1.
INTRODUCTION
1.1
Contamination
can be defined as “the introduction by man into the environment of substances
or energy liable to cause hazards to human health, harm to living resources and
ecological systems, damage to structures or amenity, or interference with
legitimate uses of the environment” (Holdgate 1979, and adopted by the RCEP,
1984). The soil is a primary recipient, intended or otherwise, of many waste
products and chemicals used in modern society.
1.2
The
Spur Line passes across a range of landuses, including agricultural,
residential, container storage, industrial and fish farming areas. While there
are no extensive areas of contaminated land such as landfills, chemical stores,
etc. across which the Spur Line passes, there is potential for the presence of
small industries or storage sites to create an impact in the construction and
operation of the Spur Line. This Contaminated Land Assessment Plan (CAP) has
been written for the contaminated land assessment of Agreement No. EA990008,
Sheung Shui to Lok Ma Chau Spur Line (Spur Line) in accordance with EPD
Practice Note for Professional Persons Concerning ProPECC PN 3/94 - Contaminated Land Assessment and Remediation and
the EPD Guidance Notes for Investigation
and Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards or
Car Repair/Dismantling Workshops. The CAP is prepared to fulfil the
requirement of section 3.11.2 of the EIA Study Brief.
2.
METHODOLOGY
2.1
This
contaminated land assessment includes the following steps:
(i)
A desktop study on the history
of landuse along the Spur Line alignment (the Desktop Study) which provides a
clear and detailed account of the relevant past land history and the present
land uses along the alignment. This identifies areas of potential land
contamination.
(ii)
Identification
of works associated with Spur Line construction that may impact contaminated
sites.
(iii)
A
site survey in order to identify all potentially contaminated areas and
pollutants for the land contamination assessment.
(iv)
Recommendations
for a schedule of 2 stage sampling, initially at potentially contaminated areas
identified in the Desktop Study and during the site survey followed by further
sampling to determine the extent of contaminated areas if contamination is
confirmed, and the laboratory analysis of essential parameters. This should be
carried out at the site investigation stage of works to confirm the presence or
absence of contamination.
(v)
Recommendations
on appropriate remedial action for several scenarios based on the range of
different types of contaminants which may be found during site investigations.
Any remedial action proposed will be beneficial not only in terms of preparing
the land for construction but will also alleviate potential impacts on
groundwater, water quality in river courses and the ecology of the area.
(vi)
The
application of the recommended sampling, analysis and remediation programme to
specific locations along the alignment to facilitate the implementation of the
Contamination Assessment Plan during the site investigation stage.
3.
STUDY AREA
3.1
The Study Area includes
the immediate track and tunnel alignment and the engineering works boundary
(Figure 2.1). Three temporary
works areas have been earmarked at Lok Ma Chau, Kwu Tung and at the Sheung
Shui Temporary Housing Area. In the Lok Ma Chau area, fishponds will require
temporary draining and stabilisation with partial or complete infilling to
create a base for pier and station foundation works.
3.2
4.3
km of the alignment passes through a tunnel under rural areas dominated by
agriculture. Within this predominantly tunnelled section, a range of ground
surface works will be undertaken, some in locations where there is potential
for contaminated land to be impacted. These surface works include: the TBM
launching shaft at Sheung Shui, the recovery shaft at Chau Tau, Emergency
Access Points (EAPs) and ventilation buildings, the locations where surface jet
grouting is required for the construction of cross passages and the Kwu Tung
station box. The most significant areas where potential impacts may occur are
the Kwu Tung station box where a number of small industries and storage areas
are located, at the scrap metal yards in Sheung Shui around the launching shaft
and around the recovery shaft at Chau Tau, where a number of container storage
yards may contribute to land contamination.
3.3
Figures
10.1, 10.2, 10.3,
10.4 show the alignment and
future surface structures which may have impacts on contaminated land.
3.4
Construction
methods will include excavation works for surface structures, for the cut and
cover tunnel sections, launching and reception shafts and the Kwu Tung station
box, bored piling works for the viaduct supports and for Lok Ma Chau station
construction, and excavation of material from the tunnel. The tunnel is
sufficiently deep that it is unlikely to impact any contaminated areas. The
extent of surface impacts, and the type of remediation to be proposed will
depend on whether the works is extensive, such as the TBM launching and
recovery shaft excavation, or minimal, as in the viaduct pier supports.
4.
RISKS TO HEALTH
4.1
A
contamination assessment is important because of the health risks posed to site
workers on exposure to contaminated soil or sediments, and contamination of
groundwater during earth moving operations, excavation or piling works. Workers
could become exposed to contaminants either directly e.g. skin contact during
the work by inhalation of dust or vapours, or through ingestion whilst eating
or smoking on site.
4.2
If
remediation is found to be necessary at any point of the alignment it should be
carried out to a suitable level so as not to pose any future health risks to
users of the site. As long as there is no direct human - soil interface, it is
likely that in many places the sediments could remain in-situ or be remediated
to a level sufficient for its future use.
4.3
Contaminants
of particular concern due to their potential health risks include inorganics
such as cyanides and heavy metals, organics such as mineral oils, halogenated
solvents, polycyclic aromatic hydrocarbons and volatile aromatic hydrocarbons
and minerals such as asbestos.
4.4
Contaminants
may also pose a fire hazard or explosion risk if volatile gasses or flammable
contaminants are found.
5.
DESKTOP STUDY
Industries
having the Potential to Cause Land Contamination
5.1
Historically
there is evidence that the New Territories was the location for various light
industries and other landuses which change frequently but often have a
potential to contaminate the land. These include car repair yards, container
storage areas, livestock farms, paint and dye factories and other small scale
industries. Many of these small industries still operate today, although the
density of factories has reduced over recent years. In addition there are
dumping grounds, refuse collection points and illegal dumping areas which are
likely to result in some ground contamination. Many of these landuses fall
within the areas of the proposed alignment and, if unmitigated, give rise to
concern for their future landuse.
5.2
A
number of industries have been identified in ProPECC PN 3/94 as having the
potential to cause land contamination. These include:
·
oil installations (e.g. oil
depots, oil filling stations);
·
gas
works;
·
power
plants;
·
shipyards/boatyards;
·
chemical
manufacturing/processing plants;
·
steel
mills/metal workshops; and
·
car
repairing/dismantling workshops.
5.3
This
list is not exhaustive and judgement is needed to determine if contamination is
likely from other land uses or industries.
