Appendix 4.3
Powered Mechanical Equipment (PME) for Different Construction Tasks During Normal Daytime Working Hours -
Mitigated Scenario (Use of Quiet Plant and Movable Noise Barrier for all NSRs except SK4 and SK6)
Sai Kung River
Site Clearence
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1),(2) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 2 103 70% 0 104
Total 106
Channel Construction
Excavation CH350-CH165
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Loader(1),(2) BS C3/97 1 105 80% 5 99
Excavator(1),(2) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 1 103 70% 0 101
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Generator(1) CNP103 1 95 100% 0 95
Drainage Pump(2) CNP 283 3 85 100% 10 80
Total 106
Channel Construction
Excavation CH165-CH000
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Loader(1),(2) BS C3/97 1 105 80% 5 99
Excavator(1),(2) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 1 103 70% 0 101
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Generator(1) CNP103 1 95 100% 0 95
Drainage Pump(2) CNP 283 3 85 100% 10 80
Total 106
Box Culvert and Bridge(3)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Power Rammer (petrol)(2) CNP 169 1 108 100% 5 103
Total 103
Earthworks
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1),(2) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 1 103 70% 0 101
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Generator(1) CNP103 1 95 100% 0 95
Drainage Pump(2) CNP 283 2 85 100% 10 78
Total 105
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 1 100 70% 0 98
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 100
Backfilling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70% 0 101
Excavator / Loader(1),(2) BS C3/97 1 105 80% 5 99
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Total 104
Max SWL for Box Culvert and Bridge 105
Backfilling / Channel lining CH420-CH000
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70% 0 101
Excavator / Loader(1),(2) BS C3/97 1 105 80% 5 99
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Concrete Lorry Mixer(1) BS C6/23 1 100 70% 0 98
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Total 105
Note:
(1) Use of Quieter Plant
(2) Use of Movable Barrier
(3) For Box Culvert and Bridge, piling, earthworks, reinforcement fixing/concret operation and backfilling will not be carried out at the same time. Thus, the maximum SWL of these activties will be used for calculation.
Appendix 4.3
Powered Mechanical Equipment (PME) for Different Construction Tasks During Normal Daytime Working Hours -
Mitigated Scenario (Use of Quiet Plant and Movable Noise Barrier for NSR PK1 and PK5)
Pak Kong River
Site Clearence
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 2 103 70% 0 104
Total 106
Channel Construction
Excavation
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Loader(1) BS C3/97 1 105 80% 5 99
Excavator(1) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 2 103 70% 0 104
Generator(1) CNP103 1 95 100% 10 85
Drainage Pump CNP 283 3 85 100% 10 80
Total 106
Box Culvert  (3)
Sheetpiling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Power Rammer (petrol)(2) CNP169 1 108 100% 5 103
Total 103
Earthworks
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 2 103 70% 0 104
Generator(1) CNP103 1 95 100% 10 85
Drainage Pump CNP 283 2 85 100% 10 78
Total 106
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 2 100 70% 0 101
Vibratory Poker(1) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter CNP 021 1 90 100% 5 85
Total 103
Backfilling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 2 103 70% 0 104
Excavator / Loader(1) BS C3/97 1 105 80% 5 99
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Total 106
Max SWL for Box Culvert and Bridge 106
Retaining Wall
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 2 100 70% 0 101
Vibratory Poker(1) BS C6/40 3 98 70% 10 91
Bar Bender / Cutter CNP 021 1 90 100% 5 85
Total 103
Backfilling / Channel lining
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 2 103 70% 0 104
Excavator / Loader(1) BS C3/97 1 105 80% 5 99
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Concrete Lorry Mixer(1) BS C6/23 1 100 70% 0 98
Vibratory Poker(1) BS C6/40 2 98 70% 10 89
Total 107
Note:
(1) Use of Quieter Plant
(2) Use of Movable Barrier
(3) For Box Culvert and Bridge, piling, earthworks, reinforcement fixing/concret operation and backfilling will not be carried out at the same time. Thus, the maximum SWL of these activties will be used for calculation.
