Table 2.1 Details of the Concerned Project Sections
Location |
Bed width (m) |
Bank Width (m) |
Depth (m) |
|||
Existing |
Future |
Existing |
Future |
Existing |
Future |
|
Sai Kung River |
2 - 3 |
5 |
10 - 12 |
16 - 24 |
1 - 2.5 |
3 - 3.5 |
Pak Kong River (box culverts) |
7 - 13 |
16 |
12 - 13 |
16 |
3 |
3 |
Pak Kong River (Channel Widening) |
4 - 12 |
7 - 18 |
5 - 18 |
13 - 18 |
3 |
3 |
Pak Kong River (Slope stabilization) |
- |
- |
- |
- |
6 |
6 |
Ho Chung Channel |
7 - 28 |
17 - 34 |
15 - 30 |
17 - 42 |
3 - 5 |
3.8 - 5 |
(A) |
Sai
Kung River and Sha Ha Diversion Culvert |
(a) |
The concerned existing river
section would be widened and deepened. |
(b) |
Gabion lining with
planting pits is proposed along the channel. In addition, natural substrates
and rip-rap bedding would be provided at the channel bed. |
(c) |
Pools and riffles would be
constructed along the riverbed. |
|
|
(B) |
Ho Chung Channel |
(a) |
Gabion walls with planting
pits would be provided along the concerned river channel. At the channel bed,
natural substrates and rip-rap bedding would also be provided. |
(b) |
Since there are many
village houses adjacent to the concerned river section, the structural
stability of these houses is the major concern. As such, a retaining wall
would be provided behind the gabion walls. To allow movement of water between
the existing ground and river channel, drain pipes would be installed at the
retaining wall. |
(c) |
At the mid section of the
concerned channel, a bored pile wall would be constructed due to the limited
space available adjacent to existing village houses. Masonry lining and
climbers are proposed at the wall surface. |
(d) |
At the downstream area, no
deepening works would be carried out. Moreover, the riverbed adjacent to the
existing Ho Chung Road would remain untouched as far as possible. During the
construction stage, an earth bund or concrete blocks would be constructed
along the river in order to avoid the construction activities affecting the
existing riverbed. |
|
|
(C) |
Pak Kong River |
(a) |
One footbridge and one
vehicular crossing would be reconstructed to 3-cell box culverts. |
(b) |
A retaining wall would be
constructed to stabilise the existing river bank
adjacent to the Hiram’s Highway. |
(c) |
The existing riverbed
would remain untouched as far as possible. |
Table 2.2 Summary of Project Elements
Works Programme |
Dec 2005 to April 2008 |
|||
Major Elements in Sai Kung River and Sha Ha Diversion Culvert |
||||
(a) Open Trapezoidal Channel |
Length = 150m |
Depth = 3m – 3.5m |
||
|
Bank width = 16m – 24m |
Bed width = 5m |
||
|
Gabion walls with rip-rap bases and natural substrates |
|||
(b) Diversion Box Culverts |
Length = 280m |
3 cells 3m(W) x 3m(H) |
||
(c) Low Flow Pipes |
Length = 12m |
3 x 600mm diameter |
||
|
|
|
||
Major Elements in Pak Kong River |
||||
(a) Channel Widening |
Length = 100m |
Depth = 3m (approx.) |
||
|
Bank width = 13m – 18m |
Bed width = 7m – 18m |
||
|
To be reinstated by gabion blocks and concrete retaining wall |
|||
(b) Reprovision of crossings |
2 numbers (1 vehicular crossing and 1 pedestrian crossing) |
|||
|
|
|
||
Major Elements in Ho Chung Channel |
|||||
(a) Open Trapezoidal Channel |
Length = 300m |
Depth = 3.8m – 5m |
|||
|
Bank width = 17m – 42m |
Bed Width = 17m – 34m |
|||
|
Gabion walls with rip-rap bases and natural substrates |
||||
(b) Rectangular Channel |
Length = 350m |
Depth = 5m |
Width = 17m – 25m |
||
(c) Reprovision of crossings |
4 numbers (1 vehicular crossing and 3 pedestrian crossings) |
||||
(d) Floodwall |
Length = 300m |
Height = 1m |
|||
(i)
Sai
Kung River
Sai
Kung town centre and Sha Kok Mei are located at the downstream of the Sai Kung
River. Hiram’s Highway Bridge, Sai Kung
Nullah and Sai Kung Township Culvert in the downstream section of the Sai Kung
River can only provide a 1-in-10-year flood protection level to the adjacent
commercial areas in Sai Kung Township.
