Table A1 Preliminary Construction Programme      
     
Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Period Descriptions 03 03 03 03 03 04 04 04 04 04 04 04 04 04 04 04 04 05 05 05 05 05 05 05 05 05 05 05 05 06 06 06 06 06 06 06 06 06 06 06
     
YL/KT Sewerage - Designated and Potential Designated Elements      
Aug 03 - Feb 06 Package 1A-1T                
Aug 03 - Nov 03 General Site Clearance/Demolition Works        
     
Dec 03 - Aug 05 Construction of Sewage Pumping Stations - P1, P2 & P3            
     
Aug 03 - Feb 06 Construction of Sewers and Rising Mains - S2, S4, S5 & S6              
     
Jun 04 - Nov 06 Package 1B-1T            
Jun 04 - Sep 04 General Site Clearance/Demolition Works        
     
Oct 04 - Jan 06 Construction of Sewage Pumping Stations - P4, P5, P6 & P7          
     
Jun 04 - Nov 06 Construction of Sewers and Rising Mains - S1             
     
YL/KT Sewerage - Non-Designated Elements      
Aug 03 - Feb 06 Package 1A-1T      
Construction of Sewers and Rising Mains - S3 & S7                
Jun 04 - Nov 06 Package 1B-1T      
Construction of Sewers and Rising Mains - S3            
Aug 04 - Feb 08 Package 1A-2T      
Construction of Sewers and Rising Mains - S8            
     
Other Concurrent Projects      
Jun 01 to Dec 03 6246 TH - Kam Tin Bypass        
     
Nov 02 to Nov 05 70CD - Yuen Long Bypass Floodway            
     
Dec 05 to Dec 08 215DS - YLKT SSDS stage 2 Ngau Tam Mei /San Tin Trunk sewerage Phase 1 & 2          
     
Jan 04 to Jun 06 92CD - Yuen Long, Kam Tin, Ngau Tam Mei and Tin Shui Wai Drainage Improvement Stage 1 - Phase 2            
     
     