3 NOISE IMPACT

3.0.0.1 This Section presents an assessment of the potential noise impacts associated with the construction and operation of the proposed Deep Bay Link. Noise impacts during the construction phase are mainly associated with the construction activities and the use of powered mechanical equipment for construction works. For operation phase, the noise impacts are primarily from the road traffic through the Deep Bay Link.

3.1 Legislation, Policies, Plans, Standards and Criteria

3.1.1 Construction Noise

3.1.1.1 The principal legislation governing the control of construction noise is the Noise Control Ordinance (NCO) (Cap 400) and the Environmental Impact Assessment Ordinance (EIAO) (Cap 499). Guidelines concerning the assessment methodology and relevant criteria are provided in the supporting Technical Memoranda (TMs). The following TMs are applicable to the control of noise from construction activities:

Percussive Piling

3.1.1.2 Percussive Piling is prohibited at any time on Sundays and public holidays and during the weekday evening and night-time hours (1900-0700hrs, Monday through Saturday). A Construction Noise Permit (CNP) is required for such works during the weekday daytime hours (0700-1900hrs Monday through Saturday).

3.1.1.3 When assessing a CNP application for carrying out percussive piling, the Noise Control Authority is guided by the PP-TM. The Noise Control Authority will look at the difference between the Acceptable Noise Levels (ANLs), as promulgated in the PP-TM, and the Corrected Noise Levels (CNLs) that are associated with the proposed piling activities. Depending on the level of noise impact on nearby Noise Sensitive Receivers (NSRs), the Noise Control Authority would determine the time periods for percussive piling operation. The time periods are indicated in Table 3.1.

Table 3.1 Permitted Hours of Operation for Percussive Piling (not involving the use of diesel, pneumatic and/or steam hammers)

Amount by which CNL exceeds ANL

Permitted hours of operation on any day not being a holiday

more than 10 dB(A)

0800 to 0900 and 1230 to 1330 and 1700 to 1800

more than 0 dB(A) and less than or equal to 10 dB(A)

0800 to 0930 and 1200 to 1400 and 1630 to 1800

no exceedance

0700 to 1900

3.1.1.4 The Government is committed to phase out the use of diesel, pneumatic and steam hammer pile drivers, which are particularly noisy. There are more stringent requirements for the use of diesel, pneumatic and steam hammer after 1 October 1999.

General Construction Works

3.1.1.5 Noise generated by general construction works during normal working hours (i.e. 0700 to 1900 hours on any day not being a Sunday or public holiday) fall within the scope of the EIAO-TM. The recommended noise standards are presented in Table 3.2 below.

Table 3.2 EIAO-TM Daytime Construction Noise Limit

Uses

Noise Standard (Leq, 30 min dB(A))

Domestic Premises

75

Educational Institutions (normal periods)

70

Educational institutions (during examination periods)

65

3.1.1.6 The NCO provides statutory controls on general construction works during the restricted hours (i.e. 1900 to 0700 hours Monday to Saturday and at any time on Sundays and public holidays). The use of powered mechanical equipment (PME) for the carrying out of construction works during the restricted hours would require a Construction Noise Permit (CNP). The Noise Control Authority is guided by the GW-TM when assessing such an application.

3.1.1.7 When assessing a CNP application for the use of PME, the Noise Control Authority will compare the ANL's as promulgated in the GW-TM, and the CNLs (after accounting for factors such as barrier effects and reflections) associated with the agreed PME operations. A CNP may be issued if the CNL is equal to or less than the ANL. The ANLs are related to the noise sensitivity of the area in question and the Noise Control Authority will judge these at the time of the CNP application. As conditions may vary between the time of the EIA for a project and the time of a CNP application, the assignment of any Area Sensitivity Ratings in the EIA is not binding upon the Noise Control Authority. The relevant ANLs are shown in Table 3.3.

Table 3.3 Acceptable Noise Levels (ANL, Leq 5min dB(A))

Time Period

Area Sensitivity Rating

A

B

C

All days during the evening (1900-2300 hours) and general holidays (including Sundays) during the day and evening (0700-2300 hours)

60

55

70

All days during the night-time (2300-0700 hours)

45

50

55

3.1.1.8 In addition to the general controls on the use of PME during the restricted hours, the Noise Control Authority has implemented a more stringent scheme via the DA-TM. The DA-TM regulates the use of five types of Specified Powered Mechanical Equipment (SPME) and three types of Prescribed Construction Work (PCW), which are non-PME activities, in primarily densely populated neighborhoods called Designated Areas (DAs) during restricted hours. The SPME and PCW are shown in Table 3.4 below:

Table 3.4 Specified Powered Mechanical Equipment (SPME) and Prescribed Construction Work (PCW) controlled under DA-TM

Specified Powered Mechanical Equipment (SPME)

Prescribed Construction Work (PCW)

  • Hand-held breaker
  • Erection or dismantling of formwork or scaffolding
  • Bulldozer
  • Loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material
  • Concrete lorry mixer
  • Hammering
  • Dump Truck
 
  • Hand-held vibratory poker
 

3.1.1.9 In the interest of offering additional protection to the population, the carrying out of PCW is generally banned inside a DA during restricted hours. As for the use of SPME, it would be necessary to comply with DA-TM noise level requirements that are 15 dB(A) less than those listed in the GW-TM before a CNP may be issued.

3.1.1.10 Factors such as the assigning of Area Sensitivity Rating, ANLs etc could affect the assessment results of a CNP application. The Noise Control Authority would decide these at the time of assessment of such an application based on the contemporary situations/conditions. It should be noted that the situations/conditions around the sites may change from time to time.

3.1.1.11 Despite any description or assessment made in the subsequent paragraphs, the Noise Control Authority will be guided by the Technical Memorandum (Memoranda) in assessing an application, once filed, for a Construction Noise Permit (CNP). The Authority will consider all the factors affecting their decision taking contemporary situations/conditions into account. Nothing in this report shall bind the Authority in making their decision. There is no guarantee that a CNP will be issued. If a permit is to be issued, the Authority shall include any condition it thinks fit, and such conditions shall be followed while the works covered by the permit are being carried out. Failure to comply with any conditions could result in the cancellation of the permit and prosecution action under the NCO.

3.1.2 Operational Noise / Traffic Noise

3.1.2.1 The EIAO-TM provides guidance on acceptable road traffic noise levels at the openable windows of various types of noise sensitive buildings. The relevant criteria are shown in Table 3.5 below:

Table 3.5 EIAO-TM Road Traffic Noise Planning Criteria

Uses

Road Traffic Noise L10, (1hr) dB(A)

Domestic Premises

70

Hotel and Hostels

70

Offices

70

Educational Institutions

65

Hospital & Clinics

55

Places of public worship and courts of law

65

Note: The criteria presented in the above apply to noise sensitive uses which rely on opened window for ventilation.

 

3.1.2.2 In cases where practicable direct mitigation measures alone would not be adequate in mitigating noise impacts, indirect technical remedies for existing NSRs may be adopted provided that the residual impacts satisfy all three criteria below:

(i) the predicted overall noise level from the new road together with other traffic in the vicinity must be above the specified noise level (e.g. 70 dB(A) for domestic premises and 65 dB(A) for education institutions, all in L10(1hr));


(ii) the predicted overall noise level is at least 1.0 dB(A) more than the "prevailing traffic noise level", i.e. the total traffic noise level existing before the works to construct were commenced; and


(iii) the contribution to the increase in the predicted overall noise level from the new road must be at least 1.0 dB(A).

The total number of existing dwellings, classrooms and other noise sensitive elements that may qualify for indirect technical remedies are then estimated.

3.1.2.3 For the purpose of this assessment, the roads within the study scope could be classified as follows:

3.2 Description of Environment

3.2.1 Potential Noise Sources

3.2.1.1 The proposed Deep Bay Link is a trunk road of dual-3 lane standard providing a strategic link between the proposed Shenzhen Western Corridor, Yuen Long Highway and the proposed Route 10. Potential operational phase noise sources from the proposed DBL includes:

3.2.1.2 During the construction phase, noise from construction activities is also likely to affect noise sensitive receivers nearby.

3.2.1.3 There are a few existing noise sources in the surrounding areas. They are basically the road traffic noise from distributors and trunk roads, namely Castle Peak Road and Yuen Long Highway.

3.2.1.4 The area is generally under intensive planning for the future development. A strategic growth area, the Hung Shui Kiu NDA, was under active design and planning stage. In HSKNDA, a new town will be formed which creates a number of new noise sensitive receivers near DBL.
3.2.1.5 Yuen Long Highway is also undergoing the design for a dual-3 widening which also increase the amount of traffic noise in the area. The project has completed an EIA Report in December 2001.

3.2.1.6 Furthermore, DBL will connect the traffic from the proposed Route 10 which may also affect noise sensitive receivers nearby.

3.2.2 Noise Sensitive Receivers

3.2.2.1 With reference to Annex 13 of the EIAO-TM, noise sensitive receivers (NSRs) include residential uses (all domestic premises including temporary housing), institutional uses (educational institutions including kindergarten and nurseries, hospitals, medical clinics, homes for the aged, convalescent homes, places of worship, libraries, court of law, performing arts centres, auditoria and amphitheaters) and others. NSRs within a distance of 300 m from the either side of and along the full sketch of the project boundary (including the proposed road and the associate facilities) were identified for noise assessments.

3.2.2.2 Locations of existing and planned/committed NSRs are shown in Figure 3.1. The works limit/area presents the construction work area and the proposed land resumption limit. Existing receivers inside the land resumption limit will be removed at that time. Existing NSRs were identified by reference to topographic maps and field surveys. They are listed in the following Table 3.7.

