13                     ENVIRONMENTAL MONITORING AND AUDIT

 

13.1               Introduction

 

13.1.1         The development of appropriate environmental monitoring and audit (EM&A) programmes and methodologies are a vital part of the environmental management and control of the Project.  This chapter provides an outline of the EM&A requirements for the Project, highlighting the environmental parameters to be monitored, timing of the monitoring work and the frequency of the monitoring and audit work.   A detailed scope of work will be provided in the EM&A Manual, prepared in accordance with Annex 21 of the TMEIA and EPD’s EM&A Guidelines for Development Projects in Hong Kong.

 

13.1.2         The broad objectives of the monitoring and audit process are:

 

(i)         to clarify and identify sources of pollution, impact and nuisance arising from the works;

 

(ii)        to establish a record of change associated with the implementation of a project;

 

(iii)       to verify all or selected parameters measured are in compliance with legal and contract specifications, internal policies and standards;

 

(iv)       to provide an early warning system for impact prevention;

 

(v)        to provide a database of environmental parameters against which to determine any short term or long term environmental impacts;

 

(vi)       to propose timely, cost-effective and viable solutions to actual or potential environmental issues;

 

(vii)      to setup event and action plans and determine the degree and scope of any necessary remedial measures in case of exceedance of compliance, for which environmental monitoring forms the basis, or the recommendation of environmental controls in the event that the environmental objectives are not achieved;

 

(viii)      to monitor performance of the mitigation measures and to assess their effectiveness and, whenever necessary, identify any further need for additional measures;

 

(ix)       to verify the EIA predicted impacts and compare the impact predictions with actual impacts for the purpose of assessing accuracy of impact predictions in EIA;

 

(x)        to collate information and evidence for use in public and Government consultation; and

 

(xi)       to audit the environmental performance.        

 

13.2               EM&A Requirements

 

13.2.1         In accordance with the EIA, EM&A procedures are required during the design, construction and operational phases of the project implementation and a summary of the requirements for each of the environmental parameters is detailed in Table 13.1 below.

 

Table 13.1                Summary of EM&A Requirements

 

Parameter

EM&A Phase

Design Phase

Construction Phase

Operational Phase

Air Quality

 

U

 

Noise

 

U

U

Ecology

U

U

U

Water Quality

 

U

 

Landscape and Visual

U

U

U

Waste

 

U

 

Cultural Heritage

 

U

 

 

13.2.2         The EM&A works during the design phase shall comprise an iterative audit process of specific design elements by a suitably qualified auditor(s).  The specifications for certain ecological and landscape mitigation measures recommended by the EIA will be required to be designed during the detailed design phase of the project.  These items will include:

 

¨                  transplantation of the shrub Pavetta hongkongensis, orchids Acampe rigida and Liparis viridiflora and tree Artocarpus hypargyreus;

¨                  special design of new culverts and culvert inlet and outlets for streams 19 and 21 (Figure 6.1) and culvert inlet and outlets for Stream 18;

¨                  translocation of Hong Kong Newt, Lesser Spiny Frog and Romer’s Tree Frog from streams 15, 18, 19 and 21;

¨                  scheduling of works in streams 15, 18, 19 and 21 to avoid the period April to June which is the key breeding period for fish, amphibians and odonates;

¨                  translocation of Romer’s Tree Frog between Lung Tseng Tau and Shek Mun Kap;

¨                  provision of water filled pots as habitats for the Romer's Tree Frog between Lung Tseng Tau and Shek Mun Kap;

¨                  translocation of isolated population of Beijiang Thick-lipped Barb in Stream 15 to tributary of Tung Chung Stream;

¨                  provision of slope surfaces at step channels for aquatic fauna to move up and down stream at the existing bridge at stream 15;

¨                  provision of escape routes from drainage channels for amphibians;

¨                  provision of wildlife tunnels for faunal transfer; and

¨                  landscape design drawings.

