7. LANDSCAPE AND VISUAL CHARACTER ASSESSMENT

7.1 Introduction


Project Description


7.1.1 The element of the proposed works that could have significant landscape or visual impacts is the proposed sewage treatment plant site and sewerage system at Ngong Ping.

Limits of the Study Area

7.1.2 Landscape and visual impact assessment and the associated mitigation works will cover all areas within permanent land take and temporary works areas at the Ngong Ping STW site. The associated effluent pipeline alignment from Ngong Ping to Tai O will mainly be located under the existing Ngong Ping Road and Tai O Road. Landscape and visual impacts would be minimal and is therefore not considered in the assessment.  The limit of study for the assessment of impacts on landscape resources and character is 500m on either side of the limit of the works, as shown on Drawing No. 23400/EN/024.  The assessment for visual impact is defined by the visual envelope (zone of visual influence) which is generally the viewshed formed by natural / man-made features such as ridgeline or building blocks.  The limit of study for the visual impacts studies are the zones of visual influence (ZVI's) of the works during the construction and operation stages.

Assessment Legislation

7.1.3 The evaluation of landscape and visual impacts associated with the construction and operation of the Ngong Ping Sewage Treatment Works and Sewerage has been made in accordance with the Environmental Impact Assessment Ordinance (Cap 499 S.16) and the Technical Memorandum on EIA Process (EIAO TM), together with the recently issued EIAO Guidance Note No. 8/2002 for the Preparation of Landscape and Visual Impact Assessments (LVIA).

7.1.4 The following standards and guidelines are applicable to the evaluation of landscape and visual impacts associated with the construction and operation of the proposed Works:

Hong Kong Planning Standards and Guidelines;

WBTC No. 25/93 - Control of Visual Impact of Slopes;

WBTC 17/2000 - Improvement to the Appearance of Slopes is also relevant and should be included.

GEO Publication 1/2000 - Technical Guidelines on the Landscape and Bio-engineering of Slopes and Retaining Walls

WBTC No. 14/2002 - Management and Maintenance of Natural Vegetation and Landscape Works, and Tree Preservation issued on 10.5.2002.

7.2 Assessment Methodology

7.2.1 Landscape and visual impacts will be assessed separately for the construction, operational (Opening Day) and residual (Year 10) stages. The assessments will take into account existing/planned/approved land uses as baseline conditions, and assess all direct and indirect impacts on existing/planned/approved land uses, and on future outlook of the area. Potential impacts will be identified in terms of being beneficial/adverse, direct/indirect, short term/long term, and reversible/irreversible.

7.2.2 Impacts will be determined in terms of significance thresholds, which are the product of the magnitude of change to baseline conditions due to the proposed works and the sensitivity of resource/character/receivers. In general terms, magnitude of change relates to parameters of the proposed works in the context of baseline conditions, and sensitivity refers to properties of resource/character/receivers:

7.2.3 Where appropriate the cumulative impacts of other development proposals will be considered.

Landscape Impacts

7.2.4 The assessment of landscape impacts will involve the following procedures:

Identification and quantification on the loss of the baseline landscape resources (physical and cultural) and landscape character found within the study area. This has been   achieved by site visit and desk-top study of topographical maps, information databases and photographs.

Assessment of the degree of sensitivity to change of the landscape resources/character. This is influenced by a number of factors includingquality and maturity of landscape characters/resources,

rarity of landscape elements: whether is considered to be of local, regional, national or global importance ability of the landscape resource/character to accommodate change,

whether there are any statutory or regulatory limitations/ requirements relating to the resource

Identification of potential sources of landscape impacts. These are the various elements of the construction works and operational procedures that would generate landscape impacts.

Identification of the magnitude of landscape impacts. The magnitude of the impact depends on a number of factors including

scale of development, and the physical extent of the impact,

compatibility of the project with the surrounding landscape,

duration of impacts i.e. whether it is temporary (short, medium or long term), under construction and operation phases, potentially reversible, or permanent and irreversible

Identification of potential landscape mitigation measures. These may take the form of adopting alternative designs or revisions to the basic engineering and architectural design to prevent and/or minimise adverse impacts; remedial measures such as colour and textural treatment of building features; and compensatory measures such as the implementation of landscape design measures (e.g. tree planting, creation of new open space etc) to compensate for unavoidable adverse impacts and to attempt to generate potentially beneficial long term impacts.

Prediction of the significance of landscape impacts before and after the implementation of the mitigation measures. This achieved by synthesis of the above information leading to an evaluation of the degree of significance of the landscape impacts into thresholds of substantial, moderate, slight, or negligible. Impacts are classified depending on whether the impacts are adverse/beneficial, and irreversible/reversible. By synthesising the magnitude of the various impacts and the sensitivity of the various landscape resources it is possible to identify a series of thresholds to be used as a basis for the categorisation of the degree of significance of the impacts in a logical, well reasoned and consistent fashion.

7.2.5 The Table 7.1 indicates a rationale for dividing the degree of significance into four thresholds, namely substantial, moderate, slight and negligible depending on the combination of large-intermediate-small-negligible magnitude of change, and high-medium-low degree of sensitivity.

7.2.6 The inclusion of a 'negligible' magnitude of impact is necessary because a negligible impact is different from a 'small' magnitude of impact. A 'small' magnitude impact will cause a varying degree of resultant impact significance depending on whether the landscape resource's sensitivity is low, medium or high. However, a negligible magnitude of impact will always result in negligible significance, irrespective of the sensitivity of the resource.

Table 7.1 Relationship between Receptor Sensitivity and Impact Magnitude in Defining Impact Significance

Impact Significance

Receptor Sensitivity (Landscape Resource or VSR)

Low

Medium

High

Magnitude of change to baseline conditions due to the Works

Large

Slight/Moderate

Moderate/ Substantial

Substantial

Intermediate

Slight

Moderate

Moderate/ Substantial

Small

Negligible/Slight

Slight

Slight/Moderate

Negligible

Negligible

Negligible

Negligible


7.2.7 The assessment of visual impacts will involve the following procedures.

Identification of the Zones of Visual Influence during the construction and operational Stages of the Improvement Works. This is achieved by site visit and desk-top study of topographic maps and photographs, and preparation of cross-sections to determine visibility of the Improvement Works from various locations.

Identification of the Visually Sensitive Receivers (VSR's) within the ZVI's at construction and operational Stages. These are the people who would reside within, work within, play within, or travel through, the ZVI's.

Assessment of the degree of sensitivity to change of the VSR's. Factors affecting the sensitivity of receivers for evaluation of visual impacts:

value and quality of existing views,

availability and amenity alternative views,

type and estimated number of receiver population,

duration or frequency of view, and

degree of visibility

Those who view the impact from their homes are considered to be highly sensitive as the attractiveness or otherwise of the outlook from their home will have a substantial effect on their perception of the quality and acceptability of their home environment and their general quality of life. Those who view the impact from their workplace are considered to be only moderately sensitive as the attractiveness or otherwise of the outlook will have a less important, although still material, effect on their perception of their quality of life. The degree to which this applies depends on whether the workplace is industrial, retail or commercial. Those who view the impact whilst taking part in an outdoor leisure activity may display varying sensitivity depending on the type of leisure activity. Those who view the impact whilst travelling on a public thoroughfare will also display varying sensitivity depending on the speed of travel and whether the view is continuous or occasionally glimpsed.

Identification of potential sources of visual impacts. These are the various elements of the construction works and operational procedures that would generate visual impacts.

Assessment of potential magnitude of visual impacts. This depends on a number of factors including

scale of development,

compatibility of the project with the visual context,

duration of impacts under construction and operation phases,

reversibility of change,

distance of the source of impact from the viewer, and

potential obstruction of view.

Identification of potential visual mitigation measures. These may take the form of revisions/refinements to the engineering and architectural design to minimise potential impacts, and/or the implementation of landscape design measures (e.g. screen tree planting, colour design of hard landscape features etc) to alleviate adverse visual impacts and generate potentially beneficial long term visual impacts.