Table 3.7 Existing Noise Sensitive Receivers (NSRs) Identified

NSR

Name

Type

Description

E1

Lo Fung Hang

Residential

2-3 storeys squatter house/private residential development

E2

Nam On Fat Tong

Places of Worship

1 storey temple

E3

Rural/village houses near Route 10 portal

Residential

2-3 storeys squatter house/private residential developments

E4

Lam Tei Gospel School

Educational

1 storey primary school

E5

Rural/village houses near Lam Tei Gospel School

Residential

2 storeys village residential developments

E6

Rural/village houses near Shun Tat Street

Residential

3 storeys village residential developments

E7

Botania Villa

Residential

12 storeys private medium density residential development

E8

Fuk Hang Tsuen village

Residential

2-3 storeys squatter houses/private residential developments

E9

Tuen Mun San Tsuen

Residential

3 storeys private residential development

E10

Madam Lau Kam Lung Secondary School of Miu Fat Buddhist

Educational

6 storeys secondary school

E11

Miu Fat Buddhist Monastery

Places of Worship

6 storeys temple

E12

Rural/village houses near Tsoi Yuen Tsuen

Residential

2-3 storeys squatter house/village residential developments

E13

Tsoi Yuen Tsuen

Residential

3 storeys village residential developments

E14

Tsing Chuen Wai

Residential

3 storeys village residential developments

E15

Rural/village houses north to Tsing Chuen Wai

Residential

2-3 storeys squatter house/private residential development

E16

Nai Wai

Residential

3 storeys village residential development

E18

Rural/village houses near future Area 3B

Residential

2-3 storeys squatter house/private residential developments

E19

Tan Kwai Tsuen

Residential

2-3 storeys squatter house/village residential developments

E20

Ying Yin School

Educational

1 storey primary school

E22

San Sang San Tsuen

Residential

1-3 storeys squatter house/village residential developments

E24

Rural/village houses near Ngau Hom Shek

Residential

1 storey squatter house/private residential developments with fish ponds and farms

E25

Fu Tai Estate

Residential

40 storeys public residential developments


3.2.2.3 Existing NSRs in areas encircled by the proposed Lam Tei Interchange would be resumed together with the proposed Route 10 Northern Section project. The traffic at the beginning of DBL operation would be lower than the traffic in year 2021. Considering the NSRs are low-rise in nature, they are not likely affected during the intermediate period.

3.2.2.4 Planned/committed NSRs in the future were identified by reference to relevant Outline Zoning Plans, Outline Development Plans, Layout Plans and other published plans in relation to the Planning and Development on Northwest New Territories. These NSRs were mostly found in the proposed Hung Shui Kiu New Development Area and some local planned private developments were also identified. Table 3.8 gives the details of the planned/committed NSRs.

Table 3.8 Future Noise Sensitive Receivers (NSRs) identified in Planned/Committed Development

NSR

Name

Type

Description

F1A

Fuk Hang Tsuen Road CDA -

A/DPA/TM-LTYY/110

CDA

Assumed 7–13 storeys with a total of 13 blocks of private residential development north of Botania Villa, with a height restriction of 45mPD

F1B

A/DPA/TM-LTYY/111

CDA

Proposed 144 residential units in 5 domestic blocks, in 2-6 storeys, clubhouse & recreational facilities

F1C

A/YL-TYST/14

Residential

Proposed 124 residential units in 8 domestic blocks of 4 storeys, club house, swimming pool & car park.

F1D

A/TM-LTYY/012

Residential

Proposed 1 small house of 3 storeys high

Hung Shui Kiu New Development Area

F2

Area 1C – E

Educational

Assumed 6 storeys of primary and secondary schools for assessment purpose.

F3

Area 2A – R1

(RS/HOS/PSPS)

Residential

Assumed 50 storeys public housing developments for assessment purpose.

F4

Area 2B – R1

Residential

Assumed 50 storeys private housing developments for assessment purpose.

F5

Area 2B – E

Educational

Assumed 6 storeys of primary and secondary schools for assessment purpose.

F6

Area 2C – R2 (QTRS)

Residential

Assumed 50 storeys private housing developments for assessment purpose.

F7

Area 2D – R2 (PSPS)

Residential

Assumed 50 storeys public housing developments for assessment purpose.

F8

Area 2D – E

Educational

Assumed 6 storeys of primary and secondary schools for assessment purpose.

F9

Area 3C – RR2

Residential

Assumed 12 storeys residential developments for assessment purpose.

Note: information was based on the available data as the date of the issue of this report.

3.2.2.5 For the purpose of this assessment, an alternative layout was included for air and noise assessments for HSKNDA. The alternative layout with NSRs included the following revisions:

3.3 Assessment Methodology

3.3.1 Construction Noise

3.3.1.1 Construction noise impact was assessed by adopting the standard acoustic principles and the methodologies relevant to technical memoranda issue under the Noise Control Ordinance, primarily the TM on Noise from Construction Work other than Percussive Piling (GW-TM).

3.3.1.2 During daytime from 0700hr to 1900hr on weekdays other than general holidays, the assessment of construction noise excluding percussive piling was carried out in accordance with the methodology stipulated in paragraphs 5.3 and 5.4 of Annex 13 and the criteria in Table 1B of Annex 5 of the EIAO-TM.

3.3.1.3 The assessment also made reference to the British Standard BS 5228:Part 1:1984 Noise Control on Construction and Open Sites, Part 1: Code of Practice for Basic Information and Procedures for Noise Control. Sound power levels of equipment will be referenced to these TMs and the BS5228, where applicable, and the emission levels in previous projects in Hong Kong were also be referenced.

3.3.1.4 Figure 3.24 shows the locations of notional noise source for construction noise assessment. Notional noise sources were assumed at the bridge pier location where intensive activities were likely found.

3.3.1.5 Practicable direct mitigation measures including movable barriers, enclosures, quieter alternative methods, re-scheduling and restricting hours of operation of noisy task were recommended if exceedance of relevant criteria was predicted. In case where the mitigated noise levels still exceeded the relevant criteria, the duration of the noise exceedance was given.

3.3.1.6 Cumulative impacts from other projects had been included for assessment. Proposed mitigation measures of the Yuen Long Highway Widening were assumed in place in this assessment with reference to the Final Environmental Impact Assessment Report - Widening of Yuen Long Highway between Lam Tei and Shap Pat Heung Interchange Preliminary Design and Ground Investigation Assignment exhibited under EIAO.

3.3.2 Traffic Noise

3.3.2.1 The computer programme, HFANoise, was used to model traffic noise on the road networks. It adopts methodology of the UK Department of Transport's Calculation of Road Traffic Noise (CRTN) which has been accepted for the assessment of road traffic noise impact in the Annex 13 of the EIAO-TM. The road traffic noise was presented in terms of noise levels exceeded for 10% of the one-hour period for the hour having the peak traffic flow [L10(1hr) dB(A)].

3.3.2.2 The procedures of CRTN assume typical traffic and noise propagation conditions which are consistent with moderately adverse wind velocities and direction. All noise levels were expressed in terms of L10 hourly dB(A). The value of L10 hourly dB(A) is the noise level exceeded for just 10% of the time over a period of one hour. The calculations were worked to 0.1dB(A) keeping within the quoted range of the validity charts. For comparison with the specified noise level or the EIAO-TM standards, the relevant noise level from traffic expected to use the highway was to be rounded to the nearest whole number (0.5 being rounded up). Details of the methods are given in the CRTN.

3.3.2.3 Considering the scope of this Project, road sections were classified as the following categories for purpose of road traffic noise assessment:

(i) New roads

(ii) Altered/Planned roads:

(iii) Existing roads
 

3.3.2.4 The road classification for assessment is graphically presented in Figure 3.34. The cross-sections of the different alignment settings are given in Figure 10.6.3.1.

3.3.2.5 Calculations of future road traffic noise were based on the peak hourly flow in respect of the maximum traffic projected within a 15 years period upon commencement of operation i.e. afternoon peak hour traffic flow in year 2021. The traffic flow forecasts were endorsed by Transport Department for use in this EIA and a memo from TD is given in Appendix 3B. It had assumed with the future strategic growth and planning of traffic routes including regional developments like HSKNDA, operation of Route 10 Northern Section, potential widening of Yuen Long Highway to a dual-4-lanes configuration. The traffic flow data for year 2021 afternoon peak hour are presented in Appendix 3B Figures 3.1a, 3.1b and 3.1c.

3.3.2.6 Both the morning peak and afternoon peak for traffic flows were evaluated. Peak hourly traffic may vary for PM & AM at some parts of the DBL. The main reasons for choosing PM peak hourly traffic are: i) DBL mainly serves cross-boundary traffic for which after which the peak is in the afternoon, and ii) The total emissions over the entire DBL are higher in the afternoon considering the flow and length of the road involved. The case may be different for HSKNDA and Yuen Long Highway.

3.3.2.7 The scenario without Route 10 in year 2011 was also evaluated. Without Route 10 in year 2011 the traffic is likely using YLH as the main dispersion route. The year 2021 traffic forecast have taken into account for the possible growth (growth in cross-boundary traffic, incoming population for HSKNDA, and other regional increase in traffic) during the next 15 years after the operation of DBL. The case for year 2021 is much larger in traffic volume as compared to that of the year 2011 and therefore, it is considered as the worst-case within 15 years for use in assessing the environmental impact for traffic air and noise pollution. The traffic flow data for year 2021 afternoon peak hour are presented in Appendix 3B Figures 3.1d and 3.1e.

3.3.2.8 Assessment points (APs) at the worst-affected noise sensitive façade by DBL were selected to represent identified NSRs for quantitative noise assessments. Details of the APs are presented in Figure 3.1 for location and in Appendix 3B for calculation assumptions. Traffic noise levels at the APs in respect of each road section and the overall noise levels from the combined road sections (both new and existing) were calculated.

3.4 Identification, Prediction and Evaluation of Potential Impacts

3.4.1 Construction Phase

Construction Method

3.4.1.1 The construction of DBL alignment typically involves piling, pile cap construction, pier construction and superstructure construction. For the construction of superstructure, two methods of construction are considered for viaducts, namely the segmental launching method and the span by span cast in-situ method. The mainline of DBL together with the ramps cross over YLH, KCRC West Rail and Castle Peak Road where falsework will be high and where bridge decks are fairly straight will best be constructed by segmental launching methods. Other ramps not crossing major roads and where falseworks are low, conventional span by span cast in-situ method should be used. The construction procedure of DBL alignment is illustrated in Figure 3.22.

3.4.1.2 The construction work of DBL could be divided into the following work tasks and areas:

1) Deep Bay Link Mainline
The road layout of the mainline is a dual-3-lane carriageway. However, due to bifurcation of slip roads, the deck is generally wider than 2 lanes in each direction. A twin box section for the mainline is therefore proposed. Typical span length will be 40m with monolithic reinforced concrete column.

2) Ramps in Lam Tei Interchange Connecting to Yuen Long Highway
All ramps at Lam Tei Interchange would be constructed by cast-in-situ method. They can be constructed simultaneously with the Mainline.

3) Precast Yard for Segmental Launching Method
The segmental construction requires a precast yard for fabrication of the concrete segments and the curing and storage of the completed concrete segments. There would be approximately 2500 numbers of segments which may required up to 6 production lines. The size of a fabrication yard will be approximately 500 m2 and the storage yard will be approximately 700 m2 allowing the stacking up of segments.

It is also considered to import concrete segments from Mainland China instead of setting up a precast yard. This would require a barging point at Tuen Mun for shipping the concrete segments and an initial proposal is to use the same barging point as for Shenzhen Western Corridor Project. The environmental impact for this alternative arrangement is assessed in the Section Barging Point for Lung Kwu Sheung Tan.

4) Concrete Batching Plant
Concrete batching plant would be used for the project which would be located at the loop encircles by ramps at Lam Tei Interchange and at Ha Tsuen Interchange.

