8                                            WASTE MANAGEMENT

8.1                                      Introduction

This section sets out the handling, recycling, storage, transportation and disposal measures which are recommended to avoid or minimise potential adverse impacts associated with waste arising from the construction of the Designated and Potentially Designated Elements.

8.2                                      Waste Management Practices

The Construction Contractor(s) should incorporate these recommendations into a Waste Management Plan for the construction phase of the Project. Such a management plan should incorporate site specific factors, such as the designation of areas for the segregation and temporary storage of reusable and recyclable materials.

Possible waste arising during the construction phase will include dredged/excavated sediment, construction waste, chemical waste and general refuse.

The Implementation Schedule in Annex E, provides details on the appropriate mitigation measures for avoiding and minimising potential adverse impacts associated with waste arising from the construction of the Project and the associated developments.  The Waste Management Plan should be refined and updated as more detailed information is generated on the volume of dredged/excavated sediment. Similarly, it should be regularly reviewed, and updated as appropriate, throughout the course of the construction works to ensure that it remains current with the latest detailed information and works practices. 

It is the Contractor’s responsibility to ensure that only approved licensed waste collectors are used and that appropriate measures to minimise adverse impacts, including windblown litter and dust from the transportation of these wastes are employed.  In addition, the contractor must ensure that all the necessary waste disposal permits are obtained and complied with.

The Waste Management Plan should also outline the requirements for a waste audit programme to ensure the measures outlined in the plan are effectively implemented and adhered too.

8.3                                      EM&A Recommendations

In order to ensure that the Contractor has implemented the recommendations of the EIA, the IEC shall conduct regular site audits of each of the waste streams, to determine if wastes are being managed in accordance with the approved procedures and the site waste management plan.  The scope of the waste management audits is presented below.

8.3.1                                Objectives of the Waste Audit

The aims of the waste management audit will include, but are not limited to, the following:

·         ensuring that the wastes arising from works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner and comply with the relevant requirements under the Waste Disposal Ordinance (WDO) and its regulations;

·         ensuring that the Contractor properly implements the appropriate environmental protection and waste pollution control mitigation measures, as outlined in the Implementation Schedule (Annex E) to minimise and control the potential for waste impacts;

·         ensuring the effective implementation of the Contractor’s Environmental Management System (EMS) and waste management plan;

·         ensure the Contractor(s) enforce strict application of the public fill license and monitor the material placed in the reclamation and barges to control disposal of unauthorised material.  Also to ensure the Contractor provide floating booms and collect any floating materials on a daily basis at the public filling area.

·         to monitor the disposal of construction and demolition material and solid wastes at public filling facilities and landfills, and to control fly-tipping, a trip-ticket system should be included as one of the contractual requirements and implemented by the Environmental Team during the EM&A programme.  The IEC should be responsible for auditing the result of the system; and

·         to encourage the reuse and recycling of materials.

8.3.2                                Methodology and Criteria

The Contractor should ensure that the necessary waste disposal permits or licences are obtained from appropriate authorities in accordance with the various Ordinances.  In addition to the IEC audits, the Contractor and his ET Leader should also regularly inspect and audit the waste management practices on site with reference to the recommendations given in the Implementation Schedule contained in Annex E.

General Legislation for Waste Management

·       Waste Disposal Ordinance (Cap 354);

·       Waste Disposal (Chemical Waste) (General) Regulation (Cap 354);

·       Land (Miscellaneous Provisions) Ordinance (Cap 28);

·       Public Health and Municipal Services Ordinance (Cap 132) - Public Cleansing and Prevention of Regulation;

·       Dumping at Sea Ordinance (1995); and,

·       The storage, handling and disposal of chemical waste should be audited with reference to the requirements of the Code of Practice on the Package, Labelling and Storage of Chemical Wastes published by the EPD.

Other Relevant Guidelines

Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch Government Secretariat;

Environmental Guidelines for Planning In Hong Kong (1990), Hong Kong Planning and Standards Guidelines, Hong Kong Government;

New Disposal Arrangements for Construction Waste (1992), Environmental Protection Department & Civil Engineering Department;

Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), Environmental Protection Department;

Works Branch Technical Circular, 32/92, The Use of Tropical Hard Wood on Construction Site; Works Branch, Hong Kong Government;

Works Branch Technical Circular Nos. 2/93, 2/93B, Public Dumps, Works Branch, Hong Kong Government;

Works Branch Technical Circular No. 16/96, Wet Soil in Public Dumps; Works Branch, Hong Kong Government;

Works Bureau Technical Circular Nos. 4/98,  4/98A, Use of Public Fill in Reclamation and Earth Filling Projects; Works Bureau, HK SAR Government;

Works Bureau Technical Circular No 5/98, On-site Sorting of Construction Waste on Demolition Site; Works Bureau, HK SAR Government;

Waste Reduction Framework Plan, 1998 to 2007, Planning, Environment and Lands Bureau, Government Secretariat, 5 November 1998;

Works Bureau Technical Circular Nos. 5/99, 5/99A Trip-ticket System for Disposal of Construction and Demolition Material; Works Bureau, HK SAR Government;

Works Bureau Technical Circular No 19/99,Metallic Site Hoardings and Signboards; Works Bureau, HK SAR Government;

Work Bureau Technical Circular Nos. 25/99, 25/99A, 25/99C Incorporation of Information on Construction and Demolition Material Management in Public Works Sub-committee Papers; Works Bureau, HK SAR Government;

Works Bureau Technical Circular No. 12/2000, Fill Management; Works Bureau, HK SAR Government;

Works Bureau Technical Circular No 29/2000, Waste Management Plan. Works Bureau, Hong Kong SAR Government; and

Works Bureau Technical Circular No 31/2000, Specification Allowing the Use of Recycled Inert Construction and Demolition Material. Works Bureau, Hong Kong SAR Government.

8.4                                      Mitigation Measures

Details of the recommended mitigation measures are included within the Implementation Schedule (Annex E).

 

                                                              Back to Contents