3. AIR QUALITY IMPACT

3.1 Introduction

3.1.1.1 Air quality is considered as one of the key environmental issues of concern during both construction and operational phases of the proposed project. During the construction phase, there will be potential dust impacts on existing and future sensitive receivers from the construction activities undertaken at the project sites. During the operational phase, potential odour emissions from the proposed expanded San Wai STW and Ha Tsuen Pumping Station on nearby sensitive receivers would be a major environmental issue of concern.

3.1.1.2 This section presents the assessments on construction phase dust impacts and the operational phase odour emission impacts.

3.2 Environmental Legislation, Policies, Plans, Standards and Criteria

3.2.1.1 The air quality impact assessment criteria make reference to the Air Pollution Control Ordinance (APCO) (Cap.311), and Annex 4 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

3.2.1.2 For construction dust, Annex 4 of EIAO-TM specifies a total suspended particulates (TSP) limit in air over an 1-hour period of 500 µgm-3. The maximum acceptable TSP concentration averaged over 24-hour and annual periods is 260 µgm-3 and 80 µgm-3 respectively as defined in the Air Quality Objectives (AQOs) encompass by the APCO.

3.2.1.3 The Air Pollution Control (Construction Dust) Regulation specifies processes that require special control. Contractors and site agents are required to inform EPD before commence "notifiable work" and adopt dust reduction measures while carrying out "notifiable work" or "regulatory work" as defined under the regulation. "Notifiable work" includes site formation, reclamation, demolition of a building, construction of the foundation or superstructure of a building, road construction work, etc. "Regulatory work" includes road opening or resurfacing work, slope stabilisation work, handling or transfer of dusty materials, etc

3.2.1.4 Amendment to the APCO (1993) has included objectionable odour as an air pollutant, but with no quantitative criteria. The EIAO-TM stipulates an odour nuisance limit of 5 odour units (OU) based on an averaging time of 5 seconds. An OU is defined as the dilution factor required for samples of odorous gases to be diluted with clean odour-free air to the detection threshold.

3.3 Description of the Environment

3.3.1.1 The vicinity of the western part of the study area is mostly rural in nature (and with some container storage areas) and become more urbanised in the eastern part. Existing air quality in the area is influenced by emissions from:
· Road network within and around the study area; and
· Construction activities within and around the study area.

3.3.1.2 There is currently no EPD-operated air quality monitoring station located within the study area. Historical air quality monitoring data from the nearest station, namely the rooftop Yuen Long station operated by EPD are taken to examine the historical trend of the air quality condition in the vicinity of the study area.

3.3.1.3 The last three published years of TSP monitoring data, namely 1998, 1999 and 2000 at Yuen Long station are tabulated in Table 3.1.

Table 3.1 EPD’s TSP Monitoring Data at Yuen Long Station, 1998 to 2000

Year

Highest 2 Daily Average

Annual Average

1998

198 / 189

97

1999

301 / 241

102

2000

288 / 194

95

Note: Monitoring results exceeded AQO are shown as bold characters.

3.3.1.4 As shown by the monitoring results in Table 3.1 for the rooftop Yuen Long station, it is observed that the TSP concentrations in the Yuen Long area remained high during the last few years and exceedance of the annual average AQO for TSP was recorded for the last three years. The reasons may be largely due to dust emissions from the construction activities and traffic emissions from road network.

3.3.1.5 As shown in Figure 1.8, the proposed Deep Bay Link will encroach upon the southwestern corner of the existing San Wai STW in the form of a viaduct. With reference to the Environmental Impact Assessment Report for Agreement No. CE109/98 Deep Bay Link Investigation and Preliminary Design (July 2002), the modelling results showed exceedance of the 24-hour average AQO for nitrogen dioxide at 10m above ground at the existing San Wai STW under the worst-case scenario. The predicted exceedance is at 10m above ground level and covers an area within about 50m from the southwestern corner of the existing San Wai STW. Since there is no sensitive use located at the area of exceedance within the existing and the future San Wai STW, adverse air quality impact is therefore not expected.

3.4 Air Sensitive Receivers

3.4.1.1 In accordance with the definition stipulated in Annex 12 of EIAO-TM, air sensitive receiver (ASR) is defined as:
· Any domestic premises, hotel, hostel, hospital, clinic, nursery, temporary housing accommodation, school, educational institution, office, factory, shop, shopping centre, place of public worship, library, court of law, sports stadium or performing arts centre; and
· Any other premises or place with which, in terms of duration or number of people affected, has a similar sensitivity to the air pollutants as the above listed premises and places.

3.4.1.2 The Assessment Area for air quality impact assessment includes an area 500m from the boundary of the works areas. Figures 3.1 and 3.2 show respectively the Assessment Area around the proposed expanded San Wai STW and Ha Tsuen Pumping Station. Existing land uses within the Assessment Area of San Wai STW include mainly agricultural land, container storage areas, and scattered village houses. Whereas the existing land uses around the Ha Tsuen Pumping Station are mainly public and private residential housing estates with a number of schools.

3.4.1.3 Future ASRs around the proposed expanded San Wai STW and Ha Tsuen Pumping Station include the planned sensitive land uses of the HSKNDA and HSK North NDA as shown in Figure 1.9. Immediately to the southwest of the proposed San Wai STW is the proposed Deep Bay Link. The road users of the proposed Deep Bay Link might be susceptible to the future odour impacts from the operation of San Wai STW. For reference purpose, the closest point of San Wai STW to Deep Bay Link is taken as an air quality assessment point (A41) of the operational phase odour impact assessment for San Wai STW.

3.4.1.4 Existing and future representative ASRs within the Assessment Area likely to be affected by the construction and/or operation of the San Wai STW, Ha Tsuen Pumping Station, and emergency bypass culvert are identified as assessment points for this assessment. The selected assessment points are summarised in Tables 3.2 to 3.4 and are shown in Figures 3.1 to 3.3. With reference to Section 1.2 of this report, the proposed emergency bypass will be constructed in the form of box culvert and will only be used for conveying treated effluent from San Wai STW. The major air quality impact of the proposed emergency bypass culvert would be associated with the construction activities.

Table 3.2 Identified Air Quality Assessment Points Around the San Wai STW

Assessment Point

Location

Distance from the Boundary of Expanded San Wai STW

Subject to construction phase impact

Subject to operational phase impact

A15

Tseung Kong Wai

443m

ü

ü

A16

Tseung Kong Wai

450m

ü

ü

A17

Tseung Kong Wai

368m

ü

ü

A31

Villa Oasis

483m

ü

ü

A37

San Wai village house

208m

ü

ü

A38

San Wai village house

190m

ü

ü

A39

San Wai village house

260m

ü

ü

A40

San Wai village house

270m

ü

ü

A41

Deep Bay Link (closest point to San Wai STW)

0m

 

ü

A42

Area 5a of HSKNDA (future ASR)

213m

 

ü

 

Table 3.3 Identified Air Quality Assessment Points Around the Ha Tsuen Pumping Station

Assessment Point

Location

Distance from the Boundary of Expanded Ha Tsuen PS

Subject to construction phase impact

Subject to operational phase Impact

A1

Ho Ming Primary School

134m

ü

ü

A2

Pui Shing Catholic Secondary School

170m

ü

ü

A3

Ho Tak Sum Primary School

173m

ü

ü

A4

QE School Old Students' Association Branch Primary School

344m

ü

ü

A5

Tang Siu Tong Secondary School

222m

ü

ü

A6

Tin Shing Court

99m

ü

ü

A7

Tin Shing Court

126m

ü

ü

A8

Tin Shing Court

153m

ü

ü

A9

Tin Oi Court

470m

ü

ü

A11

Home for Aged at Sha Chau Lei Road

183m

ü

ü

A12

Sha Chau Lei Tsuen

225m

ü

ü

A43

HSK North NDA Residential Area (future ASR)