5) Haul Road Construction traffic
Since there is no large scale site formation nor cut-and-fill works for DBL, the construction traffic generated is small. The access to the site will be diverted to several proposed routes as shown in Figure 3.25.
3.4.1.3 The proposed locations of the precast yard and concrete batching plant are shown in Appendix 3A - Drawing 22913/P/53/597 and Drawing 22913/P/53/598.

3.4.1.4 For the assessment of construction noise impact on the sensitive receivers at Ngau Hom Shek, the construction activities in association with the construction activities of Shenzhen Western Corridor are assumed as follows:

Construction activity 1 - construction of SWC shore alignment;
Construction activity 2 - construction of DBL landside alignment at the work site;
Construction activity 3 - construction of DBL alignment;
Construction activity 4 - SWC work site;
Construction activity 5 - construction of haul road;
Construction activity 6 - construction traffic;
Construction activity 7 - construction of SWC shore alignment (500m offshore); and
Construction activity 8 - construction of SWC shore alignment (1500m offshore).

3.4.1.5 The SWC work site (construction activity 4) will be required by SWC team for the construction of shore alignment and this part of alignment (construction activity 2) will therefore be constructed at the last stage. In the view of this arrangement construction activities 1, 3, 4, 7, 8 would likely be working at the same time under the worst-case. When these activities are completed, construction activity 2 will be carried out over the area of the work site at the end. The construction of haul road and haul road traffic which are in different locations will be separately analysed.

3.4.1.6 The information regarding SWC have been agreed with the SWC Project Team for use in this EIA report as best available information at the time of submission.

3.4.1.7 In general percussive piling is not recommended due to potential noise impacts and bored piling would be used instead.

Tentative Construction Schedule

General Works

3.4.1.8 Only a tentative construction schedule is available in this preliminary design stage. The construction period of DBL is anticipated from 2003 to 2006. Major construction activities would be started in 2003 and completed in 2006.

3.4.1.9 It is anticipated that there will be no construction work carried out during the restricted hours (i.e. between 7pm and 7am and any time during general holidays including Sunday) under the scheduled construction programme for general works, except the unavoidable night works for several road segments over major roads and rails.

Night Works

3.4.1.10 Unavoidable night works are likely required for limited alignment construction crossing over major roads (Castle Peak Road and Yuen Long Highway) and the West Rail and LRT.

3.4.1.11 For constructing the viaduct decks spanning across railways and major roads using balance cantilevering method, it is a must as required by Transport Department and the Police Force that no live traffic should be underneath the launching operation for safety reasons. Further consultation with KCRC revealed that segmental viaduct construction would not be permitted above live rail tracks during the operational hours of both LRT and West Rail. Hence these activities can only be carried out when the railways are in the isolation period and roads are closed to public traffic. It would be during the night-time period when the closure of railway and roads would cause less disturbance to the traffic.

3.4.1.12 The isolation period of KCRC and LRT will be around 1:00am to 5:00am. Major road closure will be around 12:00 midnight to 6:00am. Hence night works are unavoidable in this regard.

3.4.1.13 The major activity will be the launching deck segments. Each operation can launch two segments at each night. For a 2.5m wide segment, a span of around 40m long will contain 16 segments. It will required 16 days to complete one span using balance cantilever method. It is envisaged that the contractor may propose faster erection method such that 2 segments can be launched per night, but it will be subject to the contractor's proposal.

3.4.1.14 It is essential to use segmental launching for this project, since this will save the erection of false work to support the bridge deck. The height of the bridge decks are relatively high in general, for instance, the deck is 16m above Castle Peak Road in order to span over the West Rail viaduct. There are difficulties and expensive in erecting the false works for such a height. Segmental launching is the most effective and common construction method to over come these difficulties.

3.4.1.15 However according to our experience in the construction of Route 3 country park section and the West Rail viaducts recently, there are requirements from the traffic police and KCRC that the no live traffic should be underneath the launching operation. That is to say the roads have to be closed and the Railways had to be isolated during such operation. For the strategy roads such as Yuen Long Highway, Castle peak Road, West rail and LRT, the only time they can be closed or isolated will be around 12:00 midnight to 6:00am every night. Although the window for the closure of isolation is short, a pair of segment launching is usually achievable.

3.4.1.16 As reviewed from previous projects, this operation is unavoidable and this is the only construction method that the bridge deck can be constructed for such a type programme project. Therefore the night shift are unavoidable. The operation, however will only mobilize the launching girder and the lorries supplying the bridge segments. No other plants are required. In general, each span requires around 16 continuous nights, say 2 weeks per span. There are 2 spans over West Rail, 2 spans over LRT and Castle Peak Road and 8 spans over YLH. The detail work methods have not been available at this stage.

3.4.1.17 In the view of the stringent noise limits during night-time, the preliminary estimate showed that the it was difficult to mitigate to the 45 dB noise limit even that all reasonable mitigation measures were considered exhausted including quiet plant and temporary noise barriers had been assumed. The prediction is given in Appendix 3B Table 3A2.7.

3.4.1.18 Before these unavoidable night works to be carried, the future contractor has to apply for a Construction Noise Permit (CNP) under NCO for carrying nighttime construction work under the circumstance. It should be note that the Noise Control Authority, at its discretion, issue a CNP even if the noise limit is exceeded if it can be demonstrated to his satisfaction that carrying nighttime construction work during restricted hours would cause less public annoyance or inconvenience than would be caused by carrying out the construction work during non-restricted hours.

Alignment Construction at Local Level

3.4.1.19 Construction of alignment segment at local level would be a more important concern that the overall construction programme. Sensitive receivers are mainly affected by the construction of road alignment which in turn operates in a sequential manner. After completion of a particular task, the construction activities and equipment move to the next location. Receivers are only affected temporarily and intermittently.

3.4.1.20 The timing for the construction of road segment in front of a sensitive receiver would likely be the true impact period of construction. For a typical span of 40m long, piling for each pier is about 3 weeks, wait for 2 weeks, then complete pile cap within 2 weeks, wait 3 weeks and construct the pier. The construction of pier requires 3 weeks, wait for 3 weeks before constructing the deck. The first pier will be available to receive load after 16 weeks. It would take another 2 weeks for launching of road segments.

3.4.1.21 It is estimated that the fabrication yard and the associated batching plant can be formed and set up within 2 months of commencement. The first segment can be cast in the 4th month after commencement. Launching should not start until there is a balance between the speed of building piers and deck launching. It is very likely that the launching should start 8 months after commencement.

Cumulative Impact due to Concurrent Other Construction Activities

3.4.1.22 For the purpose of this EIA, cumulative impacts of DBL associated with other concurrent project was assessed based on the following programme:

Project Anticipated Construction Programme
Deep Bay Link 2003-2006
Shenzhen-Hong Kong Western Corridor* 2003-2005
Yuen Long Highway Widening* 2003-2005
Hung Shui Kiu New Development Area* 2004-2010
Route 10 Northern Section* 2004-2007
San Wai Sewerage Treatment Works* 2004-2007

* The programme is tentative only and subject to review by respective study.

3.4.1.23 Since most of the noisy construction work like foundation and structural work would be completed by 2005 for DBL, the cumulative impacts would only be signification with the construction of SWC, Route 10 Northern Section and Yuen Long Highway widening at localized areas.

Potential Impacts for Unmitigated Scenario

3.4.1.24 DBL is constructed to a certain extent by resumption of existing rural land. The extent of land resumption together with the construction work site boundary is typically 10 m to 30 m from the edge of the proposed road alignment. Under these circumstances, some existing noise sensitive receivers are lying quite close to the construction work site. Table 3.9 shows the buffer distance required for the different work tasks as an indication.

Table 3.9 Board Estimate of the Influence of Construction Noise for Unmitigated Scenario

Construction Task

Worst-case Sound Power Level

Estimated Buffer Distance* (m)

Remarks

Bridge cast in-situ method

122

126

During piling

Bridge segmental method

122

126

During piling

Precast (Fabrication) yard

126

200

--

Concrete Batching Plant

120

100

--

Roadwork

120

100

During cut and fill

* Buffer distance required to meet 75 dB(A) criteria

    Sound power level are obtained in the unmitigated scenario presented in Appendix 3A2.4.

3.4.1.25 It can be seen that NSRs located within 200 m away from the construction activities would likely be affected by the construction noise for unmitigated scenario.

3.4.1.26 The haul roads to construction sites likely to cause noise concern were assessed. The proposed routes of construction site access were shown in Figure 3.25. Since there would be no longer any large-scale cut and fill, or site formation activities, the peak haul road traffic would likely be around 40 veh/hr for both to-and-from directions. While the peak haul road traffic near Ngau Hom Shek would be around 80 veh/hr for both to-and-from directions.

3.4.1.27 Noise due to haul road traffic was estimated and the details of the prediction are presented in Appendices 3A1 (for Ha Tsuen and Lam Tei areas) and 3A3.6 (for Ngau Hom Shek area). The results show that at distances 3m, 5m, and 10m from the centre of the haul road the noise levels would be 70, 68 and 65 dB(A) respectively. Hence, the potential noise impacts to nearby NSRs would not be adverse and be within the acceptable standard of 75 dB(A).

3.4.1.28 For the haul road traffic noise impact arising from Fung Kong Tsuen Road near Ngau Hom Shek, the results show that at distances 3m, 5m, and 10m from the centre of the haul road the noise levels would be 73, 71 and 68 dB(A) respectively. Hence, the potential noise impacts to nearby NSRs would not be adverse and be within the acceptable standard of 75 dB(A).

3.4.1.29 Details of construction noise activities and assessments are presented in Appendices 3A1 and 3A2.

3.4.1.30 For the sensitive receivers at Ngau Hom Shek (E24), details of the construction noise activities and assessments are given in Appendix 3A3.
Barging Point at Lung Kwu Sheung Tan

3.4.1.31 During construction stage, it would be necessary to provide a barging point for barges to transport the construction materials (e.g. concrete for in-situ construction, precast viaduct segments, dump waste (e.g. dredged materials) through marine route and then by land to the site. There is no marine construction site for the Project.

3.4.1.32 The proposed location for the barging point is located at Lung Kwu Sheung Tan to the south of WENT Landfill along Yung Long Road. As shown in Drawing No. 23306/P/03/104 in Appendix 3A, road access is provided by Yung Long Road connecting Lung Kwu Tan Road, which then leads to Tuen Mun Road to other places. The roads are currently used as access for the power station in Lung Kwu Tan, thus upgrading is generally not necessary.

3.4.1.33 The number of vehicles for loading and unloading in barging points is expected to be small, likely around 2 nos. per hour at maximum. The likely mechanical equipment involved are one barge, the crane of the barge or probably a mobile crane.

3.4.1.34 No NSRs were identified within 300m from this proposed barging point and hence there would be no adverse impact expected.

