10 LANDSCAPE AND VISUAL IMPACT

10.1 Introduction

10.1.0.1 This chapter outlines the landscape and visual impacts associated with the Deep Bay Link Road in accordance with the Environmental Impact Assessment Ordinance which became law in Hong Kong on 1st April 1998. Both construction and operation impacts are assessed. The assessment includes:

Alignment Options

10.1.0.2 Alignment Options are discussed in detail in Section 1 of this report. Briefly these options considered the following:

10.1.0.3 The Environmental Assessment Technical Report provides the initial assessment of the DBL routing and the landing point of the SWC. The report determined that there were three feasible alternatives for the landing point. These were 1) the landing point at Pak Nai; 2) the landing point at Sheung Pak Nai and 3) the landing point at Ngau Hom Shek. The result of the option assessment for these landing points concluded that Ngau Hom Shek was the most feasible.

10.1.0.4 A supplementary study was carried out prior to this DBL EIA to consider a tunnel alignment of DBL based upon the landing point at Ngau Hom Shek. This comprised an option assessment of three alternatives: 1) At Grade Scheme, 2) a Tunnel Scheme and 3) a Cavern Scheme. The at grade scheme, which is the basis of this EIA, had demonstrated that it provided the overall best solution taking into account environment, land, engineering, cost and programme.

10.1.0.5 Considerations for the refinement of the alignment in the current scheme include landuse, engineering and connection requirements, burial grounds, Ecologically Sensitive Areas and SSSI, sites of archaeological interest and cultural heritage importance and a range of environmental considerations.

10.2 Environmental Legislation and Guidelines

10.2.0.1 The following legislation, standards and guidelines are applicable to the evaluation of landscape and visual impacts associated with the construction and operation of the DBL:

10.2.0.2 In addition, reference has been made to:

10.3 Scope and Content of the Study

10.3.0 Deep Bay Link - Investigation and Preliminary Design

10.3.0.1 The nature and extent of the Deep Bay Link Road is described below:

10.3.0.2 The Deep Bay Link is a 5.4km proposed trunk road of dual - 3 lane standard providing a strategic link between Shenzen Western Corridor (landfall at Ngau Hom Shek) and Yuen Long Highway and the proposed Route 10 at Lam Tei. The majority of the DBL will be on an elevated viaduct with the exception of approximately 990m which will be at grade.

10.3.0.3 An interchange is included in the project, the Lam Tei Interchange will connect DBL to Yuen Long Highway and the possible future Route 10. An additional interchange is proposed at Hung Shui Kiu.

10.3.0.4 Associated civil, structural, geotechnical, landscape and drainage works, street lighting aids (including sig. gantries), noise barriers, fire hydrants, traffic control and surveillance system, security control system and E&M works.

10.3.0.5 Reprovisioning and modification works to San Wai Sewage Treatment Works and any associated compensatory land.

10.3.0.6 The works will include:

10.3.1 Limits of the Study Area

10.3.1.1 The limit of the landscape impact study is 500m on either side of the limit of the Deep Bay Link Road. The limits of the visual impact studies are the zones of visual influence (ZVIs) of the Deep Bay Link Road during the construction and operation phases, which are illustrated in Figure 10.5.12.

10.3.2 Assessment Methodology

10.3.2.1 Landscape and visual impacts have been assessed separately for the construction, operational (opening day) and residual (Year 10) stages. The assessments take into account existing/planned/approved land uses as baseline conditions, and assess all direct and indirect impacts on existing/planned/approved land uses, and on future outlook of the area. Potential impacts are identified in terms of being beneficial/adverse, direct/indirect, short term/long term, and reversible/irreversible.

10.3.2.2 Impacts are determined in terms of significance thresholds, which are the product of the magnitude of change to baseline conditions due to the proposed Works and the sensitivity of resource/character/receivers. In general terms, magnitude of change relates to parameters of the proposed Works in the context of baseline conditions, and sensitivity refers to properties of resource/character/receivers:

10.3.2.3 Where appropriate the cumulative impacts of other development proposals is considered.
Landscape Impacts

10.3.2.4 The assessment of landscape impacts involves the following procedures:

10.3.2.5 The rationale for dividing the degree of significance into four thresholds, namely substantial, moderate, slight and negligible depending on the combination of large-intermediate-small-negligible magnitude of change, and high-medium-low degree of sensitivity is presented in Table 10.1.

10.3.2.6 The inclusion of a 'negligible' magnitude of impact is necessary because a negligible impact is different from a 'small' magnitude of impact. A 'small' magnitude impact will cause a varying degree of resultant impact significance depending on whether the landscape resource's sensitivity is low, medium or high. However, a negligible magnitude of impact will always result in negligible significance, irrespective of the sensitivity of the resource.

Table 10.1 Relationship between Receptor Sensitivity and Impact Magnitude in Defining Significance

Impact Significance

Receptor Sensitivity (Landscape Resource or VSR)

Low

Medium

High

Magnitude of to baseline conditions due to the Works

Large

Slight/Moderate

Moderate/ Substantial

Substantial

Intermediate

Slight/Moderate

Moderate

Moderate/ Substantial

Small

Negligible/Slight

Slight/Moderate

Slight/Moderate

Negligible

Negligible

Negligible

Negligible

10.3.2.7 The assessment of visual impacts involves the following procedures.

10.3.2.8 Those who view the impact from their homes are considered to be highly sensitive as the attractiveness or otherwise of the outlook from their home will have a substantial effect on their perception of the quality and acceptability of their home environment and their general quality of life. Those who view the impact from their workplace are considered to be only moderately sensitive as the attractiveness or otherwise of the outlook will have a less important, although still material, effect on their perception of their quality of life. The degree to which this applies depends on whether the workplace is industrial, retail or commercial. Those who view the impact whilst taking part in an outdoor leisure activity may display varying sensitivity depending on the type of leisure activity. Those who view the impact whilst travelling on a public thoroughfare will also display varying sensitivity depending on the speed of travel and whether the view is continuous or occasionally glimpsed.

10.3.2.9 The rationale for dividing the degree of significance into four thresholds, namely substantial, moderate, slight and negligible depending on the combination of large-intermediate-small-negligible magnitude of change, and high-medium-low degree of sensitivity of the VSR's is presented in Table 10.1. The inclusion of a 'negligible' magnitude of impact is necessary because a negligible impact is different from a 'slight' magnitude of impact. A 'slight' magnitude impact will cause a varying degree of resultant impact significance, depending on whether the receptor's sensitivity is low, medium or high. However, a negligible magnitude of impact will always result in negligible impact significance, irrespective of the sensitivity of the VSR.

10.3.2.10 In addition, the following assumptions have been made in the assessment:

10.3.3 Route 10 Study Interface

10.3.3.1 The study area for this agreement interfaces with the proposed Route 10 at the area between Lam Tei Quarry and Yuen Long Highway. The landscape and visual impacts south of this interface are being addressed under the Route 10 agreement. It is necessary to consider the impacts assessed in both agreements on a collective or cumulative basis. It is envisaged that as both studies proceed further detailed references will be incorporated within each respective report. At present detail regarding the design development of Route 10 is not available and assessment of the works with respect to the interface with DBL is broad and preliminary only.

10.3.4 SWC Study Interface

10.3.4.1 The study area for this project has changed from that indicated in previous papers on LVIA. The interface with the SWC is now located along the coastline (i.e. MHW). Previously, it was located 300m inland from the coastline. It is necessary to consider the impacts assessed in both projects on a collective or cumulative basis. It is envisaged that as both studies proceed further detailed references will be incorporated within each respective report. The construction phase delineation remains at a point 300m inland from the coastline.

10.4 Planning and Development Control Framework

10.4.0 Planned and Committed Development

Hung Shui Kiu NDA RODP

10.4.0.1 The Hung Shui Kiu area has been identified as priority development area in the Planning and Development Study on North West New Territories commissioned by Territory Development and Planning Department. A Recommended Outline Development, which has taken into account the preliminary alignment of DBL, has been prepared for the new development area. In this Recommended Outline Development Plan for Hung Shui Kiu NDA, land is reserved for DBL. This recommended Outline Development Plan is depicted in Figure 1.8 and described in more detail below:

10.4.0.2 The key components of the Hung Shui Kiu RODP are briefly described below:

10.4.0.3 Please note for a more detailed description of the HSK NDA RODP refer to the Explanatory Statement.

10.4.1 Landscape Planning Destination

10.4.1.1 A review has been undertaken of the current planning goals and objectives, statutory land-use and landscape planning designations for the Study Area. These have drawn upon information based upon the Outline Zoning Plans.

10.4.1.2 The current statutory designations for the Study Area are shown on the following Outline Zoning Plans:

10.4.1.3 Under the current OZPs the proposed DBL alignment passes or affects land designated for the following uses: 'Coastal Protection Area (CPA)', 'Agriculture (AGR), 'Green Belt (GB)', 'Government/Institution/Community (G/IC)', 'Recreation (REC)', 'Conservation Area (CA)', 'Residential Groups B,C & D (R(B,C & D)), 'Undetermined (U)', 'Other Specified Uses (OU)', and 'Village Type Development (V)'. No lands are reserved for the DBL in these OZPs. The zoning of lands is depicted in Figures 10.4.1 to 10.4.4 and 1.8.

10.4.1.4 The planning intentions of these designated OZPs are described below in terms of landscape and visual impact assessment of the proposed DBL. Only the planning intentions of relevant designated areas discussed. The current OZPs will require amendment to incorporate the DBL alignment once it gains approval.

Approved Lam Tei and Yick Yuen Outline Zoning Plan

10.4.1.5 'Green Belt': the planning intention of this zone is to define urban and sub-urban limits, contain urban sprawl and to act as a buffer area between developments and more sensitive areas. The Green Belt affected in this area provides a significant buffer between Yuen Long Highway and adjacent areas. It also provides a buffer to the Lam Tei Quarry area. It comprises stands of significant trees.

10.4.1.6 'OU' annotated 'Quarry': the Lam Tei Quarry is expected to cease operation prior to the roads completion.

10.4.1.7 Other designated zones affected are 'Residential C & D', 'Other Uses' including Petrol Filling Stations, 'Village Type Development' and 'Undetermined'. Specific landscape and visual impacts of the road are addressed later in this report.

Approved Ha Tsuen Outline Zoning Plan

10.4.1.8 'Green Belt': the planning intentions for this zone are as described above. The Green Belt zones in this area include the ranges of vegetated knolls and permitted burial grounds to the east and south east of Ngau Hom Shek and Ngau Hom Sha respectively, and the burial grounds to the north of the San Wai Sewage Treatment Plant and to the north of San Sang San Tseun. Since much of the area is designated permitted burial grounds, these areas are not frequently used as recreation resources. The DBL dissects the Green Belt Area located to the south of Ngau Hom Shek. It follows a narrow, steep sided valley which runs north south linking the north of Ha Tsuen with Ngau Hom Shek.

10.4.1.9 'Agriculture': the planning intention of this zone is to retain and safeguard good agricultural land for agricultural purposes. The agricultural land in Ngau Hom Shek is categorised 'good quality' and is under active cultivation. The DBL traverses this zone and links with the SWC bridge with the northern approach road section.

10.4.1.10 'Coastal Protection Area' (CPA): the planning intention of this zone is to preserve the natural coastline with a minimum of built development so as to retain their attractive coastal features. The DBL traverses this zone at Ngau Hom Shek to join with the SWC bridge.

10.4.1.11 Ha Tsuen/Castle Peak Firing Range: to the west of the area covered by the Ha Tsuen OZP lies Castle Peak Firing Range. Access to this area is restricted.

10.4.1.12 Justifications for the development are provided within the Cross Border Links Feasibility Study, and Preliminary Project Feasibility Study (PPFS) Report for Deep Bay Link prepared by the Transport Department (May 1999) and the fact that the alignment has been included in the latest development study for the area (Hung Shui Kiu NDA RODP). The project, therefore, is in accordance with the planning goals and objectives for the study area. Nevertheless, the Deep Bay Link must be very carefully designed to minimise any potentially adverse impacts on the environment.

10.5 Baseline Study

10.5.0 Physical Landscape Resources - Generally

10.5.0.1 The landscape resources are mapped in Figures 10.5.1 to 10.5.4. Photo views illustrating the landscape and visual characteristics are illustrated in Figures 10.5.5 to 10.5.11 inclusive.

Landform

10.5.0.2 The proposed DBL alignment commences at the point where Route 10 exits from the tunnel above Lam Tei Quarry, crosses the Yuen Long - Tuen Mun corridor and follows the interface of the foothills of Yuen Tau Shan and the large, flat valley area of Ha Tsuen. This valley extends from Tuen Mun and Lam Tei in the south to Lau Fau Shan and Kai Shan in the north and Yuen Long in the northeast. The valley is bounded by the mountain ranges of Yuen Tau Shan to the west, Tai Lam to the south and east and Kai Shan and Lau Fau Shan to the north. These mountain ranges and associated foothills consist of steep sided hills and valleys and form a dramatic edge to the valley.

10.5.0.3 In the north, where the proposed DBL will join the Shenzen Western Corridor bridge at Ngau Hom Shek village, the topography consists of a narrow coastal plain bounded by the Yuen Tau Shan foothills to the south and Deep Bay to the north.

10.5.0.4 To the south, where the proposed DBL meets Proposed Route 10, the topography consists of the narrow valley area which forms the Yuen Long - Tuen Mun Corridor bounded by the foothills of Tai Lam in the south and Castle Peak in the north.

Drainage

10.5.0.5 There is an extensive network of natural streams and small rivers associated with the foothills and valleys of Lau Fau Shan mountain. In addition, there are several streams located within the foothills of Tai Lam, adjacent to the Lam Tei Quarry and associated with Lam Tei and Hung Shui Hang Reservoirs. These streams eventually discharge into the main drainage channel running from Lam Tei to Tin Shui Wai.

10.5.0.6 Many of these streams supply wetlands, marshes, fish ponds and other agricultural fields within the study area. An example of this is at Tseung Kong Wai where a small valley containing fish ponds, orchards and other agricultural fields which are irrigated by a small stream.

10.5.0.7 The small steep sided valley adjacent to Ngau Hom Shek also contains a prominent stream and associated marshes.

10.5.0.8 For more detailed information on the natural drainage systems impacted by the project refer to the Water Quality and Ecology Chapters.

Vegetation

10.5.0.9 The vegetation of the subject site consists of the following:

10.5.1 Human and Cultural Landscape Resources - Generally

Buildings and Settlements

10.5.1.1 Primarily, the existing development within the study area consists of several villages and village type developments with large areas of container storage yards located adjacent to the foothills of Lau Fau Shan. A couple of high density residential developments exist in the Lam Tei area within the study boundary. Much of the area is subject to the HSK NDA RODP.

10.5.1.2 Villages within the study area include:

10.5.1.3 The high density residential developments surrounding the subject site include:

Infrastructure

10.5.1.4 Infrastructure present within the study area includes:

10.5.1.5 Future committed infrastructure includes:

10.5.2 Landscape Resources

10.5.2.1 Several landscape resources have been identified within the study area. These are described below and indicated in Figures 10.5.1 to 10.5.4. A summary is provided in Table 10.2.

L1: Mangrove
10.5.2.2 Areas of mangrove are located on the coastline at Ngau Hom Shek. In addition to their ecological value, these provide an important visual definition to this narrow coastal plain. They also provide a landscape/visual buffer between village development and Hau Hoi Wan. The landscape sensitivity to change of this area is judged to be High.

L2: Mudflat
10.5.2.3 Mudflats are an inherent part of the coastal landscape in this area. The shallow water of Deep Bay results in an extensive tidal variation. The mudflats, whilst being a valuable ecological resource, provide a unique visual and landscape component within the study area. The landscape sensitivity to change of this area is judged to be High.

L3: Marsh & Wet Agriculture
10.5.2.4 Several areas of marsh occur in the study area. The major areas are 1) an area located to the east of Ngau Hom Shek and is associated with the Ngau Hom Shek East Stream; 2) an area located in the narrow valley located adjacent to Ngau Hom Shek where the SWC joins the DBL and 3) several small areas located at the valley adjacent to Ha Tsuen. All are formed by abandoned fish ponds and, therefore, semi-natural. The wet agricultural areas consist of small areas located in Ha Tsuen and Hung Shui Kiu. The landscape sensitivity to change of this area is judged to be High.

