Appendix 4 IMPLEMENTATION
SCHEDULE
Table A4.1 Recommended
Maximum Daily Dredging VolumeRates (in-situ Volume) for Working Zones
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note:
(a) The recommended maximum dredging rate refers to the
maximum dredging rates when all dredging activities taking place at one
particular working zone. For the grab
dredger option, dredging may be carried out concurrently at more than one
working zones during some time periods.
In this case, the combined dredging rates during those time periods
should not exceed the lowest of the maximum rates recommended for the concerned
working zones.
The above maximum daily dredging rates are based on
24-hour operations. If the daily working hours are restricted, the maximum
daily dredging rates should be reduced proportionally.
The division of working zones are illustrated in Figure A4.2.
Table A4.2 Recommended
Maximum Hourly/Cycle Dredging Volume (in-situ Volume) for Working Zones
|
|
|
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note:
(a) The recommended maximum dredging rate refers to the
maximum dredging rates when all dredging activities taking place at one
particular working zone. For the grab
dredger option, dredging may be carried out concurrently at more than one
working zones during some time periods.
In this case, the combined dredging rates during those time periods
should not exceed the lowest of the maximum rates recommended for the concerned
working zones.
(b) The division of working zones are illustrated in Figure A4.2.
Appendix 4 IMPLEMENTATION
SCHEDULE
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration
of Measures/Timing of Completion of Measures |
Implementation Agent |
Implementation
Stage |
Relevant
Legislation & Guidelines |
|||
Des |
C |
O |
Dec |
|
|||||
Mitigation Measures for both Grab Dredger and
TSHD Options |
|||||||||
3.11 |
|
No
dredging should be carried out at Working Zone BCs from February to April. |
Location: Working Zone BCs Timing/Duration: February to April |
HEC & Dredging Contractor |
|
a |
|
|
Wild Animals Protection Ordinance, Marine Parks
Ordinance and Marine Parks Regulations,
Animals and Plants Ordinance |
3.11 |
|
Vessel
route between the dredging site and the disposal sites should avoid the Finless Porpoise
habitat area and be subject to a maximum speed limit of 10 knots in southern
Lamma waters as indicated in Figure A4.3. |
Location: South Lamma Timing/Duration: During the Project period |
HEC & Dredging Contractor |
|
a |
|
|
Wild Animals Protection Ordinance, Marine Parks
Ordinance and Marine Parks Regulations, Animals and Plants Ordinance |
5.2 |
|
The
number of dredgers and operation conditions specified in the applicable CNPs
should be strictly followed. In
applying for the CNPs, it should
be ensured that the number of dredgers and operation conditions are
compatible with the recommendations of this EIA. |
Location: The Project Area Timing/Duration: During restricted hours of the
Project period |
HEC & Dredging Contractor |
|
a |
|
|
Noise Control Ordinance |
2.11.2 |
|
The
grab
dredger
option
and TSHD option
should
not be operated concurrently. |
Location: The Project Area Timing/Duration: During the Project period |
HEC & Dredging Contractor |
|
a |
|
|
WQOs for Southern and Western Buffer WCZs, WPCO,
Noise Control Ordinance |
EIA
Ref. |
EM&A
Log Ref |
Environmental
Protection Measures |
Location/Duration
of Measures/Timing of Completion of Measures |
Implementation
Agent |
Implementation
Stage |
Relevant
Legislation & Guidelines |
||||
Des |
C |
O |
Dec |
|
||||||
Mitigation Measures for TSHD Option Only |
||||||||||
2.11.4 |
|
Dredging
works should be carried out in phases in accordance with the programme,
number of dredgers and maximum dredging rates specified in Table A4.3. |
Location: The Project Area Timing/Duration: During dredging |
HEC & Dredging Contractor |
|
a |
|
|
WQOs for Southern and Western Buffer WCZs, WPCO |
|
2.11 |
|
There
should not be more than one TSHD operating concurrently at any time. |
Location: The Project Area Timing/Duration: During dredging |
HEC & Dredging Contractor |
|
a |
|
|
WQOs for Southern and Western Buffer WCZs, WPCO |
|
Mitigation Measures for Grab Dredger Option Only |
||||||||||
2.11.4 |
|
Dredging
works should be carried out in phases in accordance with the programme,
number of dredgers and maximum dredging rates specified in Table A4.2. |