124m

 

ü

A44

HSK North NDA Residential Area (future ASR)

57m

 

ü

A45

HSK North NDA Residential Area (future ASR)

56m

 

ü

A46

HSK North NDA Educational Land Use (future ASR)

55m

 

ü

A47

HSK North NDA Educational Land Use (future ASR)

57m

 

ü

A48

HSK North NDA Residential Area (future ASR)

32m

 

ü

A49

HSK North NDA Residential Area (future ASR)

36m

 

ü

A50

HSK North NDA Residential Area (future ASR)

56m

 

ü

A51

HSK North NDA Commercial Area (future ASR)

128m

 

ü

 

Table 3.4 Identified Air Quality Assessment Points Around the Emergency Bypass Culvert

Assessment Point

Location

Distance from Emergency Bypass Culvert

Alternative

1

2

3

4

A11

Home for Aged at Sha Chau Lei Road

>500m

>500m

322m

>500m

A12

Sha Chau Lei Tsuen

476m

>500m

274m

>500m

A14

Sik Kong Wai

462m

>500m

445m

>500m

A15

Tseung Kong Wai

>500m

>500m

423m

92m

A16

Tseung Kong Wai

466m

>500m

386m

159m

A17

Tseung Kong Wai

415m

>500m

328m

132m

A21

San Sang Tsuen

249m

148m

455m

>500m

A22

San Lee Uk Tsuen

>500m

123m

>500m

>500m

A23

San Lee Uk Tsuen

>500m

238m

>500m

>500m

A24

San Uk Tsuen

139m

409m

110m

>500m

A25

San Uk Tsuen

228m

478m

147m

>500m

A26

Shek Po Tsuen

349m

420m

235m

>500m

A27

Shek Po Tsuen

340m

402m

268m

>500m

A28

Kau Lee Uk Tsuen

25m

32m

245m

>500m

A29

Kau Lee Uk Tsuen

14m

147m

121m

>500m

A30

Kau Lee Uk Tsuen

8m

238m

38m

>500m

A31

Villa Oasis

485m

>500m

408m

182m

A32

Villa Oasis

448m

>500m

372m

246m

A33

Sunny Villas

>500m

>500m

>500m

255m

A34

Sunny Villas

>500m

>500m

>500m

187m

A35

King's Garden

>500m

>500m

491m

270m

A36

King's Garden

>500m

>500m

471m

278m

A37

San Wai village house

335m

>500m

263m

181m

A38

San Wai village house

287m

>500m

212m

163m

A39

San Wai village house

322m

>500m

236m

193m

A40

San Wai village house

441m

>500m

401m

37m

3.5 Enhancement Measures to Control Emergency Discharge

3.5.1 General

3.5.1.1 With reference to Section 1.2 of this report, in order to reduce the chance of discharging raw sewage into Tin Shui Wai Drainage Channel and hence Deep Bay, an emergency bypass culvert will be constructed in the form of box culvert from San Wai STW to nearby drainage channel as part of this project.

3.5.1.2 Four alternative alignments of the proposed emergency bypass culvert were considered and are shown in Figure 3.4. Figure 3.4 also indicates the extent of the construction works areas associated with the four alternative alignments.

3.5.2 Construction Phase Impact

3.5.2.1 In general, the construction works areas for the emergency bypass culverts would be a 10m wide strip along the culvert alignment from the expanded San Wai STW up to the connection point with the existing Ting Shui Wai Drainage Channel for Alternatives 1, 2, and 3, and with the existing Lo Uk Tsuen Drainage Channel for Alternative 4. A summary of the length and the total construction works areas for the four alternatives is shown in Table 3.5.

Table 3.5 Length and Total Construction Works Area for the Four Alternatives of the Proposed Emergency Bypass Culvert

Alternative

Length

Works Area

1

1300m

13,000m2

2

1600m

16,000m2

3

1350m

13,500m2

4

600m *

6,000m2

* The length of Alternative 4 requiring construction (600m) is from San Wai STW to the existing Lo Uk Tsuen drainage channel only.

3.5.2.2 It is expected that the works related to the construction of the emergency bypass culvert would be carried out section by section. The dust generated from each section of the culvert construction works would be of small scale, localised, and short-term. By comparing the length and works area associated with the four alternatives, Alternative 4 would involve the shortest length and the smallest works area. The dust emissions associated with the construction of Alternative 4 would thus be the lowest among the four alternatives.

3.5.2.3 With the implementation of proper dust control and suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and described in Section 3.9 below, adverse dust impact from the construction activities of the proposed emergency bypass culvert is not expected.

3.5.3 Operational Phase Impact

3.5.3.1 All the four alternatives of the emergency bypass culvert will be constructed in the form of box culvert up to the connection point with the existing Ting Shui Wai Drainage Channel for Alternatives 1, 2, and 3, and with the existing Lo Uk Tsuen Drainage Channel for Alternative 4. The existing drainage channels will then convey the effluent to the Deep Bay.

3.5.3.2 With reference to the discussion in Section 1.2, the proposed emergency bypass culvert will only be used for conveying treated effluent from San Wai STW under the emergency event when the NWNT effluent tunnel or the Urmston Road outfall is out of operation. Since the residual sulphide content in the treated effluent would be minimal if any. Hydrogen sulphide emission from treated effluent flowing along the proposed emergency bypass culvert and the existing open drainage channels would thus not be expected. Odour impact at the nearby existing and future ASRs (including Tin Shui Wai New Town, HKSNDA and HSK Norht NDA) from the operation of the proposed emergency bypass culvert is therefore not anticipated.

3.5.3.3 Other than the scenario described above with the break down of the NWNT effluent tunnel or the Urmston Road outfall, the other emergency discharge scenarios for the existing and the future arrangements are the same and would result in the discharge of raw sewage. Nonetheless, the chance of discharging raw sewage into the Tin Shui Wai Drainage Channel is in fact very remote and has not happened since the commissioning of the existing San Wai STW, the Ha Tsuen Pumping Station, and the NWNT effluent tunnel and Urmston Road outfall for more than 10 years. Besides routine monitoring, inspection, and maintenance to ensure satisfactory working condition of the system, the following have been and will be applied to the Ha Tsuen Pumping Station to further reduce the chance of system failure:

Standby pumps and screens to facilitate maintenance and repair of equipment;
Back-up power in the form of dual power supply;
24-hour manned pumping station; and
Hand-cleaned bar screen at overflow bypass to prevent discharge of floating solids.

3.5.3.4 A contingency plan would also be developed at the detailed design stage to deal with the emergency discharges that may occur during the operational stage of the project. It is recommended to include the following items in the contingency plan:

Locations of the sensitive receivers in the vicinity of the emergency discharges at Deep Bay and Urmston Road;
A list of relevant government bodies to be informed and to provide assistance in the event of emergency discharges. Information on key contact persons and telephone numbers should be included;
Reporting procedures required in the event of emergency discharges; and
Procedures listing the most effective means in rectifying the breakdown of San Wai STW, Urmston Road Tunnel or Ha Tsuen Pumping Station in order to minimise the discharge duration.

3.6 Assessment Methodology

3.6.1 Construction Phase Assessment

3.6.1.1 Construction dust impacts are assessed by determining dust-generating activities and recommending corresponding dust control and suppression measures. Details of dust-generating construction activities, including the site area and the construction program were reviewed.

