A noise assessment has been undertaken to define the nature and scale of potential environmental impacts associated with the implementation of the Tung Chung Cable Car Project specifically in terms of the effects in the vicinity of sensitive receivers. Both construction and operational phase impacts have been assessed and mitigation measures have been identified to determine whether residual impacts can be reduced to acceptable levels.
Construction Noise
The principal legislation
for the control of construction noise is the Noise Control Ordinance (NCO) (Cap
400) and
the Environmental Impact Assessment Ordinance (EIAO)(Cap 499). Various Technical Memoranda (TMs), which
stipulate control approaches and criteria, have been issued under the NCO and
EIAO. For this project, the following
TMs are
applicable to the control of noise from construction activities relevant to the assessment of
the construction noise impacts:-
·
Technical
Memorandum on Noise from Percussive Piling (PP-TM);
· Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM);
· Technical Memorandum on Noise from Percussive Piling (PP-TM); and
· Technical Memorandum on Environmental Impact Assessment Process (TMEIA).
Percussive Piling
Percussive piling is prohibited at any time on Sundays and public holidays and during the weekday evening and nighttime hours (1900-0700 hours, Monday through Saturday). A Construction Noise Permit (CNP) is required for such works during the daytime hours (0700-1900 hours) Monday through Saturday.
When assessing a CNP application for carrying out of percussive piling, the Environmental Protection Department (EPD) is guided by the PP-TM. The EPD will look at the difference between the Acceptable Noise Levels (ANLs), as promulgated in the PP-TM, and the Corrected Noise Levels (CNLs) that are associated with the proposed piling activities. Depending on the level of noise impact on nearby NSRs, the EPD would allow 3, 5 or 12 hours of piling time daily (see Table 4.1 below).
Table 4.1 Permitted Hours of Operation for Percussive Piling
Amount by which CNL exceeds ANL |
Permitted hours of operation on any day not being a holiday |
more than 10 dB(A) |
0800 to 0900 and 1230 to 1330 and 1700 to 1800 |
between 0 dB(A) and 10 dB(A) |
0800 to 0930 and 1200 to 1400 and 1630 to 1800 |
no exceedance |
0700 to 1900 |
General Construction Works
Noise impacts arise from general construction works during normal working hours (i.e. 0700 to 1900 hours on any day not being a Sunday or public holiday) at the openable windows of noise sensitive buildings are to be assessed as per the guidelines contained in the TMEIA. The recommended noise standards are 75dB(A) for domestic premises, 70dB(A) for educational institutions, 65dB(A) during examinations.
The NCO provides statutory controls on general construction works during the restricted hours (i.e. 1900-0700 hours Monday to Saturday and at any time on Sundays and public holidays). The use of powered mechanical equipment (PME) for carrying out construction works during the restricted hours would require a CNP. The EPD is guided by the GW-TM when assessing such an application.
When assessing an application for the use of PME, the EPD will compare the ANLs, as promulgated in the GW-TM, and the CNLs (after accounting for factors such as barrier effects and reflections) associated with the proposed PME operations. A CNP will be issued if the CNL is equal to or less than the ANL. The ANLs are related to the noise sensitivity of the area in question and different Area Sensitivity Ratings (ASR) have been drawn up to reflect the background characteristics of different areas. The relevant ANLs are shown in Table 4.2 below.
Table 4.2 Acceptable Noise Levels (ANL, Leq, 5 min dB(A))
Time Period
|
Area Sensitivity Rating |
||
A |
B |
C |
|
All days during the evening (1900-2300 hours) and general holidays (including Sundays) during the day and evening (0700-2300 hours) |
60 |
65 |
70 |
All days during the night-time (2300-0700 hours) |
45 |
50 |
55 |
Regardless of any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a CNP will be issued for construction of the project. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the Noise Control Ordinance. The Noise Control Authority will take into account contemporary conditions / situations of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP. Nothing in this EIA Report shall bind the Noise Control Authority in making his decision. If a CNP is to be issued, the Noise Control Authority shall include in it any condition he thinks fit. Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.
At this moment, only construction works during non-restricted hours are assumed and the feasibility of carrying out works during restricted hours has not been assessed.
Helicopter Operation
For planning purposes, the
noise standards for the operation
control
of helicopter noise are provided in Table 1A of TMEIA which are reproducedtabulated below in Table 4.3.
However, if the helicopter is considered to be a place piece of construction
equipment then the 75dB(A) at the sensitive receivers should be met.
Table 4.3 Noise Standard for Helicopter Operation
Uses |
Helicopter Noise Lmax dB(A) 0700 to 1900 |
All domestic premises including temporary housing accommodation |
85 |
Hotels and hostels |
85 |
Offices |
90 |
Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required |
85 |
Places of public worship and courts of law |
85 |
Hospitals, clinics, convalescences and homes for the aged · Diagnostic rooms · Wards |
85 |
Notes :
(i) The above standards apply to uses which rely on open windows for ventilation;
(ii) The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external facade.
Noise standards are
presented in the Noise Control Ordinance and its subsidiary Technical
Memorandum for assessment against possible noise impact from industrial
operation sources. Ngong
Ping Area is generally rural in nature and with scattered village type
developments. No influencing factors
(i.e. major road and airport) are affected this area. On the other hand, as the Tung Chung area is being affected by Hong Kong International Airport
(i.e. influencing factor) and is generally urban in nature. Hence,Iin the vicinity of the
cable car alignment noise sensitive receivers at Ngong Ping and at Tung Chung are
assumed as Area Sensitivity Rating “A” and “C” respectively. The Area
Sensitivity Rating assumed in this EIA Report is for indicative assessment only given that details of the plant layout are
not yet available and building layout is only provisional. It should be noted that fixed noise sources
are controlled under section 13 of the NCO.
At the time of investigation, the Noise Control Authority shall
determine noise impact from concerned fixed noise sources on the basis of
prevailing legislation and practices being in force, and taking account of
contemporary conditions / situations of adjoining land uses.
Nothing in this EIA Report shall bind the Noise Control Authority in the context of law enforcement against all the fixed noise sources being assessed.
For planning purposes, the noise standards for fixed noise sources are stipulated in Table 1A of TMEIA. The planning standards are 5dB(A) below the appropriate Acceptable Noise Levels (ANL) shown in Table 3 of the Technical Memorandum for the Assessment of Noise from places other than Domestic Premises, Public Places on Construction Sites or the prevailing background noise levels (for quiet areas with levels 5dB(A) below ANL). The ANL for the NSRs is presented in Table 4.4.
Table 4.4 Acceptable Noise Level at the Noise Sensitive Receivers
Time Period |
Acceptable Noise Level |
|
All days during the day (0700 to 1900 hours) and evening (1900 to 2300 hours) |
60 dB(A) (i) |
70 dB(A)(ii) |
All days during the night-time (2300-0700) |
50 dB(A) (i) |
60 dB(A)(ii) |
Notes:
(i) Area Sensitivity Rating is classified as “A” i.e. Ngong Ping
(ii) Area Sensitivity Rating is classified as “C” i.e. Tung Chung
As the gondolas
will traverse the area between Ngong Ping and Tung Chung the most stringent
criteria (for ASR “A”) will apply.