Prediction of the significance of visual impacts before and after the implementation of the mitigation measures. This achieved by synthesis of the above information leading to an evaluation of the degree of significance of the visual impacts into thresholds of substantial, moderate, slight, or negligible. Impacts are classified depending on whether the impacts are adverse/beneficial, and irreversible/reversible. By synthesising the magnitude of the various visual impacts and the sensitivity of the various VSR's it is possible to identify a series of thresholds to be used as a basis for the categorisation of the degree of significance of the impacts in a logical, well reasoned and consistent fashion.

7.2.8 Table 7.1 indicates a rationale for dividing the degree of significance into four thresholds, namely substantial, moderate, slight and negligible depending on the combination of negligible slight-moderate-substantial magnitude of impacts and a low-medium-high degree of sensitivity of VSR's. The inclusion of a 'negligible' magnitude of impact is necessary because a negligible impact is different from a 'small' magnitude of impact. A 'small' magnitude impact will cause a varying degree of resultant impact significance, depending on whether the receptor's sensitivity is low, medium or high. However, a negligible magnitude of impact will always result in negligible impact significance, irrespective of the sensitivity of the VSR.

7.3 Planning and Development Control Framework

7.3.1 The Ngong Ping Development Permission Area Plan No. DPA/I-NP/2 has been replaced by the draft Ngong Ping Outline Zoning Plan (OZP) No. S/I-NP/1, which was exhibited on 12 July 2002 for public inspection for two months (i.e. ending on 12 September 2002). (See Drawing No. 23400/EN/023)

7.3.2 The planning intention of Ngong Ping OZP is to conserve the natural environment, the character of existing developments, and to promote tourist developments. The new OZP will provide a comprehensive land use planning framework within Ngong Ping boundary area. It is noted in the OZP that the proposed STW site falls within an area zoned "Other Specified Use" annotated "Sewage Treatment Plant". This means the proposed STW development in Ngong Ping is permitted under the OZP being there is no objection to the zone.

7.3.3 The study area also falls within the South West New Territories Development Strategy Review (SWNTDSR). The sub-regional study sets out the recommended land use planning and development strategy for Hong Kong S.A.R South West Region to the year 2016.

7.3.4 The planning vision of the SWNTDSR is to strengthen tourist attractions and to develop a 'religious / leisure node' at Ngong Ping aimed at attracting both local and international tourists.
Existing Use and Potential Impacts

7.3.5 The principal land use zonings within Ngong Ping comprise Residential (Group C) "R(C)", Government / Institution or Community "G/IC", Village Type Development "V", Green Belt "GB", Open Spaces "O", Conservation Area "CA", Site of Special Scientific Interest "SSSI", and Undetermined "U".

7.3.6 The existing developments within these zonings include Ngong Ping Village, Po Lin Monastery, Tian Tan Buddha Statue, Tea Farm, bus terminus, and S.G. Davis Youth Hostel.

7.3.7 The proposed STW is bounded by Ngong Ping Road to the south, Ngong Ping Village to the east, and Lantau North Country Park to the north. The proposed development is located within a "GB" zone. The intention of this zone is to identify the limit of development and to enhance the protection of natural landscape amenity. The existing condition of the STW site is mainly abandoned agricultural land with natural grass and shrub vegetation.

7.3.8 The proposed development will affect the natural vegetation and the natural landscape amenity located nearby. The construction and operation of the development, including slope works, would affect the existing and adjacent natural setting. It is therefore appropriate that conservation and protection of natural landscape setting should be considered and applied during construction and operation stage.

7.3.9 The current OZP emphasises that there is a general presumption against development within this zone. Any proposed developments require planning permission from the Town Planning Board under Section 16 of the Town Planning Ordinance. Proposed development will be considered on its individual merits. The current OZP designates the proposed STW site under "Other Specified Use" annotated "Sewage Treatment Plant" zoning on the OZP subject to the acceptance of the EIA by EPD.


Existing Character of Adjacent Areas

7.3.10 The proposed development will mainly surrounded by Conservation Areas and Country Park. These areas are be naturally vegetated and have ecological, landscape and scenic value for both residents and tourists. Construction of the development is likely to affect the existing and adjacent natural setting and alter the landscape character area. Minimising the scale and extent of works, will help to minimise the landscape and visual impacts during the construction and operation stage.

7.3.11 A columbarium is located to the north east of the proposed STW site. Impact on the columbarium and its existing natural environs should be minimised. However, since the columbarium is located far away from the study area and falls outside the boundaries of the Ngong Ping OZP boundaries, no land use impacts are anticipated.

7.3.12 The North Lantau Country Park and Conservation Area located immediately to the north and west of the proposed development respectively, are both areas providing protection of natural landscape beauty. The proposed development would have no direct impact on these areas, but may affect their landscape setting. Mitigation measures undertaken during construction and operation stage should address this.

7.3.13 The Tian Tan Buddha Statue and Po Lin Monastery are located to the south west of the proposed development. They are the dominant structures and have unique heritage and religious value for Hong Kong. The visual setting of these areas is of prime importance and measures should be adopted in the development of the STW to avoid any adverse visual impact.


Planned and Committed Development

7.3.14 The proposed cable car link was recommended under the SWNTDSR. The proposed cable car link aims to connect Tung Chung to Ngong Ping. The Tung Chung Cable Car System is intended to help boost the tourism and to provide tourist facilities at Ngong Ping (e.g. resort-style hotel, scenic trails, folk museum, etc.).

7.3.15 Currently, the proposed cable car terminal is located to the south east of the STW site, and has been identified in the Ngong Ping OZP. The extent of the construction and operation of the cable car link should not have land use impacts to the proposed STW site. However, if the alignment and the terminal of the cable car link is amended to run in closer proximity to the proposed sewage plant, then there is likely to be a visual impact on cable car users, which needs to be addressed in the design of both the Cable Car System and the STW. Currently, a public transport interchange is also proposed to the east of the STW site. Possible land use interface with the proposed public transport interchange should be minimised.

7.3.16 The explanatory notes to OZP has mentioned the proposed treatment plant will be located at the foothills in the western end of the area (where it is currently being proposed).


Landscape Planning Designation

7.3.17 The Ngong Ping OZP has highlighted a number of sites that have a valuable landscape features and ecological diversity. The following sections briefly describe the potential areas for conservation and landscape designation identified under current planning studies.

7.3.18 Most of the Conservation Area and the SSSI are located to the south-western part of Ngong Ping at some distance to the study site.. The planning intention is to protect against disturbance and encroachment by developments.

7.3.19 The Lantau Trails run in an east-west direction within Lantau South Country Park. The trails provide a high quality landscape setting for recreational users, local and international visitors.

7.4 Baseline Conditions


7.4.1 Areas of sensitive landscape within the Study Area (considered to be a 500m area from the proposed STW site) include Ngong Ping village, Tian Tan Buddha, Po Lin Monastery, etc. The proposed STW site is shown on the annotated aerial photograph in figure drawing 23400/EN/078. The principal physical landscape resources within the Study Area comprise :


Topography and Land Form (LR1)

7.4.2 The land forms of Lantau contribute significantly to its identity. Within the Lantau, generally lower slopes are gentle with deep soil layers. These comprise loose material which is the result of landslides and ground slump. This is generally fairly unstable material. Upper slopes are generally steeper and more spectacular, comprising a topography of bare rock outcrop and boulder strewn hillsides resulting in an often dramatic and rugged appearance. The Ridgelines and peaks are particularly significant topographic elements of this landscape adding to its distinctiveness.

7.4.3 The settlement at Ngong Ping lies on a plateau close to the ridgeline at an approximate elevation of 450 mPD. The area is relatively level although rises sharply to the north east towards Nei Lak Shan, and to the south-east towards Lantau Peak. The ground generally falls dramatically in to the south and West.