 

13.2.3         The design audit shall be undertaken as and when the relevant design aspects are produced and the Consultant will be required to prepare a Design Audit Report at the end of the detailed design which will confirm that the requirements of the EIA have been fully taken into account in the project design.

 

13.2.4         During the construction and operational phases, the EM&A requirements are divided into environmental monitoring and/or project auditing in the form of site inspection and supervision.  The environmental monitoring will be conducted in three distinct stages, as follows:

 

(i)                     baseline (pre-construction);

 

(ii)          construction phase impact; and

 

(iii)         operational phase impact.

 

13.2.5         Environmental monitoring and audit for dust, noise and water quality during the construction phase is recommended in order to ensure all proposed mitigation measures are implemented and effective.  Obtaining a suitable and representative baseline data set will be critical to the whole monitoring and audit process because it forms the standard against which environmental impacts are assessed.  Thus, baseline monitoring for dust, noise and water quality will be required prior to the start of construction.  All three of these parameters will also be subject to audit through site supervision.

 

13.2.6         Site supervision and procedures audit will be required during the construction phase to ensure the proper handling, storage, transportation and disposal of the various waste arisings from the project.

 

13.2.7         Audit of the implementation of the design elements and mitigation measures to avoid ecological and landscape and visual impacts have also been recommended by the EIA, and thus, monitoring in the form of regular site inspections shall also be required to ensure mitigation measures are being implemented and are effective.  EM&A for both ecology and landscape and visual resources will extend through the construction phase and into the operational phase to ensure landscape and ecological planting/replanting have been effective.

 

13.2.8         Operational noise monitoring shall be undertaken during the first year of the operation of the project to assess the effectiveness of the direct noise mitigation measures recommended by the EIA.

 

13.2.9         The details of monitoring are discussed in the following sections and summarised in Table 13.2 below.

 


Table 13.2:         Framework for Environmental Monitoring Plan

 

Monitoring

 

Period

Parameters

Monitoring

Frequency

Responsibility

Noise

 

 

Baseline

(1 occasion)

Leq

L10

L90

Continuous sampling for two consecutive weeks analysed every 24 hours plus one hour sampling

three times per day during the same period

Environmental Team

Construction Phase Impact

Leq

L10

L90

 

    (i)        One set of measurements between 0700-1900 hours on normal weekdays once per 6 days;

    (ii)       One set of measurements between 1900-2300 hours;(*)

    (iii)      One set of measurements between 2300-0700 hours of next day; and(1)

    (iv)      One set of measurements between 0700-1900 hours on holidays(1)

For (i) one Leq(30 minute) reading is required.

One set of measurements for (ii), (iii) and (iv) shall include at least three

consecutive Leq (5 min) results

 

(Note (1): as an when required if work in unrestricted periods is undertaken only)

Environmental Team

Operational Phase Impact

 

Leq

L10

L90

During the first year of operation, monitoring during any three 30 minute periods during week day peak times.  Repeated in months 6 and 12.

Environmental Team

Dust

 

Baseline

Total Suspended Particulates, wind speed/

direction

Continuous 24 hour sampling and 1 hour sampling 3 times a week for 2 consecutive weeks

Environmental Team

Construction Phase Impact

Total Suspended Particulates, wind speed/ direction

24 hour TSP at least once every 6 days and 1hour TSP three times every 6 days

Environmental Team

Ecology

Design

Specifications for:

¨    transplantation of the shrub Pavetta hongkongensis, orchids Acampe rigida and Liparis viridiflora and tree Artocarpus hypargyreus;

¨    special design of new culverts and culvert inlet and outlets for streams 19 and 21(Figure 6.1) and culvert inlet and outlets for Stream 18;

¨    translocation of Hong Kong Newt, Lesser Spiny Frog and Romer’s Tree Frog from streams 15, 18, 19 and 21;

¨    scheduling of works in streams 15, 18, 19 and 21 to avoid the period April to June;

¨    translocation of Romer’s Tree Frog between Lung Tseng Tau and Shek Mun Kap;

¨    provision of water filled pots as habitats for the Romer's Tree Frog between Lung Tseng Tau and Shek Mun Kap;

¨    translocation of isolated population of Beijiang Thick-lipped Barb in Stream 15 to tributary of Tung Chung Stream;

¨    provision of slope surfaces at step channels for aquatic fauna to move up and down stream at the existing bridge at stream 15;

¨    provision of escape routes from drainage channels for amphibians;

¨    provision of wildlife tunnels for faunal transfer;

Audit as and when designs are prepared

Auditor(s) designated by the Design Consultants

 

Baseline

Walk over survey of area of disturbance and surrounding area.

