.1).

 

4.2.2        Where ponds are joined the bund material currently separating them will be lowered and side cast to create shallow sloping margins to islands and / or shoals as well as interconnecting channels. This will create additional areas of muddy shallows that will provide suitable feeding areas for herons, egrets, spoonbills and, during low water levels, smaller wading birds. The levels to be attained on each modified bund are indicated in Figure A3.1a in Appendix 3.1.

 

4.2.3        The purpose of reprofiling the selected pond bunds is to create as shallow a slope as feasible (given the properties of the bund materials) between the Initial Operating Level (IOL) and Maximum Operating Levels (MOL) and over the range of the Low Operating Levels (LOL; see Table 5.1).

 

4.2.4        To facilitate vehicle access to all parts of the site, for water level management and other activities, some works on the remaining bunds will be necessary.  The tops of the bunds may require some vegetation clearance and strengthening with a geofabric to enable them to be used as accessways. Current practice is to use some stone fill to form the running surface and it is proposed to extend this where necessary.

 

4.2.5        The work to lower the bund between ponds 13a and 13b will require the removal of some electricity poles.

 

4.2.6        Consideration will be given to the use of earth covered floating platforms seeded with Paspalum distichu.  These could be placed in each operating fish pond to provide additional foraging areas for herons and egrets etc and potential breeding sites for some water birds (such as Little Grebe) as well as shelter for fish and aquatic invertebrates.

 

Marshland

 

4.2.7        The marsh area around the station will principally consist of a shallow basin sloping gradually away from the station buildings, to produce a zoned wetland with drier terrestrial habitats on the upper slopes and permanent wet marshland  and pools at the lower end (see Figure 4.2).

4.2.8        A clay curtain will be placed at locations where tranverse flows from the marsh could take place, causing a loss of water.  Levels will be controlled by adjustable sluices, whilst the addition of water will generally be by a small pump.

 

4.2.9        A feature of this area is the likely consolidation of ground if it is surcharged over and above current pressures, and the length of time taken to achieve ultimate consolidation. This has a bearing on the design of the water control structures and the fill levels during construction. For example, draining and filling a pond to the top of the bund is likely to lead to a settlement of the order of 500 mm. Whilst the first 300 mm ma take place in the first month, after 10 years the settlement would be 420 mm. To overcome this movement there are three options:

 

                       A significant initial surcharge to achieve faster consolidation

                       The installation of vertical drains to accelerate consolidation

                       Design of the fill and water control structures to allow for the long term consolidation.

 

4.2.10    Of these three, the last option will be implemented with the first item depending on the availability of excess materials arising from the construction of Lok Ma Chau StationTerminus.

 

4.2.11    After completion of the site formation, according to the design drawings and specifications described above, further site formation works will be carried out to provide fine scale modifications to the topography, e.g. creation of uneven edges to ditches, small pools (0.5 m deep) and hummocks and variations in slopes, to increase structural diversity across each mitigation area. These works will be directed by an on-site wetland habitat creation ecologist.

 

4.3              Soils

 

4.3.1        It is assumed that ground water levels will be sufficiently low during the dry season that all of the wetland mitigation areas will potentially subject to water losses through seepage. It is therefore essential that the loss of water through seepage is kept at negligible levels. Within the entire mitigation area it is assumed that seepage is within acceptable levels as the long term persistence of fish ponds indicate that rainfall and water retention is adequate to maintain fish production without the requirements for external water supplies (see Section 1.4).

 

4.3.2        As described above, the existing pond clays in the marshland area will be overlain with a layer of imported sand (see above) as a surcharge and to bring the marsh up to its required levels. Water will readily permeate this layer but will be held within the wetland mitigation area by the clays underlying the ponds and in the existing pond bunds.

4.3.3        Within the marshland area the sand layer will be overlain with a layer of top soil as required to raise the ground levels to those indicated in the land formation plan (Figure 4.2). The soils will consist of a mix of pond bund material, sand and completely decomposed granite as described in the specification provided in Appendix 3.2.