Land
Ownership
5.4
There
is a variety of ownership along the alignment of the Spur Line. Across Long
Valley there are many agricultural lots, whilst in Kwu Tung many owner occupied
small houses typical of the New Territories are found. Significant areas of
land along the alignment are Government Land, particularly in the Lok Ma Chau
and Sheung Shui areas.
Landuse
History
5.5
In
order to assess potential land contamination, the past landuse history and the
present landuse of the areas which will fall under the Spur Line alignment have
been reviewed. Aerial photographs have been used and landuse information has
been obtained from the District Land Offices in Yuen Long (DLO Yuen Long) and
Fanling (DLO North).
6.
SITE SURVEY
Objectives
and Methodology
6.1
The
objectives of a site survey for the land contamination assessment are to
confirm any land-uses found in the DLO records and to identify any other uses
which may be illegal and not recorded. The Study Area has been taken to be the
gazetted area of the Spur Line, although large portions of this gazetted
alignment will not be directly affected except via the underground tunnel. The
site survey has also been used to gather information on other activities such
as storage and management of hazardous substances.
6.2
Initial
site inspections were carried out on 17 May, 27 July 1999 and 17 September
2001. No advance notice was given to land users in order to obtain as authentic
information as possible. A number of sites along the alignment were disregarded
due to information obtained during the desktop study and site visits which
indicated no likelihood of contamination. The findings of the site survey are
evaluated to identify all potentially contaminated areas and parameters for
further investigation in a sampling and analysis programme.
6.3
Ground
conditions were also observed during the site surveys, to determine the ease of
infiltration and potential for underground dispersion of pollutants.
Results
of Desktop Study and Site Visits
6.4
A full listing of the
desktop study results and the findings of site visits to each site are provided
in Appendix A. As some sites cover more than one lot, each site listed has
been assigned a letter. The sites are described from west to east along the
alignment and their locations identified in Figures
10.1, 10.2, 10.3,
10.4. The nature of the land
in each lot, and the activities being carried out which may potentially contaminate
the ground, are shown in Plates
10.1 to 10.5, 10.6 to 10.10,
10.11 to 10.15, 10.16
to 10.19, 10.20 to 10.24,
10.25 to 10.29. Not all
lots could be photographed, however, a description of each lot is given in
the following tables. Table 6.1 lists lot numbers, their assigned letter and
the type of works which may impact the area (viaduct, EAP, launching shaft,
etc).
Table
6.1
Lot
Numbers, Assigned Letters and Section
Letter |
Lot Number |
Section |
Letter |
Lot Number |
Section |
A |
DD99/372
S.D RP |
Ramp and Viaduct |
G |
DD95/ 786, 791, 792, 772 (part) |
Kwu Tung Station Box |
B |
DD99/ 470 -
483, 486 – 493, 527, 545 - 548 |
Recovery Shaft |
H |
DD96/ 772
(part) |
Kwu Tung Station Box |
C |
DD96/352,
353, 354, 355, 423 |
Miscellaneous Storage
Area (TBC) |
I |
DD95/ 803 S.A. ss. |
Kwu Tung Station Box
(TBC) |
D |
DD96/ 428 |
Miscellaneous Storage
Area/Cross Passage |
J |
DD95/ 803 S.B. |
Kwu Tung Station Box
(TBC) |
E |
DD 96/645 –
sections |
Cross Passage |
K |
DD95/ 43 - 45, 53 - 59, 65 - 67, 70 -
74 |
Cross Passage |
F |
DD 96/717, 718, 721 |
Cross Passage |
L |
Sheung Shui
Government Land |
Launching Shaft |
TBC: To be
confirmed. These sites may fall outside of the above ground works areas and
therefore may be removed from the contamination assessment at a later date if
it is found that they will not be impacted by works.
6.5
Table
6.2 summarises the results of the desktop study and site visits. The table
lists the registered landuse of the site and the likely potential and extent of
contamination. CAP Appendix A includes any permit numbers or Short Term Tenancy
Agreements (STT) or Short Term Waivers (STW) which cover the lots.
Table
6.2
Findings
of Desktop Study & Site Visits and the likely Potential for Contamination
Site and Lot No. |
Figure No. / Plate No |
DLO Registered Landuse |
Site Inspection |
Potential for Land
Contamination |
A DD99/372 |
Container
vehicle park, open storage |
Confirmed
landuse. Some petrol pumps, chemical waste area |
Likely,
rough surface, cracked concrete, storage of chemical and hydrocarbons on site |
|
B DD99/470-483,
486-493, 527, 545-548 |
NA* |
Containers,
open storage, storage of chemicals, oils and solvents |
Likely,
gravel and cracked surface and storage of potential contaminants and scrap
metals |
|
C DD96/352,
353, 354, 355, 423 |
NA* |
Sign
stated car repairs. Previous storage of many chemical drums, most marked
harmful. Site now cleared (Sept 2001). |
Likely,
evidence of spillage on ground. Concrete cracked (Works area TBC) |
|
D DD96/428 |
NA* |
Disused/abandoned
pig farm with chemical storage |
Likely,
cracked surface and spillage evident |
|
E DD96/645 |
NA* |
Farm
buildings, chemical storage, livestock waste drums, site generally littered
with waste |
Inventory
of chemicals and pesticides used required. Rough surface may have allowed
some infiltration |
|
F DD96/717,
718, 721 |
P:
- |
NA* |
Container
storage area, some parked vehicles and drum storage |
Possible,
some containers are very old, and battered, spillages could have occurred. |
G DD95/786,
791, 792, 722 |
Illegal
container storage |
Container
and storage area with temporary structures. Surface rough and some chemicals
stored |
Possible
- depending on whether any spillages have occurred. |
|
H DD96/772 |
No
registered landuse |
Metal
recycling company. Many parked vehicles, rough gravel surface. |
Possible
- depending on whether spillages have occurred |
|
I DD95/803 |
P:
- |
NA* |
Storage
area for adjacent factory. |
Possible
from historic contamination as this was a leather goods factory |
J DD95/803 |
NA* |
Car
repairs/dismantling yard. Ground concreted and vegetated |
Likely
due to infiltration through cracked concrete and vegetation |
|
K DD95/43-45,
53-59, 65-67, 70-74 |
NA* |
Access
denied but site is fenced and appears to be used as a repairs and maintenance
site for Paul Y ITC |
Likely
but activities carried out here must be clarified. Site access not possible. |
|
L
Government Land in Sheung Shui |
NA* |
Access
denied but scrap metal yard in operation observed. Some storage of chemical
drums and metal waste |
Likely
but exact locations must be determined. |
Note NA* - No information available from DLO
6.6
The
main areas for concern are container storage areas, particularly those in DD99
close to Lok Ma Chau (A and B), the car repair/dismantling yards at Kwu Tung
(J) and the scrap metal yards in Sheung Shui (L).
