4.1
The water quality assessment in the
EIA Report for the Project identified that the key issue in terms of water
quality would be related to earthworks for the proposed extension of Siu Ho Wan
WTW, and the
proposed Siu Ho Wan Raw Water Booster Pumping Station,
and trench excavation for the mainlaying works at Pui O, and demolition works for Pui O Raw Water
Pumping Station. The EIA concluded that
the identified water quality impacts could be minimized by implementing the
recommended mitigation measures for the construction works, such as control
measures on runoff and drainage from the works areas to minimise construction
run-off and proper site management and good housekeeping practices. No unacceptable residual water quality impact
was expected. It was recommended that
regular site inspections be undertaken to inspect the construction activities
and works areas in order to ensure the recommended mitigation measures are
properly implemented.
4.2
Mitigation measures recommended for
the construction phase of the Project are summarized below and are common to both
the designated project and non-designated project elements. Specific mitigation measures applicable to the mainlaying
works at Pui O are also summarized below. The implementation schedule of the
recommended water quality mitigation measures for the
designated project and non-designated project of Siu Ho
Wan WTW Extension is presented in Appendix A.
Construction Site Run-off and Drainage
4.3
Proper site management measures should
be implemented to control site runoff and drainage, and thereby minimize
potential adverse impacts on water quality.
The site practices outlined in ProPECC PN 1/94 Construction Site
Drainage should be followed as far as practicable in order to minimize surface
runoff and the chance of erosion, and also to retain and reduce any suspended
solids prior to discharge. These
practices include the following measures:
· Before
commencing any site formation work, all sewer and drainage connections should
be sealed to prevent debris, soil, sand etc. from entering public
sewers/drains.
· Sand/silt
removal facilities such as sand traps, silt traps and sediment basins should be
provided to remove sand/silt particles from runoff to meet the requirements of
the Technical Memorandum standard under the Water Pollution Control
Ordinance. The design of silt removal
facilities should be based on the guidelines provided in ProPECC PN 1/94. All drainage facilities and erosion and
sediment control structures should be inspected monthly and maintained to
ensure proper and efficient operation at all times and particularly during
rainstorms.
· Water
pumped out from foundation excavations should be discharged into silt removal
facilities.
·
Open trench excavation for the mainlaying works at Pui
O near the stream courses should be avoided in the wet season as far as
practicable (i.e. during April to October), and the trench should be excavated
and backfilled in short sections.
· Exposed
soil surfaces should be protected by paving or fill material as soon as
possible to reduce the potential of soil erosion.
· Open
stockpiles of construction materials or construction wastes on-site of more
than 50m3 should be covered with tarpaulin or similar fabric during
rainstorms.
General Construction Activities
4.4
Debris and refuse generated on-site
should be collected, handled and disposed of properly to avoid entering the
nearby watercourses and storm water drains.
Stockpiles of cement and other construction materials should be kept
covered when not being used. In
particular, care should be exercised during the mainlaying works at Pui O at
the locations where the proposed raw water mains would be constructed over the
top of the streams.
4.5
Oils and fuels should only be used and
stored in designated areas which have pollution prevention facilities. All fuel tanks and storage areas should be
provided with locks and be sited on sealed areas, within bunds of a capacity
equal to 110% of the storage capacity of the largest tank. The bund should be drained of rainwater
after a rain event.
Sewage from Construction Workforce
4.6
Temporary sanitary facilities, such as
portable chemical toilets, should be employed on-site. A licensed contractor would be responsible
for appropriate disposal and maintenance of these facilities.