6                                            LANDSCAPE AND VISUAL Impact Assessment

6.1                                      Introduction

This section presents the findings of the landscape and visual impact assessment (LVIA) for the proposed wind turbine at Tai Ling in Lamma Island (hereafter described as “The Project”) and outlines the potential impacts to the existing landscape and visual context of the area together with the mitigation measures proposed to alleviate those impacts.

6.2                                      Relevant Legislation and Guidelines

 

The methodology of the LVIA is based on Annexes 10 and 18 in the Hong Kong SAR Government's Technical Memorandum on the Environmental Impact Assessment Process (EIAO-TM) under the EIA Ordinance (Cap.499, S16), entitled "Criteria for Evaluating Visual and Landscape Impact" and "Guidelines for Landscape and Visual Impact Assessment", respectively and the EIAO Guidance Note No. 8/2002 “Preparation of Landscape and Visual Impact Assessment Under the Environmental Impact Assessment Ordinance.”

 

In addition, The Hong Kong Planning Standards and Guidelines (HKPSG) Chapter 10 – Landscape and Conservation outlines relevant design criteria that should be considered in this project.

6.3                                      Assessment Methodology

In accordance with the EIAO Guidance Note No.8/2002, the main components of the LVIA will be as follows:

 

·                     description of the Project;

·                     baseline study of landscape and visual resources;

·                     review of planning and development control framework;

·                     landscape impact assessment during construction and operation;

·                     visual impact assessment during construction and operation;

·                     recommendations for landscape and visual mitigation measures for both construction and operation stage; and

·                     assessment of residual impact and conclusion on the acceptability of the Project.

 

The baseline study is examined in Section 6.4 of this report.  It identifies and examines the existing landscape and visual resources within the study area. The baseline study describes the landscape resources by identifying broadly landscape character areas (LCAs) and key landscape elements within the study area (refer to Figure 6.1). The landscape character was rated low, medium or high depending not only on the quality of elements present but also to its sensitivity to change and its importance at a local, district, regional or international level.

 

Visual resources considered were key viewpoints, location and direction of views towards the project. A visual envelope (refer to Figures 6.2 and 6.3) was established which approximately defined the extent of visual influence of the project and, therefore, of the potential visual impacts.  Definition of the extent of the viewshed was based on desktop study and site investigation. The visual envelope/viewshed is generally formed by natural/man made features such as ridgeline or building blocks.

 

Visually Sensitive Receivers (VSRs) identified in here are “representative” in that individuals or groups that have a similar sensitivity to changes in the visual and landscape environment are grouped together within a single VSR that can represent the whole group. The Hong Kong Planning Standards and Guidelines (HKPSG) define sensitive users as “land uses which, by virtue of the nature of the activities thereon…. are susceptible to the influence of residual or physical changes generated by polluting uses”.

 

The next stage was a review of the planning and development control framework. Landscape related zonings on the Outline Zoning Plan (OZP) and other relevant non-statutory layout plan were mapped and analyzed to provide an insight to the future outlook of the area affected and the way the Project would fit into its wider context.  For the proposed works, the following document is reviewed:

 

·         The Lamma Island Outline Zoning Plan (Plan no. S/I-LI/4, 2002)

·         Hong Kong Planning Area No.  10 – Pok Fu Lam – Outline Zoning Plan (Plan no. S/H10/14)

·         Hong Kong Planning Area No. 14  - The Peak Area – Outline Zoning Plan (Plan no. S/H14/6)

·         Hong Kong Planning Area Nos. 15 & 16 – Aberdeen & Ap Lei Chau – Outline Zoning Plan (Plan no. S/H15/20)

·         Hong Kong Planning Area No. 17 – Shouson Hill & Repulse Bay – Outline Zoning Plan (S/H17/7)

·         Hong Kong Planning Area No. 19 – Stanley – Outline Zoning Plan (S/H10/14)

 

The following stage was to assess impacts on the landscape and visual resources during construction and operation.  The impact assessments allow predictions to be made about the likely levels and significance of landscape and visual impacts.

 


The sensitivity of receivers for evaluation of landscape impacts will result from:

·         quality of landscape characters/resources;

·         importance and rarity of special landscape elements;

·         ability of the landscape to accommodate change;

·         significance of the change in local and regional context, and

·         maturity of the landscape.

 

The degree of sensitivity is classified as follows:

·         High – eg important components or landscape of particularly distinctive character susceptible to small changes;

·         Medium – eg a landscape of moderately valued characteristics reasonably tolerant to change;

·         Low – eg a relatively unimportant landscape which is able to accommodate extensive change.

 

The magnitude of change for assessing landscape impacts is based on:

·         compatibility of the project with the surrounding landscape;

·         duration of impacts under construction and operation phases;

·         scale of development, and

·         reversibility of change.

 

The magnitude of change is classified as follows:

·         Large – notable change in the landscape characteristics over an extensive area ranging to very intensive change over a more limited area;

·         Intermediate – moderate changes to a local area;

·         Small – changes to components;

·         Negligible – no perceptible changes.

 

The system for the assessment of landscape and visual impact is summarized in Tables 6.1 and 6.2.  The significance threshold of landscape and visual impact is derived from the combined analysis of the magnitude of change and the sensitivity of receivers.  The matrix in Table 6.1 indicates how the significance threshold is derived.  Table 6.1 explains the terms used to in Table 6.2.

Table 6.1         Significance Threshold of Potential Landscape/Visual Impact

      

Magnitude of Change

 

Sensitivity of Receiver

Low

Medium

High

Large

Moderate Impact

Moderate-Significant Impact

Significant Impact

Intermediate

Slight-Moderate Impact

Moderate Impact

Moderate- Significant Impact

Small

Slight Impact

Slight- Moderate Impact

Moderate Impact

Negligible

Negligible

Negligible

Negligible

 


Table 6.2         Adverse / Beneficial Impacts of Landscape/Visual Impact

Significant:

Moderate:

Slight:

Negligible

Adverse / beneficial impact where the proposal would cause significant degradation or improvement in existing landscape baseline conditions or visual character of the setting

Adverse / beneficial impact where the proposal would cause noticeable degradation or improvement in existing landscape baseline conditions or visual character of the setting

Adverse /beneficial impact where the proposal would cause a barely noticeable degradation or improvement in existing landscape conditions or where the changes brought about by the project would not be apparent in visual terms

The proposal does not affect the existing landscape baseline conditions or visual character of the setting.

 

The assessment of potential visual impacts will result from:

·         The sensitivity of receivers at VSR locations to change and visual intrusion;

·         The magnitude of change to the visual baseline condition.

 

The sensitivity of receivers for evaluation of visual impacts will result from:

·         value and quality of existing views;

·         availability and amenity alternative views;

·         type and estimated number of receiver population;

·         duration or frequency of view, and

·         degree of visibility.

 

The sensitivity of receivers at VSR locations will be classified as follows:

·         High

i.          The nature of the viewer groups expect a high degree of control over their immediate environment, (eg people residing in their homes); and

ii.        The viewer groups are in proximity to the Project.

 

·         Medium - 

i.          The nature of the viewer groups expect a high degree of control over their immediate environment, (eg people residing in their homes); or

ii.        The nature of the viewer groups expect some degree of control over their immediate environment, (eg teachers in schools); but

iii.      The viewer groups are not in proximity to the Project.

 

·        Low –

i.          The nature of the viewer groups do not expect a high degree of control over their immediate environment, (eg people at their place of employment or temporarily in attendance at the VSR location); or

ii.        People in transit (eg drivers and passengers in vehicles).

 


The magnitude of change for assessing visual impacts is based on:

·         compatibility of the project with the surrounding landscape;

·         duration of impacts under construction and operation phases;

·         scale of development;

·         reversibility of change;

·         viewing distance, and

·         potential blockage of view.

 

The magnitude of change to the views will be classified as follows:

·         Large: eg the majority of viewers affected / major change in view.

·         Intermediate: eg many viewers affected / moderate change in view.

·         Small: eg few viewers affected / minor change in view.

·         Negligible: eg very few viewers affected / no discernible change in view.