Location: The Project Area Timing/Duration: During dredging |
HEC & Dredging Contractor |
|
a |
|
|
WQOs for Southern and Western Buffer WCZs, WPCO,
Noise Control Ordinance |
|
2.8.12 |
|
Each
grab dredger to be deployed should have a grab capacity of no less than 8 m3. |
Location: The Project Area Timing/Duration: During dredging |
HEC & Dredging Contractor |
|
a |
|
|
WQOs for Southern and Western Buffer WCZs, WPCO |
|
2.12 |
|
Cage-type
silt curtains as
illustrated in Figure A4.1
should
be deployed for grab
dredgers. The
silt curtains should be properly maintained during the dredging period. |
Location: The Project Area Timing/Duration: During dredging |
HEC & Dredging Contractor |
|
a |
|
|
WQOs for Southern and Western Buffer WCZs, WPCO |
|
2.11 |
|
There
should be no more than 5
grab dredgers operating concurrently at any time. |
Location: The Project Area Timing/Duration: During dredging |
HEC & Dredging Contractor |
|
a |
|
|
WQOs for Southern and Western Buffer WCZs, WPCO,
Noise Control Ordinance |
|
EIA Ref. |
EM&A Log Ref |
Environmental
Protection Measures |
Location/Duration of Measures/Timing of
Completion of Measures |
Implementation Agent |
Implementation Stage |
Relevant Legislation & Guidelines |
||||
Des |
C |
O |
Dec |
|||||||
Good Site Practice |
||||||||||
2.12 |
|
Daily
dredging volume should be
spread as evenly as possible over the 24 hour period whenever practical. Special
care should be taken during lowering and lifting grabs to minimize
unnecessary disturbance to the seabed. |
Location: The Project Area, the disposal areas
and on route between the dredging site and the disposal areas Timing/Duration: During dredging and disposal |
HEC & Dredging Contractor |
|
a |
|
|
WQOs for Southern and Western Buffer WCZs, WPCO |
|
|
|
Vessels used should have adequate clearance of
the seabed. |
|
|
|
|
|
|
|
|
|
|
Barges
should be fitted with tight
fitting seals to their bottom openings to prevent leakage of material. |
|
|
|
|
|
|
|
|
|
|
Grabs
should be tightly closed and hoist speed is suitably low. |
|
|
|
|
|
|
|
|
|
|
Barges
should not be filled to a level which will cause overflow of materials during loading and
transportation. |
|
|
|
|
|
|
|
|
|
|
Appropriate
monitoring of WQ in accordance with EM&A Manual during dredging works
should be undertaken to allow the implementation of appropriate Action Plans
to prevent any unacceptable WQ impacts. |
|
|
|
|
|
|
|
|
|
|
Large
objects should be removed from the grab to avoid losses from partially closed
grabs. |
|
|
|
|
|
|
|
|
EIA Ref. |
EM&A Log Ref |
Environmental
Protection Measures |
Location/Duration of Measures/Timing of
Completion of Measures |
Implementation Agent |
Implementation Stage |
Relevant Legislation & Guidelines |
|||
Des |
C |
O |
Dec |
||||||
3.11 |
|
The
vessel operators should be fully briefed on the following: ·
Possible
presence of dolphins and porpoises in the vicinity of the Study Area and
along routes to the Project Area; ·
Rules
for safe vessel operation
around cetaceans; ·
Slowing to 10 knots in the presence of cetaceans
within the area marked on Figure A4.3; and ·
The dumping of chemicals, rubbish, oils etc into
the waters is strictly prohibited and enforced. |
Timing: In the event of spotting porpoises or
dolphins |
Dredging Contractor |
|
a |
|
|
Wild Animals Protection Ordinance, Marine Parks
Ordinance and Marine Parks Regulations, Animals and Plants Ordinance, Dumping
at Sea Ordinance, Waste Disposal Ordinance |
Table A4.1 Recommended
Maximum Daily/Hourly/Cycle Dredging Volume (in-situ Volume) for Working Zones
Season |
Wet
Season (April to September) |
Dry
Season (October to March) |
|||||||
Working Zone |
ABn |
ABs |
BCn |
BCs |
ABn |
ABs |
BCn |
BCs |
|
Grab Dredger with Silt Curtains (Grab Capacity ³ 8 m3) |
m3/day |
33,800 |
31,400 |
26,300 |
21,200 |
43,800 |
33,200 |
33,200 |
34,200 |
m3/hr |
1,549 |
1,439 |
1,205 |
972 |
2,008 |
1,522 |
1,522 |
1,568 |
|
TSHD |
m3/day |
12,500 |
11,300 |
8,300 |
5,300 |
39,500 |
34,300 |
27,000 |
19,700 |
m3/cycle |
1,432 |
1,295 |
951 |
607 |
4,526 |
3,930 |
3,094 |
2,257 |
Note:
(a) The recommended maximum dredging rate refers to the
maximum dredging rates when all dredging activities taking place at one
particular working zone. For the grab
dredger option, dredging may be carried out concurrently at more than one
working zones during some time periods.
