Kowloon Canton Railway Corporation
KSL GSA 5100 Environmental Impact Assessment
& Associated Services
Environmental Impact Assessment Report
Ove Arup & Partners Hong Kong Ltd
Level 5, Festival Walk, 80
Tat Chee Avenue, Kowloon Tong, Kowloon, Hong Kong
Tel +852 2528 3031 Fax
+852 2268
2. Selection Of The PreFerRed Alignment
3. Construction
Methodologies for the Selected Route Alignment
4. Construction
Dust Impact Assessment
5. Airborne
Noise Impact Assessment
5.2 Operational
Airborne Noise
6. Groundborne
Noise Impact Assessment
6.1 Construction
Groundborne Noise
6.2 Operational
Groundborne Noise
7. Water
Quality Impact Assessment
8. Waste
Management IMPLICATIONS
9. Land
Contamination ASSESSMENT
11. Landscape
and Visual Impact Assessment
11.1 Construction
Phase Landscape and Visual Impacts
11.2 Operation
Phase Landscape and Visual Impacts
12. Cultural
Heritage Assessment
13. Environmental
Monitoring and Auditing Requirements
Figures
General Alignment |
|
|
|
KSL Route Corridor Canton Road Scheme (2 of 3) |
|
KSL Route Corridor Canton Road Scheme (3 of 3) |
|
|
|
KSL Route Corridor Kowloon Park Drive Scheme (2 of 3) |
|
KSL Route Corridor Kowloon Park Drive Scheme (3 of 3) |
|
|
|
KSL Route Corridor Kowloon Point Scheme (1 of 3) |
|
KSL Route Corridor Kowloon Point Scheme (2 of 3) |
|
KSL Route Corridor Kowloon Point Scheme (3 of 3) |
|
|
|
KSL Route Corridor Harbour City Scheme (1 of 3) |
|
KSL Route Corridor Harbour City Scheme (2 of 3) |
|
KSL Route Corridor Harbour City Scheme (3 of 3) |
|
|
|
Construction Methodology & Construction Area Plan (1 of 3) |
|
Construction Methodology & Construction Area Plan (2 of 3) |
|
Construction Methodology & Construction Area Plan (3 of 3) |
|
|
|
Recommended Watering Frequency |
|
|
|
Recommended Construction Noise Mitigation Measures |
|
|
|
Location of Excavated Marine Deposits Tested for Biological
Screening |
|
|
|
Location of Drillhole for Soil Contamination |
|
|
|
Photomontages of Project 10 Years after Landscape and Visual
Mitigation Measures Implemented |
|
Photomontages of Project 10 Years after Landscape and Visual
Mitigation Measures Implemented |
Ove Arup & Partners
(Arup) was commissioned by Kowloon Canton Railway Corporation (KCRC) to undertake an
Environmental Impact Assessment (EIA) of the proposed
Kowloon Southern Link (KSL) in
accordance with the requirements of the Technical Memorandum on Environmental
Impact Assessment Process (TM-EIA) and the study brief (Ref No.
ESB-097/2002). The scopes of the EIA
study include the impact assessments of construction dust, airborne noise,
groundborne noise, water quality, waste management, land contamination, landscape
and visual, cultural heritage, and hazard.
The selection of railway alignment, construction methodologies,
requirements of EM&A, and environmental outcomes of the Project have also
been detailed in the EIA report.
The proposed
underground KSL will improve the accessibility to Tsim Sha Tsui (TST) and West
Kowloon districts (Figure 1-1).
It connects the new KCRC East TST Station to the current West Rail (WR)
Nam Cheong Station (NAC), with its alignment running under Salisbury Road,
Canton Road and West Kowloon Reclamation area.
The total length of the new railway is approximately 3.7km. West Kowloon Station (WKN) will be located
at West Kowloon on the west side of Canton Road between Austin Road and Jordan
Road. Neither reclamation nor dredging
is anticipated for KSL.
Mechanical services
plant will be located within the WKN and at two ventilation / plant buildings
along the route alignment including:
·
Yau Ma Tei (YMT)
Ventilation Building at Hoi Ting Road, and between YMT
Interchange and Cherry Street; and
·
Canton Road Plant
Building (CRPB) at the junction of Kowloon Park Drive and Canton Road;
The construction work will commence in
early 2005 and is scheduled to be completed by late 2007. Testing and commissioning of the railway
system will then be conducted for target completion for operation in late 2008
/ early 2009.
2.