 

The degree of visual impact or significance threshold has been rated in a similar fashion to the landscape impact described above, ie significant, moderate, slight and negligible.  The impacts may be beneficial or adverse.

 

The significance threshold of visual impact is rated for the construction phase and for Day 1 and Year 10 of the operation phase and is illustrated in Tables 6.1 and 6.2.

 

The next stage of the study following impact assessment is to recommend mitigation measures.  The identification of the landscape and visual impacts will highlight those sources of conflict requiring design solutions to reduce adverse impacts. Mitigation measures may include revisions/refinement to the engineering design and/or the implementation of landscape design measures including screen tree planting, hard landscape design to minimize adverse landscape and visual impacts.

 

The final stage of the LVIA study is to assess the significance of the residual impacts of the study assuming landscape and visual mitigation measures are incorporated into the design.  In conclusion of the landscape and visual impacts were then classified into one of five levels of significance based on criteria in Annex 10 of the EIAO-TM, as summarized below:

 

·        The impact is beneficial if the project will complement the landscape and visual character of its setting, will follow the relevant planning objectives and will improve the overall and visual quality of the study area;

 

·        The impact is acceptable if the assessment indicates that there will be no significant effects on the landscape, no significant visual effects caused by the appearance of the project, or no interference with key views;

 

·        The impact is acceptable with mitigation measures if there will be some adverse effects, but these can be eliminated, reduced or offset to a large extent by specific measures;

·        The impact is unacceptable if the adverse effects are considered too excessive and are unable to mitigate practically; and

 

·        The impact is undetermined if significant adverse effects are likely, but the extent to which they may occur or may be mitigated cannot be determined from the study. Further detailed study will be required for the specific effects in question.

6.4                                      Baseline Conditions

6.4.1                                Project Description

The aim of the installation of wind turbine by The Hongkong Electric Co., Ltd. is to supply renewable electric energy to the customers of The Hongkong Electric Co., Ltd. in order to provide quality power supply to customers with due care for the environment. The Project is described in detail in Section 3 of the EIA.  This section summarises the main elements of the proposed works affecting the landscape and visual baseline conditions. 

The project will comprise of the construction and operation of a 600-850kW wind turbine and associated equipment. The wind turbine comprises basically of 3 rotor blades, a nacelle and a tapered monopole. Hub height and rotor blade diameter of a 600-850kW wind turbine are approx. 45 and approx. 52m respectively as shown in Figure 6.23. The overall height is approximately 71m. The aspects of the project elements that are likely to affect the landscape and visual baseline conditions during construction and operation will be activity associated with:

 

··      site formation of the platform for the wind turbine and the two equipment huts including construction of retaining walls;

··      laying of approx. 50m underground distribution cables;

··      views of the wind turbine with rotating blades.

The proposed wind turbine is located adjacent to the existing concrete paved 275kV cable road at approximately 92m P.D. . The Project Site is approached on the cable road from the southwest which slopes gently upwards. To the immediate west and southeast of the Project Site are two knolls of 127m and 136mP.D. respectively. These two knolls form a natural visual screen for most viewers from the west and southeast such as those at Yung Shue Wan, Tai Wan San Tsuen, Tai Wan Kau Tsuen and Lo Tik Wan.

The topography slopes steeply towards the northeast from the site and as a result, the views from the east and north will be relatively open. Most viewers on the coastline of Hong Kong Island south and Ap Lei Chau will have an uninterrupted view across the Lamma East Channel. The existing view of Lamma Island from these viewers is generally a lush green island with gently undulating terrain. The three chimneys of the Lamma Power Station can be seen in the background behind the ridges of Lamma Island.     

On a closer scale, the Project Site is dominated by grass with some small shrubs and occasional trees. East of the site a footpath is located leading up to Tai Ling Pavilion overlooking the northeastern part of Lamma Island.  This pavilion is located less than 100m from the Wind Turbine at the level of approximately 104m P.D. half-way between the Wind Turbine platform and the top of the southeastern knoll.  The pavilion is an important lookout point to Hong Kong Island. The view from this pavilion towards the proposed wind turbine is shown on Figure 6.23. 

6.4.2                                Limitation of the Study

For the purpose of assessing potential impacts on landscape resources, the study has included all areas within 500m from the proposed wind turbine. 

The limits of the visual impact studies are the zones of visual influence (ZVIs) of the works during the construction and operation phases. For the purpose of assessing potential visual impacts of the proposed wind turbine, the study area comprises ZVIs extending to Ap Lei Chau, South-east Hong Kong and Lamma Island, ferry en-route to Lamma Island and popular walking trails on Lamma Island. This and the location of VSRs within it are shown in Figures 6.2 and 6.3.

6.4.3                                Project Design and Construction

The design and construction of the proposed wind turbine and associated works are stipulated in Section 3.

6.4.4                                Categorization of Landscape Character Areas and Landscape Resources

The Study Area is defined as the area within 500m of either side and along the site boundary and is located at Tai Ling on Lamma Island adjacent to the Joint Bay No. 8 along the 275kV Cable Route from Lamma Power Station to Cable Landing Point at Luk Chau Wan. It faces the Hong Kong Island to the northeast.

To assist in the assessment of landscape resources in the study area one (1) Landscape Character Area (LCA) have been identified and five (5) landscape resources (LRs) within the Study Area have been quantified .

The landscape character of North Lamma Island is typical of Hong Kong rural island coastal upland covered with shrubby grassland with scattered trees/tree clumps and a small amount of village settlements on exposed hilly slopes.  The whole study area is considered to be covered under one single Landscape Character Area (LCA 1).

 

Landscape Resources found within the Study Area include secondary woodland, shrubland, shrubby grassland, village/developed area and streams (Figure 6.1).  Colour photographs of these landscape resources types, as well as other features and species of conservation interest, are presented in Figures 5.3, 5.4 and 5.5.

A total of 122 plant species were recorded. For details, please refer to Annex C Table 5.  A locally protected species Pavetta hongkongensis was recorded within the Study Area (Figure 5.8).  The number of plant species and the size of each identified Landscape Resources type are presented in Table 6.3.

Table 6.3         Landscape Resources Recorded Within the Study Area

Landscape Resources type

Number

Area (hectare)/

Length (Km)

Number of Plant Species Recorded

Secondary Woodland

LR1

20.5 ha

64

Shrubland

LR2

49.4 ha

74

Shrubby Grassland

LR3

5.7 ha

25

Stream

LR4

 

42

Stream S1

 

0.03 km

 

Stream S2

 

0.38 km

Stream S3

 

0.46 km

Stream S4

 

0.23 km

Village/Developed Area

LR5

3.8 ha

18

 

Total

79.4 ha

 

Details description of each of these Landscape Character Area and Landscape Resource are listed below:

 

North Lamma Coastal Uplands – LCA 1

 

North Lamma Coastal Uplands is a landscape character area consisting of coastal uplands and hillsides and is characteristic of most of Lamma Island except for urban peripheral village landscapes formed by settlements such as Pak Kok San Tsuen to Hung Shing Ye; Lo So Shing and Sok Kwu Wan; and Mo Tat Old Village and Tung O.  Other identified landscape character areas of the island are quarry landscape around Luk Chau Village, the industrial urban landscape of the Power Station, and one unsettled valley and rural inland plains to the mid south of the island.  As the Study Area is within the North Lamma Coastal Upland area the Landscape Character Area under discussion shall be focused on this landscape area type.

 

The topography of this area consists of rolling and sometimes hilly ridges, spurs and hillsides with isolated boulders and crags protruding above the scattered trees/tree clumps, woodland scrub and grasslands (Figure 6.4).  It tends to be steeper on the eastern slopes which fall directly to the east lamma channel.  The area is undeveloped except for small villages at Lo Tik Wan (Figure 6.5).  Western slopes, in comparison, are criss-crossed by footpaths and a trail between Yung Shue Wan and Sok Kwu Wan.  The slopes are also traversed by a 5.5m wide cable trench running from the power station to the sea off Luk Chau Wan in the south and Pak Kok in the north.  Hills are of a similar height, ranging from 138mPD at Pak Kok Shan in the north to 135 mPD in the south.  Landuse within the hills is characterised by pockets of semi-abandoned fields and village development (Figure 6.6), a service reservoir in the centre and the Lamma Island Youth Hostel to the south. 