L4: Agriculture, Orchards and Plantations
10.5.2.5 The areas identified as agriculture include orchards and vegetable fields. Orchards are common around villages and dwellings. Typical orchard species include Wampi, Longan, Litchi, Breadfruit, mango and citrus trees. Vegetable fields include a wide variety of species including Cabbages, Corriander, Lettuce, etc. Plantation woodlands include trees of mostly exotic species and generally occur in lower slope areas adjacent to village and other agriculture. Typical species include Acacia, Lophostemon, Slash Pine and Eucalyptus sp. The plantations are also usually located to other stands of naturally occuring woodland. The agricultural and plantation areas contribute significantly to the agri- rural visual character of many of the areas within the study area, especially those areas around Ha Tsuen and Ngau Hom Shek. The landscape sensitivity to change of this area is judged to be High.

L5: Fish Ponds
10.5.2.6 Several fish ponds are located within the study area. These are generally abandoned, under-utilised or have been filled in but a few remain managed. These are mostly located at Ngau Hom Shek and the valley adjacent to Ha Tsuen. The fish ponds located at Ngau Hom Shek are regarded as significant contributor to the coastal Deep Bay wetland ecosystem but the those located at Ha Tsuen are isolated (refer to the ecological impact section). The value of fish ponds in terms of visual significance is high. The landscape sensitivity to change of this area is judged to be Medium.

L6: Stream Channels
10.5.2.7 There are a number of small stream channels within the study area. These are generally in a natural and rocky state on the hillsides but tend to be channelised or culverted or diverted to be used in wet agriculture and fish ponds at the valley floor. As a consequence the streams have a high landscape value on the hill sides but this value is reduced once they reach the lower slope areas and valley floor. The landscape sensitivity to change of this area is judged to be High.

L7: Grassland
10.5.2.8 Grassland and low shrub areas are located within the Green Belt and Conservation Areas adjacent to Ha Tsuen / Castle Peak Firing Range. These are composed of large areas located generally on ridgelines and steeper slopes which cannot support woodland planting and are typical of Hong Kong's upland landscape. The combination of topography and grassland/scrub mosaic is of high visual value. The landscape sensitivity to change of this area is judged to be Medium.

10.5.2.9 A prominent ridgeline located within the Greenbelt directly to the south of Ngau Hom Shek is significant in terms of its landform rather than its vegetative cover. Vegetative cover consists of grassland and some small isolated trees. This is generally of poor quality due to the regularly burning it receives, the dumping of rubbish and generall disturbance.

L8: Woodland (including Tall Shrub)
10.5.2.10 Woodland areas are located within the Green Belt and Conservation Areas adjacent to Ha Tsuen / Castle Peak Firing Range and Lam Tei Country Park. These woodlands, together with the grassland/shrub areas create a green backdrop to the valley and are an important visual amenity along the DBL route. Much of the woodland in the lower Green Belt areas is interspersed with graves and their associated access trails. As a consequence to this, the woodland here tends to be poor in quality. In addition, at the edges of most of the Green Belt woodland areas, burning and haphazard development has encroached destroying many trees resulting in very poor quality woodland. Refer to Figure 10.5.8. The landscape sensitivity to change of this area is judged to be High.

L9: Village / Residential / Warehouse / Factory / Roads and similar developments.
10.5.2.11 Village type development consists of small rustic dwellings and workshops. The character of the village areas is represented by a mixed land use of small scale dwellings, minor storage areas, small scale agriculture and other individual dwellings. The landscape sensitivity to change of this area is judged to be Low.

10.5.2.12 There are many villages within the valley. Those within the landscape study area include Ngau Hom Shek, Ha Tsuen, Tseung Kong Wai, Kau Lee Uk Tsuen, San Sang San Tsuen, and many in the Lam Tei area. Some of these are San Hing Tsuen, Fu Ha Tsuen, Tsoi Yuen Tsuen, Lam Tei Tsuen, Yick Yuen Tsuen, Sun Fung Wai and Chun Uk Tsuen.

10.5.2.13 Residential developments identified in the Baseline Landscape Conditions include those medium / high density residential developments located around the Lam Tei area. These include:

10.5.2.14 High rise residential developments exist at Tin Shui Wai. These are located outside the landscape study boundary but within the visual envelope. At the nearest point, these estates are located 1,500 metres from the proposed DBL. The estates include Tin Shui Estate, Tin Oi Court, Kingswood Villas, Tin Yiu estate and Tin Yau Court.

10.5.2.15 Major infrastructure includes large roads and highways, canals, rail lines, etc. Major infrastructure elements within the study area include Yuen Long Highway, Castle Peak Road and interchanges. Future committed works include west rail and infrastructure associated with HSK NDA. These are not indicated on the baseline conditions plan but will be included in assessing the impacts. Refer to Figure 10.5.6.

10.5.2.16 Open Storage yards are areas used for the storage of large shipping containers. These are stacked sometimes up to seven containers high and yards cover large areas of the landscape creating major landscape and visual impact. Many yards have been created through the filling of ponds and clearing of vegetation. Areas of these yards exist in Ha Tsuen in the HSK NDA. Refer to Figure 10.5.7.

10.5.2.17 There are two large quarries bordering Tai Lam Country Park. One is located to the north of Lam Tei and the other is located at the vicinity of Lam Tai interchange (Lam Tei Quarry). These quarries are located on the slopes of the foothills of Tai Lam Country park and, as such, involve extensive slope cutting. Both these quarries can been seen from many areas within the valley.

L10: Landform
10.5.2.18 Landform has been included as a landscape resource as it can provide highly significant contribution to the landscape character of an area and plays an inherent role in defining vegetation associations. There are three significant areas of landform in the study area which may be impacted upon. These areas are part of the foothills of Yuen Tau Shan and are typical of Hong Kong lowland topography. As mentioned previously, the steep sided hills and there interface with the flat valley floor create a dramatic topographic form. The proposed DBL road will impact these within the Greenbelt area south of Ngau Hom Shek and at San Sang San Tsuen. The landscape sensitivity to change of this area is judged to be Medium.

10.5.3 Landscape Character Areas

10.5.3.1 The study area consists of eight distinct landscape character zones (LC). These are described below and indicated in Figures 10.5.2 to 10.5.4. A summary is provided in Table 10.2.

LC1: Agricultural Coastal Lowland
10.5.3.2 This landscape character zone comprises low-lying land which is used for agricultural purposes, ponds and wetland marsh area. The character of this zone is generally open with few built structures or roads. Trees of any substance are largely limited to around the edges of this Character Area or along watercourses. The landscape sensitivity to change of this area is judged to be Medium.

LC2: Greenbelt Foothills
10.5.3.3 The Greenbelt Foothills are characterised by eroded slopes primarily vegetated by grassland species. The natural quality of this character area is mixed with few built structures with the exception of a number of graves and associated trails. This tends to have a detrimental effect on the quality of the grasslands. However, the zone provides important containment for the coastal strip, providing isolation from nearby urban areas and therefore has a high landscape value. The landscape sensitivity to change of this area is judged to be High.

LC3: Village Coastal Lowland
10.5.3.4 The Village Coastal Lowland forms a modified strip along the coast containing small rustic dwellings and workshops. The character of the buildings is generally small scale, nestled into the landscape rather than competing or contrasting. The buildings however are of poor quality with many being used for storage. The landscape sensitivity to change of this area is judged to be Medium.

LC4: Sea Edge
10.5.3.5 The Sea edge consists of mud flats and mangroves, providing an important transition between the land and Deep Bay. The character is open with expansive views available across Deep Bay. The natural character of this zone is generally high with the exception where rubbish has been dumped. The landscape sensitivity to change of this area is judged to be High.

LC5: Valley Lowland Agriculture
10.5.3.6 This zone comprises agricultural areas including plantations, orchards, some paddy fields and fish ponds located on the valley floor within the Ha Tsuen and Lam Tei areas. These areas are dotted amongst villages, open storage areas and other development which is rapidly encroaching upon these areas. Many of these fields are abandoned. They provide a remnant agrarian character in the study area. Much of these areas will be developed by the future HSK NDA. The landscape sensitivity to change of this area is judged to be Medium.

LC6: Valley Lowland Mosaic
10.5.3.7 The bulk of the valley floor within the study area comprises development such as open storage yards, villages, small industries, residential development and associated infrastructure. Much of this is generally haphazard with little landscape value and will be developed by the future HSK NDA. The landscape sensitivity to change of this area is judged to be Low.

LC7: Lam Tei
10.5.3.8 Lam Tei comprises a mix of well established existing villages, recent low rise residential developments and associated land uses such as G/IC and open spaces. The infrastructure is more developed. Future projects such as the widening of Yuen Long Highway and the West Rail project will have a marked impact upon these areas. The landscape sensitivity to change of this area is judged to be Medium.

LC8: Green Belt / Country Park Uplands
10.5.3.9 The upland areas of Yuen Tau Shan and Tai Lam Country Park form the physical and visual boundary of the study area. They are essentially natural areas comprising of wooded and grassland slopes. These hills form a scenic backdrop surrounding the valley and are an important visual resource. The landscape sensitivity to change of this area is judged to be High.

10.5.4 Baseline Visual Conditions

10.5.4.1 The visual study area can be divided into two zones: 1) the small portion located at Ngau Hom Shek where the DBL joins the SWC on the coastline and 2) the other areas located within the Ha Tsuen/Lam Tei Valley.

Ngau Hom Shek

10.5.4.2 The isolated character of Ngau Hom Shek and the Deep Bay Coastline, combined with Castle Peak Range and the narrow low-lying agricultural areas, reduce the potential visibility of the section of DBL and the number of VSRs. However, the elevated nature of the road will increase its visibility to residents of Ngau Hom Shek and other adjacent VSRs. To the southeast the visual envelope will be contained by the ridgelines emanating from Castle Peak, and of indefinable length stretching out in the coastal waters to the north and south. This small section of the road will have limited visual impact compared to the SWC which stretches out across Deep Bay to Shenzhen.

10.5.4.3 Generally throughout the low-lying coastal areas, visibility is limited by vegetation. By retaining this vegetation, screening of the DBL will be possible due to the area's low-lying nature. With elevation, due either to topography or structures, the visibility of the proposal will increase proportionately.

Ha Tsuen / Lam Tei Valley

10.5.4.4 This large valley extends from Ha Tsuen and Lam Tei in the west to Tin Shui Wai and beyond in the east. It is bounded in the north and south by the foothills of Yuen Tau Shan and Tai Lam Country Park respectively. Surrounding hillsides create a picturesque scene and the long distance views to development in the east is visually exciting. The valley floor comprises a mosaic of villages, agriculture, open storage yards and other development.

10.5.4.5 The proposed DBL extends from the foothills of Tai Lam Country Park at Lam Tei and flies across at elevation to meet the foothills of Yuen Tau Shan. It then skirts the valley floor and generally follows the contours and horizontal alignment of the foothills both at grade and elevated in some areas.

10.5.4.6 The major visual impacts are expected at Lam Tei where it cuts across the valley floor at a high elevation. To add to this impact, the Lam Tei interchange on/off ramps and proposed noise barriers will contribute markedly to this impact.

10.5.4.7 By its location at the interface of the foothills and valley floor at Ha Tsuen and by its reduced elevation, visual impact here will be reduced. The present proliferation of open storage yards and other negative visual resources adjacent to its alignment in this area results in expected reduction in visual incompatibility. That is, the road form and structure will not be as visually contrasting as opposed to say being surrounded by natural woodland.

10.5.4.8 Consideration, however, must be given to the future HSK NDA which will occupy much of the valley floor adjacent to the road alignment. At present minimal detail as to the form of development within the NDA is available and certain assumptions are made to estimate the future visual conditions. In the future scenario, the DBL will be seen in conjunction with the extensive infrastructure development associated with the HSK NDA. This is an important consideration in assessing the visual impacts in this area.

10.5.5 Landscape Sensitivity to Change

10.5.5.1 The landscape resources that will be affected during the construction phase and operation phase, together with their sensitivity to change, are listed in Table 10.5. For ease of reference and co-ordination between text, tables and figures each landscape resource is given an identity number.

Table 10.2 List of the Landscape Resources affected during Construction & Operational Phases

Ref.

Landscape Resource / Landscape Character Area

Area (Ha) within study area

Sensitivity to Change

(Low, Medium, High)

Landscape Resource

L1

Mangrove Areas located on coastline

2.5

High

L2

Mudflats

17.5

High

L3

Marsh / Wet Agriculture

45.9

High

L4

Agriculture / Orchards / Plantation

150

High

L5

Fish Ponds

10.6

Medium

L6

Stream Channels

more than 2km

High

L7

Grassland

140

Medium

L8

Woodland (including tall scrub)

90

High

L9

Village / Residential / Warehouse / Factory / Roads / and similar developments.

450

Low

L10

Landform

-

Medium

Landscape Character Area

LC1

Agricultural Coastal Lowland

-

Medium

LC2

Greenbelt Foothills

-

High

LC3

Village Coastal Lowland

-

Medium

LC4

Sea Edge

-

High

LC5

Valley Lowland Agricultural

-

Medium

LC6

Valley Lowland Mosaic

-

Low

LC7

Lam Tei

-

Medium

LC8

Greenbelt/Country Park Uplands

-

High

10.5.5 Zone of Visual Influence (ZVI)

10.5.5.1 The ZVI does not vary between the construction and operational phases. The ZVI for both phases is illustrated in Figure 10.5.12. Due to the large flat valley area and the length of the proposed road, the ZVI is quite extensive and is generally defined by the following:

10.5.6 Key Visually Sensitive Receivers (VSRs)

10.5.6.1 Table 10.3 list the key VSRs found within the ZVI's for the construction phase and operational phase. For ease of reference, each VSR is given an identity number, which is used in the table and also in Figure 10.5.12. Table 10.3a summarises the characteristics of key views as seen in the photomontages.

Table 10.3 Identity and Characteristics of Key Visually Sensitive Receivers (VSRs) during Construction & Operation Phases

Ref

Location of Receiver

Number of receivers

Very Few/Few/Many/Very Many

Type of view

Partial/Vista/Panoramic

Duration of view

Constant

/Periodic

/Infrequent

Approximate

Minimum Distance to site (metres)

Residential Receivers

       

VSR1

Residents in Coastal Protection Area and Agriculture Area at Ngau Hom Shek

Few

Vista

Constant

0

VSR3

Residents in Existing Villages and Comprehensive Development Area northwest of HSK NDA

Many

Vista

Constant

500

VSR5

Users of Proposed Residential, Commercial and Community Facilities at HSK NDA

Very Many

Panoramic

Constant

50m

VSR6

Residents and Users of Proposed Residential Development and Community Facilities at HSK NDA.

Many

Vista / Partial

Constant

0

VSR9

Residents of Village Type Development at Fui Sha Wai

Many

Partial

Constant

1100

VSR11

Residents of Residential Development East of San Hing Tsuen and undetermined area Northwest of San Hing Tsuen

Many

Panoramic

Constant

0

VSR12

Residents of Residential Developments and Comprehensive Development Area East of Lam Tei Tsuen

Many

Panoramic

Constant

0

VSR13

Not Used

-

-

-

-

VSR16

Residents of High Rise Residential at Tin Shui Wai at the far north

Very Many

Partial

Constant

1500

Recreational Receivers

       

VSR2

Walkers in Green Belt and Conservation Areas at Ngau Hom Shek and Yuen Tau Shan.

Very Few

Panoramic

Constant

0

VSR7

Proposed Amenity Areas at HSK NDA

Few

Panoramic

Constant

50

VSR14

Walkers in Green Belt north of Yuen Long Highway

Very Few

Panorama

Constant

0

VSR15

Walkers in Green Belt south of To Yuen Wai

Very Few

Panorama

Constant

0

VSR10

Walkers in Green Belt and Conservation Area south of the Yuen Long Highway

Very Few

Panorama

Constant

0

VSR17

Walkers in Tai Lam Country Park

Few

Vista

Constant

500

Occupational Receivers

       

VSR4

Users of Proposed Other Specified land uses at HSK NDA (includes village & commercial use)

Few

Panorama

Constant

0

VSR8

Other Users in HSK NDA

Few

Partial

Constant

500

Travelling Receivers

       

T1

Travellers on Deep Bay Road

Very Many

Vista

Constant

0

T2

Travellers on Yuen Long Highway

Very Many

Panorama

Periodic

0

T3

Travellers on Castle Peak Road

Many

Vista

Periodic

0

T4

Travellers on Proposed West Rail at Hung Shui Kiu

Very Many

Vista

Infrequent

0

T5

Travellers on the proposed Deep Bay Link Road

Few

Vista

Periodic

0

* As the Bay is very shallow, marine craft are limited to the Southern Navigation Channel (HKSAR) and the Northern Navigation Channel. Since it is adjacent to the HKSAR / Shenzhen border, traffic is restricted. Only cargo and other commercial vessels are expected to be impacted upon.