3.6.1.2 The construction works involved in this project include works associated with the construction of the proposed expanded San Wai STW, the expanded Ha Tsuen Pumping Station, and the emergency bypass culvert.

Emission Inventories

3.6.1.3 The major potential air quality impacts during the construction phase of the proposed expanded San Wai STW and the expanded Ha Tsuen Pumping Station would result from dust arising from construction activities including:
· Site clearance and preparation;
· Excavation and filling;
· Open site erosion;
· Construction of foundation and superstructure; and
· Handling and transportation of construction and demolition material.

3.6.1.4 With reference to Section 1.3 of this report, apart from the construction of this project, there are a number of major projects planned in the vicinity of the study area which might cause cumulative construction phase impacts to the environment. These projects include YLKTSSD Stage 1, YLKTSSD Stage 2, Deep Bay Link, and the HSKNDA. Concurrent construction activities identified within 500m from the San Wai STW and the Ha Tsuen Pumping Station are shown in Figures 3A.1 and 3A.2 in Appendix 3A. For the purpose of this assessment, it was assumed that all these construction activities, together with the construction of preferred Alternative 4 of the proposed emergency bypass culvert, would occur at the same time. All these construction activities were included in the dust modelling to predict the worst-case cumulative dust impacts at the assessment points. Details of the construction dust emissions calculation are presented in Appendix 3A.

3.6.1.5 The prediction of dust emissions was based on typical values and emission factors from United States Environmental Protection Agency (USEPA) Compilation of Air Pollution Emission Factors (AP-42), 5th Edition. A ten-hour working day was assumed during construction phase of the Project. References of the calculations of dust emission factors for different dust generating activities are listed in Table 3.6.

Table 3.6 References of Dust Emission Factors for Different Activities

Activities

References (AP-42, 5th Edition)

Dust emissions due to truck loading and unloading

Table 11.9-4

Dust emissions due to bulldozing of overburden

Table 11.9-2

Dust emission due to vehicle traffic on unpaved site roads

Section 13.2.2

Wind erosion of open site

Table 11.9-4

 

3.6.1.6 In this assessment, dust suppression measures and estimated mitigation efficiencies were incorporated into the dust emission calculations. With reference to Section 11.2.4.4 of AP-42 4th Edition, dust emissions from construction areas could be reduced by 50% by twice daily watering with complete coverage of active construction areas. Dust generated from vehicle traffic on unpaved site roads would be reduced by lowering the vehicle travelling speed. The percentage dust reduction is estimated in accordance with Section 13.2.2.2 of AP-42 5th Edition.
Dispersion Modelling

3.6.1.7 The USEPA approved Industrial Source Complex Short-Term 3 (ISCST3) model was used to model dust dispersion. The model assumed the algorithm for the "rural" mode, with the dry depletion and gradual plume rise options. The minimum Monin-Obukhov length of 1 metre suggested in ISC3 Model User's Guide for rural area was taken in the ISCST3 model for the dry deposition algorithm.

3.6.1.8 For the purpose of this assessment, it is considered that dust emissions from vehicles moving on unpaved site areas would constitute the major dust source for the general works areas. Since no site specific information is available relating to particle size distribution, and the unpaved road emission equation from AP-42 5th Edition is applicable for different geographical conditions, the particle size distribution used in the ISCST3 model is estimated based on the particle size multipliers for the unpaved road emission equation (Equation (1) of Section 13.2.2 of AP-42 5th Edition). With particle size classes of 0-2.5 µm, 2.5-10 µm and 10-30 µm, the percentage in each class is estimated to be 3.8%, 22.2% and 74% respectively.

3.6.1.9 During daytime working hours (8am to 6pm), it was assumed that dust emissions would be generated from all dust generating activities and site erosion. During nighttime non-working hours (6pm to 8am of the next day), it was assumed that dust emissions would only be generated from site erosion.

Concentration Calculations

3.6.1.10 The worst-case 1-hour average TSP concentrations and the worst-case 24-hour average TSP concentrations are calculated at the assessment points at height of 1.5m above ground, 1.5m is the average height of human breathing zone. Since all the dust generating sources are at ground level, this assessment height would represent the height with the worst-case impact.

3.6.1.11 Historical wind data from Lau Fau Shan meteorological station for year 1996 to 2000 are used in the calculation of the worst-case 1-hour and worst-case 24-hour average concentrations. For each hour of a year, the wind direction from the historical data was taken at 10-degree resolution. Calm hours (hours with wind speed less than 1ms-1) were disregarded in accordance with Section 9.3.4 of the Guideline on Air Quality Models, USEPA. For wind speed less than 2ms-1, the wind speed was conservatively converted to 1ms-1 in the model. For wind speed equal to or larger than 2ms-1, the wind speed was conservatively converted to 2ms-1 in the model.

3.6.1.12 The hourly average concentration for each assessment point is then calculated as described above based on the converted wind direction and wind speed. The maximum 1-hour average and 24-hour average concentrations over the five years are then taken as the worst-case concentrations for the assessment points.

3.6.1.13 After all, background TSP concentration of 87 µgm-3 is added to the results calculated above to produce the worst-case concentrations. The background concentration is derived from EPD's monitoring data for rural area.

3.6.2 Operational Phase Assessment

3.6.2.1 Odour would be one of the key environmental concerns during the operational phase of the project. Potential odour sources within the proposed expanded San Wai STW include the fine screen, the detritors, the sludge holding tanks, the solid handling house, the sludge dewatering house, the rapid mix and flocculation tank, and the primary sedimentation tanks. Whereas the major odour sources for the expanded Ha Tsuen Pumping Station would be the existing and the future wet wells of the pumping station.

3.6.2.2 The odour is mainly due to the presence of hydrogen sulphide (H2S) that is a major odorous gas in sanitary sewer systems, particularly in places with relatively warm climate such as Hong Kong. Sulphide generation would be promoted under anaerobic conditions in sewage conveyance system. H2S is often detectable when all odour components have been diluted to below their detection thresholds. H2S is therefore adopted as the main parameter for assessing odour impact in this study.

3.6.2.3 The odour impact assessment for this study is carried out by first estimating the H2S emission rates using well-recognised equations and then predicting the worst-case H2S concentrations at the assessment points using computer dispersion modelling. As discussed in Section 3.2 above, the EIAO-TM stipulates an odour nuisance limit of 5 odour units (OU) based on an averaging time of 5 seconds. An OU is defined as the dilution factor required for samples of odorous gases to be diluted with clean odour-free air to the detection threshold.

3.6.2.4 Therefore, in order to convert the predicted H2S concentration at the assessment points to OU for compliance checking with the EIAO-TM odour nuisance limit, it is required to correlate the H2S concentration with OU, or in simple term, to determine the detection threshold (i.e. one OU) of H2S for those potential odour sources of concern in this assessment. For the purpose of this assessment, a conservative detection threshold for H2S of 0.0005ppm or 0.00076 mgm-3 is adopted (Source: Woodfield M. and Hall D. (1994). Odour Measurement and Control - An Update. AEA Technology and National Environmental Technology Centre).