 

Vegetation is dominated by emergent scrub and grassland with small pockets of trees located within sheltered seasonal stream courses.  The uplands command open views across the East Lamma Channel to Aberdeen and Ap Lei Chau in the east.

 

The site is located at the valley form by two knolls in the central portions of north Lamma Island, some 200m north north-east of Tai Ling.  The knolls are 127 – 136 mPD high and the Wind Turbine platform is to be at 92mPD.  Hence the Wing Turbine is to be sited at a somewhat shelter position within the topography. 

 

The aesthetic and perceptual quality of the landscape is of large, open, remote, and coherent characteristics with low diversity of landuse and high visual exposure to other landscape character areas.  It is frequently visited by tourists and urban dwellers as an outing destination for its pleasant and tranquil natural qualities.  It is considered to have an overall high landscape character value.

Secondary Woodland – LR1

Secondary woodlands were found mainly at the east and southwest of the Study Area.  A total of 64 plant species were recorded in the secondary woodlands.

The secondary woodlands located at the southwest of the Study Area were semi-natural with exotic plantation at the fringe of the woodland and the understory was dominated by native plant species.  The secondary woodlands were fragmented by the 275 kV Cable Route, which was covered by cement and grass-crete acting as a concrete road connecting to other areas on Lamma Island.  The exotic plantation was found mainly at the fringe of the woodland and along the 275 kV Cable Route at Tai Wan Kau Tsuen, Long Tsai Tsuen and Tai Ling Tsuen.  Village houses were scarcely located within the woodland, which were mainly on both sides of the 275 kV Cable Route.  The canopy species were 10 to 14 m in height and dominated by Acacia confusa, Albizia labbeck, Leucaena leucocephala and Melaleuca leucadendron.  The understory was occupied by native trees and shrubs, which can be divided into a middle layer 4 to 8 m in height and a lower layer 1 to 3 m in height.  The middle layer of understory was dominated by Cinnamomum camphora, Macaranga tanarius and Schefflera octophylla while the lower layer of understory was dominated by Ilex asprella, Litsea glutinosa and Sterculia lanceolata. 

 

Secondary woodland found in the east of the Study Area near Lo Tik Wan was a large patch of woodland dominated by native tree species.  Village houses were scarcely located within the woodland and some of them were abandoned.  The woodland was dominated by climax species such as Cinnamomum camphora, Mallotus paniculatus, Sterculia lanceollata, Macaranga tanarius and Dimocarpus longan.  Canopy species reached a height of 12-15 m.  The understorey was densely vegetated and dominated by woody species including Litsea rotundifolia, Ligustrum sinensis, Eurya nitida and the climbers Gnetum montanum and Uvaria microcarpa.  A locally protected species Pavetta hongkongensis were found within the secondary woodland (Figures 5.7 and 5.8).  This woodland is remote from the turbine location.

This Landscape Resource LR1 - Secondary Woodland has an overall medium landscape sensitivity.

Shrubland – LR2

Shrubland was the dominant landscape resources type within the Study Area and was 1 to 4 m in height.  It was dominated by several native shrub species including Rhodomrytus tomentosa, Cratoxylum cochinchinensis, Dalbergia benthami, Eurya nitida, Embelia laeta, Embelia ribes and Gordonia axillaries.  Shrubland patches in the valleys were usually taller with an average 2 to 4 m in height while those on the hill slope and ridge of the hills were 1 to 2.5 m in height.  A total of 74 plant species were recorded within the shrublands.

This Landscape Resource LR2 - Shrubland has an overall medium landscape sensitivity.

Shrubby Grassland – LR3

Shrubby grasslands were mainly found in the middle of the Study Area and close to the Project Area, which was located at the north of Yung Shue Long Old Village and next to the WSD Service Reservoir.  The area was expected originally to have been shrublands but has been disturbed due to hill fires leading the area to become dominated by grass species.  The area had been burnt a short period of time before the surveys.  A total of 25 plant species were recorded within the shrubland and dominated by Ischaemum aristatum and Eriachne pallescens.  

This Landscape Resource LR3 – Shrubby Grassland has an overall medium landscape sensitivity.

Streams – LR4

Three partially modified and one less disturbed streams, S1 to S4, were found within the Study Area (Figure 5.2).  Forty-two plant species were recorded along the streams and no rare/protected species were found during the surveys.

Stream S1 is a drainage channel running along with the 275 kV Cable Route (Figure 5.2).  The lower course of stream S1 was cemented while the upper course was an underground channel.  Only limited water flow was recorded in Stream S1 during the survey. 

Stream S2 was partially channelized in the upper and middle courses (from the Service Reservoir to Tai Ling Tsuen).  Stream S2 has natural bottom, particularly in the middle and lower courses, dominated by medium to small sized boulders and sand.  The upper and middle courses were covered by the close canopy of the adjacent woodland while the lower course of the stream was more open with limited shading by the shrubs and grasses in the vicinity.  Only limited water flow was recorded in lower course and no water flow recorded in the upper and middle courses during the survey. 

Stream S3, located at the northwest of the Study Area, was relatively less disturbed.  Water flow in stream S3 was low and the stream bank was natural with medium-sized boulders and sand bottom.  The riparian vegetation of the stream was integrated with the surrounding shrubland with semi-open canopy. 

Stream S4 was partially channelized in the lower course but the upper and middle courses remained natural, with relative steep slope.  The bottom of Stream S4 remains natural, composed of sand and small to medium sized boulders.  No water was found in the upper course.  The middle course has several small pools filled with water but the water flow was limited.  The close canopy of secondary woodland covered the whole section of the stream with limited open space in the middle and lower courses.

This Landscape Resource LR4 – Streams has an overall medium landscape sensitivity.

Village/Developed Areas – LR5

Village/developed areas, comprising village houses, 275 kV Cable Route and the Service Reservoir, were scattered within the Study Area.  The Service Reservoir was located close to the Project Area.  All of the vegetation recorded within this landscape resource type, such as Michelia alba and Ficus microcarpus, were planted for landscaping purposes.  Fruit trees such as Musa paradisiacal, Dimocarpus longan, Citrus sinensis and Clausena lansium were also recorded.  A total of 18 plant species were found in this landscape resource area and no rare plant species were found. 

This Landscape Resource LR5 – Village/Developed Areas has an overall medium landscape sensitivity.

6.4.5                                Visually Sensitive Receivers

In accordance with the study methodology, the Visually Sensitive Receivers (VSRs) within the visual envelope are identified. The representative viewpoints on Lamma Island and Hong Kong Island are identified from VSRs. (refer to Table 6.4 and 6.5).

In summary, the VSRs can be classified into 3 main groups.

·                     Resident and people at work VSRs on Lamma Islands where the proposed wind turbine would be visible

·                     Resident and people at work VSRs on Hong Kong Island south and Ap Lei Chau

·                     Visitors and viewers in transit such as those on hiking tracks on Lamma Island and along the ferry routes as well as those in Ocean Park

·                     Visitors to the Tai Ling Pavilion and cable road adjacent to the Project Site

People in transit are considered to be less sensitive to visual impact than people residing in their homes, although the visitors to the cable road and Tai Ling Pavilion immediately next to the site will be much more sensitive to the visual impact of the Wing Turbine.

The representative visual receiver groups on Lamma Island are identified in Figure 6.2.  The natural topography of Lamma Island provides a visual barrier over the southern areas of the island. To the south, the proposed wind turbine would be visually screened from the villages around Lo Tik Wan Hung Sing Ye Beach, Lo So Shing Beach, Sok Kwu Wan Pier and Mo Tat Wan Pier by the Headland or the southeastern knoll near the site. To the west, the views from Yung Shue Long, Tai Wan San Tsuen and Tai Wan Kau Tsuen are screened by the natural steep terrain or the western knoll.