Table 10.3a Characteristics of Key Views (refer to Figures 10.7.14 – 10.7.37)

View Point No.

Location

Type of View

Approximate Distance to Works (m)

Figure No.

1.1 & 1.2

View from existing Lam Tei Quarry

Panorama looking north west from elevated position adjacent to Lam Tei quarry.

350

10.7.14

2.1 & 2.2

Viewed from High Rise Residential Siu Hong Court

Elevated, panoramic view looking north east to Botania Villas and San Hing Tsuen with Tin Shui Wai in the background.

500

10.7.15

3.1 & 3.2

Viewed from Low rise Residential at Nai Wai

Ground level vista looking south.

250

10.7.16

4.1 - 4.4

Viewed from Hill North of San Sang San Tsuen

Elevated Vista looking south from crest of small hill.

60

10.7.17 & 18

5.1 - 5.4

Viewed from hill east of Ha Tsuen

Elevated vista looking NW from crest of hill.

50

10.7.19 & 20

6.1 - 6.4

Viewed from Hill west of Ha Tsuen

Elevated panorama looking east from hillside adjacent to valley showing Tin Shui Wai in background and rural / container storage areas.

80

10.7.21 & 22

7.1 - 7.4

Viewed from Hill north of San Wai.

Elevated panorama looking south towards Lam Tei.

300

10.7.23 & 24

8.1 - 8.4

Viewed from Deep Bay Road looking west.

Ground level vista from Deep Bay Road in Ngau Hom Shek.

100

10.7.25 & 26

Aerial View

Aerial Photo View to Deep Bay Link

Aerial view looking north from above Tai Lam Country Park

700

10.7.27a & b

10.1 - 10.4

3D Simulation view from HSK NDA

Computer generated view looking west from a hypothetical residential tower block within HSK NDA at an elevation of 20m.

250

10.7.28 & 29

11.1 - 11.4

3D Simulation view from HSK NDA

Computer generated view looking west from a hypothetical residential tower block within HSK NDA at an elevation of 20m.

250

10.7.30 & 31

12.1 - 12.4

3D Simulation view from HSK NDA

Computer generated view looking west from a hypothetical residential tower block within HSK NDA at an elevation of 20m.

250

10.7.32 & 33

13.1 - 13.4

Viewed from Ngau Hom Shek/Deep Bay Road

Ground level vista looking east from Deep Bay Road

300

10.7.34 & 35

14.1 - 14.4

Viewed from Greenbelt

Elevated panoramic view looking NW to SW of Deep Bay, Shenzhen coastal area, Ngau Hom Shek and west down HK coastline.

200

10.7.36 &10.7.37

10.6 Construction Impacts

10.6.0 Potential Sources of Impacts during Construction Phase

10.6.0.1 Briefly, the proposed DBL would involve construction of:

10.6.0.2 These key elements are described more fully in other chapters of this report. The extent of the above works is indicated in Figures 10.6.1 to 10.6.3.

10.6.0.3 The proposed development would create varying levels of impact on the physical landscape and on the visual amenity of the surrounding areas during the construction stage. Potential impacts would result from the following:

10.6.1 Nature and Magnitude of Landscape Impacts in Construction Phase (see Table 10.5)

Landform (L10)

10.6.1.1 Some impacts are expected on the form of the topography within the DBL alignment. These are described below:

10.6.1.2 For a length of approximately 500m, the road is to be constructed in the small valley located just south of Ngau Hom Shek. Some of the road is elevated on columns but there is substantial slope cutting to hillsides, excavation and filling to the valley bottom. It is estimated approximately 28,000 square metres of landscape will be affected. It is considered that that this impact will be permanent and irreversible. Topographic magnitude of change during construction is expected to be intermediate.

10.6.1.3 North of San Wai Sewerage Treatment Plant there are two on/off ramps leading to Ha Tsuen. In addition, an access track to a proposed emergency helicopter pad is also proposed. These facilities will have additional, though intermediate change to the topography of the area. Quantity of the area affected is included in the above figure.

10.6.1.4 There will be some minor embankment, cut and fill slopes created at the edges of the access way to the existing San Wai Sewerage Chamber which is to remain after construction. The sensitivity is medium and the magnitude of change is expected to be small.

10.7.1.5 Along the length of the road from San Wai Sewerage Treatment Plant to San Sang San Tsuen there are minor cut and fill slope works associated with the road (say 10,000 square metres). The magnitude of change in the topography is expected to be negligible to small.

10.6.1.5 Future Route 10 connection will affect more than 4,000 square metres of landform and will involve substantial slope cutting.

Vegetation

10.6.1.6 There is expected to be some minor impact upon the mangrove areas located on the coastline of Ngau Hom Shek (L1). This will be due to the construction of the SWC. The impact is expected to be moderate and temporary. An area of approximately 2,500 square metres could be affected. The sensitivity is high, the magnitude of change here is considered intermediate and unmitigated impact significance moderate.

10.6.1.7 Within the DBL alignment, permanent and irreversible impact to the marsh & wet agriculture (L3) within the study area. Approximately 5,000 square metres of marsh and wet agriculture areas will be permanently lost. The unmitigated magnitude of the impact here is considered small. Marsh associated with the Ngau Hom Shek east stream is expected to be affected. However, the marsh can be re-created and a wetland compensatory scheme is expected to be included within this project (refer to ecological impact report). Magnitude of change is expected to be small with a high sensitivity and an unmitigated impact significance of slight/moderate.

10.6.1.8 Permanent and irreversible impact is expected to some agriculture, orchards and plantation areas (L4). Approximately 59,000m² of agriculture, 10,000m² of orchards and 32,000m²of plantation area is expected to be lost. Totalling 101,000m² (10.1 Ha). The sensitivity of this resource is high. The magnitude of the change here is considered intermediate and unmitigated impact significance moderate/substantial.

10.6.1.9 Approximately 101,000m² of grassland and low scrub (L7) is expected to be impacted upon. Some impacts are expected on the form of the topography and grassland on the ridge east of the interface with the DBL alignment. In this area, the road will be cut into a ridge adjacent Ngau Hom Shek. Similar cutting will be expected at the head of this valley near Ha Tsuen. The rest of grassland/scrub affected occurs at the lower slopes. Much of the grassland located at these is highly disturbed and of generally a poor quality. It is considered the interesting topography combined with the grassland is of a greater landscape value. The sensitivity of this resource is high. The magnitude of change here is considered intermediate and unmitigated impact significance moderate.

10.6.1.10 Areas of woodland (L8) including groups of trees will also be affected within the alignment. Approximately 12,000m² will be impacted upon. Only fringe areas of woodland are expected to be lost. The sensitivity of this resource is high. The magnitude of change here is considered intermediate and unmitigated impact significance moderate/substantial.

10.6.1.11 There are a total 5,829 trees within the proposed alignment. These include native woodland, orchard and plantation trees. Of these, 1,671 trees are proposed to be retained, 373 transplanted and 3,785 are proposed to be felled. A proposed 6,473 new trees are proposed within the Compensatory and Master Landscape Plan. Most of these will be native woodland species and, whilst many will be planted as early as possible in the construction phase, it is expected most will be planted at the latter stages.

Mud Flats

10.6.1.12 Approximately 7,500 square metres of mudflats (L2) is expected to be affected due to the construction of bridge piers in the inter-tidal zone. The sensitivity of this resource is high. The magnitude of the change here is considered intermediate and unmitigated impact significance moderate/substantial.

Fish Ponds

10.6.1.13 Some impact is expected on active and abandoned fish ponds (L5). Approximately 7,300m² of ponds will be lost. Many have been abandoned or are currently being filled in. The sensitivity of this resource is medium. The magnitude of change here is considered intermediate and unmitigated impact significance moderate.

Stream Channels

10.6.1.14 Approximately 2km of stream channel (L6) is expected to be affected to some extent. The Ngau Hom Shek east stream will be heavily disturbed but there is potential to restore it. This will be undertaken via the wetland compensation scheme proposed under this project. Other streams affected are mostly channelised in some form. The sensitivity of this resource is high. The magnitude of change here is considered intermediate and unmitigated impact significance moderate.

Village / Residential / Warehouse /Factory/ Roads and Similar Developments

10.6.1.15 The buildings and human settlements (L9) along the alignment of the DBL will experience a large magnitude of change. However, due to their low sensitivity to change they will only experience a slight to moderate impact significance before mitigation.

Landscape Character

10.6.1.16 Generally, the unmitigated impact upon the overall landscape character will vary from slight to substantial. Village areas within the alignment, as well as rural and natural areas such as the valley south of Ngau Hom Shek and Tseung Kong Wai, will experience permanent and irreversible substantial impact. Other areas, such as open storage yards and the Lam Tei Quarry will experience negligible to slight impact.

LC1: Agricultural Coastal Lowland
10.6.1.17 The character of the agricultural coastal lowland will be significantly affected. This will primarily be limited to areas immediately adjacent to Ngau Hom Shek. The sensitivity of this resource is medium. The magnitude of change expected is intermediate and the unmitigated impact will be moderate.

LC2: Greenbelt Foothills
10.6.1.18 The character of the greenbelt foothills adjacent to Ngau Hom Shek will be modified by some slope cutting, loss of vegetation and the construction of an incongruous, significantly large, linear structure. This will affect the character of the area. The sensitivity of this resource is high. The magnitude of change expected is small and the unmitigated impact will be slight/moderate.

LC3: Village Coastal Lowland
10.6.1.19 The character of the village coastal lowland to Ngau Hom Shek will be modified by the construction of an incongruous, significantly large, linear structure, temporary works areas, additional construction traffic, storage of construction material and general loss of vegetation. The sensitivity of this resource is medium. The magnitude of change expected is large and the unmitigated impact will be moderate/substantial.

LC4: Sea Edge
10.6.1.20 The Sea Edge will be modified by the construction of an incongruous, significantly large, linear structure, the loss of mangrove and other coastal vegetation, and the disturbance to the mud flats. The sensitivity of this resource is high. The magnitude of change expected is intermediate and the unmitigated large will be moderate/substantial.

LC5: Valley Lowland Agriculture
10.6.1.21 The character of the valley lowland agriculture will be modified by the construction of an incongruous, significantly large, linear structure, temporary works areas, additional construction traffic, storage of construction material and general loss of vegetation. The sensitivity of this resource is medium. The magnitude of change expected is small and the unmitigated impact will be slight/moderate.

LC6: Valley Lowland Mosaic
10.6.1.22 The character of the valley lowland mosaic will be modified by the construction of an incongruous, significantly large, linear structure, temporary works areas, additional construction traffic, storage of construction material and some loss of vegetation and small scale structures. Much of the area which will be affected includes open storage areas and light industrial areas. The sensitivity of this resource is low. The magnitude of change expected is small and the unmitigated impact will be negligible/slight.

LC7: Lam Tei
10.6.1.23 The character of the Lam Tei area will be significantly modified by the construction of an incongruous, significantly large, linear structure, temporary works areas, additional construction traffic, storage of construction material and some loss of vegetation and small scale structures. The sensitivity of this resource is medium. The magnitude of change expected is intermediate and the unmitigated impact will be moderate.

LC8: Greenbelt / Country Park Uplands
10.6.1.24 The character of the uplands area will not be directly affected by the construction of the DBL. The sensitivity of this resource is high. The visual affect of the DBL upon these areas is expected to be negligible.

Cumulative Impacts

10.6.1.25 Impacts associated with related developments are described below.


10.6.1.26 Overall, the unmitigated magnitude of change during construction will, collectively, be intermediate.

10.6.2 Nature & Magnitude of Visual Impacts in Construction Phase

Residential

10.6.2.1 Residents in the coastal Protection area and Agricultural area at Ngau Hom Shek (VSR1) will have direct, short range views to the construction works which is immediately adjacent or very close to several receivers. There is expected to be a large magnitude of change.

10.6.2.2 Residents in existing villages and CDA east of HSK NDA (VSR3) will have intermittent, distant views to the DBL which will mostly be screened by the containers within the open storage areas. Magnitude of change is expected to be small.

10.6.2.3 Residents in the proposed residential and community facilties and within the proposed village type development at HSK NDA (VSR5 & 6) will not be subjected to the construction works due to the fact that the DBL road will be completed prior to these facilities being completed for occupancy.

10.6.2.4 Residents in village type development at Fui Sha Wai (VSR9) will have intermittent, very distant views to the DBL which will mostly be screened by the containers within the open storage areas and other structures. Magnitude of change is expected to be negligible.

10.6.2.5 Residents in the residential development east of San Hing Tsuen and undetermined area northwest of San Hing Tsuen (VSR11) will have direct, close views to the DBL which will be elevated adjacent to this receiver. Magnitude of change is expected to be intermediate.

10.6.2.6 Residents in the developments and CDA area east of Lam Tei Tsuen (VSR12) will have direct, very close views to the DBL and Lam Tei interchange which will be elevated adjacent to this receiver. Magnitude of change is expected to be Large.

10.6.2.7 Residents in high rise residential development at Tin Shui Wai (VSR16) will have intermittent, very distant views to the DBL. Magnitude of change is expected to be Small.

Occupational

10.6.2.8 Workers in proposed other specified land uses at HSK NDA (VSR4) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy.

10.6.2.9 Workers in proposed possible extension to HSK NDA (VSR8) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy.

Recreational

10.6.2.10 Walkers in the greenbelt and conservation area at Ngau Hom Shek and Yuen Tau Shan (VSR2) would have intermittent but close views to the construction works. However, very few people walk in these areas due to the presence of grave sites and its isolated nature and much of the area has already been disturbed to some extent. Magnitude of change is expected to be Small.

10.6.2.11 Walkers in the proposed amenity areas at HSK NDA (VSR7) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy.

10.6.2.12 Walkers in the greenbelt and conservation area south of Yuen Long Highway (VSR10) would have intermittent but close views to the construction works. However, very few people walk in these areas due to the presence of grave sites and its isolated nature and much of the area has already been disturbed to some extent. Magnitude of change is expected to be Small.

10.6.2.13 Walkers in the greenbelt north of Yuen Long Highway (VSR14) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy.

10.6.2.14 Walkers in the greenbelt south of To Yuen Wai (VSR15) would have direct, close views to the construction works. However, very few people walk in this area and the existing Yuen Long Highway means that significant changes are not expected. Magnitude of change is expected to be small.

10.6.2.15 Walkers in Tai Lam Country Park (VSR17) would have intermittent, direct views to the construction works of the DBL and Lam Tei interchange. The distance and topography (in addition to the vegetation) means that views will be rare. They will also look down onto a valley floor that has already been significantly developed. Magnitude of change is expected to be small.

Travellers

10.6.2.16 Travellers on Deep Bay Road (T1) would have intermittent, single vista views to the construction works of the DBL mainline. Views from the road approaching Ngau Hom Shek will more likely be dominated by the SWC. Magnitude of change is expected to be small.

10.6.2.17 Travellers on Yuen Long Highway (T2) would have direct views to the construction works of the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be dramatically interrupted by the construction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent developments. Magnitude of change is expected to be intermediate.

10.6.2.18 Travellers on Castle Peak (T3) would have intermittent views to the construction works of the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be interrupted by the construction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent developments. Magnitude of change is expected to be small.

10.6.2.19 Travellers on the proposed West Rail (T4) would have intermittent views to the construction works of the DBL mainline and Lam Tei interchange. Views from the train approaching Hung Shui Kiu will be interrupted by the construction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. Magnitude of change is expected to be small.

10.6.2.20 Travellers on Deep Bay Link (T5) will not be subject to impacts resulting from construction.

10.6.3 Mitigation Measures in Construction Phase

10.6.3.1 Recommended landscape and visual mitigation measures for impacts caused during the construction process are described in Table 10.4 together with the associated implementation agency.