Selection Of The PreFerRed Alignment
The alignment is
divided into two main sections, north and south, basically following the alignment
proposed in the Railway Development Strategy 2000 (RDS-2000) Report.
The alignment in this northern section runs in the narrow corridor
between the existing Airport Express Line, West Kowloon Expressway and various
planned developments in the vicinity.
All these constraints prohibit any alternative corridors or even very
minor deviations to the alignment proposed in the RDS-2000 Report. The original
southern portion of the RDS-2000 alignment assumed the implementation of the
Kowloon Point Reclamation and the location of the Kowloon Point Station on the
reclaimed land. However, as the Kowloon
Point Reclamation will not be implemented, it is impossible to adopt the
original RDS-2000 alignment. Four alternative alignments have therefore been identified,
including two inland (namely Canton Road Scheme and Kowloon Park Drive Scheme)
and two seaward options (namely Kowloon Point Scheme and Harbour City
Scheme). Figures 2-1-1 to 2-4-3
indicate the routes for the four alignment options.
The four alignment
options were evaluated on the basis of the critical engineering, environmental
and social factors in the EIA study. A
summary of the reasoning that has been considered during the route selection
process is given below:
Table 2-1 : Summary of reasoning for route alignment
selection
|
Route
Alignment Options |
|||
Criteria |
#1: Canton
Road Scheme |
#2:
Kowloon Park Drive Scheme |
#3:
Kowloon Point Scheme |
#4:
Harbour City Scheme |
Engineering Factors |
|
|
|
|
Resumption of Buildings |
· Resumption of
private buildings not required |
· Resumption of
YMCA Building (Not feasible) · Resumption of
Fuk Tak Koo Temple |
· Not required |
· Resumption of
Star House & Marco Polo HK Hotel (Not feasible) |
Accessibility
& Connectivity |
·
Less attractive with CAR deferred ·
Good with CAR in place |
· Good |
·
Not desirable ·
No connection to Kowloon Point Station |
·
Not desirable |
Reclamation |
·
Not required |
· Not
required |
· Required (reclamation will not be implemented since it is inconsistent with the
Protection of Harbour Ordinance) |
· Not required |
Environmental Factors |
|
|
|
|
Landscape resources |
· Less impact · No
impacts on champion trees[1] |
· Higher impact · Champion trees
may be affected |
·
Less impact ·
No impacts on champion trees |
· Less impact · No
impacts on champion trees |
Construction noise & dust |
· Minimal
impact, use of bored tunnelling along Canton Road will minimize the construction
noise and dust impacts, and other disruptions to the commercial premises. |
· High impact if
cut-&-cover needs to be adopted · Similar impacts as Canton
Road Scheme if bored tunnelling is adopted |
· Minimal impact (but
acceptable with mitigation measures) |
· Minimal impact
(but acceptable with mitigation measures) |
Visual impacts |
· Minimal
impact, use of bored tunnelling along Canton Road will minimize the visual. |
· High impact if
cut-&-cover needs to be adopted · Similar impacts as Canton
Road Scheme if bored tunnelling is adopted |
· Construction
vessels will affect the attractiveness and visual appeal of the harbour |
· Construction
vessels will affect the attractiveness and visual appeal of the harbour |
Heritage Buildings |
· FMPHQ
and Old Fire
Station Building (OFSB) protected by
no contact construction methodology |
· No impact |
· No impact |
· No impact |
Waste generation |
· No polluted
sediment generation · Use of
bored tunnelling can minimize the amount of excavated materials |
· More
excavated materials |
· Potential
release of polluted marine sediment |
· Potential
release of polluted marine sediment |
Groundborne Noise & Vibration |
· Operational
noise
& vibration can be mitigated · Train service
& passenger comfort not compromised |
· Unacceptable impact on the
line capacity due to tight curvature of the track near the junction between
Salisbury Road and Kowloon Park Drive; · More severe operational noise and vibration
problems · Train services
& passenger comfort compromised |
· Operational noise &
vibration can be mitigated · Train service
& passenger comfort not compromised |
· Operational noise &
vibration can be mitigated · Train service
& passenger comfort not compromised |
Impacts on parks |
· No impact on Kowloon
Park · Encroach onto a
relatively small open space at junction of Canton Road and Kowloon Park Drive |
· Higher impact · Temporary
possession of KPDCP · Encroachment
into Kowloon Park |
· No impact on
KPDCP & Kowloon Park |
· No impact on
KPDCP & Kowloon Park |
Ecology
& Water Quality |
· No ecological impact · No water quality impact |
· No ecological impact · No water quality impact |
· No terrestrial
ecological impact · Dredging will
affect water
quality |
· No terrestrial
ecological impact · Dredging will
affect water
quality |
Other Factors |
|
|
|
|
Disruption to harbour activities |
· No impact |
· No impact |
· Affect harbour
activities · Affect Star
Ferry |
· Affect harbour
activities |
Commercial & Cultural Activities |
·
Disruptions to commercial premises along Canton
Road will be minimized by using bored tunnelling |
·
Several hotels affected ·
Alignment furthest away from Hong Kong Cultural
Centre (HKCC) ·
Ex-Museum of History would be affected |
·
Several hotels affected but alignment closer to
the HKCC |
·
Several hotels affected but alignment closer to
the HKCC |
It is identified that
both Kowloon Point Scheme and Harbour City Scheme are not viable given the current
engineering constraints with regard to building resumption, disruption to ferry
operation, requirements of harbour protection, and the likelihood that Kowloon
Point Reclamation will not proceed in the near future. On the other hand, the Kowloon Park Drive
Scheme has severe drawbacks of YMCA resumption, unacceptable railway alignment
and operations due to tight curvature of the track, disruption of Champion
trees, and encroachment into Kowloon Park and Kowloon Park Drive Children
Playground.