The existing environment of
the proposed Tung Chung Cable Car Project is primarily affected by the traffic
on Tung Chung such as North Lantau HighwayExpressway,
Tung Chung Waterfront Road, Tat Tung Road and Shun Tung Road. Immediately north
of the works site for the proposed Tung Chung Terminal are the bus/car parks.
No industrial uses are located within the Study Area. As such, the local
traffic is considered to be the dominant source affecting the ambient
background noise level.
The traffic on Ngong Ping such as Ngong Ping Road and other local roads is the dominant noise source at the Ngong Ping terminal.
According to the noise survey findings extracted from sub-clause 4.2.4 of Section 4 of approved EIA report under Register No. EIA-079/2002 “Ngong Ping Sewage Treatment Work and Sewerage”, the noise measurement results indicated that the lo
west background noise level during night-time is 45dB(A), which is 5dB(A) below the relevant ANL under the ASR of “A” for this area. Hence, 45(A) is to be adopted as noise criteria for Ngong Ping Area.
Based on the noise survey findings conducted at
Tung Chung Town, the noise measurement results indicated that the noise levels
(Leq)
ranged from 66.7 dB(A) to 71.7 dB(A) during daytime/evening while the noise levels (L eq) ranged from 57.8 dB(A) to
64.2 dB(A) during night-time. Hence, "“ANL-5"” *(i.e. 55 dB(A)) under the ASR
of "“C"” is more stringent than
prevailing background noise level i.e. 57.8 dB(A) and is to be adopted asnoise shown criteria for Tung Chung Area.
Representative Noise
Sensitive Receivers (NSRs) within 300m of the project limit have been
identified according to the criteria set out in the TM-EIA and NCO and through
site inspections and a review of land use plans. NSRs and their horizontal
distance to the nearest noise source have been identified and are summarized in
Table 4.5. Locations of the NSRs are
shown in Figures 4.1-to 4.3.
Table 4.5 Representative Noise Sensitive Receivers
NSRs |
Area |
Location |
Usage |
Distance to the nearest Noise Source |
NSR1a |
|
Village houses - Kam Wai Yuen |
Residential |
140 |
NSR1b |
Ngong Ping |
Village houses along Ngong Ping Road near bus terminus |
Residential |
370 |
NSR2 |
|
Tin Tan Buddha Status |
Religious |
440 |
NSR3 |
|
Lin Chi Monastery |
Religious |
270 |
NSR4 |
|
Tung Chung Crescent - Block 7 (Flat A) |
Residential |
50 |
NSR5 |
Tung Chung |
Fu Tung Estate - Tung Ma House (Flat 03) |
Residential |
330 |
NSR6 |
|
Seaview Crescent - Block 1 (Flat D) |
Residential |
340 |
NSR7 |
|
Wan Ho Kan Primary School |
Institutional |
440 |
NSR8 |
|
Village houses at Tin Sum |
Residential |
345 |
The main construction
activities comprise construction of site formation, excavation foundations and
superstructure. Construction activities
for the Cable Car project are expected to be undertaken during normal daytime
working hours (i.e. 0700 to 1900 hours on any day not being a Sunday or public
holiday) although some works at the Tung Chung Terminal could take place over a
longer period of time (eg 0700 - 2300 for steel fixing/form work etc.). According to the programme given in the EIA
for the construction of Ngong Ping Sewage Treatment Work (STW) construction
works are likely to overlap with Cable Car project to match the opening date.
The cumulative noise impact of Cable Car project and relevant component
sections of Ngong Ping STW (based on Table 4.8 of Section 4 of approved EIA
report under Register No. EIA-079/2002 “Ngong Ping Sewage Treatment Work and
Sewerage” ) have thus been assessed.
Due
to the project nature, threeA
plant inventory lists consisting of Airport Island
Angle Station, Ngong Ping/Tung
Chung Terminals and Nei Lak Shan Angle Station/Towers for the Cable Car
project,
as confirmed by Mass Transit Railway Corporation (MTRC) and Ngong Ping STW (based on Table 4.8 of Section 4
of approved EIA report under Register No. EIA-079/2002 “Ngong Ping Sewage
Treatment Work and Sewerage” ) has been established. The details are contained in Tables 4.6 to 4.8.
Table 4.6Plant Inventory for Airport Island Angle Station/Towers T1 and T2 (No Mitigation Measures)
Plant Inventory for Airport Island Station/Towers
T1 and T2
|
PME |
TM Ref. |
No. |
SWL/Unit, dB(A) |
Sub-SWL, dB(A) |
|
Site Formation and Excavation |
|
|
|
|
Site Foundation and Excavation |
Breaker, excavator mounted (hydraulic) |
CNP 028 |
2 |
122 |
125 |
|
Excavator |
CNP 081 |
1 |
112 |
112 |
|
Dump Truck |
CNP 067 |
2 |
117 |
120 |
|
|
|
|
Total SWL |
126 |
|
Substructure |
|
|
|
|
Piling |
Piling, large diameter bored(1) |
CNP 164 |
1 |
115 |
115 |
|
Excavator |
CNP 081 |
1 |
112 |
112 |
|
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard |
CNP 101 |
1 |
108 |
108 |
|
Dump Truck |
CNP 067 |
1 |
117 |
117 |
|
|
|
|
Total SWL |
120 |
Pile Cap |
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard |
CNP 101 |
1 |
108 |
108 |
|
Lorry |
CNP 141 |
1 |
112 |
112 |
|
|
|
|
Total SWL |
113 |
Concreting |
Crane, mobile |
CNP 048 |
1 |
112 |
112 |
|
Concrete lorry mixer |
CNP 044 |
1 |
109 |
109 |
|
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
114 |
|
Superstructure |
|
|
|
|
Formwork and Reinforcement |
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard |
CNP 101 |
1 |
108 |
108 |
|
Crane, mobile |
CNP 048 |
1 |
112 |
112 |
|
Saw, circular, wood |
CNP 201 |
1 |
108 |
108 |
|
Lorry |
CNP 141 |
1 |
112 |
112 |
|
|
|
|
Total SWL |
116 |
Concreting |
Crane, mobile |
CNP 048 |
1 |
112 |
112 |
|
Concrete lorry mixer |
CNP 044 |
1 |
109 |
109 |
|
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
114 |
Cabling |
Conveyor belt |
CNP 041 |
1 |
90 |
90 |
|
Generator |
CNP 102 |
1 |
100 |
100 |
|
Hoist |
CNP 122 |
1 |
95 |
95 |
|
Winch |
CNP 262 |
