Table 3.1 Noise Monitoring Stations during Construction Phase
Project Classification |
Identification No. |
Noise Monitoring Location |
Non-designated
Project |
BOS |
Bui O Public
School |
Non-designated
Project |
LWT2 |
Pui O Lo Wai Tsuen facing
South Lantau Road |
Non-designated
Project |
LWT3 |
Pui O Lo Wai
Tsuen facing the Pumping Station |
·
Monitoring at sensitive receivers close to the major
site activities which are likely to have noise impacts;
·
Monitoring at the noise sensitive receivers as defined in the Technical
Memorandum;
·
Assurance of minimal disturbance to the occupants during monitoring.
·
one set of measurements
between 0700 and 1900 hours on normal weekdays.
Table 3.2 Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 – 1900 hours on
normal weekdays |
When one documented
complaint is received |
75 dB(A) for residential dwellings 70 dB(A) for educational
institutes (65dB(A) during examination period) |
Table 3.3 Event / Action Plan for Construction Noise
EVENT |
ACTION |
|||
|
ET |
IC(E) |
ER |
CONTRACTOR |
Action Level |
1.
Notify IC(E) and Contractor; 2.
Carry out investigation; 3.
Report the results of investigation to the IC(E), ER and Contractor; 4.
Discuss with the Contractor and formulate remedial measures; 5.
Increase monitoring frequency to check mitigation effectiveness. |
1. Review the analysed
results submitted by the ET; 2.
Review the proposed remedial measures by the Contractor and advise
the ER accordingly; 3.
Supervise the implementation of remedial measures. |
1.
Confirm receipt of notification of failure in
writing; 2.
Notify Contractor; 3.
Require Contractor to propose remedial
measures for the analysed noise problem; 4.
Ensure remedial measures are properly
implemented. |
1. Submit noise mitigation proposals to IC(E); 2. Implement noise mitigation proposals. |
Limit Level |
1.
Identify source; 2.
Inform IC(E), ER, EPD and Contractor; 3.
Repeat measurements to confirm findings; 4.
Increase monitoring frequency; 5.
Carry out analysis of Contractor’s working procedures to determine
possible mitigation to be implemented; 6.
Inform IC(E), ER and EPD the causes and actions taken for the
exceedances; 7.
Assess effectiveness of Contractor’s remedial actions and keep IC(E),
EPD and ER informed of the results; 8.
If exceedance stops, cease additional monitoring. |
1.
Discuss amongst ER, ET, and Contractor on the potential remedial
actions; 2.
Review Contractors remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; 3.
Supervise the implementation of remedial measures. |
1.
Confirm receipt of notification of failure in
writing; 2.
Notify Contractor; 3.
Require Contractor to propose remedial
measures for the analysed noise problem; 4.
Ensure remedial measures properly
implemented; 5.
If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated. |
1.
Take immediate action to avoid further exceedance; 2.
Submit proposals for remedial actions to IC(E) within 3 working days of notification; 3.
Implement the agreed proposals; 4.
Resubmit proposals if problem still not under control; 5.
Stop the relevant portion of works as determined by the ER until the
exceedance is abated. |
·
Use of quiet equipment during raw water mains construction at Pui O,
and demolition and reprovisioning of Pui O Raw Water Pumping Station;
·
Use of movable noise barriers during laying raw
water mains at Pui O for Bui O Public School and the NSRs located less than 25m
from the raw water mains construction site.;
3.18 Regarding the educational NSR BOS, the
following mitigation measures were proposed for carrying out raw water mains
construction in vicinity of this NSR such that it would comply with noise
criterion of 65 dB(A) during examination period.
·Excavation
of Trench / Breaking up Pavement – wheeled excavator/loader fitted with
hydraulic breaker would not be operated during examination period;
·Reinstating
Road Surface during raw water mains construction – Reduction of 50% operated
On-time percentage of lorry;
Installation
of Pipes and Bedding – Reduction of number of operated mobile crane. (Use one mobile crane only)
- Only well-maintained plant
should be operated on-site and plant should be serviced regularly during the
construction programme;.
- Silencers or mufflers on construction
equipment should be utilised and should be properly maintained during the
construction programme;.
- Mobile plant, if any, should be sited as far away from NSRs as
possible;.
- Machines and plant (such as trucks) that may
be in intermittent use should be shut down between work periods or should be
throttled down to a minimum;.
- Plant known to emit noise strongly in one direction
should, wherever possible, be orientated so that the noise is directed away
from the nearby NSRs;.
- Material stockpiles and other structures
should be effectively utilised, wherever practicable, in screening noise from
on-site construction activities.