7.1.1
This section reviews the potential
environmental issues associated with land contamination for all land lots/sites
within the study boundary due to their past or present land uses. Where
appropriate, areas which are suspected as potential contamination sites and
would be identified for further assessment in the subsequent construction phase
of the proposed drainage improvement works in Sai Kung River, Pak Kong River
and Ho Chung Channel.
7.2.1
The Practice Note for Professional
Persons ProPECC PN3/94 “Contaminated Land Assessment and Remediation” and
“Guidance Notes for Investigation and Remediation of Contaminated Sites of
Petrol Filling Stations, Boatyards, and Car Repair / Dismantling Workshops”
issued by the Environmental Protection Department (EPD) provide guidance on
land contamination assessment. In Hong
Kong, the “Dutch List” is generally referenced as the criteria for assessing
soil and groundwater contamination under the ProPECC PN3/94.
7.2.2
Provision for consideration of
contamination issues is also given in the Section 3 “Potential Contaminated
Land Issues” of Annex 19 “Guidelines for Assessment of Impact on Sites
of Cultural Heritage and Other Impacts” of the Technical Memorandum on
Environmental Impact Assessment Process (EIAO-TM).
7.2.3
The following legislation, documents
and guidelines also cover or have some bearing upon land contamination and the
handling, treatment and disposal of contaminated waste in Hong Kong.
·
Water Pollution Control Ordinance
(WPCO);
·
Waste Disposal Ordinance (Cap. 354);
·
Waste Disposal (Chemical Waste)
(General) Regulation (Cap. 354); and
·
Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes, Environmental Protection Department
(1992).
7.3.1
The assessment methodology was
developed in accordance with the Practice Note ProPECC PN3/94 “Contaminated
Land Assessment and Remediation” and “Guidance Notes for Investigation
and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards,
and Car Repair / Dismantling Workshops” issued by EPD. Under the ProPECC PN
3/94 and the Guidance Notes, evaluation of the following issues should be made
before any construction works being carried out in the subject site. They
include:
i)
Preliminary review of the present and
historical land uses to evaluate the likely level of potential for
soil/groundwater contamination;
ii)
Identification of the nature of
potential contaminants;
iii)
Evaluation of potential environmental
impacts, risks, hazards or health concerns arising from the proposed
river/channel improvement works; and
iv)
Overview of possible remediation and mitigation
measures for the site, where necessary, in order to remedy the site to the
satisfaction of the EPD.
7.3.2
During the course of the study, the
following tasks with respect to land contamination assessment have been
undertaken:
·
Desktop study (including review of
Hong Kong Government Survey Maps, Hong Kong Geological Survey Maps (Series:
HGM20) – Sheets no. 7, 8 and 11 and The Geochemical Atlas of Hong Kong by R J Sewall, 1999).
·
Review of historical aerial
photographs taken along the three rivers
·
Acquisition of relevant information
from government departments
·
Site inspection
Baseline
Condition
7.4.1
As detailed in Sections 1 and 2,
the principle works of this Project are improvement of the three watercourses
in order to prevent flooding problems in Sai Kung Town Centre, Pak Kong and Ho
Chung. The existing Sai Kung River flows through Sai Kung town centre in a box
culvert before entering Inner Port Shelter. The Pak Kong River currently runs
alongside Hiram’s Highway before entering a road crossing to Hebe Haven. The Ho
Chung Channel runs along Ho Chung Road before passing under Hiram’s Highway to
Hebe Haven in the South. Based on reviewing the contemporary and historic Hong
Kong Government Survey Maps and site appraisal carried out in November 2002,
the surrounding areas of the three rivers are mostly undeveloped sites, either
rural in nature with mainly agricultural lands or villages/squatter houses
scattered on the nearby lands. A number of vehicle repairing/maintenance workshops
were also identified close to the Pak Kong River. As potential contaminants
including heavy metals, petroleum oils, acids and solvents could be released to
the environment due to localised spillages/leakages from the above mentioned
activities, these land uses may give rise to potential concerns for land
contamination and warrant this contaminated land study.
Land Zoning
7.4.2
The
Pak Kong & Sha Kok Mei Outline Zoning Plan (OZP No.
