11               Environmental monitoring and Audit (EM&A) requirements

11.1             Introduction

11.1.1       This section further elaborates the requirements of environmental monitoring and audit (EM&A) for the construction and operation phases of the Project, based on the assessment results of the various environmental issues.  The objectives of carrying out EM&A for the Project include the following:

·      to provide a database against which any short or long term environmental impacts of the Project can be determined;

·      to provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;

·      to monitor the performance of the Project and the effectiveness of mitigation measures;

·      to verify the environmental impacts predicted in the EIA Study;

·      to determine project compliance with regulatory requirements, standards and government policies;

·      to take remedial action if unexpected problems or unacceptable impacts arise; and

·      to provide data to enable an environmental audit.

11.1.2       The following sections summarises the recommended EM&A requirements for the Project.  Details of the specific requirements are provided in a stand-alone EM&A Manual.

11.2             Construction Air Quality Impact

11.2.1       The air quality assessment has concluded that the TSP levels at the ASRs areare well within the dust criteria, with the implementation of recommended mitigation measuresmitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulation. Air monitoring during the construction of the Project is considered not necessary but weekly site audits are required to ensure that the dust and odour control measures are properly implemented.

11.3             Construction Noise Impact

11.3.1       Construction of the proposed drainage improvement works is likely, if unmitigated, to generate high noise levels exceeding 75 dB(A) Leq(30-min) at the NSRs identified in close proximity to the proposed work sites. By using quietsilenced equipment, movable noise barriers and temporary noise barrier, the mitigated noise levels at the NSRs due to this Project would comply with the daytime construction noise standard as set out in the EIAO-TM.

11.3.2       Noise monitoring stations are were proposed in in the vicinity of Sai Kung River, Pak Kong River and Ho Chung Channel. The construction noise level measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 min) shall be used as the monitoring parameter for the time period between 0700-1900 hours on normal weekdays. Detailed monitoring requirements are addressed in a stand-alone EM&A Manual.

11.4             Water Quality Impact

11.4.1       The water quality assessment in the EIA Report identified that the key issue in terms of water quality would be related to excavation works for during the earth channel construction of the proposed drainage improvement works.  To minimisze potential impacts on water quality of surrounding water bodies during the channel construction, less disturbing construction methods have beenwere recommended. The EIA concluded that other identified water quality impacts could be minimiszed by implementing the recommended mitigation measures for the construction works, such as control measures on runoff and drainage from the works areas to minimisze construction run-off and as well as proper site management and good housekeeping practices.

11.4.2       In order to detect any deterioration of water quality in the proposed three rivers and initiate any necessary mitigation actions, water quality monitoring and audit was proposed during the construction phase. Such d, and the details are included in a stand-alone the separate EM&A Manual.

11.5             Waste Management Implications

11.5.1       Waste management will be the contractor’s responsibility to ensure that all wastes produced during the construction of the Project are handled, stored and disposed of in accordance with the recommended good waste management practices and EPD’s regulations and requirements.  The mitigation measures recommended in Section 6 should form the basis of the site Waste Management Plan to be developed by the Contractor at the construction stage.

11.5.2       It is recommended that the waste arising generated during the construction activities should be audited periodically to determine if wastes are being managed in accordance with approved procedures and the site Waste Management Plan.  The audits should look at all aspects of waste management including waste generation, storage, recycling, transport and disposal. An appropriate audit programme is to undertake a first audit near the commencement of the construction works, and then to audit on a quarterly basis thereafter.  In addition, the routine site inspections should check the implementation of the recommended good site practices and other waste management mitigation measures.