7.4.4 The Study site lies in a below the local peak of Sze Tsz Tau Shan and the Buddha Statute, at an elevation of approximately 440 mPD. It is generally flat falling slightly to the north. The ground retains some of it's natural profile, although appears to have been modified in the past, possibly by agricultural activity. A pronounced slope lies along the north-eastern side, giving it a slight elevation with relation to the areas immediately to the north and east.

7.4.5 The site (approximately 21,160sq.m) has very few rock outcrops or boulders (probably removed at an earlier date), although the surrounding natural hill slopes are heavily strewn with small weathered rocks and boulders. These help give a distinct wild upland character to the landscape. The sensitivity to change is considered to be high.

Agricultural Soils

7.4.6 Lantau Island consists of what is principally volcanic rock. The upland areas (approximately 276,960sq.m) in which the study site is located are composed of principally undifferentiated volcanic rock of the Repulse Bay formation. In western Lantau, pyroclastic rocks and lava are dominant, and a few of these occur as outcrops around Tung Chung Road. The area to the south of the central Lantau Uplands, lies on coarse tuff.

7.4.7 The site lies on a typically thin layer of colluvium, and has recently been used for agriculture. The exposed location and the general instability of the soils have inhibited the development of vegetation resulting in soils of low fertility. Given their general abundance of such soils, their sensitivity to change is considered to be low.


Woodland Trees (LR3) / Grassland / Shrubland (LR4)

7.4.8 Across Lantau Island generally, the natural vegetation pattern shows a transition from secondary woodland in the lower sheltered valleys through tall and low shrub in more open valleys to grassland in the higher more exposed ridgelines. This pattern represents the natural development of the vegetation, and in time, without human interference, the grassland of the upper hill slopes would succeed to shrub and secondary woodland.

7.4.9 Although the site is generally open characterised by rock and sparse grass (approximately 92,729 sq.m), similar to the surrounding natural hill slopes, there are a number of trees loosely distributed across the site. These comprise fruit trees (Litchi / Longan), and a mixture of exotics (Acacia / Casuarina) and recently established pioneers (Macaranga / Mallotus). They appear to be remnants of former agricultural activities and recent colonisation rather than native shrubs or woodland species.

7.4.10 There are more substantial areas of woodland trees (approximately 21,554 sq.m) to the north and east, again associated with former agricultural land around the Ngong Ping Village. Collectively they provide screening and landscape amenity to the Ngong Ping Area.

7.4.11 Beyond the Ngong Ping settlement the natural hills support some low shrub and open grassland. These are valuable both in ecological and landscape terms but due to their wide spread and rapid establishment have only a low sensitivity to change.

 

Stream Courses (LR5)

7.4.12 The Ngong Ping area contains a number of seasonal small streams. Although there is only one within the STW site. The streams are shallow and lined intermittently by with riparian shrubs and grasses, and appear to have been modified in many places during cultivation of surrounding areas. They are considered to be of only limited landscape amenity value.

7.4.13 Beyond the STW site the streams on the open hillsides are often precipitous with steep sides and are associated with flora and fauna that, in certain cases, is found nowhere else in Hong Kong. Thus many of these stream courses are of particular value. The smaller less well developed seasonal streams are considered to be of medium sensitivity to change, while the permanent streams supporting the richer floral and faunal communities are considered to be medium sensitive to change.

Cultural and Historic Landscapes

7.4.14 The site may previously been under agricultural production. Some adjacent areas to the north and east show distinct field patterns, although most of the fields are abandoned and have been colonised by vegetation.

7.4.15 The slopes to the south of the Tian Tan Buddha (LR6) and Po Lin Monastery (LR8) contain a large number of graves with prospects to the west and south.

7.4.16 A columbarium (LR7) (place for storage of urns and memorials) containing a large number of graves is located on a woodland near the northern edge of the site. The building is in an informal Chinese style, and is a distinct feature on the hill slopes behind the villages. The site is dependent on the surrounding natural landscape for it's character, and is considered to be highly sensitive to change. It may also have Fung Shui associations.

Settlements (LR9)

7.4.17 The Tian Tan Buddha Statute (tallest seated outdoor statue of Buddha) was created to offer benediction, and is one of the primary tourist destinations in Hong Kong. It has a strong association with the surrounding landscape, with the visitor experience created largely by the walk up the long flight of steps from the North West. The prominent location acts as an important landmark for many areas on Lantau and the Western side of Hong Kong.

7.4.18 On arrival at the platform on which the Buddha is located, visitors have spectacular views in all directions. To the North and East they look out over Ngong Ping, with panoramic views of the Po Lin Monastery and surrounding villages. The STW site is located to the north west and is only visible from the west side of the platform.

7.4.19 The Po Lin Monastery situated to the eastern part of plateau, is the best known Buddhist monasteries on Lantau. The yellow roofs of the Temple of Heaven Buddha are a distinctive feature in the landscape. Several other monastery sites of cultural and spiritual importance are located within the Upper Tai O Valley.

7.4.20 The Buddha Statute and Po Lin Monastery are of particular cultural and spiritual importance, and are Hong Kong's most popular tourist destinations. Due to the relationship between their use and the surrounding landscape both are considered to be highly sensitive to change.

7.4.21 A number of small villages are set on the lower hillsides above the plateau. These comprise loosely laid out two and three storey buildings in traditional style, and are interspersed by belts of mature trees and vegetation.

7.4.22 The only road within the area, is the single carriageway Ngong Ping Road which leads to the Buddha and Po Lin Monastery. This follows a sinuous alignment up the hillsides from the Shek Pik Reservoir, and is significant as the key tourist arrival route to the Ngong Ping Area. A large car park area has been established immediately in front of the Monastery.

7.4.23 A number of hiking paths associated with the ridgeline. Local footpaths run along the east and west sides of the site leading to the northern columbarium.

7.5 Landscape Character Zones

7.5.1 Within the Study Area it is possible to define two different landscape character areas, as shown in drawing 23400/EN/024.

Natural Uplands (LC1) - Landscape Character Area

 

7.5.2 The landscape of Lantau Island, south of Tung Chung, is characterised by a high mountainous ridge running along the length of the island. The peaks rise sharply from the sea to 934 mPD on Lantau Peak, which lies to the south east of Ngong Ping. The uplands form rugged and dramatic ridges, peaks and spurs, angular in appearance and often given an undulating form by the numerous streams and gullies that run down them. Otherwise, the hilltops are large in scale, exposed and tranquil. The lower slopes are characterised by shrubs or woodland vegetation whilst the upper slopes are grass-covered with numerous rock outcrops and landslip scars. The area is large-scale and naturalistic in character and is of high landscape quality which is medium sensitivity to change.

Ngong Ping Development (LC2) - Landscape Character Area

7.5.3 The site of the proposed STW lies in a hilltop area surrounding the Buddha Statute which was developed for the associated monastery, village and agricultural land uses. As the site has attracted more tourists, subsequent development has focus on tourist facilities including car parks and toilet block. Together these represent a distinctly different character from the surrounding natural hill slopes. Smaller in scale and having a character derived from the complex arrangement of monastery buildings, village houses agricultural fields (although largely abandoned now), and mature woodland vegetation. Given the distinct and valuable in character of the area the sensitivity of change is considered to be high.

7.6 Landscape and Visually Sensitive Receivers


Visual Context and Visually Sensitive Receivers


7.6.1 The visual envelope of the site of the proposed sewage treatment plant site and sewerage system at Ngong Ping is relatively small. The elevated position at 450mPD, restricts views to the areas in the immediate vicinity and the limited areas of higher ground.

7.6.2 The principal potential visually sensitive receivers within the study area comprises :
Residential Receivers

7.6.3 Residents at the Ngong Ping villages (R1) and the Po Lin Monastery (R2) are located at the lower level of the Ngong Ping settlements. These visually sensitive receivers have a medium range and intermittent view to the STW site. Given that the residents will have a permanent view to the STW site, the receptor sensitivity is considered to be high.