Once immediately prior to commencement of construction works.

Ecologist/Landscape Architect (members of the Environmental Team)

Ecology

Construction Phase Impact

Walk over survey of area of disturbance and surrounding area.

Once a week during construction works.

Ecologist/Landscape Architect (members of the Environmental Team)

 

Operational Phase Impact

Walk over survey of area of disturbance and surrounding area.

Once every two months for a one year period after completion of construction works.

Ecologist/Landscape Architect (members of the Environmental Team)

Water

Baseline

Stream and tributary survey along entire road alignment together with measurements of suspended solids, dissolved oxygen and pH

Baseline data at least 4 days per week for at least four weeks before the start of the construction for all monitoring stations.

Environmental Team

Construction Phase Impact

 

Survey of watercourses in area of active construction works and other areas with stock piled materials on exposed ground surface together with measurements of suspended solids, dissolved oxygen and pH.

Survey of all water courses once per week.

Measurements three times per week for all monitoring stations.  Daily at specified locations for in-situ measurements (pH, turbidity, DO)

Environmental Team

Landscape/

Visual

Resources

 

Design

Detailed landscape proposals and specifications

As and when designs are produced.

Auditor(s) designated by the Design Consultants

Baseline

 

Comprehensive Tree Survey and Vegetation Mapping.

Once immediately prior to construction works.

Landscape Architect (members of the Environmental Team)

Construction Phase Impact

Survey of protection measures for trees and landscaping.

Twice a month during construction works

Landscape Architect (members of the Environmental Team)

Operational Phase Impact

 

Survey of coverage and growth of plantings.

Once every two months for a one year period after completion of construction works

Landscape Architect (members of the Environmental Team)

Cultural Heritage

Baseline

Walkover survey of shrine in Lung Tseng Tau and Fong Yuen Nunnery

Once immediately prior to construction works.

Archaeologist (member of the Environmental Team)

 

Construction Phase Impact

Survey of protection measures for shrine in Lung Tseng Tau and Fong Yuen Nunnery and any areas identified in baseline survey.

As per site inspection schedule

Archaeologist (member of the Environmental Team)

 

 

 

 

 

 

Waste

Baseline

n/a

n/a

n/a

Construction Phase Impact

Routine supervision of construction works

As per site inspection schedule

Environmental Team

 


13.3               Baseline Monitoring

 

13.3.1         Noise

 

13.3.1.1   Noise surveys will collect L10, L90, and Leq parameters as shown in Table 13.2 prior to the start of construction at strategic noise sensitive receivers. The designated monitoring locations are detailed in the EM&A Manual.

 

13.3.2         Air Quality

 

13.3.2.1   Dust surveys will consist of a daily 24 hour sampling for two weeks and one hour sampling three times per day at representative sensitive receivers as shown in Table 13.2.  The designated monitoring locations are detailed in the EM&A Manual.

 

13.3.3         Ecology

 

13.3.3.1   Ecology surveys will consist of a walk-over survey prior to construction works.  It may be necessary to rope off and protect specific habitats or species of special interest identified during the ecological surveys.  Works around ecologically sensitive streams and rivers will require particular attention.

 

13.3.4         Water Quality

 

13.3.4.1   Baseline water quality monitoring of the streams in the study area will be carried out 4 days per week for a period of 4 weeks to measure suspended solids, turbidity, dissolved oxygen and pH at all monitoring stations.  A walkover survey of watercourses within the study area will also be undertaken, including Tung Chung and Cheung Sha Streams and their tributaries, to note and photograph the visual conditions of the water bodies. 