Latest engineering
design of the Canton Road Scheme has confirmed the feasibility of adopting
bored tunnelling along Canton Road without the need for resumption of private
buildings. A summary of the
environmental benefits of the Canton Road Scheme is given below:
·
As most of the
construction activities for the tunnels along Canton Road would be conducted
underground, impacts from construction noise, fugitive dust, visual and
disruption to the retail outlets along Canton Road would be minimised during
the construction phase.
·
The use of bored
tunnelling along Canton Road will minimise the generation of spoil for this
section of tunnels.
·
The Canton Road
Scheme does not require any reclamation and dredging works which would inevitably
affect the marine water quality and ecology.
·
The construction
works for the Canton Road Scheme would not encroach onto Kowloon Park. All Champion Trees along Haiphong Road would
therefore kept intact during the construction phase.
·
The current construction
method along Salisbury Road will ensure that the Old Fire Station Building
(OFSB), a building with heritage value, in the FMPHQ site will be kept intact
during the entire construction period.
Temporary dismantle is not required.
Canton Road Scheme is
therefore considered to be the preferred option.
3.
Construction
Methodologies for the
Selected Route Alignment
A
number of construction methodologies have been considered for tunnelling during
the design process, including cut-&-cover tunnelling, bored tunnelling, and
mined tunnelling. The environmental benefits and disbenefits of the
construction methodologies have been addressed in the EIA report. The key construction elements along the
alignment is summarised in the table below (Figures 3-1-1 to 3-1-3).
Table 3.1 – Summary of key construction elements
Tunnel Section |
Construction method |
Reasons |
Tunnels under Salisbury Road |
Cut & cover |
·
Bored tunnelling is
impracticable due to insufficient soil cover to achieve the arching effect for
safe operation and space constraint imposed by the presence of existing MTR
tunnels, the New World Subway near Nathan Road, and the East Rail Extension. |
Underground tunnel beneath the existing FMPHQ site and
OFSB. |
Mined
Tunnelling |
·
Bored tunnelling is not
preferred due to relatively small radius curve and the high risk of tunnel
collapse due to minimal separation between tunnels. ·
Mined tunnelling (drill
& blast) is adopted. A clear separation of 6m between the tunnels and the
OFSB, and 16m from the Main Building will be maintained. |
Tunnel between Canton Road & WKN (with an Emergency
Egress Point at the south of Canton Road) |
Bored tunnelling |
·
Bored tunnelling is
preferred as most of the construction activities will be conducted
underground (except for ground treatment and construction of shafts), the
associated construction noise and dust impacts will be much less than the cut
& cover option. Disruption to the
retail outlets along Canton Road will be minimized. |
WKN, station entrances & associated facilities |
Cut & cover |
·
Construction of station
concourse, entrances, back-of-house areas would require cut-&-cover
approach regardless of the tunnelling method. Use of bored tunnelling in this section would therefore have no
environmental benefits. |
Tunnel from WKN to Cherry Street. |
Cut & cover |
·
Bored tunnelling is not
practicable due to the width constraints to tunnelling imposed by YMT Highway
Interchange foundations. ·
If bored tunnelling is used
for south of Cherry Street, the most appropriate location for the TBM
retrieval shafts would be in the YMT Ventilation Building site. The presence of pocket track and box
culverts to the north of WKN also supports the cut-&-cover method. The length of bored tunnelling for the
remaining tunnel section will only be as short as about 500m and its benefit
is limited to a few numbers of sensitive receivers in this area. ·
Use of cut-&-cover
would have a programme advantage of about 9 months over bored
tunnelling. Bored tunnel is therefore
not adopted. |
Tunnel underneath Cherry Street |
Cut & cover |
·
Bored tunnelling is not
practical due to the width constraints to tunnelling imposed by the foundations
of the adjacent Olympic Station and Olympic City II. |
Underground tunnel between Cherry Street and WR Nam
Cheong Station |
Cut & cover |
·
Bored tunnelling is not
practicable for the WR interface section because of insufficient soil cover
and the relatively high gradient. |
4.