S/SK-PK/7) gazetted in February 2004 was reviewed and the OZP showed that the
proposed land uses along the study boundary of Sai Kung River and Pak Kong
River are mostly zoned for ‘Recreation’, ‘Agricultural’, ‘Village Type
Development’ and ‘Green Belt’. For the Ho Chung Channel, the information
obtained from the Ho
Chung Outline Zoning Plan (OZP No. S/SK-HC/6) gazetted
in July 2004 also revealed that the lands adjacent to the Ho Chung Channel are
zoned for Green Belt, agricultural and Village Type Development. As observed
from the site visits, vehicle repair workshops which encroach upon the proposed
Pak Kong River alignment are located at the areas currently zoned for
‘Recreation’ and ‘Green Belt’.
Site
Geology and Superficial Geological Deposits
7.4.3
According to the Hong Kong Geological
Survey Map (Series: HGM20) – Sheets No. 7, 8 and 11 on the solid geology across
the Sai Kung area, the inferred solid geology of the subject area is mainly
identified to be undivided and coarse ash crystal tuff of Tai Mo Shan
Formation. Not much variation is identified for the superficial geology beneath
the three rivers. A layer of alluvium, which consists of well-sorted to
semi-sorted clay/slit, sand and gravel from the Pleistocene and Holocene eras
of the Quaternary age is shown underlying the three rivers and its surrounding
areas. The subsurface geology is important in connection to surface
contamination. Any contaminants, especially those associated with petroleum
hydrocarbon products such as gasoline, fuels and oils, may enter the soil through spills and easily migrate through the
underground medium if the soil matrix consists of high content of sand and
gravel. For the subject site with alluvial deposit, the nature is generally
with low permeability and the ability of potential contaminant migration through
this horizon would be relatively low.
Site History
7.4.4
A review of historical aerial
photographs (Table 7.1) covering the study area has been
undertaken. The aim of this review is
to evaluate land-use changes and development of specific properties closely along
Sai Kung River, Pak Kong River and Ho Chung Channel.
Table 7.1
Historical Aerial Photographs Reviewed
Year
|
Photograph References
|
Height (feet)
|
1976
|
12309,
12331, 12898
|
6000,
6000, 4000
|
1979
|
25642,
25729, 25678
|
2500,
2500, 2500
|
1981
|
39518,
36524, 37331
|
2500,
2500, 4000
|
1984
|
57430,
57427, 57424
|
4000,
4000, 4000
|
1986
|
A05250,
A04162, A05256
|
3800,
2000, 3800
|
1989
|
A16889,
A16901, A16357
|
4000,
1500, 2000
|
1991
|
A25909,
A26761, A25732
|
2000,
2000, 2500
|
1993
|
A35506,
A35501, A35779
|
4000,
4000, 1500
|
1995
|
CN10846,
CN 10934, CN10966
|
2500,
2500, 2500
|
1999
|
CN23106,
CN23112, CN23115
|
2800,
4000, 2500
|
2001
|
CNW32821,
CW32602, CW30728
|
4000,
1400, 1500
|
Source
of historical aerial photographs:
Survey and Mapping Office, Lands Department.
7.4.5
As revealed from the historical aerial
photographs from 1976 to 2001, most of the areas adjacent to the Sai Kung River
were agricultural lands. Village houses adjacent to the proposed river boundary
were built in late 1970s and since then no significant change was observed
along the Sai Kung River. For Ho Chung Channel, a large number of village
houses and the ATV Studio which is currently still in operation were found along
the Channel. Apart from some new village houses be recently built opposite to
the Ho Chung Village as well as the road construction works opposite to the Sai
Kung Central Primary School in 2001, neither major development nor
contamination-related industry was found along the Ho Chung Channel in the
recent decade. For Pak Kong River, few locations have been identified to have
potential contaminating sources during the site visits as mentioned above.
7.4.6
The aerial photographs further confirm
that there are two locations, namely Sites A and B, were noticed to have land
use changes leading to potential land contamination implication. The locations
are shown in Figure 7.1. The findings of the historical aerial
photograph review in respect of Pak Kong River are summarised as follows:
Year 1976
·
Mainly farmland and open spaces were
observed along the Pak Kong River.
