9           Conclusions and Environmental outcomeS

9.1         Introduction

9.1.1        The future development and population growth in Tai Po and the adjacent area will inevitably increase the sewage flows and loads and thereby increase the demand for sewage treatment in order to preclude environmental deterioration.  Inevitably, given projected population levels in the catchment area, the projected sewage flows and loads would be in excess of the existing treatment capacity of the TPSTW. In addition the revised, more stringent, discharge standard to be adopted for the treated sewage of TPSTW also requires the upgrading of the existing sewage treatment facilities in TPSTW to achieve further improvement in environmental conditions.

 

9.1.2        Implementation of the Project will have several environmental benefits.  Firstly, upgrading of the Tai Po sewage treatment works will provide greater treatment capacity at an enhanced level of treatment meeting the revised, more stringent, discharge standard to be adopted to achieve further improvement in environmental conditions. Thus, despite the projected increase in sewage flows and loads from the Tai Po catchment, routine effluent discharges will be of a better quality and will benefit water quality in Victoria Harbour.  In addition, provision of greater treatment capacity is needed to match the continued development of Tai Po and proposed extensions of sewerage network under other projects to capture and treat sewage flows that may otherwise be discharged without treatment into Tolo Harbour.  Furthermore, there would also be benefits arsing from enhancements to be made to the existing sewage treatment works and thus the general area in its vicinity to control odours and noise.  Without the upgrading works, the existing Tai Po sewage treatment works would not be able to cope with the flow build-up.  If the treatment capacity of the plant is exceeded, inadequately treated sewage may need to be discharged into the vulnerable Tolo Harbour.  This, if allowed to happen, will lead to environmental deterioration.

9.1.1        The development and population growth in Tai Po and adjacent area will increase the demand of sewage treatment and be over the treatment capacity of existing TPSTW. The revised more stringent discharge standard also requires the upgrading of  

9.1.3        This EIA study has assessed the potential environmental impacts during the construction and operation of the Project. Key issues including odourair quality, water qualitywater quality, solid waste management, landfill gas hazards and noise impacts have been assessed.

9.2         Air Quality Impact

9.2.1        Air quality assessment for the construction and operation of the Project has been assessed.  With the implementation of mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation, dust nuisance at ASRs would not be is not expected.  An EM&A programme was recommended for the construction phase to ensure that the dust criteria would be satisfied at the ASRs.

9.2.2        Odour emission from the TPSTW would be the main concern during the operation phase.  Air dispersion modelling was conducted to simulate the potential odour impacts of the TPSTW on the ASRs.  It was recommended that the exposed area of inlet pumping stations, grit removal, weir area of Stage IV primary sedimentation tank, sludge digestion tank outlet chambers, sludge gravity thickeners and sludge consolidation tanks should be covered, with the foul air drawn through deodorization units and discharged after treatment.  The exposed area of grit removal, flume channel, weir launders at primary sedimentation tanks, exposed sewage area of return activated sludge pumping station, screening unit (next to dewatering house) and wet well of sludge pumping station should also be covered.  Addition of chemical in sewage at Tai Yuen Ssewage Ppumping Sstations No. 3 and 4 III and Tai Yuensewage pumping station IV to reduce odour impact arising from the Stage IV inlet pumping station, Stage IV screen house and Stage IV primary sedimentation tanks is required.  Good house keeping should also be conducted to minimise odour generation from the TPSTW.  With the proposed mitigation, the residual odour impacts at the ASRs were predicted to be in compliance with the odour criterion.  A field trial test is recommended to determine the chemical dosage at different sewage flows before the commissioning the Stage V of TPSTW.

9.3         Water Quality Impact

Construction Phase

9.3.1        Minor water quality impact would be associated with land-based construction, including demolition of existing facilities and installation of new works. Impacts may result from the surface runoff and sewage from on-site construction workers.  Impacts could be controlled to comply with the WPCO standards by implementing the recommended mitigation measures. Unacceptable residual impacts on water quality would not be expected.

 

Operation Phase

9.3.2        AAn assessment of water quality impact due to the operation of the Project was made using the Delft3D model.  With this quantitative modelling tool, impacts were assessed over a year’s duration.  Despite the model input parameters being conservative, comparison between the baseline and operational water quality modelling results indicated no adverse impact on the marine water quality in Victoria Harbour during normal operation of the TPSTW after commissioning of the Project.  To cope with the potential impact of effluent from TPSTW (and STSTW) into Tolo Harbour due to overflow discharges during normal operation of the TPSTW, upgrading of existing Tai Po and Sha Tin effluent pumping stations and the associated facilities is recommended, as described in detail in paragraph 4.7.25.  In passing, it is noted that for the 2010 scenario when Phase I of the Project is commissioned, overflow at TPSTW may occur only occasionally during storm events and the extent of impact is much less significant as compared to that of the 2016 ultimate flow scenario.  And under the Phase I works, mitigation measures, including dual power supply or ring main from CLP, standby equipments and treatment units would be provided to avoid the occurrence of any emergency discharge.  An EM&A programme is recommended to collect water quality data during emergency discharge or THEES tunnel maintenance to confirm the model predictions.

