·
to identify and
highlight all archaeological deposits, cultural heritage resources, built
heritage structures and cultural/ historical landscapes in the Study Area;
·
to assess direct
and indirect impacts which may result from the proposed construction activities
of this Project on these resources; and
·
to recommend
mitigation of impacts where required.
Antiquities
and Monuments Ordinance
Environmental
Impact Assessment Ordinance
Ho Chung Channel River
Pak Kong River
Sha Ha River
a.
FirstlyA desk-based
research was conducted in order to identify potential and known
archaeological sites.
b.
Secondly aAn archaeological
survey was carried out in the areas identified. The Study Area was
determined to contain the potential for archaeological remains and it was established
that a field survey had to be conducted in all areas where potential was
established and existing information was not conclusive for the purposess of the
assessment. The field survey for this
Project was sub-contracted by tender. A tender document was prepared, including
a detailed methodology, listed in Appendix
10.1. A three-step
methodology was specified in the tender document and implemented in each area
requiring field evaluation, according to the requirements of the Criteria for
Cultural Heritage Impact Assessment given by the
AMO:
1.
Field Scan
of
the natural landscape in a systematic manner, with attention to areas of
exposed soil and recent cuts.
2.
Systematic Auger
Survey
of
the identified areas which will be impacted by proposed works in order to
establish soil sequence, the presence/absence of cultural soils or deposits and
their horizontal extent.;
3.
Test Pit
Excavation
in areas of potential identified by surface scan and auger
testing; hand digging of pits measuring 2 x 2m in order to determine the
presence/absence of archaeological deposits and their stratigraphy.
c. FinallyAn an assessment
of the archaeological deposits identified in the study corridor by the field
survey was undertaken and identified impacts resulting from the works. Mitigation measures were recommended, if
needed.
· Ho Chung River study area: The study area impacts largely on the riverbanks of the Ho Chung River and the river runs through a valley deposit of large boulders within alluvial deposits. The works would impact no area of archaeological potential.
· Pak Kong River study area: The works will impact on recent river bank deposits and will not impact on areas of archaeological potential.
· Sha Ha River study area: The study area was found to have archaeological potential.
(1) It partially impacts on the known archaeological site of Sha Ha; and
(2) Partial falls within an area which is located in the immediate vicinity of the archaeological site but which has not previously been tested for its archaeological potential.
a. The
eastern section, which comprises east of Tai Mong Tsai Road, a lowland area
which lies at elevation between 4 to 7mPD;
b. The middle section, which was found to be occupied by temporary structures, fenced gardens and waterlogged fields; and
c. The western section, which is located to the west of the road and lies at an elevation between 11 and 15mPD.
Table 10.1 Survey Results of Eastern Section at
Sha Ha
Task |
Material
found |
Location |
Field scan |
One
coarse ware geometric sherd was collected during the field scan |
The sherd was collected
aside a construction site situated to the east of the eastern section |
Auger hole
tests |
A8:
tile fragment between 10 and <20cm below the surface |
Auger test was
located to the southeast corner of the study area |
10 test pits |
Pottery
belonging to from the Song to the Qing Dynasty was found intermixed with
undiagnostic and modern material. |
Mixed pottery
deposits were excavated from all test pits. |
Table 10.2 Survey
Results of Middle Section at Sha Ha
Task |
Material found |
Location |
Field
scan |
No archaeological
remains were discovered during the field scan of this area |
Middle
section at Sha Ha |
Auger
hole tests |
No
artefacts were retrieved from the auger hole tests |
East
of the river |
Table
10.3 Survey Results of Western
Section at Sha Ha
Task |
Material found |
Location |
Field scan |
No archaeological remains were discovered during the
field scan of this area; pottery dated to the late historical period were
recovered from the surfaces of the test pit locations |
The area west of the western section was a large wetland
and excluded from the evaluation |
Auger hole tests |
A31: pottery in the topsoil; A34: red tile in the topsoil |
On the southern bank close to Sha Kok Mei |
A51: pottery between 15 and 35cm below surface A55: tile between 10 and 25cm below surface A57 tile between 10 and 40cm below surface A67 tile between 10 and 35cm below surface |
On the northern bank close to Wang Kong Tsuen |
|
10 test pits |
T11-T15 Intermingled ceramics dated to historical period were
found in all but T13. |
Southern bank close to Sha Kok Mei |
T16-T20 ceramics mainly undiagnostic or dated to historical
period were found in all test pit excavations. Additional in T16 a prehistoric
adze (together with b/w ceramic) was recovered at a depth between
approximately 50 and 85cm below the surface. |
Northern bank close to Wang Kong Tsuen |
·
Building A: A shed with mud and uncut stone walls and a
modern roof. The building is in almost ruinous condition and of very low
heritage value. (Plate 20, Appendix 10.6).