Programme of Implementation of Mitigation Measures in Construction Phase

10.6.3.2 The measures listed in Table 10.4 should be adopted from the commencement of construction and should be in place throughout the entire construction period. Programme of implementation is provided elsewhere in this report. The proposed landscape and visual mitigation measures in the construction phase are illustrated in Figures 10.6.1 to 10.6.3.

Table 10.4 Proposed Construction Phase Mitigation Measures

ID No.

Mitigation Measure

Apply to Landscape Resource / VSR

Date to be Implemented

Implementation Agency

CM1

Control of night-time lighting

All VSRs

Detailed Design & Construction Period

HyD

CM2

Replanting of disturbed vegetation should be undertaken and this should use predominantly native plant species.

L1, 3, 4, 7 & 8 & All VSRs except VSR4 and 14

Early 2006

HyD

CM3

Screen hoarding, using decorative graphic and chromatic devise should be erected around the works wherever possible to screen works within the road corridor.

VSR1-7, 10-15, 17, T1-4

July 2003

HyD

CM4

Planting should be undertaken at the earliest possible stage during construction, and opportunities should be sought for undertaking any advance planting.

L1, 3, 4, 7 & 8 & All VSRs except VSR4 and 14

Late 2003

HyD

CM5

Excavated topsoil to be conserved for reuse (maximum height of stockpiling is not exceed 2m)

L4 & 5

Late 2003

HyD

CM6

Transplanting mature trees with good amenity value.

L4 & 8, VSR1-7, 10-15, 17, T1-4

July - October 2003

HyD

10.6.4 Prediction of Significance of Landscape Impacts in Construction Phase

10.6.4.1 The potential significance of the landscape impacts during the construction phase, before and after mitigation, were previously explained in 10.6.1 and are summarised below in Table 10.5 and illustrated in Figures 10.6.4 to 10.6.6. This assessment follows the methodology outlined in Section 10.3.2 and assumes that the appropriate mitigation measures identified in Table 10.4 above would be implemented.

Table 10.5 Significance of Landscape Impacts in Construction Phase

Ref

Landscape Resource / Character Area

Sensitivity to Change (Low, Medium, High)

Extent of Loss

 

 

Magnitude of Change before Mitigation (Negligible, Small, Intermediate, Large)

Magnitude of Change After Mitigation (Negligible, Small, Intermediate, Large)

Impact Significance before Mitigation

Measures

(Negligible, Slight, Moderate, Substantial)

Impact Significance after Mitigation Measures (Negligible, Slight, Moderate, Substantial)

Landscape Resource

           

L1

Mangrove Areas located on coastline.

High

2,500m²

Intermediate

 

Intermediate

Moderate / Substantial

Moderate (4)

L2

Mudflat

High

7,500m²

Intermediate

Intermediate

Moderate/ Substantial

Moderate(4)

L3

Marsh & Wet Agriculture

High

5,000m²

Small

 

Small

Slight/Moderate

Slight/Moderate

L4

Agriculture, Orchards & Plantations

High

10,100m²

Intermediate

Intermediate

Moderate/

Substantial

Moderate

L5

Fish Ponds

Medium

7,300m²

Intermediate

Intermediate

Moderate

Moderate

L6

Stream Channels

High

2km in length

Intermediate

Intermediate

Moderate / Substantial

Moderate

L7

Grassland

Medium

101,000m²

Intermediate

Small

Moderate

Slight

L8

Woodland (including tall scrub & significant tree groups)

High

12,000m²

Intermediate

Intermediate

Moderate/ Substantial

Moderate / Substantial(5)

L9

Village / Residential/ Warehouse / Factory / Roads and similar developments.

Low

 

Large

Large

Slight/Moderate

Slight/Moderate(5)

L10

Landform

Medium

38,000m²

Intermediate

 

Intermediate

Moderate

Moderate(5)

Landscape Character Area

           

LC1

Agricultural Coastal Lowland

Medium

 

Intermediate

Intermediate

Moderate

Moderate(4)

LC2

Greenbelt Foothills

High

 

Small

Small

Slight / Moderate

Slight / Moderate(4)

LC3

Village Coastal Lowland

Medium

 

Large

Large

Moderate / Substantial

Moderate / Substantial(4)

LC4

Sea Edge

High

 

Intermediate

Intermediate

Moderate to Substantial

Moderate to Substantial(4)

LC5

Valley Lowland Agriculture

Medium

 

Small

Small

Slight / Moderate

Slight / Moderate

LC6

Valley Lowland Mosaic

Low

 

Small

Small

Negligible / Slight

Negligible / Slight

LC7

Lam Tei

Medium

 

Intermediate

Intermediate

Moderate

Moderate

LC8

Greenbelt / Country Park Uplands

High

 

Negligible

Negligible

Negligible

Negligible

Notes : 

(1) All impacts are negative / adverse unless otherwise stated
(2) Source of landscape impact on all resources / character areas would be construction of bridge & elevated road including piers, columns road platform, earthworks including slope cuts, retaining walls, temporary works areas and associated activities.
(3) Extent of loss is equal to the total area of the landscape resource that would be affected by the temporary and permanent works.
(4) Impact must be considered collectively with the SWC bridge.
(5) Impact must be considered collectively with the proposed widening of Yuen Long Highway and Route 10 scope of works.

10.6.5 Prediction of Significance of Visual Impacts in Construction Phase

10.6.5.1 The potential significance of the residual visual impacts during the construction phase, before and after mitigation, are briefly described below, provided in detail in Table 10.6, and illustrated in Figures 10.6.4 to 10.6.6. This assessment follows the methodology outlined in Section 10.3.2 and assumes that the appropriate mitigation measures identified in Table 10.4 above would be implemented. The effect of the mitigation measures will be to reduce the potential visual impacts in varying degrees.

Residential

10.6.5.2 Residents in the coastal Protection area and Agricultural area at Ngau Hom Shek (VSR1) will have direct, short range views to the construction works which is immediately adjacent or very close to several receivers. The sensitivity of this VSR is high. There is expected to be a intermediate magnitude of change after mitigation with residual impact significance being moderate.

10.6.5.3 Residents in existing villages and CDA east of HSK NDA (VSR3) will have intermittent, distant views to the DBL which will mostly be screened by the containers within the open storage areas. The sensitivity of this VSR is high. There is expected to be a small magnitude of change after mitigation with residual impact significance being slight/moderate.

10.6.5.4 Residents in the residential and community facilities and within the proposed village type development at HSK NDA (VSR5 & 6) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy. The sensitivity of these VSRs is high.

10.6.5.5 Residents in village type development at Fui Sha Wai (VSR9) will have intermittent, very distant views to the DBL which will mostly be screened by the containers within the open storage areas and other structures. The sensitivity of this VSR is high. There is expected to be a negligible magnitude of change after mitigation with residual impact significance being negligible.

10.6.5.6 Residents in the residential development east of San Hing Tsuen and undetermined area northwest of San Hing Tsuen (VSR11) will have direct, close views to the construction of the DBL which will be elevated adjacent to this receiver. The sensitivity of this VSR is high. There is expected to be a intermediate magnitude of change after mitigation with residual impact significance being moderate/substantial.

10.6.5.7 Residents in the developments and CDA area east of Lam Tei Tsuen (VSR12) will have direct, very close views to the DBL and Lam tei interchange which will be elevated adjacent to this receiver. The sensitivity of this VSR is high. There is expected to be a large magnitude of change after mitigation with residual impact significance being substantial.

10.6.5.8 Residents in high rise residential development at Tin Shui Wai (VSR16) will have intermittent, very distant views to the DBL. The sensitivity of this VSR is high. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight.

Occupational

10.6.5.9 Workers in proposed other specified land uses at HSK NDA (VSR4) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy. The sensitivity of this VSR is low.

10.6.5.10 Workers in proposed possible extension to HSK NDA (VSR8) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy. The sensitivity of this VSR is low.

Recreational

10.6.5.11 Walkers in the greenbelt and conservation area at Ngau Hom Shek and Yuen Tau Shan (VSR2) would have intermittent but close views to the construction works. However, very few people walk in these areas due to the presence of grave sites and its isolated nature and much of the area has already been disturbed to some extent. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight. The sensitivity of this VSR is low.

10.6.5.12 Walkers in proposed amenity areas at HSK NDA (VSR7) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy. The sensitivity of this VSR is high.

10.6.5.13 Walkers in the greenbelt and conservation area south of Yuen Long Highway (VSR10) would have intermittent but close views to the construction works. However, very few people walk in these areas due to the presence of grave sites and its isolated nature and much of the area has already been disturbed to some extent. The sensitivity of this VSR is low. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight.

10.6.5.14 Walkers in the greenbelt north of Yuen Long Highway (VSR14) will not be subjected to the construction works due to the fact that the DBL road will be complete prior to these facilities being completed for occupancy. The sensitivity of this VSR is low.

10.6.5.15 Walkers in the greenbelt south of To Yuen Wai (VSR15) would have direct, close views to the construction works. However, very few people walk in this area and the existing Yuen Long Highway means that significant changes are not expected. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight. The sensitivity of this VSR is low.

10.6.5.16 Walkers in Tai Lam Country Park (VSR17) would have intermittent, direct views to the construction works of the DBL and Lam Tei interchange. The distance and topography (in addition to the vegetation) means that views will be rare. They will also look down onto a valley floor that has already been significantly developed. There is expected to be a small magnitude of change after mitigation with residual impact significance being slight/moderate. The sensitivity of this VSR is high.

Travellers

10.6.5.17 Travellers on Deep Bay Road (T1) would have intermittent, single vista views to the construction works of the DBL mainline. Views from the road approaching Ngau Hom Shek will more likely be dominated by the SWC. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight. The sensitivity of this VSR is low.

10.6.5.18 Travellers on Yuen Long Highway (T2) would have direct views to the construction works of the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be dramatically interrupted by the construction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. There is expected to be a intermediate magnitude of change after mitigation with residual impact significance being slight/moderate. The sensitivity of this VSR is low.

10.6.5.19 Travellers on Castle Peak (T3) would have intermittent views to the construction works of the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be interrupted by the construction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight. The sensitivity of this VSR is low.

10.6.5.20 Travellers on the proposed West Rail (T4) would have intermittent views to the construction works of the DBL mainline and Lam Tei interchange. Views from the train approaching Hung Shui Kiu will be interrupted by the construction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight. The sensitivity of this VSR is low.

10.6.5.21 Travellers on Deep Bay Link (T5) will not be subject to impacts resulting from construction.

10.6.5.22 The assessment of visual impacts during Construction Phase on VSR's within the HSK NDA are subject to the programming of construction works of the HSK NDA developments. Currently, Road P1 and adjacent areas of HSK NDA are scheduled not commence before 2006. The proposed completion date for DBL is mid 2006. Therefore, depending upon phasing and programming of development in the HSK NDA, construction impacts to these VSRs may be irrelevant.

10.6.6 Cumulative Construction Impacts

10.6.6.1 Cumulative construction impacts are expected as a result of construction of the SWC at Ngau Hom Shek where the works identified under the DBL in this EIA study up to a point 350m inland from the coastline will be entrusted to the SWC. Construction of the elevated decks and bridge structures in Deep Bay under the SWC will also result in significant visual impact upon residents at Ngau Hom Shek (VSR1). Small impacts are expected upon the residents at Tin Shui Wai (VSR16). In addition, walkers in the greenbelt and conservation area at Ngau Hom Shek will also be affected.

10.6.6.2 Cumulative construction impacts are also expected as a result of the widening of Yuen Long Highway. These work at Lam Tei interchange are entrusted to the DBL. These will affect residents at San Hing Tsuen (VSR11) and at Lam Tei (VSR12) as well as surrounding recreational receivers.

Table 10.6 Significance of Visual Impacts During Construction Phase (Note: All impacts adverse unless otherwise noted)

Type and Identity No. of VSR

Key Visually Sensitive Receiver (VSR)

Source(s) of Impacts

Minimum Distance Between VSR and Source(s)

Receptor Sensitivity (Low, Medium, High)

Magnitude of Change before Mitigation Measures (Negligible, Small, Intermediate, Large)

Construction Phase Mitigation Measure

Magnitude of Change after Mitigation Measures (Negligible, Small, Intermediate, Large)

Impact Significance before Mitigation Measures (Negligible, Slight, Moderate, Substantial)

Residual Impact Significance after Mitigation Measures (Negligible, Slight, Moderate, Substantial)

Residential Receivers

               

VSR1

Residents in Coastal Protection Area and Agriculture Area at Ngau Hom Shek

Shenzhen Western Corridor

0m

High

Large

CM 1-4, 6

Intermediate

Substantial

Moderate (4)

VSR3

Residents in Existing Villages and Comprehensive Development Area east of HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, Helicopter Pad and access track, Construction Access Roads, and the Temporary Works Areas.

500m

High

Small

CM 1-4, 6

Small

Slight / Moderate

Slight / Moderate (3,5,6)

VSR5

Residents in Proposed Residential and Community Facilities at HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, Construction Access Roads, and the Temporary Works Areas.

50m

High

N/A

-

N/A

N/A

N/A

VSR6

Residents in Proposed Village Type Development and Community Facilities at HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps.

0m

High

N/A

-

N/A

N/A

N/A

VSR9

Residents in Village Type Development at Fui Sha Wai

Road Mainline, Support Columns, Parapet, On/Off Ramps, Construction Access Roads, and the Temporary Works Areas.

1100m

High

Negligible

-

Negligible

Negligible

Negligible

VSR11

Residents in Residential Development East of San Hing Tsuen and undetermined area Northwest of San Hing Tsuen

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, Temporary Works Areas.

0m

High

Intermediate

CM 1, 3, 4, 6

Intermediate

Moderate / Substantial

Moderate / Substantial

VSR12

Residents in Residential Developments and Comprehensive Development Area East of Lam Tei Tsuen

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, Temporary Works Areas.

0m

High

Large

CM 1, 3, 4, 6

Large

Substantial

Substantial(3,5)

VSR13

Not Used

               

VSR16

Residents in High Rise Residential at Tin Shui Wai at the far north

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange.

1500m

High

Small

-

Small

Negligible / Slight

Negligible / Slight(3)

Recreational Receivers

               

VSR2

Walkers in Green Belt and Conservation Area at Ngau Hom Shek and Yuen Tau Shan.

Road Mainline, Support Columns, Parapet, On/Off Ramps, Helicopter Pad and access track, Construction Access Roads, and the Temporary Works Areas.

0m

Low

Small

CM 1, 3, 4, 6

Small

Negligible / Slight

Negligible / Slight

VSR7

Walkers in Proposed Amenity Areas at HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps.

50m

High

N/A

-

N/A

N/A

N/A

VSR10

Walkers in Green Belt and Conservation Area south of the Yuen Long Highway

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, and Temporary Works Areas.

0m

Low

Small

CM 1, 3, 4, 6

Small

Negligible / Slight

Negligible / Slight (5)

VSR14

Walkers in Green Belt north of Yuen Long Highway

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, Temporary Works Areas.

0m

Low

N/A

-

N/A

N/A

N/A

VSR15

Walkers in Green Belt south of To Yuen Wai

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, Temporary Works Areas.

0m

Low

Small

CM 1, 3, 4, 6

Small

Negligible / Slight

Negligible / Slight

VSR17

Walkers in Tai Lam Country Park

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange.

500m

High

Small

-

Small

Slight / Moderate

Slight / Moderate

Occupational Receivers

               

VSR4

Workers in Proposed Other Specified land uses at HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, Construction Access Roads, and the Temporary Works Areas.

0m

Low

N/A

-

N/A

N/A

N/A

VSR8

Workers in Proposed possible extension to HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, Construction Access Roads, and the Temporary Works Areas.

500m

Low

N/A

-

N/A

N/A

N/A

Travelling Receivers

               

T1

Travellers on Deep Bay Road

Road Mainline, Support Columns and Parapet.

0m

Low

Small

CM 4-3, 6

Small

Negligible / Slight

Negligible / Slight

T2

Travellers on Yuen Long Highway

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange.

0m

Low

Intermediate

CM 43, 6

Intermediate

Slight / Moderate

Slight / Moderate

T3

Travellers on Castle Peak Road

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange.