In this case, the combined dredging rates during those time periods
should not exceed the lowest of the maximum rates recommended for the concerned
working zones.
(b)
The above maximum daily dredging rates are based on
24-hour operations. If the daily working hours are restricted, the maximum
daily dredging rates should be reduced proportionally.
(c)
The division of working zones are illustrated in Figure A4.2.
(d) For
the grab dredger option, recommended maximum hourly dredging rate = 1.1 *
recommended maximum daily dredging rate/24.
(e)
For the TSHD option, recommended maximum cycle
dredging rate = 1.1 * recommended maximum daily dredging rate/9.6 (where 9.6 is
the number of dredging cycle in a day assumed in water quality modelling).
Table A4.2 Proposed
Working Schedule - Grab Dredger Option
Working
Zone |
Construction
Programme |
|||||||
May-03 |
Jun-03 |
Jul-03 |
Aug-03 |
Sep-03 |
Oct-03 |
Nov-03 |
Dec-03 |
|
ABn |
GD1 |
GD1 |
GD1 |
GD1 |
GD1 |
GD1 |
|
|
GD2 |
GD2 |
GD2 |
GD2 |
GD2 |
GD2 |
GD2 |
GD2 |
|
ABs |
GD3 |
GD3 |
GD3 |
GD3 |
GD3 |
GD3 |
GD3 |
GD3 |
GD4 |
GD4 |
GD4 |
GD4 |
GD4 |
|
|
|
|
BCn |
GD5 |
GD5 |
GD5 |
GD5 |
GD5 |
GD5 |
|
|
|
|
|
|
|
|
|
|
|
BCs |
|
|
|
|
|
GD4 |
GD4 |
GD4 |
|
|
|
|
|
|
GD5 |
GD5 |
|
|
|
|
|
|
|
GD1 |
GD1 |
|
Maximum dredging rate (m3/day) |
26,300 |
33,200 |
||||||
Maximum dredging rate (m3/hr) |
1,205 |
1,522 |
Note:
1.
GD1 denotes Grab Dredger No. 1.
2.
The above maximum daily dredging rates are based on
24-hour operations. If the daily working hours are restricted, the maximum
daily dredging rates should be reduced proportionally.
Table A4.3 Proposed Working Schedule - TSHD Option
Working
Zone |
Construction
Programme |
|||||||
May-03 |
Jun-03 |
Jul-03 |
Aug-03 |
Sep-03 |
Oct-03 |
Nov-03 |
Dec-03 |
|
ABn |
TSHD |
|
|
|
||||
ABs |
|
|
|
|
|
|
TSHD |
|
BCn |
|
|
|
|
|
|
|
TSHD |
BCs |
|
|
|
|
|
TSHD |
|
|
Maximum dredging rate (m3/day) |
12,500 |
19,700 |
34,300 |
27,000 |
||||
Maximum dredging rate (m3/cycle) |
1,432 |
2,257 |
3,930 |
3,094 |
Note:
1. TSHD denotes Trailer Suction Hopper Dredger
2. The above maximum daily dredging rates are based on
24-hour operations. If the daily working hours are restricted, the maximum
daily dredging rates should be reduced proportionally.