 

4.4              Water Control Structures

 

Fish Ponds – Wet Season Controls

 

4.4.1        The engineering inputs to the LMC ponds are principally to install a water management system and to provide access for management. The proposed water management system comprises an arterial pipe system to transfer water between ponds in the dry season when the major draining down will take place, plus a series of adjustable sluices to allow fine control of water levels in the wet season (Figure 4.1). The sluices would automatically allow through excess water from a group of ponds to the lowest pond in the group, from where it will be pumped to a watercourse. The pump will be located in a manhole constructed in the bund; Appendix 3.3 refers.

 

4.4.2        Current practice is to drive small vehicles around the ponds, and this will be the case under the new regime. The vehicles will transport the pump and other small equipment.

 

4.4.3        A bridge over the watercourse to gain access to Ponds 1 and 2 will be constructed to carry a pipe to remove excess water from these ponds. The bridge superstructure, which will be constructed in timber, will be founded on a hollow concrete structure. There will be no access for personnel across the bridge – Figure 4.3 refers.

 

4.4.4        All wood structures will be designed to BS 5268 Part 2 and treated in accordance with the recommendations of BS 5268 Part 5.

 

4.4.5        The excess water drainage facility comprises a catchpit with an adjustable weir, and pipe through the bund to the receiving pond. A difference in waterlevels between ponds of 200 to 300 mm is necessary to ensure this can operate. Draining of the ponds is likely for the construction of these elements.


4.4.6        To drain wet season excess water from the ponds at low operating levels, they will be grouped as follows:

 

           Group 1           Ponds 9b, 9a, 6b, 6a, 3b: 3a

           Group 2           Ponds 4, 7: 8b: 11: 8a

           Group 3a          Ponds 10b, 10a: 13b: 13a

           Group 3b         Ponds 14a, 14b: 15     

 

4.4.7        For one year in 3 a group will be at low operating level, with rotation of groups on a 3 year cycle. Ponds in a group separated by commas flow one to the other to reach the collection pond. The last pond (in bold) in each group is drained by pumping. All other ponds drain by pipes and weirs.

 

4.4.8        The same groupings apply in the years when the ponds are at normal operating levels, but with different collection ponds. These are the pond numbers which are underlined.

 

4.4.9        The water management system is based on a uPVC pipe system buried in the bunds, which is also carried by the bridge.

 

            Fish Ponds – Dry Season Controls

 

4.4.10    In the dry season water can be a scarce commodity, and the operation of the ponds requires that a considerable quantity of water can be transferred from pond to pond in a relatively short time. It is assumed that drain down from one pond/filling of the receiving pond should take approximately one week. Interim storage in a reservoir is not considered to be feasible. On this basis the maximum weekly flow is approximately 20,000 m3 a week, or around 80 litres/second assuming daytime operation for six days of the week. Flows will be in opposite directions according to need.

 

4.4.11    This is a significant quantity of water. There are two options for the design of the system: a gravity system or a pumped system. Given the constraints of a gravity system and the flow requirements, and also the wet season excess water controls, a pumped system is necessary.

 

4.4.12    The pumped system would be sealed, and a portable pump lowered into the appropriate bund manhole. The pump would be connected by a flexible pipe to the permanent system, and water directed through the arterial system to the appropriate manhole from which it can be directed into the receiving pond. The required pump rating is approximately 15kW.

 


4.4.13    At the receiving pond the water would outfall onto a precast concrete slab on the bed of the pond. Reducing turbidity to a minimum is a desirable feature of the system.

 

4.4.14    Power for the pumps would come from a supply installed around the ponds, such that no generators are necessary. Both systems will require some concrete catchpits, manholes etc, but these will be below ground and will be constructed of precast items.