Construction Dust Impact
Assessment
Construction dust will
be potentially generated from soil excavation activities, backfilling, wind
erosion of all open sites, storage of spoil on site,;
transportation / handling of spoil, underground blasting activities, as well as
loading and unloading of excavated materials at barging facility and
stockpiles.
Temporary decks will
be installed along Salisbury Road, mucking out locations along Canton Road, and
the WKN northern tunnel section between Lin Cheung Road and Lai Cheung Road to
maintain traffic flow during construction, and reduce the dust dispersion to
the vicinity of the site. For the mined
and bored tunnel sections, as most of the works will be performed underground,
dust will only be generated during excavation and reinstatement of the access
shafts.
Dust impact assessments have been carried out in accordance
with TM-EIA, on the basis of the USEPA AP-42 dust emission factor. Results indicate that the predicted 1-hour and
24-hour averaged TSP concentrations
at some sensitive receivers will exceed the TM-EIA requirements of 500µg/m3
during the construction of KSL under the “unmitigated” scenario. However, with proper watering throughout the
construction phase (at least four times a day for WKN and at least twice a day for
the other sections, as indicated in Figure 4-1), dust
impact could be effectively mitigated to within the TM-EIA requirement at all
ASRs. There would be no adverse
dust impact caused by construction of KSL.
The cumulative impacts caused by the concurrent projects have been
addressed in the EIA based on the latest available information. It
has been concluded that there will be no adverse cumulative dust impact during the period of
concurrent construction for the projects.
Appropriate dust
suppression measures have been also recommended in the EIA report. By implementing appropriate control measures and good construction site practice, no residual dust impacts are anticipated. The Contractor should follow the procedures
and requirements (key mitigation measures include proper watering, vehicle
washing facilities, covering temporary stockpiles by impervious sheeting etc)
given in the Air Pollution Control (Construction Dust) Regulation, and also
implement an environmental audit and monitoring programme during the
construction phase to ensure that the construction dust impacts are controlled to within the Hong Kong Air Quality
Objectives (HKAQO).
5.
Airborne Noise
Impact Assessment
Potential impacts on Noise Sensitive Receivers (NSRs)
during the construction phase will arise mainly from Powered Mechanical
Equipment (PME) to be operated. The
major construction works would include site clearance and formation activities,
building/ structure demolition, station construction, tunnel construction,
installation of diaphragm walls or pipe pile walls, underpinning subway, piers
and footbridge, diversion of box culverts, spoils removal from underground
works & stockpiling, backfilling and reinstatement works, and barging activities. For
cut-&-cover sections along Salisbury Road, mucking out locations along
Canton Road, and WKN northern tunnel section between Lin Cheung Road and Lai
Cheung Road where temporary decking will be installed for traffic management, most of excavation works and tunnel
construction will be undertaken under the decks to minimise the noise impacts
during construction.
Assessment results indicate that adverse
construction noise impacts are predicted at most of the NSRs under
“unmitigated” scenario. Suitable noise
mitigation measures are therefore proposed in the EIA study to minimise the
construction noise impact. These
include:
·
Good site
practices such as orientating the noisy plants away from the nearby NSRs,
intermittent uses of plants, proper fitting of silencers and mufflers on the
construction equipment, etc;
·
Use of site
hoarding as noise barrier to screen noise at low level of NSRs;
·
Use of movable
barriers, enclosures and acoustic mat to screen noise from generally static
noisy plants such as air compressor, generators, handheld breakers, pipe pile
rigs, circular saw, drill hole machine, and grout pump, etc;
·
Scheduling of
construction works outside school examination periods in critical area; and
·
Use of quiet plant
and working methods.
