6 LAND CONTAMINATION IMPACT

6.0.0.1 This Section presents the results of the investigations into the potential environmental issues related to land contamination, and where appropriate, identifies areas for further assessment in the subsequent construction phases of the Deep Bay Link (DBL).

6.0.0.2 The main objectives of the land contamination investigation are to:

6.1 Legislation, Policies, Plans, Standards and Criteria

6.1.0.1 Assessments of land contamination and the potential impacts are guided by the EPD's document Professional Persons Environmental Consultative Committee Practice Note 3/94 - Contaminated Land Assessment and Remediation (ProPECC PN 3/94), the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), and the EPD's 1999 Guidance Notes for Investigation and Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards, and Car Repair/Dismantling Workshops (Guidance Notes). In accordance with these documents, the assessment evaluation should:

6.1.0.2 Under the ProPECC PN 3/94 note and the Guidance Notes, and in the absence of any formal legislation requiring cleanup of soil and groundwater contamination in Hong Kong, the "Dutch Ministry of Housing, Planning and Environmental Soil and Groundwater Standards" (the Dutch Guidelines) (1994) are used as reference criteria by the EPD for the classification of contaminated materials. It should be noted that the Dutch Guidelines, whilst widely recognised and generally applicable on a global scale, are not enforceable standards in Hong Kong. In the Netherlands, the Dutch Guidelines were developed in the specific case where the drinking water supply is source entirely from groundwater. Hence, the Dutch Guidelines are very strict in regard to some specific contaminants, but must be viewed in the relative context of the Hong Kong situation.

6.1.0.3 Under the EIA Ordinance, Annex 19: Guidelines for Assessment of Other Impacts, and the 1999 Guidance Notes, consideration shall be given to a number of potentially contaminating historical land uses, including petrol filling stations, oil installations, shipyards/boatyards, car repairing and dismantling, power plants and gas works. If these land uses are identified, then the applicant is required to generate a Contamination Assessment Plan (CAP).

6.1.0.4 The following legislation, documents and guidelines may also cover or have some bearing upon land contamination and the handling, treatment and disposal of contaminated waste in Hong Kong:

6.2 Description of Environment

6.2.0.1 The DBL passes through a variety of land uses along its proposed alignment. At the Ngau Hom Shek end of the alignment (Figure 6.1a), the uses are mainly residential areas, fields, fish ponds, livestock farms, hillside and some workshops / open storage areas.

6.2.0.2 For the area of the proposed Ha Tsuen Interchange (Figure 6.1a) the current land use are mainly open storage of mixed materials and machinery, car repair and dismantling area and workshops.

6.2.0.3 Areas south to the San Wai Sewage Treatment Works (Figure 6.1a) are mainly open storage for cargo containers, and some farms and abandoned green areas.

6.2.0.4 Areas further south (Figure 6.1b) is made up of open storage sites of mixed materials, workshops, car repair and dismantling sites, farms, pigeon farms, and a concrete batching plant nearby.

6.2.0.5 Areas near Lam Tei Interchange and Yuen Long Highway (Figure 6.1c) where the alignment will pass through are mainly residential with village/squatter houses. Near Fuk Hang Tsuen, the alignment encroaches workshops of mixed nature, including car repairing and dismantling sites, hardware manufacturing sites etc. At the Lam Tei Interchange, many of the residential areas are 1-3 storey houses with a small field / farm area nearby.

6.2.0.6 Most of the land being used/resumed are those directly encroached by the alignment (the affected land), or those just next to the affected land. Typically the affected area or work areas will be 30m or less from both sides of the alignment.

6.3 Assessment Methodology

6.3.0.1 The objective of the current land contamination study is to identify and screen any concerns with respect to potential soil and groundwater contamination along the proposed DBL alignment.

6.3.0.2 The following methodology has been adopted in this land contamination study:

6.3.0.3 During this study reference to the following sources of information was made:

6.3.0.4 A list of the aerial photographs reviewed during the course of the study is presented in Table 6.1 below. The photographs are reviewed for general changes in land use, as well as specific development.

