1                     INTRODUCTION 

1.1                 Background to the Study

1.1.1           The Land Drainage Division of the Drainage Services Department (DSD) completed the Stormwater Drainage Master Plan in Sai Kung, East Kowloon and Southern Lantau (DMP Study) and Preliminary Project Feasibility Study Report for the drainage improvements in Sai Kung in September 2000 and October 2001 respectively.

1.1.2           The DMP Study identified deficiencies and flooding problems in the existing drainage systems within the study area.  The proposed drainage improvement works, included under PWP Item No. 120CD - Drainage Improvement in Sai Kung (hereinafter called ‘the Project’), is to implement as a part of the recommendations in the DMP Study for upgradeing sections of the three existing rivers in Sai Kung, namely Sai Kung River, Pak Kong River and Ho Chung Channel as a part of the recommendations in the DMP Study.

1.1.3           According to the Project Brief, the drainage improvement works of this Project mainly comprise the following:

(a)    Construction of approximately 150m longof channel using grass concrete and masonry lined bank in Sai Kung River, approximately 280m longo channel with f three cells 3.0m x 3.0m box culvert between Sai Kung River to Sha Ha and approximately 270m longof of access road.  The section of Sai Kung River required improvement work under this Project is about 150m compared to the total length of Sai Kung River of about 1.3 km.

(b)   Construction of approximately 600m long of channel using grass concrete and masonry bank and natural bed in Pak Kong River and construction of approximately 50m longof access road.  The section required improvement work under this Project is about 600m compared to the total length of Pak Kong River of about 1.32 km.

(c)    Construction of approximately 650m longof channel using grass concrete and masonry bank and natural bed in Ho Chung Channel, construction of approximately 80m longof access road and reconstruction junction and weir arrangement adjacent to WSD Ho Chung Lowland Pumping Station. The section required improvement works under this project is about 650m compared to the total length of Ho Chung River of about 1.6km.

1.1.4           The proposed drainage improvements works have beenwere critically reviewed. Comprehensive consultation with local residents, village representatives, the Rural Committee, the District Council and green groups have beenwere also conducted. The proposed lining for the Sai Kung River and Ho Chung Channel were revised to gabion lining. In addition, the local residents in Pak Kong also requested during public consultation to reduce the scope of works at Pak Kong to only re-construction of two bottlenecks in the river and stabilisation of an existing slope adjacent to Hiram’s Highway. The detailed description of alternatives and revised scope of works are described in Section 2 of this EIA Report.

 

1.1.5           The location plan for the three rivers in Sai Kung is presenteshownd in Figure 1.1 and the individual layout plans for the sections withof improvement works at Sai Kung River, Pak Kong River and Ho Chung Channel are given in Figures 1.2 to 1.4.  A schematic cross- section layout and typical sections are presented in Figures 1.5, 1.6 and 1.7.

1.1.6           The construction workImplementation of the Project is scheduled to commence in August 2002 for the design works and for the construction work in DDecember 2005 with a view to completing all the construction works by mid 2008.

1.1.7           An application (No. ESB-088/2001) for an Environmental Impact Assessment (EIA) study brief under section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by the Applicant on 1 November 2001 with a Project Profile (No. PP-149/2001) for the captioned proposed project.

1.1.1           The proposed project is a Designated Project under Schedule 2 Part I Category I.1 (b) of the EIAO and requires an environmental permit under the EIAO for its construction and operation.  An EIA Study Brief (No. ESB-088/2001) was obtained for the preparation of this EIA.

1.1.8           The proposed project covers one non-designated project (at Sai Kung River/Sha Ha Diversion and two designated projects (at Pak Kong River and Ho Chung Channel). Since the rivers at Pak Kong and Ho Chung finally discharge to ‘Coastal Protection Areas’ which are within 300m from the nearest proposed project boundaries, they require an environmental permit under Schedule 2 Part I Category I.1 (b) of the EIAO for its construction and operation. An EIA Study Brief (No. ESB-088/2001) was obtained for the preparation of this EIA.

1.2                 Purpose and Scope of the EIA

1.2.1           The purpose of this EIA study is to access and concludeprovide information on the nature and extent of environmental impacts arising from the construction and operation of the proposed project and related activities takening place concurrently.  Theis information will contribute to decisions by the Director of Environmental Protection (DEP) on:

(i)                  the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the proposed project;

(ii)                the conditions and requirements for the detailed design, construction and operation of the proposed project to mitigate against adverse environmental consequences wherever practicable; and

(iii)               the acceptability of residual impacts after the proposed mitigation measures are implemented.