Recreational Receivers

7.6.4 Visitors and recreational users at the Po Lin Monastery (C2), Nei Lak Shan Ridgeline Trail and associated footpaths (C4), and the columbarium (C5) have a medium range view to the STW site. As these recreations consists a limited number of sensitive receivers and only on a temporary basis and would not count as permanent sensitive receivers, it is considered to be medium sensitivity to change.

7.6.5 The Tian Tan Buddha statute (C1) is one of the popular tourist attractions in Hong Kong. It is also an important landmark of the Lantau Island. Visitors on arrival at the Buddha have a 360-degree vista view over the surrounding areas, and are considered to be high sensitivity of change.

7.6.6 Similar to Buddha Statute, visitors at the future Ngong Ping Cable Car System (C6) would have medium range, vista view to STW site. The receptor sensitivity is considered to be high.

7.6.7 The youth hostel and the Tea Garden Restaurant (C3) are located at the lower level of the Ngong Ping settlements, far away from the STW site. Visual receivers at this area are limited, and duration of the view over the STW site is intermittent. It is considered to be low sensitivity of change.

Occupational Receivers

7.6.8 The youth hostel, Tea Garden Restaurant (O1) and the Po Lin Monastery (O2) are located at the lower level of the Ngong Ping settlements far away from the STW site. The number of sensitive receivers are limited and duration of view are constant. It is therefore considered to be medium sensitivity of change.

Travelling Receivers

7.6.9 The Ngong Ping Road and the proposed public transport interchange (T2) are located close to the STW site. This consists of a number of sensitive receivers including travellers, and motorists (T1). These receivers have a close and brief view on the STW site, and are considered to be high sensitivity of change.

7.6.10 The potential visually sensitive receivers (VSR's), the identity and character of which are set out in Table 7.2, and their locations are shown in Drawing No. 23400/EN/025 together with the locations of key views of the site are identified in Table 7.3.

Table 7.2 Identity and Characteristics of the Key Visual Receivers

Ref

Location of Receiver

Number of receivers

Type of view

Duration of view

Approximate Distance to Site (metres)

Residential Receivers

R1

Residents of Ngong Ping villages

Few

Partial

Constant

20-700

R2

Residents of Po Lin Monastery Complex

Few

Vista

Constant

450-800

Recreational Receivers

C1

Visitors to the Buddha Statute

Many

Vista

Periodic

450-800

C2

Recreational users of Po Lin Monastery

Many

Vista

Periodic

450-800

C3

Recreational users of youth hostel

Few

Vista

Intermittent

800-1000

C4

Hikers on the Nei Lak Shan ridgeline trail, and associated footpaths

Few

Panorama

Constant

500-1200

C5

Visitors of Columbarium

Few

Panorama

Periodic

10-300

C6

Future Users of the Ngong Ping Cable Car Terminal

Few

Vista

Periodic

10-300

Occupational Receivers

O1

Workers at the youth hostel

Very Few

Vista

Periodic

800-1000

O2

Workers at the Po Lin Monastery

Few

Vista

Constant

450-800

Travelling Receivers

T1

Motorists / travellers on Ngong Ping Road

Many

Panorama

Intermittent

10-300

T2

Travellers of the Future Public Transport Interchange

Many

Vista

Periodic

10-30

 

Table 7.3 Characteristics of Key Views

No.

Location

Type of View

Approximate Distance to Site (m)

Representative of Views from

PM1

View from Ngong Ping Road

Elevation

10

Typical vista from the road of upland areas

PM2

View from the Statue of Buddha

Panorama

350-400

Long range views of Ngong Ping

PM3

View from the Columbarium

Panorama

50-400

Panoramic view of Subject Sites

 

7.7 Construction Stage Impact Assessment

Potential Sources of Impact during the Construction Stage

7.7.1 The nature and extent of the proposed works associated with the Ngong STW would comprise: -

 site formation including new cut slopes platform and excavation for underground structures;

formation of sewage and associated facilities, and buildings with heights ranging from approximately 2.5m to 7.6m; and

new road within the site;

7.7.2 The proposed works would create varying levels of impacts on the physical landscape and visual amenity to the surrounding environs during construction stage. Potential impacts would result from the following activities:

Site clearance works involving the removal of existing vegetation;

Formation of construction accesses and temporary works area;

Haulage off-site of excavated materials;

Importation and storage of construction equipment and materials; and

Construction of roads, slopes, utilities, drainage STW structures and buildings

Night lighting

Nature and Magnitude of Landscape Impacts during the Construction Stage

7.7.3 There will be night-time lighting during both construction and operational stage. The intention of night lighting is for the site entrance and emergency purposes only. Construction works would not be carried out at night.

Physical Landscape Resources

7.7.4 There would be impact on existing topography due to minor slope cutting and levelling of platform on the north-eastern side of the STW site. Construction work also comprises excavation of land, soil, and rock outcrops / boulders for the construction of emergency storage tanks and SBR tanks located below ground level. These associated facilities are located at the western and eastern side of the STW site. Overall, the magnitude of change on topography and landform as a landscape resource during construction is, however considered to be small.

7.7.5 There would be impact on existing topography (LR1) due to minor slope cutting and levelling of platform on the north-eastern side of the STW site. Construction work also comprises excavation of land, soil, and rock outcrops / boulders for the construction of emergency storage tanks and SBR tanks located below ground level. These associated facilities are located at the western and eastern side of the STW site. Overall, the magnitude of change on topography and landform as a landscape resource during construction is, however considered to be small.

7.7.6 Construction of STW would result in the need to remove the thin layer of existing soil. However, given that the agricultural soil (LR2) is regarded as low fertility in comparison to the total magnitude of the change on this landscape resource is considered to be intermediate.

7.7.7 There would be loss of shrubs (approximately 18,105 sq.m) loosely distributed across the STW site. As the total resource of the woodland trees (LR3) in the Ngong Ping area is significant, the loss to the STW site would constitute a small change.

7.7.8 There would be loss of shrubland and grassland (approximately 3,055 sq.m) (LR4) across most of the STW site. although in the context of the wider landscape this would represent only a small magnitude of change on this landscape resource.

 

7.7.9 Construction of the STW would require minor modification of the existing streamcourse (LR5) , but in terms of total resource of streams, the magnitude of change is considered to be negligible. Location of the streamcourse is illustrated in Drawing no. 23400/EN/024.

Human and Cultural Landscape Resources

7.7.10 The proposed STW works would have no direct impact on the Tian Tan Buddha (LR6), the columbarium (LR7) and Po Lin Monastery (LR8). But there would be an alteration in the quality of landscape setting to both these features through loss of vegetation and construction works (addressed under Landscape Character). The distinct field pattern to the north and the south of the STW would not be directly affected by the construction work.

 

Settlements (LR9)

 

7.7.11 There would be no direct impact on the landscape setting on the Buddha Statue, the Po Lin Monastery, and the Ngong Ping Road, although loss of vegetation and disturbance of the surrounding landscape would have an effect on the landscape character within which these sites are located. In this case, the magnitude of change would be small.

 

Landscape Character Zones

7.7.12 There would be impact on the Lantau Peaks and Uplands landscape character area (LC1) and Ngong Ping Development (LC2) during construction stage. The introduction of construction machinery, site formation, and building structures at both evaluated / below ground level would cause disturbance to the topography, vegetation, and rock outcrops, would be in contrast with the current sensitive natural landscape and the development area within Ngong Ping. In this case, the magnitude of change would be intermediate and small.

Nature and Magnitude of Visual Impacts during the Construction Stage

7.7.13 The visual envelope of the proposed STW works would include all areas within the baseline visual envelope. It would additionally extend into a wider area of the Nei Lak Shan. The key visual receivers are set out in Table 7.3.

