5.1
Identified Sensitive Receivers
5.1.1
Representative
Noise Sensitive Receivers (NSRs) have been identified in accordance with
criteria set out in the Environmental Impact Assessment Ordinance (EIAO) and
Technical Memorandum on the Environmental Impact Assessment Process (TMEIA).
5.1.2
Preliminary
NSRs have been identified in an area 300m either side of the full stretch of
the proposed roads. Existing noise
sensitive receivers who may be adversely affected by increases in noise as a
result of the construction and operation of the improved Tung Chung Road are
listed in Table 5.1. The representative NSRs can also be seen in Figures 5.1a
to 5.1g. The density of village
properties in the Tung Chung Valley, Ha Ling Pei and Wong Ka Wai, has made it
necessary to allocate further sensitive receivers in this area for the
assessment of construction noise for permanent noise barrier construction and
operational noise impacts. The
additional sensitive receivers in this area are shown in Figure 5.3a. Visitors to the country park are also
potentially sensitive to impacts but as no permanent facilities, such as camp
grounds, are affected and all other visitors would be transient in nature, no
significant impacts are predicted.
5.1.3 In addition to the above, the Cheung Sha Layout Plan – Lantau Island, Plan No. L/I-CS/1, has identified several future sales sites in the vicinity of the junction of the new Tung Chung Road with the South Lantau Road. These sites have been allocated for future low rise 2 storey residential development. The boundaries of the site are indicative only and the layout of the properties is not known at this time. However, representative locations at the sites which are closest to the proposed road have been selected at the site boundaries in order to assess the potential impacts to any future receivers, as shown on Figure 5.1e. The properties will not be constructed and occupied until after the opening of the proposed widened Tung Chung Road and as such the representative ASRs are relevant to the operational phase of the project only.
Table 5.1: Noise Sensitive Receivers
Figures
No. |
NSR Ref. |
NSR |
No. of
Floor |
Shortest
Slant Distance (m) |
Description |
|
5.1a/5.3a |
SR1 |
8, Ha Ling Pei |
3 |
235 |
Residential |
|
SR2 |
7, Wong Ka Wai |
3 |
119 |
Residential |
||
SR3 |
Village House |
3 |
256 |
Residential |
||
SR4 |
8, Lung Tseng Tau |
3 |
56 |
Residential |
||
SR5 |
Village House |
3 |
168 |
Residential |
||
5.1b |
SR6 |
41, Shek Lau Po |
3 |
246 |
Residential |
|
SR7 |
Village House |
3 |
198 |
Residential |
||
SR8 |
1, Shek Mun Kap |
3 |
230 |
Residential |
||
5.1c |
SR9 |
AFCD Staff Quarters |
1 |
156 |
Residential |
|
|
|
|
|
|
|
|
5.1d |
SR10 |
74, Leyburn Villas |
2 |
298 |
Residential |
|
5.1e |
SR11 |
12, Cheung Sha Sheung Tsuen |
3 |
277 |
Residential |
|
SR12 |
32, Cheung Sha Sheung Tsuen |
3 |
266 |
Residential |
||
SR13 |
31B, South Lantau Road |
2 |
35 |
Residential |
||
SR14 |
Village House |
2 |
153 |
Residential |
||
SR15 |
YWCA Youth Camp |
1 |
55 |
Residential |
||
5.1f |
SR16 |
Block 1, Acacia Villa |
3 |
161 |
Residential |
|
SR17 |
37, South Lantau Road |
3 |
234 |
Residential |
||
SR18 |
39, South Lantau Road |
3 |
289 |
Residential |
||
5.1g |
SR19 |
Block 17, Butterfly Crest |
3 |
# |
Residential |
|
Additional Sensitive Receivers in Tung Chung Valley |
||||||
5.3a |
SR1A |
10, Ha Ling Pei |
3 |
273 |
Residential |
|
SR1B |
8, Ha Ling Pei |
3 |
256 |
Residential |
||
SR1C |
7, Ha Ling Pei |
3 |
215 |
Residential |
||
SR2A |
14, Wong Ka Wai |
3 |
165 |
Residential |
||
SR2B |
9, Wong Ka Wai |
3 |
132 |
Residential |
||
SR2C |
7, Wong Ka Wai |
3 |
99 |
Residential |
||
SR2D |
3A, Wong Ka Wai |
3 |
83 |
Residential |
||
SR4A |
10A, Lung Tseng Tau |
3 |
60 |
Residential |
||
SR4B |
7, Lung Tseng Tau |
3 |
45 |
Residential |
||
SR4C |
13, Lung Tseng Tau |
3 |
55 |
Residential |
||
SR4D |
28, Lung Tseng Tau |
3 |
34 |
Residential |
||
Future Sensitive Receivers in Cheung Sha(1) |
||||||
5.1f |
CS1 |
Cheung Sha future sale site
|
2 |
35(2) |
Residential |
|
CS2 |
Cheung Sha future sale site
|
2 |
32(2) |
Residential |
||
CS3 |
Cheung Sha future sale site
|
2 |
56(2) |
Residential |
||
CS4 |
Cheung Sha future sale site
|
2 |
53(2) |
Residential |
||
CS5 |
Cheung Sha future sale site
|
2 |
25(2) |
Residential |
||
CS6 |
Cheung Sha future sale site
|
2 |
20(2) |
Residential |
||
CS7 |
Cheung Sha future sale site
|
2 |
20(2) |
Residential |
||
CS8 |
Cheung Sha future sale site
|
2 |
25(2) |
Residential |
||
CS9 |
Cheung Sha future sale site
|
2 |
29(2) |
Residential |
||
CS10 |
Cheung Sha future sale site
|
2 |
33(2) |
Residential |
||
CS11 |
Cheung Sha future sale site
|
2 |
50(2) |
Residential |
||
CS12 |
Cheung Sha future sale site
|
2 |
22(2) |
Residential |
||
CS13 |
Cheung Sha future sale site
|
2 |
42(2) |
Residential |
||
Note: # The distance between SR19 and the improved
Tung Chung Road is more than 500m and thus it will only be potentially affected
by the slope remediation works on the obsolete sections of the existing Tung
Chung Road during the construction phase
(1): Future sensitive receivers relevant to the operational phase only.
(2):
Based upon assumed locations of sensitive receivers only and site boundaries
are indicative.
5.1.4
All the sensitive receivers are residential and, thus,
the noise criteria for general construction work during normal working hours
(0700 to 1900 hours on any day not being Sunday and Public Holiday) will be 75
dB(A) (Leq (30mins)) and 70 dB(A) (L10(1hour)) for the
operational phase as detailed in Section 3.
5.1.5
The Remaining Development in Tung Chung and Tai Ho
Comprehensive Feasibility Study has also proposed sensitive development on the fringes of Tung Chung,
close to the northern edge of the project and these could be adversely affected
by the operation of the improved Tung Chung Road. The impacts on these
sensitive receivers are reported separately in Section 12 of this report.
5.2.1
The
majority of the proposed road, with the exception of the northern and southern
end, is situated within very quiet rural areas, with the surrounding land
comprising country parks, open space and agricultural activities. Noise levels for the majority of the study
area are very low, the only major noise sources is the traffic of existing Tung
Chung Road.
5.2.2
Noise
levels at the northern end of the alignment in Tung Chung are influenced by
traffic from the Yu Tung Road and existing Tung Chung Road. The southern end of the alignment connects
with the South Lantau Road and thus, noise levels in this area are higher due
to the presence of road traffic.
5.3.1
Construction Activities
5.3.1.1
The
construction equipment for each stage of the project has been determined and
the sound power level (SWL) of each piece of equipment is based upon the Technical Memorandum on Noise From
Construction Work Other Than Percussive Piling and BS5228 when the SWL are not listed in the Technical
Memorandum. No percussive piling is
anticipated for the Project.
5.3.1.2
The
construction activities for the Project can be divided into four broad areas,
namely roadworks and bridgeworks for the main alignment, slope stabilisation
works and slope remediation works for the obsolete section of the existing Tung
Chung Road. The key construction
activities within these broad activities will include:
(i)
Roadworks - earthworks
(including
utility works) - retaining wall construction (required
for all
areas
not on structure); and
-
pavement
construction.
(ii) Bridgeworks: - foundation
construction; and
- deck construction.
(iii) Slope Stabilisation - soil
nailing/rock dowelling; and
-
equipment
transportation.
-
(iv) Slope Remediation - earthworks;
and
-
slope
nailing.
(v) Noise Mitigation - foundation
construction; and
- erection.
5.3.1.3
The
individual pieces of equipment required for each of these stages have been
highlighted in Section 2. The
construction plant has been further divided into working scenarios for each of
the broad construction activities as detailed in Table 5.2 below:
Table 5.2: Equipment
Scenarios
Main Activity |
Sub-Activity |
Equipment Scenario |
Scenario Reference |
Roadworks |
Earthworks(1) |
Scenario 1 - Rock/earth excavation |
E1 |
Scenario 2 - Removal
/spreading of earth/rock |
E2 |
||
Scenario 3 - Forming of earthworks. |
E3 |
||
Retaining Wall Construction |
Scenario 1 - Foundation works |
R1 |
|
Scenario 2 - Piling |
R2 |
||
Scenario 3 - Formwork/concreting. |
R3 |
||
Scenario 4 - Backfilling Works |
R4 |
||
Pavement Construction (1) |
Scenario 1 - Preparation of Roadbase |
P1 |
|
Scenario 2 - Laying of Surface Material |
P2 |
||
Scenario 3 - Road Marking |
P3 |
||
Bridgeworks |
Foundation Construction |
Scenario 1 - Excavation |
F1 |
Scenario 2 - Piling |
F2 |
||
Scenario 3 - Formwork |
F3 |
||
Scenario 4 - Concreting |
F4 |
||
Deck Construction |
Scenario 1 - Formworks |
D1 |
|
Scenario 2 - Concreting |
D2 |
||
Scenario 3 - Deck elevation |
D3 |
||
Slope(2) Stabilisation |
Rock Dowelling |
Scenario 1 – Rock dowelling |
SS1 |
Equipment Transportation |
Scenario 1 – Delivery by helicopter |
SS2 |
|
Slope (2) Remediation |
Earthworks |
Scenario 1 – Earthworks |
SR1 |
Slope Nailing |
Scenario 1 – Slope Nailing |
SR2 |
|
Noise Mitigation |
Foundations and Erection |
Scenario 1 – Foundation Works |
NB1 |
Scenario 2 – Piling |
NB2 |
||
Scenario 3 – Formwork/Concreting |
NB3 |
||
Scenario 4 – Backfilling Works |
NB4 |
||
Scenario 5 - Erection |
NB5 |
Notes (1):
Includes minor works associated with utilities.
(2):
No drainage works are required for the slope stabilisation works. Noise associated with the drainage and
shotcreting works for the remediation of slopes on the existing Tung Chung Road
are considered to be minor but covered in Table 5.8d.
5.3.1.4 The equipment included in each of these scenarios, together with the appropriate sound power levels are provided in Tables 5.3 to 5.7 below for roadworks, bridge works, slope stabilisation works, slope remediation works and noise mitigation works respectively. As noted, in Section 2.7.2, the equipment lists have been confirmed by the Project Proponent as being practical for completing the works.