·
Building B: Two-storey house with recessed central section.
Tile roof, brick walls with render. The building is in deteriorating condition
and of moderate heritage value. (Plates,
21, 22 and 23, Appendix 10.6)
·
Building C: Two-storey house, right hand façade wall is
brick, left unit façade and side walls covered in render. Cut
granite lintel and frame at entrance. Tile roof. The building is in good
condition and of significant heritage value (Plates 24 and 25, Appendix 10.6)
·
Building D: Two-storey house, brick walls covered by render.
Piers on either end of façade. Tile roof. Building is in good condition and is
of moderate heritage value (Plate 26, Appendix 10.6).
·
Buildings E
and F: One end unit and one
mid unit courtyard style terrace. Brick walls, cut granite entranceway elements
and corner stones. Decorative canopies over entrances. Tile roof. The units are
in deteriorating condition and of significant heritage value (Plates 27 and
28, Appendix 10.6).
·
Buildings G
and H: Two single storey,
single room terrace units. Shared pitched tile roof. Brick and uncut stone
walls, some render covered. The building is in ruinous condition and of very
low heritage value (Plates 29 and 30, Appendix 10.6).
·
Buildings I,
J and K: Three terraced
sheds, uncut stone and mud walls, shared pitched tile roof. The building is in
ruinous condition and of very low heritage value (Plate 31, Appendix 10.6).
·
Building L: The ancestral hall of the Chan family. Brick and
render covered walls with 3 cut granite courses on lower facade, entrance
section of façade is recessed. Decorative frieze panels on the façade and
gable. Tile roof with decorative ridge (Plates 11, 12 and 13, Appendix 10.6).
·
Building M: Reconstructed historical bridge on the Ho Chung River
located just slightly to the south west of Ho Chung Village. Modern walkway and
railing, some evidence of stone revetments. The bridge was once part of a major
historical New Territories trackway that ran from Kowloon to Sai Kung (Plate
14, Appendix 10.6).
·
Higher earth
god shrine: Modern concrete
shrine, on the northern side of Ho Chung Road. Cut stone incense holder on the
altar. Red inverted cone shaped burner to the right of the shrine (Plates
35, 36 and 37, Appendix 10.6).
·
The Che Kung
Temple, fung shui wall and second earth god shrine: This is a Grade II structure originally built
during the mid to late 16th century, according to the local
villagers. The Temple was rebuilt over the years and the current structure dates
to the Qing Dynasty. The Temple is set at the base of a steep hill slope and
there is an uncut stone retaining wall directly behind the structure. There is
an earth god shrine located on the hill slope approximately 15 m to the south
of the Temple. The shrine is of modern concrete construction and set directly
onto a hillside boulder. The Temple has strong historical and social ties to
the village of Ho Chung (Plates 2, 3, 4, 5, 6, 18, 19 and 34, Appendix 10.6).
Pak Kong River
· The Fet Kong Temple/ Nunnery: The Nunnery (also referred to as the Fat Kwong Nunnery) was founded by a Buddhist monk during the 1930’s. He built a small hut and later a villa on the site. The present structures and compound date to 1975, when the villa was demolished. The compound does not have any connections with the surrounding villages (Plates 15, 16 and 17, Appendix 10.6).
Sai Kung River
ii) Graves
iii) Cultural and Historical Landscape Features
Prediction of Impacts: Construction Phase
Evaluation of
Impacts: Construction Phase
Prediction of Impacts: Construction Phase
Ho Chung River: Construction works associated with the channelling of the
river, including proposed slopes, concrete pipes, re-providing of bridges,
pedestrian crossings, fung shui weirs, inlet channels and retaining walls.