 

4.4.15    The system has parallels with commercial practice and the practices adopted by WWF at Mai Po, pond 20.

 

Marshland

 

4.4.16    Watercourse A (to the east of the site) will receive rainfall runoff from the station roof. To separate the station area run-off from the pond system a weir will be constructed, with a crest level of +3mPD. Given the potentially high flows associated with a storm, the watercourse , as part of the pond system, will receive half of the roof run-off, whist the other half and all station groundwater run-off will outfall directly into the Shenzhen River. The banks forming the channel are at +3.5mPD. Under a 10 year storm event water levels rise to +3.5mPD, that is the area is inundated, although the channel itself can theoretically sustain a 1 in 200 year event. The excess water resulting from an annual event will not adversely impact the channel because:

 

                       There is spare capacity under an annual event,

                       The channel has been designed assuming a catchment which includes half the ponds.

 

 

4.4.17    Water levels in the marshland mitigation area will be controlled by an adjustable sluice allowing flow from Water Course A out of the marsh, or by pumping in using a small pump, depending on seasonal water levels.

 

4.5              Water Source

 

Fish Ponds

 

4.5.1        All fish pond water will be obtained by direct rainfall and will be retained and recirculated during drain-down periods as necessary. One pond will also be used in each year as a reservoir pond as a contingency measure to ensure that pond water levels are kept within tolerance levels (see below). No surface or groundwater water supplies will be used for fish pond operations.

Marshland

 

4.5.2        The water requirements for the marshland area will be met by direct rainfall supplemented with runoff from the station roof area, which will be stored in Water Course A (Figure 4.1).

 

4.5.3        A water budget with predicted water levels for the marsh area based on average monthly rainfall and evaporation rates between 1990 and 1999 is provided in Appendix A3.4. This indicates that over the last 10 years the available water from direct rainfall and the station roof runoff would have been sufficient to maintain water levels at target levels (see Appendix A3.4). These target levels allow restricted falls in water levels to provide newly exposed and wet margins to the wetland areas, which provide good feeding areas for many wetland birds.

 

4.6              Vegetation

 

Vegetation to be Retained

 

4.6.1        All of the semi-natural areas are readily re-creatable and there are no individual plant species or specimens which should be conserved in situ or transplanted. No restrictions requiring the protection of existing vegetation are, therefore, necessary; indeed in many instances the deliberate destruction of existing vegetation of limited ecological value will be required.

 

Vegetation to be Established in the Fish Pond Area

 

4.6.2        A list of the species to be established on the fish pond bunds is provided in Table 4.1 below. Reed-fringed areas will provide suitable habitat for Ardeids (especially bitterns Ixobrychus spp.), rails and passerines. Paspalum distichum will provide loafing areas for Common Teal as well as food for this and other duck species.

 

4.6.3        Phragmites will be planted in Pond 5 and along the eastern margins of Ponds 13a and 13b and the southern margins of Ponds 14a and 15. Paspalum will be planted along all the bunds of Ponds 1 and 2. On the remaining bunds natural regeneration of vegetation will be allowed, but with 25% of these kept as largely bare banks to provide foraging and/or loafing areas for larger Ardeids, Black-faced Spoonbills and Red-billed Starlings. The areas kept bare will be rotated on an annual basis.

 


Table 4.1

Wetland Species to be Established in the Fish Pond Mitigation Area

 

Species

Approx. density (no. m-2)

 % cover

Quantity(no. hectare)

Growth form

Approx. height for planting (cm)

Phragmites australis

4

100

 

Monostands

>20 cm

Paspalum distichum

N.A.

0 – 100*

Broadcast seed

Monostands

N.A.

 Notes:   * Paspalum distichum seed to be broadcast on permanently dry and seasonally wet areas. Overall percentage of cover along punds to be 25 – 75% around each pond.

 

Marshland

 

4.6.4        A list of the species to be established in the marshland mitigation areas is provided in Table 4.2 below. The planting list is derived from those native species known from Luk Keng Marsh, Liu Pok Marsh and recently established freshwater wetland areas at Mai Po and San Tin. There are no suitable lowland freshwater wetlands in Hong Kong of sufficient size, diversity and naturalness to provide a template for a suitable planting list or species mix as all such wetlands (even the most natural such as Luk Keng) are highly modified by man and/or domestic animals. The proposed list is, therefore, made up of native species and contains redundancies to accommodate the likelihood that not all species selected will necessarily thrive in the particular conditions to be created. Habitats to be created will cater for requirements of target species detailed in Section 2 above. 