Year 1981
·
Some small houses were built at the
location of Site A but exact activities being carried out at the site could not
be recognised due to the small resolution of the photograph.
Years 1984 and 1986
·
No significant change was observed.
Year 1989
·
Workshops at both Sites A and B were
developed.
Year 1993
·
No significant change in terms of land
use was noticed at both sites since 1993.
7.4.7
As shown
in the above records, land-use changes were initiated since late 1980s. Most of
the obvious changes were from vegetated lands to car repairing workshops of
which might cause potential land contamination although the scale may be
generally localised. Historical records of chemical spillage and registration
of Chemical Waste Producers (CWP) within the study area were sought by sending
inquiry letters to several Government Departments. Details
are shown in the following section.
Environmental
Protection Department (EPD)
7.4.8
Inquiry
letter has been sent to EPD to acquire information about the registered
Chemical Waste Producer(s) within the Study Area and records of accidents of
spill/leakage of chemicals within the Study Area.
7.4.9
According
to the information provided by EPD, there were 4, 21 and 25
registered/de-registered Chemical Waste Producers (CWPs) found near Sai Kung
River, Pak Kok River and Ho Chung Channel respectively. However, there were no
records of chemical spill/leakage within the Study Area.
7.4.10 Most of the CWPs on the list were
vehicle repair workshops. As noted,
some of the CWPs were in a considerable distance from the project boundary and
some were either not found at the address provided by EPD or already
surrendered, only one of which in proximity to the project worksite likely had
a potential for contaminated land concerns. Details of the CWP are tabulated in
Table 7.2. It should be noted that this CWP had already been identified
as potential contaminated site during the site visits. Location and relevant
photographs are shown in Figure 7.2.
Table 7.2 Details
of Chemical Waste Producer (CWP) Within the Study Area
Nearby River
|
CWP
|
Business
|
Status
|
Pak
Kong River
|
Wah
Shing Motor Repair Factory
|
Repairing
of Motor Vehicle
|
Existing
CWP
|
Fire Services Department (FSD)
7.4.11
Inquiry letter had also been sent to FSD
to acquire information about current and past registration of dangerous goods
stored within the Study Area and records of spillage/leakage of dangerous goods
stored within the Study Area. According to the information provided by the FSD,
there were no available records of application for storage of dangerous goods
nor any known spillage/leakage of dangerous goods within the Study Area.
Lands Department (LD)
7.4.12
Inquiry letter had been sent to Lands
Department to acquire information about the current and past land uses within
the Study Area. Response from LD indicated that there was no available
information regarding land uses within the Study Area.
7.5.1
Based on the information obtained from
the site visits conducted in November 2002, activities related to land
contamination were not identified in or near to Sai Kung River and Ho Chung
Channel. However, there were two potential contaminated workshops, mainly
vehicle repairing workshops, identified near Pak Kong River. Site inspection,
photo-documentation and interview with the site personnel were carried out as
far as possible. Details of the two potential contaminated workshops are listed
in Table 7.3 and their locations are illustrated in Figure 7.2.
Table 7.3 Potentially
Contaminative Land Uses Near Proposed Work Boundary of Pak Kong River
Workshop Reference Number
|
Name of Company
|
Nature of Trade
|
Workshop
- A
|
- Wah Shing Motor Car
Repairing Factory
|
Repairing of lorry engines
|
Workshop
– B
|
- Wing Chong Car Repair
|
Repairing of car engines
|
Workshop - A: Wah Shing Motor
Repairing Factory
·
This motor repair workshop has been
operated for more than 10 years as revealed by the site personnel and historical
aerial photographs. It located at the area adjacent to the riverbank of Pak
Kong River. As observed during the site visits, activities of engine repairing
and maintenance for heavy goods vehicles had been carried out in the site.
Physical evidence of contamination was identified as heavy oil stains were
noted on the paved ground. This might be caused by the local spillage of engine
oils/lubricating oils during repairing or direct leakage from the parking
vehicles. A lot of equipment for motor maintenance was observed inside the
working hut of the workshop. This workshop has been registered as a Chemical
Waste Producer with EPD. As told by the site personnel, the chemical waste
would be stored in a 220 litre lid drum inside a chemical waste storing room
with size of approximately 1.5m x 1.5m. Based on the nature of the industry and
the general site observation, further investigation for contaminated land is
recommended for this workshop.