Table 6.1 Aerial Photographs Reviewed

Date / Year

Location

Photographs

Notes

06 November 1945

NWNT

Y00768

From 20,000 feet

18 November 1954

NWNT

Y02787 / Y02788

From 29,200 feet

13 December 1964

NWNT

Y13045 / Y13046

From 12,500 feet

20 December 1973

NWNT

7928 / 7929 / 7930

From 12,500 feet

23 November 1976

NWNT

16443 / 16444 / 16495 / 16496

From 12,500 feet

19 May 1981

Yuen Long

38146

From 10,000 feet

 

Ha Tsuen

38147 / 38146

From 10,000 feet

1 October 1985

Yuen Long

67314 / 67315 / 67316

From 10,000 feet

3 November 1988

Yuen Long

A15037 / A15038 / A15039

From 10,000 feet

3 December 1990

Yuen Long

A24290 / A24291

From 10,000 feet

 

Nim Wan

A24292

From 10,000 feet

21 October 1994

Yuen Long

A39411 / A39412 / A39413

From 10,000 feet

1 November 1997

Yuen Long

CN18848 / CN18849

From 10,000 feet

 

Nim Wan

CN18850

From 10,000 feet

11 November 1998

Lau Fau Shan

CN21747

From 8,000 feet

 

Tin Shiu Wai

CN21746

From 8,000 feet

 

Yuen Long

CN21582

From 8,000 feet

 

Tuen Mum

CN21512 / CN21513

From 8,000 feet

9 February 1999

Lau Fau Shan

CN22449 / CN22450 / CN22451

From 3,500 feet

 

Ha Tsuen

CN22400 / CN22401 / CN22447 / CC22448

From 3,500 feet

8 February 1999

Lam Tei

CN22563 / CN22564

From 4,000 feet

 

Tuen Mun

CN22604 / CN22604

From 4,000 feet

3 February 1999

Yuen Long

CN22290

From 20,000 feet

 

Tuen Mum

CN22291

From 20,000 feet

6.4 Identification, Prediction and Evaluation of Potential Impacts

6.4.1 Sources of impact

6.4.1.1 The DBL project requires the taking over of some of the existing government land and private land for the construction of roads and carriageways. Much of the road alignment will be formed on existing hillside or agricultural land. A minor portion of land which DBL will run through is occupied by workshops and open storage sites. Depending on the nature of these operations, potential contaminants may enter the soil and groundwater to varying extent, which may lead to land contamination impact. However, DBL is comprised of mainly elevated roads and carriageways which are relatively insensitive to land contamination. Impact of land contamination may only be apparent during the construction phase when the suspected sites within the foundation areas are disturbed.

6.4.2 Review of Historic and Current Land Uses

6.4.2.1 A review of selected historical aerial photographs indicates that the majority of land along the proposed alignment and its associated facilities has primarily been used for farms, fish ponds and residential uses (e.g. Ngau Hom Shek, Lam Tei Interchange), and storage area of cargo containers (near San Wai Sewage Treatment Works). Table 6.2 below lists the historical change in land use in these major areas.

Table 6.2 Historical Change in Land Use along the Proposed DBL Alignment

Location

Year

General Primary Land Usage

Alignment from Ngau Hom Shek to San Wai Sewage Treatment Works

1999

Rural residential areas, fields, ponds, open storage, workshops

1994-1997

Rural residential areas, fields, ponds, open storage

1964-1990

Rural residential areas, fields, ponds

Alignment from San Wai Sewage Treatment Works to Hung Shui Kiu exit.

1999

Predominantly open storage for cargo containers, small percentage of fields, workshops

1997-1998

Predominantly open storage for cargo containers, small percentage of fields

1990-1994

Residential areas, fields, open storage of cargo containers

1964-1988

Fields, rural areas

Alignment from Hung Shui Kiu exist to Castle Peak Road

1964-1999

Fields, rural areas

Alignment from Castle Peak Road to Lam Tei Interchange

1999

Predominantly rural residential areas, small percentage of fields, workshops

1973-1998

Predominantly rural residential areas, small percentage of fields

Note: Aerial photographs of 1945 and 1954 show that the entire area along the proposed alignment were predominantly fields and residential areas

6.4.3 Potential Sources of Land Contamination

6.4.3.1 Potential sources of land contamination along the DBL alignment and its vicinity are presented in Figure 6.1, and the details are summarized in Table 6.3.