The inadequate capacity of the Sai Kung township culvert and Hiram’s
Highway Bridge would cause flooding in storm events greater than 1-in-10-year
event. Floodwater would spill out of the nullah and flood the roads and areas
in the town centre.
After completion of the drainage improvement
works, some of the floodwater from Sai Kung River will be diverted to Sha Ha
Diversion Box Culvert. The flooding conditions at Sai Kung Town and Sha Kok Mei
will be greatly alleviated accordingly.
A 1-in-50-year level of protection will be achieved.
The
flow to downstream of Sai Kung River will be maintained at all times via the
diversion pipes. During heavy rainstorms, the floodwater will overflow into the
Sha Ha Diversion Box Culvert without causing flooding to downstream area of Sai
Kung River and Sai Kung Town.
(ii)
Pak
Kong River
The existing nurseries and houses along the
downstream of Pak Kong Rivers are located at the north east of Tai Chung Hau.
The downstream section of the river and culvert has a protection level of less
than 1 in 5 years. Nurseries and houses
at the downstream section of the Pak Kong River are occasionally flooded mainly
due to low banks, inadequate channel size and constriction caused by existing
crossings.
DSD had conducted several consultations and
presented the current flooding hazards of Pak Kong River to the local
residents. DSD proposed the improvement of the existing river to the current
flood protection standard of 1-in-50-year. However, the widening of the river
would resume some of the houses in the proximity. The residents objected the
full-scale training works and would accept the flooding risks as a trade-off.
They also proposed DSD to remove two existing bottlenecks at Pak Kong River and
stabilise an existing riverbank. As such, the scale of works as stated in the
Project Brief was reduced as the people to be protected compromised to a higher
flooding risk in oppose to the resumption of houses.
(iii)
Ho
Chung Channel
Ho Chung is a flooding black spot identified by
DSD. The immediate downstream of the
confluence near the Ho Chung Lowland Pumping Station and Ho Chung Village is a
flooding problem area. Flooding occurs
due to the following reasons:
·
Flooding
occurs as a result of the two very fast tributaries of Ho Chung Channel joining
at a very sharp angle at the confluence.
Re-profiling the junction is required to improve the drainage condition.
·
Flooding
onto Ho Chung Road adjacent to Ho Chung Village is exacerbated by the high
level and long length of weirs alongside the Ho Chung Lowland Pumping
Station. Modifications to the weirs are
required to reduce the flooding at the Ho Chung Village.
·
Ho
Chung Channel has a flood protection level of less than 1 in 5 years at the
section alongside with the Ho Chung Road mainly due to the inadequate
size. River widening and bank raising
along the right bank of the river is therefore required. After completion of
drainage improvement works at Ho Chung Channel, the flooding situation at Luk
Mei Tsuen, Ho Chung Valley, Shui Hau, Ho Chung Village will be alleviated. A
1-in-50-year level of protection will be achieved.