Odour Emission Estimation

3.6.2.5 The generation of sulphide in sewerage systems is predominantly an anaerobic microbiological reaction involving sulphate and sulphate-reducing bacteria. The bacteria are concentrated in slimes that form on the walls of sewers and associated facilities. Although sulphide is also produced in the wastewater, these slimes are generally responsible for the majority of sulphide generated in sewerage systems. Apart from the need to have anaerobic conditions, the following factors may also influence the rate of sulphide generation:

Ø Liquid velocity
Ø Soluble electron donor concentration (which effectively is the soluble biochemical oxygen demand concentration)
Ø Sulphate concentration
Ø Temperature

3.6.2.6 Several predictive equations (e.g. Pomeroy, Thistlethwayte) are available for estimating the build-up of sulphide in sewerage systems. These equations were derived empirically from measurements taken on a large number of operating systems. Although different equations and different coefficients adopted in these equations may result in different predictions, in most cases, these equations should provide a reasonable basis for developing sulphide control strategies.

3.6.2.7 Having said that, Thistlethwayte equation has been reported to overestimate the sulphide flux when excess sulphate was available in sewage (USEPA, 1985). The use of the Thistlethwayte equation is also not recommended for low sewage velocity (say less than 0.5m/s) (Technological Standing Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989a). It is recommended in the Hydrogen Sulphide Control Manual (Technological Standing Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989a), one of the most comprehensive guidelines available today, that the Pomeroy equation be used because of its simplicity and reliability in predicting sulphide flux over a wider range of velocities.

Prediction of Sulphide Build-up in Pumping Mains

3.6.2.8 The equation suggested by Pomeroy to predict the sulphide flux from wall slimes (Technological Standing Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989a) is:

G = M[BOD5]1.07T-20

where G sulphide flux from wall slimes, g/m2h

[BOD5] 5-day biochemical oxygen demand

T temperature, oC

M coefficient, m/h

3.6.2.9 A value of 1x10-3 m/h for M was recommended by Pomeroy for normal pressure mains. High values of M (around 2.9x10-3) were obtained by Pomeroy from two systems where the wastewater contained a significant proportion of seawater and where anaerobic corrosion of iron produced a very rough inside surface of the pipe, which promote slime growth.

3.6.2.10 The sulphide generated in the wastewater itself may also form a portion of the total sulphide build-up. The build-up in sulphide concentration by bacteria activity in both slime and wastewater is given by the following equation which was derived by performing a mass balance over the length of the pipeline (Technological Standing Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989a):

Cs = 4G(1 + 0.4D)t / D

where Cs sulphide concentration build-up, mg/l

D diameter of tunnel or sewer, m

t retention time, hour

G sulphide flux, g/m2h


Prediction of Sulphide Build-up in Gravity Sewers

3.6.2.11 With reference to the Hydrogen Sulphide Control Manual (Technological Standing Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989), one of the most comprehensive guidelines available today, the equation below presented by Pomeroy and Parkurst is taken to estimate the sulphide concentration for the gravity sewers:

S2 = {(aS1 – b)e-at + b} / a

where S1 sulphide concentration at start of section, mg/L

S2 sulphide concentration at end of section, mg/L

a = N(SV)3/8 / dm

b = M’[BOD5]1.07T-20/r

t flow time through the section of sewer, h

S total energy head gradient

V sewage velocity, m/s

dm mean hydraulic depth, m

[BOD5] 5-day biochemical oxygen demand

T temperature, oC

r hydraulic radius, m

M’ specific sulphide flux for partially filled pipes, m/h

N constant used in sulphide build-up equation

3.6.2.12 A value of 0.32x10-3 m/h for M' and 0.96 for N recommended by Pomeroy and Parkurst for median or "average" sulphide generation condition are adopted in this assessment in the above equation.

3.6.2.13 Details of the hydrogen sulphide build-up calculations for this assessment are presented in Appendix 3B.

Hydrogen Sulphide Gas Release

3.6.2.14 The odour problem associated with hydrogen sulphide is caused by the release of molecular hydrogen sulphide gas. The rate of release is dependent on many factors, including pH, temperature, turbulence, ventilation conditions, etc.

3.6.2.15 The concentration of molecular hydrogen sulphide in wastewater is dependent on the pH value and the temperature. Figure 3.5 shows this relationship and indicates that pH is more important than temperature in the release of molecular hydrogen sulphide in wastewater, particularly when the pH drops below 8 (towards a more acidic condition). When pH is constant, the release of molecular hydrogen sulphide would increase with decreasing temperature.

3.6.2.16 The major potential odour emission sources within the proposed expanded San Wai STW are shown in Figure 3.6 which include:
· the inlet chamber;
· the fine screen;
· the detritors;
· the sludge holding tanks;
· the solid handling house;
· the sludge dewatering house;
· the rapid mix and flocculation tank;
· the primary sedimentation tanks; and
· the connection channels.

3.6.2.17 For the proposed expanded Ha Tsuen Pumping Station, the major odour sources would be the existing and future wet wells of the pumping station.

3.6.2.18 The H2S emission flux from potential odour sources was estimated as a free surface sewage flow with the following equation (Design Manual on Odor and Corrosion Control in Sanitary Sewerage Systems and Treatment Plants, 1985):

                              f = 0.69(SV)3/8 j [DS]

            where f hydrogen sulphide surface flux, g/m2h

S total energy head gradient

V sewage velocity, m/s

j proportion of dissolved sulphide present in molecular form (see Figure 3.5)

[DS] dissolved sulphide concentration in the wastewater, mg/L

 

3.6.2.19 The H2S emission flux from the wet wells of the proposed expanded Ha Tsuen Pumping Station was calculated in accordance with Chapter 4.3 (Waste Water Collection, Treatment and Storage) of USEPA Compilation of Air Pollution Emission Factors (AP-42), 5th Edition for wastewater sump tank.

3.6.2.20 Details of the H2S emission flux calculations for the major odour sources are presented in Appendix 3B.

Odour Dispersion Modelling

3.6.2.21 The USEPA approved ISCST3 model was used to simulate odour dispersion. Mixing height of 500m and ambient temperature of 298K were taken in the model.

3.6.2.22 To ascertain the worst-case condition, the dispersion modelling considered 5940 predefined separate meteorological conditions. The resolution on the wind direction is set to 2-degree increments. The following stability class and wind speed taken by USEPA for screening purpose were taken in this assessment:

Stability Class     A : 1,2,3 m/s

B : 1,2,3,4,5 m/s

C : 1,2,3,4,5,8,10 m/s

D : 1,2,3,4,5,8,10,15,20 m/s

E : 1,2,3,4,5 m/s

F : 1,2,3,4 m/s

3.6.2.23 Odour assessment was based on a 5-second averaging time due to the short exposure period tolerable by human receptors. However, the shortest averaging time for ISCST3 is one hour, which is also the limitation of most other dispersion models. Conversion of model-computed hourly average results to 5-second values is therefore necessary. The hourly concentration was first converted to a 3-minute average value according to a power law relationship that is stability dependent (Duffee, O'Brien and Ostojic, 1991). Another conversion factor (10 for unstable conditions and 5 for neutral to stable conditions) was then applied to convert the 3-minute average to 5-second average (Keddie, 1980). The odour threshold of hydrogen sulphide was taken as 0.5ppb or 0.76mgm-3. The conversion factors for different stability classes are summarised in Table 3.7.

Table 3.7 Factors for Converting Hourly Average Odour Values to 5-second Average Odour Values

Stability Class

Factors to Convert

Concentration (m g/m3) from 1-hr average to

5-second average

(A)

Concentration (m g/m3) to Odour Unit

(B)

1-hr average concentration (m g/m3) directly to

5-second Odour Unit (OU)

(A x B)

A

44.7

1.32

59.0

B

44.7

1.32

59.0

C

27.1

1.32

35.8

D

9.1

1.32

12.0

E

8.3

1.32

10.9

F

8.3

1.32

10.9

3.7 Identification of Environmental Impacts

3.7.1.1 The major potential air quality impacts during the construction phase of this project would result from dust arising from construction activities including:
· Site clearance and preparation;
· Excavation and filling;
· Open site erosion;
· Construction of foundation and superstructure; and
· Handling and transportation of construction and demolition material.