Appendix 4.3
Powered Mechanical Equipment (PME) for Different Construction Tasks During Normal Daytime Working Hours -
Mitigated Scenario (Use of Quiet Plant and Movable Noise Barrier for all NSRs excpet HC1, HC4 and HC6)
Ho Chung Channel
Site Clearence
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1),(2) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 2 103 70% 0 104
Total 106
Channel Construction
Excavation
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Loader(1),(2) BS C3/97 1 105 80% 5 99
Excavator(1),(2) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 1 103 70% 0 101
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Generator(1) CNP103 1 95 100% 0 95
Drainage Pump(2) CNP 283 3 85 100% 10 80
Total 106
Box Culvert and Bridge  CH320(3)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Piling, large diameter bored, reverse circulation drill CNP166 1 100 100% 0 100
Total 100
Earthworks
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1),(2) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 1 103 70% 0 101
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Generator(1) CNP103 1 95 100% 0 95
Drainage Pump(2) CNP 283 2 85 100% 10 78
Total 105
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 1 100 70% 0 98
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 100
Backfilling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70% 0 101
Excavator / Loader(1),(2) BS C3/97 1 105 80% 5 99
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Total 104
Max SWL for Box Culvert and Bridge 105
Box Culvert and Bridge CH190(3)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Piling, large diameter bored, reverse circulation drill CNP166 1 100 100% 0 100
Total 100
Earthworks
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1),(2) BS C3/97 1 105 80% 5 99
Dump Truck(1) BS C9/39 1 103 70% 0 101
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Generator(1) CNP103 1 95 100% 0 95
Drainage Pump(2) CNP 283 2 85 100% 10 78
Total 105
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 1 100 70% 0 98
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 100
Backfilling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70% 0 101
Excavator / Loader(1),(2) BS C3/97 1 105 80% 5 99
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Total 104
Max SWL for Box Culvert and Bridge 105
Weir System
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 2 100 70% 0 101
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 103
Retaining Wall CH650-CH330
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 2 100 70% 0 101
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 103
Retaining Wall CH153-CH100
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 2 100 70% 0 101
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 103
Floodwall
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 2 100 70% 0 101
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 103
Backfilling / Channel lining
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70% 0 101
Excavator / Loader(1),(2) BS C3/97 1 105 80% 5 99
Vibratory Roller(1) BS C8/25 1 96 100% 0 96
Concrete Lorry Mixer(1) BS C6/23 1 100 70% 0 98
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Total 105
Pilling Work in Ho Chung CH20-CH189(4)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Piling, large diameter bored, reverse circulation drill CNP166 1 100 100% 0 100
Total 100
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 1 100 70% 0 98
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 100
Max SWL for Piling Work in Ho Chung 100
Pilling Work in Ho Chung CH350-CH450(4)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Piling, large diameter bored, reverse circulation drill CNP166 1 100 100% 0 100
Total 100
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1)(2) C7/114 1 101 70% 5 94
Concrete Lorry Mixer(1) BS C6/23 1 100 70% 0 98
Vibratory Poker(1),(2) BS C6/40 2 98 70% 10 89
Bar Bender / Cutter(2) CNP 021 1 90 100% 5 85
Total 100
Max SWL for Piling Work in Ho Chung 100
Note:
(1) Use of Quieter Plant
(2) Use of Movable Barrier
(3) For Box Culvert and Bridge, piling, earthworks, reinforcement fixing/concret operation and backfilling will not be carried out at the same time. Thus, the maximum SWL of these activties will be used for calculation.
(4) For Piling Work in Ho Chung Area, piling and reinforcement fixing/concret operation will not be carried out at the same time. Thus, the maximum SWL of these activties will be used for calculation.