Pak Kong River: Construction works associated with the improvement works,
including reconstruction of box culverts and stabilisation of existing river
slope by retaining walls.
Sai Kung River: Construction works associated with the channelling of the
river and Sha Ha diversion, box culverts, existing slope, ramp, retaining wall
and maintenance access.
Prediction of Impacts: Operational Phase
Ho Chung River: Alteration in the condition of currently existing river channel,
including slopes along the south side of the river, concrete pipes,
re-providing of bridges, pedestrian crossings, fung shui weirs, inlet channels,
retaining walls and access ramp.
Pak Kong River: Alteration in the condition of currently existing river
channel, including reconstruction of two bottlenecks and stabilisation of
existing river slope by retaining wall.
i) Built
Heritage Features
Ho Chung River
Table 10.4 Potential Impacts to the Identified Resources,
Ho Chung River
Resource |
Min.
Distance (Works
Boundary) |
Intervening
Landscape |
Potential
Impacts |
Structures
in Ho Chung Village (Buildings
A through L) |
10
metres |
Concrete
covered open area in front of village, fung shui wall and Ho Chung Road |
No adverse impacts will
result from the Project as the distance of the recorded resources from the
works provides an adequate buffer zone. |
Building
M: Bridge |
Within
works area |
None |
The existing bridge platform
and railings are completely modern and reprovisioning will not cause any
adverse impacts on cultural heritage grounds. The revetment consists mainly
of concrete and contains some stones from the former bridge structure. The
majority of the revetment is modern concrete. It would be directly impacted
by the works. |
Higher
earth god shrine |
Within
works area |
None |
The shrine may be damaged
during the construction works. Access to the shrine may be
restricted during construction works. |
The
Che Kung Temple, fung shui wall and second earth god shrine |
10 m |
Ho
Chung Road |
Access to the Temple and shrine
may be restricted during construction works. |
Pak Kong River
Table
10.5 Potential Impacts to the Identified Resources,
Pak Kong River
Resource |
Min.
Distance (Works
Boundary) |
Intervening
Landscape |
Potential
Impacts |
Fet Kong
Temple/ nunnery |
110 m |
Tree covered hill slope |
No adverse impacts
will result from the Project as the distance of the recorded resources from
the works provides an adequate buffer zone |
Sai Kung River
ii) Graves
iii) Cultural and Historical Landscape Features
Ho Chung River
Table 10.6 Potential Impacts to the Identified Features,
Ho Chung River
Resource |
Min. Distance to Alignment (works area) |
Intervening Landscape |
Potential Impacts |
Trees
located along the river banks |
Within works area |
N/A |
The trees are in close proximity to the works area
and may be directly impacted. |
Pak Kong River
Table 10.7
Potential Impacts to the Identified Features, Pak Kong River
Resource |
Min.
Distance to Alignment (works area) |
Intervening Landscape |
Potential
Impacts |
Mature
trees located along the river banks |
Within works area |
N/A |
If any such trees are in close proximity to the
works area, they may be directly impacted. |
Sai
Kung River
Table 10.8 Potential Impacts to the Identified
Features, Sai Kung River
Resource |
Min Distance to Alignment
(works area) |
Intervening Landscape |
Potential Impacts |
Trees
located along the river banks |
Within works area |
N/A |
The
trees are in close proximity to the works area and may be directly impacted. |
Evaluation of Impacts: Operational Phase
i) Built Heritage Features
Ho Chung River
Table 10.9 Potential Impacts to the Identified Resources,
Ho Chung River
Resource |
Min.
Distance (T |
Direction
Faced and Orientation to Alignment |
Surrounding
Landscape |
Potential
Impacts |
Structures
in Ho Chung Village (Buildings
A through L) |
Kerbing
along northern bank of the river (15 m) |
Village
structures face south, towards the river. |
Concrete
covered open area in front of village, fung shui wall and Ho Chung Road |
There would be no adverse impacts to the
village structures. The village consists of over 90% modern structures. The
channelling works will not affect the cultural setting of the village. |
Building
M: Bridge |
Footbridge
to be reprovided. |
Bridge
crosses river. |
None |
The existing bridge platform and railings
are completely modern and reprovisioning would not cause any adverse impacts
on cultural heritage grounds. |
Higher
earth god Shrine |
Installation
of concrete pipes (5m)
kerbing along northern bank of river. |
The shrine
faces south, towards the river and parallel to the proposed pipe. |
Ho
Chung Road |
There would be no adverse impacts to the
shrine. |
The
Che Kung Temple, fung shui wall and second earth god shrine |
Proposed slope on south bank of river 940
m), concrete pipes on north side of river (10 m). |
The
Temple and shrine face southwest, towards the river. |
Ho
Chung Road |
The environmental setting of the Temple
and shrine may be adversely affected by the channelling. |
Pak Kong River
Table 10.10 Potential Impacts to the Identified
Resources, Pak Kong River
Resource |
Min.