3.7.1.2 There would likely be cumulative dust impacts during the construction phase of this project arising from concurrent construction activities of other major projects in the vicinity of the study area. These projects include YLKTSSD Stage 1, YLKTSSD Stage 2, Deep Bay Link, and the HSKNDA.

3.7.1.3 During operational phase of the project, major air quality impacts would be related to the potential odour emissions from the activities associated with the proposed expanded San Wai STW and the expanded Ha Tsuen PS.

3.8 Prediction and Evaluation of Environmental Impacts

3.8.1 Construction Phase Impacts

Proposed Expanded San Wai STW

3.8.1.1 The modelling results at the selected assessment points for the mitigated and unmitigated scenarios are presented in Table 3.8. The assessment height is 1.5m above local ground level. All the results presented in the table included the background concentration. For the mitigated scenario, 50% dust reduction by twice daily watering with complete coverage is assumed for the active construction areas of this project. It is also assumed that the construction vehicle travel speed on unpaved site areas of this project would be limited to not more than 10 km per hour.

Table 3.8 Predicted Construction Phase Dust Impacts at Assessment Points Around San Wai STW for Unmitigated and Mitigated Scenarios

Assessment Point

Unmitigated Scenario

Mitigated Scenario

Worst-case 1-hour Average TSP (µgm-3)

Worst-case 24-hour Average TSP (µgm-3)

Worst-case 1-hour Average TSP (µgm-3)

Worst-case 24-hour Average TSP (µgm-3)

A15

306

161

222

127

A16

282

161

187

127

A17

325

178

200

133

A31

274

155

179

125

A32

280

156

196

128

A33

241

135

165

116

A34

265

143

166

120

A35

235

139

173

119

A36

252

143

175

121

A37

515

250

298

170

A38

577

271

330

180

A39

453

221

257

155

A40

476

255

416

224

Highest

577

271

416

224

% AQO / Guideline level

115%

104%

83%

86%

3.8.1.2 As shown by the modelling results, without any dust suppression measures for the construction sites of this project, exceedance of the TSP 1-hour average guideline level of 500 µgm-3 and/or the 24-hour average AQO of 260 µgm-3 would be expected at some existing village houses at San Wai (assessment points A37 and A38) in close proximity to the works areas.

3.8.1.3 With the implementation of dust suppression measures, exceedance of the TSP guideline level and AQO would not be expected. The modelling results showed that the worst-case dust impacts at the assessment points are on average reduced by about 33% and 21% respectively for the 1-hour average TSP level and the 24-hour average TSP level.

3.8.1.4 The predicted worst-case hourly and daily average TSP concentration contours at 1.5m above ground around the proposed expanded San Wai STW for the unmitigated and mitigated scenarios are shown in Figures 3.7 to 3.10. No air sensitive use is identified within the areas with predicted exceedance of the hourly and daily TSP guideline level / AQO during the construction period under the mitigated scenario.

3.8.1.5 With the implementation of proper dust control and suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and described in Section 3.9 below, adverse dust impact from the construction activities of the proposed expanded San Wai STW is not expected.

Proposed Expanded Ha Tsuen Pumping Station

3.8.1.6 The modelling results at the selected assessment points for the mitigated and unmitigated scenarios are presented in Table 3.9. The assessment height is 1.5m above local ground level. All the results presented in the table included the background concentration. For the mitigated scenario, 50% dust reduction by twice daily watering with complete coverage is assumed for the active construction areas of this project. It is also assumed that the construction vehicle travel speed on unpaved site area of this project would be limited to not more than 10 km per hour.

Table 3.9 Predicted Construction Phase Dust Impacts at Assessment Points Around Ha Tsuen Pumping Station for Unmitigated and Mitigated Scenarios

Assessment Point

Unmitigated Scenario

Mitigated Scenario

Worst-case 1-hour Average TSP (µgm-3)

Worst-case 24-hour Average TSP (µgm-3)

Worst-case 1-hour Average TSP (µgm-3)

Worst-case 24-hour Average TSP (µgm-3)

A1

264

154

173

124

A2

239

150

166

120

A3

236

136

171

114

A4

167

107

133

99

A5

196

126

145

109

A6

342

182

234

141

A7

329

174

224

137

A8

270

146

188

122

A9

182

118

160

113

A11

274

152

274

139

A12

302

155

302

148

Highest

342

182

302

148

% AQO / Guideline level

68%

70%

60%

57%

3.8.1.7 As shown by the modelling results, in view of the low intensity of the construction activities involved, exceedance of the guideline level and AQO for TSP would not be expected without any dust suppression measures.

3.8.1.8 With the implementation of dust suppression measures, the modelling results showed that the worst-case dust impacts at the assessment points are on average reduced by about 22% and 14% respectively for the 1-hour average TSP level and the 24-hour average TSP level.

3.8.1.9 The predicted worst-case hourly and daily average TSP concentration contours at 1.5m above ground around the proposed expanded Ha Tsuen Pumping Station for the unmitigated and mitigated scenarios are shown in Figures 3.11 to 3.14. No air sensitive use is identified within the areas with predicted exceedance of the hourly and daily TSP guideline level / AQO during the construction period under the mitigated scenario.

3.8.1.10 With the implementation of proper dust control and suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and described in Section 3.9 below, adverse dust impact from the construction activities of the proposed expanded Ha Tsuen Pumping Station is not expected.

3.8.2 Operational Phase Impacts

Proposed Expanded San Wai STW

3.8.2.1 Two operation scenarios namely the unmitigated and the mitigated scenarios were considered and assessed with the odour dispersion model. In the unmitigated scenario, it was assumed that all major odour sources within the proposed expanded San Wai STW would be open to the atmosphere. All H2S emissions would be dispersed directly from the sources at ground level.

3.8.2.2 In the mitigated scenario, it was assumed that all the major odour sources would be contained within either building structures or enclosures. All the odour emissions from the odour sources would be ventilated to a centralised deodorization unit located at the centre of the STW. In this assessment, it is estimated that an H2S removal efficiency of up to 96% would be required for the deodorization unit so as to achieve the 5 OU criteria at all the ASRs as well as the assessment point representing the road users of Deep Bay Link (assessment point A41). All the treated air would be emitted from the exhaust vent shaft of the deodorization unit with an exhaust height of 5m above ground and an exit velocity of 10m/s.

3.8.2.3 The worst-case 5-second average odour levels were calculated at the assessment points in the vicinity of the proposed expanded San Wai STW as shown in Figure 3.1. The ASRs in the vicinity of the proposed expanded San Wai STW are all low-rise structures. The assessment heights were taken as 1.5m to 30m above local ground level. The modelling results for the unmitigated and mitigated scenarios at the assessment points are shown in Tables 3.10 and 3.11 respectively.

