2.
Project Description
2.1.
The proposed works includes a new
sewage collection system comprising gravity sewers, pumping stations and rising
mains to collect and transfer the sewage generated from the Sok Kwu Wan and the
surrounding areas to a new sewage treatment works (STW). The sewage would receive secondary treatment
with nitrogen removal and disinfection prior to disposal through a submarine
outfall to the entrance to the Picnic Bay.
The scope of this Project includes the following:
·
Construction of approximately 1.4 km of gravity sewers;
·
trench excavation for installation of underground sewer
pipes along Chung Mei Village, Sok Kwu Wan Village and Mo Tat Road;
·
modification of the existing combined stormwater system
to separate drainage and sewerage systems;
·
construction of three new sewage pumping stations, P1a,
P1b and P2, with installed capacities (ADWF) of approximately 353 m3/day,
508 m3/day and 879 m3/day, respectively;
·
construction of approximately 1.4 km rising main;
·
construction of a full secondary level sewage treatment
works (STW) with nitrogen removal and UV disinfection unit with an installed
capacity (ADWF) of 940 m3/day;
·
construction of a submarine effluent outfall of
approximately 765 m.
2.2.
Figure 2.1 illustrates the layout plan
of the proposed sewerage works. Based
on the preliminary construction programme, the construction of the Project was
scheduled to commence in December 2004 and for completion in August 2007. Since at this early stage of the Project
there are uncertainties over the way that individual contractors would
programme elements of the work, the programme has adopted a worst case scenario
and assumed that certain activities would be carried out concurrently.