6.7
The
main contaminants are likely to be oils, organic solvents and heavy metals.
Some chemicals known to be hazardous were found. These included methylene
chloride, listed as a hazardous air pollutant (under the US Clean Air Act,
1991). Many chloro alkanes are designated as priority pollutants (Clean Water
Act) and are on the Superfund Hazardous substances list, as is chloroform which
was found close to site F. In addition to specific named substances and
chemicals there was much evidence of oil and petrol spillage, piles of scrap
metals and storage of unspecified chemicals.
Site
Appraisal
6.8
From
the desktop study and site visit information collected, it is possible to
determine whether a contaminated land site investigation is needed. This
information was used to check against the set of criteria described in Table
6.3 which is taken from the EPD Guidance
Notes for Investigation and Remediation of Contaminated Sites of: Petrol
Filling Stations, Boatyards or Car Repair/Dismantling Workshops. For this
set of landuses if the answer to any of the criteria is ‘No’, a full scale site
investigation is recommended. A positive answer to all criteria indicates that
simplified site investigation may be sufficient. The criteria can be used as
guidelines or indicators for different potentially contaminating landuses.
Table
6.3
Criteria
for Adoption of Full-scale or Simplified Site Investigation
Criteria |
Yes/No |
1. Length
of operation of the site is less than 5 years. |
|
2. There
is a practice of recording spill incidents or monitoring chemical storage. |
|
3. Waste
disposal is carried out in accordance with Government requirements |
|
4. Absence
of underground storage tank on site |
|
5. Absence
of surface contamination indicators which include: a) stained areas b) uncontrolled chemical drum
storage c) cracked concrete near
storage of chemical drums d) unnatural colours and odours;
and e) abandoned
piping/mechanical components or cans. |
|
6.9
In
the case of Spur Line, no site along the alignment is known to have an
underground storage tank. At several sites where chemicals are stored, a
negative answer is likely to criteria 2 and 3 as most sites landuse is illegal
and no DLO records are available. At many of the sites there is evidence of
spillage of chemicals, uncontrolled chemical drum storage, cracked concrete or
rough gravel surfaces, all of which are criteria for full scale site
investigations. On the basis of this information, a Land Contamination
Assessment Plan (CAP) is recommended. The following section describes the CAP
for the Spurline Project.
7.
LAND CONTAMINATION ASSESSMENT
PLAN (CAP)
7.1
This
section summarises the results of the desktop study and site inspection and
proposes a sampling and analysis programme based on the data collected. The
sampling programme should be carried out during the site investigation stage.
Site
Investigations
7.2
A
site investigation should be approached in a systematic way bearing in mind the
purpose and the level of detail which is required. The main topics, as defined
by EPD (1999) are:
·
Physical site conditions,
including geology, topography, soil type and physical properties, drainage and
groundwater.
·
Likely
contaminants - previous site use.
·
Extent
and severity of contamination, the concentrations, depth, spatial distribution
of contamination in both soils and groundwater.
·
Effects
on users, including the nature and level of contamination with regard to future
use.
·
Potential
environmental harm.
·
Hazards
during construction.
7.3
The
subsurface geology and groundwater flow are important as petroleum hydrocarbons
in particular can float and migrate some distance. This could impact other
drainage waters around the Spur Line alignment and cause modification of BOD5,
SS and other important parameters. Many of the areas where potential
contamination sites were identified, are located on flat, low-lying land, not
far above the water table. There is therefore potential for contaminants to
enter the groundwater in these areas.
7.4
Table
7.1 below lists the site numbers and the main activities at each site
identified. Likely contaminants associated with different site activities are
listed in Table 7.2. The level of contamination and the extent of contamination
need to be determined through a formal sampling and analysis programme and the
most suitable methods for clean up of the site determined.
Table
7.1
Lots
along the Spur Line and Potential Contaminating Landuses
Site |
Fuelling Areas |
Servicing/Parking Areas |
Paint Shop |
Fitting out/ repairs |
Coating/ steel treatment |
Vehicle Breaking |
Chemicals or waste storage |
Drainage and soakaway systems |
Agricultural Activities |
A |
√ |
√ |
√ |
√ |
√ |
√ |
√ |
√ |
|
B |
√ |
√ |
√ |
√ |
√ |
√ |
√ |
|
|
C |
|
|
|
|
|
|
√ |
|
|
D |
|
|
|
|
|
|
√ |
|
√ |
E |
√ |
|
|
|
√ |
|
√ |
|
|
F |
|
|
|
|
|
|
√ |
|
|
G |
|
√ |
√ |
√ |
|
√ |
√ |
|
|
H |
|
√ |
|
|
|
|
√ |
|
|
I |
|
|
|
|
|
|
√ |
|
|
J |
|
√ |
√ |
√ |
|
|
√ |
|
|
K |
√ |
√ |
√ |
√ |
√ |
√ |
√ |
|
|
L |
√ |
√ |
|
√ |
√ |
√ |
√ |
√ |
|
Table
7.2
Activities
found along the Spur Line and their likely associated contaminants
Contaminant |
Fuelling Areas |
Servicing/Parking Areas |
Paint Shop |
Fitting out/ repairs |
Coating/ steel treatment |
Vehicle Breaking |
Chemicalsor waste storage |
Drainage and soakaway systems |
Others |
Metals (all) |
√ |
√ |
√ |
√ |
√ |
√ |
√ |
√ |
√ |
Lead |
√ |
√ |
√ |
|
|
|
|
|
|
Chromium |
|
√ |
|
|
|
|
|
|
|
Zinc |
√ |
|
√ |
|
|
|
|
|
|
Copper |
√ |
√ |
|
|
|
|
|
|
|
Cyanides |
|
|
|
√ |
√ |
|
√ |
√ |
√ |
Organic Contaminants |
|
√ |
√ |
√ |
√ |
|
√ |
√ |
√ |
Simple
aromatics |
√ |
√ |
|
√ |
√ |
√ |
√ |
|
√ |
Organic
solvents |
√ |
√ |
√ |
√ |
√ |
|
√ |
|
√ |
Polyaromatic
hydrocarbons |
|
√ |
|
|
√ |
√ |
√ |
|
√ |
Fuels/oils |
√ |
√ |
|
√ |
|
√ |
√ |
√ |
√ |
Biocides |
|
|
|
√ |
√ |
√ |
√ |
√ |
√ |
Oily
sludges |
|
√ |
|
√ |
√ |
√ |
√ |
√ |
√ |
Microbacteriological |
|
|
|
|
|
|
√ |
√ |
√ |
Acids |
|
|
|
√ |
√ |
√ |
√ |
√ |
|
NOTE:
Simple
aromatics includes benzene, toluene, ethylbenzene, xylene etc
Organic
solvents includes non-halogenated and halogenated solvents
Fuels/oils
includes Total Petroleum Hydrocarbons
Acids
includes sulphuric and hydrochloric
SOURCE:
EPD
(1999)
Voelcker
Science (1999)
Methodology
for Evaluation of Contaminated Land
Selection of sampling
locations
7.5
From
the desktop study and site visit information collected, the need for a
contaminated land site investigation was determined. This information was used
to identify areas of potentially contaminated land. The approach taken in
selecting suitable locations for sampling and analysis took into account the
following factors.