0m

Low

Small

CM 3, 6

Small

Negligible / Slight

Negligible / Slight

T4

Travellers on Proposed West Rail at Hung Shui Kiu

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange.

0m

Low

Small

CM 43, 6

Small

Negligible / Slight

Negligible / Slight

T5

Travellers on Deep Bay Link Road

Not assessed during construction phase.

   

N/A

 

N/A

N/A

N/A

Notes : 

(1) All impacts are negative / adverse unless otherwise stated
(2) Source of landscape impact on all VSRs would be construction of bridge & elevated road including piers, columns road platform, earthworks, temporary works areas and associated activities.
(3) Impacts must be considered in relation to the current negative visual impact at existing open storage yards.
(4) Impacts must be considered collectively with the SWC works.
(5) Impacts must be considered collectively with Route 10 and Yuen Long Highway widening works.
(6) The assessment of visual impacts during construction phase upon VSR's within the HSK NDA are subject to the programming of construction works of the HSK NDA developments. During construction it is not anticipated that there will be any visual impact upon HSK NDA VSRs'

10.7 Operational Impacts

10.7.0 Potential Sources of Impacts in Operational Phase

10.7.0.1 The sources of impacts of the project at the operational stage are illustrated in Figures 10.6.1 to 10.6.3.7. Additional details are provided in the Master Landscape Plans (Refer Appendix- Master Landscape Plans).

Table 10.7 Summary of Noise Barriers

Location

Noise Barrier Type

Length (Lin.m)

Lam Tei Interchange, mainline of DBL from Lam Tei to HSK Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

6,846m

Lam Tei Interchange and DBL Mainline to HSK Interchange

Vertical barrier (5m)

860

DBL mainline at HSK Interchange, Lam Tei Interchange,

Vertical barrier (3m)

2,161

Near area 2B of HSK NDA.

Semi – enclosure with enclosed side facing HSK NDA

200

10.7.1 Nature and Magnitude of Landscape Impacts in Operation Phase (see Table 10.9)

Landform (L10)

10.7.1.1 Some impacts are expected on the form of the topography within the DBL alignment. These are described below:

10.7.1.2 For a length of approximately 500m, the road is to be constructed in the small valley located just south of Ngau Hom Shek. Some of the road is elevated on columns but there is substantial slope cutting to hillsides, excavation and filling to the valley bottom. It is estimated approximately 28,000 square metres of landscape will be affected. It is considered that that this impact will be permanent and irreversible. Topographic magnitude of change during operation is expected to be intermediate.

10.7.1.3 North of San Wai Sewerage Treatment Plant there are two on/off ramps leading to Ha Tsuen. In addition, an access track to a proposed emergency helicopter pad is also proposed. These facilities will have additional, though intermediate change to the topography of the area. Quantity of the area affected is included in the above figure.

10.7.1.4 There will be some minor embankment, cut and fill slopes created at the edges of the access way to the existing San Wai Sewerage Chamber which is to remain after construction. The magnitude of change is expected to be small.

10.7.1.5 Along the length of the road from San Wai Sewerage Treatment Plant to San Sang San Tsuen there are minor cut and fill slope works associated with the road (say 10,000 square metres). The sensitivity of this resource is medium. The magnitude of change in the topography is expected to be negligible to small. Impact significance after mitigation will be slight / moderate.


Vegetation

10.7.1.6 There is expected to be some minor impact upon the mangrove areas located on the coastline of Ngau Hom Shek (L1). This will be due to the construction of the SWC. The impact is expected to be moderate and temporary. An area of approximately 2,500 square metres could be affected. The sensitivity of this resource is high. The magnitude of change here is considered intermediate and unmitigated impact significance moderate/substantial. Mitigation after construction will include re-planting of mangroves. The condition will improve as they establish. Mitigated significance is considered moderate/substantial.

10.7.1.7 Within the DBL alignment, permanent and irreversible impact to the marsh & wet agriculture (L3) within the study area. Approximately 5,000m² of marsh and wet agriculture areas will be permanently lost. Marsh associated with the Ngau Hom Shek east stream is expected to be affected. The sensitivity of this resource is high. However, the marsh can be re-created and a wetland compensatory scheme is expected to be included within this project (refer to ecological impact report) The recreated marsh is expected to be located adjacent to the DBL alignment at Ngau Hom Shek after construction. Magnitude of change is expected to be small and unmitigated impact significance slight/moderate.

10.7.1.8 Permanent and irreversible impact is expected to some agriculture, orchards and plantation areas (L4). Approximately 59,000m² of agriculture, 10,000m² of orchards and 32,000m² of plantation area is expected to be lost. Totalling 101,000m² The sensitivity of this resource is high. The magnitude of the change here is considered intermediate and the unmitigated impact significance slight/moderate. Mitigation measures will include substantial compensatory planting (refer to Master Landscape Plans).

10.7.1.9 Approximately 10,100m² of grassland and low scrub (L7) is expected to be impacted upon. Some impacts are expected on the form of the topography and grassland on the ridge east of the interface with the DBL alignment. The sensitivity of this resource is medium. In this area, the road will be cut into a ridge adjacent Ngau Hom Shek. Similar cutting will be expected at the head of this valley near Ha Tsuen. The rest of grassland/scrub affected occurs at the lower slopes. Much of the grassland located at these is highly disturbed and of generally a poor quality. It is considered the interesting topography combined with the grassland is of a greater landscape value. The magnitude of change here is considered intermediate and unmitigated impact significance moderate. Mitigation measures will include bio-engineering and hydroseeding of slopes and replanting of grassland/scrub/trees within affected areas.

10.7.1.10 Areas of woodland (L8) including groups of trees will also be affected within the alignment. Approximately 12,000m² will be impacted upon. Only fringe areas of woodland are expected to be lost. The sensitivity of this resource is high. The magnitude of change here is considered intermediate and the unmitigated impact significance moderate/substantial. Mitigation will include transplanting of existing mature tree stock and the provision of new woodland planting and amenity trees.

10.7.1.11 There are a total 5,829 trees within the proposed alignment. These include native woodland, orchard and plantation trees. Of these, 1,671 trees are proposed to be retained, 373 transplanted and 3,785 are proposed to be felled. A proposed 6,473 new trees are proposed within the Compensatory and Master Landscape Plan. Most of these will be native woodland species.


Mud Flats

10.7.1.12 Approximately 7,500 square metres of mudflats (L2) is expected to be affected due to the construction of bridge piers in the inter-tidal zone. The sensitivity of this resource is high. The magnitude of the change here is considered intermediate and unmitigated impact significance moderate/substantial. Mitigation will include re-contouring of mudflats after construction.

Fish Ponds

10.7.1.13 Some impact is expected on active and abandoned fish ponds (L5). Approximately 7,300 square metres of ponds will be lost. Many have been abandoned or are currently being filled in. The sensitivity of this resource is medium. The magnitude of change here is considered intermediate and the unmitigated impact significance moderate.

Stream Channels


10.7.1.14 Approximately 2km of stream channel (L6) is expected to be affected to some extent. The Ngau Hom Shek east stream will be heavily disturbed but there is potential to restore it. This will be undertaken via the wetland compensation scheme proposed under this project. Other streams affected are mostly channelised in some form. The sensitivity of this resource is high. The magnitude of change here is considered intermediate and the unmitigated impact significance moderate/substantial. Mitigation will include re-chanelling affected streams. Mitigated impact signicance is considered moderate/substantial.

Village / Residential / Warehouse /Factory/ Roads and Similar Developments

10.7.1.15 The buildings and human settlements (L9) along the alignment of the DBL will experience an intermediate magnitude of change during the operational phase. However, due to their low sensitivity to change they will only experience a slight to moderate impact significance after mitigation.

Landscape Character

10.7.1.16 Generally, the unmitigated impact upon the overall landscape character will vary from slight to substantial. (See 10.7.0.1 for Potential Sources of Impact). Village areas within the alignment, as well as rural and natural areas such as the valley south of Ngau Hom Shek and Tseung Kong Wai, will experience permanent and irreversible substantial impact. Other areas, such as open storage yards and the Lam Tei Quarry will experience negligible to slight impact.

LC1: Agricultural Coastal Lowland
10.7.1.17 The agricultural coastal lowland will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, access paths and night lighting will affect this area. The sensitivity of this resource is medium. The magnitude of change is expected to be intermediate and unmitigated impact moderate.

LC2: Greenbelt Foothills
10.7.1.18 The greenbelt foothills will experience changes to its character from the introduction of a large, elevated linear element into the landscape, slope cutting and some land formation. Columns, road deck, access paths, slope cuts, culverting and night lighting will affect this area. The sensitivity of this resource is high. The magnitude of change is expected to be small and unmitigated impact slight/moderate.

LC3: Village Coastal Lowland
10.7.1.19 The Village Coastal Lowland will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, access paths and night lighting will affect this area. The sensitivity of this resource is medium. The magnitude of change is expected to be large and unmitigated impact moderate/substantial.

LC4: Sea Edge
10.7.1.20 The Sea Edge will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Much of the impact will be from the SWC. Columns, road deck, access paths and night lighting will affect this area. The sensitivity of this resource is high. The magnitude of change is expected to be large and unmitigated impact moderate/substantial.

LC5: Valley Lowland Agriculture
10.7.1.21 The Valley Lowland Agricultural areas will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, ramps at HSK and Lam Tei interchanges, noise barriers, access paths, maintenance areas, slope cutting, reduction in vegetation, the introduction of a helipad and night lighting will affect these areas. This will be seen in conjuction with existing development such as open storage areas, light industry and other infrastructure (Yuen Long Highway, West rail, Castle Peak Road, etc). The sensitivity of this resource is medium. The magnitude of change is expected to be small and the unmitigated impact slight/moderate.

LC6: Valley Lowland Mosaic
10.7.1.22 The Valley Lowland Mosaic areas will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, ramps at HSK and Lam tei interchanges, noise barriers, access paths, maintenance areas, slope cutting, reduction in vegetation, the introduction of a helipad and night lighting will affect these areas. This will be seen in conjuction with existing development such as open storage areas, light industry and other infrastructure (Yuen Long Highway, West rail, Castle Peak Road, etc). The sensitivity of this resource is low. The magnitude of change is expected to be small and the unmitigated impact negligible/slight.

LC7: Lam Tei
10.7.1.23 The Lam Tei area will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, ramps at Lam Tei interchange, noise barriers, access paths, maintenance areas, slope cutting and night lighting will affect these areas. The road will be elevated up to a maximum of 28 metres off the ground with some noise barriers of a height of 5.5m with cantilever 2.5m. This will be seen in conjuction with existing development such as open storage areas, light industry and other infrastructure (Yuen Long Highway, West Rail, Castle Peak Road, etc). The sensitivity of this resource is medium. The magnitude of change is expected to be intermediate and the unmitigated impact moderate.

LC8: Greenbelt / Country Park Uplands
10.7.1.24 The Greenbelt and Country Park Uplands will experience minimal changes to their character from the introduction of a large, elevated linear element into the adjacent landscape. Columns, road deck, ramps at Lam Tei interchange, noise barriers, access paths, maintenance areas, slope cutting and night lighting may affect these areas. This will be seen in against a background of existing development such as open storage areas, light industry and other infrastructure (Yuen Long Highway, West Rail, Castle Peak Road, etc) and residential. The sensitivity of this resource is high. The magnitude of change is expected to be negligible and the unmitigated impact negligible.

Cumulative Impacts

10.7.1.25 Impacts associated with related developments are described below.


10.7.2 Nature and Magnitude of Visual Impacts in Operation Phase

Residential

10.7.2.1 Residents in the Coastal Protection Area and Agricultural area at Ngau Hom Shek (VSR1) will have direct, short range views to the DBL road which is immediately adjacent or very close to several receivers. The sensitivity of this VSR is high. There is expected to be a large magnitude of change.

10.7.2.2 Residents in existing villages and CDA east of HSK NDA (VSR3) will have intermittent, distant views to the DBL which will mostly be screened by the containers within the open storage areas. The sensitivity of this VSR is high. The magnitude of change is expected to be small.

10.7.2.3 Residents in the proposed residential and community facilities and within the village type development at HSK NDA (VSR5 & 6) will have close, direct views of the DBL mainline, HSK and Lam Tei Interchanges. The magnitude of change is expected to be large. The sensitivity of these VSRs is high.

10.7.2.4 Residents in village type development at Fui Sha Wai (VSR9) will have intermittent, very distant views to the DBL which will mostly be screened by the containers within the open storage areas and other structures. The magnitude of change is expected to be negligible. The sensitivity of this VSR is high.

10.7.2.5 Residents in the residential development east of San Hing Tsuen and undetermined area northwest of San Hing Tsuen (VSR11) will have direct, close views to the DBL which will be elevated adjacent to this receiver. Impacts will be the elevated mainline and ramps, columns, noise barriers, night lighting, etc. Magnitude of change is expected to be intermediate. The sensitivity of this VSR is high.

10.7.2.6 Residents in the developments and CDA area east of Lam Tei Tsuen (VSR12) will have direct, very close views to the DBL and Lam Tei interchange which will be elevated adjacent to this receiver. Impacts will be the elevated mainline and ramps, columns, noise barriers, night lighting, etc. Magnitude of change is expected to be large. The sensitivity of this VSR is high.

10.7.2.7 Residents in high rise residential development at Tin Shui Wai (VSR16) will have intermittent, very distant views to the DBL. Magnitude of change is expected to be Small. The sensitivity of this VSR is high.

Occupational

10.7.2.8 Workers in proposed other specified land uses at HSK NDA (VSR4) will have close, direct views of the DBL mainline, helipad, maintenance areas and night lighting. Magnitude of change is expected to be intermediate. The sensitivity of this VSR is low.

10.7.2.9 Workers in proposed possible extension to HSK NDA (VSR8) will have distant, intermittent views of the DBL mainline and night lighting. The magnitude of change is expected to be small. The sensitivity of this VSR is low.

Recreational

10.7.2.10 Walkers in the greenbelt and conservation area at Ngau Hom Shek and Yuen Tau Shan (VSR2) would have intermittent but close views to the DBL mainline. However, very few people walk in these areas due to the presence of grave sites and its isolated nature and much of the area has already been disturbed to some extent. The magnitude of change is expected to be small. The sensitivity of this VSR is low.

10.7.2.11 Walkers in proposed amenity areas at HSK NDA (VSR7) will be significantly affected by the DBL mainline and HSK interchange. Associated noise barriers and semi-enclosure will have a significant affect on the users of this space. The magnitude of change is expected to be large. The sensitivity of this VSR is high.

10.7.2.12 Walkers in the greenbelt and conservation area south of Yuen Long Highway (VSR10) would have intermittent but close views to the construction works. However, very few people walk in these areas due to the presence of grave sites and its isolated nature and much of the area has already been disturbed to some extent (Quarry and similar land uses). The magnitude of change is expected to be small. The sensitivity of this VSR is low.

10.7.2.13 Walkers in the greenbelt north of Yuen Long Highway (VSR14) will be significantly affected by the DBL mainline and Lam Tei Interchange. Associated noise barriers and other structures will have a significant affect on the users of this space. The magnitude of change is expected to be large. The sensitivity of this VSR is low.

10.7.2.14 Walkers in the greenbelt south of To Yuen Wai (VSR15) would have direct, close views to the Lam tei interchange and the widening of Yuen Long Highway. However, very few people walk in this area and the existing Yuen Long Highway means that significant changes are not expected. Magnitude of change is expected to be small. The sensitivity of this VSR is low.

10.7.2.15 Walkers in Tai Lam Country Park (VSR17) would have intermittent, direct views to the DBL and Lam Tei interchange. The distance and topography (in addition to the vegetation) means that views will be rare. They will also look down onto a valley floor that has already been significantly developed. Magnitude of change is expected to be small. The sensitivity of this VSR is high.

Travellers

10.7.2.16 Travellers on Deep Bay Road (T1) would have intermittent, single vista views to the DBL mainline. Views from the road approaching Ngau Hom Shek will more likely be dominated by the SWC. The magnitude of change is expected to be small. The sensitivity of this VSR is low.

10.7.2.17 Travellers on Yuen Long Highway (T2) would have direct views to the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be dramatically interrupted by the introduction of ramps, elevated road decks, noise barriers and other structures, and night lighting. Views will be seen against a backdrop of adjacent development. The magnitude of change is expected to be intermediate. The sensitivity of this VSR is low.