Table 6.3 Review of Potential Contaminants and Contaminated Sites along the DBL Alignment

Locations

Marked Area

Site Description & Current Land Use

Potential Site Contaminants

Remarks

Ngau Hom Shek

A1 and 2

The site was of mixed land use of open storage of construction materials / iron bars and workshop of unknown activities. Basically these were inert materials as observed.

It was seen on aerial photos of 1997, 1998 & 1999. It cannot be identified on previous aerial photos and therefore it is likely that its current land use began in 1997.

Metal scraps, rusted metal scraps above ground

Not likely to cause adverse land contamination impact. Some potential concerns may come from the equipment maintenance activities carried out inside the site, but this should be of small scale.

Between Ngau Hom Shek and Ha Tsuen Interchange

B

This was a workshop site of unknown activities. The site being fenced off with metal plates, making it unavailable for visual inspection.

The site was seen on aerial photos of 1997, 1998 & 1999. It cannot be identified on previous APs and therefore it is assumed that its current land use began in 1997.

Unknown

Site inspect shall be carried out to verify the site if access to the site is possible (e.g. when the site is resumed)

Between Ngau Hom Shek and Ha Tsuen Interchange

C1

Wastes such as used car tyres, cans, drums and other unknown materials were found on this site. These may be unauthorized dumping of wastes.

Ground surface with signs of open burning recently (blackened soils).

Discoloration of soil (usually dark color) was observed in localised areas.

Car tyres, used cans, other wastes

The site is near the proposed helipad.

Some wastes may require special handling if the site is used by DBL during construction period.

Between Ngau Hom Shek and Ha Tsuen Interchange

C2

The site was an open storage area of iron gates and other inert structural materials.

Inert/solid metals

Not likely to cause adverse land contamination impact to DBL.

Between Ngau Hom Shek and Ha Tsuen Interchange

C3

The site was an open storage area. Much of the area was vacant at the time of visit. Several drums were observed and might be related to chemicals.

Some unknown chemicals

The site should be reviewed upon land resumption.

Near Ha Tsuen Interchange

D

The site was of mixed usage involving open storage area for construction materials, equipment, heavy machinery, chemicals, wastes, and as open workshop for car repairs and dismantle. Discoloration of ground surface was observed at some localized areas.

It was seen on APs of 1997, 1998 & 1999. It cannot be identified on previous APs and therefore it is assumed that its current land use began in 1997.

Metal scraps, hydraulic fluids, used car batteries, fuel, solvents, metals, coolants

Localized contamination would be likely.

The part of the site within resumption limit should be reviewed

Alignment south to San Wai Sewage Treatment Works

E

The area was an open storage of cargo containers.

During site visit, there was some suspected illegal filling (fuels) activities in some of the sites.

It is seen on APs of 1994, 1997, 1998 & 1999. It cannot be identified on previous APs and therefore it is assumed that its current land use began in 1994.

Fuel residues from heavy vehicles, lubricants

 

Site E occupied a large area. The area within DBL works limit was found to be mainly with container storage activities. The vehicle maintenance activities observed was at the area hightlighted in Figure 6.1a rea Observed to have vehicle Maintenance Activites which is about 150m away. There should not be any adverse impact to DBL.

Alignment south to San Wai Sewage Treatment Works

E1

The site was an open storage of construction materials and iron gates, and workshop for marbles. Some cuttings was performed by the marble workshop.

It is seen during site visitation and on APs of 1999, but too small to be identified on APs of previous years.

Rusted metal scraps, metal scraps, rocks

Considering the site usage was generally storage of insert materials, it would not be likely to cause adverse land contamination impact.

This site is outside DBL.

Alignment south to San Wai Sewage Treatment Works

F

The site was deal with car repairing / dismantling with residential use nearby.