Table 2.3 List of
Flooding Complaints Recorded
Ho Chung |
Date |
Location/Details |
|
09/06/1998 |
Ho Chung Road (Pak Sha Wan) |
|
28/08/1998 |
13 Ho Chung Road |
|
05/08/1999 |
13 Ho Chung Road |
|
22/08/1999 |
Ho Chung Road |
|
22/08/1999 |
17 Ho Chung Road |
|
25/08/1999 |
Hiram’s Highway (Ho Chung Road No. 23) |
|
25/08/1999 |
Hiram’s Highway (Ho Chung Road turning
area) |
|
14/04/2000 |
Ho Chung Tsuen |
|
23/04/2000 |
Hiram’s Highway (Nam Pin Wai to Ho Chung) |
|
09/06/2001 |
Ho Chung Road |
|
09/06/2001 |
Ho Chung Tsuen |
|
27/06/2001 |
Ho Chung Road |
|
27/06/2001 |
Ho Chung Tsuen |
|
19/05/2002 |
Hiram’s Highway (Ho Chung Road near pm5866) |
|
20/05/2002 |
Ho Chung Road |
|
10/08/2002 |
Ho Chung Road |
Sai Kung Town |
Date |
Location/Details |
|
02/07/1997 |
Po Tung Road |
|
19/07/1997 |
28 Fuk Man Street |
|
22/08/1997 |
Po Tung Road |
|
09/06/1998 |
Po Tung Road near Lok Yuk Kindergarden |
|
08/06/1999 |
120 Man Nin Street |
|
05/08/1999 |
120 Man Nin Street |
|
25/08/1999 |
1795 Ground Floor, Po Tung Road |
|
15/09/2000 |
Sai Kung Plaza |
|
01/09/2001 |
94A, Sai Kung Road |
|
19/06/2002 |
182 & 6 Po Tung Road |
Pak Kong |
Date |
Location/Details |
|
09/06/1998 |
Tai Chung Hau Road |
|
09/06/1998 |
Tai Chung Hau River |
|
10/06/1998 |
8B, Fung On Village (Landslide, failure
slope adjacent to a Crown Land License squatter) |
|
11/06/1998 |
49, Tai Chung Hau Village (Landslide) |
|
14/04/1999 |
Tai Chung Hau Village |
Table 2.4
Summary of Continuous Public Involvement
Date |
Subject |
20 Oct 03 |
Public Consultation Meeting with VRs (Sha
Ha, Sha Kok Mei, Pak Kong, Tai Chung Hau and Ho Chung) |
3 Nov 03 |
Public Consultation Meeting with Ho Chung
VR and Villagers |
2 Dec 03 |
Public Consultation with Tai Chung Hau VR
and Villagers |
8 Dec 03 |
Public Consultation with Sai Kung Rural
Committee |
17 Feb 04 |
Public Consultation with Tai Chung Hau VR
and Villagers |
24 Feb 04 |
Public Consultation with Sai Kung District
Council |
30 Apr 04 |
Public Consultation with Green Groups (CA, GP,
WWF, AFCD, DSD/PM and MCAL) |
11 Jun 04 |
Public Consultation with Green Groups (GP,
WWF, DSD/PM, AFCD, EPD and MCAL) |
16 Jun 04 |
Public Consultation with the Conservancy
Association |
Table 2.5 Summary of Comments/Recommendations from
the Public
Concerned Parties |
Major Comments/Recommendations |
Responses/Outcomes |
Tai Chung Hau VR and villagers |
The
proposed works at Pak Kong should be reduced from full-scale training to
widening of 2 existing bottlenecks. |
The
local residents were reminded that the flood protection level of existing Pak
Kong River could not meet the current flood protection standard during the
public consultation. Flooding may occur during heavy rainstorm. Nevertheless,
the public insisted to reduce the scope works to avoid resuming existing
lands. The scope of works was therefore reduced from full sale training to
removal of two bottlenecks at Pak Kong River. |
Ho Chung VR and Villagers |
The
existing overflow should be re-provided due to the fung shui reason. |
The
general layout was revised to re-provide the overflow weir at Ho Chung
Channel. |
Green groups |
(a) Existing riverbed should be untouched as far as possible. (b) More ecological friendly design should be included. (c) Provide fish-ladder over the weir. |
To
enhance the ecological conditions, the general layout was revised according
to the recommendation/ comments from green groups. (a) The masonry and grasscrete lining was revised to gabion lining with
planting pits. (b) Natural substrates, pools and riffles will be provided at the
riverbed. (c) The existing river will be untouched and will not be deepened as far
as possible. (d) Fish-ladder will be provided at the downstream side of the weirs. |
Option E River Training
of Existing Drainage System – Widen and/or deepen the existing rivers in order to increase the
drainage capacity of the drainage system.
Option F Vegetation
Enhancement of the catchments – Planting of vegetation in the catchment in order to reduce the surface
runoff.