1 |
95 |
95 |
|
|
|
|
Total SWL |
102 |
Note(s): |
|
|
|
|
|
1. Apart from CNP164, (CNP165-Piling, large diameter bored, oscillator) or (CNP166-Piling, large diameter bored, reverse circulation drill) may be used instead for the construction activities |
Table 4.7 Plant
Inventory for Ngong
Ping/Tung Chung Terminals (No Mitigation Measures)Ngong Ping/Tung
Chung Terminals
|
PME |
TM Ref. |
No. |
SWL/Unit, dB(A) |
Sub-SWL, dB(A) |
|
Site Formation and Excavation |
|
|
|
|
Site Foundation and Excavation |
Breaker, excavator mounted (hydraulic) |
CNP 028 |
1 |
122 |
122 |
|
Excavator |
CNP 081 |
1 |
112 |
112 |
|
Dump Truck |
CNP 067 |
1 |
117 |
117 |
|
|
|
|
Total SWL |
124 |
|
Substructure |
|
|
|
|
Piling |
Piling, large diameter bored(1) |
CNP 164 |
1 |
115 |
115 |
|
Excavator |
CNP 081 |
1 |
112 |
112 |
|
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard |
CNP 101 |
1 |
108 |
108 |
|
Dump Truck |
CNP 067 |
1 |
117 |
117 |
|
|
|
|
Total SWL |
120 |
Pile Cap |
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard |
CNP 101 |
1 |
108 |
108 |
|
Lorry |
CNP 141 |
1 |
112 |
112 |
|
|
|
|
Total SWL |
113 |
Concreting |
Crane, mobile |
CNP 048 |
1 |
112 |
112 |
|
Concrete lorry mixer |
CNP 044 |
1 |
109 |
109 |
|
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
114 |
|
Superstructure |
|
|
|
|
Formwork and Reinforcement |
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard |
CNP 101 |
1 |
108 |
108 |
|
Crane, mobile |
CNP 048 |
1 |
112 |
112 |
|
Saw, circular, wood |
CNP 201 |
1 |
108 |
108 |
|
Lorry |
CNP 141 |
1 |
112 |
112 |
|
|
|
|
Total SWL |
116 |
Concreting |
Crane, mobile |
CNP 048 |
1 |
112 |
112 |
|
Concrete lorry mixer |
CNP 044 |
1 |
109 |
109 |
|
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
114 |
Cabling |
Conveyor belt |
CNP 041 |
1 |
90 |
90 |
|
Generator |
CNP 102 |
1 |
100 |
100 |
|
Hoist |
CNP 122 |
1 |
95 |
95 |
|
Winch |
CNP 262 |
1 |
95 |
95 |
|
|
|
|
Total SWL |
102 |
|
|
|
|
|
|
Note(s): |
|
|
|
|
|
1 Apart from CNP164, (CNP165-Piling, large diameter bored, oscillator) or (CNP166-Piling, large diameter bored, reverse circulation drill) may be used instead for the construction activities. |
Table 4.8Plant Inventory for Nei Lak Shan/Towers T3, T4, T5, T6 and T7 (No Mitigation Measures)
|
PME |
TM Ref. |
No. |
SWL/Unit, dB(A) |
Sub-SWL, dB(A) |
|
Site Formation and Excavation |
|
|
|
|
Site Foundation and Excavation |
Breaker, hand-held, mass > 35kg |
CNP 026 |
1 |
114 |
114 |
|
Air compressor, air flow <10m3/min |
CNP 001 |
1 |
100 |
100 |
|
Helicopter(1) |
- |
1 |
92 |
92 |
|
|
|
|
Total SWL |
114 |
|
Substructure |
|
|
|
|
Piling |
Mini Piling Rig(2) |
- |
1 |
113 |
113 |
|
Helicopter |
- |
1 |
92 |
92 |
|
|
|
|
Total SWL |
113 |
Concreting |
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
Helicopter |
- |
1 |
92 |
92 |
|
|
|
|
Total SWL |
105 |
|
Superstructure |
|
|
|
|
Formwork and Reinforcement |
Helicopter |
- |
1 |
100 |
100 |
|
|
|
|
Total SWL |
100 |
Concreting |
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
Helicopter |
- |
1 |
92 |
92 |
|
|
|
|
Total SWL |
105 |
Cabling |
Conveyor belt |
CNP 041 |
1 |
90 |
90 |
|
Generator |
CNP 102 |
1 |
100 |
100 |
|
Hoist |
CNP 122 |
1 |
95 |
95 |
|
Winch |
CNP 262 |
1 |
95 |
95 |
|
|
|
|
Total SWL |
102 |
|
|
|
|
|
|
Note(s):
1. Maximum SWL of helicopter is 100dB(A) and assume 5 minutes duration within every 30 minutes during transportation [ i.e. 10*log(10100/10x5mins/30mins) = 92 dB(A)]
2. Refer to Table C.10, item 6 of BS5228 for SWL
As the Theme
Village is still at the conceptual stage, no plant inventory has yet been
defined. However, to allow the
cumulative impacts to be addressed a maximum noise level of 75 dB(A) has been
included in the cumulative impact assessment for the construction of the Theme
Village in the assessments.
Due to the remote nature of
work sites for the tower locations, helicopters or a temporary materialaerial ropeway could
be used to transport construction materials to the tower sites (noting that the latter is not
favoured). The use of helicoptersis will not only
minimize the environmental impacts but also reduce the disturbance to the
Country Park as compared to the use of a haul road
(in the unlikely event that
the use of a haul roadwere that to would be permitted).
Use of Helicopters
Due to the
remoteness of the construction site and the flexibility of flight paths, it is
expected that helicopters are most likely to be used to convey materials to
site. The Cable Car system Contractor
has proposed two types of helicopters (Vladivostok Air - Helicopter Type KA-32
and Erickson Aircrane - Helicopter Type S64) with maximum sound power level (i.e. 100dB(A) during flyover) for use on
this project. According to the proposed alignment, work sites
(i.e. Towers 3, 4, 5, 6, 7 and the Nei Lak Shan Angle Station) are inaccessible
construction sites (i.e. cannot be accessed by existing roads/footpaths and no
new haul roads will be constructed in the Country Park). Work site (i.e. Tower
7) is
the
closest noise source to NSRs.In this connection, helicopter is considered as a
piece of PME and incorporated into the plant inventory for Nei Lak
Shan/Towers. The noise level
generated by the helicopter landing/taking-off at work sites has been modeled
as a point source and assumed 5 minutes duration within every 30
minutes during transportation. Hence,
the sound power level of helicopter during transportation is convertednectedto 92
dB(A). Moreover, calculations have been
conducted to predict the maximum sound pressure level of the helicopter at the
facades of the representative NSRs using basic acoustic principles and the
results are incorporated in all relevant
Tables of Part A of Annex H.