Appendix 4.3
Powered Mechanical Equipment (PME) for Different Construction Tasks During Normal Daytime Working Hours -
Mitigated Scenario-(Use of Quiet Plant and Temporary Noise Barrier for SK4 and SK6)
Sai Kung River
Site Clearence
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 2 103 70%   104
Total 107
Channel Construction
Excavation CH350-CH165
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Loader(1) BS C3/97 1 105 80%   104
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 1 103 70%   101
Vibratory Roller(1) BS C8/25 1 96 100%   96
Generator(1) CNP103 1 95 100%   95
Drainage Pump CNP 283 3 85 100%   90
Total 109
Channel Construction
Excavation CH165-CH000
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Loader(1) BS C3/97 1 105 80%   104
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 1 103 70%   101
Vibratory Roller(1) BS C8/25 1 96 100%   96
Generator(1) CNP103 1 95 100%   95
Drainage Pump CNP 283 3 85 100%   90
Total 109
Box Culvert and Bridge(3)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Power Rammer (petrol) CNP 169 1 108 100%   108
Total 108
Earthworks
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 1 103 70%   101
Vibratory Roller(1) BS C8/25 1 96 100%   96
Generator(1) CNP103 1 95 100%   95
Drainage Pump CNP 283 2 85 100%   88
Total 107
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 1 100 70%   98
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 104
Backfilling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70%   101
Excavator / Loader(1) BS C3/97 1 105 80%   104
Vibratory Roller(1) BS C8/25 1 96 100%   96
Total 106
Max SWL for Box Culvert and Bridge 108
Backfilling / Channel lining CH420-CH000
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70%   101
Excavator / Loader(1) BS C3/97 1 105 80%   104
Vibratory Roller(1) BS C8/25 1 96 100%   96
Concrete Lorry Mixer(1) BS C6/23 1 100 70%   98
Vibratory Poker(1) BS C6/40 2 98 70%   99
Total 108
Note:
(1) Use of Quieter Plant
(2) Use of Movable Barrier
(3) For Box Culvert and Bridge, piling, earthworks, reinforcement fixing/concret operation and backfilling will not be carried out at the same time. Thus, the maximum SWL of these activties will be used for calculation.
Appendix 4.3
Powered Mechanical Equipment (PME) for Different Construction Tasks During Normal Daytime Working Hours -
Mitigated Scenario-(Use of Quiet Plant and Temporary Noise Barrier for PK2-4)
Pak Kong River
Site Clearence
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 2 103 70%   104
Total 107
Channel Construction
Excavation
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Loader(1) BS C3/97 1 105 80%   104
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 2 103 70%   104
Generator(1) CNP103 1 95 100%   95
Drainage Pump CNP 283 3 85 100%   90
Total 109
Box Culvert  (3)
Sheetpiling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Power Rammer, (petrol) CNP169 1 108 100%   108
Total 108
Earthworks
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 2 103 70%   104
Generator(1) CNP103 1 95 100%   95
Drainage Pump CNP 283 2 85 100%   88
Total 108
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 2 100 70%   101
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 105
Backfilling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 2 103 70%   104
Excavator / Loader(1) BS C3/97 1 105 80%   104
Vibratory Roller(1) BS C8/25 1 96 100%   96
Total 108
Max SWL for Box Culvert and Bridge 108
Retaining Wall
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 2 100 70%   101
Vibratory Poker(1) BS C6/40 3 98 70%   101
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 106
Backfilling / Channel lining
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 2 103 70%   104
Excavator / Loader(1) BS C3/97 1 105 80%   104
Vibratory Roller(1) BS C8/25 1 96 100%   96
Concrete Lorry Mixer(1) BS C6/23 1 100 70%   98
Vibratory Poker(1) BS C6/40 2 98 70%   99
Total 109
Note:
(1) Use of Quieter Plant
(2) Use of Movable Barrier
(3) For Box Culvert and Bridge, piling, earthworks, reinforcement fixing/concret operation and backfilling will not be carried out at the same time. Thus, the maximum SWL of these activties will be used for calculation.