Residential


7.7.14 Residents of Ngong Ping village (R1) at the centre of Ngong Ping development area would have intermittent and oblique medium range views up into the construction of both super and underground structures and slope works on the STW site. Since most of the residents of Ngong Ping village are located at the lower level of Ngong Ping compared to the STW site, the level of visual impact would be blocked by buildings and vegetation. Only those at a high level would have intermittent views of the STW. Impacts of night time lighting to residents would be minimal as the light would be blocked by buildings and vegetation. Overall the magnitude of change is considered to be intermediate.

7.7.15 Residents of Po Lin Monastery Complex (R2) located in the Ngong Ping development area would have oblique medium range view up into the eastern section of construction works. Residents would have an intermittent view of construction of superstructures and the night lighting at the STW site, but this would mostly be screened by existing buildings and vegetation. The magnitude of change is considered to be small.

Occupational Users

7.7.16 Occupational users of the youth hostels and the Tea Garden Restaurant (O1) lying close to the Ngong Ping SSSI (the tea plantation area) would have very slight long range view of the eastern portion of the STW site. Given that the distance of these views, and interference by other buildings and vegetation, and other alternative views available from the property. Night lighting would not cause impacts to the users given the distance of these views. The magnitude of change is considered to be negligible.

7.7.17 Similar to the residents at the Po Lin Monastery (O2), workers within this area would have an oblique and medium range view up the STW site. Occupational user would have a brief view on the construction works as this would be screened by existing buildings and vegetation. The magnitude of change is therefore considered to be small.

Recreational Users

7.7.18 The Buddha Statue (C1) is one of the most famous tourist attractions in Hong Kong and is also a landmark for the Lantau Island. Visitors to the Buddha Statue on the northwestern side of the viewing platform only, would have an oblique, medium range view down to the STW site. View towards the STW site from the access steps would be screened by the existing buildings and vegetation. Impacts of night lighting during construction stage would be minimal as there would be no visitors at night. In consideration of other scenic quality of other alternative views that could be enjoyed by the visitors, it is considered that the magnitude of change would be intermediate.

7.7.19 Visitors of Po Lin Monastery Complex (C2) located in the Ngong Ping development area would have oblique medium range view up into the eastern section of construction works. Visitors would have an intermittent view of construction of superstructures and night lighting at the STW site, but this would be screened by existing buildings and vegetation. The magnitude of change is considered to be small.

7.7.20 Visitors of Youth Hostel and the Tea Garden Restaurant (C3) would have long range views of the construction works. Given that the distance of these views, interference from existing buildings and vegetation, and alternative views from this property are available. The magnitude of change in view would be negligible.

 

7.7.21 Hikers on the Nei Lak Shan Ridgeline trails (C4) and the associated footpaths would have uninterrupted views of the proposed works over a distance of some 1200 metres. The works would be seen against the backdrop of the hill slopes of the Country Park. Given the panoramic and scenic quality of alternative views, works during construction stage would results small magnitude of change in views of these users.


7.7.22 Visitors of columbarium (C5) would have a short range, direct views to the construction work at the north-western part of the STW site. This would include excavation of soil for the formation of underground structures and night lighting. Given that visitors to columbarium are only temporary basis and would not count as permanent sensitive receivers, the magnitude of change is considered as intermediate.


7.7.23 Passengers of the future Ngong Ping Cable Car System (C6) are not considered within the construction stage as the STW are assumed to be built first. This will be assessed within the operational stage.


Travellers


7.7.24 Motorists and travellers on Ngong Ping Road (T1) would have very brief, close views of the construction works in the southern section, access road construction, and slope remediation works on Ngong Ping Road. Night lighting from the STW site would also cause visual interference at night. Therefore, the construction works are likely to result in small magnitude of change in their views along Ngong Ping Road.


7.7.25 Passengers of the future public transport interchanges (T2) lies to the east of the STW site (where the possible Tung Chung Cable Car System is located) are not considered within the construction stage. It is assumed that the STW site will be built first, and this will be assessed during operational stage.


7.7.26 A summary of the significance of the landscape and visual impacts during the construction stage is illustrated in Table 7.4 and Table 7.5 for landscape and visual impacts respectively.

Table7.4 Summary of Significance of Landscape Impacts during the Construction Stage

Ref

Landscape Receiver

Sensitivity to Change

Extent of Loss (in sq.m)

Magnitude of Change before Mitigation

Magnitude of Change After Mitigation

Impact Significance before Mitigation

Impact Significance After Mitigation

LANDSCAPE RESOURCES

 

 

 

 

 

LR1

Topography and Land Form

High

21,160

Small

Small

Slight

Slight

LR2

Agricultural Soils

Low

21,160

Intermediate

Small

Slight

Negligible

LR3

Woodland Trees

Low

3,055

Small

Small

Slight

Slight

LR4

Grassland / Shrubland

Low

18,105

Small

Small

Negligible

Negligible

LR5

Stream Courses

Medium

0

Negligible

Negligible

Negligible

Negligible

LR6

Tian Tan Buddha

High

-

Negligible

Negligible

Negligible

Negligible

LR7

Columbarium

High

-

Negligible

Negligible

Negligible

Negligible

LR8

Po Lin Monastery

High

-

Negligible

Negligible

Negligible

Negligible

LR9

Settlements

High

-

Small

Small

Slight

Slight

LANDSCAPE CHARACTER

         

LC1

Natural Uplands

Medium

0

Small

Intermediate

Moderate

Moderate

LC2

Ngong Ping Development

High

-

Intermediate

Small

Moderate

Slight

Notes: (1) All impacts are negative / adverse unless otherwise stated

(2) Source of landscape impact on all resources / character areas would be earthworks, construction activity, and the formation of new roads / structures / buildings / slopes etc.

(3) Extent of loss is equal to the total area of the landscape resources that would be affected by the temporary and permanent works

Table7.5 Summary of Significance of Visual Impacts During Construction Stage

VSR

Key Visually Sensitive Receiver (VSR)

Source(s) of Impacts

Distance Between VSR and Source

(m)

Receptor sensitivity

Magnitude of Change before Mitigation Measures

Magnitude of Change after Mitigation Measures

Impact Significance before Mitigation Measures

Impact Significance after Mitigation Measures

RECREATIONAL RECEIVERS

             

C1

Visitors to Buddha Statute

New building / slope works

450-800

High

Intermediate

Intermediate

Moderate

Moderate

C2

Recreation Users to Po Lin Monastery

New building / slope works

450-800

Medium

Small

Negligible

Slight

Negligible

C3

Recreational Users of Youth Hostels / Tea Garden Restaurant

New building / slope works

800-1000

Low

Negligible

Negligible

Negligible

Negligible

C4

Hikers of Nei Lak Shan Ridgeline Trail and Associated Footpaths

New building / slope works

500-1200

Medium

Small

Small

Slight

Slight

C5

Visitors to Columbarium

New building / slope works

10-300

Medium

Intermediate

Intermediate

Moderate

Slight

C6

Future Users of the Ngong Ping Cable Car Terminal

New building / slope works

10-300

High

-

-

-

-

RESIDENTIAL RECEIVERS

 

 

 

 

 

 

 

R1

Residents of Ngong Ping Villages

New building / slope works

20-700

High

Intermediate

Small

Moderate

Slight

R2

Residents of Po Lin Monastery Complex

New building / slope works

450-800

High

Small

Negligible

Slight

Negligible

OCCUPATIONAL RECEIVERS

             

O1

Workers at the youth hostel / Tea Garden Restaurant

New building / slope works

800-1000

Medium

Negligible

Negligible

Negligible

Negligible

O2

Workers at Po Lin Monastery

New building / slope works

450-800

Medium

Small

Negligible

Slight

Negligible

TRAVELLERS

             

T1

Motorists / travellers on Ngong Ping Road

New building / slope works / road works

10-300

High

Small

Small

Slight

Slight

T2

Travellers on the future public transport interchange

New building / slope works / road works

10-30

High

-

-

-

-

Notes: All impacts are negative / adverse unless otherwise stated

7.8 Mitigation Measures During the Construction Stage


7.8.1 Landscape and visual mitigation measures which should be incorporated within the permanent landscape design to ameliorate impacts caused during construction stage. Mitigation measures during construction stage are described in Table 7.6, together with the proposed funding, implementation, and maintenance agencies. and are illustrated in Drawing 23400/EN/043.