11.6             Land Contamination

11.6.1       Based on the findings of site appraisal and desktop study, two potential contaminative workshops, including Workshop A - Wah Shing Motor Repairing Factory and Workshop B - Wing Chong Car Repair (Figure 7.3 refers) are identified partially located within the proposed alignment of Pak Kong River. Two potential contaminated zones have subsequently been confined for site investigation after Based on the findings of site appraisal and desktop study, two potential zones have beenwere confined for further investigationthe land is resumed for the Project. due to the presence of two potential contaminative workshops located within the proposed alignment of Pak Kong River, including Workshop A1 - Wah Shing Motor Repairing Factory and Workshop B1 - Wing Chong Car Repair. (Figure 7.3 refers)

11.6.2       Owing to the possibility of land-use and site condition changes, an updatinged of the preliminary contamination assessment plan ( CAP) would be required by the future Environmental Team at a later stage when full site inspection is available after the land is resumed for the Project after land resumption. Site investigation at the potential contaminated zones should should follow the requirements laid out in the approved CAP. Contamination Assessment Report (CAR) and, if necessary, Remediation Action Plan (RAP) shouldall be prepared accordingly.

11.6.3       It should be noted that the CAP, site investigation, CAR and RAP shouldall be carried out as soon as the land is resumed for the study. The Project Proponent shouldall take into account the time required for land contamination study at the identified site. Construction works mayight only be carried out at these areas until the investigation results are found acceptable. Recommended mitigation measures shouldallshould be implemented during the construction stage of the Project. Detailed are provided in a stand-alone EM&A Manual.

11.7             Ecological Impact

11.7.1       The proper implementation of mitigation measures recommended in Section 8.8 should be audited.

11.7.2       A specific monitoring programme of channels constructed to replace Sai Kung, Pak Kong and Ho Chung Rivers is recommended. The programme should provide data on the re-establishment of aquatic/riparian communities in the channels, and allow an assessment of the relative success of mitigation measures to be made. Baseline data should be collected several months before the commencement of the construction phase, with monitoring conducted 3 times a year during the construction phase, and 3 times a year for 3 years after the completion of works. Data collected should include abiotic (e.g., water quality, sediment characteristics) and biotic (e.g., avifauna, macroinvertebrate and fish populations, aquatic, emergent and riparian vegetation) parameters. Reports on the findings of each monitoring trip should be submitted to AFCD for review/discussion. A final report summarising the results of monitoring over 3 years should be prepared to serve as a reference for future projects of this kind. Monitoring should be conducted by a suitably qualified ecologist(s) appointed by the Project Proponent.

11.7.3       The newly constructed river Sai Kung River and Ho Chung River  cChannels are expected to provide a similar habitat to the rivers they would replace. It is therefore anticipated that wildlife found in the existing rivers would successfully re-colonise the new channels. However, if the post-construction phase monitoring demonstrates that re-colonisation is unsuccessful the following contingency plan should be implemented:

·        Baseline data collected prior to the construction phase should be compared with post-construction phase data. Any substantial differences in habitat characteristics (e.g., water quality, aquatic/emergent vegetation) should be noted.

 

·        The potential cause of differences between pre- and post-construction phase habitat characteristics (e.g., changes in water depth, sediment characteristics) should be identified.

 

·        Measures to further rehabilitate the habitat characteristics of river channels should be implemented (e.g., minor re-profiling of riverbed, planting of riparian/emergent/aquatic vegetation, increasing heterogeneity of substratum).

 

·        Further monitoring of abiotic and biotic parameters should be conducted to determine the relative success of the contingency habitat rehabilitation measures.

 

11.7.4       Following transplantation of the two Ehretia acuminata trees and six seedlings, and the planting of seedlings germinated from seeds collected from the two trees, regular monitoring of the trees and seedlings should be conducted to check on the health and condition of the plants. Monitoring should cover the 12-month period following transplantation and planting, and be conducted at least twice a month for the first four months after transplantation/planting, and once a month for the remaining eight months. Monitoring should be conducted by a suitably qualified botanist/horticulturalist appointed by the Project Proponent.

Baseline data collected prior to the construction phase should be compared with post-construction phase data. Any substantial differences in habitat characteristics (e.g., water quality, aquatic/emergent vegetation) should be noted.

11.1.1 

11.1.1The potential cause of differences between pre- and post-construction phase habitat characteristics (e.g., changes in water depth, sediment characteristics) should be identified.