Table 3.10 Predicted Worst-case 5-second Average Odour Levels at Assessment Points Around the Expanded San Wai STW for the Unmitigated Scenario

 

Assessment Points

Predicted 5-second Average Odour Levels ( in OU)

at Different Assessment Height Above Local Ground Level

1.5m

2.5m

5m

7.5m

10m

12.5m

15m

17.5m

20m

22.5m

25m

27.5m

30m

A15

28.5

27.9

25.2

21.3

16.9

12.5

10.9

10.6

10.3

9.9

9.5

9.2

8.7

A16

28.5

27.9

25.3

21.5

17.0

12.7

11.2

10.9

10.5

10.2

9.8

9.4

9.0

A17

35.1

34.2

30.1

24.4

18.3

14.0

13.6

13.1

12.6

12.1

11.5

10.8

10.2

A31

27.7

27.2

24.8

21.3

17.3

13.2

10.3

10.0

9.7

9.4

9.1

8.8

8.4

A32

27.3

26.8

24.6

21.3

17.4

13.5

10.1

9.9

9.6

9.3

9.0

8.7

8.3

A37

53.7

51.1

40.6

27.8

21.3

20.3

19.2

18.0

16.6

16.0

15.4

14.7

14.0

A38

63.7

60.2

46.2

30.2

25.3

24.0

22.4

20.8

19.2

18.4

17.5

16.6

15.6

A39

46.7

44.9

37.3

27.5

20.4

19.6

18.7

17.7

16.6

15.5

14.3

13.7

13.2

A40

25.3

24.4

20.9

16.3

13.9

13.5

12.9

12.7

12.4

12.1

11.7

11.4

11.0

A41

NA

NA

NA

NA

NA

NA

41.5

NA

NA

NA

NA

NA

NA

A42

57.9

54.6

41.7

27.1

25.9

24.5

22.9

21.2

20.1

19.1

18.2

17.2

16.1

Max

63.7

60.2

46.2

30.2

25.9

24.5

41.5

21.2

20.1

19.1

18.2

17.2

16.1

% Criteria

1274%

1204%

924%

604%

518%

490%

830%

424%

402%

382%

364%

344%

322%

Note: Assessment point A41 is representing the section of Deep Bay Link at 15m above ground level adjacent to the proposed San Wai STW.

Table 3.11 Predicted Worst-case 5-second Average Odour Levels at Assessment Points Around the Expanded San Wai STW for the Mitigated Scenario

Assessment Points

Predicted 5-second Average Odour Levels (in OU)

at Different Assessment Height Above Local Ground Level

1.5m

2.5m

5m

7.5m

10m

12.5m

15m

17.5m

20m

22.5m

25m

27.5m

30m

A15

0.5

0.5

0.6

0.7

0.8

1.0

1.1

1.1

1.1

1.0

0.9

0.7

0.5

A16

0.5

0.5

0.6

0.7

0.8

1.0

1.1

1.1

1.1

1.0

0.9

0.7

0.5

A17

0.5

0.5

0.5

0.7

1.0

1.2

1.3

1.4

1.4

1.2

1.0

0.8

0.6

A31

0.5

0.5

0.6

0.7

0.8

0.9

1.0

1.1

1.0

1.0

0.8

0.7

0.5

A32

0.5

0.5

0.6

0.7

0.8

0.9

1.0

1.0

1.0

1.0

0.8

0.7

0.6

A37

0.8

0.8

0.8

0.8

1.3

1.8

2.2

2.4

2.3

2.0

1.5

1.0

0.8

A38

0.9

0.9

0.9

0.9

1.4

2.0

2.5

2.8

2.7

2.2

1.7

1.1

1.0

A39

0.7

0.7

0.7

0.9

1.3

1.7

2.0

2.2

2.1

1.8

1.4

1.0

0.7

A40

0.7

0.7

0.7

0.8

1.1

1.5

1.7

1.8

1.8

1.6

1.3

0.9

0.7

A41

NA

NA

NA

NA

NA

NA

4.6

NA

NA

NA

NA

NA

NA

A42

0.9

0.9

0.9

0.9

1.5

2.1

2.6

2.9

2.8

2.4

1.7

1.1

1.0

Max

0.9

0.9

0.9

0.9

1.5

2.1

4.6

2.9

2.8

2.4

1.7

1.1

1.0

% Criteria

18%

18%

18%

18%

30%

42%

92%

58%

56%

48%

34%

22%

20%

Note: Assessment point A41 is representing the section of Deep Bay Link at 15m above ground level adjacent to the proposed San Wai STW.

3.8.2.4 The predicted worst-case 5-second average odour levels in the vicinity of the proposed expanded San Wai STW for the unmitigated scenario are shown in Figure 3.15. Since the emission heights of the odour sources were taken as ground level for the unmitigated scenario, the odour levels presented in Figure 3.15 at a receiver height of 1.5m above ground level would represent the worst-case impacts. 1.5m is the average height of human breathing zone. As shown in Figure 3.15 and in Table 3.10, very high odour impacts would be expected in the area even at a large distance from the STW. Exceedances of the 5 OU criteria level are expected at most part of San Wai. More than 60 OU are predicted at an existing village house in San Wai (assessment point A38).

3.8.2.5 For the mitigated scenario, as shown by the modelling results in Table 3.11, the worst affected height around the San Wai STW would be at 17.5m above ground level. Figure 3.16 shows the predicted worst-case 5-second average odour levels in the vicinity of the proposed expanded San Wai STW at the worst affected height of 17.5m above ground level. No air sensitive use is identified within the areas with predicted exceedance of the 5 OU criteria during the operational period under the mitigated scenario. As shown in the figure, higher odour levels are predicted around the exhaust point of the deodorization unit. The highest odour impact of about 3 OU is predicted at Area 5a of the future HSKNDA. With the implementation of the proposed odour control measures, exceedance of the 5 OU criteria is not predicted at the existing and future ASRs in the area.

Proposed Expanded Ha Tsuen Pumping Station

3.8.2.6 Under the current design, most of the sewage surface within the wet wells would not be exposed to the atmosphere under normal operation. Odour emissions from the sewage surface within the wet wells should thus be minimal during normal operation. However, the wet wells would be force-ventilated during man entry for inspection or maintenance and would result in potential odour emissions.

3.8.2.7 For the purpose of this assessment, two operation scenarios namely the unmitigated and the mitigated scenarios were considered and assessed with the odour dispersion model. In the unmitigated scenario, it was assumed that all major odour sources within the proposed expanded Ha Tsuen Pumping Station namely the existing and the new wet wells would be open to the atmosphere. All H2S emissions would be dispersed directly from the sources at ground level.

3.8.2.8 In the mitigated scenario, it was assumed that the existing and the new wet wells would be contained within building structures. All the odour emissions from the wet wells would be ventilated to a deodoriser located at the rooftop of the existing and the new pumping stations. In this assessment, it is estimated that an H2S removal efficiency of up to 97% would be required for the deodorisers so as to achieve the 5 OU criteria at all the ASRs. All the treated air would be emitted from the exhaust vent of the deodorisers with exhaust heights of 4m and 8m above ground for the existing and new wet wells, respectively, and with an exit velocity of 8m/s.

3.8.2.9 The worst-case 5-second average odour levels were calculated at the assessment points in the vicinity of the proposed expanded Ha Tsuen Pumping Station as shown in Figure 3.2. The assessment heights were taken as 1.5m to 30m above local ground level to represent the worst affected heights. The modelling results for the unmitigated and mitigated scenarios at the assessment points are shown in Tables 3.12 and 3.13 respectively.