10.7.2.18 Travellers on Castle Peak (T3) would have intermittent views to the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be interrupted by the introduction of ramps, elevated road decks, noise barriers and other structures, and night lighting. Views will be seen against a backdrop of adjacent development. The magnitude of change is expected to be small. The sensitivity of this VSR is low.

10.7.2.19 Travellers on the proposed West Rail (T4) would have intermittent views to the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be interrupted by the introduction of ramps, elevated road decks, noise barriers and other structures, and night lighting. Views will be seen against a backdrop of adjacent development. The magnitude of change is expected to be small. The sensitivity of this VSR is low.

10.7.2.20 Travellers on Deep Bay Link (T5) will have views of the new road, noise barriers from HSK to Lam Tei interchange, a semi-enclosure at HSK near HSK interchange and other structures and night lighting. Positive views over the valley and to Tin Shui Wai and Tai Lam Country Park will be provided to travellers on the road between Ngau Hom Shek and HSK interchange. Negative views will result from the noise barriers. The magnitude of change is expected to be intermediate. The sensitivity of this VSR is low.

10.7.3 Mitigation Measures During the Operation Phase

10.7.3.1 Recommended landscape and visual mitigation measures for impacts caused during the operation phase are described in Table 10.8 below and illustrated in Figures 10.7.1 to 10.7.6. Additional details are provided in the Master Landscape Plans(Appendix). Road sections are provided in Figures 10.8.1 to 10.8.2 to further illustrate mitigation measures. Associated implementation, management and maintenance agencies are identified if applicable.

Table 10.8 Proposed Operation Phase Mitigation Measures

ID No.

Mitigation Measure

Apply to Landscape Resource / VSR

Implementation Agency

Date to be Implemented

Management Agency

In accordance with Works Branch Technical Circular No. 14/2002 where applicable.

Maintenance Agency

In accordance with Works Branch Technical Circular No. 14/2002 where applicable.

OM1

Tree and shrub planting should be implemented at the road leading from the SWC to reduce the visual impact to the Deep Bay Road users

L4, 7, 8, 9 & VSR 1 & 2.

HyD

Early 2006

 

HyD

LCSD

OM2

Climbing plants should be used to soften the appearance of viaduct columns

VSR1-7, 10-15, T1-4

HyD

Early 2006

HyD

LCSD"

OM3

Woodland tree and shrub planting should be undertaken at the cut slope so as to compensate for vegetation lost during construction. Any affected slope areas should be hydroseeded and planted with woodland species, avoid shotcreting.

L4, 7 & 8, VSR2-7, T5

HyD

Early 2006

HyD

LCSD

OM4

Native shrub planting should be undertaken to screen the proposed works and blend it into the landscape.

L4, 7 & 8, All VSRs

HyD

Early 2006

HyD

LCSD

OM5

A wide buffer planting zone comprising berm and tree planting should be provided to screen the proposed works from the future residents at HSK NDA

L4, 7-9, VSR 3-8.

HyD

Early 2006

HyD

LCSD

OM6

Planting should be implemented at the interchanges to reduce the visual impact to the future residents at the adjacent HSK NDA

VSR 3-8.

HyD

Early 2006

HyD

LCSD

OM7

Planting should be specified to be undertaken at the earliest practical time in the construction period (entire site)

L4, 7 & 8, All VSRs

HyD

During Construction Period

HyD

LCSD

OM8

Size and extent of noise barriers should be reduced as much as possible. Where noise barriers are unavoidable, sensitive architectural styling and chromatic treatment of the noise barriers is important in minimizing their visual impact on motorist and in elevated views from surrounding residential receivers. The advice from ACABAS should be fully incorporated.

All VSRs

HyD

Detailed Design Phase

HyD

HyD

OM9

Planting should be incorporated where possible to screen the road in low level views from adjacent areas, and to tone down the extent of hard paving and reduce the amount of glare, especially in elevated views from the high rise tower blocks

All VSRs

HyD

Early 2006

HyD

LCSD

OM10

Not used

         

OM11

More ornamental tree and shrub planting should be undertaken at interchanges, to create a more colourful and decorative environment

L4,8,& 9, VSRs 5,6,7,12,13,T5

HyD

Early 2006

HyD

LCSD

OM12

Sensitive architectural design of engineering and other built structures, including form and finishes, this will include but not limited to: barriers, paved surfaces, retaining walls, walls, columns, buildings, surface drainage elements on slope, and other structures, light standards, etc. The advice from ACABAS should be fully incorporated.

All VSRs.

HyD

Detailed Design Phase

HyD

HyD

OM13

Lighting of road should be designed to minimise glare to all receivers.

All VSRs

HyD

Detailed Design Phase

HyD

HyD

OM14

Transplanting of Mature Tree stock

L4, 8 All VSRs

HyD

July - October 2003

HyD

LCSD

* These mitigation measures are detailed in the ecological mitigation section of the report. They are included here to indicate that these measures, although primarily ecological, will benefit the landscape resources and character areas.

Planting Proposals

10.7.3.2 Planting proposals are shown on the Landscape Mitigation Measures Plans, Figures 10.7.1 - 10.7.6 The master landscape plan proposals are included in Appendix I. The planting has three objectives :

10.7.3.3 All land disturbed during the course of the works, that will not subsequently be occupied by the permanent works, will be planted with either native woodland or shrub species. As a general approach, where these areas lie within or alongside areas of existing woodland then woodland species will be planted. In areas bordered by tall and low shrub, then appropriate shrub species will be established.

10.7.3.4 The limit of disturbance has to be contained as far as is practical to the alignment of the new road. This results in only a very limited amount of space for re-planting.

10.7.3.5 Infill planting is proposed in several areas alongside the new or existing road corridors, and at the interchanges.

Architectural Treatment of Structures

Cut Slopes

10.7.3.6 Cut slopes are proposed in the area to the ridgeline to the south of Ngau Hom Shek and to the hillsides to the north of the San Wai Sewerage Treatment plan. Additional cut slopes are proposed at San Sang San Tsuen. In total approximately 18,000m² of land area will be affected by cut slopes. The most significant of these slopes is in the area north of San Wei Sewerage Treatment Plant. The slopes on the east side of the road is expected to be 29m high and approximately 80m long.

10.7.3.7 The steepness of slopes normally poses a constraint on the species that can be planted. In this case, all slopes will generally be less than 45 degrees. This will allow planting of shrubs and trees in addition to hydroseeding. Soil cut slopes will also be less than 45 degrees and would be suitable for the establishment of woody vegetation in addition to hydro-mulching with grass, climbers and groundcover species.

10.7.3.8 Some minor retaining walls will be constructed on the west side of the road near Ha Tsuen. These are constructed to reduce the imprint of the road and the need for excessive slope cutting. They are expected to be less than 3m in height. Slightly higher walls (to 4 or 5m) are expected in the small valley north of Ha Tsuen at the proposed maintenance area. These are located at the head of the valley and are not expected to have any significant visual impact.

10.7.3.9 Where possible, low retaining walls adjacent to the road should be designed to be seen as part of the road structure. Should higher walls be required, additional treatment should be considered including stone finishing and tow planters incorporating tree, shrub and climbing plants.

10.7.3.10 Disturbed areas above and below the walls would be reinstated with native grass, tree and shrub planting, with hanging plants introduced to help add greenery and screen the structures.

Road Structures

10.7.3.11 Columns supporting the road deck should be designed and archtecturally treated to reduce their visual bulk. Rounded forms with simple relief patterns will help disguise the dimensions of these structures. Planting at the base in the form of climbers will also grow to disguise the column. Wherever possible, tree planting is provided as close as possible to the structure to maximise the screening effect.

10.7.3.12 The height of parapet walls and the thickness of the bridge deck should be minimised as much as possible to reduce the visual bulk of the road structure. The design of the decking should ensure that, wherever possible, the underside and columns are in shade for as long as possible during the day.

10.7.3.13 The design approach for the elevated road structure is to keep the elements as simple as possible, using rounded forms for the parapet, the junctions between the soffit faces of the underside of the deck and columns which have been widened out to form leaf piers to give the structure more visual support and to assist in the replacement of bearings.

10.7.3.14 Light poles will be located on the outside edge of the road. The fixings of these shall be incorporated within the parapet wall. The selection of light poles and fitting and their positioning in the road will reflect the architectural design of the road structure.

Noise Barriers

10.7.3.15 Noise barriers are proposed to almost all sections of the road and ramps at the Lam Tei Intersection to San Sang San Tsuen and HSK interchange. There are 3 types of noise barriers proposed (ranging in height from 3m to 5.5m) and a semi-enclosure (approximately 200m in length) is proposed to be located near San Sang San Tsuen at the point where the road is closest to proposed residential development of the HSK NDA. Details of the barriers are included in Section 3 (Noise Impact Assessment) and illustrated in Figures 10.6.3.5 to 10.6.3.7.

10.7.3.16 The barriers would be seen both from the road users and adjacent areas. Given the elevation of the road in the Lam Tei area, their height and form will contribute to the overall appearance of the elevated road structure (columns, road deck, parapet wall and noise barriers).

10.7.3.17 To minimise their visual appearance and to help blend them into the texture of the landscape backdrop, it is proposed that the barriers be constructed of clear vision panels within a square section GMS supporting frame. Vision panels would allow views out from the road and help reduce the visual bulk of the bridge structure from adjacent VSRs. The tinting colour should be chosen to blend into the visual background. Due to the road's elevated nature, much of the background may be open sky and subject to infinite variations dependant on weather conditions. However, the surrounding vegetated hillsides will also form much of the background and a green tint may be appropriate to blend in with these conditions.

10.7.3.18 The GMS frame supporting the vision panels would be painted to blend with the background and the colour tint of the panels. The panels and frame should, as much as possible, appear to be integrated with the parapet wall and the structure of the road decking.

10.7.3.19 Allowance for the measures listed should be made in the detailed design of the improvement works (or any part thereof) and should be fully implemented as part of the construction works so that they are in place at the date of completion. However, it should be noted that the full effect of the soft landscape mitigation measures (woodland tree and shrub planting) would not be appreciated for many years.

10.7.3.20 Advice from the Advisory Committee on the Appearance of Bridges and Associated Structures (ACABAS) has been incorporated into the architectural treatment of retaining walls, road structures, and noise barriers as described in the above paragraphs.

10.7.4 Prediction of Significance of Landscape Impacts in Operation Phase

10.7.4.1 An assessment of the potential significance of the landscape impacts during the operational phase, before and after mitigation is provided in Table 10.9, and illustrated in Figures 10.7.7 to 10.7.9. This follows the methodology outlined in Section 10.3.2 and assumes that the appropriate mitigation measures identified in Table 10.8 above would be implemented, and that the full effect of the soft landscape mitigation measures would be realised after ten years.

Table 10.9 Significance of Landscape Impacts in the Operation Phase

Ref

Landscape Resource / Character Area

Sensitivity to Change (Low, Medium, High)

Extent of Loss

 

 

Magnitude of Change before Mitigation (Negligible, Small, Intermediate, Large)

Magnitude of Change After Mitigation Day 1 (Negligible, Small, Intermediate, Large)

Magnitude of Change After Mitigation Year 10 (Negligible, Small, Intermediate, Large)

Impact Significance before Mitigation

Measures

(Negligible, Slight, Moderate, Substantial)

Impact Significance after Mitigation Measures Day 1 (Negligible, Slight, Moderate, Substantial)

Residual Impact Year 10 (Negligible, Slight, Moderate, Substantial)

Landscape Resource

L1

Mangrove Areas located on coastline.

High

2,500m²

Intermediate

 

Intermediate

Small

Moderate / Substantial

Moderate / Substantial

Slight / Moderate

L2

Mudflat

High

7,500m²

Intermediate

Intermediate

Small

Moderate / Substantial

Moderate / Substantial

Slight / Moderate

L3

Marsh & Wet Agriculture

High

5,000m²

Small

 

Small

Negligible

Slight/Moderate

Slight/Moderate

Negligible

L4

Agriculture, Orchards & Plantations

High

10,100m²

Intermediate

Small

Negligible

Moderate / Substantial

Slight/Moderate

Negligible

L5

Fish Ponds

Medium

7,300m²

Intermediate

Intermediate

Small

Moderate

Moderate

Slight / Moderate

L6

Stream Channels

High

2km in length

Intermediate

Small

Negligible

Moderate/

Substantial

Slight / Moderate

Negligible

L7

Grassland

Medium

10,100m²

Intermediate

Intermediate

Small

Moderate

Moderate

Slight / Moderate

L8

Woodland (including tall scrub & significant tree groups)

High

12,000m²

Intermediate

Intermediate

Small

Moderate/ Substantial

Moderate / Substantial

Slight / Moderate

L9

Village / Residential/ Warehouse / Factory / Roads and similar developments.

Low

Large

Large

Intermediate

Negligible

Slight / Moderate

Slight / Moderate

Slight / Moderate

L10

Landform

Medium

38,000m²

Intermediate

Intermediate

Small

Moderate

Moderate

Slight / Moderate

Landscape Character Area

LC1

Agricultural Coastal Lowland

Medium

Intermediate

Intermediate

Intermediate

Moderate

Moderate

Moderate

LC2

Greenbelt Foothills

High

Small

Small

Negligible

Slight / Moderate

Slight / Moderate

Slight / Moderate

LC3

Village Coastal Lowland

Medium

Large

Large

Intermediate

Moderate / Substantial

Moderate / Substantial

Moderate / Substantial

LC4

Sea Edge

High

Large

Large

Large

Moderate / Substantial

Moderate / Substantial

Moderate / Substantial

LC5

Valley Lowland Agriculture

Medium

Small

Small

Small

Slight / Moderate

Slight / Moderate

Slight / Moderate

LC6

Valley Lowland Mosaic

Low

Small

Small

Negligible

Negligible / Slight

Negligible / Slight

Negligible

LC7

Lam Tei

Medium

Intermediate

Intermediate

Intermediate

Moderate

Moderate

Moderate

LC8

Greenbelt / Country Park Uplands

High

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

Notes : 

(1) All impacts are negative / adverse unless otherwise stated
(2) Source of landscape impact on all resources / character areas would be construction of bridge & elevated road including piers, columns road platform, earthworks including slope cuts, retaining walls, temporary works areas and associated activities.
(3) Extent of loss is equal to the total area of the landscape resource that would be affected by the temporary and permanent works.
(4) Impact must be considered collectively with the SWC bridge.
(5) Impact must be considered collectively with the proposed widening of Yuen Long Highway and Route 10 scope of works.

10.7.5 Prediction of Significance of Visual Impacts in Operation Phase

10.7.5.1 An assessment of the potential significance of the visual impacts during the operational phase, before and after mitigation is briefly described below, provided in detail in Table 10.10, and illustrated in Figures 10.7.7 to 10.7.9. This follows the methodology outlined in Section 10.3.2 and assumes that the appropriate mitigation measures identified in Table 10.8 above would be implemented, and that the full effect of the soft landscape mitigation measures would be realised after ten years. Photomontages of the proposed development before, at day 1 without mitigation, at day 1 with mitigation and 10 years after implementation of mitigation measures are illustrated in Figures 10.7.14 to 10.7.37. Figures 10.7.28 to 10.7.33 are 3D Visual Simulations from hypothetical viewpoints in HSK NDA. Viewpoints were chosen from indicative visual corridors corresponding with the HSK NDA RODP.

Residential

10.7.5.2 Residents in the coastal Protection area and Agricultural area at Ngau Hom Shek (VSR1) will have direct, short range views to the new road which is immediately adjacent or very close to several receivers. There is expected to be a large magnitude of change after mitigation with impact significance at Day 1 being moderate.

10.7.5.3 Residents in existing villages and CDA east of HSK NDA (VSR3) will have intermittent, distant views to the DBL which will mostly be screened by the containers within the open storage areas. There is expected to be a negligible magnitude of change after mitigation with Day 1 impact significance being negligible.

10.7.5.4 Residents in the proposed residential and community facilities and within the proposed village type development at HSK NDA (VSR5) will experience views of the elevated DBL mainline and HSK interchange and associated noise barriers (5.5m with 2.5m extension) and semi-enclosure. There is expected to be a large magnitude of change after mitigation. At Day 1 it is not expected the HSK NDA development will be completed. These receivers will experience impacts which have been mitigated for at least several years.

