12. CONCLUSION AND RECOMMENDATION
12.1.1 Major air quality concerns
would be the cumulative dust impact due to the construction of the Ngong Ping
STW and the Tung Chung Cable Car Terminal as well as the potential odour impact
on the Cable Car Terminal during the operation of Ngong Ping STW.
12.1.2 For the construction of the
proposed STW at Ngong Ping, quantitative dust impact assessment was carried out.
Potential cumulative dust impacts would be related to the concurrent
construction activities associated with the proposed Tung Chung Cable Car
Terminal located immediately to the northeast of the proposed STW. With the
implementation of proper dust control and suppression measures stipulated in the
Air Pollution Control (Construction Dust) Regulation and described in Section
3.6, it is predicted that there would not be any adverse dust impact from the
construction activities of the Project.
12.1.3 In order to mitigate the
potential odour impacts from the proposed Ngong Ping STW to an acceptable level,
it is recommended that all the major odour sources within the proposed STW
namely the inlet work, the activated sludge treatment system, the sludge
thickener, the aerobic digester building, the sludge dewatering and storage
building, and the emergency storage tank should all be either contained by
building structures or constructed as underground tanks to minimise direct
emission of odour to the atmosphere. Besides, all odour emissions from the above
odour sources should be ventilated to a centralised deodourisation unit. Based
on the findings of the odour dispersion modelling, the H2S removal efficiency of
the deodourisation unit should be 99.5% or better and the H2S emission rate at
the exhaust end of the deodourisation unit should not be more than 50 µg/s. The
exhaust height and exit velocity of the treated air should not be less than 5m
and 10m/s respectively. A backup deodorization unit should be provided to cater
for the situation during maintenance or breakdown of the deodorization unit.
12.1.4 All the sludge generated from the STW will be dewatered onsite to more than 30% dry solids content before transporting to the designated landfill site for disposal and will be stored in covered container along the transporting route to avoid the possible odour impact on nearby sensitive receivers. The transportation of the sludge by sea to the disposal location is recommended, as far as practicable, in order to reduce potential air quality impacts from road transportation.
12.2.1 The noise levels from the construction of the proposed Ngong Ping STW
predicted at NSRs were within construction noise limits for the unmitigated
scenario. The noise levels could be further lowered by using quiet plant.
Cumulative noise impact due to the construction of the Ngong Ping Cable Car
Terminal has been considered with reference to the Final Feasibility Study
Report in March 1999 under the MTR Corporation's Consultancy Agreement NEX/034
Tung Chung Cable Car Feasibility Study (TCCCFS). The TCCCFS identified
compliance with noise criteria would be able to be achieved for construction
phase impact from the proposed cable car system. NSRs are generally located far
away from the proposed Ngong Ping STW. Three nearest NSRs are Lin Chi Monastery,
Tin Tan Buddha and village house on Ngong Ping Road near bus terminal which are
more than 441m, 276m and 240m away respectively. No adverse impacts would be
expected on these distant areas.
12.2.2 Construction
phase noise impact could be controlled within acceptable levels for Package 2
Ngong Ping main trunk sewer and effluent export pipeline under the proposed
mitigation measures. For Package 3 Ngong Ping sewerage, some disturbance to the
local residents may be expected due to construction of sewerage pipes inside the
village. The noise impact would be transient and localized originated from
breaking up of footpath surface. It would take only 1 day to break up the
concrete surface for individual NSRs.
12.2.3 Operation phase
would require the proposed mitigation measures to be in place in order to bring
the noise level to the acceptable limits. In the current engineering design, all
the potential noise sources at the STW are enclosed in buildings and all the
local pump chambers will be constructed as underground facilities. No further
residual impacts were identified.