With the implementation of the above recommended mitigation measures, the predicted construction
noise level could be reduced by up to 10dB(A).
However, the construction noise levels at Canton Road Government School,
Lai Chack Middle School, Man King Building, Man Fai Building, Olympian City
Phase 3 development will still exceed the criteria. Other specific mitigation measures including temporary noise
barrier for particular PME and sequencing of construction activities have been
considered.
All practicable noise mitigation measures have
been used exhaustively in order to reduce the impacts to the maximum
practicable extent (Figure 5-1).
Nonetheless, there are still 3 sensitive receivers that will be subject
to minor and short-term residual impacts. Table 5-1 summarises the
durations and magnitude of residual impacts at the affected NSRs.
Table 5-1 : Residual
construction noise impacts
Description |
Noise Impacts, dB(A) |
Duration in different noise band (Month)[1] |
||||
Criterion |
Max
Impacts |
Exceedance |
71 – 75 dB(A)[2] |
76 – 79 dB(A) |
80 – 84 dB(A) |
|
Canton Road Government School |
70 |
74 |
4 |
2 |
0 |
0 |
Lai Chack Middle School |
70 |
74 |
4 |
2 |
0 |
0 |
Man King Building |
75 |
77 |
2 |
N/A |
4 |
0 |
Since all the practicable direct noise
mitigation measures have been exhausted, indirect technical remedies (ITR) in
the form of upgraded windows and provision of air-conditioning have been considered by the Project Proponent as the last resort for mitigating
residual construction noise impacts. Results indicate that none of the above NSRs would
be qualified for ITR, given the following eligibility criteria:
·
A residual impact
of 5dB(A) or more; and
·
A duration of
noise exceedance of equal or more than 1 month.
Cumulative construction noise impacts caused by
the concurrent projects have been assessed, based on the latest
information. The cumulative impacts due
to the concurrent projects are generally not significant. Hence, no additional mitigation measures are
required under KSL project.
Since bored tunnelling will be carried out along
Canton Road, the launching shaft at the south of WKN would need to operate for 24 hours. In order to
meet the stipulated criteria, it is recommended to install a noise insulating
cover at the launching shaft. This
cover shall be shut during night-time to shelter the construction plant items
inside.
5.2
Operational Airborne Noise
The majority of the
tracks for this project will be underground except for a 150m section interfacing with WR
Nam Cheong Station. This short section is provided within a
concrete tunnel
box, and hence adverse operational
train noise impacts are not anticipated.
However, operational noise will emanate from the tunnel ventilation
fans, transformers,
pumps, ventilation shaft, and fresh
water cooling facilities. The EIA study
has established the maximum allowable Sound Power Levels (SWL) for all
above-grade louvres and ventilation plants, with regard to the separation distances
and orientation from the nearest NSRs, cumulative noise impacts from other
noise sources, as well as tonality, impulsiveness, and intermittency based on
the relevant Technical Memorandum.
These predicted maximum allowable SWLs should be implemented during the
design development in order to meet the relevant legislative requirements.
In addition, the
detailed design should also incorporate the following good practice in order to
minimise the operational noise nuisance on the neighbouring NSRs:
·
Louvres should be
orientated away from adjacent NSRs;
·
Adequate direct
noise mitigation measures including silencers, acoustic louvers, acoustic
enclosures should be adopted.
·
The facade for
these plant areas / ventilation shafts should have adequate sound insulation
properties.
With proper
implementation of the above noise control measures, adverse operational noise
impacts are not anticipated.
6.
Groundborne Noise
Impact Assessment
6.1
Construction
Groundborne Noise
Potential construction groundborne noise impacts would arise
mainly from rock breaking activities, tunnel boring etc. Other construction activities such as lorry
movement, concreting, road paving etc are unlikely to generate significant
groundborne noise. The noise impacts on
neighbouring sensitive receivers (including Hong Kong Cultural Centre, Hong
Kong Space Museum, hotels,
residential premises and schools) have been quantified. Results indicate that the predicted impacts
are within the statutory requirements and hence mitigation measures are not
required. There are no residual
construction groundborne noise impacts on the NSRs.
6.2
Operational Groundborne
Noise
7.
Water Quality
Impact Assessment
There will be no
dredging activities or marine work platform construction for the project. Potential water pollution sources during construction
phase will include sources mainly from land activities, including construction
runoff, runoff from tunnelling activities and underground works, sewage
effluent due to workforce, drainage diversion, and groundwater from potential
decontamination activities.