 

13.3.5         Landscape/Visual Resources

 

13.3.5.1   Baseline monitoring for landscape will comprise a vegetation survey of the entire selected route option undertaken on an ‘area’ basis.  Representative vegetation types will be identified along with typical species composition.  An assessment of landscape character will be made against which future change can be monitored. The landscape resources and elements of particular concern are to be noted.  Reference shall be made to the Tree Survey Report to the EIA and the habitat maps included in the EIA.

 

13.3.6         Cultural Heritage

 

13.3.6.1   Baseline monitoring for the cultural heritage resources will comprise a walkover survey of the shrine in Lung Tseng Tau and the Fong Yuen Nunnery to determine the existing baseline condition prior to construction.

 

 

 

 

13.4               Construction Phase Impact Monitoring

 

13.4.1         Action and Limit Levels

 

13.4.1.1   Monitoring stations will be set up at representative sensitive receivers and the results will be used to ensure compliance with determined performance criteria, based upon specific action and limit levels. The definition of these are as follows:

 

¨              the Action Level represents a level at which some appropriate action will be required to prevent conditions deteriorating to the extent that statutory or guide criteria are breached; and

 

¨              the Limit Level represents the upper limit permitted and is generally equivalent to the statutory levels specified in legislation.

 

13.4.1.2   The construction phase monitoring and relevant audit criteria for noise, dust and water quality are highlighted below.  Action plans will be developed for use in the event of exceedances, or non conformities in the case of ecology, landscape and visual and waste, and these will be included in the EM&A Manual. 

 

13.4.1.3   Action plans and audit criteria are not relevant to the ecology, waste, landscape and visual and cultural heritage EM&A.  However, the supervision methodology is highlighted below.

 

13.4.2         Noise

 

13.4.2.1   The construction noise level will be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).  Leq measurements will be taken during 30 minutes of typical construction activity during unrestricted periods.  For all other time periods, the average of three consecutive Leq(5 min) results will be taken for comparison with the Noise Control Ordinance (NCO) criteria. As supplementary information for data auditing and statistical analysis, parameters including Leq, L10 and L90 will also be obtained for reference.

 

13.4.2.2   Sound level metres in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications will be used for carrying out the noise monitoring, in accordance with the Technical Memorandum (TM) issued under the NCO.  The noise measurements shall be carried out 1m from the worst-affected external facades of the representative NSRs, or 1.2m above the ground in the case of the measurement not being carried out at a building and shall not be made in the presence of fog, rain or excessive steady or gusty wind.

 

13.4.2.3   The monitoring will be undertaken at representative noise monitoring locations once per 6 days and action and limit levels for work during the unrestricted period and restricted periods for reference are shown in Table 13.3.

 

 

 

Table 13.3:  Action and Limit Levels for Construction Noise

 

Time Period

Action Level

Limit Level

Unrestricted Period

Normal work days (0700 -

1900)

When one

documented

complaint is

received

75 dB(A) reduced to 70 dB(A) for

schools and 65 dB(A) during school

examination periods.

Restricted Period 1

All days during the evening

(19.00-23.00) and general

holidays (including Sundays)

during the daytime and

evening (07.00-23.00)

When one

documented

complaint is

received

60 dB(A) (for Area Sensitivity

Ratings A)

Restricted Period 2

All days during the night-time

(23.00-07.00)

When on

documented

complaint is

received

45 dB(A) (for Area Sensitivity

Ratings A)

 

13.4.3         Air Quality

 

13.4.3.1   Monitoring and audit of the Total Suspended Particulates (TSP) levels shall be carried out to detect any deterioration in air quality and so enable early action to be taken for impact prevention or amelioration. Both 1-hour and 24-hour TSP levels shall be measured to indicate the impacts of construction dust on air quality using a direct reading dust monitor and high volume sampler respectively.  Both the 24 hour TSP levels and 1-hour TSP levels shall be measured in accordance with the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.  Direct reading methods can be used for ad hoc measurements if required.  Other relevant data that will need to be recorded will include elapsed-time metre reading for the start and stop of the sampler, the prevailing weather conditions, namely wind speed and direction, temperature, pressure and rainfall.