3.4.2 Operational Phase

3.4.2.1 Predicted traffic noise levels at NSRs are summarized in Table 3.16 for existing NSRs, Table 3.17 for Planned NSRs and Table 3.18 for HSKNDA.

Ngau Hom Shek

3.4.2.2 DBL road alignment at this section is elevated and is on bridge structure. Surrounding the NSR (NSR E24) are squatter houses or temporary houses and are generally one storeys high. Since the road alignment is elevated, noise from traffic is screened by the bridge structure itself and impact is considered minimal. Predicted traffic noise levels at NSRs were around 65-70dB(A), which are within the EIAO-TM standard.

Hung Shui Kiu to Castle Peak Road

3.4.2.3 Existing landuse near the Hung Shui Kiu Exit and the mainline of DBL north of Castle Peak Road are two or three storeys high village houses or squatter houses. The predicted noise impacts are acceptable for the existing NSRs E14 and E16 but not for the existing NSR E15 (village houses near Tsing Chuen Wai). Exceedances of 1 to 4 dB(A) of noise levels at E15 was found. It was mainly due to cumulative noise impacts from the mainline of DBL and the existing Castle Peak Road.

Between Castle Peak Road and Lam Tei Interchange

3.4.2.4 Existing NSRs (NSRs E8 Fuk Hang Tsuen and E9 Tuen Mun San Tsuen) are two or three storeys high village houses or squatter houses (1 storey), while NSR E7 (Botania Villa) is 12 storeys high residential buildings. NSRs E10 and E11 are a secondary school and Miu Fat Buddhist Monastery, respectively. Noise impacts were acceptable for E9, but exceedances were found at E7, E8, E10 and E11. The predicted noise levels ranged from 66-79dB(A) for E7 and E8. Noise exceedances of about 1 to 9 dB(A) were found at E10 and E11.

3.4.2.5 Higher noise levels were predicted at those NSRs close to the mainline of DBL, Ramps B and D of Lam Tei Interchange and the existing Yuen Long Highway. The traffic from these roads is the major source of noise level exceedances.

3.4.2.6 Future planned residential area (NSRs F1A and F1B) at Fuk Hang Tsuen Road CDA was also found to exceed the noise criteria of 70dB(A). As the site area was just about 55 m away from the mainline of DBL at the nearest, therefore the total building height is already restricted to 45 mPD in the planning conditions posed by Planning Department.

Between Castle Peak Road and Route 10

3.4.2.7 Existing NSRs (NSRs E5, E12 and E13) near Tsoi Yuen Tsuen and YLH are two or three storeys high village houses or squatter houses (1 storey), whereas NSR E4 is the Lam Tei Gospel School (a primary school). The predicted noise levels ranged from 64-79dB(A).

3.4.2.8 Noise level exceedances of 70dB(A) were found at the NSRs close to the ramps of DBL and the existing Yuen Long Highway. The source of exceedances of these NSRs was mainly from the traffic on Yuen Long Highway and the ramps of DBL.

DBL mainline with Ramp H  joining Yuen Long Highway

3.4.2.9 Existing NSRs (NSRs E1 Lo Fung Hang and E3 near Route 10 portal) are two or three storeys high village houses or squatter houses, whereas NSR E2 is a temple, Nam On Fat Tong. Since Yuen Long Highway is an elevated structure, exceedance of noise levels at lower floor levels was not predicted but higher floor levels. Noise exceedances of 1 to 5 dB(A) were predicted.

3.4.2.10 The source of exceedances of noise level of 70dB(A) was mainly due to the high traffic flow of Yuen Long Highway. Partial traffic noise was from Ramp H joining the Yuen Long Highway with traffic flow of about 600 veh/hr.

Ramps A, B, C and D of DBL joining to Yuen Long Highway

3.4.2.11 Existing NSRs (NSRs E6 near Shun Tat Street, E18 near HSKNDA Area 3B and E19 Tan Kwai Tsuen) are two or three storeys high village houses or squatter houses, whereas NSR E20 is a school, Ying Yin School. The predicted noise levels ranged from 69-82dB(A).

3.4.2.12 Traffic from Ramps A, B, C and D and Yuen Long Highway is the major source of noise exceedance. The new road of Hung Shui Kiu area near Ramp C has minor contribution to noise exceedance.

3.4.3 Hung Shui Kiu New Development Area

3.4.3.1 At this stage, the Hung Shui Kiu New Development Area is undergoing planning study and there is no firm layout for use in this environmental impact assessment. A 2-tier approach is proposed to assess the noise impacts from DBL on sensitive uses in HSKNDA:

(a) calculation of noise impact at lot boundary of sensitive uses in HSKNDA, with direct at source mitigation measures in place in DBL;

(b) where exceedances are found, calculation of the minimum buffer distances between lot boundary of sensitive uses in HSKNDA and DBL required for reducing the residual impact to within the EIAO-TM.

3.4.3.2 In addition to the original layout, an alternative layout was provided by HSKNDA project team for testing in this EIA report.

3.4.3.3 For the purpose of comparison with relevant standards, the noise levels at assessment points (APs) should be applied. The summary for noise levels predicted at assessment points at site boundaries and typical school layouts are given in Table 3.18 and the detail results are given in Appendix 3B. Exceedances of EIAO-TM standards were found caused by both DBL and HSKNDA planned roads.

3.4.4 Noise from the Proposed Helipad

3.4.4.1 A helipad is proposed near Ha Tsuen Interchange for emergency uses. There would be no routine flight expected. Figure 3.3 shows the location of the helipad and it is observed that there are no existing NSRs identified within 300 m. The future landuse zoning is likely to be "green belt" and "recreational" and hence there would be no NSRs in the future. Based on the data from other previous monitoring at Tamar Basin, it was estimated that the maximum noise levels (Lmax) during take-off (measured at 25 m) were about 100 dB(A) for helicopter type Sikorsky S76 and Black Hawk S70. The highest recorded levels were noted to occur during take-off. To meet the HKPSG noise standard of 85 dB(A) Lmax, a setback of 200 m from the nearest NSR is required. In this case, without any NSRs located within 300 m, the proposed helipad location should not have any adverse impact.

3.5 Mitigation of Adverse Impacts

3.5.1 Construction Phase

3.5.1.1 The predicted noise levels showed that construction noise activities are likely to give rise to adverse daytime noise impacts at some of the identified NSRs. Mitigation measures are therefore required and the following forms of mitigation have been considered:

Use of Quiet Plant and Working Methods

3.5.1.2 The use of quiet plant was identified to be a feasible solution to tackle the adverse impacts associated with construction works. The Contractor should obtain particular models of plant that are quieter than standard types given in the GW-TM. The benefits achievable in this way would depend on the details of the Contractors' chosen methods of working, and it would be too restrictive to specify that a Contractor has to use specific items of plant for the construction operations. It is therefore both preferable and practical to specify an overall plant noise performance specification to apply to the total SWL of all plant on the site so that the Contractor is allowed some flexibility to select plant items to suit his needs. It should be noted that various types of silenced equipment could be found in Hong Kong. However, the Authority, when processing a CNP application, will apply the noise levels contained in the relevant statutory TMs unless the noise emission of a particular piece of equipment can be validated by a certificate or through a demonstration.

3.5.1.3 Quiet PME is defined as PME whose actual SWL is less than the value specified in the GW-TM for the same item of plant. Reference can be made to the British Standard BS5228: Part 1:1997 Control on Construction and Open Sites.

Using Temporary and Movable Noise Barriers

3.5.1.4 Movable barriers that can be located close to noisy plant can be very effective at screening NSRs from particular items of plant or noisy operations. Movable barriers of 3 to 5 m height with a small cantilevered upper portion and skid footing can be located within a few metres of stationary plant and within about 5 m or more of a mobile equipment such as an excavator and mobile crane etc., such that the line of slight to the NSR is blocked by the barriers. It would be possible for the Contractor to provide purpose-built noise barriers or screens constructed of appropriate material (minimum superficial density of 7 kg/m2) located close to operating PME, in order to reduce the noise impact to the surrounding sensitive uses. Certain types of PME, such as generators and compressors, can be completely screened by portable barriers giving a total noise reduction of 10 dB(A) or more.

3.5.1.5 For this assessment, it was estimated that movable noise barriers can achieve a 10 dB(A) noise reduction for stationary plant and 5 dB(A) for movable plant.

Reducing the Numbers of Plants Operating in Critical Areas Close to NSRs

3.5.1.6 In general the number of plant should be left to the choice of the Contractor so that in combination with the selection of quiet plant, any further reduction in the total plant noise level, or the site specific maximum sound power levels, as described above, can be achieved. It would be appropriate to restrict the number of operating PME within certain parts of the site that are very close to the NSRs in order to reduce the level of noise impacts. This method could be more effective for activities associated with foundation work, pile construction and excavation activities in which a large number of PME are anticipated, but not all of them would be utilised at the same time.

Using Noise Screening Structures or Purpose-built Noise Barriers along the Site Boundary

3.5.1.7 Considering the low-lying nature of surrounding NSRs (typically village houses or temporary houses), it would be effective to have noise screening structures along the site boundary to protect NSRs close to the construction site boundary. The following measures could be applied to reduce the construction noise:

i) Site buildings such as office and stores could be grouped together to form a substantial barrier separating site operations and nearby noise sensitive premises. This may be applicable for sites such as Lam Tei Interchange area and other work sites.

ii) Stacks of certain materials such as bricks, aggregate, timber or top soil can be strategically placed to form a barrier. This may be applicable for construction of road alignment.

iii) For adverse cases, purpose-built noise barriers or screens could be placed along the site boundary. This may be applicable for road alignment sites.

3.5.1.8 An estimate of about 10dB(A) reduction could be achieved for substantial structures or purpose-built noise barrier/screen. Higher reduction and benefit could also be achieved for NSRs close to the site.

Good Site Practice

3.5.1.9 The following good site practice should be adopted during the construction phase:

Proposed Specific Construction Noise Mitigation Measures

3.5.1.10 The proposed mitigation measures for construction noise are arranged in an increasing level of efforts. Since the actual activities in the construction sites may vary at local site level, the level of mitigation measures adopted should also be determined with reference to the findings of the EM&A programme.

3.5.1.11 The number of PME used on site should be reviewed from time to time to avoid excessive or dummy PME located too close to NSRs. Good site practice should be followed through the construction phase.