Table 3.12 Predicted Worst-case 5-second Average Odour Levels at Assessment Points Around the Expanded Ha Tsuen PS for the Unmitigated Scenario

Assessment Points

Predicted 5-second Average Odour Levels (in OU)

at Different Assessment Height Above Local Ground Level

1.5m

2.5m

5m

7.5m

10m

12.5m

15m

17.5m

20m

22.5m

25m

27.5m

30m

A1

90.7

84.4

60.5

47.5

40.0

32.0

26.5

23.7

21.1

19.6

18.2

16.7

15.2

A2

67.4

63.0

46.9

40.5

34.8

28.7

23.5

21.3

19.0

17.6

16.5

15.3

14.2

A3

73.4

66.7

42.6

32.6

28.5

27.0

25.3

23.4

21.4

19.4

17.3

15.3

13.3

A4

31.5

30.2

24.9

18.8

17.0

15.0

13.5

12.8

11.9

11.1

10.7

10.2

9.8

A5

54.0

50.3

36.2

26.0

22.0

20.4

19.6

18.6

17.6

16.5

15.3

14.1

12.9

A6

105.6

90.3

68.3

52.5

46.1

41.7

37.8

33.8

29.7

25.6

21.8

18.3

15.1

A7

119.8

100.5

64.0

46.5

43.1

39.1

34.8

30.3

25.9

21.6

17.8

15.9

14.1

A8

88.7

78.8

47.3

38.1

33.4

31.2

28.6

25.8

22.9

20.1

17.3

14.7

13.0

A9

27.2

26.7

24.3

20.8

16.7

13.0

12.1

11.1

10.1

9.0

8.0

7.0

6.4

A11

53.6

50.0

36.3

31.0

26.6

22.4

20.6

18.7

17.5

16.6

15.5

14.5

13.4

A12

40.8

38.6

29.9

25.8

22.8

19.5

17.3

16.0

14.7

13.9

13.2

12.5

11.7

A43

95.5

88.6

62.4

48.7

40.8

32.5

27.0

24.0

21.4

19.9

18.4

16.9

15.3

A44

114.9

103.0

85.2

64.7

55.0

49.6

43.9

38.0

32.3

26.9

22.1

17.8

15.5

A45

193.8

156.6

98.8

77.2

63.0

48.7

37.0

30.6

24.7

19.5

15.3

11.9

9.2

A46

174.1

129.2

90.7

62.5

51.6

42.3

33.2

26.7

21.9

17.6

13.7

10.5

7.8

A47

129.2

106.7

69.3

50.0

45.9

41.3

36.2

31.0

26.1

21.5

18.2

16.1

14.1

A48

164.1

123.2

88.7

75.3

66.4

56.5

46.8

37.6

29.4

23.9

20.2

16.8

13.8

A49

298.1

266.6

170.8

133.8

105.8

79.4

57.1

39.9

31.0

23.7

18.0

13.6

10.3

A50

165.3

141.5

101.3

88.8

76.6

63.6

51.1

39.8

30.1

24.7

20.3

16.4

13.2

A51

87.8

77.6

49.7

39.8

35.4

33.3

30.8

28.1

25.3

22.5

19.7

17.1

14.6

Highest

298.1

266.6

170.8

133.8

105.8

79.4

57.1

39.9

32.3

26.9

22.1

18.3

15.5

% Criteria

5962%

5332%

3416%

2676%

2116%

1588%

1142%

798%

646%

538%

442%

366%

310%

Table 3.13 Predicted Worst-case 5-second Average Odour Levels at Assessment Points Around the Expanded Ha Tsuen PS for the Mitigated Scenario

Assessment Points

Predicted 5-second Average Odour Levels ( in OU)

at Different Assessment Height Above Local Ground Level

1.5m

2.5m

5m

7.5m

10m

12.5m

15m

17.5m

20m

22.5m

25m

27.5m

30m

A1

0.5

0.5

0.5

0.5

0.8

1.0

1.2

1.2

1.1

0.8

0.5

0.5

0.5

A2

0.5

0.5

0.5

0.5

0.6

0.8

0.9

0.9

0.8

0.6

0.5

0.5

0.5

A3

0.5

0.5

0.5

0.5

0.7

0.9

1.0

1.0

0.9

0.7

0.5

0.5

0.5

A4

0.3

0.3

0.3

0.3

0.4

0.4

0.4

0.5

0.4

0.4

0.3

0.3

0.3

A5

0.4

0.4

0.4

0.4

0.5

0.6

0.7

0.8

0.7

0.6

0.4

0.4

0.4

A6

0.6

0.6

0.6

0.6

0.9

1.3

1.5

1.3

1.0

0.8

0.8

0.8

0.8

A7

0.5

0.5

0.5

0.5

0.9

1.4

1.6

1.4

1.2

0.9

0.7

0.7

0.7

A8

0.5

0.5

0.5

0.5

0.7

1.1

1.2

1.2

1.2

0.9

0.6

0.6

0.5

A9

0.2

0.3

0.3

0.3

0.4

0.4

0.4

0.4

0.4

0.3

0.3

0.2

0.2

A11

0.4

0.4

0.4

0.4

0.5

0.6

0.7

0.8

0.7

0.6

0.4

0.4

0.4

A12

0.4

0.4

0.4

0.4

0.4

0.5

0.5

0.6

0.6

0.5

0.4

0.3

0.3

A43

0.5

0.5

0.5

0.5

0.8

1.2

1.3

1.3

1.1

0.8

0.5

0.5

0.5

A44

0.6

0.6

0.7

0.7

0.9

1.5

1.7

1.4

1.2

1.0

1.0

1.0

1.0

A45

0.6

0.6

0.6

0.8

1.2

2.1

2.6

2.1

1.9

1.3

1.3

1.3

1.2

A46

0.5

0.5

0.5

0.7

1.1

1.9

2.3

2.4

2.2

1.4

1.1

1.1

1.1

A47

0.5

0.5

0.5

0.5

0.8

1.2

1.3

1.8

1.7

1.2

0.8

0.8

0.8

A48

0.6

0.6

0.6

0.6

0.9

1.4

1.7

2.3

2.2

1.4

1.2

1.2

1.2

A49

0.7

0.7

0.8

1.0

1.1

2.1

3.3

4.0

3.4

2.1

2.4

2.5

2.4

A50

0.6

0.7

0.7

0.7

0.9

1.4

1.7

2.5

2.3

1.4

1.4

1.5

1.4

A51

0.5

0.5

0.5

0.6

0.7

0.9

1.0

1.2

1.2

0.9

0.6

0.6

0.6

Highest

0.7

0.7

0.8

1.0

1.2

2.1

3.3

4.0

3.4

2.1

2.4

2.5

2.4

% Criteria

14%

14%

16%

20%

24%

42%

66%

80%

68%

42%

48%

50%

48%

3.8.2.10 The predicted worst-case 5-second average odour levels in the vicinity of the proposed expanded Ha Tsuen Pumping Station for the unmitigated scenario are shown in Figure 3.17. Since the emission heights of the odour sources were taken as ground level for the unmitigated scenario, the odour levels presented in Figure 3.17 at a receiver height of 1.5m above ground level would represent the worst-case impacts. 1.5m is the average height of human breathing zone. As shown in Figure 3.17 and in Table 3.12, very high odour impacts would be expected in the immediate vicinity of the pumping station. About 300 OU are predicted at the site boundary of a future residential area in HSK North NDA (assessment point A49).

3.8.2.11 For the mitigated scenario, as shown by the modelling results in Table 3.13, the worst affected height around the Ha Tsuen Pumping Station would be at 17.5m above ground level. Figure 3.18 shows the predicted worst-case 5-second average odour levels in the vicinity of Ha Tsuen Pumping Station at the worst affected height of 17.5m above ground level. No air sensitive use is identified within the areas with predicted exceedance of the 5 OU criteria during the operational period under the mitigated scenario. As shown in the figure, higher odour levels are predicted around the exhaust point of the deodorisers. The highest odour impact of 4.0 OU is predicted at the site boundary of a future residential area in HSK North NDA (assessment point A49). With the implementation of the proposed odour control measures, exceedance of the 5 OU criteria is not predicted at the existing and future ASRs in the area.