Landing / Taking-off at Touch Down Points
Two potential touch down points (i.e. Airport Island and Tung Chung Bay as shown in Figure 4.3) have been proposed for the construction stage. Please note that these will not be used for the operational stage which requires rescue touch down points (i.e. three located in the Country Park far from sensitive receivers, refer to Figure 2.14). The closest sensitive receiver to the touch down points is Village Houses at Tin Sum (i.e. NSR8) . The noise impact due to the helicopter operation at the touch down point has been modeled as a point source. Moreover, calculations have been conducted to predict the maximum sound pressure level generated from the helicopter at the facades of the representative NSRs using basic acoustic principles as follows.
Leq(predicted) = Leq(reference) – 20 log [D(nsr-source) / D(reference-source)] + 3 (*)
Where
Leq(predicted) is the predicted maximum noise level in dB(A);
Leq(reference) is the predicted maximum noise level being monitored;
D(nsr-source) is the distance (in metres) from noise sensitive receiver to noise source; and
D(reference-source) is the distance (in metres) from referenced monitoring location to noise source.
The maximum noise level at this receiver as shown in
Table 4.?? is36dB(A) with the separation of 345 metres which
complies with 75dB(A) noise criterion. The details are
shown in Part B of Annex H. All proposed
touch down points are therefore acceptable from a noise perspective.
Flight Path
According to the Hong Kong’s Civil Aviation Department requirements, helicopters must operate over the 152 metres (i.e. 500 ft) threshold above residential properties. Hence, based on this restricted separation, it can be seen that the maximum noise level is 43 dB(A) at 152 metres which complies with the 75 dB(A) noise criterion. The details of the flight path can only be agreed within Civil Aviation Department when the Contractor presents a construction plan for approval. However, the flight path is anticipated to be along cable car alignment and the nearest sensitive receiver to the touch down points is village houses at Tin Sum (i.e. NSR8). As discussed in preceding paragraph, the noise level at the receiver is in compliance with noise criterion.
Construction Works and Percussive Piling
The source of
noise nuisance during construction is primarily from the use of Powered
Mechanical Equipment (PME) on site.
According to the presumed plant inventory, the total Sound Power Level
(SWL) associated with each construction activity has been established and the
details are contained in Tables 4.6 and 4.7.
Table 4.6Plant Inventory for One Tower Site (No
mitigation Measures)
Table 4.7Plant
Inventory for Terminals/Angle Stations (No mitigation Measures)
* This equipment is not applicable at the Nei
Lak Shan Angle Station as the materials will be transported by helicopter.
In order to predict the
noise level in worse case scenario it has been assumed that construction at
tower sites (T1 and T7)
totally overlaps with the noisiest activities at the terminalsi, airport island angle station (i.e. site information foundation and
excavation or foundation substructure or
superstructure depending on the overall maximum sound power level of each noisy
activity)
and Ngong Ping STW. The cumulative effect of construction of the Ngong
Ping Terminal, Tower (T7) and Ngong Ping STW and as well as asthe Tung Chung Terminal and
Tower (T1) Airport Island
Angle Station have been assessed respectively. The
results are shown in Tables 4.9, 4.12 and 4.14 and the detailed calculation
sheets are presented and shown in Tables A1-3 in Part A of Annex H 4.8 below.
As As
part of the construction work for Ngong Ping STW will be carried out
concurrently with Cable Car project (Ngong Ping Area) and in order to predict
the worse case scenario, the noisiest activities (i.e. site
formation/earthworks/rock breaking) have been chosen for the construction noise
assessment.
Table
4.89 Cumulative Noise Impacts for Cable Car Project (No mitigation
Measures) - (Leq.30min dB(A))
NSRs |
Area |
Location |
Cable Car Project
|
Noise Impacts from Ngong Ping STW
|
Cumulative Noise Impacts
|
||
Tower Site
|
Terminals
|
Airport Island Angle Station |
Site Formation/ Earthworks/ rock breaking |
||||
NSR1a |
|
Village
houses - Kam Wai Yuen |
59 |
76 |
N/A |
73 |
78 |
NSR1b |
Ngong Ping |
Village
houses along Ngong Ping Road near bus terminus |
55 |
67 |
N/A |
69 |
72 |
NSR2 |
|
Tin Tan
Buddha Status |
50 |
63 |
N/A |
65 |
67 |
NSR3 |
|
Lin Chi
Monastery |
61 |
66 |
N/A |
64 |
69 |
NSR4 |
|
Tung Chung
Crescent - Block 7 (Flat A) |
N/A |
85 |
64 |
N/A |
85 |
NSR5 |
Tung Chung |
Fu Tung
Estate - Tung Ma House (Flat 03) |
N/A |
68 |
61 |
N/A |
69 |
NSR6 |
|
Seaview
Crescent - Block 1 (Flat D) |
N/A |
68 |
62 |
N/A |
69 |
NSR7 |
|
Wan Ho Kan
Primary School |
N/A |
68 |
60 |
N/A |
67 |
Notes: 1. Bold figure exceeds noise criteria 2. N.A. denotes Not Applicable 3. Façade effect is considered for all NSRs excepted NSR2 4. Information extracted from Table 4.8 of Section 4 of approved EIA report under register no. EIA-079/2002 “Ngong Ping Sewage Treatment Works and Sewerage” |
As shown in Table 4.9D1 in Part D of
Annex H, The itpredictions
indicates that the
cumulative noise impact of both unmitigated construction of Annex H activities
associated with the construction of the Terminal (i.e. site formationfoundation and excavation) and, Tower Site, Airport Island Angle Station
(only applicable for Tung Chung Area) and mitigated construction
activities relating to the construction of Ngong Ping STW (only applicable for
Ngong Ping Area), would cause exceedance of the daytime construction noise
criterion by 35dB(A) (i.e.
NSR1a of Ngong Ping Area) and 10dB(A) (i.e. NSR4 of
Tung Chung Area). Approximately 600 dwellings
of NSR 4 and 10 dwellings of NSR1a owuld would bebe expressed exposed tothe excessive noise levels. The results further
indicate that the major noise contribution to the affected receiver is the
noise impacts from the plant inventory of construction of both Terminals. The duration of the construction activities
are about one year. Mitigation
measures are therefore required
for these NSRs in
order to alleviate the noise impacts generated from cable car project.
At the Airport
Angle Station, rock excavation will be required and three impact hammers (i.e.
Breaker, excavator mounted (pneumatic) – (CNP027) and two backactors (i.e.
Bulldozer – (NP 030) would be used. The
cumulative sound power level is 127 dB(A).
The nearest receiver Tung Chung Crescent (i.e. NSR 4) from the Airport
Angle Station is over 720m from the source.
The noise level at the nearest receiver after taking into account
distance attenuation (i.e. 62 dB(A)) is 65 dB(A), which complies with the noise
criterion. No mitigation measures are
therefore required other than:
·good site practice to limit noise emissions at
source
·selection of quieter plant and working methods
The following
suite of practical and implementable mitigation measures has already been
included in MTRC’s General Specification:
Noise Mitigation Measures
Good site practice and noise management can significantly reduce the impact of construction site activities on nearby NSRs. The following package of measures should be followed during of construction:
· only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works;
· machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;
· plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;
· mobile plant should be sited as far away from NSRs as possible; and
· material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.