Along the waterfront of Yung Shue Wan including the future waterfront promenade and the dense settlements around Yung Shue Wan including Sha Po New Village, Sha Po Old Village and Tai Yuen Village, the view towards the wind turbine would be largely blocked by houses. The views from the upper storeys of the houses where a clear view towards the wind turbine is possible, would be similar to the view from Yung Shue Wan Pier.

To the northwest of the wind turbine at Tai Peng, most of the houses are orientated facing southwest and the views towards the Project Site are largely blocked by other houses or the relatively tall woodland at the fringe of the village.

All three houses at Tai Ling Tsuen face downhill while the wind turbine is on the uphill side.

However, the proposed wind turbine would be visible from the villages of Pak Kok San Tsuen, the beaches of Tai Wan To and the nearby Long Tsai Tsuen and the pier of Yung Shu Wan, with a middle ground view from a distance within 1.3 km. In addition, the proposed wind turbine would also be visible to the hikers on the relatively higher ridgelines of the Lamma Island hiking trails and one of the four pavilions along the hiking route between Yung She Wan and Sok Kwu Wan. Existing views are shown in Figures 6.7, 6.8, 6.9, 6.10 and 6.11.

The proposed wind turbine would be most visible from visitors and hikers to the track and pavilion next to the site.  From the track the entire wind turbine would be visible and from the pavilion the wind turbine shaft would be visible whilst the blades would be hidden from view by the pavilion roof. Existing view is shown in Figure 6.23.

The proposed wind turbine would be visible from a number of higher locations including The Peak and southern coastal areas on Hong Kong Island including Repulse Bay, Mount Davis, Pok Fu Lam Road, Wah Fu, Cyberport, Ocean Park, Ap Lei Chau and Chung Hom Kok. Representative visual receiver groups are shown in Figure 6.3. All of them are over 3 km away and the proposed wind turbine would be visible in relatively small scale from these long distant visual reference points.

In addition, similar views would be available to recreational boat users using the Lamma East Channel.

The existing views from the representative receiver groups are shown in Figures 6.12, 6.13, 6.14, 6.15, 6.16, 6.17, 6.18, 6.19, 6.20 and 6.21.

 


Table 6.4         Visually Sensitive Receivers on Lamma Island

 

VSR

Name

Nature of Viewer

Group/ no. of receivers

Distance to Proposed Works

Analysis of view towards proposed development

Source of impact

Sensitivity to change and visual intrusion

VSR 1

Pak Kok San Tsuen

Residents

 

Approximate number of receivers: small

over 1km

Partially obstructed views with the rotor blades of the wind turbine protruding out on the ridgeline as illustrated in Figure 6.7.

 

Proposed wind turbine

Medium

VSR 2

Yung Shu Wan Pier/Sha Po New Village/Sha Po Old Village/Tai Yuen Village

Residents, passenger & boat travellers

 

Approximate number of receivers: small

over 1km

Partially obstructed views with the rotor blades of the wind turbine protruding out on the ridgeline as illustrated in Figure 6.8.

 

Rotor blades of wind turbine

Medium

VSR 3

Tai Wan To/Long Tsai Tsuen

Hikers and residents in transit

 

Approximate number of receivers: small

750m

Partially obstructed views with the rotor blades of the wind turbine protruding out on the ridgeline as illustrated in Figure 6.9.

 

Rotor blades of wind turbine

Medium

VSR 4

 

Hiking Trail on Lamma Island (Pavilion)

Hikers

 

 

Approximate number of receivers: small

over 1.5km

Partially obstructed views towards the rotor blades of the wind turbine at the relatively higher points of the trail as illustrated in Figure 6.10 and fully obstructed views by the Lamma topographical headland along a large proportion of hiking trail.

 

Rotor blades of wind turbine

Low

VSR 5

 

Hiking Trail on Lamma Island

Hikers

 

 

Approximate number of receivers: small

over 2.5km

Partially obstructed views towards the rotor blades of the wind turbine at the relatively higher points of the trail as illustrated in Figure 6.11 and fully obstructed views by the Lamma topographical headland along a large proportion of hiking trail.

 

Rotor blades of wind turbine

Low

VSR 16

 

Tai Ling Pavilion/adjacent cable road

Hikers

 

 

Approximate number of receivers: small

Less than 100m

Dominant view of the wind turbine, the site platform and the retaining wall on a close scale.

 

Wind turbine, site platform and retaining wall

High

 


Table 6.5         Visually Sensitive Receivers on Hong Kong Island & Lamma East Channel

 

VSR

Name

Nature of Viewer

Group/ no. of receivers

Distance to Proposed Works

Analysis of of view towards proposed development

Source of impact

Sensitivity to change and visual intrusion

VSR 6

Repulse Bay

Residents and tourists

 

Approximate number of receivers: Intermediate

over 8km

Open and very distant views towards the upper part of wind turbine which would be relatively very small as illustrated in Figure 6.12.

Proposed wind turbine

Medium

VSR 7

Pok Fu Lam Road

Residents

 

Approximate number of receivers: Many

over 4km

Open, unobstructed and distant views towards the wind turbine which would be relatively small as illustrated in Figure 6.13.

 

Proposed wind turbine

High

VSR 8

The Peak

Residents and tourists

 

Approximate number of receivers: Intermediate

over 5km

Open, unobstructed and distant views towards the wind turbine which would be relatively small as illustrated in Figure 6.14.

 

Proposed wind turbine

Medium

VSR 9

Wah Fu

Residents

 

 

Approximate number of receivers: Many

over 3km

Open and unobstructed views towards the wind turbine which would be seen clearly situated near the top of the ridgeline as illustrated in Figure 6.15.

 

Proposed wind turbine

High

VSR 10

Cyberport

Residents & office occupants

 

Approximate number of receivers: Many

over 3km

Open and unobstructed views towards the wind turbine which would be clearly situated near the top of the ridgeline as illustrated in Figure 6.16.

 

Proposed wind turbine

High

VSR 11

Ap Lei Chau

 

Residents

 

 

Approximate number of receivers: Many

over 3km

Open and unobstructed views towards the wind turbine which would be clearly situated near the top of the ridgeline as illustrated in Figure 6.17.

 

Proposed wind turbine

High

VSR 12

Mount Davis

 

Residents and tourists

 

 

Approximate number of receivers: Small

over 5km

Open and very distant views towards the wind turbine against the backdrop of the Lamma hilly landscape behind. The wind turbine would be relatively small as illustrated in Figure 6.18.

 

Proposed wind turbine

Medium

VSR 13

Chung Hom Kok

 

Residents and tourists

 

 

Approximate number of receivers: small

over 8km

Open and very distant views towards the wind turbine which would be relatively very small as illustrated in Figure 6.19.

 

Proposed wind turbine

Medium

VSR 14

Lamma East Channel

Ferry users

 

 

Approximate number of receivers: small

over 1.5km

Open and unobstructed views towards the wind turbine which would be clearly situated in the headland as illustrated in Figure 6.20.

 

Proposed wind turbine

Low

VSR 15

Ocean Park

Visitors/ Tourists

 

 

Approximate number of receivers: Many

over 3km

Open and unobstructed views towards the wind turbine which would be clearly situated near the top of the ridgeline as illustrated in Figure 6.21.

 

Proposed wind turbine

Medium


6.4.6                                Review of Planning and Development Control Framework

 

The starting point for the review of the planning and development control framework was a review of the various statutory and non-statutory controls relevant to the proposed project, which affect landscape and visual impacts. 

 

The review includes information on:

 

··      The Lamma Island Outline Zoning Plan (Plan no. S/I-LI/4, 2002)

··      Hong Kong Planning Area No.  10 – Pok Fu Lam – Outline Zoning Plan (Plan no. S/H10/14)

··      Hong Kong Planning Area No. 14  - The Peak Area – Outline Zoning Plan (Plan no. S/H14/6)

··      Hong Kong Planning Area Nos. 15 & 16 – Aberdeen & Ap Lei Chau – Outline Zoning Plan (Plan no. S/H15/20)

··      Hong Kong Planning Area No. 17 – Shouson Hill & Repulse Bay – Outline Zoning Plan (S/H17/7)

··      Hong Kong Planning Area No. 19 – Stanley – Outline Zoning Plan (S/H10/14)

·         Plan showing Land Use Concept of Yung Shue Wan Reclamation Phase 2

Under the approved Lamma Island Outline Zoning Plan (Plan no. S/I-LI/4, 2002), the proposed wind turbine falls within the “Green Belt” (GB) zoning.