Table 5.3: Typical Equipment Requirement for Road Construction
CNP Equipment Code |
Equipment
Scenario |
Sound
Power Level
(SWL) in dB(A) |
Number of
Equipment |
Total
Sound Power Level (SWL) in dB(A) |
Earthworks |
||||
Scenario
E1 |
Excavation
of earth / rock and removal |
|||
028 |
Breaker |
122 |
2 |
125.9 |
067 |
Dump Truck |
117 |
1 |
|
081 |
Excavator |
112 |
1 |
|
282 |
Water Pump (Petrol) |
103 |
1 |
|
Scenario
E2 |
Spreading
of earth / rock |
|||
030 |
Bulldozer |
115 |
1 |
119.5 |
067 |
Dump Truck |
117 |
1 |
|
204 |
Scraper |
109 |
1 |
Scenario
E3 |
Forming of earthworks |
|||
030 |
Bulldozer |
115 |
1 |
120.7 |
104 |
Grader |
113 |
1 |
|
067 |
Dump Truck |
117 |
1 |
|
186 |
Roller Vibratory |
108 |
1 |
|
050 |
Compactor |
105 |
1 |
|
169 |
Power Rammer (Petrol) |
108 |
1 |
|
Retaining wall construction |
||||
Scenario
R1 |
Foundation
works |
|
||
028 |
Breaker |
122 |
2 |
125.9 |
067 |
Dump Truck |
117 |
1 |
|
081 |
Excavator |
112 |
1 |
|
282 |
Water Pump (Petrol) |
103 |
1 |
|
Scenario
R2(1) |
Piling |
|
|
|
164 |
Piling Rig |
115 |
1 |
116.9 |
282 |
Water Pump |
103 |
1 |
|
141 |
Lorry |
112 |
1 |
|
165 |
Piling, large diameter bored, oscillator * |
115 |
1 |
|
Scenario
R3 |
Formwork /
concreting |
|||
044 |
Concrete Lorry Mixer |
109 |
1 |
117.9 |
170 |
Poker |
113 |
1 |
|
101 |
Generator |
108 |
1 |
|
201 |
Saw, circular |
108 |
1 |
|
282 |
Water pump |
103 |
1 |
|
043 |
Chipper |
112 |
1 |
|
066 |
Dumper |
106 |
1 |
|
|
|
|
|
|
|
|
|
|
|
CNP Equipment Code |
Equipment Scenario |
Sound
Power Level
(SWL) in dB(A) |
Number of
Equipment |
Total
Sound Power Level (SWL) in dB(A) |
Scenario
R4 |
Backfilling
works |
|||
050 |
Compactor Vibratory |
105 |
1 |
117.8 |
067 |
Dump Truck |
117 |
1 |
|
186 |
Roller Vibratory |
108 |
1 |
|
|
Pavement Construction |
|
||
Scenario
P1 |
Preparation of Roadbase |
|||
186 |
Vibratory roller |
108 |
1 |
118.6 |
067 |
Dump truck |
117 |
1 |
|
081 |
Excavator |
112 |
1 |
|
Scenario
P2 |
Laying of
Surface Material |
|
||
004 |
Asphalt paver |
109 |
1 |
119.0 |
185 |
Road roller |
108 |
1 |
|
067 |
Dump Truck |
117 |
1 |
|
186 |
Vibratory roller |
108 |
1 |
|
044 |
Concrete Lorry Mixer |
109 |
1 |
|
Scenario P3 |
Road
Marking |
|
||
161 |
Paint line marker |
90 |
1 |
115.0 |
203 |
Saw |
115 |
1 |
* The
piling oscillator will be required to be used with the piling rig (CNP
164). However, as these pieces of
equipment will be used alternately and never concurrently, the total SWL has
been based upon the SWL of only one piece of equipment (ie one SWL of 115
only).
(1) The
equipment which will be used for the detailed ground investigation will be
similar to that required for the bored piling.
However, the bored piling rig will be noisier than the rig used for the
ground investigation.
Table 5.4: Typical Equipment Requirement for Bridge Construction
CNP Equipment
Code |
Equipment
Scenario |
Sound
Power Level
(SWL) in dB(A) |
Number of
Equipment |
Total
Sound Power Level (SWL) in dB(A) |
Deck Construction |
||||
Scenario
D1 |
Formwork |
|
||
021 |
Bar Bender and cutter |
90 |
1 |
119.8 |
171 |
Planer |
117 |
1 |
|
101 |
Generator |
108 |
1 |
|
201 |
Saw |
108 |
1 |
|
043 |
Chipper, hand-held |
112 |
1 |
|
141 |
Lorry |
112 |
1 |
|
Scenario
D2 |
Concreting |
|||
044 |
Concrete lorry mixer |
109 |
1 |
115.5 |
047 |
Concrete pump |
109 |
1 |
|
170 |
Poker |
113 |
1 |
|
Scenario
D3 |
Elevation |
|
||
048 |
Crane |
112 |
1 |
112.0 |
|
||||
Foundation/Pier Construction |
||||
Scenario
F1 |
Excavation |
|||
027 |
Breaker |
122 |
2 |
125.9 |
067 |
Dump truck |
117 |
1 |
|
081 |
Excavator |
112 |
1 |
|
282 |
Water Pump |
103 |
1 |
|
Scenario
F2 |
Piling |
|
||
164 |
Piling Rig |
115 |
1 |
119.1 |
283 |
Water Pump |
85 |
1 |
|
067 |
Dump Truck |
117 |
1 |
|
165 |
Piling, large diameter bored, oscillator* |
115 |
1 |
|
Scenario
F3 |
Formwork |
|||
021 |
Bar Bender |
90 |
1 |
118.0 |
171 |
Planer |
117 |
1 |
|
101 |
Generator |
108 |
1 |
|
201 |
Saw |
108 |
1 |
|
Scenario
F4 |
Concreting |
|
||
047 |
Concrete pump |
109 |
1 |
115.5 |
044 |
Concrete lorry mixer |
109 |
1 |
|
170 |
Poker |
113 |
1 |
* The
piling oscillator will be required to be used with the piling rig (CNP
164). However, as these pieces of
equipment will be used alternately and never concurrently, the total SWL has
been based upon the SWL of only one piece of equipment (ie one SWL of 115 dB(A)
only).
Table 5.5 Typical Equipment Requirement for Slope Stabilisation Works
CNP Equipment
Code |
Equipment
Scenario |
Sound
Power Level
(SWL) in dB(A) |
Number of
Equipment |
Total
Sound Power Level (SWL) in dB(A) |
Rock Dowelling |
||||
Scenario
SS1 |
Rock
Dowelling |
|||
183 |
Rock Drill, hand held |
116 |
1 |
116.3 |
003 |
Compressor |
104 |
1 |
|
Equipment Transportation |
||||
Scenario
SS2 |
Delivery
by Helicopter(1) |
(1)
The assessment of
helicopter noise has been based upon the Lmax for typical helicopter
models and not the SWL.
Table 5.6 Typical Equipment Requirement for Slope Remediation Works
CNP Equipment
Code |
Equipment
Scenario |
Sound
Power Level
(SWL) in dB(A) |
Number of
Equipment |
Total
Sound Power Level (SWL) in dB(A) |
Slope Remediation Earthworks |
||||
Scenario SR1 |
Earthworks |
|||
081 |
Excavator |
112 |
1 |
118.2 |
067 |
Dump Truck |
117 |
1 |
|
Slope Nailing |
||||
Scenario SR2 |
Slope Nailing |
|||
183 |
Rock Drill, hand held |
116 |
1 |
116.3 |
003 |
Compressor |
104 |
1 |
Table
5.7 Typical Equipment Requirement for
the Construction of Permanent Noise Barrier in Tung Chung Valley
CNP Equipment
Code |
Equipment
Scenario |
Sound
Power Level
(SWL) in dB(A) |
Number of
Equipment |
Total
Sound Power Level (SWL) in dB(A) |
Noise Barrier Construction |
||||
Scenario
NB1 |
Foundation works |
|
||
Scenario NB1A |
||||
026 |
Breaker, Hand Held |
114 |
1 |
114.3 |
002 |
Air compressor |
102 |
1 |
|
Scenario NB1B |
||||
081 |
Excavator |
112 |
1 |
112.5 |
282 |
Water Pump |
103 |
1 |
|
Scenario NB1C |
||||
141 |
Lorry with grab# |
112 |
1 |
112.0 |
Scenario
NB2 |
Piling |
|
||
- |
Mini Piling Rig* |
113 |
1 1 |
113.4 |
282 |
Water Pump |
103 |
1 1 |
|
Scenario
NB3 |
Formwork /
concreting |
|
||
044 |
Concrete Lorry Mixer |
109 |
1 |
114.8 |
170 |
Poker |
113 |
1 |
|
282 |
Water pump |
103 |
1 |
|
Scenario
NB4 |
Backfilling
works |
|
||
Scenario
NB4A |
||||
050 |
Compactor Vibratory |
105 |
1 |
105.0 |
Scenario
NB4B |
||||
141 |
Lorry with grab# |
112 |
1 |
112.0 |
|
|
|
||
Scenario
NB5 |
Erection |
|
||
Scenario
NB5A |
||||
141 |
Lorry with grab# |
112 |
1 |
112.0 |
Scenario
NB5B |
||||
048 |
Crane |
112 |
1 |
112.0 |
* See
Table C.10, item 6 of BS 5228 for SWL
# Lorry
(CNP 141) is assumed for the purposes of the noise assessment.
5.3.2.1
Predicted
traffic flows used in the operational noise assessment have been discussed in
Section 2.8 of this report. Transport
Department have approved the traffic figures for use in the EIA and their
approval is presented in Appendix G.
5.4
Construction Noise Impact Assessment
5.4.1
Assessment Methodology
5.4.1.1
The
assessment of the proposed alignment has comprised an evaluation of the
construction noise impacts at representative sensitive receivers along its
length based upon the full range of construction activity scenarios detailed
above. The construction noise at the
NSRs has been assessed in accordance with the methodology of the Technical Memorandum on Noise from
Construction Work Other than Percussive Piling. The noise impact from the
use of a helicopter to deliver slope stabilisation equipment has also been
assessed. While the assessment of construction
noise has been based upon non-restricted periods, this does not preclude the
Contractor from working in restricted periods should this be required. However, any work in restricted periods will
be subject to the Contractor obtaining a valid Construction Noise Permit under
the Noise Control Ordinance as detailed in Section 3.3.2. It is likely that working up to 11.00pm will
be required and further assessment of this period is presented in Section
5.4.3.12 below.
5.4.1.2
Potential
cumulative impacts associated with the construction of the development in Tung
Chung Valley are assessed in Section 12.
There are no other cumulative impacts from other contemporary projects
in the vicinity.
5.4.1.3 Construction activities on site will involve the use of heavy machinery and as detailed in Section 5.3, an indicative schedule of key equipment to be used, activities to be carried out and duration of each segment of the works has been identified. Based upon the number and type of heavy plant to be employed in the construction works, noise levels generated will probably be high and impacts are a key issue.
5.4.2.1
The
maximum noise levels at the NSRs during the construction phase of the alignment
without noise mitigation
measures applied are shown below in Tables 5.8a and 5.8b for the road
earthworks and bridge works respectively, Tables 5.8c and 5.8d for the slope
stabilisation and slope remediation respectively and Table 5.8e for the
permanent noise barrier construction. The detailed modelling result is provide
in Appendix F and a summary of the maximum unmitigated levels at each NSR is
provided in Figures 5.2a to 5.2e.