 

13.4.3.2   The sampling frequency will be at least once in every six-days for 24-hour TSP monitoring and at least three times in every six days for 1-hour TSP.  Action and limit levels are shown in Table 13.4.

 


Table 13.4:              Action and Limit Levels for Air Quality

 

Parameters

 

Action

Limit

24 Hour TSP

Level (:g/m³)

For baseline level # 200 :g/m³, action level = average of baseline level plus 30% and limit level

 

For baseline level > 200 :g/m³, action level = limit level

260

1 Hour TSP

Level (:g/m³)

For baseline level # 384 :g/m³, action level = average of baseline level plus 30% and limit level

 

For baseline level > 384 :g/m³, action level = limit level

500

 

13.4.4         Water Quality

 

13.4.4.1   Surveys are to be undertaken for watercourses which are within the influence of construction works at least twice per week. The surveys should include a description of the stream course, influencing factors, photographs of the watercourse and a map showing areas of project construction works. In addition measurements of suspended solids, dissolved oxygen and pH should be taken at all monitoring stations at least three times per week and also in-situ measurements taken daily at strategic locations, as specified in the EM&A Manual.  In association with the water quality parameter, some relevant data shall also be measured, such as monitoring location/position, time, water depth, water temperature, DO saturation, weather conditions, and any special phenomena and work underway at the construction site etc.

 

13.4.4.2   Any noticeable change to water quality should be recorded in the watercourse survey reports and should be investigated and remedial actions shall be undertaken to reduce impacts. Particular attention shall be paid to the Contractor’s incorporation of mitigation measures. Action and limit levels proposed for the water quality parameters to be measured are shown in Table 13.5.

 

Table 13.5:               Action and Limit Levels for Water Quality

 

Parameters

Action (mg/L)

Limit (mg/L)

DO in mg/L

(Surface, Middle & Bottom)

Surface and Middle

5%-ile of baseline data for surface and middle layer

 

Bottom

5%-ile of baseline data for bottom layers

Surface and Middle

4mg/L or

1%-ile of baseline for surface and middle layer

 

Bottom

2mg/L or

1%-ile of baseline data for bottom layer

Suspended Solids

95%-ile of baseline data or  120% of control station's SS (at the same tide of the same day if appropriate)

99%-ile of baseline or 130% of upstream control station's SS (at the same tide of the same day, if appropriate)

Turbidity (Tby) in NTU

(depth-averaged)

95%-ile of baseline data or 120% of upstream control station's Tby (at the same tide of the same day, if appropriate)

99%-ile of baseline and 130% of upstream control station's Tby (at the same tide of the same day, if appropriate)

pH

n/a

<6.5 or >8.5

                 Notes:             

           -    For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

           -    For SS, non-compliance of the water quality limits occurs when monitoring  result is higher than the limits.

           -    All the figures given in the table are used for reference only and the DEP may amend the figures whenever it is considered necessary.

           -    ‘Depth Averaged’ is calculated by taking the arithmetic mean of the in-situ parameters readings at all three depths.  For suspended solids ‘depth averaged’ is calculated by combining all three samples into one mixed sample which is analysed to produce a physical arithmetic mean.

 

13.4.5         Ecology

 

13.4.5.1   Walk-over ecology surveys are to be undertaken twice a month in areas which are disturbed by the construction works. The surveys shall include a report on ecological disturbances to the area and corrective measures should be recommended. 

 

13.4.5.2   Of concern during the early years of operation will be erosion of recently revegetated cut and fill slopes. These should be monitored visually and especially following storms.  Any corrective measures should be recommended.