It is seen during site visitation and on APs of 1999, but too small to be identified on APs of previous years.

Metals solvents, used car batteries, hydraulic fluids, fuels, lubricating oils

Further investigation by site inspection and soil sampling may be required to determine whether the site is contaminated the extent of contamination.

Alignment south to San Wai Sewage Treatment Works

G

The site was a workshop. Some bags of High Density Polyethylene (HDPE) was observed. There was a chimney on-site, and the site is suspected to be a plastic foam workshop.

The site is seen during site visitation and on AP of 1999, but too small to be identified on APs of previous years

Organics, solvents

Further investigation by site inspection and soil sampling may be required to determine whether the site is contaminated and if so, the level of contamination.

Alignment south to San Wai Sewage Treatment Works

H

The site was an open storage area of construction materials and mobile toilets.

It was seen on APs of 1985, 1988, 1990, 1994, 1997, 1998 & 1999. It cannot be identified on previous APs and therefore it is assumed that its current land use began in 1985.

Metals / rusted metal scraps on the surface of the ground.

Considering the site usage was generally storage of inert materials, it would not be likely to cause adverse land contamination impact.

Hung Shiu Kiu Exit

I

The site was a concrete batching plant.

It was seen on aerial photos of 1985, 1988, 1990, 1994, 1997, 1998 & 1999. It cannot be identified on previous APs and therefore it is assumed that its current land use began in 1985.

Concrete raw materials

Considering the site usage was generally for concrete batching, it would not be likely to cause adverse land contamination impact.

Along the alignment near Fuk Hang Tsuen

J

The site was comprised of several workshops, including car repairing, hardware and others.

It is seen on aerial photos since 1973, but unable to identify their usage and the change in land use over time.

Metals, fuels, oils, hydraulic fluid, cleansing solvents

Further investigation by site inspection and soil sampling may be required to determine whether the site is contaminated and if so, the level of contamination.

At Lam Tei Interchange

K

This was a workshop site. It was relatively enclosed and it was not able to inspect visually from the outside

It was seen on aerial photos since 1973, but unable to identify their usage and the change in land use over time.

Unknown

Site inspection shall be carried out to verify the site if access to the site is possible when the site is resumed.

At Lam Tei Interchange

L

The site was a car repairing / dismantling site. Discoloration of ground surface was observed in some areas. Quite a big active site with potential land contamination impacts.

It was seen on APs since 1973, but unable to identify their usage and there may be a change in land use over time.

Metal, solvents, fuels, oils, lubricating oils, used car batteries, waste oils, coolants

Further investigation by site inspection and soil sampling may be required to determine whether the site is contaminated and if so, the level of contamination

Near Lam Tei Interchange

M

The site was for car repairing / dismantling. It was active at the time of visit. Discoloration of ground surface was observed.

It was seen on APs since 1973, but unable to identify their usage and there may be changes in land use over time due to the small scales of the APs.

.

Metal, solvents, fuels, oils, lubricating oils, used car batteries, waste oils, coolants

Further investigation by site inspection and soil sampling may be required to determine whether the site is contaminated and if so, the level of contamination

6.4.3.2 Field visits revealed that the majority portion of the land where DBL is located or requires would have relatively low potential for land contamination impacts. Several sites were identified which would require further investigation and they are:

(i) Area C1 near proposed helipad
(ii) Area C3 near propose road to helipad
(iii) Area D near Ha Tsuen Interchange
(iv) Area F under the alignment of DBL south to San Wai Sewage Treatment Works
(v) Area G under the alignment of DBL south to San Wai Sewage Treatment Work
(vi) Area J under the alignment of DBL along Fuk Hang Tsuen Road
(vii) Area L at Lam Tei Interchange
(viii) Area M at Lam Tei Interchange
(ix) Area K at Lam Tei Intechange
(x) Area B near the proposed

6.4.3.3 Further contamination assessment at the above sites should follow the requirements laid out in the proposed contamination assessment plan.

6.4.3.4 For Area K and Area B, further inspection is required when access to the site is available, probably after the land is available to DBL. The inspection aims to identify if there is likely land contamination through site appraisal.