Table 5.8a Maximum
Noise Levels (dB(A)) during Road Construction without Noise Mitigation
Sensitive Receiver |
Slant Distance (m) |
Noise Level without Mitigation, dB(A) |
|||||||||
(EW+PC/RW)(1) |
Earth Works |
Retaining Wall |
Pavement Construction |
||||||||
Scenario |
E1 |
E2 |
E3 |
R1 |
R2(2) |
R3 |
R4 |
P1 |
P2 |
P3 |
|
SWL |
125.9 |
119.5 |
120.7 |
125.9 |
116.9 |
117.9 |
117.8 |
118.6 |
119.0 |
115.0 |
|
SR1 |
235/325 |
73 |
67 |
68 |
71 |
62 |
63 |
63 |
66 |
67 |
63 |
SR2 |
114/238 |
80 |
73 |
75 |
73 |
64 |
65 |
65 |
72 |
73 |
69 |
SR3 |
256/425 |
73 |
66 |
68 |
68 |
59 |
60 |
60 |
65 |
66 |
62 |
SR4 |
56/162 |
86 |
80 |
81 |
77 |
68 |
69 |
69 |
79 |
79 |
75 |
SR5 |
162/211 |
77 |
70 |
72 |
74 |
65 |
66 |
66 |
69 |
70 |
66 |
SR6 |
244/248 |
73 |
67 |
68 |
73 |
64 |
65 |
65 |
66 |
66 |
62 |
SR7 |
202/206 |
75 |
68 |
70 |
75 |
66 |
67 |
66 |
67 |
68 |
64 |
SR8 |
229/241 |
74 |
67 |
68 |
73 |
64 |
65 |
65 |
66 |
67 |
63 |
SR9 |
156/161 |
77 |
71 |
72 |
77 |
68 |
69 |
69 |
70 |
70 |
66 |
SR10 |
276/271 |
72 |
66 |
67 |
72 |
63 |
64 |
64 |
65 |
65 |
61 |
SR11 |
267/272 |
72 |
66 |
67 |
72 |
63 |
64 |
64 |
65 |
65 |
61 |
SR12 |
263/252 |
72 |
66 |
67 |
73 |
64 |
65 |
65 |
65 |
66 |
62 |
SR13 |
32/32 |
91 |
84 |
86 |
91 |
82 |
83 |
83 |
83 |
84 |
80 |
SR14 |
151/145 |
77 |
71 |
72 |
78 |
69 |
70 |
70 |
70 |
70 |
66 |
SR15 |
55/96 |
86 |
80 |
81 |
81 |
72 |
73 |
73 |
79 |
79 |
75 |
SR16 |
166/164 |
76 |
70 |
71 |
77 |
68 |
69 |
68 |
69 |
70 |
66 |
SR17 |
240/234 |
73 |
67 |
68 |
73 |
65 |
66 |
65 |
66 |
66 |
62 |
SR18 |
291/291 |
72 |
65 |
66 |
72 |
63 |
64 |
63 |
64 |
65 |
61 |
76 |
Noise
Level at the sensitive receiver exceeds relevant criteria of 75dB(A) for
domestic premises |
(1): The first distance quoted relates
to both earth works and pavement construction and the second distance in the
column is from the NSR to the nearest retaining wall works. Locations of retaining walls are shown in
Figures 5.1a to f.
(2): Equipment for the piling
activities assumed to be noisier than that required for the detailed ground investigation. However, based upon a worst case scenario,
predicted noise levels for scenario R2 could be used to represent GI works.
Table 5.8b Maximum
Noise Levels (dB(A)) at NSRs during Bridge Construction without Noise
Mitigation
Sensitive Receiver* |
Slant Distance (m) |
Noise Level without Mitigation, dB(A) |
|||||||
Deck Construction |
Foundation Construction |
||||||||
Scenario |
D1 |
D2 |
D3 |
F1 |
F2 |
F3 |
F4 |
||
SWL |
119.8 |
115.5 |
112.0 |
125.9 |
119.1 |
118.0 |
115.5 |
||
SR9 |
159 |
71 |
67 |
63 |
77 |
70 |
69 |
67 |
|
SR10 |
277 |
66 |
62 |
58 |
72 |
65 |
64 |
62 |
|
SR11 |
323 |
65 |
60 |
57 |
71 |
64 |
63 |
60 |
|
SR12 |
295 |
65 |
61 |
58 |
71 |
65 |
64 |
61 |
|
SR13 |
231 |
67 |
63 |
60 |
74 |
67 |
66 |
63 |
|
SR14 |
206 |
68 |
64 |
61 |
75 |
68 |
67 |
64 |
|
SR15 |
218 |
68 |
64 |
60 |
74 |
67 |
66 |
64 |
|
SR16 |
375 |
63 |
59 |
56 |
69 |
63 |
62 |
59 |
|
SR17 |
460 |
62 |
57 |
54 |
68 |
61 |
60 |
57 |
|
SR18 |
501 |
61 |
57 |
53 |
67 |
60 |
59 |
57 |
|
|
|
|
|
|
|
|
|
|
|
76 |
Noise
Level at the sensitive receiver exceeds relevant criteria of 75dB(A) for
domestic premises |
||||||||
* The
distance between the SR1 to SR9, SR19 and the construction work is more than
500 metres, as such noise levels would not exceed the relevant noise criteria.
Table 5.8c Maximum
Noise Levels (dB(A)) at NSRs during Slope Stabilisation Works without
Noise Mitigation
Sensitive Receiver |
Slant Distance (m) |
Noise Level without Mitigation, dB(A) |
|
Scenario |
Rock Dowelling (SS1) |
||
Total SWL |
116.3 |
||
SR1 |
325 |
61 |
|
SR2 |
238 |
64 |
|
SR3 |
425 |
59 |
|
SR4 |
162 |
67 |
|
SR5 |
211 |
65 |
|
SR6 |
248 |
63 |
|
SR7 |
206 |
65 |
|
SR8 |
241 |
64 |
|
SR9 |
161 |
67 |
|
SR10 |
271 |
63 |
|
SR11 |
272 |
63 |
|
SR12 |
252 |
63 |
|
SR13 |
380 |
60 |
|
SR14 |
145 |
68 |
|
SR15 |
96 |
72 |
|
SR16 |
164 |
67 |
|
SR17 |
234 |
64 |
|
SR18 |
291 |
62 |
|
|
|||
76 |
Noise
Level at the sensitive receiver exceeds relevant criteria of 75dB(A) for
domestic premises. |
||
* Noise from transport of equipment by
helicopter assessed below
Table 5.8d Maximum
Noise Levels (dB(A)) at NSRs during Slope Remediation without Noise
Mitigation
Sensitive Receiver* |
Slant Distance (m) |
Noise Level with Mitigation, dB(A) |
|
Earthwork |
Soil Nailing |
||
Scenario |
SR1 |
SR2 |
|
SWL |
118.2 |
116.3 |
|
SR19 |
90 |
74 |
72 |
Note: * SR1 to SR18 located near the improved
Tung Chung Road, and will not affected by the slope remediation work on the
obsolete section of the existing Tung Chung Road. (see Figures 2.12 and 2.13).
** Drainage works and
shotcreting works associated with the slope remediation works would involve a
concrete pump (CNP047) and a concrete mixer (CNP046) with a combined SWL of 109
dB(A). Based upon the fact that no
adverse impacts have been predicted for the above noisier scenarios SR1 and
SR2, no impacts from the drainage works are expected.
Table 5.8e Maximum Noise Levels (dB(A)) during
Construction of Permanent Noise Barrier in Tung Chung Valley without
Noise Mitigation
Sensitive Receiver |
Slant Distance (m) |
Noise Level without Mitigation, dB(A) |
||||||||
Construction of Noise Barrier |
||||||||||
Scenario |
NB1A |
NB1B |
NB1C |
NB2 |
NB3 |
NB4A |
NB4B |
NB5A |
NB5B |
|
SWL |
114.3 |
112.5 |
112.0 |
113.4 |
114.8 |
105.0 |
112.0 |
112.0 |
112.0 |
|
SR1A |
200 |
63 |
61 |
61 |
62 |
64 |
54 |
61 |
61 |
61 |
SR1B |
179 |
64 |
62 |
62 |
63 |
65 |
55 |
62 |
62 |
62 |
SR1 |
153 |
66 |
64 |
63 |
65 |
66 |
56 |
63 |
63 |
63 |
SR1C |
149 |
66 |
64 |
64 |
65 |
66 |
57 |
64 |
64 |
64 |
SR2A |
96 |
70 |
68 |
67 |
69 |
70 |
60 |
67 |
67 |
67 |
SR2B |
60 |
74 |
72 |
71 |
73 |
74 |
64 |
71 |
71 |
71 |
SR2 |
40 |
77 |
75 |
75 |
76 |
78 |
68 |
75 |
75 |
75 |
SR2C |
21 |
83 |
81 |
81 |
82 |
83 |
74 |
81 |
81 |
81 |
SR2D |
25 |
81 |
80 |
79 |
80 |
82 |
72 |
79 |
79 |
79 |
SR3 |
242 |
62 |
60 |
59 |
61 |
62 |
52 |
59 |
59 |
59 |
SR4A |
50 |
75 |
74 |
73 |
74 |
76 |
66 |
73 |
73 |
73 |
SR4 |
48 |
76 |
74 |
73 |
75 |
76 |
66 |
73 |
73 |
73 |
SR4B |
39 |
77 |
76 |
75 |
77 |
78 |
68 |
75 |
75 |
75 |
SR4C |
46 |
76 |
74 |
74 |
75 |
77 |
67 |
74 |
74 |
74 |
SR4D |
25 |
81 |
80 |
79 |
80 |
82 |
72 |
79 |
79 |
79 |
SR5 |
168 |
65 |
63 |
62 |
64 |
65 |
55 |
62 |
62 |
62 |
Note: * SR6 to SR19 are located more than 300 meters away from the barrier construction works and thus will not be affected by these works.
76 |
Noise Level at the sensitive receiver
exceeds relevant criteria of 75dB(A) for domestic premises |
Transportation of Slope
Stabilisation Equipment by Helicopter
5.4.2.2
As
highlighted previously, some equipment required high up the hills may need to
be transported by helicopter. The areas
where the slope stabilisation works will be required are shown by the limit of
slope stabilisation in the figures in Section 2. Based upon the works, there is the potential for short term noise
impacts on the local residents.
5.4.2.3
The
TMEIA specifies a maximum level for helicopter noise at sensitive receivers
which is 85 Lmax dB(A).
However, if the helicopter is considered to be a piece of construction
equipment then the 75 dB(A) at the sensitive receivers should be met. Thus, in order to provide a full assessment,
comparison to both these standards has been made.
5.4.2.4
Based
upon two common helicopter types used in Hong Kong, the Lmax dB(A)
of each are detailed in Table 5.9 as follows:
Brand |
Model |
Users |
Reference Height (1) |
Lmax dB(A)
(1) |
Sikorsky |
S76 |
Government Flying Service, Private |
244m (800 feet) |
78dB(A) |
Aerospatiale (Eurocopter) |
AS355 |
Private |
153m (500 feet) |
77dB(A) |
Note (1): Source: UK Institute of Acoustics (IOA), Volume 14, Part 4 (1992) “Noise Levels of Helicopters Performing Elevated Pad Take-off and Landing Procedures”.