 


Table 4.2

Species for establishment in Lok Ma Chau Freshwater Marsh (numbers below refer to planting zones shown in Appendix 3.5)

 

Mix / species

Size

Shoots

Density / sq m

% Cover

Block size

1. Lightly vegetated with bare areas (permanently damp).

Bacopa monnieri

20

5

25

10

50

Hygrophila salicifolia

10

5

25

10

50

2. Lightly vegetated with bare areas (seasonally wet).

Bacopa monnieri

20

5

25

20

50

Cyperus iria

20

3

16

10

50

Fimbristylis ferruginea

20

5

25

10

50

Saururus chinensis

20

5

25

10

50

3. Well vegetated (permanently damp).

Bacopa monnieri

20

5

25

10

100

Commelina diffusa

20

3

16

10

100

Chrysopogon aciculatus

20

5

16

10

50

Fimbristylis complanata

20

5

16

10

100

Fimbristylis subbispicata

20

5

25

20

100

Philydrum lanuginosum

40

3

16

10

100

Polygonum glabrum

20

5

16

20

100

Sagittaria trifolia

20

3

16

10

50

 4. Well vegetated (seasonally wet).

Cyperus malaccensis

40

3

16

20

100

Cyperus pilosus

40

3

16

5

50

Fimbristylis ferruginea

20

5

25

10

50

Ludwigia antipoda

20

5

25

5

50

Polygonum dichotomum

20

5

16

10

100

Polygonum hydropiper

20

5

16

20

100

Ranunculus scleratus

20

3

16

5

50

Rumex maritimus

20

5

25

10

100

Sagittaria trifolia

20

3

16

5

50

Saururus chinensis

20

5

25

10

50

5. Tall marsh (seasonally wet).

Bacopa monnieri

20

5

25

5

50

Cyperus malaccensis

40

3

16

20

100

Eleocharis plantagineiformis

20

5

16

10

100

Juncus prismatocarpus

40

3

16

10

50

Polygonum barbatum

20

5

16

10

100

Ranunculus scleratus

20

3

16

10

50

Sagittaria trifolia

20

3

16

10

50

Saururus chinensis

20

5

25

5

50

Schoenoplectus littoralis

40

3

16

20

50

6. Tall marsh (largely wet but partially dry in mid-winter).

Bacopa monnieri

20

5

25

5

50

Cyperus malaccensis

40

3

16

10

100

Eleocharis plantagineiformis

20

5

16

10

100

Equisetum debile

20

5

16

10

50

Ludwigia adscendens

20

5

25

5

50

Polygonum glabrum

20

5

16

20

100

Rumex maritimus

20

5

16

20

100

Sagittaria trifolia

20

3

16

10

50

Schoenoplectus littoralis

40

3

16

10

100

 7.  Tall marsh (permanently wet).

Cyperus malaccensis

40

3

16

20

100

Cyperus pilosus

40

3

16

20

100

Ludwigia adscendens

20

5

25

20

100

Utricularia aurea

20

3

16

10

50

Utricularia bifida

20

3

16

10

50

 8. Short marsh (seasonally wet).

Bacopa monnieri

20

5

25

20

100

Blyxa japonica

20

5

25

10

50

Commelina diffusa

20

3

16

10

100

Cyperus iria

20

5

25

10

50

Eleocharis congesta

20

5

25

10

50

Eleocharis plantagineiformis

20

5

25

10

50

Eleocharis spiralis

20

5

25

10

50

Fimbristylis cymosa

20

5

25

10

50

Fimbristylis ferruginea

20

5

25

10

50

9. Short marsh (usually wet but partially dry in mid-winter).

Bacopa monnieri

20

5

25

20

100

Blyxa japonica

20

5

25

10

100

Cyperus iria

20

5

25

5

100

Eleocharis congesta

20

5

25

10

100

Eleocharis plantagineiformis

20

5

25

20

100

Equisetum debile

20

5

25

10

100

Fimbristylis ferruginea

20

5

25

10

100

Fimbristylis subbiscipata

20

5

25

10

100

Limnophylla chinensis

20

5

25

5

100

10. Bamboo clumps (planted at 50 cm centres).

Bambusa vulgaris

 