The following sections describe measures which may be considered to reduce noise to acceptable levels, using monitoring to confirm the acceptability of the proposed mitigation.
Selecting Quieter Plant and Working Methods
The Contractor may be able to obtain particular models of plant that are quieter than standards given in GW-TM. Benefits which can be achieved through this approach will depend on the details of the Contractor chosen methods of working. As it is considered too restrictive to define specific items of plant for the construction operations, it is more practical to specify an overall plant noise performance specification to apply to the total SWL of all plant on the site so that the Contractor is allowed some flexibility to select plant to suit his needs.
Quiet plant is defined as
PME whose actual SWL is less than the value specified in GW-TM for the same
piece of equipment. Examples of SWLs
for specific silenced PME taken from a British Standard, namely Noise Control
on Construction and Open Sites, BS 5228 : Part 1 : 1997, which are known to be
used are given in Table 4.109.
Table 4.109 Sound Power Levels for Specific Silenced
PME
PME |
BS 5228 Table no |
Ref no |
SWL dB(A) max |
Generator |
C.7 |
6 |
1 |
|
|
|
|
Excavator |
C.3 |
97 |
105 |
|
|
|
|
Breaker, excavator mounted (hydraulic) |
C.8 |
13 |
110 |
|
|
|
|
Dump Truck |
C.9 |
29 |
109 |
|
|
|
|
Concrete Lorry Mixer |
C.6 |
35 |
100 |
|
|
|
|
Lorry |
C.9 |
27 |
105 |
|
|
|
|
Mobile Crane |
C.7 |
118 |
99 |
|
|
|
|
Chain Saw |
C.7 |
78 |
106 |
Table 4.11Plant Inventory for Ngong Ping/Tung Chung
Terminals (Using quiet pplant)Ngong Ping/Tung Chung Terminals
|
PME |
TM Ref. /BS5228 |
No. |
SWL/Unit, dB(A) |
Sub-SWL, dB(A) |
|
Site Formation and Excavation |
|
|
|
|
Site Foundation and Excavation |
Breaker, excavator mounted (hydraulic)* |
C.8-13 |
1 |
110 |
110 |
|
Excavator* |
C.3-97 |
1 |
105 |
105 |
|
Dump Truck* |
C.9-29 |
1 |
109 |
109 |
|
|
|
|
Total SWL |
113 |
|
Substructure |
|
|
|
|
Piling |
Piling, large diameter bored(1) |
CNP 164 |
1 |
115 |
115 |
|
Excavator* |
C.3-97 |
1 |
105 |
105 |
|
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard* |
C.7-62 |
1 |
100 |
100 |
|
Dump Truck* |
C.9-29 |
1 |
109 |
109 |
|
|
|
|
Total SWL |
116 |
Pile Cap |
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard* |
C.7-62 |
1 |
100 |
100 |
|
Lorry* |
C.9-27 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
106 |
Concreting |
Crane, mobile* |
C.7-118 |
1 |
99 |
99 |
|
Concrete lorry mixer* |
C.6-35 |
1 |
100 |
100 |
|
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
107 |
|
Superstructure |
|
|
|
|
Formwork and Reinforcement |
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard* |
C.7-62 |
1 |
100 |
100 |
|
Crane, mobile* |
C.7-118 |
1 |
99 |
99 |
|
Saw, circular, wood* |
C.7-78 |
1 |
106 |
106 |
|
Lorry* |
C.9-27 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
110 |
Concreting |
Crane, mobile* |
C.7-118 |
1 |
99 |
99 |
|
Concrete lorry mixer* |
CNP 044 |
1 |
100 |
100 |
|
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
107 |
Cabling |
Conveyor belt |
CNP 041 |
1 |
90 |
90 |
|
Generator |
CNP 102 |
1 |
100 |
100 |
|
Hoist |
CNP 122 |
1 |
95 |
95 |
|
Winch |
CNP 262 |
1 |
95 |
95 |
|
|
|
|
Total SWL |
102 |
Note(s):
1. Apart from CNP164, (CNP165-Piling, large diameter bored, oscillator) or (CNP166-Piling, large diameter bored, reverse circulation drill) may be used instead for the construction activities.
2. '*' denotes quiet alternative is used in accordance with BS5228, 1997
With quiet plant (as
described in Table 4.109 above) substituted in the equipment
inventories given in Table
4.11 s 4.10 and 4.11,
the cumulative noise impact of both unmitigated construction activities
associated with the construction of Ngong Ping Terminal, and Tower Site, Airport
Island Angle Station and mitigated construction
activities related to the construction of Ngong Ping STW, would be further
reduced as shown in Table4.12.
Table 4.12 Cumulative Noise Impacts for Cable Car Project (Using Quiet Plant) - (Leq.30min dB(A))
NSRs |
Area |
Location |
Noise Impacts from Cable Car Project /dB(A)
|
Noise Impacts from Ngong Ping STW /dB(A)
|
Cumulative Noise Impacts /dB(A)
|
||
Tower Site
|
Terminals
|
Airport
Island Angle Station |
Site Formation/ Earthworks/ rock breaking |
||||
NSR1a |
|
Village
houses - Kam Wai Yuen |
59 |
66 |
N/A |
73 |
75 |
NSR1b |
Ngong Ping |
Village
houses along Ngong Ping Road near bus terminus |
55 |
60 |
N/A |
69 |
70 |
NSR2 |
|
Tin Tan
Buddha Status |
50 |
56 |
N/A |
65 |
66 |
NSR3 |
|
Lin Chi
Monastery |
61 |
59 |
N/A |
64 |
67 |
NSR4 |
|
Tung Chung
Crescent - Block 7 (Flat A) |
N/A |
77 |
64 |
N/A |
78 |
NSR5 |
Tung Chung |
Fu Tung Estate
- Tung Ma House (Flat 03) |
N/A |
61 |
61 |
N/A |
64 |
NSR6 |
|
Seaview
Crescent - Block 1 (Flat D) |
N/A |
61 |
62 |
N/A |
64 |
NSR7 |
|
Wan Ho Kan
Primary School |
N/A |
59 |
60 |
N/A |
62 |
Notes: 1. Bold figure exceeds noise criteria 2. N.A. denotes Not Applicable 3. Façade effect is considered for all NSRs excepted NSR2 4. Information extracted from Table 4.8 of Section 4 of approved EIA report under register no. EIA-079/2002 “Ngong Ping Sewage Treatment Works and Sewerage”
|
Table
4.10 Plant Inventory for One Tower Site
(Using Quiet Plant)
*Items replaced by quiet plant
Table 4.11 Plant Inventory for Terminals (Using Quiet
Plant)
*Items replaced by quiet plant
Table 4.12 Cumulative
Noise Impacts for Cable Car Project (Using Quiet Plant) - (Leq.30min dB(A))
Table 4.13 The results indicates that with the use of quiet plant
under the construction of Terminal and Tower Site,
the cumulative noise impact of both mitigated construction activities
associated with the construction of Tung Chung Terminal (i.e. foundationsubstucture)
and Tower Site Airport Island
Angle Station would cause exceedance of the daytime construction noise
criterion by 4 3 dB(A) at NSR4 in the Tung Chung Area. Approximately 600 dwellings of NSR4 would be
exposed the to excessive noise levels. The results further indicate that the major
contribution to the affected received in the noise impacts from the plant
inventory of construction of both terminals.