5.4.2.5
The
impact of noise from the helicopter can be calculated at the facades of the
representative NSRs in terms of maximum LAmax using basic acoustic
principles as follows:
At a specified distance, say D1, the Sound Pressure Level (Lp) should be
Lp(at D1) = Lw - distance attenuation (D1) ……(1)
where Lw is the Sound Power Level
Since the helicopter noise is a point source, then (1) can be converted:
Lp(at D1) = Lw - 20log(D1) ……(2)
At distance D2, then
Lp(at D2) = Lw - 20log (D2) ……(3)
Rearrange (2) and (3)
Lw=Lw, then,
Lp(at D1) + 20log (D1) = Lp (at D2) + 20 log(D2), and
Lp(at D2) = Lp(at D1) + 20log (D1) - 20log (D2), and
Lp(at D2) = Lp(at D1) + 20(log(D1/D2)) ……(4)
Equation (4) can be used to convert the reference noise level from the
helicopter measurement to the noise level at a specified distance. The facade correction factor is then
included.
5.4.2.6
The
predicted noise levels in Lmax dB(A) based on the two different
helicopter types at a set of distances from noise sensitive receivers are shown
in Table 5.10 below.
Table 5.10 Predicted Helicopter Noise (Lmax
dB(A))
Distance (metres) |
Sikorsky S76 |
Aerospatiale
AS355 |
||
Reference Noise
Level 78 |
Reference Distance, 244 m |
Reference Noise
Level 77 |
Reference Distance, 153 m |
|
Noise Level (non-building) |
Noise Level (facade) |
Noise Level
(non-building) |
Noise Level (facade) |
|
10 |
106 |
109 |
101 |
104 |
20 |
100 |
103 |
95 |
98 |
30 |
96 |
99 |
91 |
94 |
40 |
94 |
97 |
89 |
92 |
50 |
92 |
95 |
87 |
90 |
60 |
90 |
93 |
85 |
88 |
70 |
89 |
92 |
84 |
87 |
80 |
88 |
91 |
83 |
86 |
90 |
87 |
90 |
82 |
85 |
100 |
86 |
89 |
81 |
84 |
110 |
85 |
88 |
80 |
83 |
120 |
84 |
87 |
79 |
82 |
130 |
83 |
86 |
78 |
81 |
140 |
83 |
86 |
78 |
81 |
150 |
82 |
85 |
77 |
80 |
160 |
82 |
85 |
77 |
80 |
170 |
81 |
84 |
76 |
79 |
180 |
81 |
84 |
76 |
79 |
190 |
80 |
83 |
75 |
78 |
200 |
80 |
83 |
75 |
78 |
210 |
79 |
82 |
74 |
77 |
220 |
79 |
82 |
74 |
77 |
230 |
79 |
82 |
73 |
76 |
240 |
78 |
81 |
73 |
76 |
250 |
78 |
81 |
73 |
76 |
260 |
77 |
80 |
72 |
75 |
270 |
77 |
80 |
72 |
75 |
280 |
77 |
80 |
72 |
75 |
290 |
76 |
79 |
71 |
74 |
300 |
76 |
79 |
71 |
74 |
310 |
76 |
79 |
71 |
74 |
320 |
76 |
79 |
71 |
74 |
330 |
75 |
78 |
70 |
73 |
340 |
75 |
78 |
70 |
73 |
350 |
75 |
78 |
70 |
73 |
360 |
75 |
78 |
70 |
73 |
370 |
74 |
77 |
69 |
72 |
380 |
74 |
77 |
69 |
72 |
390 |
74 |
77 |
69 |
72 |
400 |
74 |
77 |
69 |
72 |
410 |
73 |
76 |
68 |
71 |
420 |
73 |
76 |
68 |
71 |
430 |
73 |
76 |
68 |
71 |
440 |
73 |
76 |
68 |
71 |
450 |
73 |
76 |
68 |
71 |
460 |
72 |
75 |
67 |
70 |
470 |
72 |
75 |
67 |
70 |
480 |
72 |
75 |
67 |
70 |
490 |
72 |
75 |
67 |
70 |
500 |
72 |
75 |
67 |
70 |
5.4.2.7
In
accordance with Hong Kong’s Civil Aviation Department requirements, helicopters
must operate outside a 500ft (152 metres) ceiling from residential
properties. This distance, will,
therefore, be the shortest distance between the noise sensitive receivers and
any helicopter noise. Based upon the results in Table 5.9, it can be seen that
the maximum noise of both helicopter types would not exceed the 85dB(A) noise
limit at this distance.
5.4.2.8
Based
upon the testing and investigation, the approximate area for slope
stabilisation works is shown in Section 2. The distance between slope
stabilisation work and the nearest sensitive receivers is about 500 metres.
According to the result shown in Table 5.10, the Lmax for the
helicopter, the Sikorsky S76 and Aerospatiale AS355,
is 75 and 70 dB(A) at 500m respectively which is within the 85 dB(A) criteria.
The noise at the sensitive receivers is also within the 75 dB(A) noise criteria
if the helicopter is considered to be a piece of construction equipment.
5.4.2.9
The
helicopter pick-up location will be located at the proposed Contractor’s works
area which is shown in Figure 2.10.
This area is 400 meters away from the nearest existing noise sensitive
receivers. Based upon this distance and
the levels provided in Table 5.10 above, the maximum noise level at the closest
sensitive receiver would be 77 and 72 for the Sikorsky S76 and Aerospatiale
helicopters respectively. Thus, the
Sikorsky S76 helicopter would marginally exceed the noise criteria 75dB(A) if
the helicopter remained on the works area for a period of 30 minutes.
5.4.2.10
It has been determined that in order to meet the 75
dB(A) standard, the operation of the helicopter at the pick-up location should
be restricted to 60%, which equates to the helicopter operating for only 18
minutes in any half hour period at the pick-up point. This period is more than
sufficient for the helicopter to remove or drop off equipment in this location
and move away. In addition, the scenarios assessed are the worst case, with
noise levels being lower with a quieter helicopter.
5.4.2.11
Thus,
no unacceptable impacts are predicted from the use of the helicopter, as is the
case for the slope stabilisation and slope remediation activities associated
with the new road.
5.4.2.12
However,
the results detailed above for road construction, bridge construction and noise
barrier construction in Tung Chung Valley indicate that, the maximum noise
levels at some of the NSRs will exceed the day time noise criteria of 75dB(A).
Mitigation measures are, therefore, required to reduce the noise levels to meet
the standards. Recommended mitigation measures are detailed in Section 5.4.3.
5.4.3
Construction Mitigation Measures
5.4.3.1
Based
upon the anticipated construction scenarios for the main alignment, the maximum
noise levels at the closest NSRs would exceed the 75dB(A) noise guideline for
non restricted hours at residential properties during road construction and
permanent noise barrier construction.
Thus, the following noise mitigation measures should be implemented to
reduce the construction noise to an acceptable level. The noise
mitigation measures and the sound reduction estimated are based on current
noise control technologies and BS5228 and have been confirmed by the Project
Proponent as being practical.
5.4.3.2 Noise mitigation measures are recommended at SRs 2, 4, 5, 9, 13-16 during road construction and SR9 during bridge construction and SRs 2 and 4 in Tung Chung Valley during permanent noise barrier construction as detailed below in Tables 5.11 and 5.12 respectively.
Table 5.11: Recommended
Mitigation Measures for the Noisy Equipment during Road Construction and Bridge
Construction
Plant |
Mitigation
Measures* |
Noise
Reduction, dB(A)* |
Reduction
Assumed, dB(A) |
·
Breaker (Excavator
Mounted) |
¨
Fit suitably designed muffler
or sound reduction equipment. ¨
Use dampened bit to eliminate
ringing |
Up to 15 |
5 |
|
|
|
|
· Dump Truck ·
Excavator ·
Bulldozer ·
Concrete Lorry Mixer |
¨
Fit more efficient
exhaust sound reduction equipment ¨
Manufacturers’
enclosure panels should be kept closed |
5 to 10 |
5 |
·
Chipper · Poker |
¨
Fit suitably designed muffler
or sound reduction equipment. ¨
Ensure all leaks in air line
are sealed ¨
Use dampened bit to eliminate
ringing |
Up to 15 |
5 |
* Reference: Noise and vibration control on
construction and open sites, BS5228: Part 1: 1997, P.15-16.
Table 5.12 Recommended Mitigation
Measures for the Noisy Equipment during Permanent Noise Barrier Construction
Plant |
Mitigation
Measures* |
Noise
Reduction, dB(A)* |
Reduction
Assumed, dB(A) |
·
Excavator ·
Crane ·
Lorry ·
Concrete Lorry Mixer |
¨
Fit more efficient exhaust
sound reduction equipment ¨
Manufacturers’ enclosure panels
should be kept closed |
5 to 10 |
5 |
·
Poker |
¨
Fit suitably designed muffler
or sound reduction equipment. ¨
Ensure all leaks in air line
are sealed ¨
Use dampened bit to eliminate
ringing. |
Up to 15 |
5 |
* Ref: Noise and vibration control on
construction and open sites, BS5228: Part 1: 1997, P.15-16.
5.4.3.3
Temporary
noise barriers are also required at SR4, SR13 and SR15 during road
construction, and SR2 and SR4 during permanent noise barrier construction in
Tung Chung, such that the stationary construction equipment will be totally
screened providing a 10 dB(A) attenuation and a 5dB(A) attenuation provided for
moving equipment. The equipment which
can be screened to 10dB(A) and 5 dB(A) respectively is listed below:
Equipment
receiving 10dB(A) reduction
-
Air
Compressor;
-
Generator;
-
Hand-Held
Breaker;
-
Mini
Piling Rig;
-
Poker;
-
Saw;
and
-
Water
Pump.
Equipment receiving 5dB(A)
reduction
-
Asphalt
Paver;
-
Chipper;
-
Compactor;
-
Concrete
Lorry Mixer;
-
Crane;
-
Dump
Truck;
-
Dumper;
-
Excavator;
-
Excavator
Mounted Breaker;
-
Lorry
(with Grab);
-
Paint
Line Marker;
-
Power
Rammer;
-
Road
Roller; and
-
Roller
Vibratory.
5.4.3.4
In addition to the above, the
number of excavator mounted breakers in operation during road construction
scenarios E1 (rock/earth excavation) and R1 (retaining wall foundation works)
at any one time should be restricted from two to only one breaker in Tung Chung
(SR 4) and the Cheung Sha area (SRs 13 and 15). Based upon the results shown in Tables 5.8a to 5.8e, no exceedance
will occur when the receiver is located at 200m away from the all construction
scenarios (Unmitigated noise level during the worst case scenario E1/R1 at SR7,
which is 198m from the work, is 75db(A)). Therefore, the Contractor should
ensure the distance between the construction work and the sensitive receiver is
more than 200m when operating two breakers simultaneously.
5.4.3.5
Noise
levels can be further controlled with the following standard noise pollution
control clauses:
¨
good
site practice to limit noise emissions at source;
¨
avoidance
of simultaneous noisy activities;
¨
reduction
in the numbers of plant operating in critical areas close to NSRs;
¨
use of
a quiet equipment and maintenance of it so as to minimise noise; and
¨
proper
planning of work area.