The Government intend to reclaim land in the Yung Shue Wan area to form a landscaped promenade in front of the existing one.  The visual impact of the extended promenade has been discussed in Section 6.4.5. 

Under the Outline Zoning Plans for South Hong Kong including plan no. S/H10/4, S/H14/6, S/H15/20, S/H17/7 and S/H10/14, there is no large development/reclamation planned for the future. Landuse within Hong Kong South Island would be foreseen to not have a significant change. The recently developed Cyberport has been included as one of the visual sensitive receivers in this assessment.  

6.5                                      Landscape and Visual Impact Assessment during Construction

6.5.1                                Prediction and Evaluation of Landscape Impacts during Construction

 

The magnitude of the impacts, before implementation of mitigation measures, on the landscape resources and landscape character areas that would occur in the construction phase are described below and tabulated.  All impacts are adverse unless otherwise stated.

 


Construction activities which will affect landscape and visual aspect include:

·                     Erection of a wind turbine (hub height approximately 45m and rotor blade diameter of approximately 52 m, overall height of the wind turbine approximately 71 m);

·                     Excavation and construction of the wind turbine foundation (affected area approximately 15 m by 15 m);

·                     Construction of a site platform and retaining wall (affected area approximately 3,100sq.m.);

·                     Construction of one stainless steel hut as high voltage distribution pillar (HVDP) (size approximately 4.6 m length, 2.5 m width, 2.8 m height) for housing of switchgear and power conditioning devices;

·                     Laying of underground distribution cables for connecting to the nearby existing cable route (approximately 50 m in length).

 

The total effect of all the above works would result in the disturbance of approximately 3,100 sq.m.. The whole of this is within the Project Site. The extent and location of these impacts are shown on Figure 6.26.

 

The quantification of the disturbances to the LCA1 and various LR types are presented in Table 6.6.

Table 6.6         Summary of Disturbance to LCA1 and Various Landscape Resources

LCA/LR

Type of Landscape Resources Present in the LCA/LR

Quantification of Landscape Resources within the LCA/LR

Area in conflict with the proposed works

Magnitude of Change during Construction

LCA1

North Lamma Coastal Uplands

Approx. 79.4 ha

Approx. 3,100 m2

Small

LR1

Secondary Woodland

20.5 ha

0m2

Negligible

LR2

Shrubland

49.4 ha

0m2

Negligible

LR3

Shrubby Grassland

5.7 ha

Approx. 3,100 m2

Small

LR4

Stream

Total 1.1 km

0 km

Negligible

LR5

Village/Developed Area

3.8 ha

0m2

Negligible

 

Disturbance to North Lamma Coastal Uplands – LCA 1

 

The work areas as described above (approx. 3,100 sq.m.) fall within LCA1.

In the context of the study area, the possible affected area is considered small (representing 0.39%) and thus the magnitude of change to the overall landscape character of the area is small. As LCA1 is considered to have an overall high landscape character value, the significance threshold is moderate/adverse.

 


Disturbance to Shrubby Grassland – LR3

The whole work areas fall within LR3. During the construction works approximately 3,100 sq.m. of shrubby grassland need to be removed which represents 5.4% of the 5.7 ha of LR3. The magnitude of change is considered small. As LR3 has an overall medium landscape sensitivity, the significance threshold is slight moderate/adverse.

Disturbance to Stream – LR4     

During construction activities the primary sources of water quality impacts will be from pollutants in site run-off.  Pollutants, mainly suspended sediments, may also enter receiving waters if any pumped groundwater is not adequately controlled on-site.

The potential sources of impacts to water quality may be readily controlled by appropriate on-site measures to minimise potential impacts as described in Section 8.6.  With the implementation of such measures adverse impacts to water quality are not expected to result from land based construction activities. The magnitude of change and the significance threshold are both negligible.

Disturbance to Other Landscape Resources Secondary Woodland – LR1, Shrubland – LR2 and Village/Developed Area – LR5    

The construction activities do not confilict with these LRs and the magnitude of change and the significance threshold are negligible for all these LRs.

Landscape within the Project Site

 

A detailed tree survey has been conducted for the Project site. The survey identifies trees that are in or at the vicinity of the works area. The survey identifies 45 nos. of trees in which 2 nos. are within the Project site. All 45 trees are to be retained.

6.5.2                                Prediction and Evaluation of Visual Impacts during Construction

 

The visual impact during construction will be arising from:

 

··      site formation and construction activities for maintenance platform, mini-pile and pile cap;

··      lifting of turbine components by crane;

··      temporary hoarding.

 

The visual impacts during construction will be (refer to Table 6.8 for summary):

 

··      VSR1 Pak Kok San Tsuen, VSR2 Yung Shu Wan Pier/Sha Po New Village/Sha Po Old Village/Tai Yuen Village, VSR3 Tai Wan To/Long Tsai Tsuen, VSR4 Hiking Trail in Lamma Island (Pavilion) & VSR5 Hiking Trail in Lamma Island – The construction plants would be dominant unsightly elements partially visible in the middleground seen by residents in their homes and hikers along trials. The magnitude of change during construction would be intermediate as the full view would be blocked by topography and existing trees/houses in the foreground.

 

Since the sensitivity to change for VSR 1 Pak Kok San Tsuen, VSR2 Yung Shu Wan Pier/Sha Po New Village/Sha Po Old Village/Tai Yuen Village and VSR3 Tai Wan To/Long Tsai Tsuen  is medium, the significant threshold would be moderate/adverse. The sensitivity to change for the other VSRs is low and the corresponding significant threshold would be slight-moderate/adverse.

 

··      VSR7 Pok Fu Lam Road, VSR9 Wah Fu, VSR10 Cyberport, VSR11 Ap Lei Chau, VSR14 Lamma East Channel and VSR15 Ocean Park – The construction plants and site formation works would be seen in the distant middleground from a distance of 1.5 to 5km by residents in their homes or commuters on ferries or tourists/visitors. However, these are not dominant elements and the magnitude of change during construction is considered intermediate.

 

Since the sensitivity to change for VSR14 Lamma East Channel is low, the significant threshold would be slight-moderate/adverse. The sensitivity to change for VSR15 Ocean Park is medium, the significant threshold would be moderate/adverse. The sensitivity to change for the other VSRs is high and the corresponding significant threshold would be moderate-significant/adverse.

 

··      VSR6 Repulse Bay, VSR8 The Peak, VSR12 Mount Davis, VSR13 Chung Hom Kok – The construction plants and site formation works would be seen in the distant background from a distance of over 5km. The construction work is not noticeable in this far distance. The magnitude of change during construction is considered small.

 

Since the sensitivity to change for VSR6 Repulse Bay, VSR8 The Peak, VSR12 Mount Davis, VSR13 Chung Hom Kok is medium, the significant threshold would be slight-moderate/adverse.

 

·         VSR16 Tai Ling Pavilion/adjacent cable road – The construction plants and site formation works would be seen upclose and would be dominating especially during the erection of the wind turbine when large scale cranes are used.  The magnitude of change during construction is large.

 

Since the sensitivity to change for VSR16 Tai Ling Pavilion/adjacent cable road is high, the significant threshold would be significant/adverse.

6.6                                      Landscape and Visual Impact Assessment during Operation

6.6.1                                Prediction and Evaluation of Landscape Impacts during Operation

Upon the completion of the construction, part of the new cut and fill slopes and other land affected by construction works would be reinstated to natural land form and topography of the natural slope as far as practical. New shrub land/grass land planting would be implemented in-keeping with the surrounding landscape character.  In addition, appropriate landscape planting including trees, shrubs and grasses (approx. 1,400 sq.m.) will be provided to soften the ground level appearance resulting in a net loss of 1,700 sq.m.of vegetation. These mitigation measures are more described in more detail in section 6.7.

The extent and location of the loss of vegetation ie the landscape impact during operation is shown on Figure 6.26.