Workshop – B: Wing Chong Car Repair
·
As shown in the review of historical
aerial photographs, this car repair workshop being relatively smaller in scale
than the Wah Shing Motor Repairing Factory has been operated for about 14
years. It located just next to the Pak Kong River with land location number of
Lot DD 217 989 6A. The business nature of this workshop is engine repairing for
private cars and mini-vans. During the site inspection, oil stains were
observed at a few locations and the ground was not well paved. Interview had
been carried out with the site personnel and they expressed that chemical waste
generated from this site would be usually transferred to the chemical waste
storage drum of Wah Shing Motor Car Repair Factory. Due to the nature of
business and its long history of operation, further investigation for
contaminated land is also recommended for this workshop.
7.6.1
The proposed drainage improvement
works at Pak Kong River include (1) reconstruction of one footbridge and one vehicular
crossing to 3-cell box culverts, and (2) construction of a retaining wall for
the purpose of stabilizing the existing riverbank adjacent to the Hiram’s
Highway. In regard to this, site clearance, excavation, construction of
concrete structures would be carried out within the defined site boundary.
7.6.2
As aforementioned, the findings of the
site inspection and desktop study indicated that there are two potential
contaminative workshops located within the proposed site boundary of Pak Kong
River. Activities mostly car repairing/servicing were undertaken by such
workshops and stains were generally observed on the ground of the sites.
Potential sensitive receivers which may come into contact with excavated
contaminated soils are mainly construction workers via the principal exposure
routes of (1) inhalation of dust, (2) direct ingestion through poor hygiene
practices, such as eating or drinking on site as well as (3) dermal contact
with the contaminated materials. As there may have potential adverse effects on
the health and safety of workers during construction of Project, a detailed
site investigation would be recommended for those areas falling within the
Project boundary in order to assess the degree and extent of potential land
contamination. Contaminated soil should be remediated before construction work
could be started at the concerned areas.
7.6.3
As shown in Figure 7.2, there
are two workshops, including Workshop A - Wah Shing Motor Repairing Factory
and Workshop B - Wing Chong Car Repair, with part of the site areas
encroaching upon the proposed drainage work area of Pak Kong River. The major
concern associated with these workshops would be of lube oil, engine oil and/or
solvents that could be inaptly be disposed of by workers or leaked from
vehicles causing contamination in the site and its vicinity. According to EPD’s
“Guidance Notes for Investigation and Remediation of Contaminated Sites of
Petrol Filling Stations, Boatyards, and Car Repair / Dismantling Workshops”
and “ProPECC PN3/94”, site contamination assessment and remediation,
where necessary, are required to avoid or minimise any risks or hazards
associated with the sites prior to any construction works taken place. In
regard to this, two potential zones, namely SI-1 and SI-2, are confined for conducting
site contamination investigation, as shown in Figure 7.3.
7.6.4
Based on the requirement stated in
EPD’s “Guidance Notes for Investigation and Remediation of Contaminated
Sites of Petrol Filling Stations, Boatyards”, a full-scale site
investigation is required as both workshops A and B have been operated for more
than 5 years. Due to inaccessibility of the workshops for full site inspection,
location of contamination hotspots could not be accurately determined at this
stage. Instead, only approximate number of sampling locations required for the
Areas SI-1 and SI-2 are estimated based on the confined potential areas
recommended for carrying out site investigation. Table 7.4 shows the preliminary
Contamination Assessment Plan (CAP) which summarises the identified activities,
possible contaminants, number of sampling locations and testing parameters
suggested for further investigation.
