TABLE OF CONTENT

1 INTRODUCTION

1.1 Purpose of this Manual

1.2 Objectives of EM&A Program

1.3 Background of the Project

1.4 Project Time Table

1.5 Structure of this Manual

 

2 PROJECT ORGANIZATION

2.2 Architect’s Representative (AR)

2.3 The Contractor

2.4 Environmental Team (ET)

2.5 Independent Checker (Environment) (ICE)

 

3 KEY ENVIRONMENTAL ISSUES

3.2 Air Quality

3.3 Noise

3.4 Land Contamination

3.5 Waste Management

3.6 Water Quality

3.7 Landscape and Visual Issues

3.8 Hazard to Life

 

4 AIR QUALITY MONITORING

4.1 Monitoring Parameters and Locations

4.2 Baseline Monitoring

4.3 Air Quality Action and Limit Levels

4.4 Impact Monitoring

4.5 Reporting

4.6 Monitoring Methodology

4.7 Monitoring Equipment

4.8 Laboratory Measurement / Analysis

4.9 Equipment Calibration

4.10 Operation Monitoring

4.11 Mitigation Measures to Reduce Adverse Environmental Impacts

 

5 NOISE MONITORING

5.1 Monitoring Parameters and Locations

5.2 Baseline Monitoring

5.3 Noise Action and Limit Levels

5.4 Impact Monitoring

5.5 Reporting

5.6 Monitoring Methodology

5.7 Monitoring Equipment

5.8 Equipment Calibration

5.9 Noise Mitigation Measures for Construction and Demolition Works

 

6 LAND CONTAMINATION

6.1 Introduction

6.2 Proposed Remediation Action Plan

6.3 Potential for Future Land Contamination

 

7 WASTE MANAGEMENT

7.1 Introduction

7.2 Mitigation of Adverse Environmental Impacts for Construction and Demolition Phase

7.3 Mitigation of Adverse Environmental Impacts for Operation Phase

 

8 LANDSCAPE AND VISUAL IMPACT

8.1 Introduction

8.2 Monitoring Requirements

8.3 Measures to Mitigate Landscape and Visual Impacts

 

9 WATER QUALITY

9.1 Introduction

9.2 Mitigation of Adverse Environmental Impacts

 

10 HAZARD TO LIFE

10.1 Introduction

10.2 Recommended Safety Measures

 

11 ENVIRONMENTAL AUDITING

11.1 Auditing/Inspection Approach

11.2 Compliance with Legal and Contractual Requirements

11.3 Environmental Complaints

 

12 REPORTING

12.1 General

12.2 Baseline Monitoring Report

12.3 Monthly EM&A Reports

12.4 First Monthly EM&A Report

12.5 Subsequent Monthly EM&A Reports

12.6 Quarterly EM&A Summary Reports

12.7 Final EM&A Summary Report

12.8 Data Keeping

12.9 Interim Notification of Environmental Quality Limit Exceedances

 

APPENDICES

Appendix A Proposed Project Programme

Appendix B Environmental Mitigation Implementation Schedule

Appendix C Event/Action Plan for Action/Limit Level Exceedance (Air and Noise)

Appendix D Dust and Noise Monitoring Field Log Sheets

Appendix E Notification of Exceedance Form

 

List of Tables

Table 4.1 Air Quality Monitoring Locations

Table 4.2 Action and Limit Levels for Air Quality

Table 4.3 Recommended Air Quality Monitoring Equipment

Table 5.1 Noise Sensitive Receiver Identified as Possible Location for Noise Monitoring

Table 5.2 Noise Action and Limit Levels

Table 5.3 Noise Monitoring Equipment

Table 6.1 Requirements for Supplementary Site Investigations

Table 6.2 Requirement for Confirmatory Site Investigations

Table 7.1 Further Contamination Investigation Requirements

Table 7.2 Proposed Contamination Classification for Ash Waste with DCM/HMCM/PAHCM

Table 7.3 Demolition, Handling, Treatment and Disposal of Moderately Contaminated DCM and Moderately/Severely Contaminated HMCM / PAHCM

Table 7.4 Demolition, Handling, Treatment and Disposal of Severely Contaminated DCM

 

List of Figures

Figure 1.1 Project Site Plan

Figure 2.1 Project Organization

Figure 4.1 Sampling Locations for TSP Baseline and Impact Monitoring

Figure 5.1 Representative Noise Monitoring Locations

Figure 6.1 Location of Exploratory Holes

Figure 6.2 Summary of the Remediation Works

 

List of Abbreviations

AL

Action/Limit

AR

Architect’s Representative

Arch SD

Architectural Services Department

ASRs

Air Sensitive Receivers

CAR

Contaminated Assessment Report

CAR

Contamination Assessment Report

CFR

Code of Federal Regulations

CLAP

China Light and Power

CNP

Construction Noise Permit

DGO

Dangerous Goods Ordinance

EIA

Environmental Impact Assessment

EM&A

Environmental Monitoring and Audit

EPD

Environmental Protection Department

ET

Environmental Team

FEHD

Food and Environmental Hygiene Department

HEPA

High Efficiency Particulate Air

HKPSG

Hong Kong Planning Standards and Guidelines

HVS

High Volume Sampling

ICE

Independent Checker (Environmental)

NCO

Noise Control Ordinance

NSRs

Noise Sensitive Receivers

PAH

Polyaromatic Hydrocarbons

PAHCM,

Polyaromatic Hydrocarbons Containing Materials

PCB

Polychlorinated Biphenyls

PCBCM

Polychlorinated Biphenyls Containing Materials

RAP

Remediation Action Plan

RAP

Remediation Action Plan

SLMs

Sound Level Meters

TCLP

Toxicity Characteristic Leaching Procedure

TM

Technical Memorandum

TPH

Total Petroleum Hydrocarbon

TPHCM

Total petroleum Hydrocarbon Containing Materials

TSP

Total Suspended Particulates

WPCO

Water Pollution Control Ordinance