100

See plan

11. Buffer tree/shrub mix (planted at 50 cm centres).

 

Growth form

% Cover

Block size

Bridelia tomentosa

Tree

10

Groups of 5

Celtis tetranda

Tree

20

Groups of 3

Litsea glutinosa

Tree

5

Groups of 3

Melastoma candidum

Shrub

20

Groups of 10

Melastoma sanguineum

Shrub

10

Groups of 10

Morus alba

Tree

5

Groups of 3

Rhaphiolepis indica

Shrub

10

Groups of 5

Sapium sebiferum

Tree

20

Groups of 5

 

Notes:    At least 5% of the areas (except 10 & 11) need to be bare mud and water. The quantity per metre is converted to the quantity required per hectare by the following equation: 36 x 4840 x 2.471 / 39.  

 


4.6.5        Vegetation establishment will be established according to the specification and planting plan provided in Appendix 3.5.

 

4.7              Access and Fencing

 

4.7.1        The ecological mitigation area will be fenced immediately after the site is handed over to KCRC. Access will then be limited to authorized personnel.

 

4.7.2        The mitigation area perimeter fencing will comprise 1.2m high railposts 2m apart, with two bars across the rails, spaced 0.3m from the ground and the top of the post respectively. Fencing is to be outdoor quality recycled plastic, ultra violet light and fire resistant, self coloured dark brown or black. Fencing may be pr-fabricated or final finishing may be undertaken on site (suppliers will recommend appropriate construction / assembly methods). Contractors unfamiliar with recycled plastic fencing are advised that numerous suppliers of these materials may be sourced by Internet search. It is possible that it will be necessary to source a supplier from overseas.

 

4.7.3        Recycled plastic supplier and a sample of the proposed fencing material, together with construction / assembly method should be provided for the approval of the Resident Engineer or his representative prior to erection on site.

 

4.7.4        Access to the wetland mitigation areas will be provided by means of lockable gates to be located at appropriate positions.

 

4.7.5        The station works area will be screened off from the rest of the site before the start of any works, to reduce disturbance to wildlife in the surrounding area. Similarly the marshland area must be screened off from the surrounding wetland areas during the wetland construction works.

 

4.7.6        Screening must consist of solid hoarding over at least 2m height.

 

4.8              Construction and Habitat Establishment Work Programme

 

4.8.1        An outline list of the main actions necessary for the creation of the marshland and enhancement of the fish pond habitats is provided in Tables 4.3 and 4.4 below. General procedures are listed in Appendix 3.6. Pond numbers referred to in the table are indicated in Figure 4.1. Time periods, start and completion dates for these actions are dependent on the overall railway and station construction programme, which has yet to be approved and scheduled. Dates will be added to this list when an Environmental Permit has been granted and a construction programme established.

 


Fish Ponds

 

4.8.2        It is important to avoid disturbance to the western ponds, because these will provide mitigation for the disturbance occurring as a result of the station and marshland mitigation works. Therefore, it is proposed that mitigation construction works are carried out in two phases. The first phase will consist of works within the eastern half of the fish ponds area (i.e. east of Ponds 9a, 10a, 10b and 11) and the marshland area. During this period works in the western half of the mitigation area will be restricted to selective tree felling (to open up enclosed areas), other vegetation management and traditional fish pond management of Ponds 3a, 3b, 4, 6a, 6b, 7, 8a and 8b (but with half taken out of production and part drained in each year in rotation). Ponds 1 and 2 will be drained and allowed to refill with rain water and maintained at shallow to moderate water levels (by simple pumping when necessary) to provide high quality habitat primarily for water fowl.

