Construction Programme for "Improvement Work of Ho Chung Road"
Ho Chung
Description   SWL DIST Barr* SPL 05 2006                      
            Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Drainage Improvement Work at Ho Chung                                  
Site Clearance   106 25 10 63                          
Ho Chung Channel                                    
Excavation CH650 - CH300 106 245 10 43                          
  CH300 - CH000 106 25 10 63                          
Box Culvert/Bridge (2 nos) CH320 107 228 10 45                          
  CH190 107 120 10 50                          
WSD's Weir System CH150 - CH31 106 33 10 60                          
Retaining Walls CH650 - CH330 105 220 10 43                          
  CH300 - CH100 105 60 10 55                          
Floodwall CH550 - CH20 105 15 10 67                          
Backfilling/channel lining CH671 - CH300 106 245 10 43                          
  CH300 - CH000 106 25 10 63                          
Pilling CH20 - CH189 107 13 10 70                          
  CH350 - CH450 107 270 10 43                          
                                     
Improvement Work of Ho Chung Road                                    
Excavation/ Filling / Road Work   89 12   62                          
For the Improvement Works for Ho Chung Road, the works mainly involve resurfacing from CH400 - CH650, excavation, filling and road works from CH0 to CH450. The construction works will commence from Mar 05 to Sep 06.