·
The
extent to which the potentially contaminated land site overlapped with the KCRC
Scheme boundary.
·
The
form of the railway alignment at the location of each site (viaduct, cut and
cover, ramp or tunnel).
·
The
location of boreholes conducted for the Site Investigation (S.I.).
7.6
The sections of each
potentially contaminated land site which fall within the Spur Line Scheme
Boundary and may potentially be impacted by above ground activities are shown
on Figures 10.1, 10.2,
10.3, 10.4
and tabulated in Table 7.3. The figures also show the limits of the viaduct,
cut and cover and tunnel sections along the alignment. The locations of those
boreholes that are within potentially contaminated sites and will be used
for sampling and analysis under the Contamination Assessment Plan (Stage 1)
are highlighted in Figures 10.6,
10.7, 10.8,
10.9. These boreholes have
been located, to coincide (as far as possible), with the locations of identified
potentially contaminated areas during site visits. These potentially contaminated
areas are generally locations where staining has been noted from vehicles,
chemical storage areas, or spillage.
7.7
Figures
10.10, 10.11, 10.12,
10.13, 10.14,
10.15, 10.16,
10.17, 10.18
show detailed site layout and monitoring locations for the CAP investigation.
7.8
Where
no boreholes are available for sampling close to the potentially contaminated
site, a trial pit will be dug at the potentially contaminated area. The section
on sampling methodology outlines sampling procedures, including appropriate
depths.
7.9
In
some cases, access could not be gained during the site visits and the location
of the trial pit will need to be defined when the land has been resumed. At
this stage a Supplementary CAP will be submitted to EPD for approval of the
reviewed sampling locations. If access to the site confirms an absence of
potentially contaminating activities no sampling will be proposed. In this case
the CAP will recommend no further action. It however, contamination is
suspected, the contractor will carry out sampling after approval of the
Supplementary CAP and the results will be provided in a Supplementary CAR,
leading to a Supplementary RAP if necessary.
7.10
Table
7.3 details the locations of each borehole/trial pit to be sampled at Stage 1
and parameters chosen for testing at each site, and whether access is currently
possible.
Table
7.3
Chosen
Sampling Locations and Parameters
Site |
DH/TP No. |
Chosen Sampling Locations |
Chosen Parameters for Testing |
A |
DH/084 |
Adjacent to chemical waste point and
vehicle repairs area (plate 10.2) concrete is cracked and infiltration may
have occurred. |
Metals, CN, TPH and organics have been
chosen due to the varying vehicle maintenance activities and storage of
unknown chemical wastes in the vicinity. |
A |
DH/085 |
Adjacent to chemical stores and with
visible spillage of potential contaminants on ground. The vehicle repair area
at the east side of the site is unlikely to be affected by construction
works. |
Metals, CN, TPH and organics chosen due
to unknown nature of contaminants. |
A |
A-TP1 – A-TP3 |
Locations will be specified after
resumption of land when access is gained. One GP likely to be close to
vehicle washing area (plate 10.3) and oil drums (plate 10.4) |
Metals, CN, TPH and organics |
B |
DH/071 |
Located adjacent to and slightly below
a vehicle repair workshop. This is an area to which runoff is lively to have
occurred and is above a stream contaminated with similar runoff. |
Metals, TPH, CN and organics chosen
because of the nature of vehicle repair activities. |
B |
DH/076 |
Located inside a vehicle repair
workshop where drums of chemicals / petrol are stored (plate 10.8). There is
evidence of spills on the floors. |
Metals, TPH, CN and organics due to the
nature of vehicle repair activities and uncertain nature of stored chemicals. |
B |
B-TP1 - B-TP3 |
Inside vehicle repair workshop as
DH/071 |
As DH/071 |
C |
C-TP1 |
At the KCRC site boundary closest point
to the adjacent chemical store (Plate 10.13). Chemicals have been spilt and
may have dispersed this far. |
Metals, TPH and organics due to the
variety of contaminants which could be associated with the chemical store. |
D |
D-TP1 |
Hotspot located adjacent to stored
drums and where evidence of chemical / petroleum spillage can be seen (Plate
10.16). The indoor drum storage area has a concrete floor and spills would
have washed to the location of D-TP1. |
Metals, TPH and organics will all be
tested for due to the unknown contaminants which could have been spilt at this
site. |
E |
DH/051 |
Hotspot located adjacent to stored
petrochemical drums and where some oil spillage was noted (Plate 10.17). |
Metals and TPH chosen based on evidence
of activities occurring at this site. |
F |
DH/043 |
Located where spills of oils are visible. |
Metals and TPH chosen as basic
indicative parameters. Methylene chloride & Chloroalkanes will be tested
for. |
G |
DH/034 and G-TP1 & 2 |
Hotspot located adjacent to waste drums
(Plate 10.18) where chemical spills noted. |
Metals and TPH chosen as representative
of contaminants likely to be found due to the nature of container storage
activities. |
H |
H-TP1 & 2 |
Hotspot will be located where visual
inspections show possible metal contamination of land may have occurred(plate
10.20 & 21). |
Metals and TPH chosen as these are
likely to have been used in on site activities. |
I |
I-TP1 |
Located next to workshop area. |
Metals and TPH chosen as basic
indicative parameters. Total Sulphur will be tested for due to leather
treating activities at adjacent site. |
J |
J-TP1 |
Inside vehicle repair workshop. Located
where there is evidence of spillages. |
Metals, CN, organics and TPH chosen to
test for contamination from vehicle maintenance activities. |
K |
K-TP1 – 3 |
Adjacent to the suspected more
contaminated areas (to which access can not be gained). In an area where
containers are stored and maintained. Decision made on contamination testing
after resumption of land |
Metals and TPH |
L |
L-TP1 - 4 |
Adjacent to suspected contaminated
areas where chemicals are stored or scrap metal piled. Decision to be made
after resumption of land |
Metals and TPH |
Sampling Methodology
7.11
Prior
to a borehole being constructed, it is usual practice to dig an inspection pit
up to 3 m deep to verify the presence or absence of utilities. An
environmental scientist with experience in contaminated land assessment should
be on site to monitor the first few boreholes to confirm that the samples are
being taken at the right locations and in the correct manner. A visual
inspection of the trial pits will also enable the environmental scientist to
make a visual assessment of the likelihood of severe contamination.
