· Protective measures should be provided for the shrine if works are taken place in close proximity. The protective measures should consist of the following:
1) High visibility fencing at a distance of one meter around the shrine.
2) Heavy duty plastic sheeting to be placed over the exterior surfaces of the shrine for duration of ongoing works.
Table 12.1 Summary of Public Consultation Conducted
Date |
Subject |
Outcomes |
20
Oct 03 |
Public Consultation
Meeting with VRs (Sha Ha, Sha Kok Mei, Pak Kong, Tai Chung Hau and Ho Chung) |
VRs supported the drainage
improvement project. Ho Chung VR requested a joint
site inspection. |
3
Nov 03 |
Public Consultation
Meeting with Ho Chung VR and Villagers |
Villagers requested to
retain the existing overflow weir and the general layout was revised
accordingly. |
2
Dec 03 |
Public Consultation with Tai
Chung Hau VR and Villagers |
Review the drainage
improvement works. Public objected full-scale training. |
8
Dec 03 |
Public Consultation with
Sai Kung Rural Committee |
SK Rural Committee
supported the drainage improvement project. |
17
Feb 04 |
Public Consultation with
Tai Chung Hau VR and Villagers |
The scope of works was
reduced from full-scale training to widening of two bottlenecks and
stabilization of existing slope. The public accepted the existing flooding
risks. |
24
Feb 04 |
Public Consultation with
Sai Kung District Council |
Sai Kung District Council
supported the drainage improvement project. |
30
Apr 04 |
Public Consultation with
Green Groups (Conservancy Association, Green Power, World Wild Fund) |
The channel design was advised
to be reviewed in order to include ecological friendly design. |
11
Jun 04 |
Public Consultation with
Green Groups (Conservancy Association, Green Power, World Wild Fund) |
Gabion lining, planting
pits, pools and riffles were proposed to be included into the channel
details. The existing river will remain untouched as far as possible. Green
Power and WWF welcomed the revised details. |
16
Jun 04 |
Public Consultation with
the Conservancy Association |
Gabion lining, planting pits,
pools and riffles were proposed to be included into the channel details. The
existing river will remain untouched as far as possible. Conservancy
Association welcomed the revised details. |
Table 12.2 Summary of Key
Environmental Outcomes/ Benefits
Issue |
Environmental Outcomes/Benefits |
The Project |
·
Relieve the risk of
flooding ·
Minimise economic loss ·
Minimise disruption to
everyday life especially during the wet season in Sai Kung and Ho Chung ·
The existing Pak Kong
River would be less susceptible to flooding after improving the bottlenecks.
No resumption of existing structures is required. |
Drainage Options, alignment and
Construction Methods |
The following
ecological-friendly design would be incorporated into the channel details in
order to mitigate the environmental impact.
·
Natural riverbeds and substrates would be retained as far as
practicable. New sections of riverbed would be lined with natural substrates
instead of using concrete lining. ·
In new sections of riverbeds, substrates would be arranged to mimic
the natural pool/riffle sequence of the existing river. ·
New riverbanks would largely be constructed of rock-filled gabion
rather than concrete/grasscrete. Pits would be provided in the gabion for
planting of riparian vegetation. ·
Compensatory planting provided to mitigate the loss of natural
riparian vegetation. ·
A fish-ladder would be installed in the Ho Chung River to increase the
range of fish species above and below existing weirs. |
Construction Air Quality
Impact |
·
Air Sensitive
Receivers identified nearby the construction site are protected from construction
air quality impact through implementation of mitigation measures: Sai Kung River and Sha Ha Diversion Culvert -
Sha Kok Mei, Muk Min
Shan, Tyburn House, Burlingame Garden and scattered village houses nearby the
construction site (Figure 3.1 refers) Pak Kong River -
Tai Chung Hau and
scattered village houses nearby the construction site (Figure 3.2 refers) Ho Chung Channel - Ho
Chung, Ho Chung New Village, Berkeley Bay Villa and Che Kung Temple (Figure
3.3 refers) |
Construction Noise Impact |
·
Unmitigated cumulative
construction noise levels: 65 dB(A) to 97 dB(A). ·
Affected Noise
Sensitive Receivers include: Sai Kung River and Sha Ha Diversion Culvert -
Sha Kok Mei, Muk Min Shan,
Tyburn House, Burlingame Garden and scattered village houses nearby the
construction site (Figure 4.4 refers) Pak Kong River -
Tai Chung Hau and
scattered village houses nearby the construction site (Figure 4.5 refers) Ho Chung Channel -
Ho Chung, Ho Chung New
Village, Berkeley Bay Villa and Che Kung Temple (Figure 4.6 refers) ·
All affected NSRs
would be protected from construction noise by implementation of recommended