Distance ( |
Direction
Faced and Orientation to Alignment |
Surrounding Landscape |
Potential
Impacts |
The
Fet Kong Temple/ nunnery |
Improvement of two bottle necks and stabilisation of
existing river slope (110 m)
|
The nunnery compound faces east and
towards the river |
Highway, plant nurseries |
There would be no adverse impacts to the
Temple/ nunnery as the structure is of modern construction and the
channelling works would not affect the cultural setting of the compound. |
Sai
Kung River
ii) Graves
iii) Cultural and Historical Landscape Features
Ho Chung River
Table 10.11 Potential Impacts to the Identified
Features, Ho Chung River
Resource |
Minimum
Distance |
Direction
Faced and Orientation to Alignment |
Intervening
Landscape |
Potential
Impacts |
Traditional Environmental
Setting |
Next
to river |
N/A |
N/A |
The newly channelled river may cause minor
adverse aesthetic impacts to the overall cultural setting of the valley. |
Pak Kong River
Table 10.12 Potential Impacts to the Identified
Features, Pak Kong River
Resource |
Minimum
Distance |
Direction
Faced and Orientation to Alignment |
Intervening
Landscape |
Potential
Impacts |
Traditional
Environmental Setting |
Next
to river |
N/A |
N/A |
The
improvements to the two bottlenecks and construction of the retaining wall
will not cause any adverse impacts. |
Sai Kung River
Table 10.13 Potential Impacts to the Identified
Features Sai Kung River
Resource |
Minimum Distance |
Direction Faced and
Orientation to Alignment |
Intervening Landscape |
Potential Impacts |
Traditional Environmental
Setting |
Next to river |
N/A |
N/A |
The newly channelled river and upgraded
footpaths may cause minor adverse aesthetic impacts to the overall cultural
setting of the valley. |
Operational Phase
Built Heritage
Table 10.14 Mitigation Recommendations
for Resources in the Ho Chung River Area
Resource |
Impact Assessment |
Mitigation
Recommendation |
Structures
in Ho Chung Village (Buildings
A through L) |
No adverse impacts would
result from the construction works. |
No mitigation measure is recommended. |
Building
M: Bridge |
The bridge platform and
railing are completely modern and would not be adversely impacted by
reprovisioning. The revetment consists mainly of concrete and contains some
stones from the former bridge structure. It would be directly impacted by the
works. The majority of the revetment is modern concrete. |
The bridge platform and
railing would not require mitigation measures. The revetment does not
represent a historically significant architectural feature and would not
require mitigation measures. |
Higher
earth god shrine |
The shrine may be damaged
during construction works. Access to the shrine may be restricted
during construction works. |
The works are in extremely
close proximity to the shrine. ·
Protective
measures should be provided for the shrine if works are taken place in close
proximity. The protective measures should consist of the following: (1) High visibility fencing; at a
distance of one meter around the shrine. (2) Heavy duty plastic
sheeting to be placed over the exterior surfaces of the shrine for duration
of ongoing works. The contractor should ensure
that a pedestrian access path to the shrine be maintained throughout the
construction period. As the shrine is located within the works area, the path
should be marked with a temporary fence and the access route clearly marked by
signage. |
The
Che Kung Temple, fung shui wall and second earth god shrine |
Access to the Temple and
shrine may be restricted during the construction works. |
The pedestrian entrance to the
Temple from Hiram’s Highway is not within the works area and mitigation
measures would not be required. Vehicle access is from Ho Chung Road and
parking is currently available in an open lot directly to the northwest of
the Temple. If the works area infringes on the parking area, alternative
parking facilities should be made available. The contractor should provide
clear signage for directions to the Temple from Hiram’s Highway. |
Pak Kong River
Table 10.15 Mitigation Recommendations
for the Resources in the Pak Kong River Area
Resource |
Impact
Assessment |
Mitigation
Recommendation |
The
Fet Kong Temple/ nunnery |
No adverse impacts will result from the Project
as the distance of the recorded resources from the works provides an adequate
buffer zone. |
No mitigation measure is recommended. |
Sai Kung River
ii) Graves
iii) Cultural and Historical Landscape
Features
Ho Chung River
Table 10.16 Mitigation Recommendations
for the Resources in the Ho Chung River Area
Resource |
Impact
Assessment |
Mitigation
Recommendation |
Trees located along the river
banks |
The