The Contractor is
required to implement good site practices as stipulated in ProPECC Note 5/93
“Drainage Plan subject to Comment by the Environmental Protection Department”,
ProPECC Note 1/94 “Construction Site Drainage'” and “Recommended Pollution
Control Clauses for Construction Contracts” in order to control the
construction site discharges.
The groundwater
analytical results for samples at WKN and the tunnel to the north indicate
occasionally elevated concentrations of metals including copper, lead and
mercury. Such results are not
considered unusual for groundwater in urban areas, where there are numerous
potential diffuse sources of contamination.
However, none of the samples exceed the calculated Risk Based Screening
Level, and therefore remedial action is not considered necessary for
groundwater. However, the pollution
levels have exceeded the respective discharge limits. Hence, all the groundwater during the dewatering process for the
excavation of WKN and the tunnels to the north of WKN should be recharged
within the site areas.
During the operational
phase of the project, potential water pollution sources are identified as the
run-off from rail track, station runoff, discharge from fresh water cooling
facility, and sewage from station operation.
Run-off from rail track could be contaminated with limited amount of
grease. Standard silt trap and oil
interceptor will be provided to remove the oil, lubricants etc from the waste
water before discharging into the stormwater drainage. The flow from the fresh water cooling
facility will be discharged to the flushing system and then enter the sewerage
system as flushing water. Since station
runoff is not contaminated and sewage generated from station will be connected
to sewer system, no residual water quality impact is anticipated.
8.
Waste Management
IMPLICATIONS
The EIA study has
assessed the potential environmental impacts associated with the handling and
disposal of waste arising from the construction
works. It is estimated that about
1,218,800m3 of construction and demolition (C&D)
materials will be excavated and the
maximum annual generation of excavated material would be about 638,300m3
during Year 2005.
Several temporary
stockpile locations have been identified to maximise the opportunity of reusing
excavated fill material for backfilling and reinstatement works. It is
estimated that approximately 331,100m3 of the inert C&D
materials could be reused and the remaining 887,700m3 would need to
be disposed of. The C&D materials
to be disposed of will be transported by lorries to the barging facility in
West Kowloon Cultural Development (WKCD) site for final disposal at approved
Public filling area. The peak
hourly flow of lorries carrying C&D materials to the barging facilities for
the entire KSL would be approximately 43 veh/hr. The disposal
programme of surplus C&D materials is given in the EIA report.
Besides, it is
estimated that about 94,900m3 marine deposits and alluvium will be
generated during the construction of KSL.
A Sediment Quality Report was prepared and approved in Year 2003 as per
the requirements given in the Work Bureau Technical Circular (WBTC) 34/2002
“Management of Dredged / Excavated Sediment”.
A few of the samples (Figure 8-1) have failed the biological
screening and these marine deposits should be therefore disposed of at Type 2
confined marine disposal site. The rest
of the marine deposit along the proposed alignment should be assigned for Type
1 open sea disposal.
The Contractor will be requested
to prepare a Waste Management Plan to summarise their specific proposal for
minimising waste generation, on-site sorting, recycling inert C&D
materials, handling of chemical waste etc.
During the operational phase, the station and the associated facilities
will generate general refuse, industrial waste and chemical waste. It is anticipated that waste generated by
the WKN alone would be approximately 500kg/day. A reputable waste collector should be employed to remove general
refuse and industrial wastes from the stations on a daily basis to minimise
odour, pest and litter impacts. The
requirements given in the Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes should be followed in the handling of chemical
wastes. A trip-ticket system should be
operated to monitor all movements of chemical wastes, which will be collected
by a licensed collector to licensed facility for final treatment and
disposal. With the implementation of
recommended mitigation measures, residual impacts are not anticipated for both
the construction and operational phases.
9.
Land Contamination ASSESSMENT
The relevant
historical information has been reviewed for the land contamination assessment
in the EIA study. Site inspection has also
been carried out to obtain more information regarding the current industrial
activities and to select the sampling locations for contamination assessment.
The potential land contamination areas are identified as below:
·
Diesel and petrol
contamination from the two underground oil storage tanks inside TST
Fire Station, which is at approximately 60m to the west of the alignment;
·
Contamination from
the ex-dockyard site at West Kowloon Reclamation between the Canton Road
Government Offices and TST Fire Station;
·
Residual marine
deposits contamination from the ex-government maintenance workshop located at
the waterfront of the Canton Road Government Office;
·
Contaminated
marine deposits from the West Kowloon Reclamation Area;
·
Diesel
contamination from the two underground tanks for petrol filling station located
at Skyway House which is at approximately 50m from the alignment;
·
Contamination from
past industrial activities next to Skyway House; and
·
Contaminated
marine deposits from ex-shipyard operation near Tung Chow Street Park.