 

Table 7.6 Proposed Construction Stage Mitigation Measures

No.

Mitigation Measures

Funding Agency

Implementation Agency

Management Agency

CM 1

Retention and protection of existing woodland trees

DSD

DSD

DSD

CM 2

Decorative hoarding along publicly assessable boundaries of the site

DSD

DSD

DSD

CM 3

Topsoil stripped and stored for re-use in the construction of the soft landscape works

DSD

DSD

DSD

CM 4

Grass Hydroseeding of slopes as soon as they are complete

DSD

DSD

DSD

CM 5

Control of night-time lighting

DSD

DSD

DSD

 

7.8.2 There will be no off-site landscape mitigation measures for the proposed at Ngong Ping STW site. Full allowance of mitigation measures listed should be in the detailed design of all components of the scheme, and should be adopted from the commencement of the construction and should be in place throughout the entire construction period.

7.9 Prediction of Significance of Landscape Impacts during the Construction Stage

7.9.1 The potential significance of landscape impacts during the construction stage, before and after mitigation, are described in Table 7.4 and illustrated in Drawing 23400/EN/026. This assessment follows the assessment methodology outlined in Section 7.2. It assumes that appropriate construction stage mitigation measures identified in Table 7.6 above would be implemented.

7.10 Prediction of Significance of Visual Impacts during the Construction Stage

7.10.1 The potential significance of the residual visual impacts during the construction stage, before and after construction stage mitigation has been implemented is given in Table 7.5 and illustrated in Drawing 23400/EN/040. This assessment follows the assessment methodology outlined in Section 7.2. It assumes that appropriate construction stage mitigation measures identified in Table 7.6 above would be implemented.

7.10.2 Illustrations of the likely impacts on key views of the proposed improvement works during construction stage are given in the photomontages in Drawing 23400/EN/048,(049, 050, 051, 052)and Drawing 23400/EN/053.

7.11 Operational Impacts

7.11.1 Potential Sources of Impacts in the Operational Stage

7.11.2 The extent of works for the proposed improvement works is indicated in the site layout plan, and again within the landscape mitigation measures plans shown in Drawing 23400/EN/044. The sources of impacts of the project at the operational stage would include the following: -

Newly formed soil and rock cut slopes and retaining structures;
Building structures (building heights ranging from approximately 2.5m to 7.6m);
Underground structures; and
New road access.

Nature and Magnitude of Landscape Impacts in the Operational Stage

Physical Landscape Resources

7.11.3 The formation of new cut platforms and both underground and superstructures within the site would permanently alter the topography (LR1). However, compared to the overall context of the area, the impact on topography and landform will remain small upon completion and in the long term.

7.11.4 The retention and re-use of soil stripped (LR2) from the area of the works, in the landscape mitigation planting, will help to reduce the magnitude of change on this landscape resources to slight level during the Opening Day and negligible in the long term.

7.11.5 The extensive area of proposed compensation tree planting on the northeastern portion of the site and along the STW boundaries, would in time mitigate the loss of existing trees (LR3). The magnitude of impact, however at the Opening Day would be slight, and with the growth in the new vegetation, would become negligible in the long term.

7.11.6 The proposed compensation planting of grassland / shurbland (LR4) on top of underground structures (Emergency Storage Tank, and Sequencing Batch Reactor), and, planting of both tall and low shrubs the existing / new formed slopes and along the STW boundary will in time mitigate the magnitude of the impacts to negligible level at Opening Day and would become an intermediate positive impact in time.

7.11.7 The magnitude of change of streamcourse (LR5) would remain negligible level at both Opening Day and over the long term.

Human and Cultural Landscape Resources

7.11.8 The operation of the STW would not directly affect the Tian Tan Buddha (LR6), the columbarium (LR7), and Po Lin Monastery (LR8), so the magnitude of impacts would remain negligible at Opening Day and in the long term.

Settlements

7.11.9 Given that mitigation measures would be applied to blend the STW site with the existing Ngong Ping settlements (LR9) during operation stage. The settlements would still have a physical impact on the overall topography and disturbance to the surrounding landscape. The magnitude of change would remain slight levels at the Opening Day and in long term.

Landscape Character Zones

7.11.10 The landscape character areas of Lantau Peak natural uplands (LC1) would similarly be able to reduce the level of impacts in time. The mitigation measures including careful engineering, sensitive compensation planting, and sensitive architectural detailing of superstructures proposed, would reduce the overall magnitude of the impact to intermediate levels at Opening Day, and to slight levels in the long term.

7.11.11 The extensive shrub and tree planting along the northern portion of the STW site would similarly be able to reduce the impact on the Ngong Ping Development area (LC2) in time. The magnitude of change on the character area would reduce to small at Opening Day and to negligible over time.

Nature and Magnitude of Visual Impacts during the Operational Stage

Residential

7.11.12 Grass hydroseeding and shrub and tree planting on new formed slopes to screen the superstructures of the STW site would effectively reduce the magnitude of change in the view from existing villagers at Ngong Ping area (R1). The impact would reduce to small levels at Opening Day and slight levels by Year 10.

7.11.13 Similarly grass hydroseeding, shrub and tree planting would mitigate the visual impacts for residents of Po Lin Monastery complex (R2). The magnitude of changes in the view from the Po Lin residents would be negligible at Opening Day and by Year 10.

Occupational Users

7.11.14 The proposed planting would reduce impacts on long range views of occupational users at the youth hostel / Tea Garden Restaurant (O1) would be negligible at Opening Day and by Year 10.

7.11.15 Screen trees with shrub planting would preserve the scale of impact to negligible levels at Opening Day and in long term in view of occupational users of Po Lin Monastery (O2).

Recreational Users

7.11.16 Although the architectural treatment of the superstructures and proposed planting would reduce the colour contrast between the STW site and the surrounding natural vegetation in the long range view of visitors of the Buddha Statute (C1). Given the elevated nature of the views, there is likely that the magnitude of change would be intermediate levels at Opening Day and small in the long term.

7.11.17 Screen trees with shrub planting would preserve the scale of impact to negligible levels at Opening Day and in long term in view of visitors of Po Lin Monastery (C2).

7.11.18 Grass hydroseeding, tree and shrub planting on new formed slopes, and the retention of woodland trees to screen the superstructures of the STW. Due to the long range view the impact would be negligible at Opening Day and by Year 10 in view of visitors of the youth hostel / Tea Garden Restaurant (C3).

7.11.19 The proposed planting, and careful architectural treatment would lessen the colour contrast of the STW site with its surroundings in very long range view of the recreational users of Nei Lak Shan Ridgeline trail and associated footpaths (C4). However, given the elevated nature of the views, the magnitude of change is considered to be small at both Opening Day and in long term.

7.11.20 Proposed mitigation planting along the newly formed slopes and careful architectural design of new buildings, it would reduce the impacts on views of visitors of columbarium (C5). Due to the short range of views from columbarium to the STW site, the magnitude of change resulting from works would still be moderate levels at Opening Day but would reduce to small in long term.

7.11.21 The magnitude of changes in views of passengers of future Tung Chung Cable Car System (C6) would depend on the location of the cable car terminal, its design and layout, and the angle of how cable car approaches. However, passengers are likely to have a medium distance, oblique views down to the proposed STW site. Given the panoramic nature of other alternative views, careful architectural design, and proposed screening mitigation measures, the magnitude of change would be intermediate at Opening Day and with the growth of screen vegetation, small in long term.