9.1         n assessment of water quality impact due to the operation of the Project was made using the Delft3D model.  With this quantitative modelling tool, impacts were assessed over a year.  Although the model input parameters were conservative, comparison between the baseline and operational water quality modelling results suggested that there should be no adverse impact on the marine water quality in Victoria Harbour during normal operation of the TPSTW after commissioning of the Project.  To cope with the potential impact of effluent from TPSTW (and STSTW) into Tolo Harbour due to overflow discharges during normal operation of the TPSTW, upgrading of existing Tai Po and Sha Tin effluent pumping stations and the associated facilities is recommended.  The need for the upgrading of the Tai Po effluent pumping station and Sha Tin effluent pumping station, has been identified in a previous consultancy study Review of North District and Tolo Harbour Sewerage Master Plan Studyconducted by EPD.  It is noted that the upgrading of Shatin effluent pumping station is currently in the Category C of the Public Works Programme (PWP), whilst the inclusion of upgrading of the Tai Po effluent pumping station into the PWP is being processing processed by the EPD.  Nevertheless, for 2010 scenario, overflow at TPSTW may occur only occasionally occur only during storm events and the extent of impact is considered minor.  Other mitigation measures, including dual power supply or ring main from CLP, standby equipments and treatment units would be provided to avoid the occurrence of any emergency discharge.  An EM&A programme is recommended to collect water quality data during emergency discharge or THEES tunnel maintenance to confirm the model predictions.  The monitoring results shall be employed to identify areas for any further necessary mitigation measures to avoid, rectify and eliminate environmental damage associated with the Project.

9.4         Waste Management Implications

9.4.1        Wastes generated by the construction activities are likely to include C&D material from the site formation and demolition works at the existing TPSTW site, general refuse from the workforce and used bentonite slurry. Provided that these identified waste arisings are to be handled, transported and disposed of using the recommended methods and that good site practices are to be strictly followed, adverse environmental impacts are not anticipated during the construction works.

9.4.2        Waste management will be the contractor’s responsibility to ensure that all wastes produced during the construction of the Project are handled, stored and disposed of in accordance with good waste management practices and EPD’s regulations and requirements. The recommended mitigation measures shall should form the basis of the site Waste Management Plan to be developed by the Contractor at the commencement of the construction phase. 

9.5         Landfill Gas Hazard

9.5.1        A landfill gas (LFG) hazard assessment has been undertaken to assess the potential hazard posed by the Shuen Wan Landfill to TPSTW which is located within the Consultation Zone of Shuen Wan Landfill.  The results suggest that the overall level of the landfill gas hazard is High.

9.5.2        Some appropriate protection measures have been proposed to minimise the landfill gas hazard for the proposed project site during the construction phase and operational phase. 

9.5.3                    Construction stage

·        Prior to and during development or construction, contractors would be advised of the possible presence of LFG in the subsurface for them to take into account in the design, construction and maintenance of their works. Procedures shall be established for pre-entry monitoring for ducts, manholes, and chambers. 

 

·        Portable gas detectors shall be used to regularly check the levels of methane, carbon dioxide and oxygen in depressions, trenches, and excavations area. The regular monitoring shall be undertaken at least for the beginning of each half working day (i.e. morning and afternoon) for the entire period the excavation remains open. If elevated LFG level is measured during monitoring at depressions, trenches and excavations, ventilation of such area shall be provided and sources of ignition shall be kept away from areas where build-up of LFG is possible.

 

Operational stage

 

·        Procedures shall also be established for pre-entry monitoring of ducts, manholes, and chambers. The atmosphere within utility manholes and chambers shall be checked for methane, carbon dioxide and oxygen prior to entry.  The frequency of routine monitoring is recommended to be monthly at least during the initial stage (first 3 months) of the operational phase of the project in order to make sure no accumulation of landfill gas. The frequency can be subsequently relaxed to a quarterly basis or eventually terminated with the approval of EPD based on available monitoring data for methane, carbon dioxide and oxygen.

9.5.4        Provided that the recommended protection measures (details in section 6 of the report) are implemented properly, the health and safety of the site workers/personnel working at the proposed project site will be safeguarded and there would be no adverse impact arisen from the proposed project.

 

 

9.6         Noise Impact

9.6.1        Construction noise impacts and the operation noise impacts arising from the Project have been identified as key environmental issues. The potential noise impacts arising from the Project have been assessed and evaluated.

 

Construction Phase

9.6.2        For the construction phase, the unmitigated noise levels at the identified NSR in Tai Po Sewage Treatment Plant would be in the range of 67 dB(A) to 82 dB(A).  To alleviate the noise impact, sufficient nNoise control measures would be required to mitigate the potential construction noise impacts. The rRecommended mitigation measures include the use of silenced types PMEs and implementation of good site practices.

9.6.3        With the recommended control measures in place, the mitigated noise levels at the identified NSR due to the Tai Po STW would comply with the daytime construction noise standard as set out in the EIAO-TM. In addition, an EM&A programme would be implemented to monitor the construction noise impact.

 

Operation Phase

9.6.4        The noise impacts associated with the operation of the Project were also assessed. According to the assessment result, the predicted unmitigated noise levels would comply with the daytime and night-time noise criteria. Thus, no mitigation measure would be required.