Five drillholes were
selected for soil and groundwater analysis and a total of 33 soil samples have
been collected. Results indicate that a
small quantity of 39m3 of soil (1.0 - 2.0m below ground level) has
been contaminated by Lead at one of the drillholes (Figure 9-1). Different remediation options including
excavation and landfill disposal, solidification and stabilisation,
soil-washing, and physical separation have been investigated with respect to
their associated advantages and disadvantages.
Landfill disposal has been recommended as a last resort, and the
contaminated soil has been tested to be acceptable for landfill disposal in
accordance with the Toxicity Characteristic Leaching Procedure (TCLP)
testing. Specification for the remedial
works covering the disposal methodology, requirements for compliance testing,
and the need for protective and safety measures has been also prepared in the
EIA report.
According to the latest
design information, there will not be overnight storage of explosive and hence
there is no potential hazard impact.
11.
Landscape and
Visual Impact Assessment
All landscape resources and landscape character areas in the vicinity of the alignment have been identified, including the Champion trees in the Kowloon Park Drive Children’s Playground (KPDCP) and along Haiphong Road. All the visually sensitive receivers within the visual envelopes during the construction and operational phases have been identified and their impacts have been evaluated. All these Champion trees will be kept intact during both the construction and operational phases of the KSL.
The minimising of potential landscape and visual impacts has been a very important factor in the development of the project design. During project design development, the physical extent of the works have been reduced as far as possible so as to minimise impacts on existing trees and open spaces, and to minimise the degree of visual impact. A comprehensive package of landscape and visual mitigation measures has been recommended. Figures 11-1 and 11-2 indicate the indicative appearance after 10 years of the WKN, CRPB and YMT Ventilation Building.
11.1
Construction Phase
Landscape and Visual Impacts
This assessment is based on the following assessment of quantified landscape impacts:
·
The temporary loss of public open space during the construction phase
will not exceed 15,000sq.m.;
·
The Project Proponent shall review the
site works in order to maxmize the preservation of the trees of good amenity
value in situ. The maximum number of
existing trees affected (not counting any new trees planted after the date of
this report) will not exceed 1,200 of which not more than 105 will be of high
amenity value;
· There will be no impacts on Champion Trees;
· There will be no impacts on any trees in the site of the FMPHQ site;
· The project proponent shall maximize the transplantation of trees of high amenity value if preservation in situ is not feasible. A minimum of 80% of the affected trees of high amenity value shall be transplanted.
· The number of compensatory trees planted as part of the mitigation measures shall be at least 130% of the total number of affected trees. The compensatory tree planting shall be at least heavy standard size, unless planting is on a slope, in which case tree size will be the largest practical size given technical restrictions due to slope angle. Semi-mature trees shall be used at sensitive and prominent locations e.g. Salisbury Garden.
After implementation of the mitigation measures (including the use of clean and tidy hoardings, minimise soil erosion, transplanting of trees etc), there will still be some landscape and visual impacts caused by cut-&-cover construction techniques and the associated temporary noise barriers and temporary traffic arrangements, which are unavoidable for an essentially subterranean project in an urbanised district.
The most significant construction phase
residual landscape and visual impacts would be of substantial significance for
the temporary working areas at Nam Cheong Park, Salisbury Road, Canton Road
(Southern section), forecourt at Olympian City 2 development, and the Public
Open Space at Corner of Canton Road and Kowloon Park Drive. These impacts,
although significant, are relatively temporary in nature.
11.2
Operation Phase
Landscape and Visual Impacts
Landscape and visual impacts in the operational phase would potentially be caused by the residual impacts of trees lost during the construction phase, and by the permanent built structures including the YMT Ventilation Building, CRPB, WKN, and Emergency Egress Point.
However, with the implementation of the proposed mitigation measures and after 10 years growth of compensatory tree planting, the residual landscape and visual impacts in the operational phase would be insubstantial, with the exception of the impact on the Public Open Space at the corner of Canton Road and Kowloon Park Drive (LR54), which will be subject to an adverse impact of moderate significance due to the permanent loss of approximately 300sq.m. of public open space due to the proposed CRPB.
This assessment is based on the following assessment of quantified landscape impacts and mitigation measures:
· The permanent loss of public open space in the operation phase will not exceed 500sq.m.;
· The permanent loss of this public open space will be partially mitigated by the provision of an attractive public streetscape area in front of the WKN building (at least 400sq.m.), with shade tree planting; and
· There will be no further tree impacts in addition to those affected during the construction phase.