5.4.3.6
The maximum
noise levels at the NSRs during the road construction phase and bridge
construction with noise mitigation measures applied are shown in Table 5.13 and
Table 5.14 respectively. A summary of
the maximum mitigated levels at each representative NSR is provided in Figures
5.2a to 5.2e.
Table 5.13 Maximum Noise Levels (dB(A)) during Road
Construction with Noise Mitigation
Sensitive Receiver |
Slant Distance (m) |
Noise Level with Mitigation, dB(A) |
|||||||||
(EW+PC/RW)(1) |
Earth Works |
Retaining Wall |
Pavement Construction |
||||||||
Scenario |
E1 |
E2 |
E3 |
R1 |
R2(2) |
R3 |
R4 |
P1 |
P2 |
P3 |
|
Mitigated SWL |
120.9 |
115.3 |
117.9 |
120.9 |
116.9 |
115.8 |
114.0 |
114.3 |
115.9 |
115.0 |
|
SR1 |
235/325 |
*73 |
*67 |
*68 |
*71 |
*62 |
*63 |
*63 |
*66 |
*67 |
*63 |
SR2 |
114/238 |
75 |
*73 |
*75 |
*73 |
*64 |
*65 |
*65 |
*72 |
*73 |
*69 |
SR3 |
256/425 |
*73 |
*66 |
*68 |
*68 |
*59 |
*60 |
*60 |
*65 |
*66 |
*62 |
SR4# |
56/162 |
74 |
70 |
73 |
64 |
*68 |
*69 |
*69 |
69 |
71 |
*75 |
SR5 |
162/211 |
72 |
*70 |
*72 |
*74 |
*65 |
*66 |
*66 |
*69 |
*70 |
*66 |
SR6 |
244/248 |
*73 |
*67 |
*68 |
*73 |
*64 |
*65 |
*65 |
*66 |
*66 |
*62 |
SR7 |
202/206 |
*75 |
*68 |
*70 |
*75 |
*66 |
*67 |
*66 |
*67 |
*68 |
*64 |
SR8 |
229/241 |
*74 |
*67 |
*68 |
*73 |
*64 |
*65 |
*65 |
*66 |
*67 |
*63 |
SR9 |
156/161 |
72 |
*71 |
*72 |
72 |
*68 |
*69 |
*69 |
*70 |
*70 |
*66 |
SR10 |
276/271 |
*72 |
*66 |
*67 |
*72 |
*63 |
*64 |
*64 |
*65 |
*65 |
*61 |
SR11 |
267/272 |
*72 |
*66 |
*67 |
*72 |
*63 |
*64 |
*64 |
*65 |
*65 |
*61 |
SR12 |
263/252 |
*72 |
*66 |
*67 |
*73 |
*64 |
*65 |
*65 |
*65 |
*66 |
*62 |
SR13# |
32/32 |
78 |
75 |
78 |
78 |
74 |
74 |
74 |
74 |
76 |
70 |
SR14 |
151/145 |
72 |
*71 |
*72 |
73 |
*69 |
*70 |
*70 |
*70 |
*70 |
*66 |
SR15# |
55/96 |
74 |
70 |
73 |
69 |
*72 |
*73 |
*73 |
70 |
71 |
*75 |
SR16 |
166/164 |
72 |
*70 |
*71 |
72 |
*68 |
*69 |
*68 |
*69 |
*70 |
*66 |
SR17 |
240/234 |
*73 |
*67 |
*68 |
*73 |
*65 |
*66 |
*65 |
*66 |
*66 |
*62 |
SR18 |
291/291 |
*72 |
*65 |
*66 |
*72 |
*63 |
*64 |
*63 |
*64 |
*65 |
*61 |
71 |
Scenarios requiring mitigation measures;
mitigated noise level recorded. |
Note: Relevant
noise criteria for all sensitive receiver is 75dB(A).
(1): The
first distance quoted relates to both earth works and pavement construction and
the second distance in the column is from the NSR to the nearest retaining wall
works.
(2): Equipment for the piling
activities assumed to be noisier than that required for the detailed ground
investigation. However, based upon a worst
case scenario, predicted noise levels for scenario R2 could be used to
represent GI works.
* Noise
level within the noise criteria before implementation of noise mitigation
measure, the mitigation measure is not applied.
# Temporary noise
barrier is applied as mitigation measure.
Table 5.14 Maximum Noise Levels (dB(A)) during
Bridge Construction with Noise Mitigation
Sensitive Receiver |
Slant Distance (m) |
Noise Level with Mitigation, dB(A) |
||||||
Deck Construction |
Foundation Construction |
|||||||
Scenario |
D1 |
D2 |
D3 |
F1 |
F2 |
F3 |
F4 |
|
Mitigated SWL |
118.6 |
111.9 |
112.0 |
120.8 |
114.1 |
118.0 |
111.9 |
|
SR9 |
159 |
*71 |
*67 |
*63 |
72 |
*70 |
*69 |
*67 |
SR10 |
277 |
*66 |
*62 |
*58 |
*72 |
*65 |
*64 |
*62 |
SR11 |
323 |
*65 |
*60 |
*57 |
*71 |
*64 |
*63 |
*60 |
SR12 |
295 |
*65 |
*61 |
*58 |
*71 |
*65 |
*64 |
*61 |
SR13 |
231 |
*67 |
*63 |
*60 |
*74 |
*67 |
*66 |
*63 |
SR14 |
206 |
*68 |
*64 |
*61 |
*75 |
*68 |
*67 |
*64 |
SR15 |
218 |
*68 |
*64 |
*60 |
*74 |
*67 |
*66 |
*64 |
SR16 |
375 |
*63 |
*59 |
*56 |
*69 |
*63 |
*62 |
*59 |
SR17 |
460 |
*62 |
*57 |
*54 |
*68 |
*61 |
*60 |
*57 |
SR18 |
501 |
*61 |
*57 |
*53 |
*67 |
*60 |
*59 |
*57 |
71 |
Scenarios requiring mitigation measures;
mitigated noise level recorded. |
Note: Relevant
noise criteria for all sensitive receiver is 75dB(A).
* Noise
level within the noise criteria before implementation of noise mitigation
measure, the mitigation measure is not applied.
5.4.3.7
Table
5.13 and Table 5.14 shows that the recommended mitigation measures are
sufficient to reduce levels to within the noise standard during road and bridge
construction works, with the exception of SR13 during road works.
5.4.3.8
Further
mitigation measures are required for SR13 during the construction scenario E1,
E3, R1 and P2 at South Lantau Road.
Restriction on the period of operation of power mechanical equipment is,
therefore, required. When the operation
time of the breaker, dump truck, bulldozer and grader is restricted by 50%, the
predicted noise level would be 75dB(A) during scenarios E1, E3, R1 and P2 and
no exceedance would occur.
5.4.3.9
The
maximum noise levels at the NSRs during the permanent noise barrier
construction with noise mitigation measures applied are shown in Table
5.15. A summary of the maximum
mitigated levels at each representative NSR is provided in Figures 5.2a to
5.2e.
Table 5.15 Maximum Noise Levels
(dB(A)) during Construction of Permanent Noise Barrier in Tung Chung Valley With
Noise Mitigation
Sensitive Receiver |
Slant Distance (m) |
Noise Level with Mitigation, dB(A) |
||||||||
Construction of Noise Barrier |
||||||||||
Scenario |
NB1A |
NB1B |
NB1C |
NB2 |
NB3 |
NB4A |
NB4B |
NB5A |
NB5B |
|
Mitigated SWL# |
104.3 |
102.5 |
102.0 |
103.4 |
102.1 |
105 |
102.0 |
102.0 |
102.0 |
|
SR1A |
200 |
*63 |
*61 |
*61 |
*62 |
*64 |
*54 |
*61 |
*61 |
*61 |
SR1B |
179 |
*64 |
*62 |
*62 |
*63 |
*65 |
*55 |
*62 |
*62 |
*62 |
SR1 |
153 |
*66 |
*64 |
*63 |
*65 |
*66 |
*56 |
*63 |
*63 |
*63 |
SR1C |
149 |
*66 |
*64 |
*64 |
*65 |
*66 |
*57 |
*64 |
*64 |
*64 |
SR2A |
96 |
*70 |
*68 |
*67 |
*69 |
*70 |
*60 |
*67 |
*67 |
*67 |
SR2B |
60 |
*74 |
*72 |
*71 |
*73 |
*74 |
*64 |
*71 |
*71 |
*71 |
SR2 |
40 |
67 |
*75 |
*75 |
66 |
65 |
*68 |
*75 |
*75 |
*75 |
SR2C |
21 |
73 |
71 |
71 |
72 |
71 |
*74 |
71 |
71 |
71 |
SR2D |
25 |
71 |
70 |
69 |
70 |
69 |
*72 |
69 |
69 |
69 |
SR3 |
242 |
*62 |
*60 |
*59 |
*61 |
*62 |
*52 |
*59 |
*59 |
*59 |
SR4A |
50 |
*75 |
*74 |
*73 |
*74 |
63 |
*66 |
*73 |
*73 |
*73 |
SR4 |
48 |
66 |
*74 |
*73 |
*75 |
63 |
*66 |
*73 |
*73 |
*73 |
SR4B |
39 |
67 |
66 |
*75 |
67 |
65 |
*68 |
*75 |
*75 |
*75 |
SR4C |
46 |
66 |
*74 |
*74 |
*75 |
64 |
*67 |
*74 |
*74 |
*74 |
SR4D |
25 |
71 |
70 |
69 |
70 |
69 |
*72 |
69 |
69 |
69 |
SR5 |
168 |
*65 |
*63 |
*62 |
*64 |
*65 |
*55 |
*62 |
*62 |
*62 |
71 |
Scenarios requiring mitigation measures;
mitigated noise level recorded |
* |
Noise level within the noise criteria
before implementation of noise mitigation measure, the mitigation measure is
not applied |
# |
Temporary noise barrier is taken into
account on the total sound power level for SR2 and SR4 |
5.4.3.10
After
the implementation of above noise mitigation measures, the noise during construction
of the permanent noise barrier will be reduced to acceptable levels.
Cumulative Effect
5.4.3.11
In order to prevent the cumulative effect due
to the simultaneous construction activities, the operation of gangs of
equipment should keep a certain distance between each other. According to the Table 4 – Summation of Noise Levels,
Technical Memodrandum on Noise From Construction Work Other Than Percussive
Piling, the amount in dB(A) add to the higher noise level would be 0 dB(A),
if the difference between two noise levels are more than 12 dB(A). In the worst
case construction scenario E1 and R1 and based upon the closest NSR, a distance
of 150m between two gangs is sufficient to eliminate the cumulative effect.
Nighttime Working
5.4.3.12
In
addition to works being on-going during the unrestricted period of 7.00am to
7.00pm weekdays and Saturdays, it is likely that construction works will also
be undertaken during Restricted Period 1, between 7.00pm and 11.00pm in the
evening and on public holidays in order to condense the works programme as far
as possible. Works during restricted
periods are controlled by the Noise Control Ordinance and the Contractor will
be required to obtain a Construction Noise Permit (CNP) before undertaking any
construction activities involving powered mechanical equipment in these times.