The quantification of the net loss to the LCA1 and various LR types are presented in Table 6.7.

 

Table 6.7         Summary of Net Loss to LCA1 and Various Landscape Resources

LCA/LR

Type of Landscape Resources Present in the LCA/LR

Quantification of Landscape Resources within the LCA/LR

Net Loss in Area

Magnitude of Change during Construction

LCA1

North Lamma Coastal Uplands

Approx. 79.4 ha

Approx. 1,700 m2

Small

LR1

Secondary Woodland

20.5 ha

0m2

Negligible

LR2

Shrubland

49.4 ha

0m2

Negligible

LR3

Shrubby Grassland

5.7 ha

Approx. 1,700 m2

Small

LR4

Stream

Total 1.1 km

0 km

Negligible

LR5

Village/Developed Area

3.8 ha

0m2

Negligible

The net loss in Landscape Resources is considered small in LCA1 as it only represents 0.2% of the total Study Area. The significance threshold is moderate/adverse.

The magnitude of change to LR3 remains small and the significance threshold also remains at slight moderate/adverse.

The significance threshold for all other LR types remains as negligible.

6.6.2                                Prediction and Evaluation of Visual Impacts during Operation

 

The operation of the proposed wind turbine will not consume fuel and generate waste or side products. Major impacts during operational phase are associated with the visual impact of the wind turbine with rotating blades and other associated built structures including the platform, retaining wall at a closer scale.

 

The visual impact arising during operation will be:

 

··      VSR1 Pak Kok San Tsuen, VSR2 Yung Shu Wan Pier/Sha Po New Village/Sha Po Old Village/Tai Yuen Village, VSR3 Tai Wan To/Long Tsai Tsuen, VSR4 Hiking Trail in Lamma Island (Pavilion) and VSR5 Hiking Trail in Lamma Island – The rotating blades of the proposed wind turbine would be permanently discernible against background, but is not conspicuous. The magnitude of change during operation would be intermediate as the views would be partially blocked by topography and existing trees/houses in the foreground.

 

Since the sensitivity to change for VSR 1 Pak Kok San Tsuen, VSR2 Yung Shu Wan Pier/Sha Po New Village/Sha Po Old Village/Tai Yuen Village and VSR3 Tai Wan To/Long Tsai Tsuen is medium, the significant threshold would be moderate/adverse. The sensitivity to change for the other VSRs is low and the corresponding significant threshold would be slight-moderate/adverse.

 

··      VSR7 Pok Fu Lam Road, VSR9 Wah Fu, VSR10 Cyberport, VSR11 Ap Lei Chau, VSR14 Lamma East Channel and VSR15 Ocean Park – The proposed wind turbine would be seen in the distant middleground from a distance of 1.5 to 5km. The proposed wind turbine would be prominent, but it is not dominating the whole view to the Lamma Island. The magnitude of change during operation is considered intermediate.

 

Since the sensitivity to change for VSR14 Lamma East Channel is low, the significant threshold would be slight-moderate/adverse. The sensitivity to change for VSR15 Ocean Park is medium, the significant threshold would be moderate/adverse. The sensitivity to change for the other VSRs is high and the corresponding significant threshold would be moderate-significant/adverse.

 

··      VSR6 Repulse Bay, VSR8 The Peak, VSR12 Mt. Davis, VSR13 Chung Hom Kok – The proposed wind turbine would be seen in the distant background from a distance of over 5km. The proposed wind turbine is not noticeable in this far distance. The magnitude of change during operation is considered small.

 

Since the sensitivity to change for VSR6 Repulse Bay, VSR8 The Peak, VSR12 Mount Davis, VSR13 Chung Hom Kok is medium, the significant threshold would be slight-moderate/adverse.

 


·         VSR16 Tai Ling Pavilion/adjacent cable road – The wind turbine with rotating blades and other associated built structures including the platform, retaining wall would be seen upclose and would be dominating. The magnitude of change during operation at this close distance is large.

 

Since the sensitivity to change for VSR16 Tai Ling Pavilion/adjacent cable road is high, the significant threshold would be significant. There is no doubt that the visual impact of the wind turbine at this close distance would be significant. However, whether it is an adverse or beneficial impact would very much depend on the viewers acceptance towards the use of this kind of renewable energy as a substitute to coal burning.

 

One of the objectives of this project is to educate the public and in particular students, for promotion of green awareness. With the gain in knowledge of the benefits of renewable energy such as the improvement of air quality, the likelihood of acceptance of the visual impact would be increased.

 

A summary of landscape and visual impacts during operation is given in Table 6.8 and 6.9.

6.7                                      Recommended Landscape and Visual Mitigation Measures

In order to mitigate these impacts, a number of soft landscape and colour scheme mitigation measures are recommended for incorporation into the Project.  These mitigation measures are summarised in the following paragraphs and shown on Table 6.11. The extent and location is shown on Figure 6.24 and a photomontage of the project with and without mitigation measures is shown on Figure 6.25.

Mitigation Measure 1 (MM1) – Partial Reinstatement of Disturbed Areas (To be completed with construction stage)

·                     New cut and fill slopes and other land affected by construction works would be reinstated to natural land form and topography of the natural slope as far as practical. Grading of these slopes to resemble a natural, rolling landform similar to that of adjacent topography would be carried out.

Approximately 1,400 sq.m. of disturbed areas would be reinstated.

Mitigation Measure 2 (MM2) – Compensatory Planting (To be completed with construction stage and maintained during operation)

In compensation for the disturbance to existing vegetation area of approximately 3,100 sq.m., appropriate landscape planting including trees, shrubs and grasses (approx. 1,400 sq.m.) will be provided to soften the ground level appearance of the proposed wind turbine site. These include hydroseeding of a grass mix similar to those found in the area, together with the following native tree and shrub seeds included in the hydroseeding mix, to quickly re-establish any disturbed slopes.


Botanical Name

Size

Tree

 

Acacia confusa

Light Standard

Schefflera heptaphylla

Light Standard

Ficus hispida

whip

Celtis sinensis

Light Standard

Cinnamomum camphora

Light Standard

Litsea glutinosa

whip

Microcos paniculata

whip

Sterculia lanceolata

whip

Sapium discolor

Light Standard

Notes:  A mixture of the above trees will be planted at Standard to Heavy Standard size immediately in front of the retaining wall at the downside slope of the edge of the platform area, to mitigate the impact of the wall.

Shrub

 

Ilex pubescens

500-600mm Ht.

Melastoma candidum

500-600mm Ht.

Rhodomytrus tomentosa

500-600mm Ht.

Rhaphiolepis indica

500-600mm Ht.

Mitigation Measure 3 (MM3) – Colour Scheme and non-reflective paints (To be completed with construction stage)

A proper colour selection will be made to enable the proposed wind turbine to blend in well with natural surroundings and minimise the visual intrusion.

It is noted that in general practices the rotor blades, nacelle and pole are generally in white colour. In this case, as demonstrated in the photomontages from the different VSRs, the wind turbine would be seen either against a sky or greenery backdrop.

An investigation was carried out to find out the visual effect of various light colour tones on the wind turbine (see Fig. 6.22). In case of good visibility and weather conditions, the wind turbine in any light colour would be relatively prominent due to its special shape either against the sky or greenery. However, a light grey colour would render the wind turbine less intrusive in mid to low visibility conditions as the light grey colour is less contrasting to the grey sky backdrop comparing with other colours such as white, green or blue. The effect of reducing the intrusiveness would be particularly noticeable for the distant viewers.

As a colour mitigation measure, a light grey non-reflective colour is thus selected. The proposed colour is similar to the colour chip as shown in Fig. 6.23 (ICI colour code 1369 North Beach 50BG 72/011).

Mitigation Measure 4 (MM4) –Soil Conservation (To be completed with construction stage)

Soil conservation is a consideration in the management of the construction phase. Existing soil resources on site from the cut slope will be re-used for backfilling at site as far as practicable to minimize the need to import or export soils.

Mitigation Measure 5 (MM5) – Selection of low rotating speed machine (To be completed with construction stage)

 

In order to minimize the visual disturbance, a low rotating speed machine will be chosen.