3.5.1.12 Noise sensitive receivers were affected by both fixed construction sites (precasting yards, concrete batching plant and work sites) and alignment construction for the carriageways. Two main causes for noise exceedance were identified:

i) NSRs are too close to the construction sites, particularly for those along the road alignment
ii) Construction of foundation was noisy but short-term

3.5.1.13 To minimize the potential of adverse impact, the following measures are specifically recommended to be adopted for DBL:

i) Purpose-built construction site hoardings are to be installed in such a way to act as an acoustic screen/noise barrier for active carriageway construction work proximity to NSRs in locations shown in Figure 3.20(A, B). The boundary wall or hoarding shall:

The exact location of purpose-built construction site hoarding would be subject to local site conditions. Temporary noise barriers should be placed close to the noisy mechanical equipment in case the purpose-built site hoarding could not effectively screen the NSRs.

ii) Quiet plant/power mechanical equipment of sound power level lowered than those listed in Table 3 of the GW-TM shall be used for all construction sites as far as practicable.

3.5.1.14 Considering the NSRs close to the construction site boundaries (within 30m) are low-rise housings (typically 1 storey in height), their sensitive facades could be screened by a 3m high purpose-built site hoarding for viewing the ground-level construction equipment (both moving and stationary). A 10 dB(A) reduction was assumed in this regard since it would be able to screen both stationary and mobile equipment along the other side of the hoarding. For construction superstructure or other elevated works, the effect would be less and it was assumed nil reduction in this case. The purpose-built site hoarding should be erected until the completion of structural work or the time no longer having noisy work. The effectiveness is illustrated in Figure 3.21 and the site hoarding should be erected and adjusted in any case to protect the nearby NSRs.

3.5.1.15 Table 3.10 summarizes the specific mitigation measures proposed for construction activities. Table 3.11 presents the summary of results.

Table 3.10 Proposed Specific Construction Noise Mitigation Measures

Construction Site

Proposed Mitigation Measures

All sites

Use of quiet equipment/plant

Locations and extent as indicated in Figure 3.20

Purpose-built boundary wall/site hoarding


3.5.1.16 Cumulative construction impacts were assessed for likely concurrent projects in the area. Based on the available information, it was understood that construction activities of Hung Shui Kiu NDA development, Yuen Long Highway Widening and Route 10 Northern Section were likely coincided with the construction schedule of DBL. Since construction work is likely controlled by actual construction progress and respective construction schedule, the assessment had been carried out based on some worst estimates and worst NSRs.

3.5.1.17 NSRs near Tsing Chuen Wai and Castle Peak road are likely affected by both HSKNDA and DBL construction activities. Based on the worst affected assessment point 8327 (NSR E15), it was found that the overall noise level would be around 72dB(A) with DBL being the main source of construction noise. The level is within the acceptable noise limit of 75dB(A) with mitigation measures in place.

3.5.1.18 NSRs near the portal of Route 10 were also assessed as represented by assessment points 76 (NSR E3 near Route 10 portal ) and 8801 (NSR E4 Lam Tei Gospel School). Cumulative noise levels are 72-73 dB(A) for both NSRs and NSR E3 is found within the noise limit of 75 dB(A). For Lam Tei Gospel School (E4 8801), it requires further mitigation measures in order to meet the noise limits (70 and 65 dB(A)) as indicated in Table 3.12.

3.5.1.19 Cumulative impacts with SWC have been assessed with the APs of NSR E24 Ngau Hom Shek and presented in the results shown in Table 3.10. No exceedances were found.

3.5.1.20 With only the mitigation measures proposed in Table 3.10, some of the NSRs still exceeded the noise criteria from 1 to 4 dB(A). It is found that these NSRs are too close to the construction work. As present in Table 3.11, the four NSRs found to have residual impacts are E4 AP8801 Lam Tei Gospel School (residual impact of 3 dB during normal school date and 8 dB during examination period), E8 AP8414 Fuk Hang Tsuen village house (residual impact of 1 dB, representing about 2 dwellings), E12 AP43 Rural /village houses near Tsoi Yuen Tsuen (residual impact of 1 dB, representing 5 dwellings) and E13 AP8605 village house in Tsoi Yuen Tsuen (residual impact of 4 dB, representing about 6 dwellings). The duration is expected to be around 5 weeks during the pile and pile cap construction.

3.5.1.21 The residual impact could be reduced by special measures which are summarized in Table 3.12. For NSRs E4, E8 and E12, the residual impacts could be reduced to relevant limits by special measures. Only NSR E13 would be subject to residual impact of 4dB for a duration of about 5 week during non-restricted hours i.e. normal daytime (0700-1900) at intermittent worst periods under the current programme.

3.5.1.22 For E4 Lam Tei Gospel School, early liaison with the school for the planned examination periods is recommended to plan for the construction work. Noisy piling and pile cap construction should be avoided.

3.5.1.23 The special measures require the reduction of the number of concurrent bridge pier constructions. The applicability of special measures should be reviewed during the construction phase by the Contractor as a part of the EM&A process. A construction noise mitigation proposal is required to be submitted by the contractor for the reviewed by ET and approval by IEC.

3.5.1.24 Calculations of the predicted noise level with proposed specific measures are detailed in Appendix 3A2.5.


3.5.1.25 The construction plant inventory assumed for this assessment was confirmed by the project proponent HyD as practicable and reasonable for the completion of the project within the scheduled construction programme based on the information available at this stage.

3.5.1.26 A detailed review of the construction noise assessment is recommended prior to the construction work commencement during the construction stage to re-conform the requirements for construction noise mitigation. The review should be carried out by the Construction Contractor and the Environmental Team using contemporary information regarding construction equipment and construction programme.

Table 3.11 Summary of Potential Cumulative Construction Noise Impacts

NSR

AP

Acceptable Noise Levels (dB(A))

Source of Construction Noise

Predicted Noise Levels Worst-case (dB)

Residual impact and its source

Unmitigated

Mitigated

E1 – Lo Fung Hang

6

75

  • From DBL alignment construction
  • From YLH widening

79

65

Not expected

E2 – Nam On Fat Tong

8504

75

  • Mainly from DBL alignment construction

74

61

Not expected

E3 – Rural/village houses near Route 10 portal

76

75

  • From DBL alignment construction
  • From YLH widening

86

73

Not expected

E4 – Lam Tei Gospel School

10

(8801)

70/65

  • From DBL alignment construction
  • From Lam Tei Interchange Work Sites
  • From YLH widening

86

72

(refer to Table 3.12)

Residual impact of 3 dB likely for NSRs close to the alignment site. The source of noise is mainly due to construction of piles and piers. The construction of pile could be limited to one at a time instead of three working concurrently.

It is proposed to conduct piling and pier construction work during schools holidays in summer periods.

It is also proposed to liaise with the school for proper arrangement of construction work avoiding noisy activities during examination period.

Please refer to Table 3.12 to deal with the impact.

E5 – Rural/village houses near Lam Tei Gospel School

8804

75

  • From DBL alignment construction
  • From Lam Tei Interchange Work Sites

82

68

Not expected

E6 – Rural/village houses near Shun Tat Street

82

75

  • From DBL alignment construction
  • From YLH widening

86

73

Not expected

94

75

  • From DBL alignment construction
  • From YLH widening

83

67

Not expected

E6 – Rural/village houses near Shun Tat Street

8808

75

  • From DBL alignment construction
  • From YLH widening

88

75

Not expected

E7 – Botania Villa

8425

75

  • Mainly from DBL alignment construction

78

65

Not expected

E8 – Fuk Hang Tsuen village

40

75

  • From DBL alignment construction
  • From YLH widening

85

67

Not expected

42

75

  • From DBL alignment construction
  • From Lam Tei Interchange Work Sites

83

69

Not expected

8414

75

  • From DBL alignment construction
  • From Lam Tei Interchange Work Sites

88

76

(refer to Table 3.12)

Residual impact of 1 dB likely for NSRs close to the alignment site.

Please refer to Table 3.12 to deal with the impact.

8427

75

  • From DBL alignment construction
  • From YLH widening

79

66

Not expected

E9 – Tuen Mun San Tsuen

8407

75

  • Mainly from DBL alignment construction

74

61

Not expected

E10 – Madam Lau Kam Lung Secondary School of Miu Fat Buddhist

8405

70/65

  • Mainly from DBL alignment construction

77

65

Not expected

E11 – Miu Fat Buddhist Monastery

8432

75

  • Mainly from DBL alignment construction

75

62

Not expected

E12 – Rural/village houses near Tsoi Yuen Tsuen

43

75

  • From DBL alignment construction
  • From Lam Tei Interchange Work Sites

88

76

(refer to Table 3.12)

Residual impact of 1 dB likely for NSRs close to the alignment site.

Please refer to Table 3.12 to deal with the impact.

44

75

  • From DBL alignment construction
  • From Lam Tei Interchange Work Sites

85

72

Not expected

E12 – Rural/village houses near Tsoi Yuen Tsuen

45

75

  • From DBL alignment construction
  • From Lam Tei Interchange Work Sites
  • From YLH widening

85

72

Not expected

E13 – Tsoi Yuen Tsuen

8601

75

  • From DBL alignment construction

80

68

Not expected

8602

75

  • From DBL alignment construction

83

71

Not expected

8603

75

  • From DBL alignment construction

87

75

Not expected

8605

75

  • From DBL alignment construction
  • From Lam Tei Interchange Work Sites

91

79

(refer to Table 3.12)

Residual impact of 4 dB likely for NSRs close to the alignment site.

Please refer to Table 3.12 to deal with the impact.

E14 – Tsing Chuen Wai

8329

75

  • Mainly from DBL alignment construction

76

64

Not expected

E15 – Rural/village houses north to Tsing Tsuen Wai

8302

75

  • From DBL alignment construction
  • From work sites near HSK-NDA Area

82

70

Not expected

8323

75

  • Mainly from DBL alignment construction

85

73

Not expected

8327

75

  • Mainly from DBL alignment construction

84

72

Not expected

E16 – Nai Wai

8613

75

  • Mainly from DBL alignment construction

73

60

Not expected

E18 – Rural/village houses near future Area 3B

8704

75

  • Mainly from DBL alignment construction

76

64

Not expected

E19 – Tan Kwai Tsuen

96

75

  • Mainly from DBL alignment construction
  • From YLH widening

85

70

Not expected

8724

75

  • Mainly from DBL alignment construction
  • From YLH widening

83

64

Not expected

E20 – Ying Yin School

8725

70/65

  • Mainly from DBL alignment construction

72

59

Not expected

E22 – San Sang San Tsuen

8201

70

  • Mainly from DBL alignment construction

69

56

Not expected

E24 – Rural/village houses near Ngau Hom Shek

8004

75

  • Mainly from DBL alignment construction

73

67

Not expected

8010

75

  • Mainly from DBL alignment construction

81

72

Not expected

8016

75

  • Mainly from DBL alignment construction

83

70

Not expected

8025

75

  • Mainly from DBL alignment construction

74

69

Not expected

E25 – Fu Tai Estate

8918

75

  • Mainly from DBL alignment construction

70

57

Not expected

 

Table 3.12 Summary of Special Measures for Affected NSRs

NSR

AP

Special Measures for Affected NSRs

E4 – Lam Tei Gospel School

10 (8801)

The number of operating piling machine should be limited as far as possible in order to achieve the 70 dB(A) and 65 dB(A) during examination periods for this school NSR.