Travellers

7.11.22 Tree and shrub planting along the southeastern boundary should mitigate the impact on view of motorists / travellers on Ngong Ping Road (T1). The growth of the planting is likely to reduce this further to slight levels in the Opening Year and in long term.

7.11.23 Travellers at the future public transport interchanges (T2) would have a short range but a brief view looking at the STW site. In consideration that these travellers are only staying for a short time, the proposed screening mitigation measures is likely to reduce the impact to moderate level in Opening Day and small in long term.

7.11.24 A summary of the significance of the landscape and visual impacts during the Operational Stage is illustrated in Table 7.8 and Table 7.9for landscape and visual impacts respectively.

7.12 Mitigation Measures During the Operating Stage

7.12.1 Landscape and visual mitigation measures which should be incorporated within permanent landscape design to ameliorate impacts caused during the operation stage. This is illustrated in Table 7.7 , together with the proposed funding, implementation, and management and maintenance agencies. The mitigation measures are illustrated in Drawing 23400/EN/044.

Table 7.7 Proposed Operation Stage Mitigation Measures

No.

Mitigation Measures

Funding Agency

Implementation Agency

Management Agency

Maintenance Agency

OM 1

Grass hydroseeding and planting of native shrubs and trees to provide green backdrop to the development, and to blend the slope into the surrounding natural slopes, and to compensate for grass and shrubs and trees lost during construction

DSD

DSD

DSD

DSD

OM 2

Grass hydroseeding (with groundcover) on top of the underground structures within STW site

DSD

DSD

DSD

DSD

OM 3

Grass hydroseeding and tree and shrub planting to screen elevated structures along the souutheastern boundary of STW site, to provide visual interest, and to provide shade and shelter.

DSD

DSD

DSD

DSD

OM 4

Sensitive architectural and chromatic treatment of the elevated structures

DSD

DSD

DSD

DSD

OM 5

Night Lighting should be designed to minimise glare to all receivers.

DSD

DSD

DSD

DSD

 

Planting Proposal

 

7.12.2 Planting Proposals are shown on the Landscape Mitigation Measures Plans, Drawing 23400/EN/044. The Landscape Mitigation Plans has three objectives: -

to compensate for the loss of existing vegetation,

to screen sensitive views, and

as an environmental benefit to local residents, workers, recreational users and tourists.

7.12.3 All land disturbed during the course of the works, that will not subsequently be occupied by the permanent works, will be planted with either native woodland and shrub species. As a general approach, where these areas lie within or alongside areas of the existing woodland then woodland species will be planted. In areas bordered by tall and low shrubs, then appropriate shrub species will be established.

7.12.4 The steepness of the new slopes poses a constraint on the species that can be planted. Slopes with a gradient of not more than 35 degrees would be suitable for the establishment of tall trees species, and slopes in excess of 45 degrees would not be appropriate for small tree and tall shrub species. Soil cut slopes in excess of 55-60 degrees would not be suitable for the establishment of vegetation and would be hydro-mulched to provide green appearance.

7.12.5 Grass hydroseeding with hard groundcover is also proposed on top of the underground structures. This is to provide solid platform for the grassing and to enhance the value of landscape resource and character of these areas.

7.12.6 The limits of disturbance have to be contained as far as is practical within the STW site. This results in only a very limited amount of space for re-planting.


Architectural Treatment of Structures


7.12.7 The Ngong Ping STW would be visible from the existing Tian Tan Buddha, the Po Lin Monastery, the proposed Tung Chung Cable Car System, and to a lesser extent from the Ngong Ping Road.

7.12.8 To minimise the visual impacts of the surrounding areas, visual appearance of elevated structures within the STW site would be sensitively designed and help to blend them with the surrounding landscaped setting.

7.12.9 The massing, shape and layout of the building structures within the STW site should be compatible with the surrounding environs. This architectural design of buildings should be similar to other monastery buildings located within the Ngong Ping area in order to decrease the viewers from distance. Selection of building materials should be able to blend with the environs and should minimise the glare from reflected light source arising from the development. Structure being put underground should have compensatory planting over the top, aimed to blend in with the existing landscaped setting. Key design approaches for the STW are outlined below:-

Provision of landscaped banks and tall tree plantings to minimise the visible extent of the STW complex.

Provision of soft landscaping in keeping with the local flora where there is direct line of sight view in order to maintain the country park atmosphere.

Locating as many structures below ground level as is practicable.

Minimising the height of structures as much as possible to make them compatible with the scale of the existing structures.

Distributing the buildings around the site and varying their orientation to create a "village feel" to the STW complex.

Architectural treatment of building walls, roofs, building materials, building shape, and scale will employ traditional Chinese architectural building elements and colours, interpreted in a contemporary manner in keeping with the area to minimise visual intrusion.

Night Glare

7.12.10 The night lighting produced from the Ngong Ping STW would be visible from existing Tian Tan Buddha, along Ngong Ping Road, and the proposed Tung Chung Cable Car Terminal. The level of night lighting will be kept to minimal and the direction of the lighting should be facing inwards to minimise the visual intrusion. Selection of building materials should also be considered in keeping reflection of day and night glare from the buildings.

 

7.12.11 Illustration of the likely impacts on key views of the proposed STW site at Opening Day are illustrated in the photomontages in Drawing 23400/EN/048(049, 050, 051, 052) to Drawing 23400/EN/053. The STW site layout plan and elevation drawings are illustrated in Drawing 23400/EN/045(046)to Drawing 23400/EN/047 .

 

7.13 Prediction of Significance of Landscape Impacts in the Operating stage


7.13.1 An assessment of the potential significance of the landscape impacts during the operational stage, before and after mitigation is provided in Table 7.8 and illustrated in Drawing 23400/EN/027. This follows the methodology outlined in Section 7.3 and assumes that appropriate mitigation measures identified in Table 7.7 had been fully implemented.

7.14 Prediction of Significance of Visual Impacts in the Operation Stage

7.14.1 An assessment of the potential significance of the visual impacts during the operation stage, before and after mitigation is provided in Table 7.9, and illustrated in Drawing 23400/EN/041. This follows the methodology outlined in Section 7.3 and assumes that appropriate mitigation measures identified in Table 7.7 had been fully implemented.

Table7.8 Summary of Significance of Landscape Impacts in Operational Stage

Ref

Landscape Receiver

Sensitivity to Change

Extent of Loss (in sq.m)

Magnitude of Change before Mitigation

Magnitude of Change After Mitigation (Day1)

Magnitude of Change After Mitigation (Year 10)

Impact Significance before Mitigation

Impact Significance After Mitigation (Day 1)

Residual (Year10)

LANDSCAPE RESOURCES

 

 

 

 

 

 

 

LR1

Topography and Land Form

High

21,160

Small

Small

Small

Slight

Slight

Slight

LR2

Agricultural Soils

Low

21,160

Intermediate

Small

Negligible

Slight

Slight

Negligible

LR3

Woodland Trees

Low

3,055

Small

Small

Negligible

Slight

Slight

Negligible

LR4

Grassland / shrubland

Low

18,105

Small

Small

Intermediate (+ve)

Negligible

Negligible

Moderate (+ve)

LR5

Stream Courses

Medium

0

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

LR6

Tian Tan Buddha

High

-

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

LR7

Columbarium

High

-

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

LR8

Po Lin Monastery

High

-

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

LR9

Settlements

High

-

Small

Small

Small

Slight

Slight

Slight

LANDSCAPE CHARACTER

             

LC1

Natural Uplands

Medium

0

Intermediate

Intermediate

Small

Moderate

Moderate

Slight

LC2

Ngong Ping Development

High

-

Moderate

Small

Negligible

Moderate

Slight

Negligible

Notes: (1) All impacts are negative / adverse unless otherwise stated

(2) Source of landscape impact on all resources / character areas would be earthworks, construction activity, and the formation of new roads / structures / buildings / slopes etc.