fung shui wood is in close proximity to the works area and may be directly impacted
by the works. |
The felling of mature trees
should be avoided. If it is unavoidable, any trees that are removed from the
area should be replaced by trees of the same species. |
Pak Kong River
Table 10.17 Mitigation Recommendations
for the Resources in the Pak Kong River Area
Resource |
Impact
Assessment |
Mitigation
Recommendation |
Mature trees located along the river
banks |
|
The felling of mature trees should be
avoided. If it is unavoidable, any such trees that are removed from the area
should be replaced by trees of the same species. |
Sai Kung River
Table 10.18 Mitigation Recommendations for the Resources in
the Sai Kung River Area
Resource |
Impact
Assessment |
Mitigation
Recommendation |
Trees located along the river banks |
The fung shui wood
is in close proximity to the works area and may be directly impacted by the
works. |
The felling of mature trees should be
avoided. If it is unavoidable, any trees that are removed from the area
should be replaced by trees of the same species. |
Operational Phase
i) Built Heritage Features
Ho Chung
River
Table 10.19 Mitigation
Recommendations for the Resources in the Ho Chung River Area
Resource |
Impact Assessment |
Mitigation
Recommendation |
Structures in Ho Chung Village (Buildings
A through L) |
There would be no adverse impacts to the
village structures. |
No mitigation measure is
recommended. |
Building M: Bridge |
The existing bridge platform and railings
are completely modern and reprovisioning would not cause any adverse impacts
on cultural heritage grounds. |
No mitigation measure is
recommended. |
Higher earth god shrine |
There would be no adverse impacts to the
shrine. |
No mitigation measure is
recommended. |
The Che Kung Temple, fung shui wall and
second earth god shrine |
The southwest bank of the river in the
vicinity of the Temple is vegetated. The environmental setting of the Temple
may be adversely affected by the channelling. |
The vegetation along the south bank of
the section of the river visible from the Temple should either be retained or
if removed during the construction phase replaced by similar species of
plants. |
Pak Kong River
Table 10.20 Mitigation Recommendations for the Resources in
the Pak Kong River Area
Resource |
Impact
Assessment |
Mitigation
Recommendation |
The
Fet Kong Temple/ nunnery |
There
would be no adverse impacts to the Temple/ nunnery. |
No mitigation measure is
recommended. |
Sai Kung River
ii) Graves
Ho Chung River
Table 10.21 Mitigation Recommendations
for the Resources in the Ho Chung River Area
Resource |
Impact
Assessment |
Mitigation
Recommendation |
Traditional
Environmental Setting |
The newly channelled river and upgraded footpaths
would cause minor adverse aesthetic impacts to the overall cultural character
of the valley. |
The channel design should include
proposals for designs that would minimise any change in character to the
environmental setting, such as the incorporation of building materials for
the construction activities, that are compatible to the existing environment,
such as cobbles and gravel and the incorporation of features that would
encourage vegetation growth along the banks, such as grass concrete and natural
verges. |
Pak Kong River
Table 10.22 Mitigation
Recommendations for the Resources in the Pak Kong River Area
Resource |
Impact
Assessment |
Mitigation
Recommendation |
Traditional
Environmental Setting |
The improvement
to the two bottlenecks and construction of a retaining wall will not cause
any adverse impacts. |
No mitigation measure is
recommended. |
Sai Kung River
Table 10.23 Mitigation Recommendations
for the Resources in the Sai Kung River Area
Resource |
Impact
Assessment |
Mitigation
Recommendation |
Traditional
Environmental Setting |
The newly channelled river and
upgraded footpaths would cause minor adverse aesthetic impacts to the overall
cultural character of the valley. |
The channel design should
include proposals for designs that would minimise any change in character to
the environmental setting, such as the incorporation of building materials
for the construction activities, that are compatible to the existing
environment, such as cobbles and gravel and the incorporation of features
that would encourage vegetation growth along the banks, such as grass concrete
and natural verges. |
Archaeology
Built Heritage
·
Maintenance of
vegetation, especially mature trees, to as close to the currently existing
level as possible; and
·
The incorporation
of natural riverine material, such as cobbles or gravel, or compatible replacements,
in the channel design in order to maintain the current environment as much as
possible.