1.2.2           The objectives of the EIA study are as follows:

(i)                  to describe the proposed project and associated works together with the requirements for carrying out the proposed project;

(ii)                to identify and describe the elements of the community and environment likely to be affected by the proposed project and/or likely to cause adverse impacts to the proposed project, including both the natural and man-made environment;

(iii)               to identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potential affected uses;

(iv)              to identify any potential impacts from point and non-point pollution sources on the identified water systems and sensitive receivers during the construction and operation stages;

(v)                to identify and quantify any potential losses and damage to flora, fauna and wildlife habitats;

(vi)              to identify and quantify, where applicable, any potential landscape and visual impacts and determine the significance of impacts on sensitive receivers;

(vii)             to identify any potential impacts to the historical, archaeological and cultural resources and propose measures to mitigate these impacts;

(viii)           to propose the provision of infrastructure or mitigation measures so as to minimise pollution, environmental disturbance and nuisance during construction and operation of the proposed project;

(ix)              to identify, predict and evaluate the residual (i.e. after practicable mitigation) environmental impacts and the cumulative effects expected to arise during the construction and operation phases of the proposed project in relation to the sensitive receivers and potential affected uses;

(x)                to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the proposed project, which are necessary to mitigate these environmental impacts and reduce them to acceptable levels;

(xi)              to investigate the extent of secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification;

(xii)             to design and specify the environmental monitoring and audit requirements, if required, to ensure the implementation and the effectiveness of the environmental protection and pollution control measures adopted; and

(xiii)           to consider alternatives with a view to avoiding or minimiszing the potential environmental impacts to the sensitive uses, and to compare the environmental benefits and dis-benefits of each of the different options and to provide reasons for selecting the preferred option(s) and to describe the part environmental factors played in the selection.

1.2.3           The scope of this EIA study covers the proposed project mentioned in Section 1.1.3 above.  The EIA study addresses the likely key issues described below,; together with any key issues identified during the course of the EIA study.

(i)                  the potential impacts on the drainage, hydrology and water quality from the discharge of stormwater into the coastal waters of Hebe Haven, Sha Ha and Inner Port Shelter during construction and operation phases of the proposed project, and the potential impacts on the drainage, hydrology and water quality of the downstream of the existing Sai Kung River during the construction and operation of the future Sai Kung River & Sha Ha Diversion Culvert;

(ii)                the potential aquatic and terrestrial ecological impacts arising from the construction works, including loss of habitats, removal of vegetation and disturbance to animals of the proposed project;

(iii)               the potential landscape and visual impacts arising from the removal of vegetation and the cutting of banks and slopes of the proposed project.  In addition, appropriate landscape treatment shall also be provided to enhance the amenity value of the affected areas;

(iv)              the potential noise and dust impacts to sensitive receivers during the construction phases, in particular at areas near the school(s), village houses and other residential quarters/dwellings of the proposed project; and

(v)                the potential impacts on the cultural heritage sites, in particular Che Kung Temple in Ho Chung, Ho Chung Archaeological Site and Sha Ha Archaeological Site, if they are affected by the construction works of the proposed project.

1.3                 EIA Study Area

1.3.1           The relevant Assessment Areas for the purpose of this EIA Study, as specified in the Brief, are:, is presented below:

·         Noise impact assessment – include all areas within 300m from the Project boundary.  (If the first layer of noise sensitive receivers provides acoustic shielding to those receivers further from the site, the assessment area could be reduced accordingly).

·         Air quality impact assessment - the assessment area shall be a distance of 500m from the Project boundary.

·         Water quality impact assessment – include all areas within 500m from the Project boundary. 

·         Ecological impact assessment – the assessment area for terrestrial ecological assessment shall include all areas within 500 m distance from the site boundary of the works areas, or the area likely to be impacted by the Project.  For aquatic ecology, the assessment area shall be the same as for water quality assessment.

·         Cultural heritage impact study - all sites of cultural heritage that might be adversely affected by the impacts due to vibration associated with the construction activities of the Project.

·         Landscape and visual impact assessment – the assessment area for landscape impact assessment shall include all areas within a 500 m distance from the work limit of the proposed Project, while the assessment area for the visual impact assessment shall be defined by the visual envelope of the Project.

1.4                 Structure of the Report

1.4.1           The remainder of the report is organised as follows:

·         Section 2 describes the Project and its need, implementation programme, and addresses alternative considerations;

·         Section 3 identifies and assesses the potential air quality impacts associated with the construction of the Project, and recommends necessary mitigation measures;

·         Section 4 identifies and assesses the potential noise impacts associated with the construction of the Project, and recommends mitigation measures to comply with the established noise standards, wherever necessary;

·         Section 5 identifies and assesses the potential water quality impacts associated with the construction and operation of the Project, and recommends mitigation measures to minimise the impact;

·         Section 6 identifies and assesses the potential waste management implications associated with the construction of the Project and recommends appropriate waste handling, transportation and disposal practices;

·         Section 7 identifies and assesses the potential land contamination impacts associated with the construction of the Project;

·         Section 8 identifies and assesses the potential ecological impact associated with the construction and operation of the Project, and recommends mitigation measures to minimise the impact;

·         Section 9 identifies and assesses the potential cultural heritage impact associated with the construction and operation of the Project;

·         Section 10 identifies and assesses the potential landscape and visual impacts associated with the construction and operation of the Project;

·         Section 11 highlights the Environmental Monitoring and Audit (EM&A) requirements for the Project.  The scope and approach are presented in detail in a stand-alone EM&A Manual;

·         Section 12 concludes the findings and environmental outcomes of the EIA Study; and

·         Section 13 presents the Implementation Schedules of the various environmental issues addressed in the EIA Study.

 


1  INTRODUCTION  1-1

1.1  Background to the Study  1-1

1.2  Purpose and Scope of the EIA  1-2

1.3  EIA Study Area  1-4

1.4  Structure of the Report  1-5

1  INTRODUCTION  1-1

1.1  Background to the Study  1-1

1.2  Purpose and Scope of the EIA  1-2

1.3  EIA Study Area  1-4

1.4  Structure of the Report  1-5