 

4.8.3        Pond 5 will be planted with reeds during the initial mitigation phase.

 

4.8.4        After completion of the station and marshland construction the remaining mitigation works will be carried out on one pond at a time to minimize disturbance impacts on the other ponds and marshland areas nearby.

 

Table 4.3

Habitat enhancement work programme for the Lok Ma Chau Station fish pond area wetland mitigation

 

 

Action

Start date

Completion date

Notes

 

Preworks period;

 

 

 

1

Site handover

 

 

 

2

Erection of boundary fencing and works area hoarding

 

 

 

 

1st Mitigation Phase during station & marshland construction period:

 

 

 

 

Pond 5

 

 

 

3

Partial drainage and planting of pond with Phragmites

 

 

 

 

Ponds 1 and 2

 

 

 

4

Drainage of Ponds 1 and 2

 

 

 

5

Cary out selective tree felling and vegetation management to open up habitat in vicinity of western ponds

 

 

 

6

Allow partial re-filing of ponds from rainfall

 

 

Maintain water levels below target levels by pumping

 

Ponds 9a/b, 10a/b, 11, 12, 13a/b, 14a/b & 15.

 

 

 

7

Drainage of ponds and drying of substrate

 

 

Trash fish etc to be transferred to other ponds, commercial fish to be sold.

8

Construction of water pumping system

 

 

 

9

Lowering of connecting bunds to form islands and shoals, and connection of ponds

 

 

 

10

Reprofiling of pond base and bunds

 

 

 

11

Filling and land formation with topsoil on vegetated islands

 

 

 

12

Construction of water control structures and jetties

 

 

 

13

Final fine scale land formation

 

 

 

14

Initial soil preparation for planting

 

 

 

15

Fish farming preparations (liming, fertiliser applications*etc)

 

 

No toxic compounds for killing pathogens, to be used.

16

Planting / translocations of wetland vegetation

 

 

Possibly including wetland plant rhizomatous material

17

Refilling to initial operational water level

 

 

Check water quality

18

Start fish farming operations

 

 

(see Management below)

19

Vegetation establishment management (e.g. weeding, thinning, replacement planting, irrigation)

 

 

 

 

2nd Mitigation Phase: Post construction period (Ponds 1, 2, 3a, 3b, 4, 6a, 6b, 7, 8a & 8b)

 

 

 

20

Drainage of ponds and drying of substrate

 

 

Trash fish etc to be transferred to other ponds, commercial fish to be sold.

21

Construction of bridge across water course to Ponds 1 & 2

 

 

 

22

Completion of water pumping system

 

 

 

23

Lowering of connecting bunds to form islands and shoals, and connection of ponds

 

 

 

24

Reprofiling of pond base and bunds

 

 

 

25

Filling and land formation with topsoil on vegetated islands

 

 

 

26

Construction of water control structures and jetties

 

 

 

27

Final fine scale land formation

 

 

 

28

Initial soil preparation for planting

 

 

 

29

Fish farming preparations (liming, fertiliser applications*etc)

 

 

No toxic compounds for killing pathogens, to be used.

30

Planting / translocations of wetland vegetation

 

 

Possibly including wetland plant rhizomatous material

31

Refilling to initial operational water level

 

 

Check water quality

32

Start fish farming operations

 

 

(see Management below)

33

Vegetation establishment management (e.g. weeding, thinning, replacement planting, irrigation)

 

 

 

 

*              Liming is used after pond draining, to adjust pH of oxidized and acidic mud. These practices are described in more detail later in this report.          

 


Marshland

 

4.8.5        An outline list of the main actions necessary for the construction and establishment of the marshland habitats is provided in Table 4.4 below.