5.4.3.13
Notwithstanding,
based upon the worst case construction activity and based upon the Restricted
Period 1 noise criteria for residential properties of 60 dB(A), the maximum
setback from residential properties for evening and public holiday working has
been determined. The setback has been
calculated using Table 5 – Correction Factors to Obtain the Predicted
Noise Level from Sound Power Level at Given Distances, Technical Memodrandum on
Noise From Construction Work Other Than Percussive Piling and for the
distance greater than 300m, the correction factors is calculated based on the
standard acoustical principles and practices and the proposed silenced
equipment will be used during all construction scenario assumed. Based upon
this, Figure 5.7 shows the areas where works during the evening and public
holidays are likely to be able to take place, subject to the Contractor
obtaining a valid CNP. Further details
on the requirement for a CNP are provided in Section 3.3.2.
Summary of
Dwellings Affected
5.4.3.11
The
approximate number of dwellings affected by the works, based upon the maximum
noise levels during the construction activities, and the number of dwellings
benefiting from the mitigation measures are summarised in Table 5.16 below,
where one building has assumed to be one dwelling. The result show that, in the worst case, about 44 dwellings will
be affected by the construction works, and all can be protected by the mitigation
measures detailed in the section above.
Table 5.16 Summary
of Dwellings Affected by Adverse Construction Noise and Benefitting from
Mitigation Measures
Sensitive
Receiver |
Number of
Dwelling Experiencing Noise Exceed Criteria without Mitigation Applied |
Number of
Dwelling Experiencing Noise Exceed Criteria with Mitigation Applied |
Number of
Dwelling Benefiting from the Mitigation Measures |
||||||
Affected
Dwelling of NSR itself |
Affected
Dwellings in Vicinity |
Sub-total |
Affected
Dwelling of NSR itself |
Affected
Dwellings in Vicinity |
Sub-total |
Affected
Dwelling of NSR itself |
Affected
Dwellings in Vicinity |
Sub-total |
|
SR1 |
1 |
14 |
15 |
0 |
0 |
0 |
1 |
14 |
15 |
SR2 |
1 |
14 |
15 |
0 |
0 |
0 |
1 |
14 |
15 |
SR3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR4 |
1 |
10 |
11 |
0 |
0 |
0 |
1 |
10 |
11 |
SR5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR6 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR9 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
SR10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR11 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR12 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR13 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
SR14 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR15 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
SR16 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR18 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
|
44 |
|
0 |
|
44 |
5.4.4
Residual Construction Impacts
5.4.4.1 Based upon the application of the recommended mitigation measures, the noise level at all sensitive receivers will be within the relevant noise criteria, and no adverse residual impacts are predicted.
5.5 Operational Noise Impact Assessment
5.5.1 Model Application
Road Traffic
5.5.1.1 Operational noise is largely attributable to road traffic. The impact of road noise arising from the Improved Tung Chung Road, South Lantau Road and internal roads in the Tung Chung development, as shown in Section 2, have been calculated at the facades of the representative NSRs in terms of L10(1hour) in dB(A) using the SoundPlan package. The calculation methodology was based on the Calculation of Road Traffic Noise (CRTN) methodology, issued by the UK Department of Transport in 1988.
5.5.1.2
The following assumptions have been made for the purposes of the
noise modelling:
¨
peak
hour traffic flows and vehicle mixes for the worst case year of 2021 based on
data provided by the traffic and transportation modelling study. All the traffic data have been approved for
use by the Transport Department, see Appendix G;
¨
in
view of the close proximity of the NSRs to the noise sources, effects due to
the absorption by air have not be allowed for;
¨
meteorological
conditions have not been allowed for due to the proximity of the receivers to
the noise source; and
¨
the
limit for the proposed road has stipulated speed been assumed to be 50 km per
hour for the Improved Tung Chung Road, South Lantau Road, Shek Mun Kap
Road, Yu Tung Road and Road L7.
¨
no
idling and waiting will be undertaken in the bus lay-bys or the turning circle
for extended periods. Noise generated in these areas are included in the noise
modelling.
5.5.2.1 The impact of operational noise has been assessed with reference to the TMEIA and the maximum L10(1hour) traffic noise levels at sensitive facades are shown in Table 3.4
5.5.3.1 The predicted traffic flow figures for the noise modelling for the prevailing year of 2006 and the worst case design year 15 years after the opening of the road of 2021 are detailed in Section 2.8. Transport Department’s approval of the traffic figures for use in the EIA, together with a figure showing the road links which have been input into the noise model, are provided in Appendix G.
5.5.3.2 The L10(1hour) noise levels in dB(A) at the representative NSRs during the operational phase without noise mitigation measures applied are shown in Table 5.17 below. The predicted noise levels at identified future sensitive receiver associated with the sales sites in the vicinity of the junction of the new Tung Chung Road with the South Lantau Road are shown in Table 5.18. Values at every floor of each sensitive receiver are given below and a complete set of modelling results are provided in Appendix G. A summary of the maximum unmitigated operational noise levels at each NSR is also provided in schematic form in Figures 5.4a to 5.4f. Additional modelling points have been designated at SR13 as shown in Figure 5.3b.
Table 5.17 Predicted Traffic Noise Levels, L10 (1hour), dB(A), at the Noise Sensitive Receivers During Operation Phase Without Noise Mitigation Measures in the Year 2021
Sensitive Receiver |
Floor |
Predicted Prevailing L10 Noise (1hour), dB(A) |
Predicted L10 Noise Level (1 hour) dB(A) (without
noise mitigation) (Criteria 70 dB(A) |
SR1 |
1 |
70.2 |
76.4 |
2 |
70.2 |
76.5 |
|
3 |
70.0 |
76.4 |
|
SR2 |
1 |
71.4 |
76.5 |
2 |
71.2 |
76.6 |
|
3 |
70.8 |
76.4 |
|
SR3 |
1 |
67.2 |
67.7 |
2 |
67.1 |
67.8 |
|
3 |
67.1 |
67.8 |
|
SR4 |
1 |
62.7 |
70.3 |
2 |
62.7 |
70.5 |
|
3 |
62.7 |
70.5 |
|
SR5 |
1 |
58.6 |
59.2 |
2 |
58.6 |
60.1 |
|
3 |
58.7 |
60.9 |
|
SR6 |
1 |
64.4 |
62.6 |
2 |
64.2 |
64.6 |
|
3 |
64.1 |
64.7 |
|
SR7 |
1 |
66.7 |
63.3 |
2 |
66.3 |
68.3 |
|
3 |
65.9 |
68.2 |
|
SR8 |
1 |
65.4 |
64.8 |
2 |
65.3 |
64.7 |
|
3 |
65.4 |
64.6 |
|
SR9 |
1 |
60.1 |
60.9 |
SR10 |
1 |
50.4 |
51.8 |
2 |
50.4 |
51.9 |
|
SR11 |
1 |
55.0 |
58.5 |
2 |
55.1 |
58.9 |
|
3 |
55.1 |
59.2 |
|
SR12 |
1 |
52.5 |
57.9 |
2 |
52.9 |
58.2 |
|
3 |
53.2 |
58.7 |
|
SR13a |
1 |
66.9 |
68.5 |
SR13b |
1 |
68.0 |
69.5 |
SR13c |
2 |
59.7 |
60.9 |
SR14 |
1 |
46.1 |
49.5 |
2 |
46.4 |
49.8 |
|
SR15 |
1 |
62.5 |
64.2 |
SR16 |
1 |
53.8 |
55.5 |
2 |
59.2 |
60.7 |
|
3 |
67.9 |
69.4 |
|
SR17 |
1 |
64.5 |
66.1 |
2 |
64.5 |
66.1 |
|
3 |
64.4 |
66.1 |
|
SR18 |
1 |
67.1 |
68.5 |
2 |
67.0 |
68.4 |
|
3 |
66.9 |
68.3 |
70.6 |
Noise Level
at Sensitive Receiver exceed the relevant Noise Criteria |
Table 5.18 Predicted Traffic Noise Levels, L10
(1hour), dB(A), at the Future Noise Sensitive Receivers of the Cheung Sha
Sale Sites During Operation Phase Without Noise Mitigation Measures in
the Year 2021
Sensitive Receiver |
Floor |
Predicted L10 Noise Level (1 hour) dB(A) (without
noise mitigation) (Criteria 70 dB(A)) |
CS1 |
1 |
67.2 |
CS1 |
2 |
69.0 |
CS2 |
1 |
65.3 |
CS2 |
2 |
66.8 |
CS3 |
1 |
60.0 |
CS3 |
2 |
61.5 |
CS4 |
1 |
60.9 |
CS4 |
2 |
61.9 |
CS5 |
1 |
64.1 |
CS5 |
2 |
65.9 |
|
|
|
CS6 |
1 |
69.0 |
CS6 |
2 |
71.1 |
CS7 |
1 |
70.4 |
CS7 |
2 |
71.6 |
CS8 |
1 |
65.3 |
CS8 |
2 |
67.4 |
CS9 |
1 |
70.2 |
CS9 |
2 |
71.4 |
CS10 |
1 |
71.3 |
CS10 |
2 |
72.1 |
CS11 |
1 |
66.6 |
CS11 |
2 |
67.3 |
CS12 |
1 |
70.9 |
CS12 |
2 |
70.9 |
CS13 |
1 |
68.1 |
CS13 |
2 |
68.1 |
5.5.3.3 The results for the improved Tung Chung Road indicate that operational noise will affect some sensitive receivers. The noise level at sensitive receivers SR3, SR5 to SR18 are protected either by their distance or the fact that the alignment is elevated as it passes. However, the modelling has predicted that sensitive receivers SR1, SR2 and SR4 in Tung Chung will be subject to operational noise levels in excess of the 70dB(A) limit for residential properties. However, the results in Appendix G indicate that the main noise contribution affecting SR1 and SR2 is from the section of Tung Chung Road which is outside this project limit and partly Yu Tung Road, with the improved Tung Chung Road included in this project having a negligible contribution.
5.5.3.4 However, in order to obtain further detailed information on the noise impacts in the Tung Chung area as a basis for determining the optimum configuration for mitigation measures, addition sensitive receivers have been identified. The addition sensitive receivers are list in Table 5.19 below and shown in Figure 5.3a. The L10(1hour) noise levels in dB(A) at the additional representative NSRs during the operational phase without noise mitigation measures applied are shown in Table 5.20 below for reference.