The duration of the construction activities are about one year. Further mitigation
measures are therefore required in order to alleviate the noise impacts
generated during construction of the Cable Car Project at NSR4.
Construction of Movable Noise Barriers
Movable barriers can be very effective in screening noise from particular items of plant when constructing the Tung Chung and Ngong Ping Terminal. A noise barrier located close to the noise generating component of a PME could produce at least 10 dB(A) screening for stationary plant and 5 dB(A) for mobile plant provided it blocked the direct line of sight between the PME and the NSR. The noise screening benefit for each item of plant considered in this assessment is listed as follows:
·
stationary
plant - assuming 10 dB(A) reduction:
air compressor, concrete pump, lorry mixer, poker vibrator and bar
bender;
·
mobile and items of large plant -
assuming 5 dB(A) reduction: piling, large diameter boredrock driller and compactor.
Table 4.13 Plant Inventory for Ngong Ping/Tung Chung Terminals (Using movable noise barrier)
|
PME |
TM Ref. /BS5228 |
No. |
SWL/Unit, dB(A) |
Sub-SWL, dB(A) |
|
Site Formation and Excavation |
|
|
|
|
Site Foundation and Excavation |
Breaker, excavator mounted (hydraulic)* |
C.8-13 |
1 |
110 |
110 |
|
Excavator* |
C.3-97 |
1 |
105 |
105 |
|
Dump Truck* |
C.9-29 |
1 |
109 |
109 |
|
|
|
|
Total SWL |
113 |
|
Substructure |
|
|
|
|
Piling |
Piling, large diameter bored(1)# |
CNP 164 |
1 |
110 |
110 |
|
Excavator* |
C.3-97 |
1 |
105 |
105 |
|
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard* |
C.7-62 |
1 |
100 |
100 |
|
Dump Truck* |
C.9-29 |
1 |
109 |
109 |
|
|
|
|
Total SWL |
113 |
Pile Cap |
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard* |
C.7-62 |
1 |
100 |
100 |
|
Lorry* |
C.9-27 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
106 |
Concreting |
Crane, mobile* |
C.7-118 |
1 |
99 |
99 |
|
Concrete lorry mixer* |
C.6-35 |
1 |
100 |
100 |
|
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
107 |
|
Superstructure |
|
|
|
|
Formwork and Reinforcement |
Bar bender and cutter (electric) |
CNP 021 |
1 |
90 |
90 |
|
Generator, standard* |
C.7-62 |
1 |
100 |
100 |
|
Crane, mobile* |
C.7-118 |
1 |
99 |
99 |
|
Saw, circular, wood* |
C.7-78 |
1 |
106 |
106 |
|
Lorry* |
C.9-27 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
110 |
Concreting |
Crane, mobile* |
C.7-118 |
1 |
99 |
99 |
|
Concrete lorry mixer* |
CNP 044 |
1 |
100 |
100 |
|
Compactor, vibratory |
CNP 050 |
1 |
105 |
105 |
|
|
|
|
Total SWL |
107 |
Cabling |
Conveyor belt |
CNP 041 |
1 |
90 |
90 |
|
Generator |
CNP 102 |
1 |
100 |
100 |
|
Hoist |
CNP 122 |
1 |
95 |
95 |
|
Winch |
CNP 262 |
1 |
95 |
95 |
|
|
|
|
Total SWL |
102 |
Note(s):
1. Apart from CNP164, (CNP165-Piling, large diameter bored, oscillator) or (CNP166-Piling, large diameter bored, reverse circulation drill) may be used instead for the construction activities.
2. '*' denotes quiet alternative is used in accordance with BS5228, 1997
3. '#' denotes the movable noise is used
The effect of the use of quiet plant and using movable barriers (as described in Table 4.13) has been investigated for the practicable construction activities and the results are presented in Table 4.14.
Table 4.14 Cumulative Noise Impacts for Cable Car Project (Using Noise Barrier at terminals) - (Leq.30min dB(A))
NSRs |
Area |
Location |
Noise Impacts from Cable Car Project /dB(A)
|
Noise Impacts from Ngong Ping STW /dB(A)
|
Cumulative Noise Impacts /dB(A)
|
||
Tower Site
|
Terminals
|
Airport
Island Angle Station |
Site Formation/ Earthworks/ rock breaking |
||||
NSR1a |
|
Village
houses - Kam Wai Yuen |
59 |
66 |
N/A |
73 |
74 |
NSR1b |
Ngong Ping |
Village
houses along Ngong Ping Road near bus terminus |
55 |
57 |
N/A |
69 |
70 |
NSR2 |
|
Tin Tan Buddha
Status |
50 |
53 |
N/A |
65 |
66 |
NSR3 |
|
Lin Chi
Monastery |
61 |
56 |
N/A |
64 |
66 |
NSR4 |
|
Tung Chung
Crescent - Block 7 (Flat A) |
N/A |
74 |
64 |
N/A |
75 |
NSR5 |
Tung Chung |
Fu Tung
Estate - Tung Ma House (Flat 03) |
N/A |
58 |
61 |
N/A |
63 |
NSR6 |
|
Seaview
Crescent - Block 1 (Flat D) |
N/A |
58 |
62 |
N/A |
63 |
NSR7 |
|
Wan Ho Kan
Primary School |
N/A |
56 |
60 |
N/A |
61 |
Notes: 1. Bold figure exceeds noise criteria 2. N.A. denotes Not Applicable 3. Façade effect is considered for all NSRs excepted NSR2
4. |
With the incorporation of
quiet plant, and the use of movable barriers
(to reduce noise level at source) at the Terminal, Tthe results indicate that
the cumulative noise impact of both mitigated construction activities
associated with the construction of Terminal (i.e. substructure) at both Tung Chung and Ngong Ping, Airport
Island Angle Station and Tower (together with the construction of Ngong Ping
STW), would fully comply with the daytime construction noise criterion.
The mitigation measures described herein are a suite of measures which need to be considered in stages. The actual noise levels of the construction works should be checked and where necessary mitigation measures applied as required to reduce the noise to acceptable levels.
Table 4.13 Plant Inventory for Terminals (Using Noise
Barrier)
*Items replaced by quiet plant
#Items mitigated by noise barriers
With the
incorporation of quiet plant, and the use of movable barriers (to reduce noise level at source) at the
Terminal, Table 4.14indicates that
the cumulative noise impact of both mitigated construction activities
associated with the construction of Terminal (site formation) and towers at
both Tung Chung and Ngong Ping, (together with the construction of Ngong Ping
STW), would fully comply with the daytime construction noise criterion.