7.12
It
is preferable that samples are taken from the trial pit as a visual assessment
of the ground material can be made more readily than a borehole and the exact
sample depth can be verified. If contamination is suspected at the base of the
trial pit, samples will be taken at greater depth from the borehole.
7.13
The
approach to sampling will be dependent on the section of the alignment and
construction methods to be used. In most sections, Stage 1 boreholes will be
sampled to 3 m depth. This is considered sufficient as excavation will be
to around 2 m depth. Any trial pits in the vicinity of future landscaped
areas will be sampled at 0.5 m as works will only affect the surface
layers.
7.14
Trial
pits and boreholes should be sampled at three depths each. These are 0.0 – 0.5m
depth, 1.0 – 1.5m depth and 2.5 – 3.0m depth, unless otherwise specified.
7.15
Table
7.4 describes the locations and number of boreholes and trial pits to be sampled,
the number of samples to take and the parameters to be tested. In all cases,
Total Petroleum Hydrocarbons (TPHs) will be analysed. In selected samples,
metals, cyanide and organics (chlorinated and non-chlorinated solvents,
aromatics and polyaromatic hydrocarbons (PAHs)) will be included in Stage 1
sampling. In sites such as container yards, organics are unlikely to be a
problem and are therefore not included in the parameter list. Some sites will
require organics testing. The results of these analyses will help to fine tune
the testing required for Stage 2 sampling and analysis.
7.16
At
sites where access has not been possible a rapid on-site assessment must be
made once land is resumed. This will confirm the likely extent of contamination
expected and propose the number of trial pits necessary. At present the number
of trial pits proposed is based purely on the area of likely contamination and
how many trial pits are proposed according to EPDs guidelines. Likewise, the
parameters for sampling will be confirmed and agreed with EPD, as current
proposed parameters are based on assumptions without having gained access to he
land. Locations within each such site will be finalised at this time dependant
on the activities causing potential contamination. This rapid assessment and
agreement with EPD will be particularly necessary at Site L, where the TBM
launching shaft is located.
7.17
In
addition, some sites have been included at this stage prior to final
confirmation of the above ground works. Some sites may be dropped from this
assessment at a later stage if no above ground works affect them , e.g. C, I
and J.
Table
7.4
Number
of Samples and Sampling Methods at
Each
of the Potential Contaminated Land Sites
Site & Lot No. |
Section |
Potentially
Contaminated land directly impacted by engineering works (m²) |
Sampling Number (Boreholes) |
Sampling Number (Trial Pits) |
Depth of Sampling |
Total number of
samples to be analysed |
Analysis Parameter For each sample |
A DD99/372S.D.RP |
Open
Ramp Section |
5,000 |
DH/085 DH/084 |
A-TP1 A-TP2 A-TP3 |
DH-3.0
m TP-3.0
m |
15 |
Metals,
CN, TPH and Organics |
B DD99/471-483,
486-493,527,
545-548 |
Recovery
Shaft and Cut and Cover section |
5,000 |
DH/076 DH/071 |
B-TP1 B-TP2 B-TP3 |
DH-3.0
m TP-3.0
m |
15 |
Metals,
TPH, CN and Organics |
C DD96/351-355,
425 |
Temporary
Works (TBC) |
TBC |
- |
C-TP1
|
0.5
m |
1 |
Metals,
TPH and Organics |
D DD96/428 |
Temporary
Works and Cross Passage |
100 |
- |
D-TP1 |
3.0
m |
3 |
Metals,
TPH and Organics |
E DD96/645 |
Cross
Passage |
250 |
DH/051 |
- |
3.0
m |
3 |
Metals
and TPH |
F DD
96/717, 718, 721 |
Cross
Passage |
100 |
DH/043 |
- |
3.0
m |
3 |
Metals
and TPH Selected
organics |
G DD95/
786, 791, 792, 772 (part) |
Kwu
Tung Station Box |
1500 |
DH/034 |
G-TP1 G-TP2 |
DH-3.0
m TP-3.0
m |
9 |
Metals
and TPH |
H DD96/
772 (part) |
Kwu
Tung Station Box |
600 |
- |
H-TP1 H-TP2 |
3.0
m |
6 |
Metals
and TPH |
I DD95/
803 S.A. ss. |
Kwu
Tung Station Box (TBC) |
TBC |
- |
I-TP1 |
3.0
m |
3 |
Metals
and TPH Total
Sulphur |
J DD95/
803 S.B. |
Kwu
Tung Station Box (TBC) |
TBC |
- |
J-TP1 |
3.0
m |
3 |
Metals,
CN and TPH Organics |
K DD95/
43 - 45, 53 – 59, 65 - 67, 70 – 74, 29 |
Cross
Passage |
800 |
- |
K-TP1 K-TP2 K-TP3 |
3.0m |
9 |
Metals
and TPH |
L
Government
Land at Sheung Shui |
Launching
Shaft |
5,000 TBC |
|
5
trial pits likely |
TP
– 3.0 m |
15 |
Metals
and TPH |
Remarks :
·
Metals analysis include all Dutch List Metals. TCLP tests
should also be carried out for metals.
·
CN - Cyanide
·
TPH is Total Petroleum Hydrocarbon
·
Organics (simple aromatics , non-halogenated and halogenated
solvents, polyaromatic hydrocarbons).
·
Trial pits carried out at the potential temporary works area
will only be sampled at 0.5m due to minimal earth moving activities at this
site.
·
TBC = To be confirmed
7.18
At
Stage 2, the aim will be to determine the extent of the contamination at sites
where contaminants have been detected. Where contaminants have been identified
an estimation of the depth and extent of contamination will be made based on
results obtained at Stage 1.
7.19
A
5m diameter will be assumed around each borehole/trial pit at which Dutch B
levels have been exceeded and this area will be excavated. A minimum of 5
samples, comprising 4 from around the boundary and 1 from the centre of the
base of excavation will be taken. Excavated material should be stockpiled and
bunded using appropriate measures while the 5 samples are tested. If Dutch B
levels are still exceeded excavation will be extended outwards in 0.5m
increments and further samples tested until levels below Dutch B standards are
reached.