Table 5.19 Additional Noise Sensitive Receivers at Tung Chung
NSR Ref. |
NSR |
No. of
Floor |
Shortest
Distance (m) |
Description |
SR1A |
10, Ha Ling Pei |
3 |
273 |
Residential |
SR1B |
8, Ha Ling Pei |
3 |
256 |
Residential |
SR1C |
7, Ha Ling Pei |
3 |
215 |
Residential |
SR2A |
14, Wong Ka Wai |
3 |
165 |
Residential |
SR2B |
9, Wong Ka Wai |
3 |
132 |
Residential |
SR2C |
7, Wong Ka Wai |
3 |
99 |
Residential |
SR2D |
3A, Wong Ka Wai |
3 |
83 |
Residential |
SR4A |
10A, Lung Tseng Tau |
3 |
60 |
Residential |
SR4B |
7, Lung Tseng Tau |
3 |
45 |
Residential |
SR4C |
13, Lung Tseng Tau |
3 |
55 |
Residential |
SR4D |
28, Lung Tseng Tau |
3 |
34 |
Residential |
SR4C |
13, Lung Tseng Tau |
3 |
55 |
Residential |
SR4D |
28, Lung Tseng Tau |
3 |
34 |
Residential |
Table 5.20 Predicted Traffic Noise Levels, L10 (1hour), dB(A), at the Additional Noise Sensitive Receivers in Tung Chung During Operation Phase Without Noise Mitigation Measures in the Year 2021
Sensitive Receiver |
Description |
Floor |
Noise
Criteria, dB(A) |
Predicted Prevailing L10 Noise (1hour), dB(A) |
Predicted L10 Noise Level (1 hour) dB(A) (Without
Noise Mitigation) |
SR1A |
Residential |
1 |
70 |
69.3 |
74.3 |
2 |
70 |
69.3 |
74.5 |
||
3 |
70 |
69.3 |
74.5 |
||
SR1B |
Residential |
1 |
70 |
69.6 |
75.0 |
2 |
70 |
69.6 |
75.2 |
||
3 |
70 |
69.6 |
75.2 |
||
SR1 |
Residential |
1 |
70 |
70.2 |
76.4 |
2 |
70 |
70.2 |
76.5 |
||
3 |
70 |
70.0 |
76.4 |
||
SR1C |
Residential |
1 |
70 |
68.9 |
75.2 |
2 |
70 |
68.9 |
75.3 |
||
3 |
70 |
68.8 |
75.2 |
||
SR2A |
Residential |
1 |
70 |
67.4 |
73.3 |
2 |
70 |
67.4 |
73.6 |
||
3 |
70 |
67.4 |
73.6 |
||
SR2B |
Residential |
1 |
70 |
67.3 |
73.3 |
2 |
70 |
67.3 |
73.5 |
||
3 |
70 |
67.3 |
73.6 |
||
SR2 |
Residential |
1 |
70 |
71.4 |
76.5 |
2 |
70 |
71.2 |
76.6 |
||
3 |
70 |
70.8 |
76.4 |
||
SR2C |
Residential |
1 |
70 |
70.7 |
75.1 |
2 |
70 |
70.5 |
75.1 |
||
3 |
70 |
70.1 |
75.1 |
||
SR2D |
Residential |
1 |
70 |
64.1 |
67.7 |
2 |
70 |
64.1 |
67.8 |
||
3 |
70 |
64.1 |
67.8 |
||
SR4A |
Residential |
1 |
70 |
66.7 |
70.2 |
2 |
70 |
66.7 |
70.4 |
||
3 |
70 |
66.7 |
70.4 |
||
SR4 |
Residential |
1 |
70 |
62.7 |
70.4 |
2 |
70 |
62.7 |
70.5 |
||
3 |
70 |
62.7 |
70.5 |
||
|
|
|
|
|
|
SR4B |
Residential |
1 |
70 |
67.2 |
70.8 |
2 |
70 |
67.2 |
70.9 |
||
3 |
70 |
67.1 |
70.9 |
||
SR4C |
Residential |
1 |
70 |
61.6 |
64.1 |
2 |
70 |
61.7 |
64.3 |
||
3 |
70 |
61.7 |
64.5 |
||
SR4D |
Residential |
1 |
70 |
67.4 |
70.1 |
2 |
70 |
67.4 |
70.2 |
||
3 |
70 |
67.3 |
70.3 |
70.6 |
Noise Level
at Sensitive Receiver exceeds the relevant Noise Criteria |
5.5.4
Operational Mitigation Measures
5.5.4.1 Based upon the above Table 5.20 it can be seen that the majority of the residential properties in the Tung Chung area will be subject to noise levels in excess of the criteria and will require mitigation measures. Table 5.18 also shows that the future properties closest to the proposed road at the future sale sites in Cheung Sha will also need protection.
Tung Chung
5.5.4.2 In respect of Tung Chung, as the road is being widened on-line along this section is it not possible to move the alignment further away from the sensitive receivers as a means to reduce the noise impacts. In addition, due the low speed limit of the road and the presence of the numerous ingress and egress points and the roundabout, noise reducing surfacing would not be effective.
5.5.4.3 Thus, a full range of noise structures have been considered for the protection of the NSRs to ensure that the optimum scheme is recommended. The noise predictions (see Appendix G) confirm that the noise levels in excess of the 70 dB(A) criteria at SRs 1, 1A, 1B, 1C, 2, 2A, 2B and 2C in Wong Ka Wai and Ha Ling Pei are as a result of traffic on the “existing” roads (other sections of Tung Chung Road and Yu Tung Road) which are not being modified as part of this project. However, in accordance with the ExCo policy endorsed in November 2000, retrofitting of direct mitigation measures on the existing Tung Chung Road to protect these properties has been assessed. The guiding principles to be taken into account when considering retrofitting of barrier to existing roads include:
¨ the new structures should not obstruct emergency access or fire fighting;
¨ the structures should not undermine road safety or impede pedestrian and vehicular movement;
¨ the structures should not interfere with commercial activities or cause social disruptions; and
¨ adequate space for retrofitting is available.
5.5.4.4
There are numerous pedestrian and vehicular access
points to the private properties and land adjacent to the road between Ha Ling
Pei and Wong Ka Wai, as shown on Figure 5.5, and these run-ins need to be
maintained. The access points are
indicated on the gazette plans and it has been determined at gaps of 4m should
be provided in each case. As such, any retrofitted barrier along this stretch
of road would need to have may gaps in it to allow access to be
maintained. Based upon standard
acoustic principals and practices, the presence of numerous gaps and openings
would degrade the performance of any noise barriers, with the barriers having
to be of an incommensurate height for the rural setting to compensate for the
noise getting through the gaps.
5.5.4.5 Futhermore, sight-line requirements have to be taken into account and this would require any barrier to be located tight against the boundary of the private land and thus, an overlapping barrier at the front of this to screen the gaps would compromise the sightline. In addition, due to space constraints between the widened road and the private property in Tung Chung Village, there would be insufficient space to provide an overlapping noise barrier at the back of the structure without affecting private land, as shown in Figure 5.5. It would also not be possible to reduce the number of gaps by providing common access without affecting private land. Therefore, retrofitted direct mitigation measures along most of the section of road in Ha Ling Pei and Wong Ka Wai are not considered practical.
5.5.4.6
However, there is a length of road of 70m which does
not have any gaps, and it has been determined that a barrier of between 3 to 5m
in height could be installed and would provide some reduction of the noise
levels at some NSRs in this area. The
barrier would also comply with the guidelines for retrofitting. The location of the possible future section
of retrofitted barrier identified is shown in Figure 5.5.
5.5.4.7 In summary, retrofitting of barriers is not considered practical for much of the section of road in front of Ha Ling Pei and Wong Ka Wai. Therefore, the test according to the three Eligibility Criteria for Indirect Technical Remedies defined under the ExCo directive “Equitable Redress for Persons Exposed to Increased Noise Resulting from the Use of New Roads” has been applied to these NSRs. The three criteria are:
(i) the predicted overall noise level from the new road together with other traffic noise in the vicinity must be above 70 dB(A) for domestic premises and 65 dB(A) for school;
(ii) the predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level; i.e. the total traffic noise level existing before the works to construct the road were commenced; and
(iii) the contribution to the increase in the predicted overall noise level from the new road must be at least 1.0 dB(A).
5.5.4.8 The three eligibility criteria test for the maximum noise levels at the NSR are shown in Appendix G. However, it can be seen in Appendix G that due to the contribution of noise from existing roads, these properties are not eligible for indirect technical remedies. Nevertheless, upon commissioning of the project, it is recommended that a review of the situation be initiated by HyD based upon the contemporary conditions to see whether any noise mitigation measures that could bring significant benefit to this section of Tung Chung Road, between the Project limit and the study boundary (see Figure 5.5), covering Wong Ka Wai and Ha Ling Pei, could be achieved.
5.5.4.9 For the properties which are affected by noise to above the acceptable limit from the widened section of Tung Chung Road which forms part of this project (SRs 4 and 4B), direct noise mitigation measures for implementation under this project have been considered. As noted above, due to the speed limit of the road, the numbers of heavy vehicles and the numerous access points, noise reducing road surfacing is not practical and the road alignment cannot be moved further away from the sensitive receivers. Therefore, various heights of noise barrier and canopy have been considered. It has been determined that the transmission loss[1] for the barriers should be at least 30 dB in order to screen the noise from the road to the sensitive receiver. Most of the commercially available noise mitigation panels in Hong Kong can achieve this criteria. The full set of modelling results can be seen in Appendix G and the results are discussed below.
5.5.4.10
Three sections of noise
barrier have been proposed at the front of the properties at Lung Tseng Tau,
two of 1.5m in height and one of 4.5m. Barriers will be located behind the proposed footpath and paved amenity area near
to the roundabout to take account of the sight-line requirements on the inside
of the road bends and at the roundabout, as shown in Figure 5.5. One gap of 4m has been provided between two
of the sections of barrier to accommodate an existing pedestrian access to the
private properties behind the road in Lung Tseng Tau, as shown in Figure
5.5. While a height of 1.5m for the
middle section of barrier is sufficient to reduce the noise to within
acceptable levels, it is considered that it would be preferable from an
aesthetic perspective the vary the height of this barrier from 1.5m to 4.5m to
blend with the other barriers either side.
The proposed barriers also have the benefit of providing noise
attenuation for other residential properties in the area which are not
adversely affected by traffic noise.
5.5.4.11 The extent of the mitigation determined in Tung Chung is summarised in Table 5.21 below and detailed in Figure 5.5. A total length of 127m of noise barriers has been recommended in the Tung Chung area and an indicative cross-section of the barrier is provided in Figure 5.6. The maximum mitigated noise levels at each of the NSRs is given in Table 5.22 and a summary of the maximum unmitigated and mitigated levels at each NSR provided in Figures 5.4a to 5.4e. While existing and future residential properties will be opposite the road, the distance of these (greater than 300m) means that reflective barriers can be used. This also has aesthetic advantages and a photomontage of the proposed barriers is also provided in Section 9.