The mitigation
measures described herein are a suite of measures which need to be considered
in stages. The actual noise levels of
the construction works should be checked and where necessary mitigation
measures applied as required to reduce the noise to acceptable levels.
Use of
Helicopters
Due to the
remoteness of the construction site and the flexibility of flight paths, it is
expected that helicopters are most likely to be used to convey materials to
site. Based on a commonly used helicopter (Aerospatiale-AS355), the Lmax dB(A) of the
helicopter is 77dB(A)@153m and was used for the noise assessment under worst
case scenario. However, the Cable Carsystemaccording to
thecContractor has proposedinformation two types ofproposed helicopters (Vladivostok Air -use Helicopter Type KA-32 and Erickson Aircrane -use Helicopter Type S64) with relatively less sound
pressure level (i.e. 48dB(A)@153m) for use on this
projectwill be used for transportation. Notwithstanding
the foregoing the worst case scenario was considered.Hence, more
conservative results were obtained. According to
the proposed alignment, the nearest noise sources are the work sites (i.e.
Towers T3 and T7) and proposed touch down points (i.e. Airport Island, Tung
Chung Bay and Ngau Tau Touch Down Points as shown in Figure 4.3). The noise level generated by the helicopter
landing/taking-off at work sites has been modeled as a point source. Moreover, calculations have been conducted
to predict the maximum sound pressure level of the helicopter at the facades of
the representative NSRs using basic acoustic principles and the results are
shown in Table 4.15.
Landing /
Taking-off at Touch Down Points
As stated in
the preceding section, three potential touch down points have been proposed for the
construction stage. As shown in Table 4.15, the results indicate
that full compliance is expected. The
closest sensitive receiver is Lin Chi Temple (75 dB(A) under worst case
scenario), and even at NSRs 8 and 9
which are closest to the touch down points (i.e. Village Houses at Tin
Sum and Ngau Au) the noise standard can be achieved. All proposed touch down points are therefore acceptable from a
noise perspective.
Landing /
Taking-off at Work Sites
As stated in
preceding section, work sites (i.e. Towers 3, 4, 5, 6, 7 and the Nei Lak Shan
Angle Station) are inaccessible construction sites (i.e. cannot be accessed by
existing roads/footpaths and no new haul roads will be constructed in the
Country Park). Work sites (i.e. Towers 3 and 7) are the closest noise sources
to NSRs. As shown in Table 4.15, the
results indicate that the receivers at NSR 3 (i.e. Lin Chi Monastery) will not
experience noise levels in excess of the criterion.
Flight Path
According to
the Hong Kong’s Civil Aviation Department requirements, helicopters must
operate over the 152 metres (i.e. 500 ft) threshold above residential
properties. Hence, based on this
restricted separation, it can be seen that the maximum noise requirement, as
shown in Table 4.14for the
helicopter, is 75 dB(A) at 152 metres which complies with the 75 dB(A) noise
criterion. The
details of the flight path can only be agreed within Civil Aviation
Department when the Contractor presents a construction plan for approval. Assessments contained herein have considered
the worst case situation.
Table 4.15 Predicted Helicopter Noise- (LmaxdB(A))
Material Ropeway
For similar reasons as those given for the helicopter, a material ropeway is another alternative to transport construction materials to the remote sites. As the material ropeway is not expected to generate noise except at the Angle Station and the distance between the Angle Station and the nearest sensitive receiver (i.e. NSR 3 - Lin Chi Monastery) is over 1200m, the distance attenuation is over 60 dB(A). Hence, it can be concluded that the noise impact generated from the temporary aerial ropeway system is insignificant.
It should be noted that
helicopters would still be required to take deliver materials to site to construct
the ropeway and the comments in the preceding section apply.
Notwithstanding the foregoing the use of a material ropeway is not recommended on ecological or visual grounds.
During the operational
phase, noise generated from the operation of the project essentially relates to
the use of mechanical equipment at the Tung Chung Terminal and Ngong Ping
Terminal, and the wheel “squeal” or chatter
from the cable
car runners passing over the ropewaycars using the
cable car system.
Tung Chung Terminal/Ngong Ping Terminal/Airport Angle Station
No Minor mechanical
equipment will be installed at the cable car terminiTerminals,
(i.e Tung Chung Terminal and Ngong Ping Terminal) only wheels and electrical
motor for turning the operating system.
The noise generated from tdriving wheel hose is
insignificant. Major mechanical equipment will be installed at the Angle
Stations
of Airport Island at Tung Chung and at Nei Lak Shan.
In the current engineering design, all the potential noise sources (i.e. all mechanical equipment) shall be fully enclosed within the building structure. It is assumed that all the mechanical equipment installed at the Angle Stations of Airport Island and Nei Lak Shan will be housed inside concrete building or other suitable material with at least 20 dB(A) noise reduction.
Cable Car travelling along the Ropeway
Discrete noise impacts,
“wheel squeal/chatter” or “clamp shock”, will be
generated from the cable car runners passing over the ropeway.
Evaluation
Normal operation of the
cable car is assumed to be within the period 0700 to 2300 hours. and 2300to
0700 hours (for special occasion such as Buddha’s Birthday) The relevant noise
guidelines
for ASR
“A” daytime/evening of 55 dB(A) and night-time of 450 dB(A) as well as for
ASR “C” daytime/evening of 65 dB(A) and night-time of 55 dB(A) areis adopted as discussed in preceding
section 4.2. An assessment of operational noise impacts at the nearest receiver
was made based on standard acoustic principles after taking into account the
distance attenuation and façade correction.
Also, due to the noise impacts of the mechanical equipment from terminal and cable car travelling along the ropeway and in order to predict the noise level generated from both concurrent activities at the receivers under worst case scenario, it has been assumed that the maximum noise level arising from the Terminals (i.e. Tung Chung Terminal and Ngong Ping Terminal) and Towers (i.e. T1 and T7) at the nearest receiver were used for assessment purpose.
Regarding the operational noise
impact from Nei Lak Shan Angle Station and Airport Angle Station, aAs the distance from Ngong Ping Terminal (i.e. 270m)
is far shorter than from Nei Lak Shan Angle Station (i.e. 1500m) at Lin Chi
Monastery (i.e. NSR3), and . Similarly, the distance
from Tung Chung Terminal (i.e. 50m) is far shorter than from the Airport Angle
Station (i.e. 720m) at Tung Chung Crescent (i.e. NSR4), . Hence, the noise
contribution from Ngong Ping Terminal and Tung Chung Terminal respectively were used for the assessment purposes.
Also, sound power pressure level
of the mechanical equipment from terminal and cable car travelling along the
ropeway are 85
dB(A) and 75 dB(A) respectively 85 dB(A) and 75 dB(A) respectivelybased on
measurements 0.8m above platform level with the horizontal distance of 2.5m. According to the proposed alignment, the
nearest noise sources are arising from the TerminiTerminals
(i.e. Tung Chung Terminal and Ngong Ping Terminal) and Towers (i.e. T1 and T7).