Table 2.6 Comparison of the Alternative Drainage
Options
Drainage
Options |
Environmental Benefits |
Environmental Dis-benefits |
Recommendations |
Reasons & Considerations |
Maintenance of existing
rivers |
(a)
The area to be affected by proposed drainage improvement works will
be the least. (b)
The existing condition of rivers will be improved. For example, the
soil and wastes settled in the river bed will be removed. (c)
The disturbance to the ecological system and water quality in
existing rivers will be of small scale. |
No major environmental
dis-benefits are anticipated. |
Not recommended |
(a) This option can only marginally improve the capacity of the existing rivers. (b) The flood protection level provided is still very low due to the small size of existing rivers. Severe flooding in the areas will continue. (c) The aim of flooding protection cannot be achieved. The public still faces the risk of lives and economic loss during flooding. |
By-pass channel or box
culvert |
(a)
Existing rivers will not be disturbed and there is no disturbance to
the ecological system and water quality in existing rivers. |
Extensive land resumption
is required for the construction of by-pass channel or box culvert. The
public will be seriously disturbed. |
Recommend to construct
by-pass box culvert at Sha Ha to collect runoff from the Sai Kung River and
discharge to the downstream box culvert being constructed by CEDD. It is not recommended for
Ho Chung and Pak Kong. |
(a) The capacities
of the existing rivers are low and can only handle a storm of design return
period of 5 - 10 years. If the
existing rivers are kept to convey flow during rainstorm, the size of the
additional by-pass channel or box culvert is quite large, about 8m to 20m wide. (b) The
construction of by-pass channel or box culvert will require extensive land
resumption and will impose adverse impacts to other areas further away from
the flooding spots, particularly the existing village houses and building
lots at Pak Kong and Ho Chung. (c) For the Sai
Kung River, as there are abandoned agricultural lands available for the
construction of the by-pass box culvert, the diversion scheme is considered
feasible and acceptable. Besides, there are not adequate spaces for the
widening of existing drainage system in the Sai Kung town. |
Interception and Flood Storage |
(a)
Existing rivers will not be disturbed and there is no disturbance to
the ecological system and water quality in existing rivers. |
(a) Extensive land
resumption is required for construction of storage pond or interception
channel. (b)
Environmental
impacts to other areas will result.
The upstream area, which is mainly composed of dense vegetation area,
agricultural land, residential area and nurseries, will be seriously
affected. (c) |
Not recommended |
(a) It is estimated
that a detention pond of size of 200m long by 140m wide by 2m deep is
required for the Sai Kung River in order to intercept the surface runoff
during the extreme rainstorm events.
Even larger detention ponds are required for the Pak Kong River and Ho
Chung Channel. (b) There are
inadequate government lands for the implementation of this option and
large-scale land resumption is required. This large-scale land resumption will
attract great public objection, particularly at Pak Kong and Ho Chung where
land is used for village houses or intended for village development. (c) This option is
also not a cost-effective solution given the large volume of runoff needed to
be stored for which will result in resumption of large piece of land for the
construction of a large stormwater storage pond. The plan area of the pond
can be reduced by half if the depth of the pond is increased to 6m. However, a pumping station is then
required for pumping the water away after the storms. The required land resumption is still very
substantial and objection from the public cannot still be avoided. (d) This option is
therefore considered not acceptable. |
Floodwall and Pumping Station
|
(a)
Existing rivers will not be disturbed and there is no disturbance to
the ecological system and water quality in existing rivers. |
(a) Floodwall has
limited scope for improving the aesthetic. The visual impact is of concerns,
in particular, if the floodwall is high. |
Not recommended |
(a) Floodwall can
be constructed along the rivers to contain the floodwater during extreme
rainstorm events. However, the
capacities of the concerned rivers are very low and a high floodwall of
minimum 2m is needed. (b) The floodwall
protection does not provide a long-term solution because it contains
floodwater at a higher water level and causes flooding of the local drainage
systems behind the floodwalls.
Flooding in adjacent areas still persists. (c) To eliminate
the severe flooding outside the floodwalls, the floodwalls are required to be
constructed further away from the existing rivers such that an additional
flood plain flow area is allowed for conveyance of flow during extreme
rainstorms. The formation of flood plain flow area requires substantial land
resumption. In particular, there are a lot of village houses along the Pak
Kong River and Ho Chung Channel.
