DSD

 

Drainage Services Department

Hong Kong Special Administrative Region

of The People's Republic of China

 

 

Peng Chau Sewage Treatment Works Upgrade

-         Investigation, Design and Construction

 

Agreement No. CE 83/2001(DS)

 

Environmental Monitoring and Audit Manual

 

 

 

CDM

 


TABLE OF CONTENTS

 

1           INTRODUCTION

             Purpose of the Manual

             Project Description

             Works Programme

             Related Project

             Environmental Monitoring and Audit Requirements

             Project Organisation

 

2           AIR QUALITY MONITORING

             Introduction

             Air Quality Parameters

             Monitoring Equipment

             Laboratory Measurement/Analysis

             Monitoring Locations

             Baseline Monitoring

             Impact Monitoring

             Environmental Quality Performance Limits

             Event and Action Plan for Air Quality

             Mitigation Measures

 

3           NOISE MONITORING

             Introduction

             Noise Parameters

             Monitoring Equipment

             Monitoring Locations

             Baseline Monitoring

             Impact Monitoring

             Event and Action Plan

             Mitigation Measures

 

4           WATER QUALITY MONITORING

             Introduction

             Water Quality Parameters

             Monitoring Equipment

             Laboratory Measurement/Analysis

             Monitoring Locations

             Baseline Monitoring

             Impact Monitoring

             Post-construction Monitoring

             Event and Action Plan

             Operation Phase Monitoring

             Mitigation Measures

 

5                      SOLID WASTE MANAGEMNET

Introduction

Mitigation Measures

Construction Phase

Operation Phase

 

6                      MARINE ECOLOGY

Construction Phase

Operation Phase

 

7                      SITE ENVIRONMENTAL AUDIT

Site Inspection

Compliance with Legal and Contractual Requirements

Environmental Complaints

 

8                      REPORTING

General

Baseline Monitoring Report

Monthly EM&A Report

Post Commissioning Monitoring Reports

First Monthly EM&A Report

Subsequent EM&A Reports

Quarterly EM&A Summary Reports

Final EM&A Review Report

Data Keeping

Interim Notifications of Environmental Quality Limit Exceedances

 

APPENDICES

 

LIST OF TABLES

 

LIST OF FIGURES