Therefore no
noise impact due to mechanical noise and the wheel (chatter) from the cable car
travelling along the ropeway at the nearest receiver is expected. The
noise impact due to the mechanical equipment from the terminal and cable car
travelling along the ropeway at each tower location, has been modeled as a
point source. Moreover, calculations
have been conducted to predict the maximum sound pressure level generated from
the Terminal and cable car system at the facades of the representative NSRs
using basic acoustic principles as follows. and Tthe results are shown in Tables 4.1516 and 4.
and the details are shown in Part CE and F of
Annex H17.
Leq(predicted) = Leq(reference) – 20 log [D(nsr-source) / D(reference-source)] + 3 (*)
Where
Leq(predicted) is the predicted maximum noise level in dB(A);
Leq(reference) is the predicted maximum noise level being monitored;
D(nsr-source) is the distance (in metres) from noise sensitive receiver to noise source; and
D(reference-source) is the distance (in metres) from referenced monitoring location to noise source.
Table 4.115 6 Predicted Cumulative Noise
Level for Terminal and Cable Car Travelling along the Ropeway -
(Leq.30min dB(A))
NSRs |
Area |
Location |
Noise Impact from Terminal Location (Ngong Ping, Tung chung) /dB(A) |
|
|
Noise Criteria /dB(A) |
NSR1a |
|
Village
houses - Kam Wai Yuen |
53 |
36 |
53 |
45 |
NSR1b |
Ngong Ping |
Village
houses along Ngong Ping Road near bus terminus |
45 |
32 |
45 |
45 |
NSR2 |
|
Tin Tan
Buddha Status |
40 |
3 |
40 |
45 |
NSR3 |
|
Lin Chi
Monastery |
44 |
37 |
45 |
45 |
NSR4 |
|
Tung Chung
Crescent - Block 7 (Flat A) |
62 |
37 |
62 |
55 |
NSR5 |
Tung Chung |
Fu Tung
Estate - Tung Ma House (Flat 03) |
46 |
31 |
46 |
55 |
NSR6 |
|
Seaview
Crescent - Block 1 (Flat D) |
45 |
32 |
46 |
55 |
NSR7 |
|
Wan Ho Kan
Primary School |
43 |
29 |
43 |
55 |
Note(s): 1. Façade effect is considered for all NSRs excepted NSR2 2. Night-time criteria (planning) is adopted as assessment standard |
Table 4.17
Predicted Noise Level for Cable Car travelling along the Ropeway - (Leq.30min dB(A))
Note(s):
1.Façade effect is considered for all NSRs excepted
NSR2
Table 4.15 indicates that operational noise impact generated from Ngong Ping Terminal, Tower (7) as well as Tung Chung Terminal and Tower (1) would cause exceedance of noise criterion by 8 dB(A) at NSR1a and by 7 dB(A) at NSR4.
The main source at the Terminals is the tensioning system which is driven by an electrical motor. It is recommended that an acoustic enclosure is providedto house the electrical motor. Provision of an acoustic enclosure could reduce noise levels by between 10dB(A) and 20dB(A). The results after mitigation (by reduction of 10 dB(A)) are shown in Table 4.16.
Table 4.16 Cumulative Noise Level for Terminal and Cable Car Travelling along the Reopeway (with Mitigation Measures)- (Leq.30min dB(A))
NSRs |
Area |
Location |
Noise Impact from Terminal Location (Ngong Ping, Tung chung) /dB(A) |
Noise Impact from Tower Site (T1, T7)/dB(A) |
Cumulative Noise Level /dB(A) |
Noise Criteria /dB(A) |
NSR1a |
|
Village houses - Kam Wai Yuen |
43 |
36 |
44 |
45 |
NSR1b |
Ngong Ping |
Village houses along Ngong Ping Road near bus terminus |
35 |
32 |
36 |
45 |
NSR2 |
|
Tin Tan Buddha Status |
30 |
30 |
33 |
45 |
NSR3 |
|
Lin Chi Monastery |
34 |
37 |
39 |
45 |
NSR4 |
|
Tung Chung Crescent - Block 7 (Flat A) |
52 |
37 |
52 |
55 |
NSR5 |
Tung Chung |
Fu Tung Estate - Tung Ma House (Flat 03) |
36 |
31 |
37 |
55 |
NSR6 |
|
Seaview Crescent - Block 1 (Flat D) |
35 |
32 |
37 |
55 |
NSR7 |
|
Wan Ho Kan Primary School |
33 |
29 |
35 |
55 |
Note(s): 1. Façade effect is considered for all NSRs excepted NSR2 2.
Night-time criteria (planning) is adopted as
assessment standard |
After provision of mitigation measures (i.e. acoustic enclosure), Table 4.16 shows that the noise levels at receiver comply with noise criterion.
Hence, it can be concluded that the planned development would not be impacted by the operational noise provided that the separation between the planned receivers at Ngong Ping Terminal and Tung Chung Terminal are not less than 140m and 50m respectively.
Construction Phase
No exceedance
of the noise criterion is expected at Ngong Ping. The most
seriously affected area is village houses in Ngong Ping Area (at NSR1a) and Tung
Chung Crescent in the Tung Chung Area (at NSR4) where unmitigated noise levels
of up to 78
and 8581 dB(A) respectively are
predicted due to construction of Tung Chung Terminal and Tower T1.
Therefore, adequate control
measures will be necessary for the works of Cable Car project in order to meet
the standards required. Approximately 600 dwellings of Tung
Chung Crescent (NSR4) and a few 10 dwellings of
village houses (NSR1a) would be exposed to excessive noise levels. After implementing mitigation measures such
as the use of quiet plant, erection of movable noise barrier and the adoption
of regular noise monitoring during construction phase, the noise criteria for
this project can be achieved and approximately 600 dwellings (all) will be
protected.
It is also recommended that
regular monitoring of noise at NSR1a - Village houses NSR3 - Lin Chi
Monastery (Ngong Ping) and at NSR4 - Tung Chung Crescent (Tung
Chung) is carried out during the construction phase.
Good site practice and noise
management should be implemented to significantly reduce the impact of
construction site activities on nearby NSRs.
The package of measures toshould be consideredfollowed during each
phase of construction includesuch as:-
· only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works;
· machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;
· plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;
· mobile plant should be sited as far away from NSRs as possible; and
· material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.
The use of helicopters for construction works would comply with the noise standards. All potential work sites would be acceptable from a noise perspective.
Operational Phase
With the mitigation measures
proposed such as housing all mechanical equipment inside a concrete
building with
at least 20 dB(A) noise reduction (for the
Airport Angle Station) or using or using then suitable material with at least 120 dB(A) noise reduction (i.e.
installation of acoustic enclosure of the electrical motor at the
terminals) and design standards imposed, noise
generated as a result of this project would meet the required standards.