Archaeology
Built Heritage
Construction Phase
Operational Phase
Archaeology
Built Heritage
·
The
higher earth god shrine should be
provided with protective covering if works come within 1 metre of the
structure. Safe public access should be maintained throughout the construction
period;
·
For the Che Kung Temple and second earth god shrine,
a vehicle parking area should be maintained or alternative parking facilities
should be made available. Clear signage for directions to the Temple should be
provided from Hiram’s Highway;
·
Felling of mature
trees along all three rivers should be avoided. If it is unavoidable, any trees
that are removed from the area should be replaced by trees of the same species.; and
·
The channel design should also include
proposals for designs that would minimise any change in character to the
environmental setting, such as the incorporation of building materials for the
construction activities, that are compatible to the existing environment, such
as cobbles and gravel and the incorporation of features that will encourage
vegetation growth along the banks, such as grass concrete and natural verges.
10 Impact on Cultural heritage
10.2 Environmental
Legislation, Policies, Plans, Standards and Criteria
10.3 Description of the
Environment
10.6 Identification of
Environmental Impacts
10.7 Prediction and Evaluation
of Impacts
10.9 Residual Environmental
Impact
10.10 Environmental Monitoring and Audit Requirements
10 Impact on Cultural heritage
10.1 Introduction
10.2 Environmental Legislation, Policies, Plans,
Standards and Criteria
10.3 Description of the Environment
10.4 Assessment Methodology
10.5 Results of Field Survey
10.6 Identification of Environmental Impacts
10.7 Prediction and Evaluation of Impacts
10.8 Mitigation Measures
10.9 Residual Environmental Impact
10.10 Environmental Monitoring and Audit Requirements
10.11 Conclusions
Table
10.1 Survey Results of Eastern Section at Sha Ha
Table
10.2 Survey Results of Middle Section at
Sha Ha
Table
10.3 Survey Results of Western Section at
Sha Ha
Table
10.4 Potential Impacts to the Identified
Resources, Ho Chung River
Table
10.5 Potential Impacts to the Identified
Resources, Pak Kong River
Table
10.6 Potential Impacts to the Identified
Features, Ho Chung River
Table
10.7 Potential Impacts to the Identified Features,
Pak Kong River
Table
10.8 Potential Impacts to the Identified
Features, Sai Kung River
Table
10.9
Potential Impacts to the Identified Resources, Ho Chung River
Table
10.10 Potential Impacts to the Identified
Resources, Pak Kong River
Table
10.11 Potential Impacts to the Identified
Features, Ho Chung River
Table
10.12 Potential Impacts to the Identified
Features, Pak Kong River
Table
10.13 Potential Impacts to the Identified
Features Sai Kung River
Table
10.14 Mitigation Recommendations for
Resources in the Ho Chung River Area
Table
10.15 Mitigation Recommendations for
the Resources in the Pak Kong River Area
Table
10.16 Mitigation Recommendations for
the Resources in the Ho Chung River Area
Table
10.17 Mitigation Recommendations for
the Resources in the Pak Kong River Area
Table
10.18 Mitigation
Recommendations for the Resources in the Sai Kung River Area
Table
10.19 Mitigation Recommendations for
the Resources in the Ho Chung River Area
Table
10.20 Mitigation
Recommendations for the Resources in the Pak Kong River Area
Table
10.21 Mitigation Recommendations for
the Resources in the Ho Chung River Area
Table
10.22 Mitigation Recommendations for
the Resources in the Pak Kong River Area
Table
10.23 Mitigation Recommendations for
the Resources in the Sai Kung River Area