11.1.1 

11.1.1Measures to further rehabilitate the habitat characteristics of river channels should be implemented (e.g., minor re-profiling of riverbed, planting of riparian/emergent/aquatic vegetation, increasing heterogeneity of substratum).

11.1.1 

Further monitoring of abiotic and biotic parameters should be conducted to determine the relative success of the contingency habitat rehabilitation measures.

11.1.1             Following transplantation of the two Ehretia acuminata trees and approximately six seedlings, and the planting of seedlings germinated from seeds collected from the two trees, regular monitoring of the trees and seedlings should be conducted to check on the health and condition of the plants. Monitoring should cover the 12-month period following transplantation and planting, and be conducted at least twice a month for the first four months after transplantation/planting, and once a month for the remaining eight months. Monitoring should be conducted by a suitably qualified botanist/horticulturalist appointed by the Project Proponent.The proper implementation of mitigation measures recommended in Section 8.9 should be audited.

11.1.1             A specific monitoring programme of channels constructed to replace Sai Kung, Pak Kong and Ho Chung Rivers is recommended. The programme should provide data on the re-establishment of aquatic/riparian communities in the channels, and allow an assessment of the relative success of mitigation measures to be made. Baseline data should be collected several months before the commencement of the construction phase, with monitoring conducted 3 times a year during the construction phase, and 3 times a year for 3 years after the completion of works. Data collected should include abiotic (e.g., water quality, sediment characteristics) and biotic (e.g., avifauna, macroinvertebrate and fish populations, aquatic, emergent and riparian vegetation) parameters. Reports on the findings of each monitoring trip should be submitted to AFCD for review/discussion. A final report summarising the results of monitoring over 3 years should be prepared to serve as a reference for future projects of this kind. Monitoring should be conducted by a suitably qualified ecologist(s) appointed by the Project Proponent.

11.1.1             Following transplantation of Ehretia acuminata individuals, regular monitoring of the trees and seedlings should be conducted to check on the health and condition of the plants. Monitoring should cover the 12-month period following transplantation, monitoring conducted at least twice a month for the first four months after transplantation, and once a month for the remaining eight months. Monitoring should be conducted by a suitably qualified botanist/horticulturalist appointed by the Project Proponent.

11.8             Landscape and Visual Impact

11.1.1       The newly constructed drainage improvementsannels are expected to provide comparable landscape and visual resources to the rivers they would replace through the implementation of The proposed landscape mtigationmitigation measures . However, if the post-construction phase monitoring demonstrates that landscape mitigation measures are insufficient, the following contingency plans should be implemented:

 

·       Additional tree and vegetation planting should be carried out in locations where actual visual impacts are considered to substantially exceed the predicted visual impacts.

 

·       Measures to further vegetate the river channels should be implemented to ensure gabions are concealed (e.g., minor re-profiling of riverbed, increased planting of aquatic vegetation.

 

11.8.1       Planting whichTree planting along access roads which fails should be immediately replaced.  The drainage improvement works are expected to provide comparable landscape and visual resources to the rivers they would replace through the implementation of proposed landscape mitigation measures. However, if the post-construction phase monitoring demonstrates that landscape mitigation measures are insufficient, the following contingency plans should be implemented:

 

·        Additional tree and vegetation planting should be carried out in locations where actual visual impacts are considered to substantially exceed the predicted visual impacts.

 

·        Measures to further vegetate the river channels should be implemented to ensure gabions are concealed (e.g., minor re-profiling of riverbed, increased planting of aquatic vegetation.

 

·        Tree planting along access roads which fails should be immediately replaced.  [Input will be provided as soon as possible] The construction and operation of the Project would give rise to landscape and visual impacts varying from slight to moderate and these impacts are mainly due to the loss of existing trees and surrounding vegetation, construction of a below ground level of the channel and intrusion of the new works into existing views. The proposed works would unlikely be acceptable in landscape and visual terms if mitigation measures are not incorporated.