Table 5.21 Summary of Direct Mitigation Measures
Barrier
Height |
Location
of Barrier |
Length of
Barrier |
Barrier
Type |
4.5m |
Lung Tseng Tau |
30m |
Reflective |
1.5m to 4.5m barrier (graded height) |
Lung Tseng Tau |
59m |
Reflective |
1.5m barrier |
Lung Tseng Tau |
38m |
Reflective |
Table 5.22 Noise Levels, L10 (1hour),
dB(A), at the Additional Noise Sensitive Receivers at Tung Chung During
Operation Phase With Noise Mitigation Measures in the Year 2021
Sensitive Receiver |
Floor |
Noise
Criteria, dB(A) |
Predicted L10 Noise Level (1 hour) dB(A) (Without
Mitigation) |
Predicted L10 Noise Level (1 hour) dB(A) (With Noise
Mitigation) |
SR1A |
1 |
70 |
74.3 |
71.8 |
2 |
70 |
74.5 |
73.1 |
|
3 |
70 |
74.5 |
73.7 |
|
SR1B |
1 |
70 |
75.0 |
71.6 |
2 |
70 |
75.2 |
73.4 |
|
3 |
70 |
75.2 |
74.3 |
|
SR1 |
1 |
70 |
76.4 |
72.7 |
2 |
70 |
76.5 |
75.0 |
|
3 |
70 |
76.4 |
75.8 |
|
SR1C |
1 |
70 |
75.2 |
71.3 |
2 |
70 |
75.3 |
73.1 |
|
3 |
70 |
75.2 |
74.2 |
|
SR2A |
1 |
70 |
73.3 |
70.1 |
2 |
70 |
73.6 |
71.7 |
|
3 |
70 |
73.6 |
72.4 |
|
SR2B |
1 |
70 |
73.3 |
69.8 |
2 |
70 |
73.5 |
71.7 |
|
3 |
70 |
73.6 |
72.6 |
|
SR2 |
1 |
70 |
76.5 |
72.9 |
2 |
70 |
76.6 |
75.8 |
|
3 |
70 |
76.4 |
76.2 |
|
SR2C |
1 |
70 |
75.1 |
72.3 |
2 |
70 |
75.1 |
74.7 |
|
3 |
70 |
75.1 |
74.9 |
|
SR2D |
1 |
70 |
67.7 |
62.3 |
2 |
70 |
67.8 |
64.5 |
|
3 |
70 |
67.8 |
65.4 |
|
|
|
|
|
|
SR3 |
1 |
70 |
67.7 |
67.7* |
2 |
70 |
67.8 |
67.8* |
|
3 |
70 |
67.8 |
67.8* |
|
SR4A |
1 |
70 |
70.2 |
65.2 |
2 |
70 |
70.4 |
66.6 |
|
3 |
70 |
70.4 |
67.7 |
|
SR4 |
1 |
70 |
70.4 |
65.2 |
2 |
70 |
70.5 |
66.6 |
|
3 |
70 |
70.5 |
67.8 |
|
SR4B |
1 |
70 |
70.8 |
65.9 |
2 |
70 |
70.9 |
67.4 |
|
3 |
70 |
70.9 |
68.6 |
|
SR4C |
1 |
70 |
64.1 |
61.7 |
2 |
70 |
64.3 |
62.4 |
|
3 |
70 |
64.5 |
62.9 |
|
SR4D |
1 |
70 |
70.1 |
68.9 |
2 |
70 |
70.2 |
69.3 |
|
3 |
70 |
70.3 |
69.6 |
|
SR5 |
1 |
70 |
59.2 |
59.1* |
2 |
70 |
60.1 |
59.7* |
|
3 |
70 |
60.9 |
60.5* |
|
SR6 |
1 |
70 |
62.6 |
62.6* |
2 |
70 |
64.6 |
64.6* |
|
3 |
70 |
64.7 |
64.7* |
|
SR7 |
1 |
70 |
63.3 |
63.3* |
2 |
70 |
68.3 |
68.3* |
|
3 |
70 |
68.2 |
68.2* |
|
SR8 |
1 |
70 |
64.8 |
64.8* |
2 |
70 |
64.7 |
64.7* |
|
3 |
70 |
64.6 |
64.6* |
|
SR9 |
1 |
70 |
60.9 |
60.9* |
SR10 |
1 |
70 |
51.8 |
51.7* |
2 |
70 |
51.9 |
51.9* |
|
SR11 |
1 |
70 |
58.5 |
58.5* |
2 |
70 |
58.9 |
58.8* |
|
3 |
70 |
59.2 |
59.1* |
|
SR12 |
1 |
70 |
57.9 |
57.8* |
2 |
70 |
58.2 |
58.1* |
|
3 |
70 |
58.7 |
58.6* |
|
SR13a |
1 |
70 |
68.5 |
68.5* |
SR13b |
1 |
70 |
69.5 |
69.5* |
SR13c |
2 |
70 |
60.9 |
60.9* |
SR14 |
1 |
70 |
49.5 |
49.3* |
2 |
70 |
49.8 |
49.7* |
|
SR15 |
1 |
70 |
64.2 |
64.1* |
|
|
|
|
|
SR16 |
1 |
70 |
55.5 |
55.4* |
2 |
70 |
60.7 |
60.7* |
|
3 |
70 |
69.4 |
69.4* |
|
SR17 |
1 |
70 |
66.1 |
66.1* |
2 |
70 |
66.1 |
66.1* |
|
3 |
70 |
66.1 |
66.0* |
|
SR18 |
1 |
70 |
68.5 |
68.5* |
2 |
70 |
68.4 |
68.4* |
|
3 |
70 |
68.3 |
68.3* |
* Noise level within the noise criteria before
implementation of noise mitigation measures, thus, mitigation measure is not
required.
Cheung Sha
5.5.4.12 Some of the planned receivers at the sale sites in Cheung Sha will also be subject to noise levels which exceed the noise criteria L10 70dB(A) based upon the assumed 10m setback from the site boundary and the assumption that the properties will be facing towards the sea. Thus, mitigation measures to protect the future properties is required.
5.5.4.13 Barriers cannot be provided along the edge of the proposed road due to vehicle sightline issues associated with the bus lay-bys, the curve of the road as it descends to South Lantau Road and the roundabout junction with South Lantau Road. Due to the junction and its approach, noise reducing road surfacing would also not be effective in this area.
5.5.4.14 Table 5.23 shows that a 2 meter high landscaped bund, together with a 4m non-building area along the boundary of the sites facing the new Tung Chung Road, as indicated in Figure 5.4f, would be sufficient to reduce noise levels to within the acceptable criteria. The proposed mitigation has been confirmed as acceptable with Planning Department and the District Lands Office. The maximum mitigated noise levels at each of the NSRs is given in Table 5.23 and a summary of the maximum unmitigated and mitigated levels at each NSR provided in Figures 5.4f.
Table 5.23 Predicted Traffic Noise Levels, L10
(1hour), dB(A), at the Noise Sensitive Receivers in Sale Sites During
Operation Phase With Mitigation in the Year 2021
Sensitive Receiver |
Floor |
Predicted L10 Noise Level (1 hour) dB(A) (without
noise mitigation) (Criteria 70 dB(A)) |
Predicted L10 Noise Level (1 hour) dB(A) (with noise
mitigation) (Criteria 70 dB(A)) |
CS1 |
1 |
67.2 |
66.7 |
CS1 |
2 |
69.0 |
68.3 |
CS2 |
1 |
65.3 |
64.0 |
CS2 |
2 |
66.8 |
65.5 |
CS3 |
1 |
60.0 |
59.4 |
CS3 |
2 |
61.5 |
60.8 |
|
|
|
|
CS4 |
1 |
60.9 |
60.4 |
CS4 |
2 |
61.9 |
61.3 |
CS5 |
1 |
64.1 |
61.2 |
CS5 |
2 |
65.9 |
63.3 |
CS6 |
1 |
69.0 |
62.8 |
CS6 |
2 |
71.1 |
64.9 |
CS7 |
1 |
70.4 |
67.8 |
CS7 |
2 |
71.6 |
68.5 |
CS8 |
1 |
65.3 |
63.7 |
CS8 |
2 |
67.4 |
66.0 |
CS9 |
1 |
70.2 |
66.0 |
CS9 |
2 |
71.4 |
68.6 |
CS10 |
1 |
71.3 |
63.0 |
CS10 |
2 |
72.1 |
66.5 |
CS11 |
1 |
66.6 |
63.2 |
CS11 |
2 |
67.3 |
65.2 |
CS12 |
1 |
70.9 |
67.6 |
CS12 |
2 |
70.9 |
68.5 |
CS13 |
1 |
68.1 |
66.8 |
CS13 |
2 |
68.1 |
67.3 |
Summary of Dwellings
Affected and Benefitting
5.5.4.15 A summary of the dwellings benefitting from the mitigation before and after the implementation of direct noise measures is provided in Table 5.24 below. The results shows that, in the worst case, of the 10 dwellings which are predicted to be affected by the operation of improved Tung Chung Road which forms this project, all will be benefit from the mitigation structures proposed. Those dwellings which are not adversely affected by this project but by other existing roads are highlighted but as the source of the noise is outside the scope of this project, no mitigation measures are proposed.
Table 5.24 Summary of
Dwelling Affected by Adverse Noise and Benefitting from Direct Mitigation
Measures during the Operational Phase
Sensitive Receiver |
Number of Dwelling* Experiencing Noise Exceed Criteria without
Mitigation |
Number of Dwelling* Experiencing Noise Exceed Criteria with Mitigation
|
Number of Dwelling* Benefiting from the Mitigation Measures |
||||||
Affected by New Road |
Affected by Existing Roads(1) |
Sub-total |
Affected by New Road |
Affected by Existing Roads(1) |
Sub-total |
Affected by New Road |
Affected by Existing Roads(1) |
Sub-total |
|
SR1 |
0 |
15 |
15 |
0 |
15 |
15 |
0 |
0 |
0 |
SR2 |
0 |
16 |
16 |
0 |
16 |
16 |
0 |
0 |
0 |
SR3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR4 |
5 |
0 |
5 |
0 |
0 |
0 |
5 |
0 |
5 |
SR5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR6 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR11 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR12 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR13 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR14 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR16 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
SR18 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CS1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CS2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CS3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CS4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CS5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CS6 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
CS7 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
CS8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CS9 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
CS10 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
CS11 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
CS12 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
1 |
CS13 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
10 |
31 |
41 |
0 |
31 |
31 |
10 |
0 |
10 |
* Number of dwellings shown comprises affected dwelling of the NSR itself together with the affected dwellings in the vicinity which the NSR represents.
(1) Dwellings affected by traffic noise on existing roads not within the scope of the project and thus mitigation not provided by this project.
5.5.5
Residual Operational Impacts
5.5.5.1 Table 5.24 shows that the application of the direct noise mitigation measures will protect all properties which are subject to noise from the project. All other properties within the study boundary are affected by noise from other roads and the while not eligible for indirect technical remedies the possibility of retrofitting a section of barrier to reduce the noise levels at some NSRs has been raised as detailed above.
5.6.1 The assessment of construction noise has determined that approximately 45 dwellings will be affected by the implementation of the project in excess of the stipulated standards. However, mitigation measures during construction phases have been recommended which can achieve adequate attenuation of noise in all construction scenarios and no adverse residual impact is predicted.
5.6.2 During operational phase of improved Tung Chung Road, no residential dwellings which are affected by this project will experience noise above 70dB(A) standard after implementation of direct noise mitigation measures.
5.7
Environmental
Monitoring and Audit
5.7.1 The assessment has concluded that construction and operational noise impacts can be mitigated to acceptable levels. However, it is recommended that construction phase environmental monitoring and audit is undertaken to ensure that the recommended mitigation measures are being implemented and are effective. EM&A for operational noise is also recommended to ensure noise barriers are effective. Operational noise monitoring is recommended to be conducted twice during the 6th and 12th months during the first operational year of the road. Further details of the specific EM&A requirements are detailed in Section 13.0 of this report and in the EM&A Manual.
[1]
According to the Guidelines on Design of Noise Barrier by Environmental
Protection Department and Highway Department, Government of the Hong Kong SAR,
transmission loss (TL) is the common logarithm of energy ratios of the noise in
front of the barrier and behind the barrier, expressed in decibels (dB). The TL
of material used for a barrier should at least 10dB(A) greater than the desired
noise reduction.