 

In addition to the above, the following good site practices would also be implemented:

·         Screening of site construction by means of temporary hoarding that is appropriate to its site context.

·         Tree protective measures will be implemented to ensure the existing trees within the Project site identified as to be preserved are satisfactorily protected during the construction phase.

6.8                                      Residual impacts

6.8.1                                Residual Landscape Impacts

 

The incorporation of mitigation measures into the scheme will reduce the impacts in most cases as follows:

MM1 will ensure that new fill slope work will resemble a natural, rolling landform similar to that of adjacent topography. MM2 will compensate for the loss of vegetation through the implementation of planting of trees, shrubs and grasses as appropriate. MM4 will ensure that the valuable soil will be re-used where possible. The extent and location of these mitigation measures is shown on Figure 6.24.

 

Residual Landscape Impact to North Lamma Coastal Uplands – LCA 1 & Shrubby Grassland – LR3

With the implementation of the above mitigation measures, the magnitude of change to LCA1 and LR3 would be reduced from a net loss of 3,100 sq.m. to 1,700sq.m. ie from 0.39% to 0.2% for LCA1 and from  5.4% to 3.0% for LR3. While the overall effect of the mitigation measure towards the LCA1 is not significant, MM2 will result in a net increase in the quantity of vegetation at the Project Site and would reduce the significance threshold of the residual impact for LR3 fromslight-moderate/adverse” to “slight/adverse” during Year 1 of operation and “slight/beneficial” during Year 10 of operation.

A summary of residual landscape impacts is shown in Table 6.8.

6.8.2                                Residual Visual Impacts

 

The incorporation of mitigation measures into the scheme will reduce the visual impacts in most cases as follows:

 

··      VSR7 Pok Fu Lam Road, VSR9 Wah Fu, VSR10 Cyberport and VSR11 Ap Lei Chau and – MM3 would improve the visual appearance of the proposed wind turbine during operation with a light grey non-reflective colour scheme (MM3). Selection of low rotating speed machine (MM5) will render the wind turbine to be less conspicuous. This will lead to a reduction of “moderate-significant/adverse” unmitigated visual impact down to “moderate/adverse” residual visual impact during Year 1 and 10 years of operation.

 

··      VSR 1 Pak Kok San Tsuen, VSR2 Yung Shu Wan Pier/Sha Po New Village/Sha Po Old Village/Tai Yuen Village, VSR 3 Tai Wan To/Long Tsai Tsuen and VSR15 Ocean Park – MM3 would improve the visual appearance of the proposed wind turbine during operation with a light grey non-reflective colour scheme (MM3). Selection of low rotating speed machine (MM5) will render the wind turbine to be less conspicuous. This will lead to a reduction of “moderate/adverse” unmitigated visual impact down to “slight-moderate/adverse” residual visual impact during Year 1 and 10 years of operation.

 

··      VSR 4 Hiking Trail in Lamma Island (Pavilion) & VSR 5 Hiking Trail in Lamma Island, VSR6 Repulse Bay, VSR8 The Peak, VSR12 Mount Davis, VSR13 Chung Hom Kok and VSR14 Lamma East Channel – Similar to the VSRs above, MM3 and MM5 would improve the visual appearance of the proposed wind turbine during operation leading to a reduction of “slight-moderate/adverse” unmitigated visual impact down to “slight/adverse” residual visual impact during Year 1 and 10 years of operation.

 

·         VSR16 Tai Ling Pavilion/adjacent cable road – As the VSR is very close to the Project, the mitigation measures would not reduce the visual impacts of the wind turbine. However, MM1 and MM2 would help to improve the visual impact by minimizing the apparent disturbance to the natural landscape and screening of the retaining wall. The significance threshold would remain as significant.

 

A summary of residual visual impacts is shown in Table 6.10.


6.9                                      Conclusion and Summary of Findings

The major findings of the LVIA are as follows:

·                     The Project would result in the disturbance of approximately 3,100 sq.m. of Landcape Character Area LCA1 -  North Lamma Coastal Uplands and Landscape Resources LR3 – Shrubby Grassland out of which approximately  1,400 sq.m. will be reinstated resulting in a net loss of approximately 1,700 sq.m. With the implementation of appropriate mitigation measures including MM1 - Partial Reinstatement of Disturbed Areas,  MM2 – Compensatory Planting and MM4 – Soil Conservation, the significance threshold of the residual landscape impacts are generally negligible and range from slight/adverse” during Year 1 of operation and “slight/beneficial” during Year 10 of operation for LR3.

·                     The proposed wind turbine would be visible from various VSRs on Lamma Islands, Hong Kong Island south, Ap Lei Chau and visitors and viewers in transit such as those on hiking tracks on Lamma Island and along the ferry routes. The resultant significance threshold of the residual visual impact in slight to moderate/adverse residual visual impact on views from Lamma Island and Hong Kong Island during operation. The overall residual visual impacts are considered acceptable.

 

Based on the above findings, the landscape and visual impacts of the proposed wind turbine are considered to be acceptable with mitigation measures. 

 

6.10                                       Environmental Monitoring and Audit

 

It is recommended that implementation and operational maintenance of proposed Landscape and Visual Mitigation Measures is included with the EM&A. The design stage EM&A will consist of auditing the detailed landscape designs. Construction and operational stage EM&A will comprise audit of the compensatory planting and planting establishment in the form of site inspection. Further details of the specific EM&A requirements are detailed in the EM&A Manual Section of this report. Summary Landscape and visual Mitigation Measures Programming, Funding, Implementation, Management and Maintenance Agents is given in Table 6.11.

         


Table 6.8         Summary of Landscape Impacts (with and without Landscape Mitigation Measures)

LCA/LR Name

·       Source of Impact

·       Resulting Disturbed Area

 

Proposed Mitigation Measures

Quality/

Sensitivity to Change

Landscape Impacts without Mitigation Measures

Landscape Impacts with Mitigation Measures

Construction Phase

Operation Phase

(1 & 10 years)

Construction Phase

Operation Phase

(1 & 10 years)

Magnitude of Change and Significance Threshold of Landscape Impact

LCA1 North Lamma Coastal Uplands - Approx. 79.4 ha

 

·       Transportation and construction activities including foundation and site formation (for details, please refer to Section 6.5.1)

·       disturbance of approximately 3,100 sq.m., 1,400 sq.m. of which would be reinstated. Resulting in a net loss of 1,700 sq.m. The whole of this is within the Project Site.

MM1 (1,400sq.m.)will ensure that new fill slope work will resemble a natural, rolling landform similar to that of adjacent topography.

MM2 (1,400 sq.m.) will compensate for the loss of vegetation through the implementation of planting of trees, shrubs and grasses as appropriate.

MM4 will ensure that the valuable soil will be re-used where possible.

The extent and location of these mitigation measures is shown on Figure 6.24.

High

Small and

Moderate / Adverse

Small and

Moderate / Adverse

Small and Moderate / Adverse

Small and Moderate / Adverse for both 1 & 10 Years

LR1 Secondary Woodland – 20.5 ha

·       Negligible impact and no disturbed area.

 

Medium

Negligible

Negligible

Negligible

Negligible

LR2 Shrubland – 49.4 ha

·       Negligible impact and no disturbed area.

 

Medium

Negligible

Negligible

Negligible

Negligible

LR3 Shrubby Grassland – 5.7 ha

·       Construction activities including foundation and site formation (for details, please refer to Section 6.5.1)

·       Disturbance of approximately 3,100 sq.m., 1,400 sq.m. of which would be reinstated. Resulting in a net loss of 1,700 sq.m. The whole of this is within the Project Site.

MM1 (1,400sq.m.)will ensure that new fill slope work will resemble a natural, rolling landform similar to that of adjacent topography.

MM2 (1,400 sq.m.) will compensate for the loss of vegetation through the implementation of planting of trees, shrubs and grasses as appropriate.

MM4 will ensure that the valuable soil will be re-used where possible.

The extent and location of these mitigation measures is shown on Figure 6.24.