Appendix 4.3
Powered Mechanical Equipment (PME) for Different Construction Tasks During Normal Daytime Working Hours -
Mitigated Scenario-(Use of Quiet Plant and Temporary Noise Barrier for HC1, HC4 and HC6)
Ho Chung Channel
Site Clearence
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 2 103 70%   104
Total 107
Channel Construction
Excavation
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Loader(1) BS C3/97 1 105 80%   104
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 1 103 70%   101
Vibratory Roller(1) BS C8/25 1 96 100%   96
Generator(1) CNP103 1 95 100%   95
Drainage Pump CNP 283 3 85 100%   90
Total 109
Box Culvert and Bridge  CH320(3)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Piling, large diameter bored, reverse circulation drill CNP166 1 100 100%   100
Total 100
Earthworks
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 1 103 70%   101
Vibratory Roller(1) BS C8/25 1 96 100%   96
Generator(1) CNP103 1 95 100%   95
Drainage Pump CNP 283 2 85 100%   88
Total 107
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 1 100 70%   98
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 104
Backfilling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70%   101
Excavator / Loader(1) BS C3/97 1 105 80%   104
Vibratory Roller(1) BS C8/25 1 96 100%   96
Total 106
Max SWL for Box Culvert and Bridge 107
Box Culvert and Bridge CH190(3)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Piling, large diameter bored, reverse circulation drill CNP166 1 100 100%   100
Total 100
Earthworks
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Excavator(1) BS C3/97 1 105 80%   104
Dump Truck(1) BS C9/39 1 103 70%   101
Vibratory Roller(1) BS C8/25 1 96 100%   96
Generator(1) CNP103 1 95 100%   95
Drainage Pump CNP 283 2 85 100%   88
Total 107
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 1 100 70%   98
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 104
Backfilling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70%   101
Excavator / Loader(1) BS C3/97 1 105 80%   104
Vibratory Roller(1) BS C8/25 1 96 100%   96
Total 106
Max SWL for Box Culvert and Bridge 107
Weir System
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 2 100 70%   101
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
  105
Retaining Wall CH650-CH330
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 2 100 70%   101
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 105
Retaining Wall CH153-CH100
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 2 100 70%   101
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 105
Floodwall
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 2 100 70%   101
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 105
Backfilling / Channel lining
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Dump Truck(1) BS C9/39 1 103 70%   101
Excavator / Loader(1) BS C3/97 1 105 80%   104
Vibratory Roller(1) BS C8/25 1 96 100%   96
Concrete Lorry Mixer(1) BS C6/23 1 100 70%   98
Vibratory Poker(1) BS C6/40 2 98 70%   99
Total 108
Pilling Work in Ho Chung CH20-CH189(4)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Piling, large diameter bored, reverse circulation drill CNP166 1 100 100%   100
Total 100
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 1 100 70%   98
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 104
Max SWL for Piling Work in Ho Chung 104
Pilling Work in Ho Chung CH350-CH450(4)
Piling
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Piling, large diameter bored, reverse circulation drill CNP166 1 100 100%   100
Total 100
Reinforcement Fixing / Concrete operations
Powered Mechanical Equipment TM Ref./ No. of Items SWL/Item On-time Barrier Total SWL
(PME) other Ref.   dB(A) % dB dB(A)
Crane(1) C7/114 1 101 70%   99
Concrete Lorry Mixer(1) BS C6/23 1 100 70%   98
Vibratory Poker(1) BS C6/40 2 98 70%   99
Bar Bender / Cutter CNP 021 1 90 100%   90
Total 104
Max SWL for Piling Work in Ho Chung 104
Note:
(1) Use of Quieter Plant
(2) Use of Movable Barrier
(3) For Box Culvert and Bridge, piling, earthworks, reinforcement fixing/concret operation and backfilling will not be carried out at the same time. Thus, the maximum SWL of these activties will be used for calculation.
(4) For Piling Work in Ho Chung Area, piling and reinforcement fixing/concret operation will not be carried out at the same time. Thus, the maximum SWL of these activties will be used for calculation.