Based on the prediction results, it is recommended that the noise one piling and pile cap construction for one pier at a time for distance within 85m from the school should be followed. The contractor is required to submit a construction noise mitigation proposal to reduce the noise levels by either limit the number of operating piling machine or keep the overall noise level at Lam Tei Gospel School to within 70 dB. Alternative approach could be acceptable with justification.

It is proposed in parallel to liaise with the school for proper arrangement of construction work avoiding noisy activities during examination period and try to arrange the piling work within 60m during school holidays.

E8 – Fuk Hang Tsuen village

8414

The number of operating piling machine should be limited as far as possible in order to achieve 75 dB(A).

Based on the prediction results, the exceedance was found caused by the cumulative effects of three closest pair of piers. Other piers could be worked according to the original schedule. It is recommended that only the one pier should be working at one time within 55m of E8. The contractor is required to submit a construction noise mitigation proposal to reduce the noise levels by either limit the number of operating piling machine or keep the overall noise level to within 75 dB. Alternative approach could be acceptable with justification.

E12 Rural/village houses near Tsoi Yuen Tsuen

43

The number of operating piling machine should be limited as far as possible in order to achieve 75 dB(A).

Based on the prediction results, the exceedance was found caused by the cumulative effects of three closest pair of piers. Other piers could be worked according to the original schedule. It is recommended that only the one pier should be working at one time within 48m of E12. The contractor is required to submit a construction noise mitigation proposal to reduce the noise levels by either limit the number of operating piling machine or keep the overall noise level to within 75 dB. Alternative approach could be acceptable with justification.

E13 – Tsoi Yuen Tsuen

8603, 8605

The number of operating piling machine should be limited as far as possible in order to achieve 75 dB(A).

Based on the prediction results, the exceedance was found caused by the one pair of piers which is about 21m. There is likely residual impact of about 4 dB for a during of 5 weeks during piling and pile cap construction. Other piers could be worked according to the original schedule.

It is recommended that one pier should be working at one time within 47m of E13. The contractor is required to submit a construction noise mitigation proposal to reduce the noise levels by either limit the number of operating piling machine or keep the overall noise level to within 75 dB. Alternative approach could be acceptable with justification.

3.5.2 Operational Phase

Road Traffic Noise

3.5.2.1 Noise mitigation measures in form of barriers are proposed to build on the DBL in order to reduce excessive noise on various existing and future sensitive receivers. All NSRs are predicted to be within EIAO standards.

3.5.2.2 Details of proposed noise barriers are shown in Figure 3.2 and are summarized in Table 3.13 respectively. These noise barriers shall be designed and constructed to comply with the Guidelines On Design of Noise Barriers - Environmental Protection Department & Highways Department of the Government of the Hong Kong SAR, First Issue March, 2001. The setup for typical type of proposed noise barriers is given in Figures 10.6.3.6 and 10.6.3.7.

3.5.2.3 Some proposed mitigation measures of the Yuen Long Highway Widening were applied in this assessment with reference to the Final Environmental Impact Assessment Report - Widening of Yuen Long Highway between Lam Tei and Shap Pat Heung Interchange Preliminary Design and Ground Investigation Assignment exhibited under EIAO. This would ensure that the peak traffic flow within 15 years from YLH Dual-3 scenario was mitigated. For the recommended noise barriers on DBL in the YLH EIA Report, this DBL EIA has carried out assessment using the worst-case scenario of DBL as mentioned in Sections 3.3.2.4 to 3.3.2.8 which is considered more appropriate and realistic for DBL EIA. While assuming that the barriers on YLH will be implemented as agreed in its exhibited EIA report, this DBL EIA assessed, formulated and optimized the barriers on DBL in accordance with EIAO-TM. The may be some difference between the barriers shown in the YLH EIA on DBL alignment but in any case the NSRs are mitigated to a worst-case scenario in this DBL EIA.

3.5.2.4 Low noise surfacing will be adopted as the standard measures of HyD's guidelines for the roads with vehicle speed limit greater than 70km/hr for DBL. All proposed low noise surfacing should be designed according to the design guidelines/practice notes issued by HyD Guidance Note No. RD/GN/010A and RD/GN/011B. The traffic noise assessment has assumed that low noise road surfacing materials would be provided to the Deep Bay Link.

Table 3.13 Summary of Proposed Noise Mitigation Measures Implemented by DBL

Mitigation Measure

Location

Type

Chainage Number

Approx. Length

Implementation Stage (Des/C/O/Dec*)

Implementation Agent

Cantilever Barrier DBL1

Section of DBL mainline (SB)

Cantilever barrier (5.5m vertical plus 2.2m extension)

2+518 ~ 3+145

627m

Des

O

HyD

Cantilever Barrier DBL2

Section of DBL mainline (Central divider) near HSK Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

2+525 ~ 3+145

628m

Des

O

HyD

Barrier DBL4

Section of DBL mainline (NB) near HSK Interchange

3m vertical barrier

3+969 ~ 4+657

688m

Des

O

HyD

Barrier DBL5

Central divider (section of DBL mainline from HSK Interchange to Ramp K

5m vertical barrier

3+859 ~ 4+765

906m

Des

O

HyD

Cantilever Barrier DBL6

Section of DBL mainline (SB) near HSK Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

3+969 ~ 4+583

614m

Des

O

HyD

Barrier DBL7

Mainline of DBL (SB) in the section between Ramp M & Ramp K of HSK Interchange

3m vertical barrier

4+583 ~ 5+012

429m

Des

O

HyD

Cantilever Barrier

DBL8

Ramp B of Lam Tei Interchange connecting DBL mainline (NB)

Cantilever barrier (5.5m vertical plus 2.2m extension)

4+750 ~ 5+269

519m

Des

O

HyD

Barrier DBL9

Mainline of DBL (NB) connecting Ramp K

Cantilever barrier (5.5m vertical plus 2.2m extension)

5+110 ~ 5+740

640m

Des

O

HyD

Cantilever Barrier

DBL11

Mainline of DBL (central divider) in the section north of Ramp D of Lam Tei Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

4+765 ~ 5+842

1077m

Des

O

HyD

Barrier DBL12

Mainline of DBL (NB) in the section at Lam Tei Interchange

3m vertical barrier

4+655 ~ 4+750

95m

Des

O

HyD

Barrier DBL13

Mainline of DBL (SB) in the section connecting Ramp H of Lam Tei Interchange

3m vertical barrier

5+027 ~ 5+511

484m

Des

O

HyD

Semi-enclosure DBL14

Near Area 2B of

HSKNDA

Semi-enclosure with enclosure side facing NSKNDA

3+145 ~ 3+345

200m

Des

O

HyD

Cantilever Barrier DBL15

Mainline of DBL (SB) connecting to HSK Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

3+345 ~ 3+851

506m

Des

O

HyD

Cantilever Barrier DBL16

Mainline of DBL (SB central divider)

Cantilever barrier (5.5m vertical plus 2.2m extension)

3+345~ 3+851

506m

Des

O

HyD

Cantilever Barrier

LT1

Ramp C of Lam Tei Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

2+200 ~ 2+844

644m

Des

O

HyD

Barrier LT2

Ramp D of Lam Tei Interchange

3m vertical barrier

2+400 ~ 2+600

217m

Des

O

HyD

Barrier LT3

Ramp D of Lam Tei Interchange

5m vertical barrier

2+600 ~ 2+800

249m

Des

O

HyD

Cantilever Barrier LT4

Ramp A of Lam Tei Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

2+500 ~ 2+920

366m

Des

O

HyD

Barrier LT5

Ramp A of Lam Tei Interchange

5m vertical barrier

2+190 ~ 2+550

365m

Des

O

HyD

Barrier LT8

Ramp H of Lam Tei Interchange

3m vertical barrier

1+760 ~ 2+008

248m

Des

O

HyD

Cantilever Barrier LT9

Ramp D of Lam Tei Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

5+460 ~ 5+760

315m

Des

O

HyD

Cantilever Barrier LT10

Ramp G of Lam Tei Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

2+033 ~ 2+283

250m

Des

O

HyD

Cantilever Barrier LT11

Ramp D of Lam Tei Interchange

Cantilever barrier (5.5m vertical plus 2.5m extension)

2+931~ 3+085

154m

Des

O

HyD

Barrier YLH1

Ramp C of Lam Tie Interchange

5m vertical barrier

2+844 ~ 3+081

237m

Des

O

HyD

Barrier YLH2B

Ramp C of Lam Tei Interchange connecting to Yuen Long Highway

Cantilever barrier (5.5m vertical plus 2.5m extension)

3+081~ 3+300

223m

Des

O

HyD

Barrier YLH14

Yuen Long Highway, south of Lam Tei Interchange

6m vertical barrier

3+325~ 3+445

120m

Des

O

HyD

(1): All proposed low noise surfacing should be designed according to the design guidelines/practice notes issued by HyD Guidance Note No. RD/GN/010A.

(2): * Des/C/O/Dec: Design/Construction/Operation/Decommissioning;

HyD: Highways Department.

 

Table 3.14 Summary of Noise Barriers on YLH Useful for DBL Within the Study Area

Mitigation Measure

Location

Type

Summary of Noise Barriers adopted from YLH EIA Report Useful for DBL (assumed dual-3-lanes)

Cantilever BarrierYLH2A

Yuen Long Highway

Cantilever barrier (5.5m vertical plus 2.5m extension)

Barrier YLH3

Yuen Long Highway

5m vertical barrier

Barrier YLH4

Yuen Long Highway

6m vertical barrier

Cantilever Barrier YLH5

Yuen Long Highway

Cantilever barrier (5.5m vertical plus 2.5m extension)

Barrier YLH6

Yuen Long Highway

3m vertical barrier

Cantilever Barrier YLH7

Yuen Long Highway

4m vertical barrier

Barrier YLH8

Yuen Long Highway

6m vertical barrier

Cantilever Barrier YLH9

Yuen Long Highway

Cantilever barrier (5.5m vertical plus 2.5m extension)

Barrier YLH10

Yuen Long Highway

6m vertical barrier

Barrier YLH11

Yuen Long Highway

3m vertical barrier

Barrier YLH12

Yuen Long Highway

5m vertical barrier

Cantilever Barrier YLH13

Yuen Long Highway

Cantilever barrier (5.5m vertical plus 2.5m extension)

Barrier YLH15

Yuen Long Highway

5m vertical barrier

Barrier YLH16

Yuen Long Highway

5m vertical barrier

Barrier YLH17

Yuen Long Highway

4m vertical barrier

Barrier YLH18

Yuen Long Highway

4m vertical barrier

Barrier YLH19

Yuen Long Highway

Cantilever barrier (5.5m vertical plus 2.5m extension)

Barrier YLH20

Yuen Long Highway

5m vertical barrier

Barrier YLH21

Yuen Long Highway

5m vertical barrier

Summary of Additional Noise Barriers Likely Required for Dual-4 Configuration of YLH (assumed dual-4-lanes)

Barrier YLH4-1

Dual-4 Yuen Long Highway

4m vertical barrier on central divider

Barrier YLH4-2

Dual-4 Yuen Long Highway

5m vertical barrier on central divider

Barrier YLH4-4

Dual-4 Yuen Long Highway

4m vertical barrier on central divider

Remarks:

These noise barriers are to be implemented by Yuen Long Highway Widening Project as recommended in its EIA Report exhibited under EIAO.