7.20
Samples
will be tested for limited parameters dependent on previous exceedances of
Dutch B at the original Stage 1 location. Testing for TCLP will also be carried
out in the case of heavy metals if it has not been previously carried out. This
will determine the potential for disposal to landfill. To speed at works where
the programme is very tight (e.g. Site L) TCLP tests can be included in the Stage
1 testing.
7.21
In
addition, the depth of testing may be limited if construction works will not be
carried out at that particular area. For example, where any sites clearance
works will be carried out it may only be necessary to handle the upper 0.5 to 1 m
of soil. This will be decided by the Environmental Manager on Site. All further
sampling parameters and depths will be in accordance with this CAP.
7.22
The
proposed analysis programme is summarised below:
Two Stage Analysis Programme
Stage
1
Sampling
of all
potentially
contaminated areas
General Examination of TPH,
Heavy Metals (and Organics and CN for selected sites)
Evaluation
of Analytical Results
Not Contaminated Contaminated
Proceed with Project without Stage 2
any
Remediation Measures
Sampling
to determine extent
of contamination
Examination of Form of
Heavy Metals
PAH,
BTEX
if not previously determined
(TCLP)
Evaluation
Not
Contaminated Contaminated
Remediation
Remediation Remediation
Measures Measures Measures
for
non hazardous for
hazardous for
heavy
organics organics metals
Sampling Methods
7.23
There
are several methods that can be used to obtain samples of potentially
contaminated material within the ground. These are listed below:
·
Hand methods - usually for
depths up to 0.5 m by manual excavation or up to 5 m with a hand
auger. This usually produces only small, disturbed samples.
·
Trial
pits - can be used up to about 3 m depth. Allows easy collection of large
samples.
·
Light
cable percussion boreholes - traditional method for geotechnical soil
investigations. Can penetrate to 50 m depth and allow easy water
monitoring or gas wells to be inserted.
·
Power auger drilling - very
quick method, however samples are limited to around 6 m depth and are
disturbed.
7.24
Trial
pits are the most widely used technique, especially when sampling is required
to depths of less than 3 m. Care should be taken to avoid underground
services. It is likely that a combination of boreholes and trial pits can be
used for the Spurline Investigations.
7.25
For
borehole sampling, samples will be collected from the top, middle and bottom
(above rockhead) of the borehole as recommended in BSI DD175. The depth of the
samples will depend on the field sampling data. For trial pit sampling, samples
will be taken at three depths (e.g. 0.5 m, 1.5 m and 3 m). If
contamination is evident at 3 m depth, additional samples at greater
depths should be collected. Where groundwater is encountered, groundwater
samples should also be taken and records kept of the ground water level in the
trial pit. Photographic records should be kept of each borehole and trial pit
to show the gradient of pollution into the ground and the appearance of each
sample. The presence of any free product floating on the top of the groundwater
and the thickness should be recorded. The floating layer should be
removed/recovered and analysed.
7.26
All
soil samples should weigh not less than 0.5 kg and must be representative of
the location at which they are taken. Samples should be handled in an
appropriate manner so as to avoid cross contamination, and should be stored
between 0 - 4ºC. Cooling of samples containing volatile contaminants is
especially important. All samples should be properly labelled and any excess
sample kept for further testing if necessary. Sample containers should be
thoroughly cleaned between sampling of individual samples. It is important for
the sampling person to avoid direct or indirect contact with potentially
contaminated materials.
7.27
All
samples should be well contained, sealed, properly labelled and any excess
sample kept for further testing if necessary.
Parameters to be Tested for
Contamination
7.28
The
parameters to be tested at each proposed sampling location are based on the
expected contaminants related to the land use. Prior to sampling, an
examination of the site should be made by an environmental scientist
responsible for the sampling, to confirm whether additional or alternative
analyses are required apart from those listed in Table 7.
7.29
Waste
automotive oils which may be detected at container sites are composed of an
organic base with additives to increase performance. Additional compounds such
as chlorinated solvents may be present in the waste oils due to blending of
used oils during storage. The presence of such suspected carcinogens and
mutagens is the basis of concern about waste oils in the environment. The
sampling programme recommends that in Step 1 only total petroleum hydrocarbons
(TPH) are tested for, and organics and CN at certain specified sites. If
necessary, Polyaromatic hydrocarbons (PAHs) and Benzene, Toluene, Ethylbenzene
and Xylene (BTEX) will be required to be determined if Step 2 of the analysis
programme is to be implemented.
7.30
For
the inorganic analysis heavy metals according to the Dutch List (including Cd,
Cr, Cu, Hg, Ni, Pb, Zn etc) should be determined in addition to cyanides where
electroplating activities may have taken place.
Analytical Laboratory and
Methodology
7.31
The
laboratory for chemical analysis for the land contamination assessment should
achieve HOKLAS accreditation for environmental testing of sediment trace
metals: Cd, Cr, Cu, Ni, Pb, Zn and Hg and preferably for TPH, and organics
including PAHs and BTEX.
7.32
The
methodology should be compatible with international standard methods. Detection
limits should be to standards listed in Table 7.5.
Table
7.25
Detection
Limits of Parameters to be analysed in Soil
Parameter |
Detection Limit (mg/kg
dry soil) |
Metals: Cd, Cr Cu Hg Ni Pb Zn |
0.1 1.0 1.0 0.1 1.0 1.0 10 |
Total Petroleum
Hydrocarbons (TPH) |
20 |
Simple Aromatics: Benzene Toluene Ethylbenzene Xylene |
1.0 |
Polyaromatic
Hydrocarbons (PAH): Acenaphthene Acenaphthylene Anthracene Chrysene Pyrene Fluorene Naphthalene 1, 2 benzo-pyrene |
0.1 0.1 0.1 0.2 0.2 0.1 0.4 |
Cyanide |
5 |
Halogenated Solvents: Dichloromethane Carbon tetra-chloride Chloroform Trichloroethylene 1,1,1, Trichloroethane Tetrachloroethylene Dichloroethane Dibromoethane Dichlorobenzene |
1.0 |
Non-Halogenated
Solvents: Heptane Nonane Dimethyl Pentane Methyl Hexane Methyl Heptane Trimethyl Pentane Octane |
1.0 |
Evaluation of Potential
Impacts
7.33
The
interpretation of analytical results should be considered by comparing the data
with the Dutch Indicative List which is recommended by EPD in ProPECC PN 3/94
for interpretation of the analytical results.