 

13.4.5.3   Success of replanting should be monitored by regular visual inspections and special care should be taken to ensure than any damaged, diseased or dying trees or shrubs are replaced as required. A detailed programme of visits should be agreed prior to commencement of the contracts and should be at least once every two months for a period of a year during the maintenance period.

 

13.4.5.4   For specific ecological mitigation measures, the audit schedule as detailed in Table 13.6 shall be followed.

 

Table 13.6   Ecological Audit Schedule during Construction

 

Number

Construction Phase

C1, C2, C3, C4

Audit compliance once at the end of the contract.

C5

Audit compliance at least three times per week during implementation which will be prior to the start of the main construction activities.

 

After translocation is complete, carry out audit survey to determine if all Pavetta hongkongensis, Acampe rigida, Liparis viridiflora and Artocarpus hypargyreus have been translocated.

C6, C7

Audit compliance at least three times per week during implementation which will be prior to the start of the main construction activities.

 

After translocation is complete, carry out audit survey to determine if all Hong Kong Newt, Romer’s Tree Frog, Lesser Spiny Frog and Beijiang Thick-lipped Barb have been moved.

 

 

 

 

 

 

13.4.6         Landscape and Visual

 

13.4.6.1   The landscape construction works will be closely monitored to ensure all measures specified to promote the healthy establishment of plants are undertaken fully and that any defects or omissions are rectified at the earliest opportunity and before the end of the construction period.

 

13.4.6.2   The protection provided to all trees and woodland blocks identified will be monitored throughout the construction period to ensure that it is kept in a good condition.  Any damage by the Contractor or by other parties to the protection of the trees and woodland will be noted for remedial action.

 

13.4.6.3   The extent of the agreed works areas will be regularly checked during the construction phase.  Any trespass by the Contractor outside the limit of the works, including any damage to existing trees and woodland, will be noted.


 

13.4.6.4   Operations relating to the supply of specialist plant material (including the collecting, germination and growth of plants from seed) will be monitored to ensure that plants will be available in time to be used within the construction works.

 

13.4.6.5   The progress of the engineering works will be regularly reviewed on site to identify the earliest opportunities for the landscape works to be undertaken.

 

13.4.7         Waste

 

13.4.7.1   Supervision of the construction works should be undertaken on a weekly basis during site inspections to ensure that waste material is being properly stockpiled and handled.  Any malpractice should be reported and remedial measures recommended.  Review of the waste documents shall be undertaken on a weekly basis to ensure waste management is being undertaken in accordance with the Waste Management Plan.

 

13.4.8         Cultural Heritage

 

13.4.8.1   Supervision of the construction works should be undertaken twice a month for the shrine in Lung Tseng Tau and the Fong Yuen Nunnery.  The surveys will audit the implementation of the recommended mitigation measures in these areas, namely the creation of a protective barrier around the shrine if it falls within the works area, maintenance of the 50 metre wooded buffer between the road and the nunnery, planting of foliage along the cycle path in the vicinity of the monastery and fence of the main building to keep it separate from the works on the cycle path. Any disturbances to these areas will be reported and corrective measures should be recommended to ensure that both buildings are adequately protected during works.

 

13.5               Operational Impact Monitoring

 

13.5.1         Post construction monitoring is limited to monitoring of noise, ecology and landscaping to ensure the recovery of habitats and plantings and ensure the effectiveness of noise mitigation measures.  Site inspections for ecological and landscape and visual resources shall be undertaken once every two months for the first year of operation. For specific ecological mitigation measures, the audit schedule as detailed in Table 13.7 shall be followed.

 

Table 13.7   Ecological Audit Schedule during Operational Phase

 

Number

Operation Phase

C1, C2, C3, C4

Audit success of wildlife tunnels, culverts and drainage channel escape ramps once every two months.  Continue for a period of one year.

 

 

C5

Audit success of transplantation twice every month for the first 4 months after transplantation and once every two months after this period by assessing survival of transplanted plants.  Continue for a period of one year.