For details, please refer to "Widening of Yuen Long Highway between Lam Tei and Shap Pat Heung Interchange Preliminary Design and Ground Investigation Assignment, Final Environmental Impact Assessment Report - December 2001"

For barriers recommended for Dual-4 configuration of Yuen Long Highway, it is recommended here for future EIA for YLH widening to dual-4 consideration by the project proponent HyD.

 

Table 3.15 Summary of Noise Barriers to be Considered by Future HSKNDA Project

Mitigation Measure

Location

Type

Approx. Length

Barrier DBL3

Road P1 of HSKNDA

5m vertical barrier

1169m

Cantilever Barrier LT6

Ramp K1 of Lam Tei Interchange

5m vertical barrier

319m

Cantilever Barrier LT7

Ramp K of Lam Tei Interchange

Cantilever barrier (5.5m vertical plus 2.2m extension)

302m

Barrier NDA2

Road P1 of HSKNDA

2m vertical barrier

610m

Remarks:

These noise barriers were agreed to be considered by HSKNDA Project by the Territory Development Department.

 

Table 3.16 Summary of Traffic Noise Impacts on Existing NSRs for Unmitigated and Mitigated Scenarios

NSR

Assessment Points

Acceptable Noise Levels (dB(A))

Noise Levels under Unmitigated Scenario (dB)

Noise Levels under Mitigated Scenario (dB)

Residual impact and its source

E1 – Lo Fung Hang

8505-8508

70

65-75

60-64

Not expected

E2 – Nam On Fat Tong

8504

65

66

62

Not expected

E3 – Rural/village houses near Route 10 portal

8501-8503, 165, 166

70

67-72

63-69

Not expected

E4 – Lam Tei Gospel School

8801

65

73

65

Not expected

E5 – Rural/village houses near Lam Tei Gospel School

8802-8807, 8809

70

68-79

64-70

Not expected

E6 – Rural/village houses near Shun Tat Street

8808, 8810-8816, 164

70

71-82

63-70

Not expected

E7 – Botania Villa

8423-8425

70

66-72

62-69

Not expected

E8 – Fuk Hang Tsuen

8403, 8413-8422, 8427-8431

70

67-79

59-72

~2 dB, dominating noise source is from the existing Castle Peak Road, DBL contribution 0.2 dB at 8403

E9 – Tuen Mun San Tsuen

8407, 8409, 155

70

62-68

59-68

Not expected

E10 – Madam Lau Kam Lung Secondary School of Miu Fat Buddhist

8404-8406

65

67-74

64-74

~8-9 dB, dominating noise source is from the existing Castle Peak Road, DBL contribution 0.4 dB at 8404 & 8406

E11 – Miu Fat Buddhist Monastery

8432

65

73-74

73-74

~8-9 dB, dominating noise source is from the existing Castle Peak Road, DBL contribution 0.1 dB.

E12 – Rural/village houses near Tsoi Yuen Tsuen

8616-8625, 156, 158, 159

70

64-75

58-70

Not expected

E13 – Tsoi Yuen Tsuen

8601-8611, 8614, 8615

70

68-74

66-74

~1-4 dB, dominating noise source is from the existing Castle Peak Road, DBL contribution 0.3 dB at 8607 & 8611

E14 – Tsing Chuen Wai

8329, 8330, 8336

70

66-69

63-66

Not expected

E15 – Rural/village houses north to Tsing Chuen Wai

8301-8308, 8320, 8323-8328, 8331-8335, 8338

70

65-74

62-73

~1-3 dB, dominating noise source is from the existing Castle Peak Road, DBL contribution 0.3 dB at 8332 & 8333

E16 – Nai Wai

8613

70

68

67

Not expected

E18 – Rural/village houses near future Area 3B

8701-8707, 160, 153, 154, 157, 170

70

66-80

64-69

Not expected

E19 – Tan Kwai Tsuen

8710, 8714, 8717, 8720, 8723, 8724, 172

70

68-82

64-69

Not expected

E20 – Ying Yin School

8725, 162

65

69-70

64-65

Not expected

E22 – San Sang San Tsuen

8201

70

71-72

67-68

Not expected

E24 – Rural/village houses near Ngau Hom Shek

8001-8006, 8008-8010, 8016-8031

70

65-70

65-70

Not expected

E25 – Fu Tai Estate

8914, 8915, 8918

70

65-72

60-67

Not expected

 

Table 3.17 Summary of Predicted Traffic Noise Impacts on Future NSRs for Unmitigated and Mitigated Scenarios

NSR

Assessment Points

Acceptable Noise Levels (dB(A))

Noise Levels under Unmitigated Scenario (dB)#

Noise Levels under Mitigated

(dB)#

Residual impact and its source

F1A - Fuk Hang Tsuen Road CDA (A/DPA/TM-LTYY/110)

9501-9507

70

67-78

62-70

Not expected

F1B - A/DPA/TM-LTYY/111

9201-9210, 9901-9912

70

68-81

58-70

Not expected

F1C - A/YL-TYST/14

9211-9217, E1, E2

70

66-76

63-69

Not expected

F1D - A/TM-LTYY/012

9921

70

73-76

63-66

Not expected

Note: # Assessment Point at site boundary

 

Table 3.18 Summary of Predicted Traffic Noise Impacts on HSKNDA NSRs for Unmitigated and Mitigated Scenarios

NSR

Assessment Points

Acceptable Noise Levels (dB(A))

Noise Levels under Unmitigated (dB)

Noise Levels under Mitigated (dB)

 

Residual impact and its source

Hung Shui Kiu New Development Area – Original Layout

Assessment Points at Site Boundary

F9 – Area 3C (RR2)

9231, 9233, O1

70

69-77

67-73

(with mitigation measures from YLH widening dual-3)

Not expected provided that with additional measures for the potential YLH further widening to dual-4, the noise level would be 60-70 dB(A)

F2 – Area 1C school sites

9010-9012

65

65-71

55-61

Not expected

F3 – Area 2A R1(RS/HOS/PSPS)

9312-9317

70

68-76

60-69

Not expected

F4 – Area 2B R1

9307-9311

70

68-77

60-70

Not expected

F5 – Area 2B school sites

9005-9009

65

66-77

58-67

2 dB at site boundary, testing should be carried out typical school facade to account for self-screening effect(see below)

F6 – Area 2C R2(QTRS)

9304-9306

70

68-78

64-70

Not expected

F7 – Area 2D R2(PSPS)

9301-9303

70

66-73

61-70

Not expected

F8 – Area 2D school sites

9002-9004

65

68-72

60-64

Not expected

Assessment Points at a typical school facades

F5 – Area 2B school sites

9005-9009

65

64-74

56-64

Not expected

Hung Shui Kiu New Development Area – Alternative Layout

Assessment Points at Site Boundary

Area 2C R2 to school sites

8001-8005

65

67-75

59-67

2 dB at site boundary, testing should be carried out typical school facade to account for self-screening effect (see below)

Area 2B School layout changes

8012-8017

65

68-77

58-68

3 dB at site boundary, testing should be carried out typical school facade to account for self-screening effect (see below)

Area 2D school sites to residential Site

9006-9008

70

68-74

61-66

Not expected

Area 1C school site change location

8018-8023

65

68-75

55-65

Not expected

 

Assessment Points at a typical school facades

Area 2C R2 to school sites

9105-9105

65

65-73

54-65

Not expected

Area 2B School layout changes

9108-9113

65

58-76

51-65

Not expected

Note: Details results for both Assessment Points at site boundary and using typical school layout for both unmitigated and mitigated scenarios are shown in Appendix 3B.

 

Table 3.19 Summary of Mitigation Measures and Constraints for HSKNDA

Mitigation Measure/Constraints

Noise Barrier

Location

Type

Approx. Length

Barrier DBL3

Road P1

5m vertical barrier

1170m

Barrier NDA2

Road P1

2m vertical barrier

610m

Cantilever Barrier LT6

Ramp K1

5m vertical barrier

320m

Cantilever Barrier LT7

Ramp K

Cantilever barrier (5.5m vertical plus 2.2m extension)

300m

Hung Shui Kiu New Development Area – Original Layout

Area 2B school sites

Using school layout or facade orientation similar to Figure 3.32 for Area 2B School sites or similar setback

Hung Shui Kiu New Development Area – Alternative Layout

Area 2C school sites

Area 2B school sites

Using school layout or facade orientation similar to Figure 3.32 for Area 2B School sites or similar setback

Uncertainty and likely Changes

It is understood that HSKNDA is undergoing planning study, it is likely that

  • population accommodation may change
  • traffic flow forecast may change due to future update information
  • landuse pattern may change

Therefore, the above are only suggestions for consideration during the design of HSKNDA. The validity of the predicted impact in this report and the suggested measures/constraints are recommended to be reviewed in the future study of HSKNDA by TDD.

Existing noise sensitive receivers

3.5.2.5 Table 3.16 summarizes the traffic noise impacts under unmitigated and mitigated scenarios for the existing sensitive receivers. With the proposed direct mitigation measures in place, noise levels would be reduced to within EIAO-TM standard except for a few existing sensitive receivers which are currently affected by existing roads.

3.5.2.6 Noise levels at NSR E10 and E11 (Madam Lau Kam Lung Secondary School and Miu Fat Buddhist Monastery) still exceeded the noise standard by 8 to 9dB(A) after mitigation. The source of exceedance is found solely due to the traffic noise of the existing Castle Peak Road. As the contribution of traffic noise from DBL was less than 1dB(A), these NSRs are not eligible for indirect measures under this Project.

3.5.2.7 Noise level at NSRs E8, E13 and E15 still exceeded the standard by about 1 to 4dB(A). The source of exceedance was due to the traffic noise of the existing Castle Peak Road, and the contribution of traffic noise from DBL was less than 1dB(A). These NSRs are also not eligible for indirect measures under this Project.