6.4.4 Proposed Contamination Assessment Plan

6.4.4.1 It is not possible to make access to some private land lots for these concerned sites at this stage of study since the sites are still in operation. Considering most sites are open sites without roof or cover, weather conditions e.g. flooding or rains and future activities would likely to change the level of contamination. An outline of the Contamination Assessment Plan (CAP) was worked out for further investigation that would be conducted before the construction stage (probably immediately after the land is made available to DBL).

6.4.4.2 Table 6.4 lists the parameters that should be analysed, and the number of samples to be taken at each identified area (according to EPD's Guidance Notes for Investigation and Remediation of Contaminated Sites). All the information given in Table 6.4 (including the number and location of sampling points and testing parameters) should be reviewed during the preparation of Contamination Asessment Plan.

Table 6.4 Parameters to be Analysed at Each Potentially Contaminated Sites Identified

Site

Potential Site Contaminants

Approx.

Site Size (m2)

Tentative

No. of Samples

(full-scale / simplified*)

Parameters to be Measured

B

unknown site

Further site inspection required after the land is available to DBL

400

to be determined after site inspection

to be determined after site inspection

C1

Possible illegal dump site

Further site inspection required after the land is available to DBL

800

1-3 at suspected locations for screening of contaminants

TPH, BTEX, lead, chromium, copper, zinc, PAHs, PCBs, organic solvents

C3

unknown site

Further site inspection required after the land is available to DBL

500

to be determined after site inspection

to be determined after site inspection

D

(area within DBL land resumption limit only)

Metals solvents, used car batteries, hydraulic fluids, fuels, lubricating oils, coolants

800

1 / 3

TPH, BTEX, lead, chromium, copper, zinc, PAHs, organic solvents

F

Car repair/

dismantling

Metals solvents, used car batteries, hydraulic fluids, fuels, lubricating oils, coolants

1800

8 / 4

TPH, BTEX, lead, chromium, copper, zinc, PAHs, organic solvents

G

Plastic workshop

Organics, solvents

2900

8 / 4

BTEX, TPH, PAH, organic solvents

J

Car repair/

dismantling

Metals, fuels, oils, hydraulic fluid, cleansing solvents, coolants

4800

8 / 4

TPH, BTEX, lead, chromium, copper, zinc, PAHs, organic solvents

K

unknown site

Further site inspection required after the land is available to DBL

400

to be determined after site inspection

to be determined after site inspection

L

Car repair/

dismantling

Metals, fuels, oils, hydraulic fluid, cleansing solvents, coolants

1000

8 / 4

TPH, BTEX, lead, chromium, copper, zinc, PAHs, organic solvents

M

Car repair/

dismantling

Metals, fuels, oils, hydraulic fluid, cleansing solvents, coolants

450

4 / 3

TPH, BTEX, lead, chromium, copper, zinc, PAHs, organic solvents

Notes:

* subject to agreement with EPD

** since the concerned activities may change with time, the location of sampling should be referenced to to prevailing conditions and to be agreed with EPD

criteria for adopting a simplified or full-scale investigation should be carried out area based on those listed in EPD’s Guidance Notes for Investigation and Remediation of Contaminated Sites

TPH : Total petroleum hydrocarbons

BTEX : Benzene, toluene, ethlybenzene, xylene

PAH : Polyaromatic hydrocarbons

Sampling and Testing methods should follow those specified in the Guidance Notes.

6.4.4.3 The Contamination Assessment Plan (CAP) shall be prepared and submitted to EPD for endorsement prior to conducting the site investigation. A Contamination Assessment Report (CAR) should be prepared based on results obtained from site investigation and submitted to EPD.

6.5 Mitigation of Adverse Impacts

6.5.0.1 Concerned sites have been identified in the previous section. Contamination assessment should be carried out to determine whether the sites are contaminated and what level of contamination is present.