7.34
The
soils, geology, groundwater and climate of Hong Kong are different to those of
the Netherlands. The reference values have been developed for use under these
specific conditions. The adsorption of pollutants to soil colloids may be
different under such conditions and therefore pose a different toxicity risk.
7.35
Appendix
A contains the Dutch list which should be considered carefully in terms of
application to the Hong Kong environment. It can be used as an indicative
measure of levels of contamination, qualitatively based on like groups of
contaminants, known landuses and possible pollutants.
Timing of Sampling and
Analysis
7.36
Where
possible all sampling should take place as soon as possible after the approval
of this CAP by EPD. Borehole and trial pit sampling can both be incorporated
into the Geotechnical Site Investigation Contracts. Following the SI, analysis
should be carried out immediately, before deterioration of samples occurs. The
CAR and RAP can then be prepared for those sites.
7.37
Where
access can not be gained to the sites sampling locations will be identified
after land resumption. The procedure is outlined in the Section on Selection of
Sampling Locations. It is expected that after resumption of the land, sampling
and analysis followed by the write up of CAR and RAP, and approval of these
reports by EPD would take a minimum of 3 months.
8.
REMEDIATION MEASURES TO BE
CONSIDERED IN THE REMEDIATION ACTION PLAN (RAP)
8.1
Following
approval of the CAP by EPD and completion of the sampling and analysis
programme, a Contamination Assessment Report (CAR) will be produced. The CAR
will detail the results of the implementation of the CAP and evaluate the
extent of the potential contamination on the site. Suitable means of minimising
the environmental impact from these areas of contamination should be defined.
If remediation of the land is required, the type of remediation should be
identified in a Remediation Action Plan (RAP).
8.2
The
selection of an appropriate remediation technique for a site is dependent on a
number of factors including:
(i) the type of contamination;
(ii) the extent of contamination;
(iii) the time available and speed of each
technique;
(iv) cost effectiveness;
(v) the future use of the site;
(vi) availability of expertise and
equipment.
8.3
There
are a range of options available for treating contaminated land sites and new
techniques are constantly being developed. The main methods in use are:
·
Retention and isolation of
material on-site using an appropriate form of cover, barrier or encapsulation
system.
·
Physical,
chemical or biological treatment to eliminate or immobilise the contaminants.
·
Removal of material from the
site for disposal elsewhere.
8.4
ProPECC
Note PN 3/94 also includes recovery trenches or wells for removal of leaked oil
and soil venting for volatile organic compounds (VOCs). It suggests that
“wherever possible, in-situ remedial measures should be adopted”. This policy
should be followed as far as possible in order to prevent increasing the
pressure on landfills.
8.5
Table
8.1 describes several techniques which would be applicable to contamination
expected within the works of the Spur Line.
Table
8.1
Remediation
techniques which could be used at sites along the Spur Line
Type of
Contamination |
Technique |
Oil – surface layers |
Bioremediation - in-situ or on site
degradation of organic pollutants to harmless CO2 & water
using microbes. Ranked 1 by Haiges (1989). Other bioremediation
techniques include adding cotton which absorbs the oils. Bacteria which occur
naturally in the cotton then degrades the oils before decomposing the cotton
into the soil and enriching it. Soil washing/flushing – addition
of a surfactant/solvent and flushing in-situ or washing excavated soil. The
oils and fluids separate out and the oily waste can then be bioremediated. |
Oil – above groundwater or at depth in the
soil. |
Recovery trenches or wells – used to
constrain groundwater flow so that oils settle and can be skimmed off. A dual
pump system uses a deep pump in the groundwater to create a depression cone
into which the free floating product will migrate. This can then be pumped
off. The dual pump system is ranked I by Haiges. Other
techniques include simpler pumps which extract both oils and water which can
then be separated at the surface.. |
Heavy hydrocarbons and oily sludges |
Thermal treatment - soil is excavated,
sorted and fed into a rotary kiln thermal unit and heated until combustion
occurs. The clean soil is then cooled and moistened and can be replaced. |
Cyanides |
Incineration – similar thermal
heating and combustion as for heavy hydrocarbons. Care must be taken to
ensure that air emissions achieve required standards. |
Heavy Metals |
Soil washing – soil is passed
through sieves and scrubbers using water or oxidising chemicals which leach
the contaminants out. The sludge residue can then be disposed of at a
chemical waste treatment plant. Discharge of washed water must comply with
WPCO standards. Stabilisation – contamination can
be permanently isolated using lime, cement, thermoplastic or soluble silicate
reagents to chelate metal ions to soil colloids. The soil is excavated,
sorted and injected with the reagent before replacing and compacting to high
density. |
Volatile Compounds |
Soil Venting – contaminant are
removed through extraction wells using a vacuum which enhances chemical
movement from soil particles to air pockets. Air Sparging – mainly used to remove
volatiles from groundwater by injecting air into the saturated zone and
transferring the contaminants to the vadose zone from which they can be
vented. |
Microbiological |
Incineration – to eliminate any
toxic micro-organisms or bacterias, such as anthrax spores, the only
consistently dependable method is incineration. |
Broad spectrum of contaminants |
Excavation and Landfilling – best used
for shallow contaminants and one off excavations. Because of limits on
contaminants that can be disposed of in landfills (based on TCLP)* pre
treatment may be required by another method (e.g. bioremediation) prior to
disposal. |
NOTE:
Haiges (1989) rated techniques from 1 (best) to 8 (worst) for treatment of oil contaminated soils on the basis of technical feasibility, achievable treatment levels, adverse impacts, cost and time taken.
* TCLP -
Toxicity Characteristic Leaching Procedure Limits - as outlined in the Guidance
notes issued by EPD (1999).
9.
APPLICATION OF CONTAMINATION
ACTION PLAN TO SPUR LINE
9.1
From
the desktop study, site survey and generic methodology for sampling and
analysing pollutants from potentially contaminated sites, a number of sites
along the Spur Line alignment have been identified as being potentially
contaminated.
9.2
An
estimate has been made of the quantity of contaminated land which may be
present at each site (Table 9.1). This is based on site visits, the extent of
the area used at each site, and the assumption that the contamination has
penetrated to a depth of approximately 1 m from the ground surface. Where
cross passages are located, it is assumed that only the surface area around
location of jet grouting will be impacted during construction. Where quantities
of material are too small to make physico-chemical or biological treatment
cost-effective, disposal of the material may be considered. In this case, if
heavy metals are found present, TCLP testes must be carried out.
9.3
The
total quantity of contaminated land is estimated at this stage of the
assessment, to be up to 18,300 m³. This volume needs to be confirmed through
implementation of the CAP and the sampling and analysis programme during site
investigation, at which time the quantities requiring remediation or disposal
will be more accurately defined.