mitigation measures, including adopting quiet construction plant; using
movable and temporary noise barriers; and implementing good site practices. ·
No cumulative noise
impacts and adverse residual noise impact would be expected. |
Water Quality Impact |
·
Minimisation
of potential impacts: working method controls
recommended e.g. excavation works carried out in the dry conditions, and
containment measures used within the channel. ·
Minimisation
of water quality deterioration: implementation of adequate mitigation
measures, proper site management and
good housekeeping practices; and appropriate treatment of sewage effluents. ·
No unacceptable
impacts on water quality would be anticipated. |
Waste Management Implication |
·
Excavated material
with suitable characteristics should be reused on-site as far as practicable
(approx. 13,700 m3). Surplus material would require disposal to a
public filling area. ·
Other
wastes generated by construction activities: general refuse from the
workforce, chemical wastes from plant and vehicle maintenance, and C&D material
from the demolition of existing structures and site clearance. ·
Surplus inert C&D
material (i.e. public fill) generated from the Project is proposed to be
disposed to the fill bank at TKO Area 137, and non-inert C&D material
(i.e. C&D waste) is proposed to be disposed to the SENT Landfill. ·
With
implementation of the recommended mitigation measures for the handling,
transportation and disposal of the identified waste, no residual waste
management impacts would be expected. |
Land Contamination |
·
Two
contaminative workshops identified with vehicle repairing activities encroach
upon the project works area of Pak Kong River which may impose health and
safety impacts to the construction workers. ·
No residual impact would
be expected if the contaminated soil (if identified any in the recommended
site investigation) would be remediated to the acceptable standards prior to
the site clearance/excavation works. |
Ecology |
·
The proposed works would provide flood protection to adjacent areas
while minimising disturbance to existing river habitats. Various mitigation
measures implemented during construction phase and the adoption of the
environmentally sensitive channel design would serve to maintain the ecology
of the existing rivers. ·
Channel design adopted at the Rivers has been considered to closely
recreate existing river habitat conditions. Impacts to existing riverbeds
would be avoided as far as practicable, thus maintaining existing ecological
conditions. Natural materials (e.g., cobbles and small boulders) would be
used to line new sections of riverbed, the riffle/pool sequence of existing
river channels would be re-created, and rock-filled gabion blocks would be
used to line new riverbanks as far as possible. ·
Measures to enhance existing ecological conditions along the rivers
have been incorporated where possible. These would include the installation
of a fish ladder at Ho Chung River to aid the passage of fish communities
above and below an existing weir, thereby extending the range of fish
communities along the whole river. ·
Following a period of establishment and re-colonisation, the newly
created channels are expected to provide a suitable habitat for aquatic
communities recorded in the existing rivers. ·
The loss of riparian vegetation would be compensated for through the
extensive tree/shrub planting along the river banks (with at least as many
trees planted as felled), planting of herbaceous riparian vegetation within
reconstructed gabion bank lining, and natural colonisation of parts of the
channel base by grasses, herbs and low shrubs. ·
Further planting of woodland tree and shrub seedlings would be
implemented within areas adjacent to the newly constructed channels. ·
Compensatory planting would make use of native plant species with
flowers/fruits attractive to wildlife. |
Landscape and Visual Impact |
·
Loss
of approximately 442 existing trees.
·
The
incorporation of landscape mitigation measures such as tree planting, the
greening of slopes and channel edges would lessen the landscape impact.
·
The
incorporation of mitigation measures such as planting within the channel,
textured concrete walling, and compensatory tree planting, will reduce
adverse visual impacts to slight adverse except for one location where visual
impact cannot be mitigated lower than moderate adverse.
·
The
presence of the drainage channels within a flat coastal landscape is not
considered to be unacceptable.
|
Impact of Cultural Heritage |
·
No adverse impacts on archaeological resources within the study areas
of the proposed drainage improvement works. ·
Minor
effects on built heritage features were found but no residual impact would be
expected with implementation of recommended mitigation measures during the
construction and operation phases.
|