 

If audit records any sign that the plants have not established properly, measures to rescue the plants should be undertaken.  specific measures should be determined by the landscape architect at the time.

C6, C7

Audit success of translocation once every two months after completion by assessing survival of transplanted species.  Continue for a period of one year.

 

 

 

13.5.2         Noise monitoring during the operational stage shall be undertaken at representative locations twice during the first year of operation in months 6 and 12.  Any three 30 minute periods during the week day peak times shall be monitored.

 

13.6               EM&A Responsibilities

 

13.6.1         In respect of the design phase EM&A, the Consultant commissioned to undertake the Design and Construct contract will be required to designate an auditor(s) to undertake an environmental audit of the design of these measures in order to ensure that the recommendations of the EIA have been fully and properly specified.  The design audit shall be undertaken as and when the relevant design aspects are produced.  The Consultant shall use suitably qualified staff to undertake the audit requirements to the satisfaction of the EPD, the AFCD and the PlanD/LPU as appropriate.

 

13.6.2         During the construction and operational phases of the project, an Environmental Specialist (ES) is to be employed by the Contractor.  He shall ensure the Contractor’s compliance with the project’s environmental performance requirements during construction and undertake the post construction EM&A works and his responsibilities will include field measurements, sampling, analysis of monitoring results, reporting and auditing.  The ES shall be approved by the ER and the Director of Environmental Protection (DEP) and shall be competent and shall have at least 7 years relevant environmental monitoring and audit experience on projects of a similar scale and nature.

 

13.6.3         The ES will require suitably qualified support staff (the Environmental Team, (ET)) to carrying out the EM&A programme.  Both the ES and members of the ET shall be independent and shall not be in any way connected to the Contractor’s company.  Due to the specialist nature of some of the EM&A works required for this project, the ET should comprise professionals proficient to undertake the tasks involved.  Thus, the ET should include personnel experienced in noise, dust and water quality monitoring and supervision of waste management.

 

13.6.4         Accordingly, a qualified ecologist(s), with a minimum of 5 years post qualification experience and two years practical experience in ecological remediation and relocation works, will be required as part of the ET to audit the transplantation of key species as recommended by the EIA.  The ecologist(s) should have suitable experience in the areas to be audited.  In addition, a Registered Landscape Architect, as defined by the Landscape Architect’s Registration Board, will be required on the ET to monitor and audit the landscaping installation works and assist in the audit of the ecological transplantation and restoration works.

 

13.6.5         In respect of the archaeological supervision, these works should be undertaken by a suitably qualified person to the acceptability of the AMO.  The responsibilities of the specialist will be to oversee the construction activities, notify the AMO, EPD and the ER of any findings and develop appropriate mitigation measures.

 

13.6.6         In addition to the ES, an Independent Checker (Environment) (IC(E)) shall be resident on site to advise the ER on environmental issues related to the project.  The role of the Checker shall be independent from the management of construction works, but the Checker shall be empowered to audit the environmental performance of the construction activities and operational mitigation.  The IC(E) shall have project management experience in addition to the requirements of the ES specified in Section 13.6.2 and the appointment of the IC(E) will be subject to the approval of the ER and the DEP.  The IC(E) may require specialist support staff in order to properly carry out his duties.

 

13.7               Reporting

 

13.7.1         Deliverables during the design phase will comprise a Design Audit Report at the end of the detailed design which will confirm that the requirements of the EIA have been fully taken into account in the project design.  Construction and operational reporting will be in the form of the baseline survey report and regular and summary EM&A Reports which should be prepared in accordance with the requirements of Annex 21 of the TMEIA.  It is recommended that EM&A Reports are issued monthly and bi-monthly for the construction and operational stages respectively.   Further details on the contents of these reports is provided in the EM&A Manual.

 

13.8               Implementation Schedules

 

13.8.1         The recommended mitigation measures specified in this EIA report have been summarised in the Environmental Mitigation Implementation Schedules provided in Appendix C for air quality, noise, water quality, waste, ecology and landscape and visual.