 

Table 4.4

Construction and habitat establishment work programme for the Lok Ma Chau Station marshland mitigation area

 

 

Action

Start date

Completion date

Notes

1

Site clearance and handover, erection of hoarding

 

[To be advised]

 

2

Underlying site land formation

 

 

 

3

Infilling with surcharge sand layer

 

 

 

4

Filling and land formation with topsoil mix

 

 

 

5

Construction of water control structures

 

 

 

6

Testing of integrity of marshland wetland unit

 

 

Clay layer to be used as contingency measure if necessary

7

Final fine scale land formation

 

 

 

8

Boundary fencing

 

 

 

9

Water filling to initial level for planting using ‘seed’ water with required invertebrate larvae and phytoplankton

 

 

 

10

Initial soil preparation for planting

 

 

 

11

Planting of wetland vegetation

 

 

Incremental increases in water level to track planting

12

Removal of hoarding

 

 

 

13

Vegetation establishment management (e.g. weeding, thinning, replacement planting, irrigation)

 

 

 

 


4.9              Mitigation Measures for Wetland Construction and Establishment Works

 

4.9.1        During the construction of wetland mitigation areas and any associated works environmental impacts must not exceed those predicted in the EIA. In particular measures must be taken to avoid or minimise the following potential ecological hazards:

 

·        Noise and visual disturbance;

·        Hydrological disruption of surface watercourses;

·        Pollution of watercourses;

·        Dust deposition;

·        Soil compaction; and

·        Soil contamination.

 

4.9.2        Mitigation measures that are related to the construction of the railway will be listed in the Particular Specification.

 

4.10          Contingency Measures

 

4.10.1    A number of measure have been included in the design, construction methods, management and monitoring proposals that aim to ensure the successful establishment and long-term sustainability of the wetland as effective compensation habitat for key target species.

 

4.10.2    The wetland designs also have in built contingency measures for key factors affecting wetland establishment, especially regarding water supply, water retention and plant establishment. These include:

 

·        The collection and storage of the station roof run-off to supplement direct rainfall supplies to the marshland area.

·        The use of a fishpond as a reservoir pond to maintain water levels within target tolerances if required (a practice not normally deemed necessary by fish pond operators)Measures to reduce high acidity in pond water by adding neutralising agents (for example, pigeon faeces or peanut waste).

·        The use of a clay base liner if tests indicate that water losses from the marshland wetland are outside tolerable limits. Further potential contingency actions if required could include placement of impermeable membranes in specific problem areas or insertion of vertical plates (or membranes) at the edge of the wetland to reduce lateral seepage.

·        High planting densities to accommodate poor plant survival (and reduce potential weed growth).

 

4.10.3    Also, as described in Section 5 routine construction and establishment phase and long-term management actions, such as weed clearance, replanting, thinning and water level control will also be undertaken. These also aim to ensure the successful establishment and long-term sustainability of the wetland cells.

 

4.10.4    In addition, specific contingency actions will be defined in a Contingency Action Plan. This will be prepared by the Contractor (as part of the development of the wetland construction Method Statement) and agreed by the Resident Engineer and Wetland Habitat Creation Ecologist before commencement of works. As a minimum, contingency measures will be prepared for potential:

 

·        inadequate water supply

·        failure of the mains pumping system (including pump and timer failure, breakage of supply pipes);

·        damage to sluices and drainage structures;

·        pollution of water supply;

·        direct pollution of wetland cells by toxic substances (e.g. from spillages / dumping);

·        unacceptable plant survival rate or growth during the 2 year establishment phase;

·        invasion by exotic or other undesirable plant species;

·        flooding of the site and other potential effects from storm events; and

·        fire damage.

 

4.10.5    As described in Section 6 detailed and intensive monitoring will be carried out of the physical and ecological performance of the wetland mitigation area during the construction and establishment phases and  in the long-term. The monitoring will be carried out in relation to defined “Action Levels” and “Limits” which trigger appropriate actions to rectify problems. Where necessary these will include actions defined in the Contingency Action Plan.

 

 

Back to Appendix A4.2