10.7.5.5 Residents in the proposed residential and community facilties and within the proposed village type development at HSK NDA (VSR6) will experience views of the elevated DBL mainline and Lam Tei interchange and associated noise barriers (up to 5.5m with 2.5m extension). There is expected to be a large magnitude of change after mitigation. At Day 1 it is not expected the HSK NDA development will be completed. These receivers will experience impacts which have been mitigated for at least several years.

10.7.5.6 Residents in village type development at Fui Sha Wai (VSR9) will have intermittent, very distant views to the DBL which will mostly be screened by the containers within the open storage areas and other structures. There is expected to be a negligible magnitude of change after mitigation with impact significance at Day 1 being negligible.

10.7.5.7 Residents in the residential development east of San Hing Tsuen and undetermined area northwest of San Hing Tsuen (VSR11) will have direct, close views to the DBL which will be elevated adjacent to this receiver. Impacts will include the elevated road, columns and noise barriers up to 5.5m with a 2.5m extension. There is expected to be a intermediate magnitude of change after mitigation with impact significance at Day 1 being moderate to substantial.
10.7.5.8 Residents in the developments and CDA area east of Lam Tei Tsuen (VSR12) will have direct, very close views to the DBL and Lam Tei interchange which will be elevated adjacent to this receiver. Impacts will arise from the elevated road, columns, noise up to 5.5m with a 2.5m extension and night lighting. There is expected to be a large magnitude of change after mitigation with Day 1 impact significance being substantial.

10.7.5.9 Residents in high rise residential development at Tin Shui Wai (VSR16) will have intermittent, very distant views to the DBL. There is expected to be a negligible magnitude of change after mitigation with Day 1 impact significance being negligible.

Occupational

10.7.5.10 Workers in proposed other specified land uses at HSK NDA (VSR4) will experience views of the elevated DBL mainline, maintenance area, helipad and access road and night lighting. There is expected to be a intermediate magnitude of change after mitigation. At Day 1 it is not expected the HSK NDA development will be completed. These receivers will experience impacts which have been mitigated for atleast several years.

10.7.5.11 Workers in proposed possible extension to HSK NDA (VSR8) will experience intermittent, distant views of the elevated DBL mainline, maintenance area, helipad and access road and night lighting. There is expected to be a small magnitude of change after mitigation. At Day 1 it is not expected the HSK NDA development will be completed. These receivers will experience impacts which have been mitigated for at least several years.

Recreational

10.7.5.12 Walkers in the greenbelt and conservation area at Ngau Hom Shek and Yuen Tau Shan (VSR2) would have intermittent but close views to the DBL. However, very few people walk inthese areas due to the presence of grave sites and its isolated nature and much of the area has already been disturbed to some extent. There is expected to be small magnitude of change after mitigation with Day 1 impact significance being negligible/slight.

10.7.5.13 Walkers in proposed amenity areas at HSK NDA (VSR7) will experience views of the elevated DBL mainline and HSK interchange and associated noise barriers (5.5m with 2.5m extension) and semi-enclosure. There is expected to be a large magnitude of change after mitigation. At Day 1 it is not expected the HSK NDA development will be completed. These receivers will experience impacts which have been mitigated for at least several years.

10.7.5.14 Walkers in the greenbelt and conservation area south of Yuen Long Highway (VSR10) would have intermittent but close views to the DBL and Lam tei interchange. However, very few people walk in these areas due to its isolated nature and much of the area has already been disturbed to some extent. There is expected to be a small magnitude of change after mitigation with Day 1 impact significance being negligible/slight.

10.7.5.15 Walkers in the greenbelt north of Yuen Long Highway (VSR14) will experience views of the elevated DBL mainline and Lam Tei interchange and associated noise barriers (5.5m with 2.5m extension). There is expected to be a large magnitude of change after mitigation. At Day 1 it is not expected the HSK NDA development will be completed. These receivers will experience impacts which have been mitigated for at least several years.

10.7.5.16 Walkers in the greenbelt south of To Yuen Wai (VSR15) would have direct, close views to the DBL and Yuen Long Highway. However, very few people walk in this area and the existing Yuen Long Highway means that significant changes are not expected. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight.

10.7.5.17 Walkers in Tai Lam Country Park (VSR17) would have intermittent, direct views to the DBL and Lam Tei interchange. The distance and topography (in addition to the vegetation) means that views will be rare. They will also look down onto a valley floor that has already been significantly developed. There is expected to be a small magnitude of change after mitigation with residual impact significance being slight/moderate.

Travellers

10.7.5.18 Travellers on Deep Bay Road (T1) would have intermittent, single vista views to the DBL mainline. Views fromm the road approaching Ngau Hom Shek will more likely be dominated by the SWC. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight.

10.7.5.19 Travellers on Yuen Long Highway (T2) would have direct views to the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be dramatically interrupted by the introduction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. The Yuen Long Highway widening and new noise barriers will add to the visual impact There is expected to be a intermediate magnitude of change after mitigation with residual impact significance being slight/moderate.

10.7.5.20 Travellers on Castle Peak (T3) would have intermittent views to the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be interrupted by the introduction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight.

10.7.5.21 10.8.5.21Travellers on the proposed West Rail (T4) would have intermittent views to the the DBL mainline and Lam Tei interchange. Views from the train approaching Hung Shui Kiu will be interrupted by the introduction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. There is expected to be a small magnitude of change after mitigation with residual impact significance being negligible/slight.

10.7.5.22 Travellers on Deep Bay Link (T5) will have views of the new road, noise barriers from HSK to Lam Tei interchange, a semi-enclosure at HSK near HSK interchange and other structures and night lighting. Positive views over the valley and to Tin Shui Wai and Tai Lam Country Park will be provided to travellers on the road between Ngau Hom Shek and HSK interchange. There is expected to be a intermediate magnitude of change after mitigation with residual impact significance being slight/moderate.

Table 10.10 Significance of Visual Impacts in the Operation Phase (Refer to Table 10.8 for a description of Operation Mitigation Measures)

Type and Identity No. of VSR

Key Visually Sensitive Receiver (VSR)

Source(s) of Impacts

Minimum Distance Between VSR and Source(s)

Receptor Sensitivity (Low, Medium, High)

Magnitude of Change before Mitigation Measures (Negligible, Small, Intermediate, Large)

Magnitude of Change after Mitigation Measures Day 1 (Negligible, Small, Intermediate, Large)

Magnitude of Change after Mitigation Measures Year 10 (Negligible, Small, Intermediate, Large)

Impact Significance Before Mitigation Measures (Negligible, Slight, Moderate, Substantial)

Impact Significance After Mitigation Measures Day 1 (Negligible, Slight, Moderate, Substantial)

Impact Significance Residual Impact Year 10 (Negligible, Slight, Moderate, Substantial)

Residential Receivers

                 

VSR1

Residents in Coastal Protection Area and Agriculture Area at Ngau Hom Shek

Road Mainline, Support Columns, Parapet, and lighting.

0m

High

Large

Large

Large

Substantial

Moderate

Moderate (4)

VSR3

Residents in Existing Villages and Comprehensive Development Area east of HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, Helicopter Pad and access track, lighting and cut slopes.

500m

High

Small

Negligible

Negligible

Slight / Moderate

Negligible

Negligible

VSR5

Residents in Proposed Residential and Community Facilities at HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, noise barriers and semi-enclosure and lighting.

50m

High

Large

Large

Intermediate

N/A

N/A

Moderate / Substantial(3,6)

VSR6

Residents in Proposed Village Type Development and Community Facilities at HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, noise barriers and semi-enclosure and lighting.

0m

High

Large

Large

Large

Substantial

Substantial

Substantial

VSR9

Residents in Village Type Development at Fui Sha Wai

Road Mainline, Support Columns, Parapet, On/Off Ramps, noise barriers and semi-enclosure and lighting.

1100m

High

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

VSR11

Residents in Residential Development East of San Hing Tsuen and undetermined area Northwest of San Hing Tsuen

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, noise barriers and lighting.

0m

High

Intermediate

Intermediate

Intermediate

Moderate / Substantial

Moderate / Substantial

Moderate / Substantial

VSR12

Residents in Residential Developments and Comprehensive Development Area East of Lam Tei Tsuen

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, noise barriers and lighting.

0m

High

Large

Large

Large

Substantial

Substantial

Substantial(3,5)

VSR13

Not Used

                 

VSR16

Residents in High Rise Residential at Tin Shui Wai at the far north

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, noise barriers and lighting.

1500m

High

Small

Negligible

Negligible

Slight / Moderate

Negligible

Negligible

Recreational Receivers

                 

VSR2

Walkers in Green Belt and Conservation Area at Ngau Hom Shek and Yuen Tau Shan.

Road Mainline, Support Columns, Parapet, On/Off Ramps, Helicopter Pad and access track, and lighting.

0m

Low

Small

Small

Small

Negligible / Slight

Negligible / Slight

Negligible / Slight

VSR7

Walkers in Proposed Amenity Areas at HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, noise barriers and semi-enclosure and lighting.

50m

High

Large

Large

Intermediate

N/A

N/A

Moderate / Substantial (5,6)

VSR10

Walkers in Green Belt and Conservation Area south of the Yuen Long Highway

Road Mainline, Support Columns, Parapet, On/Off Ramps, noise barriers and lighting.

0m

Low

Small

Small

Small

Negligible / Slight

Negligible / Slight

Negligible / Slight (5)

VSR14

Walkers in Green Belt north of Yuen Long Highway

Road Mainline, Support Columns, Parapet, On/Off Ramps, noise barriers and lighting.

0m

Low

Large

Large

Intermediate

N/A

N/A

Slight / Moderate

VSR15

Walkers in Green Belt south of To Yuen Wai

Road Mainline, Support Columns, Parapet, On/Off Ramps, noise barriers and lighting.

0m

Low

Small

Small

Small

Negligible / Slight

Negligible / Slight

Negligible / Slight

VSR17

Walkers in Tai Lam Country Park

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, noise barriers and lighting.

500m

High

Small

Small

Small

Slight / Moderate

Slight / Moderate

Slight / Moderate

Occupational Receivers

                 

VSR4

Workers in Proposed Other Specified land uses at HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps, and lighting.

0m

Low

Intermediate

Intermediate

Small

N/A

N/A

Negligible / Slight

VSR8

Workers in Proposed possible extension to HSK NDA

Road Mainline, Support Columns, Parapet, On/Off Ramps and lighting.

500m

Low

Small

Small

Negligible

N/A

N/A

Negligible (6)

Travelling Receivers

                 

T1

Travellers on Deep Bay Road

Road Mainline, Support Columns, Parapet and lighting.

0m

Low

Small

Small

Small

Negligible / Slight

Negligible / Slight

Negligible / Slight

T2

Travellers on Yuen Long Highway

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, noise barriers and lighting.

0m

Low

Intermediate

Intermediate

Small

Slight / Moderate

Slight / Moderate

Negligible / Slight

T3

Travellers on Castle Peak Road

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, noise barriers and lighting.

0m

Low

Small

Small

Small

Negligible / Slight

Negligible / Slight

Negligible / Slight

T4

Travellers on Proposed West Rail at Hung Shui Kiu

Road Mainline, Support Columns, Parapet, On/Off Ramps, Lam Tei Interchange, noise barriers and lighting.

0m

Low

Small

Small

Negligible

Negligible / Slight

Negligible / Slight

Negligible

T5

Travellers on Users of Deep Bay Link Road

Parapet, noise barriers and lighting.

0m

Low

Intermediate

Intermediate

Small

Slight / Moderate

Slight / Moderate

Negligible / Slight

Notes : 

(1) All impacts are negative / adverse unless otherwise stated
(2) Source of landscape impact on all VSRs would be construction of bridge & elevated road including piers, columns road platform, earthworks, temporary works areas and associated activities.
(3) Impacts must be considered in relation to the current negative visual impact at existing open storage yards.
(4) Impacts must be considered collectively with the SWC works.
(5) Impacts must be considered collectively with Route 10 and Yuen Long Highway widening works.
(6) The assessment of visual impacts during construction phase upon VSRs within the HSK NDA is subject to the programming of construction works of the HSK NDA

10.8 Evaluation of Residual Impacts

10.8.0 Evaluation of Residual Landscape Impacts

Landform (L10)

10.8.0.1 With a total loss of approximately 38,000m² of landform, the use of careful grading and slope treatment techniques, the residual impact after 10 years is expected to be slight/moderate.

Vegetation

10.8.0.2 There is expected to be some minor impact upon the mangrove areas located on the coastline of Ngau Hom Shek (L1). This will be due to the construction of the SWC. The impact is expected to be moderate and temporary. An area of approximately 2,500 square metres could be affected. The loss will be compensated by new planting under the ecological mitigation measures. Residual impact is expected to be slight/moderate.

10.8.0.3 Within the DBL alignment, permanent and irreversible impact to the marsh & wet agriculture (L3) within the study area. Approximately 5,000m² of marsh and wet agriculture areas will be permanently lost. The marsh will be re-created and a wetland compensatory scheme is expected to be included within this project (refer to ecological impact report) The recreated marsh is expected to be located adjacent to the DBL alignment at Ngau Hom Shek after construction. Residual landscape impact is expected to be negligible.

10.8.0.4 Permanent and irreversible impact is expected to some agriculture, orchards and plantation areas (L4). Approximately 59,000m² of agriculture, 10,000m² of orchards and 32,000m² of plantation area is expected to be lost. Totalling 101,000m². New woodland planting will account for some of the loss but it is not proposed to recreate orchards or agriculture. Much of the fields are abandoned and residual impact is expected to be negligible.

10.8.0.5 Approximately 10,100m² of grassland and low scrub (L7) is expected to be impacted upon. Some impacts are expected on the form of the topography and grassland on the ridge east of the interface with the DBL alignment. In this area, the road will be cut into a ridge adjacent Ngau Hom Shek. Similar cutting will be expected at the head of this valley near Ha Tsuen. The rest of grassland/scrub affected occurs at the lower slopes. Much of the grassland located at these is highly disturbed and of generally a poor quality. Proposed woodland and shrub/grass planting is proposed to compensate for these areas. This planting should be well established after 10 years. Residual impact is expected to be slight/moderate.

10.8.0.6 Areas of woodland (L8) including groups of trees will also be affected within the alignment. Approximately 12,000m² will be impacted upon. Only fringe areas of woodland are expected to be lost. loss of trees will be compensated in the form of woodland and individual tree planting (especially along the edges of the road and track). This should be well established after 10 Years. Residual impact is expected to be slight/moderate.

10.8.0.7 There are a total 5,829 trees within the proposed alignment. These include native woodland, orchard and plantation trees. Of these, 1,671 trees are proposed to be retained, 373 transplanted and 3,785 are proposed to be felled. A proposed 6,473 new trees are proposed within the Compensatory and Master Landscape Plan. Most of these will be native woodland species.

Mud Flats

10.8.0.8 Approximately 7,500 square metres of mudflats (L2) is expected to be affected due to the construction of the SWC bridge piers in the inter-tidal zone. Mitigation will include re-contouring of mudflats after construction under the ecological mitigation measures. residual impact is expected to be slight/moderate.

Fish Ponds

10.8.0.9 Some impact is expected on active and abandoned fish ponds (L5). Approximately 7,300 square metres of ponds will be lost. Many have been abandoned or are currently being filled in. Compensation is proposed under the ecological mitigation measures. residual impact is expected to be slight/moderate.

Stream Channels

10.8.0.10 Approximately 2km of stream channel (L6) is expected to be affected to some extent. The Ngau Hom Shek east stream will be heavily disturbed but there is potential to restore it. This will be undertaken via the wetland compensation scheme proposed under this project. Other streams affected are mostly channelised in some form. Residual impact after 10 years is expected to be negligible.

Village / Residential / Warehouse /Factory/ Roads and Similar Developments

10.8.0.11 The impact experienced by buildings and human settlements (L9) will be reduced to slight/moderate residual impact following the implementation of the mitigation measures.

Landscape Character

10.8.0.12 The landscape character of the study area will be significantly altered by Year 10. This will primarily be due to the future HSK NDA and other possible developments. The residual impact is difficult to determine given that little information on the nature of the proposed HSK NDA is available.