Medium

Small and

Slight-Moderate/

Adverse

Small and

Slight-Moderate/

Adverse for both 1 & 10 years

Small and

Slight-Moderate/

Adverse

Small and

Slight/ Adverse for 1 year

Slight/ Beneficial for 10 years

LR4 Stream – Total 1.1km

·       Negligible impact and no disturbed area.

 

Medium

Negligible

Negligible

Negligible

Negligible

LR5 Village/Developed Area – 3.8 ha

·       Negligible impact and no disturbed area.

 

Medium

Negligible

Negligible

Negligible

Negligible

 


Table 6.9         Assessment of Visual Impacts (without Landscape and Visual Mitigation Measures)

VSR

Name (refer to Table 6.43 & 6.5 for detailed information on VSRs)

Sensitivity to Change and Visual Intrusion

 

Construction Phase

Operation Phase

 

Magnitude of Visual Change

Significance Threshold of Visual Impact

Magnitude of Visual Change

Significance Threshold of Visual Impact

VSR 1

Pak Kok San Tsuen

Medium

Intermediate

Moderate/Adverse

Intermediate

Moderate/Adverse

VSR 2

Yung Shu Wan Pier/Sha Po New Village/Sha Po Old Village/Tai Yuen Village

Medium

Intermediate

Moderate/Adverse

Intermediate

Moderate/Adverse

VSR 3

Tai Wan To/Long Tsai Tsuen

Medium

Intermediate

Moderate/Adverse

Intermediate

Moderate/Adverse

VSR 4

 

Hiking Trail on Lamma Island (Pavilion)

Low

Intermediate

Slight-Moderate/Adverse

Intermediate

Slight-Moderate/Adverse

VSR 5

Hiking Trail on Lamma Island

Low

Intermediate

Slight-Moderate/Adverse

Intermediate

Slight-Moderate/Adverse

VSR 6

Repulse Bay

Medium

Small

Slight-Moderate/Adverse

Small

Slight-Moderate/Adverse

VSR 7

Pok Fu Lam Road

High

Intermediate

Moderate-Significant/Adverse

Intermediate

Moderate-Significant/Adverse

VSR 8

The Peak

Medium

Small

Slight-Moderate/Adverse

Small

Slight-Moderate/Adverse

VSR 9

Wah Fu

High

Intermediate

Moderate-Significant/Adverse

Intermediate

Moderate-Significant/Adverse

VSR 10

Cyberport

High

Intermediate

Moderate-Significant/Adverse

Intermediate

Moderate-Significant/Adverse

VSR 11

Ap Lei Chau

 

High

Intermediate

Moderate-Significant/Adverse

Intermediate

Moderate-Significant/Adverse

VSR 12

Mount Davis

 

Medium

Small

Slight-Moderate/Adverse

Small

Slight-Moderate/Adverse

VSR 13

Chung Hom Kok

 

Medium

Small

Slight-Moderate/Adverse

Small

Slight-Moderate/Adverse

VSR 14

 

Lamma East Channel

Low

Intermediate

Slight-Moderate/Adverse

Intermediate

Slight-Moderate/Adverse

VSR 15

 

Ocean Park

Medium

Intermediate

Moderate/Adverse

Intermediate

Moderate/Adverse

VSR 16

 

Tai Ling Pavilion/adjacent cable road

High

Large

Significant /Adverse

Large

Significant

 

 


Table 6.10       Summary of Residual Visual Impacts (with Landscape and Visual Mitigation Measures)

VSR Number

WITHOUT  Recommendation Mitigation Measures

Recommended Mitigation Measures

(Refer to Section 6.7)

WITH Recommendation Mitigation Measures

Significance Threshold of Visual Impact during Construction

Significance Threshold of Visual Impact during Operation

Significance Threshold of Visual Impact during Construction

Significance Threshold of Visual Impact during Operation

YEAR 1

YEAR 10

VSR 1

Moderate/Adverse

Moderate/Adverse

MM3 and 5

Moderate/Adverse

Slight-Moderate/Adverse

Slight-Moderate/Adverse

VSR 2

Moderate/Adverse

Moderate/Adverse

MM3 and 5

Moderate/Adverse

Slight-Moderate/Adverse

Slight-Moderate/Adverse

VSR 3

Moderate/Adverse

Moderate/Adverse

MM3 and 5

Moderate/Adverse

Slight-Moderate/Adverse

Slight-Moderate/Adverse

VSR 4

 

Slight-Moderate/Adverse

Slight-Moderate/Adverse

MM3 and 5

Slight-Moderate/Adverse

Slight/Adverse

Slight/Adverse

VSR 5

 

Slight-Moderate/Adverse

Slight-Moderate/Adverse

MM3 and 5

Slight-Moderate/Adverse

Slight/Adverse

Slight/Adverse

VSR 6

Slight-Moderate/Adverse

Slight-Moderate/Adverse

MM3 and 5

Slight-Moderate/Adverse

Slight/Adverse

Slight/Adverse

VSR 7

Moderate-Significant/Adverse

Moderate-Significant/Adverse

MM3 and 5

Moderate-Significant/Adverse

Moderate/Adverse

Moderate/Adverse

VSR 8

Slight-Moderate/Adverse

Slight-Moderate/Adverse

MM3 and 5

Slight-Moderate/Adverse

Slight/Adverse

Slight/Adverse

VSR 9

Moderate-Significant/Adverse

Moderate-Significant/Adverse

MM3 and 5

Moderate-Significant/Adverse

Moderate/Adverse

Moderate/Adverse

VSR 10

Moderate-Significant/Adverse

Moderate-Significant/Adverse

MM3 and 5

Moderate-Significant/Adverse

Moderate/Adverse

Moderate/Adverse

VSR 11

Moderate-Significant/Adverse

Moderate-Significant/Adverse

MM3 and 5

Moderate-Significant/Adverse

Moderate/Adverse

Moderate/Adverse

VSR 12

Slight-Moderate/Adverse

Slight-Moderate/Adverse

MM3 and 5

Slight-Moderate/Adverse

Slight/Adverse

Slight/Adverse

VSR 13

Slight-Moderate/Adverse

Slight-Moderate/Adverse

MM3 and 5

Slight-Moderate/Adverse

Slight/Adverse

Slight/Adverse

VSR 14

 

Slight-Moderate/Adverse

Slight-Moderate/Adverse

MM3 and 5

Slight-Moderate/Adverse

Slight/Adverse

Slight/Adverse

VSR 15

 

Moderate/Adverse

Moderate/Adverse

MM3 and 5

Moderate/Adverse

Slight-Moderate/Adverse

Slight-Moderate/Adverse

VSR 16

 

Significant /Adverse

Significant

MM1, 2, 3 and 5

Significant /Adverse

Significant

Significant

 


Table 6.11       Summary Landscape and Visual Mitigation Measures Programming, Funding, Implementation, Management and Maintenance Agents

 

MM Reference

Description of Landscape Mitigation Measures

Programme Stages

·          Funding

·          Implementation Agent

1.        Management  Agency during operation

2.        Maintenance Agency during operation

D

C

O

MM1

New cut and fill slopes and other land affected by construction works would be reinstated to natural land form and topography of the natural slope as far as practical. Grading of these slopes to resemble a natural, rolling landform similar to that of adjacent topography would be carried out. Approximately 1,400 sq.m. of disturbed areas would be reinstated.

 

ü

ü

 

·          Project proponent

·          Contractor

 Project proponent

MM2

Appropriate landscape planting including trees, shrubs and grasses (approx. 1,400 sq.m.) will be provided to soften the ground level appearance of the proposed wind turbine site.

ü

ü

ü

·          Project proponent

·          Contractor

Project proponent

MM3

A light grey non-reflective colour scheme will be used to enable the proposed wind turbine to blend in well with natural surroundings and minimise the visual intrusion.

ü

ü

ü

·          Project proponent

·          Contractor

Project proponent

MM4

Existing soil resources on site from the cut slope will be re-used for backfilling at site as far as practicable to minimize the need to import or export soils.

 

ü

ü

 

·          Project proponent

·          Contractor

N/A

MM5

Selection of low rotating speed machine to minimize the visual disturbance.

ü

ü

ü

·          Project proponent

·          Contractor

Project proponent