9.4
Where
volumes are relatively small and/or contaminant level is low, disposal may be a
preferable option. Where volumes are large and/or contaminant levels are high,
remediation techniques should be considered as a cost effective and
environmentally favourable option.
Table
9.1
Main
Activities at Each Site, Contaminants Likely to be
Present
and Maximum Possible Extent of Contamination
Site |
Main
Activities |
Structure or Works Impacting Area |
Estimated Maximum quantity (m³) |
Main Contaminants Likely to be present |
A |
Container
Storage |
Ramp and Viaduct |
5,000 |
Metals,
fuels/oils, acids, cyanides |
B |
Container
Storage |
Recovery Shaft |
5,000 |
Metals,
fuels/oils, acids, cyanides |
C |
Chemical
Store |
Miscellaneous Storage
Area (TBC) |
TBC |
Organics,
oils, metals, solvents |
D |
Pig Farm |
Cross Passage |
100 |
Metals,
microbacteriological |
E |
Farm
Buildings |
Cross Passage |
250 |
Metals,
microbiological |
F |
Chemical
Storage |
Cross Passage |
100 |
Organics,
solvents, metals, oils |
G |
Container
Storage |
Kwu Tung Station Box |
1,500 |
Metals,
fuels/oils, acids, cyanides |
H |
Metal
Recycling |
Kwu Tung Station Box |
600 |
Metals, TPH
|
I |
Storage |
Kwu Tung Station Box
(TBC) |
TBC |
Organics,
solvents, metals, oils |
J |
Car
Repairs/ Dismantling |
Kwu Tung Station Box
(TBC) |
TBC |
Metals,
cyanides, organics, fuels/oils, acids |
K |
Vehicle
Maintenance |
Cross Passage |
800 |
Metals,
cyanides, organics, fuels/oils, acids |
L |
Scrap Metal
Yard |
Launching Shaft |
5,000 TBC |
Metals,
fuels/oils |
Total
volume (m³) |
|
18,350 m³ |
|
Precautionary Measures to be
Taken during Construction
9.5
The
following measures should be implemented to minimise risks to workers during
remediation works, excavation of soil, construction of viaducts, jet grouting
for cross passages, piling works or excavation of Kwu Tung station and
construction of the EAPs. These measures will also mitigate against
transferring contamination to groundwater, to surface water courses or to the
air.
·
Site
workers should wear gloves, masks, and other protective clothing where exposure
to vapours or contaminated soil may be encountered.
·
Contaminated
materials should be moved with bulk earth movers to prevent human contact.
·
Adequate
washing facilities should be provided and smoking/eating should be prohibited
in the area.
·
Contaminated
sediments which have been stockpiled or are being transported should be covered
with tarpaulin.
·
Leakage
of pollutants or leaching from excavated soil should be prevented by storing on
an impermeable surface.
Temporary Works Areas
9.6
Temporary
works areas are proposed in the Sheung Shui area which have previously been
used as container parking areas. The site inspection showed that, as is typical
of such landuses there has been some leakage of oils and lubricants. However,
these sites should not pose a health risk during their use in the construction
phase provided there are no earth moving activities at the sites. The leaked
oil can be covered with a layer of gravel or sawdust to soak up the leaks, and
the materials disposed of appropriately. However, if earth movement is carried
out, the precautionary measures detailed above should be followed.
10.
OTHER PROJECTS IN THE STUDY
AREA
10.1
The
recently publicised Kwu Tung NDA under the NENT Planning Study also has the
potential to be impacted by contaminated land. The findings and recommendations
of the Spur Line EIA should be taken into account in the EIA for the NDA, and
in the development of a CAP for the NDA. In this way, the information available
about areas which overlap the two projects will be maximised and potential
environmental impacts minimised.
11.
SUMMARY
11.1
This
contaminated land assessment includes a desktop study on relevant past and
present landuses, a site survey, an assessment on the findings and
recommendations on a schedule of sampling / analysis of essential parameters
and appropriate remediation measures. Application of the sampling/analysis
programme to specific sites identified to have potential contamination along
the Spur Line alignment is included.
11.2
No
underground storage tanks or extensive areas of contaminated land have been
identified in this assessment within the works area of the alignment. The main
areas for concern are container storage areas, particularly those in DD99 close
to Lok Ma Chau (A and B), and any car repair/dismantling yards (e.g. J). The
main contaminants are likely to be oils, organic solvents and heavy metals.
11.3
A
Contamination Assessment Plan is presented which outlines the methods for
sampling and analysis of the identified potentially contaminated sites, and
criteria for evaluation.
11.4
Remediation
measures for different types of potentially contaminated land are recommended,
however, the small quantities which have been identified for several sections
of the alignment make remediation too costly to be effective, and disposal
should be considered. It is estimated that the maximum quantity of material in
areas of potential contamination, which may require treatment or disposal is
approximately 18,350 m³. These quantities and the degree of contamination need
to be confirmed at the site investigation stage when analytical results are
available for production of the CAR.
REFERENCES
Holdgate, M.W., (1979) A Perspective of Environmental Pollution, University
Press, Cambridge.
Royal Commission on
Environmental Pollution (RCEP), (1984), 10th
Report: Tackling Pollution - Experience and Prospects, Cmnd 9194, HMSO,
London.
LaGrega M.D., Buckingham P.L
& Evans J.C. (1994), Hazardous Waste
Management, McGraw-Hill, Singapore.
Cairney T (ed) (1993), Contaminated Land: Problems and Solutions,
Chapman & Hall, London.
EPD (1999), Guidance Notes for Investigation and
Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards or Car
Repair/Dismantling Workshops. Report EPD/TR1/99
Voelcker Science (1999) Guide to Contamination Packages
HSE (1998), Protection of Workers and the General Public
during Development of Contaminated Land.
http://www.ContaminatedLAND.co.uk/
- Pages on Past Industrial uses, Causes
of Contamination, Standards and Guidelines, Remediation Techniques
British Standards Institution
(1988), Draft for Development DD175: 1988
Code of Practice for the Identification of Potentially Contaminated Land and
its Investigation, BSI, London.
Kelly R.T. (1980) Site
Investigation and Material Problems, in: Reclamation
of Contaminated Land, B21-B2-13, Society of Chemical Industry.
Haiges L et al. (1989) Evaluation of underground fuel spill clean-up
technologies, in Haztech International
Conference, San Francisco.
ProPECC PN 3/94. Environmental
Protection Department. Practice Note for Professional Persons: Contaminated
Land Assessment and Remediation.