11.9             The recommended landscape and visual mitigation measures for the drainage improvement works are described in Chapter 9. The measures are mostly design measures which have to be incorporated into the detailed planning and design of the three drainage channels. Implementation of the recommended mitigation measures shall be monitored to ensure that the measures are fully addressed and incorporated into the design and construction of the Project.   Impact on Cultural Heritage

11.9.1       No archaeological potential sites were identified within the proposed project areas. Mitigation measures have been recommended for the conservation and preservation of the potentially affected cultural heritage sites development to this Project.  measuresHowever, the ccontractor should report to the eEngineer, the Drainage Services Department DSD and the AMO immediately for any discovery of the Antiquities or supposed antiquities during the course of the construction works.

11.9.2       The Built Heritage Impact Assessment identified several resources which require mitigation measures during the construction stage and they include higher earth god shrine, Che Kung Temple in Ho Chung and mature trees along the banks of all the three rivers. For the operation phase of the Project, the Built Heritage Impact Assessment has identified that mitigation measures should be provided for the Che Kung Temple, second earth god shrine and the traditional environmental setting in Ho Chung and Sai Kung River valleys. Details are provided in a stand-alone EM&A Manual.

has are listeas follows., including;Construction Phase

Higher earth god shrine

11.1.1The works are in extremely close proximity to the shrine. , the exterior of the shrine should be provided with protective covering, by the contractor, if works are taking place within 1 meter.

11.1.1Protective measures should provided for the shrine if works are taking place in close proximity. The protective measures should consist of the following:

 

             (1) High visibility fencing; at a distance of one metrer around  the shrine.

 

           

 

 

               (2) Heavy duty plastic sheeting to be placed over the exterior surfaces of the shrine for duration of

                                ongoing works.

 

 

11.1.1The contractor should ensure that a pedestrian access path to the shrine would be maintained throughout the construction period. As the shrine is located within the works area, the path should be marked with a temporary fence and the access route clearly marked by signage.

The Che Kung Temple in Ho Chung

11.1.1The pedestrian entrance to the Ttemple from Hiram’s Highway is not within the works area and mitigation measures will not be required. Vehicle access is from Ho Chung Road and parking is currently available in an open lot directly to the northwest of the Ttemple. If the works area infringes on the parking area, alternative parking facilities should be made available.  The contractor should provide clear signage for directions to the Ttemple from Hiram’s Highway.

11.1.1 

 Mature trees along the banks of all three rivers

11.1.1The felling of mature trees should be avoided. If it is unavoidable, any trees that are removed from the area should be replaced by a trees of the same species.

11.1.1 

11.1.1 

Operation Phase

For the operation phase of the Project, the Built Heritage Impact Assessment has has identified that mitigation measures should be provided for the following resources;

The Che Kung Temple, second earth god shrine

11.1.1The vegetation along the south bank of the section of the river visible from the tTeemple should either be retained or if removed during the construction phase replaced by similar species of plants.

    Traditional eEnvironmental sSetting (Ho Chung, Pak Kong and Sai Kung River valleys)

11.1.1The channel design should include proposals for designs that will minimise any change in character to the environmental setting, such as the incorporation of building materials for the channelisation, that are compatible to the existing environment, such as cobbles and gravel and the incorporation of features that will encourage vegetation growth along the banks, such as grass concrete and natural verges..

 


11  Environmental monitoring and Audit (EM&A) requirements  11-1

11.1  Introduction  11-1

11.2  Construction Air Quality Impact  11-1

11.3  Construction Noise Impact  11-1

11.4  Water Quality Impact  11-2

11.5  Waste Management Implications  11-2

11.6  Land Contamination  11-2

11.7  Ecological Impact  11-3

11.8  Landscape and Visual Impact  11-4

11.9  Impact on Cultural Heritage  11-4

11  Environmental monitoring and Audit (EM&A) requirements  11-1

11.1  Introduction  11-1

11.2  Construction Air Quality Impact  11-1

11.3  Construction Noise Impact  11-1

11.4  Water Quality Impact  11-2

11.5  Waste Management Implications  11-2

11.6  Land Contamination  11-2

11.7  Ecological Impact  11-3

11.8  Landscape and Visual Impact  11-411-3

11.9  Impact on Cultural Heritage  11-411-311-4