Resumption of these village houses is not acceptable. (d) Consideration
has been given to pumping the surface runoff in the rivers to the downstream
in order to reduce the water level and hence height of the floodwalls.
However, the peak discharges are very substantial and temporal. It is
technically impracticable to pump the peak surface runoff away without the
use of detention pond. (e) Therefore, this
option is not further considered. |
Deepening and Widening of
Existing Rivers |
The existing condition of
the rivers will be maintained by the proposed engineering works by applying
appropriate ecological friendly design. For example, gabion lining with
planting pits can enhance the ecological condition and provide river
habitats; the soil and wastes settled in the riverbed will be removed, eroded
river bank will be re-constructed. As the improvement works will be carried out
along the existing rivers, it can avoid major resumption of land and
environmental impacts in other areas. |
The existing rivers and
ecological system will be disturbed. |
River widening
and deepening ü
Sai Kung River ü
Bottlenecks at Pak Kong ü
River Upstream section of the Ho Chung Channel. River widening Downstream section of Ho
Chung Channel. |
(a) The prime
reason for flooding is that the existing rivers do not have adequate drainage
capacity. The most effective solution is to widen and deepen the existing
rivers. (b) As the river
widening works will be carried out mainly along the existing rivers, there
will be a significant reduction of land resumption as compared to other
options. (c) River widening
is more reliable and low cost option to improve the drainage of rivers compared
to the other options. (d) The channel
design could provide an ecological and aesthetical acceptable solution,
taking into account hydraulic performance and operation requirements of the
channel. (e) Appropriate
mitigation measures are required to be implemented such that the
environmental impact is kept to acceptable limit. (f) This option is
recommended and the proposed channels are lined with gabion block, and
natural bed to retain the river ecology, and to improve the aesthetic, visual
and environmental aspect of the river widening works. (g) For the Pak
Kong River, only section of the existing rivers/bottlenecks will be widened
and no deepening is required. (h) As agreed with
green groups, the riverbed of existing Ho Chung Channel should remain
untouched as far as possible. As such, the downstream section (approximately
300m) of existing Ho Chung Channel will not be deepened and the existing
riverbed will be retained. Only widening works will be carried out. |
Vegetation Enhancement |
(a) The environment
(visual and ecological etc.) of the catchment will be improved due to the
vegetation planting. (b) Existing rivers
will not be disturbed and there is no disturbance to the ecological system
and water quality in existing rivers. |
(a)
No major environmental dis-benefits are anticipated. |
Not recommended |
(a)
The upland areas of all three catchments are
already heavily vegetated, supporting extensive areas of shrubland/woodland.
Planting of additional trees in these areas would not significantly reduce
the runoff and resolve flooding problems. |
(a)
Open
concrete channel
(b)
Open
channel with natural bed and gabion walls
(c)
Rectangular
or trapezoidal drainage channel
(d)
Box
culvert
Section of
River Channel Plan of River
Channel Plan View of River Channel
|
Conceptual Design of Weir, Fish
Ladder, Pools & Riffles
Table 2.7 Summary of Alternative Construction Methods
Major Works |
Locations |
Major Activities |
Reasons & Constraints of alternative method |
Widening and deepening of existing rivers |
River widening
and deepening ü
Sai Kung River ü
Bottlenecks at Pak Kong ü
River Upstream section of the Ho Chung Channel River widening Downstream
section of Ho Chung Channel |
Earthworks
include excavation by mechanical plant; disposal of excavated soil by dump
trucks; and compacting by mechanical plant. |
It is a common
construction method. The impact to the environment is local and temporary. It
can be mitigated by appropriate measures.