3.9 Mitigation of Adverse Environmental Impacts

3.9.1 Construction Phase Measures

3.9.1.1 In order to ensure that dust emission is minimised during the construction phase of the project, relevant dust control requirements set out in the Air Pollution Control (Construction Dust) Regulation should be met. The site agent of the Contractor is required to adopt dust reduction measures while carrying out construction works. The specific measures recommended in this assessment include dust suppression by twice daily watering with complete coverage of all active construction areas and limit the construction vehicle travel speed on unpaved site areas to not more than 10 km per hour. Besides, the mitigation measures listed below should be adopted where applicable. With the implementation of effective dust control measures, adverse dust impacts from the construction works of the project is not expected.
Site clearance and demolition of existing structures
· The working area for the uprooting of trees, shrubs, or vegetation or for the removal of boulders, poles, pillars or temporary or permanent structures should be sprayed with water or a dust suppression chemical immediately before, during and immediately after the operation so as to maintain the entire surface wet;
· All demolished items (including trees, shrubs, vegetation, boulders, poles, pillars, structures, debris, rubbish and other items arising from site clearance) that may dislodge dust particles should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides within a day of demolition;
Site boundary and entrance
· Vehicle washing facilities including a high pressure water jet should be provided at every discernible or designated vehicle exit point;
· The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores;
· Where a site boundary adjoins a road, street, service and or other area accessible to the public, hoarding of not less than 2.4m from ground level should be provided along the entire length of that portion of the site boundary except for a site entrance or exit;
Access road
· Every main haul road (i.e. any course inside a construction site having a vehicle passing rate of higher than 4 in any 30 minutes) should be paved with concrete, bituminous materials, hardcores or metal plates, and kept clear of dusty materials; or sprayed with water or a dust suppression chemical so as to maintain the entire road surface wet;
· The portion of any road leading only to a construction site that is within 30m of a discernible or designated vehicle entrance or exit should be kept clear of dusty materials;
Use of vehicle
· Immediately before leaving a construction site, every vehicle should be washed to remove any dusty materials from its body and wheels;
· Where a vehicle leaving a construction site is carrying a load of dusty materials, the load should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle;
Excavation and earth moving
· The working area of any excavation or earth moving operation should be sprayed with water or a dusty suppression chemical immediately before, during and immediately after the operation so as to maintain the entire surface wet;
· Exposed earth shall be properly treated by compaction, turfing, hydroseeding, vegetation planting or sealing with latex, vinyl, bitumen, shotcrete or other suitable surface stabiliser within 6 months after the last construction activity on the construction site or part of the construction site where the exposed earth lies;
Stockpiling of dusty materials
· Any stockpile of dusty material should be either covered entirely by impervious sheeting; placed in an area sheltered on the top and the 3 sides; or sprayed with water or a dust suppression chemical so as to maintain the entire surface wet.

3.9.2 Operational Phase Measures

3.9.2.1 In order to mitigate the potential odour impacts from the proposed expanded San Wai STW, it is recommended that all the major odour sources within the proposed expanded STW namely the fine screen, the detritors, the sludge holding tanks, the solid handling house, the sludge dewatering house, the rapid mix and flocculation tank, and the primary sedimentation tanks should all be contained within either building structures or enclosure to minimise direct emission of odour to the atmosphere.

3.9.2.2 Besides, all odour emissions from the above odour sources should be ventilated to a centralised deodorization unit. Based on the findings of this assessment, the H2S removal efficiency of the deodorization unit should be 96% or better. The exhaust height and exit velocity of the treated air should not be less than 5m and 10m/s respectively.

3.9.2.3 For the proposed expanded Ha Tsuen Pumping Station, it is recommended that the air ventilated from the existing and the new wet wells should be treated by deodorisers with a H2S removal efficiency of 97% or better before discharge to the atmosphere. The exhaust of the deodorisers should be located on the rooftop of the pumping station and the exit velocity of the treated air should not be less than 8m/s.

3.9.2.4 The two likely technologies for deodorization to be adopted for this project would be adsorption of odorous chemicals by granulated activated carbon (GAC) and scrubbing of odorous air stream with chemical oxidants in a chemical scrubber. For example, chemicals such as sodium hydroxide, chlorine solution, and sodium hypochlorite etc are commonly used in scrubbers to oxidise odorous chemicals such as hydrogen sulphide and mercaptans.

3.9.2.5 A simple comparison of the operational characteristics of the two technologies, based on some manufacturers' information, are summarised in Table 3.14 below.

Table 3.14 Comparison of the Operational Characteristics of Granular Activated Carbon and Chemical Scrubber

 

Granular Activated Carbon

Chemical Scrubber

Approach

Adsorb odorous compounds

Absorb + neutralise odorous compounds

Mode of operation

Single / multi stage

Single / multi stage; packed bed / sieve tray

Air flow range

Large (ranged from 0.05 to 30 m3/s)

Preferably low range for each unit (0.1 to 1 m3/s)

Typical H2S removal efficiency

>99.7% (minimum of 99%)

>99.5% (minimum of 98%)

Characteristics

Capable of handling large volume of air flow, no requirement of solid waste disposal, more space requirement

Low cost, simple system, minimal process control, requirement of solid waste disposal

3.10 Evaluation of Residual Impacts

3.10.1.1 With the implementation of effective dust control measures during the construction phase of the project, adverse dust impacts from the construction activities of the project would not be expected. The modelling results showed that there would be no exceedance of the AQO and guideline level for TSP at the ASRs under the mitigated scenario and adverse residual dust impact during the construction phase of this project is not expected.

3.10.1.2 During the operational phase, major air quality impact associated with this project would be related to the potential odour emissions from the expanded and upgraded San Wai STW and the expanded Ha Tsuen Pumping Station. It is recommended to enclose the odour sources and ventilate all the odour emissions through deodorisers before discharge to the atmosphere. With effective implementation of these measures, residual adverse air quality impact during the operational phase of the project is not expected.

3.11 Environmental Monitoring and Audit

3.11.1.1 The detailed environmental monitoring and audit requirements for air quality during the construction phase and operational phase of this project are prepared in accordance with the requirements stipulated in Annex 21 of the TM on EIAO Process. Together with the implementation schedule for air quality mitigation measures, all the materials are included in the EM&A Manual.

3.12 Conclusions

3.12.1.1 The major potential air quality impacts during the construction phase of this project would result from dust arising from site clearance and preparation, excavation and filling, open site erosion, construction of foundation and superstructure, and handling and transportation of construction and demolition material. Practicable and effective dust suppression measures should be implemented to minimise the dust nuisance arising from the construction activities. In particular, the relevant dust control requirements set out in Parts I, III and IV of Schedule 1 of the Air Pollution Control (Construction Dust) Regulation should be adopted by the site agent while carrying out construction works. With the implementation of effective dust control measures, adverse dust impacts from the construction works of this project is not expected.

3.12.1.2 Major air quality impact during the operational phase of this project would be related to the potential odour emissions from the expanded and upgraded San Wai STW and the expanded Ha Tsuen Pumping Station. Computer dispersion modelling was undertaken to assess the potential operational phase air quality impacts due to odour emissions from the proposed works. Odour mitigation measures have been recommended. These include enclosing the odour sources and ventilating all the odour emissions through deodorisers before discharging to the atmosphere. The modelling results showed no exceedance of the odour criteria at all the identified existing and future air sensitive receivers in the vicinity of the proposed works under the mitigated scenarios.