12.3.1 In view of the sensitivity of the area, several special precautionary
measures will be adopted:
Ductile iron pipe will be used for all the Ngong Ping village sewers and effluent pipeline for its robustness, because the area is within the water gathering ground. Sealed pipe joints with hatchboxes along the pipeline will also be adopted; | |
The maximum distance between manholes would be limited to 60 m to facilitate over-pumping operations during sewer inspection or maintenance. This would also facilitate flow diversion in case of emergency situation during pipe leakage; | |
Standby units, emergency power generation and emergency storage facilities will be provided at Ngong Ping STW to avoid the need for emergency discharges. It is proposed to construct an emergency storage tank to temporary store both the raw sewage from Ngong Ping sewerage catchment and the effluent of STW to cater for the STW breakdown and bursting of effluent pipe. Furthermore, it is also proposed that the size of the emergency storage tank will be large enough to store 72hr. Sewage/effluent flow (i.e. 48 hours peak day and 24 hours average day i.e. 2 x 2956 + 1524 = 7436m3) in ultimate stage. Thus, the volume of the emergency storage tank is about 7600m3 and the size is about 50m(L) x 40m(W) x 3.8m (D). | |
The effluent will be treated to standards listed in Table 1.2 such that the impact to local water quality in the unlikely event of pipe leakage would be small. As a result of the high quality effluent and steep gradient, there would minimal chance of effluent pipeline blockage. | |
Installation of 150mm diameter borehole with 100mm diameter slotted iron sleeve for water pollution monitoring, around the STW site at suitable location. | |
The drainage of any high contamination risk areas such as the DG store will be physically separated from the drainage system of the STW site. |
12.3.2 Nevertheless, careful monitoring of the export pipeline would still be
necessary to protect the highly sensitive environment at Ngong Ping. Routine
flow monitoring will be carried out at both the upstream end (STW) and
downstream of the water gathering ground and country park to ensure early
detection of any major leakage. A flow monitoring chamber will be provided east
of Tai O for this purpose. An Action Plan should be prepared and should be
followed in the event that pipe leakage is suspected or identified. Temporary
diversion of effluent to the emergency storage tank at the STW could be arranged
to provide no-flow condition for the repair of the effluent pipeline.
12.3.3 Water quality modelling has been performed to evaluate the impact on Tai
O creek and Tai O waters due to the Ngong Ping exported effluent. The predicted
water quality results for the exported effluent scenario complied very well with
the WQO within the study area. Relatively high E. coli levels were predicted at
the existing mangroves along the Tai O creek. The predicted relatively higher E.
coli concentrations at Tai O creek were contributed by the pollution input from
existing unsewered developments. No adverse impact on the mangrove habitats is
anticipated as the natural pollution tolerance (or pollution exclusion)
displayed by mangroves is well documented. Recent studies of mangals in Hong
Kong and the Futien Nature Reserve in Shenzhen firmly concluded that the
mangrove habitats are not adversely affected by high pollution loads, including
concentrated sewage effluent (Tam et al, 1995; Tam & Wong, 1995; Wong et al,
1995; Wong, 1996(a) and 1996(b)). The increases in pollutant concentrations
caused by the discharge of Ngong Ping exported effluent are considered minimal.
No adverse effect would be expected upon the Tai O creek and Tai O bay waters.
Marine water quality monitoring is recommended to verify the findings of the
water quality modelling.
12.3.4 It is anticipated that both the construction and operational phase of the
project would not cause water pollution problem after undertaking all required
measures proposed in the EIA.
12.4.1 If appropriate mitigation measures are implemented during the
handling, collection, and disposal of construction waste material, the residual
environmental impacts would be reduced to acceptable levels. These mitigation
measures can be enforced by incorporating them into a waste management plan as
part of the contract document. Environmental monitoring and audit will be
necessary to ensure the implementation of correct disposal requirements for the
various wastes generated from construction works.
12.4.2 The sludge
generated during the operation of Ngong Ping STW should be dewatered to more
than 30% dry solids and transported to the landfills. The operators of future UV
disinfection plant should work with the supplier/manufacturer on recycling and
reuse of the defective UV lamps as far as possible. Should the disposal of UV
lamps be unavoidable, the operators should identify the content of the UV lamp
and confirm with EPD whether the UV lamps should be disposed of as chemical
waste. If so, the handling and disposal should follow the Chemical Waste
(General) Regulation. In handling the UV lamps, cautions should be exerted to
avoid breakage of lamps and release of contaminants. Unless the spent fluids
from the wet scrubber system are treated on-site to meet the discharge standards
stipulated in the TM under WPCO, they should be handled and disposed of
according to the requirements under the Chemical Waste (General) Regulation.
12.5.1 The proposed STW development would result impacts on the existing
landscape resources of the STW site, notably existing rock formations and
topography, agricultural soils, woodland trees, shrubland and grassland. These
would need to be cleared to make way for the STW development. In terms of the
surrounding landscape context the loss of these features would represent only a
slight impact.
12.5.2 Extensive
planting is proposed to the perimeter of the site, and the sinking of key
elements of the SWT underground grass can be established on covering slabs to
increase the overall greenery on site. In the long term, with the growth of the
proposed vegetation, the impact on landscape resources should be negligible.
12.5.3 The proposed
works would have an impact on the quality of the landscape character of the
Ngong Ping Plateau, which contains the landscape sensitive Tian Tan Buddha,
Columbarium, and Po Lin Monastery. During construction the removal of existing
vegetation, site formation and building works would have a slight impact on the
landscape character. The proposed planting works within and along the perimeter
of the site, and the layout and architectural treatment of the building
structures should reduce the scale of the impact on character, although it is
considered that there would be a slight residual impact in the long term.