Table7.9 Summary of Significance of Visual Impacts in Operational Stage

VSR

Key Visually Sensitive Receiver (VSR)

Source(s) of Impacts on VSR

Distance Between VSR and Source

Receptor sensitivity

Magnitude of Change before Mitigation

Magnitude of Change after Mitigation

(Day 1)

Magnitude of Change after Mitigation

(Year 10)

Impact Significance before Mitigation

Impact Significance after Mitigation (Day 1)

Impact Significance after Mitigation (Year 10)

RECREATIONAL RECEIVERS

                 

C1

Visitors to Buddha Statute

New building / slope works

450-800

High

Intermediate

Intermediate

Intermediate

Moderate

Moderate

Slight

C2

Recreation Users to Po Lin Monastery

New building / slope works

450-800

Medium

Small

Negligible

Negligible

Slight

Negligible

Negligible

C3

Recreational Users of Youth Hostels / Tea Garden Restaurant

New building / slope works

800-1000

Low

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

C4

Hikers of Nei Lak Shan Ridgeline Trail and Associated Footpaths

New building / slope works

500-1200

Medium

Small

Small

Small

Slight

Slight

Slight

C5

Visitors to Columbarium

New building / slope works

10-300

Medium

Intermediate

Intermediate

Small

Moderate

Moderate

Slight

C6

Future Users of the Ngong Ping Cable Car Terminal

New building / slope works

10-300

High

-

Intermediate

Small

-

Moderate

Slight

RESIDENTIAL RECEIVERS

 

 

 

 

 

 

 

 

 

R1

Residents of Ngong Ping Villages

New building / slope works

20-700

High

Intermediate

Small

Small

Moderate

Slight

Slight

R2

Residents of Po Lin Monastery Complex

 

 

New building / slope works

450-800

High

Small

Negligible

Negligible

Slight

Negligible

Negligible

OCCUPATIONAL RECEIVERS

                 

O1

Workers at the youth hostel / Tea Garden Restaurant

New building / slope works

 

800-1000

Medium

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

O2

Workers at Po Lin Monastery

New building / slope works

 

450-800

Medium

Small

Negligible

Negligible

Slight

Negligible

Negligible

TRAVELLERS

                 

T1

Motorists / travellers on Ngong Ping Road

New building / slope works / road works

10-300

High

Small

Small

Small

Slight

Slight

Slight

T2

Travellers on the future public transport interchange

New building / slope works / road works

10-30

High

-

Intermediate

Small

-

Moderate

Slight

Notes: All impacts are negative / adverse unless otherwise state

7.15 Residual Impacts


7.15.1 Residual impacts are those persist after the mitigation planting works have become fully effective. This is assumed to be at a nominal point ten years after the date of completion. The residual impacts represents the long term effect on the landscape and visual context of the area that would be a direct consequence of the proposed STW site.

7.15.2 The significance of residual landscape impacts is illustrated in Table 7.8 and illustrated in Drawing 23400/EN/028. This assumes that the appropriate mitigation measures identified in Table 7.7 would be implemented, and that the full effect of soft landscape mitigation measures has been be realised.

7.15.3 The significance of residual visual impacts is illustrated in Table 7.9 and illustrated in Drawing 23400/EN/042. This assumes that the appropriate mitigation measures identified in Table 7.7 would be implemented, and that the full effect of the soft landscape mitigation measures had been be realised.

7.15.4 Illustration of the likely on key views of the proposed STW site at Year 10 are illustrated in the photomontages in Drawing 23400/EN/048(049, 050, 051, 052) to Drawing 23400/EN/053. The STW site layout plans and elevation drawings are illustrated in Drawing 23400/EN/045 (046)to Drawing 23400/EN/047.

7.16 Conclusions


Landscape Impacts

7.16.1 The proposed STW will fall within GB zone. Since the proposed development may not be compatible with the planning intention of GB zone, there are likely to be land use impacts. Hence, it will be important to minimise the possible land use interface with the existing and planned / possible developments (i.e. possible locations for cable car link and associated developments) during construction and operation stage.

7.16.2 The proposed sewage plant would also create adverse landscape and visual impacts to the existing natural setting of conservation areas, SSSI, Lantau North Country Park, and Lantau Trail. It is therefore important that the future development should be sensitively designed and not adversely affects the existing landscape setting.

7.16.3 The proposed works of the STW site include excavation of soil for underground facilities at the western the eastern portion of the site. Proposed works also include construction of elevated structures predominately located on the southern and central part of the STW site. The works also comprise formation of new slopes on the northern STW boundary and a new access road linking with the Ngong Ping Road adjacent to the right.

7.16.4 The landscape resources and character of the surrounding area is of the highest quality and is sensitive to change. Sensitive engineering, architectural structure treatment and effective landscape planting within the STW site has reduced the extent of disturbance to an absolute minimum. This would result in relatively limited landscape impacts on landscape resources and character.

7.16.5 The STW would result in some impacts on existing landscape resources on the surrounding areas. There would be impacts during construction on soils and woodland trees. However, all of these would be reduced to negligible levels in the long term with the growth of proposed grassing and shrub planting on newly formed slopes and disturbed areas within the STW site.

 

7.16.6 The proposed grass hydroseeding on top of the underground structures would result in a moderate positive impact on this landscape resource. There would also be a slight negative long term impacts on the topography due to formation of new slopes and construction of elevated structures.

 

7.16.7 There would be moderate impacts on the character of natural uplands on the surrounding areas and on the Ngong Ping Development during construction stage. With appropriate grassing within and along the STW site, these impacts would reduce to slight and negligible levels in long term.

Visual Impacts

7.16.8 The popular tourist attractions and the natural upland character of the surrounding area make the area visually very sensitive. There would be a number of visually sensitive receiver affected by the proposed STW works. However, many of these would have partial or oblique views of medium to long distance.

7.16.9 There would be moderate visual impacts during construction on residents of Ngong Ping villagers high up on the slope and on the lower area, visitors to the columbarium, and motorists / travellers on Ngong Ping Road. The proposed grassing, planting of woodland tree species and shrubs would reduce these impacts to slight levels in long term.

7.16.10 There would also be moderate visual impacts during construction on visitors to Buddha Statue and the future users of the Tung Chung Cable Car System and the public transport interchange. These impacts would reduce to slight in long term given that all mitigation measures are fully applied.

7.16.11 There would be limited views of users at Po Lin Monastery and the youth hostel. This is due to the existing buildings, and dense vegetation that screen most of the views to the STW site. The proposed mitigation measures would further reduce the impacts to negligible level in long term.

7.17 Recommendations

7.17.1 If the improvement works are to proceed it is recommended that all the landscape mitigation measures described for both the construction stage, described in  Table 7.6, and the operational stage, described in  Table 7.7, together with the proposed funding, implementation, and management and maintenance agencies be adopted in full.

 

7.17.2 It is further recommended that all landscape mitigation measures, including planting works, hard landscape treatments, as well as architectural finishes to all elevated and engineering structures be supervised by site staff who have suitable qualifications in horticultural, landscape architectural, or architectural qualifications.

7.17.3 It is also recommended that requirements for monitoring the implementation of landscape mitigation measures set out in the Environmental Monitoring and Audit Manual be fully implemented, and audited by independent checkers.

7.18 Environmental Monitoring and Audit


7.18.1 In light of the landscape and visual impacts predicted, it is recommended that the EM&A during the design, construction and operational stages be undertaken. The design stage EM&A will consist of auditing the detailed landscape designs. Construction and operational stage EM&A will comprise audit of the EIA recommendations together with planting and planting establishment in the form of site inspection. The operational stage auditing will be undertaken for one year during the Contractor's maintenance period. Further details of the specific EM&A requirements are detailed in Section 11 of this report and in the EM&A Manual.