LC1: Agricultural Coastal Lowland
10.8.0.13 The agricultural coastal lowland will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, access paths and night lighting will affect this area. Even with established planting the road corridor will significantly affect the character of the area. Residual impact is expected to be moderate.

LC2: Greenbelt Foothills
10.8.0.14 The greenbelt foothills will experience changes to its character from the introduction of a large, elevated linear element into the landscape, slope cutting and some land formation. Columns, road deck, access paths, slope cuts, culverting and night lighting will affect this area. Even with established planting the road corridor will significantly affect the character of the area. Residual impact is expected to be slight/moderate.

LC3: Village Coastal Lowland
10.8.0.15 The Village Coastal Lowland will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, access paths and night lighting will affect this area. Established planting will help reducing impacts to a certain extent. Residual impact after Year 10 is expected to be moderate/substantial.

LC4: Sea Edge
10.8.0.16 The Sea Edge will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Much of the impact will be from the SWC. Columns, road deck, access paths and night lighting will affect this area. Planting cannot screen the SWC in this area. Residual impact is expected to be moderate/substantial.

LC5: Valley Lowland Agriculture
10.8.0.17 The Valley Lowland Agricultural areas will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, ramps at HSK and Lam Tei interchanges, noise barriers, access paths, maintenance areas, slope cutting, reduction in vegetation, the introduction of a helipad and night lighting will affect these areas. This will be seen in conjunction with the HSK NDA. Residual impact is expected to be slight/moderate.

LC6: Valley Lowland Mosaic
10.8.0.18 The Valley Lowland Mosaic areas will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, ramps at HSK and Lam Tei interchanges, noise barriers, access paths, maintenance areas, slope cutting, reduction in vegetation, the introduction of a helipad and night lighting will affect these areas. This will be seen in conjunction with the HSK NDA. Residual impact is expected to be negligible.

LC7: Lam Tei
10.8.0.19 The Lam Tei area will experience changes to its character from the introduction of a large, elevated linear element into the landscape. Columns, road deck, ramps at Lam Tei interchange, noise barriers, access paths, maintenance areas, slope cutting and night lighting will affect these areas. The road will be elevated up to a maximum of 28 metres off the ground with some noise barriers of a height of 5.5m with cantilever 2.5m. This will be seen in conjunction with existing development such as open storage areas, light industry and other infrastructure (Yuen Long Highway, West Rail, Castle Peak Road, etc) and the new HSK NDA. Residual impact is expected to be moderate.

LC8: Greenbelt / Country Park Uplands
10.8.0.20 The Greenbelt and Country Park Uplands will experience minimal changes to their character from the introduction of a large, elevated linear element into the adjacent landscape. Columns, road deck, ramps at Lam Tei interchange, noise barriers, access paths, maintenance areas, slope cutting and night lighting may affect these areas. This will be seen in against a background of existing development such as open storage areas, light industry and other infrastructure (Yuen Long Highway, West Rail, Castle Peak Road, etc) and the HSK NDA. The residual impact is expected to be negligible.

10.8.1 Evaluation of Residual Visual Impacts

Residential

10.8.1.1 Residents in the coastal Protection area and Agricultural area at Ngau Hom Shek (VSR1) will have direct, short range views to the new road which is immediately adjacent or very close to several receivers. Mitigation in the form of woodland planting and architectural design of road structures will help in reducing these impacts. Planting is expected to be well established at Year 10. Residual impacts are expected to be moderate.

10.8.1.2 Residents in existing villages and CDA east of HSK NDA (VSR3) will have intermittent, distant views to the DBL which will mostly be screened by the containers within the open storage areas. Mitigation in the form of woodland and other planting will help in reducing these impacts. Planting is expected to be well established at Year 10. Residual impact is expected to be negligible.

10.8.1.3 Residents in the proposed residential and community facilities and within the proposed village type development at HSK NDA (VSR5) will experience views of the elevated DBL mainline and HSK interchange and associated noise barriers (5.5m with 2.5m extension) and semi-enclosure. At year 10, screen planting is expected to be well established within the road corridor. Planting will also be incorporated within the ecological mitigation area adjacent to the DBL. Residual impact is expected to be moderate/substantial.

10.8.1.4 Residents in the proposed residential and community facilties and within the proposed village type development at HSK NDA (VSR6) will experience views of the elevated DBL mainline and Lam Tei interchange and associated noise barriers (up to 5.5m with 2.5m extension). At year 10, screen planting is expected to be well established within the road corridor. Residual impact is expected to be substantial.

10.8.1.5 Residents in village type development at Fui Sha Wai (VSR9) will have intermittent, very distant views to the DBL. At Year 10 the HSK NDA development is expected to screen most of the views from this area. Residual impact is expected to be negligible.

10.8.1.6 Residents in the residential development east of San Hing Tsuen and undetermined area northwest of San Hing Tsuen (VSR11) will have direct, close views to the DBL which will be elevated adjacent to this receiver. Impacts will include the elevated road, columns and noise barriers up to 5.5m with a 2.5m extension. Proposed adjacent planting will have minor mitigation affect on these receivers. Residual impacts are expected to remain moderate to substantial.

10.8.1.7 Residents in the developments and CDA area east of Lam Tei Tsuen (VSR12) will have direct, very close views to the DBL and Lam Tei interchange which will be elevated adjacent to this receiver. Impacts will arise from the elevated road, columns, noise up to 5.5m with a 2.5m extension and night lighting. Proposed adjacent planting will have minor mitigation affect on these receivers. Residual impacts are expected to remain substantial.

10.8.1.8 Residents in high rise residential development at Tin Shui Wai (VSR16) will have intermittent, very distant views to the DBL which at Year 10 will mostly be screened by the HSK NDA development. Residual impacts are expected to be negligible.

Occupational

10.8.1.9 Workers in proposed other specified land uses at HSK NDA (VSR4) will experience views of the elevated DBL mainline, maintenance area, helipad and access road and night lighting. Screen planting is expected to be well established at Year 10. Residual impacts are expected to be negligible/slight.

10.8.1.10 Workers in proposed possible extension to HSK NDA (VSR8) will experience intermittent, distant views of the elevated DBL mainline, maintenance area, helipad and access road and night lighting. Screen planting is expected to be well established at Year 10. Residual impacts are expected to be negligible.

Recreational

10.8.1.11 Walkers in the greenbelt and conservation area at Ngau Hom Shek and Yuen Tau Shan (VSR2) would have intermittent but close views to the DBL. However, very few people walk in these areas due to the presence of grave sites and its isolated nature and much of the area has already been disturbed to some extent. Screen planting is expected to be well established at Year 10. Residual impacts are expected to be negligible/slight.

10.8.1.12 Walkers in proposed amenity areas at HSK NDA (VSR7) will experience views of the elevated DBL mainline and HSK interchange and associated noise barriers (5.5m with 2.5m extension) and semi-enclosure. At Year 10 planting is expected to be well established and additional screen planting should be incorporated with the zone itself. residual impacts are expected to be moderate/substantial.

10.8.1.13 Walkers in the greenbelt and conservation area south of Yuen Long Highway (VSR10) would have intermittent but close views to the DBL and Lam Tei interchange. However, very few people walk in these areas due to its isolated nature and much of the area has already been disturbed to some extent. Screen planting is expected to have minor mitigation affect to these views because they are elevated. Residual impact is expected to be negligible/slight.

10.8.1.14 Walkers in the greenbelt north of Yuen Long Highway (VSR14) will experience views of the elevated DBL mainline and Lam Tei interchange and associated noise barriers (5.5m with 2.5m extension). Screen planting within the DBL corridor and the buffer planting in this zone itself is expected to be well established by Year 10. Some level of mitigation is expected. Residual impact is expected to be slight/moderate.

10.8.1.15 Walkers in the greenbelt south of To Yuen Wai (VSR15) would have direct, close views to the DBL and Yuen Long Highway. However, very few people walk in this area and the existing Yuen Long Highway means that significant changes are not expected. Screen planting is expected to be well established at Year 10. residual impact is expected to be negligible/slight.

10.8.1.16 Walkers in Tai Lam Country Park (VSR17) would have intermittent, direct views to the DBL and Lam Tei interchange. The distance and topography (in addition to the vegetation) means that views will be rare. They will also look down onto a valley floor that has already been significantly developed. Screen planting will have minor mitigation affect. Residual impact is expected to be slight/moderate.

Travellers

10.8.1.17 Travellers on Deep Bay Road (T1) would have intermittent, single vista views to the DBL mainline.Views fromm the road approaching Ngau Hom Shek will more likely be dominated by the SWC. Screen planting will be well established by Year 10. Residual impact is expected to be negligible/slight.

10.8.1.18 Travellers on Yuen Long Highway (T2) would have direct views to the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be dramatically interrupted by the introduction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. Screen planting will be well established by Year 10. Residual impact is expected to be negligible/slight.

10.8.1.19 Travellers on Castle Peak (T3) would have intermittent views to the DBL mainline and Lam Tei interchange. Views from the road approaching Lam Tei interchange will be interrupted by the introduction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. Screen planting will be well established by Year 10. Residual impact is expected to be negligible/slight.

10.8.1.20 Travellers on the proposed West Rail (T4) would have intermittent views to the the DBL mainline and Lam Tei interchange.Views from the train approaching Hung Shui Kiu will be interrupted by the introduction of ramps, elevated road decks and other structures. Views will be seen against a backdrop of adjacent development. Screen planting will be well established by Year 10. Residual impact is expected to be negligible.

10.8.1.21 Travellers on Deep Bay Link (T5) will have views of the new road, noise barriers from HSK to Lam Tei interchange, a semi-enclosure at HSK near HSK interchange and other structures and night lighting. Positive views over the valley and to Tin Shui Wai and Tai Lam Country Park will be provided to travellers on the road between Ngau Hom Shek and HSK interchange. planting adjacent to the road is expected to be well established by Year 10. Residual impact is expected to be negligible/slight.

10.9 Environmental Monitoring and Audit

10.9.0.1 It is recommended that EM&A during the design, construction and operational stages is undertaken. The design stage EM&A will consist of auditing the detailed landscape designs. Construction and operational stage EM&A will comprise audit of the EIA recommendations together with planting and planting establishment in the form of site inspection. The operational stage auditing will be undertaken for one year during the Contractor's maintenance period. Further details of the specific EM&A requirements are detailed in another section of this report and in the EM&A Manual.

10.9.0.2 The extent of the works areas should be regularly checked during the construction phase. Any trespass by the Contractor outside the limit of the works, including any damage to landscape areas should be reported to the Engineer. The progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for implementing landscape and visual mitigation measures.

10.9.0.3 The Monthly Report shall provide a statement on the general state of the landscape and visual aspects in the study area, and confirm that required mitigation measures are being implemented.

10.9.0.4 Details of the EM&A programme are provided in the EM&A Manual which is required to be made available for public exhibition under the EIAO.

10.10 Conclusions

10.10.0.1 The proposed works include 5.4km of new trunk road of dual-3 lane standard which will provide a link between SWC (landfall at Ngau Hom Shek) and Yuen Long Highway and the proposed Route 10 at Lam Tei. The works will include a large dual-3 lane mainline elevated up to 28 metres at Lam Tei and elevated for much of the rest of alignment except for areas adjacent to Ha Tsuen and Ngau Hom Shek.

10.10.0.2 The works will also include on/off ramps connecting with the YLH at Lam Tei (Lam Tei interchange), on/off ramps at HSK NDA (HSK interchange), and ramps at Ha Tsuen. The road is supported on columns at 30-40 metres spacings. Noise barriers ranging in height from 3m to 5.5m with a cantilever extension of 2.5m will line the sides and centreline of the road and ramps from Lam Tei to HSK interchange. A semi-enclosure of 200m in length is proposed just north of the HSK interchange. Additional works include a helipad, access road and maintenance area north of Ha Tsuen, and reprovisioning and modification works to San Wai Sewerage Treatment Plant.

10.10.0.3 Some of the landscape resources and character areas within the study area are of reasonable quality. These include the mangrove and mudflat areas at Ngau Hom Shek; the marsh, agricultural, orchards and plantation areas around Ngau Hom Shek and Ha Tsuen; and the woodland areas at the foothills of Yuen Tau Shan. All these resources have been judged to have a high sensitivity to change. Landscape Character areas which also have a high sensitivity to change include the Greenbelt Foothills, the Sea Edge, and the Greenbelt / Country Park Uplands.

10.10.0.4 Other resources and character areas have been so disturbed by uncontrolled development and access, fire and storage / dumping of materials that their sensitivity to change has been reduced to low or medium.

Landscape Impacts

10.10.0.5 There will be moderate to substantial impacts to the woodland areas during construction phase. The extent of loss is expected to be around 12,000m2. This can be mitigated to some extent through the transplanting of some existing trees and the planting of new stock. Mitigation via new planting within the road alignment will be more established after completion and several years after commencement of operation. The impact is expected to be reduced to slight / moderate.

10.10.0.6 There will be moderate impacts during construction to mangrove and mudflat areas and to agriculture, orchards and plantations. This will be due to the construction of the SWC. Replanting of mangroves is expected to result in slight/moderate residual impacts 10 years after commencement of operations. The re-planting mitigation is detailed under the ecological impact study. The planting of new native woodland is expected to help mitigate the impact to the agricultural areas, orchards and plantations. Residual impacts after 10 years of operation are expected to be negligible.

10.10.0.7 There is expected to be moderate to substantial impacts during construction to the landscape character of the village coastal lowland and the sea edge. Given the nature of the construction the character of these areas will be permanently and irreversibly changed. At Year 10 operation, the impacts are expected to remain at moderate to substantial.

10.10.0.8 There are a total 5,829 trees within the proposed alignment. These include native woodland, orchard and plantation trees. Of these, 1,671 trees are proposed to be retained, 373 transplanted and 3,785 are proposed to be felled. A proposed 6,473 new trees are proposed within the Compensatory and Master Landscape Plan. Most of these will be native woodland species.

Visual Impacts

10.10.0.9 Residents in the Coastal Protection Area and at the village of Ngau Hom Shek will experience moderate visual impact during construction. This will be a result of the construction works associated with the mainline connecting with the SWC and the temporary works areas to the east of the village. This impact is expected to remain as moderate due to the significant and permanent magnitude of change to the area.

10.10.0.10 There is expected to be moderate and substantial visual impacts during construction to residents in existing and proposed edevelopments east of San Hing Tsuen and the undetermined area northwest of San Hing Tsuen (VSR11) and residents in residnetial developments and CDA area east of Lam Tei Tsuen (VSR12). These residents will have direct, close views of the construction of the works including the mainline and Lam Tei interchange ramps. These residents will experience the construction of an elevated mainline (dual-3 lane trunk road of approximately 33m wide) sitting on concrete columns which are spaced at 30- 40 metres. The deck will be elevated from 29mPD to 41mPD which translates into a relative height of approximately 8 to 28 metres. On top of the road there will be noise barriers along the side and median. The tallest of these barriers is a cantilever barrier of 5.5m height with a 2.5m extension to be located on the eastern side of the mainline and along the ramps at Lam Tei interchange. Additionally, there will are more noise barriers of similar dimensions proposed for the Yuen Long Highway widening.

10.10.0.11 The magnitude of change to these areas will be large during construction and operation phases and the impacts are difficult to mitigate. The noise barriers proposed to use vision panels which will help reduce the visual bulk of the structure of overall. However, the mass of the road deck, ramps and columns will still be significant. In addition, there are concerns regarding glare created by the use of vision panels due to reflected sunlight. In addition the visual impacts expected by the construction of Route are expected to exacerbate the situation for these VSRs. Route 10 is expected to add road structure and substantial slope cutting to the visual environment.

10.10.0.12 The completion of construction of the DBL is scheduled for mid 2006. Since the VSRs identified within the future HSK NDA will not be constructed before the DBL is completed, these VSRs are not expected to be subjected to construction impacts. However, during operation phase, moderate to substantial residual impacts are expected upon the residential and community facilities at HSK NDA (VSR 5), the proposed village type development and community facilities at HSK NDA (VSR6) and the amenity area of HSK NDA located adjacent to the DBL mainline. The mainline structures and associated noise barriers and semi-enclosure will have significant visual impact upon these receivers. Mitigation in the form of screen planting and earth mounding will assist in ameliorating these impacts but the residual impacts will remain moderate to substantial.