It is recommended to maintain the existing river on one side and to
carry out the widening works on the other side. This can ensure the river is maintained at any time to minimise
the impact. The construction works
will be carried out at dry to minimise the adverse effect on the rivers. Working in wet inside the rivers or
temporary culverting the rivers are not recommended. |
Retaining Walls, Box Culvert and Floodwall |
Retaining
walls Bottlenecks,
inlet, outlet of rivers, as well as back side of gabion channel Box
Culverts ü
Sha Ha Diversion Box Culvert ü
Crossings at Pak Kong and Ho Chung Floodwall Northern bank
of Ho Chung Channel |
Earthworks include
excavation by mechanical plant; disposal of excavated soil by dump trucks;
and compaction by mechanical plant. |
It is a common construction
method. The impact to the environment can be mitigated by appropriate
measures. |
|
Concreting works include formwork
erection, reinforcement fixing and in-situ concreting. Piling works include
installation of steel casings, reinforcement fixing and concreting. |
The walls will
be cast in-situ and it is a common construction technique. Precast unit
for the retaining walls and box culvert is not preferable. As the size of retaining wall and box
culvert is large, it requires a large plant to handle and install the precast
units. Due to limited space, it is
not feasible to transport the precast units to site for installation. Bored piles are
used for the construction of retaining wall where space is limited. Percussion and driven piles are not
recommended due to noise generation during construction. |
|
Bridges |
Footbridges at
Ho Chung |
Piling works
for foundation include installation of steel casings, reinforcement fixing and
concreting. |
Shallow
foundation will not be adopted as it requires extensive area for the
construction of base slab. At Ho
Chung, lands are not available as the site is bounded by existing road and
village houses. Using bored
piles for the bridge foundation is a common construction technique.
Percussion and driven piles are not recommended due to noise generation
during construction. |
Footbridges at
Ho Chung |
Bridge
structure works include the construction of falsework, formwork erection, reinforcement
fixing and concreting. |
Similar to
retaining wall construction, there is inadequate working space for
transporting, handling and installation of precast unit. In-situ
concreting is more suitable. |
(i)
Flooding
will persist in Ho Chung and in the downstream section of Pak Kong River during
big storm events. Sai Kung town centre
will be subject to flooding during heavy rainstorms and high tides.
(ii)
Development
in Sai Kung, Pak Kong and Ho Chung will be hindered. The existing drainage system
will not provide the flood protection standard required for future
development. Further development will
increase the frequency, severity and extent of flooding.
(iii)
Damage
to properties, blockage of roads and accesses, nuisance to the public and risk to
lives will remain.
Table
2.8 Concurrent Projects Likely
to Cause Cumulative Impact
Likely
Concurrent Projects in the Vicinity |
Construction
Programme |
Potential
Cumulative impact |
(i) Proposed Sai Kung River and Sha Ha
Diversion Box Culvert |
Dec 2005 to Apr 2008 |
-- |
Dualling of Hiram’s Highway from Marina Cove
to Sai Kung Town (HyD) |
N/A |
The project implementation is currently under
review. |
Contract No. CV/2001/15 “Roads and Drains in Sai Kung Area 4”(CEDD) |
Sep 2002 to Dec 2004 |
Not expected (completed before this Project) |
(ii) Proposed Pak Kong River |
Dec 2005 to Apr 2008 |
-- |
RPIS Project No. SK015 – Improvement to Access Road at Ta Ho Tun and
Footpath of Hiram’s Highway, Sai Kung (HyD) |
Completed in end 2002 |
Not expected (completed before this Project) |
Dualling of Hiram’s Highway from Marina Cove
to Sai Kung Town (HyD) |
N/A |
The project implementation is currently under
review. |
Proposed Junction Improvement at Hiram’s Highway/Tai Chung Hau Road/New
Ta Ho Tun Road (HyD) |
Sep 2003 to Mid 2004 |
Not expected (completed before this Project) |
Design & Construction for the Eastern Transmission Pipeline along
Hiram’s Highway (HKCG) |
Jun 2002 to 2005 |
Not expected (completed before this Project) |
(iii) Proposed Ho Chung Channel |
Dec 2005 to Apr 2008 |
-- |
RPIS
Project No. SK069 – Improvement of Ho Chung Road (HyD) |
Mar 2005 |
Expected and to be addressed in this Report. |
Dualling of Hiram’s Highway between Clear Water Bay Road and Marina
Cove and Improvement to Local Access to Ho Chung (HyD) |
N/A |
The project implementation is currently under
review. |
Design & Construction for the Eastern Transmission Pipeline along
Hiram’s Highway (HKCG) |
Jun 2003 to 2005 |
Not expected (completed before this Project) |