6.5.0.2 Potential impacts from these sites are to be determined by the level of contamination present and the possible pathway of exposure by sensitive receivers. Since DBL is comprised of mostly elevated road and carriageways, potential concern would be limited to the exposure during the disturbance of soil in construction phase where foundation are located. Provided that the Contamination Assessment Plan would investigate and identify the contamination level, a Remedial Action Plan could be formulated to remediate the soil to an accepted level. No residual impact is expected after necessary remediation.

6.5.0.3 Available methods of remediation include but not limited to:

Excavation / Disposal

The principle use of this method is for shallow contamination, one-off excavation and contaminant removal. It addresses all contaminants, and pretreatment of excavated soil prior to disposal may be required.

Soil Venting / Air Sparging

The principle use of soil venting is for volatile contaminants in the unsaturated zone soils. Air sparging is mainly for groundwater treatment. These methods remove volatile chemicals and promote bioremediation.

Recovery Trenches or Wells

The principle use of this method is to remove leaked oil that floats on top of groundwater. It is a prerequisite use in conjunction with other remediation methods if leaked oil is found.

Containment of Contaminants

Due to the limitation of available landfill space for disposal of contaminated materials in Hong Kong, the EPD suggests that in-situ remediation methods should be used wherever possible. Contaminament of contaminants is one of the in-situ methods. Excavation and disposal should be the last resort and only used when (1) in-situ remediation is proved to be not feasible and (2) there is very localised contamination and the quantity of contaminated soil for landfilling is small.

6.5.0.4 The acceptance of disposal of contaminated soil at landfill also depends on the degree of contamination of the soil and the nature of the contamination. Special approval has to be obtained from the EPD for disposal to landfill. In some cases, the contaminated soil must be pretreated. According to the EPD's Guidance Notes document, the following factors should be considered when evaluating the different remediation methods and selecting the most suitable one for a site:

6.5.1 Mitigation Measures During Construction Phase

6.5.1.1 It is considered unlikely that contaminated land issues will be a concern during either the construction or the operation of the DBL alignment as remediation on contaminated area would be carried out prior to construction. However, as a precaution, it is recommended that standard good practice be implemented during the construction phase to minimise any potential exposure to contaminated soils or groundwater. These measures include:

6.6 Conclusion and Further Investigation

6.6.0.1 This preliminary investigation has identified land uses along the proposed DBL alignment with the potential to give rise to land contamination as defined in the EPD guidance documents. A preliminary Contamination Assessment Plan (CAP) is prepared and included within the EIA under Annex 19 of the EIAO TM and the 1999 Guidance Notes.

6.6.0.2 Considering the rapid changing of landuses in the areas, the CAP should be updated with reference to concurrent site conditions. It would be necessary to carry out a site apprasial to review the findings of this EIA before construction work starts and confirm the exact sampling locations and testing parameters. This should be included in the finalised CAP in agreement with EPD. Upon receipt of the EPD's approval, the CAP will be implemented and the findings of the investigations will be reported in the Contamination Assessment Report (CAR).

6.6.0.3 The results of the sampling exercise would determine whether contaminated land is, in fact, an issue that needs to be addressed further. If results from sample analysis indicate the presence of potential contaminants, then it may be necessary to update or amend the current CAP in light of the findings. If land contamination is confirmed, a Remediation Assessment Plan (RAP) shall be prepared, and both the CAR and the RAP shall be submitted as a combined report to the EPD for approval prior to the implementation of any remedial technology. If applicable and required in consultation with the EPD, the contaminated site shall be remediated in accordance with the approved CAR/RAP.

6.6.0.4 Implementation of the RAP can begin once the CAR and RAP submission are approved by the EPD. The essential steps involved in remedial programme are detailed in the EPD's Guidance Notes document. In all cases, contaminated soil remediation, treatment or disposal of it must be managed in an environmentally sound manner, including compliance with all relevant legislation and Government requirements.

6.6.0.5 The CAP together with the sampling and testing work are planned to start after the land is available to DBL through early negotiations or resumption and the subsequent CAR and RAP shall be approved by the EPD before commencement of any construction work which may disturb the ground of the concerned sites. Contaminated soil should be remediated before construction work could be started on the concerned sites. It would take about one month to complete the CAP and another two months to complete the CAR and RAP.