With reference to the five criteria
defined in Annex 10 of the EIAO TM, it is considered that the landscape and
visual impacts in the construction and operation phases are acceptable with mitigation measures.
12.
Cultural Heritage
Assessment
The works area is located
in a highly urbanized district that has undergone extensive underground
disturbance from construction of roads, buildings and the installation of
underground utilities over the past century. The likelihood that any
undisturbed landforms still exist is extremely low and hence, the
archaeological potential of these areas is also extremely low. Before commencement
of the construction work, the Contractor shall consult Antiquities and
Monuments Office (AMO) on any other mitigation measures that would be required
administratively or under the Antiquities and Monuments Ordinance. The Contractor shall implement these
requirements from AMO during the construction period.
The only resources
that will require mitigation measures are the buildings that are part of the
FMPHQ (a Declared Monument) and the OFSB Accommodation Block (a Grade II
Building), and the Old Fire Station Main Hall (a Grade III building).
The OFSB on Salisbury
Road will be impacted by the tunnelling work.
However, use of mined tunnelling can avoid physical contact with these heritage
buildings. Structural monitoring will
also be conducted throughout the construction of the tunnel underneath the
FMPHQ compound, including the former headquarters building and a small
outbuilding at its rear, the former stables, the former signal tower and the
air-raid tunnel section to be preserved to ensure compliance with the Building
Ordinance requirements. The Contractor should also monitor the structural
integrity of the two OFSB on site and carry out necessary remedial actions in
order to protect these buildings. Liaison
with the FMPHQ developer has indicated that they will conduct the condition and
impact monitoring during the construction period that overlaps with the KSL
construction. After this period, they will allow access to the site by the KSL
Contractor to carry out the necessary monitoring.
13.
Environmental
Monitoring and Auditing Requirements
It is recommended to implement an Environmental
Monitoring and Audit (EM&A) programme throughout the entire
construction period to regularly monitor the environmental impacts on the
neighbouring sensitive receivers. The EM&A manual will be prepared as a standalone
document to specify the monitoring requirements, time frame and responsibilities
for the implementation of the environmental mitigation measures identified in the EIA process.
For construction noise, in particular, the Contractor will be requested to implement and operate a continuous noise monitoring mechanism throughout the
entire construction period of the Project.
In cases where exceedances are found, immediate actions should be taken
to implement
remediation measures following the
procedures specified in the EM&A Manual.
KCRC will also establish a
Community Liaison Office with a telephone action line which enables the public
to raise any matters of concern regarding the project such as complaints,
comments, suggestions or requests for information.
The proposed 3.7km
long underground KSL is constructed to improve the accessibility to Tsim Sha
Tsui and West Kowloon districts, connecting the new KCRC East TST Station to
the West Rail Nam Cheong Station, with its alignment running under Salisbury
Road, Canton Road and West Kowloon Reclamation area. It is estimated that a total population of about 763,700 planned
by Year 2011 for Sham Shui Po district and Yau Tsim Mong district will be
directly benefited by the operation of KSL.
A more environmental
friendly construction methodology, bored tunnelling, will be adopted along
Canton Road in order to minimise environmental impacts and disturbance to
hotels, commercial premises, and residential buildings along both sides of the
road. Whilst cut-&-cover
activities are still required for the retrieval shaft and the associated
ventilation buildings, temporary decking will be installed to avoid traffic
disruption and minimise construction noise and dust impacts.
An EIA has been
undertaken in accordance with the requirements of the TM-EIAO and the Study
Brief (Ref No. ESB-097/2002). The
scopes of the EIA study include the impact assessment of construction dust,
airborne noise, groundborne noise, water quality, waste management, land
contamination, landscape and visual, cultural heritage, and hazard. A list of mitigation measures has been
recommended to protect the potential sensitive receivers to the maximum
practicable extent. Residual
environmental impacts are not anticipated except for
temporary construction noise
impacts at some of the noise sensitive receivers,
landscape and visual impacts during construction stage. However, the loss of roadside trees, the
landscape and visual impacts caused by the ventilation buildings and WKN will
be of insubstantial significance after implementing
the recommended mitigation measures and the proposed tree planting becomes mature in the future.
[1] Champion Trees are trees listed in the Urban Council publication “Champion Trees in Hong Kong” (Chinese Edition, 1998) by Dr C Y Jim.