Other Future/planned noise sensitive receivers

3.5.2.8 Table 3.17 summarizes the traffic noise impacts under unmitigated and mitigated scenarios for the future planned sensitive receivers. Noise impacts on future sensitive receivers at planned residential areas and school sites except HSKNDA were all reduced to acceptable levels, except one location at NSR F9 Area 3C (RR2).

3.5.2.9 NSR F9 is part of the future phases of HSKNDA and information from TDD and PlanD indicated that it would be likely a residential development with a maximum building height of 12 storeys in the Planning Area 3C. While no further planning information is available, assessment was carried at site boundary. It is found that there is an exceedance of 3 dB(A) at 12th floor and no exceedance at 9th floor or lower. The receiver is also found mainly affected by Yuen Long Highway (not DBL) although barriers are proposed by Yuen Long Highway Widening EIA.

3.5.2.10 The main reason for this exceedance is due the higher traffic flow data used in the DBL EIA for year 2021. In the Yuen Long Highway Widening EIA, the project scope was limited to a dual-3 carriageway (with 3 lanes on both sides) widening from the current dual-2 alignment (with 2 lanes on both sides). The amount of traffic was assumed to be around 8600 veh/hr in the dual-3 lanes. Mitigation measures of Yuen Long Highway had been designed to this capacity for dual-3 alignment. Due to the forecasted increase in traffic on Yuen Long Highway, there would be a need to further widen the dual-3 to a possible dual-4 alignment (4 lanes on both sides) in the future. Taking into account of this possible future arrangement, the traffic flow forecast for Yuen Long Highway used in this DBL EIA was higher at around 11600 veh/hr for year 2021. This is the worst case for assessment in this DBL EIA under the foreseeable transport planning. Exceedance is identified because the mitigation measures for dual-3 configuration of Yuen Long Highway could not handle the predicted increase in traffic.

3.5.2.11 Based on the prediction results, additional noise barriers on the central divider of YLH would be required for the dual-4 configuration of YLH. However, the application is likely limited by the structural loading capacity of existing bridge structures at some locations. A combination of three vertical barrier sections as shown in Table 3.14 are predicted able to achieve 70 dB(A) standard at NSR F9. These barriers are on the at-grade sections of YLH avoiding the existing bridge structures and are therefore considered feasible subject to the future investigation and detail design. No residual impact is expected in this case.

3.5.2.12 Considering the fact that the exceedance is only found after the completion of the potential dual-4 widening project of Yuen Long Highway with no further or additional measures and the proposed 12 storeys development in the Planning Area 3C of HSKNDA completed, it should be this dual-4 widening project to formulate and implement direct mitigation measures to control the traffic noise impact. By that time, an EIA would be required to deal with the impact to achieve an acceptable level based on the updated information. Upon review of the likely construction work for noise barriers on the central divider of YLH and the future difficulties in construction, it would be better in this stage to design and allow for the spatial requirements of the foundation works for these barriers on the central dividers. This should be taken up as part of the DBL Design and Construction assignment.

3.5.2.13 Both the HSKNDA project and the future dual-4 widening of Yuen Long Highway project should review the case for F9 Area 3C in their respective environmental impact assessments.

3.5.3 Hung Shui Kiu New Development Area

3.5.3.1 A semi-enclosure (200m in length on DBL) together with the cantilever barriers are proposed to minimize the traffic noise impacts at HSKNDA. With the proposed direct mitigation measures in place, noise levels would be reduced to within EIAO-TM standard except for a few future sensitive receivers at future school sites for assessment points at site boundary as summarized in Table 3.18. The assessment points for HSKNDA layout is given in Figure 3.31. The details of the assessment results are given in Appendix 3B.

3.5.3.2 The assessment results indicate that most assessment points (APs) at site boundaries of the planned sites are within the EIAO-TM standards except school site 2B with 2 dB(A) exceedance.

3.5.3.3 For the proposed alternative layout, most assessment points (APs) at site boundaries of the planned sites are found within the EIAO-TM standards except school sites at 2B and 2C with 2 dB(A) exceedance.

3.5.3.4 Sources of traffic noise contributions for these affected APs are in two folds: noise from DBL and noise from HSKNDA planned roads (Road P1 and local road L1). After the application of mitigation measures in the form of the 200m semi-enclosure and cantilever barriers together with the cantilever barrier on HSKNDA Road P1, noise contribution from DBL dropped substantially from 76 dB(A) to 61 dB(A) at school site 2B for example. The contribution from HSKNDA planned road (mainly from Road L1) was around 65 dB(A).

3.5.3.5 Further noise mitigation measures on DBL were explored which include 3 cases as shown in the following Table 3.20:

Table 3.20 Summary of Noise Mitigation Measures Explored for DBL for HSKNDA

Study Case & Measure

Effectiveness of Measures

Remarks

Original Layout F5 (2B School)

Alternative Layout F6 (2C school)

Alternative Layout F5 (2B school)

Case 1

Extend the southern end of 200m long semi-enclosure by 100m

reduction by

~0.2-0.3 dB

reduction by

~0.1-0.4dB

reduction by

~0.2-0.3 dB

Compared to the Mitigated Scenario

Case 2

Extend the southern end of 200m long semi-enclosure by 200m

reduction by

~0.2-0.5 dB

reduction by

~0.1-0.6dB

reduction by

~0.1-0.5 dB

Compared to the Mitigated Scenario

Case 3

Extend both the southern and northern ends of 200m long semi-enclosure by 200m

reduction by

~0.2-0.6 dB

reduction by

~0.1-0.6dB

reduction by

~0.1-0.6 dB

Compared to the Mitigated Scenario


3.5.3.6 The effectiveness of extending the 200m semi-enclosure is found less than 1 dB(A) reduction of noise levels at assessment points. The direct noise mitigation measures are considered not acoustically effective in this case. In addition, semi-enclosure will be a substantial structure and long semi-enclosure would cause undesirable landscape and visual impact. Noise mitigation measures should therefore be formulated using an integrated approach for development planning and the noise sources.

3.5.3.7 As it is not likely that a sensitive facade school would be located directly at site boundary with large angle of view based on a conventional school layout, a typical school building was incorporated into the HSKNDA layout and the alternative layout for a more realistic assessment.

3.5.3.8 With the use of a typical school building, the actual noise level experienced by sensitive facades is found to be smaller than at site boundaries. All the assessment points at the typical school building facade are found to be meeting the EIAO-TM standard of 65 dB(A).

3.5.3.9 No further residual impacts are expected in this case. Hence, it is considered that the current mitigation scheme is able to protect both the HSKNDA layout and its alternative layout. The layouts with the incorporation of typical school buildings are shown in Figures 3.32 and 3.33 for reference.

3.5.3.10 The mitigation measures and constraints as identified in this EIA for consideration of HSKNDA are summarized in Table 3.18. There may be some uncertainties and likely changes in the future HSKNDA since it is understood that HSKNDA is undergoing further planning study. It is likely that (i) population accommodation may change, (ii) traffic flow forecast may change due to future update information and (iii) landuse pattern may change. Therefore, the mitigation measures and constraints are only suggestions for consideration during the design of HSKNDA. The validity of the predicted impacts in this report and the suggested measures/constraints are recommended to be reviewed in the future study of HSKNDA by the Territory Development Department.


3.6 Definition and Evaluation of Residual Impacts

3.6.1 Construction Phase

3.6.1.1 Only Four NSRs were found to have residual impacts are E4 AP8801 Lam Tei Gospel School (residual impact of 3 dB during normal school date and 8 dB during examination period), E8 AP8414 Fuk Hang Tsuen village house (residual impact of 1 dB, representing about 2 dwellings), E12 AP43 Rural /village houses near Tsoi Yuen Tsuen (residual impact of 1 dB, representing 5 dwellings) and E13 AP8605 village house in Tsoi Yuen Tsuen (residual impact of 4 dB, representing about 6 dwellings). The duration is expected to be around 5 weeks during the pile and pile cap construction.

3.6.1.2 The residual impact could be reduced by special measures which are summarized in Table 3.12. The residual impact could be reduced by special measures which are summarized in Table 3.12. For NSRs E4, E8 and E12, the residual impacts could be reduced to relevant limits by special measures. Only NSR E13 (representing about 6 dwellings in Tsoi Yuen Tsuen) would be subject to residual impact of 4dB for a duration of about 5 weeks during non-restricted hours i.e. normal daytime (0700-1900) at intermittent worst periods under the current programme. For E4 Lam Tei Gospel School, early liaison with the school for the planned examination periods is recommended to plan for the construction work. Noisy piling and pile cap construction should be avoided.

3.6.1.3 The special measures require the reduction of the number of concurrent bridge pier constructions. The applicability of special measures should be reviewed during the construction phase by the Contractor as a part of the EM&A process. A construction noise mitigation proposal is required to be submitted by the contractor for the reviewed by ET and approval by IEC.

3.6.1.4 No further residual impacts exceeding the applicable criteria other than the four NSRs mentioned were predicted due to this Project with the implementation of the proposed mitigation scheme during the construction phase. For the four NSRs (E4, E8, E12 and E13), the likely residual impacts are presented in Section 3.6.1.1. The effectiveness and practicability of specific measures for reducing residual impacts needed to be reviewed on-site by the Contractor through the submission of contraction noise mitigation proposals.

3.6.2 Operational Phase

3.6.2.1 No residual impact exceeding the applicable criteria was predicted due to this Project with the implementation of the proposed mitigation scheme and the proposed development layout/constraint in HSKNDA.

3.6.2.2 It is estimated that about 1073 existing dwellings, 280 planned dwellings (excluding HSKNDA), 2 schools (Ying Yin School and Lam Tei Gospel School) and two places of worship (Nam On Fat Tong and Miu Fat Buddhist Monastery) that would exceed the EIAO noise standards without mitigation measures, would be protected to meet EIAO requirements for DBL with the implementation of the proposed direct technical remedies (traffic noise mitigation measures). The high-densities and medium densities developments and schools in HSKNDA would also be mitigated to within EIAO requirements for DBL.

3.6.2.3 The proposed mitigation measures under DBL project include a 200m long semi-enclosure, about 6.2 km of cantilever barriers and about 4.9 km of vertical barriers in summary.

3.7 Environmental Monitoring and Audit

3.7.0.1 Due to the potential construction noise impact to the nearby residential developments, it is recommended that EM&A for construction noise be carried out throughout the construction period of the project. To ensure implementation of construction phase mitigation measures with consideration of practicability in local levels, the exact location of the purpose-built construction site hoardings and other noise mitigation measures shall be reviewed during the construction phase. The changes or alternative proposals shall be reviewed by Environmental Team and the Independent Environmental Checker.

3.7.0.2 Monitoring at the operational phase is also suggested to check the effectiveness of direct measures on road traffic noise sources. The details of the EM&A program are given in Section 11 of this report and the separate EM&A manual.