Visual
12.5.4 The Works would have an impact on several visually sensitive receiver
(VSR) groups.
12.5.5 There would be
moderate level visual impacts during construction on residents of Ngong Ping
Village area reside high up on the slope and in the lower areas, visitors to the
columbarium, and motorists / travellers on Ngong Ping Road. These would be
reduced to slight level in the long term with the application of the proposed
mitigation measures.
12.5.6 There would be
limited views from the Po Lin Monastery and the youth hostel due to intervening
topography structures and vegetation. The proposed mitigation measures would
further reduce the level of impacts to negligible in the long term.
12.5.7 There would be
impacts of the long range views on hikers in the surrounding Country Park on the
Nei Lak Shan ridgeline trail and associated footpaths. In the long term, with
the growth of vegetation, the impacts of these hikers should be slight.
12.5.8 There would be
no impact on users of future cable car system and the proposed public transport
interchange during construction as it is assumed that it would not be built
later. However with the elevated nature and proximity of the system and
interchange there are likely to be moderate visual impacts from the SWT in the
operational phase. This impacts of the cable car system would depend on the
precise alignment and configuration of the cable car approach and terminal
building.
12.5.9 There would be
moderate level visual impacts during construction on visitors of Buddha Statue,
but only to the northwestern side of the viewing platform surrounding the statue
(not the approach steps). The proposed perimeter planting, grassing of the
underground structures, and the architectural treatment of the buildings should
reduce the impact on these views to slight levels in the long term.
12.5.10 Summary of the
significance of the landscape and visual impacts during construction and
operation stage is tabulated in Table 7.8 and Table 7.9 for landscape and visual
impacts respectively.
Mitigation Measures
12.5.11 The landscape and visual impacts of the STW development have been minimised through careful design. Measures to be adopted in order to mitigate the extent of the impacts are: -
Retention and protection of existing woodland trees | |
Decorative hoarding during construction along publicly accessible boundaries of the site | |
Topsoil stripped and stored for re-use in the construction of the soft landscape works | |
Control of night-time lighting | |
Grass hydroseeding of slopes and underground structures within the STW site as soon as they are completed | |
Native shrub and tree screen planting along the perimeter of the site | |
Sensitive
architectural and chromatic treatment of the elevated structures |
12.6.1 The impact to wildlife caused by the project was predicted to be
minor. The construction of the sewage treatment works and sewerage would cause a
temporary loss of 0.13 ha of plantation, 0.17 ha of grass-shrubland, 0.94 ha of
urbanised/disturbed habitats and a permanent loss of 0.01 ha of plantation, 0.11
ha of grass-shrubland, and 2.01 urbanised/disturbed habitat. The sewage
treatment works will be built on urbanised/disturbed area and the sewerage will
follow the existing road. No habitat of ecological importance would be lost to
the project. There would be no significant impact to terrestrial or aquatic
ecosystems.
12.6.2 Potential
impacts to aquatic ecology and fisheries during the construction phase would
mainly arise from sedimentation due to surface runoff. Site runoff should be
desilted, to reduce the potential for suspended sediments, organics and other
contaminants to enter stream and marine environment. Special attention should be
paid to the stream in which Romer's Tree Frog has been observed breeding. It is
recommended that earthworks near this stream should not be carried out during
the breeding season of Romer's Tree Frog (March to September).
12.7.1 Field survey was conducted
during March and April 2002. The survey team walked over the entire Project
area, applied 50 auger drills and excavated three test pits. In the areas close
to the alignment, the team identified 19 buildings, 36 stone ruins and five
graves that were dated to pre-war and retrieved a large number of cultural
relics. These cultural remains, however, would not be directly affected by the
proposed Project.
12.7.2 The survey team however has identified a series of historic ruins at Wang Hang Tsuen, Heng Mei and Kwun Yam Shan and over 20 historic buildings at Ngong Ping. Some of these ruins and buildings are located close to the proposed alignment (see Figures 5, 8 and 9 of Appendix 10B). The entire construction workforce should be informed of the locations of these historic ruins and buildings and special attention should be given during the entire process of project construction to avoid any damage to these historical remains. Construction sites which are close to these historical structures should be posted with notices at conspicuous locations to remind the workers not to make any disturbance to the structures. It is recommended to avoid the use of powered mechanical equipment in any works area which is less then 5 m away from the boundary of the identified sites of cultural heritage. With the above mitigation measures in place, it is not anticipated that there would be any adverse effect on the identified sites of cultural heritage.