7.7.1
As illustrated above, there are some
land uses in the vicinity of the proposed work limit of Pak Kong River that
could feasibly result in land contamination. Considering the nature of business
and the general site practice of the workshops, two potentially contaminative
zones have been identified at which car repairing/servicing workshops impinging
upon the proposed alignment of the River was found. As observed during the site
visits, area-wide land contamination would not be likely in terms of the
appearance of current site condition and scale of the business. Localised
contamination due to the potential incidence of spillage/leaking from
maintenance and dismantling of equipment within the study boundary would be
more likely encountered. As a whole, the overall contamination concerns would
be limited to the works area within the project boundary and significant impact
would not be anticipated taken into account the scale of the workshops.
Table 7.4 Preliminary Contamination Assessment Plan
for Further Investigation of Identified Potential Sites
Potential Site
|
Potential
Contaminating Area for SI
|
Workshops
within the Potential Contaminating Areas for SI
|
Current
Activities/Uses
|
Potential
Contaminants
|
Size/Area of
Concern to This Project
|
Proposed no. of
Sampling Points*
|
Parameters to be
Analysed*
|
Remarks
|
Site A
(Pak Kong River)
|
SI – 1
|
Workshop -A
Wah Shing Motor Car Repairing Factory
|
Long vehicle parking and maintenance
|
Lubricants, petroleum products, fuels,
battery acid and cleansing solvents.
|
200 m2
|
2
|
BTEX, TPH,
organic solvents, lead, copper, chromium, zinc & PAHs.
|
To be reconfirmed by the environmental team at the construction
stage.
.
|
Site B
(Pak Kong River)
|
SI – 2
|
Workshop -B
Wing Cheong Car Repair
|
Repairing of private vehicles and mini-vans in majority
|
Lubricants, petroleum products, fuels,
battery acid and cleansing solvents.
|
177 m2
|
2
|
BTEX, TPH,
organic solvents, lead copper, chromium, zinc & PAHs.
|
Notes: * Subject
to further confirmation/review when preparing the CAP, and to be endorsed by
EPD before the sampling work.
TPH: Total petroleum hydrocarbons: C6 to C36.
BTEX: Benzene, toluene, ethlybenzene and xylenes
PAHs: Polycyclic aromatic hydrocarbons
7.7.2
Due to the possibility of land-use
changes and variable future site conditions caused by different factors such as
weather and business operation, a full site inspection is required by the future
Environmental Team to review the validity of the preliminary CAP and define the
exact sampling locations and sampling parameters for further site
investigation. The inspection should be undertaken immediately after the site
was resumed for this project. An updated CAP shall then be prepared after the
site inspection in accordance with EPD’s “Guidance Notes for Investigation
and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards,
and Car Repair/Dismantling Workshops” and endorsed by EPD prior to
commencement of the site investigation.
7.7.3
Upon receipt of EPD’s approval on the
updated CAP, the actual site investigation for land contamination impact
assessment shall be conducted accordingly before any construction work started
at the identified contaminated sites. Soil and groundwater samples shall be
collected and tested as described in the approved CAP to provide site-specific
information for the assessment. A
Contamination Assessment Report (CAR) shall be compiled to document the findings
and shall include interpretation of laboratory testing results in accordance
with the ProPECC Note No. 3/94 and comparison of the findings with
relevant standards, such as the Dutch guidelines or other international
practices as appropriate. If land contamination is confirmed, a Remediation
Action Plan (RAP) shall be drawn up to formulate necessary remedial measures
and potential water quality impact to the river shall be also addressed if
necessary in the remediation measures. The subsequent CAR and RAP shall be
endorsed by EPD before implementation of any remedial technology. The
contaminated sites should be remediated before commencement of any construction
work at the concerned sites which may disturb the ground. The duration of
remediation should be taken into account by the Project Proponent or the
Contractor as part of the construction programme.
7.7.4
In terms of remediation measures,
examples of available practical methods widely adopted for decontamination at
small sites are listed below:
·
Excavation
& disposal;
·
Soil
venting/Air sparging; and
·
Recovery
trenches or wells.
7.7.5
In assisting the formulation of
appropriate remedial measures, the Guidance Notes for Investigation and
Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, and
Car Repair/Dismantling Workshops suggest the following factors to be taken
into consideration when evaluating different available remediation methods:
i)
degree and extent
of the contamination;
ii) anticipated future use of the site;
iii) nature of the contaminants;
iv) soil characteristics; and
v)
time available for
remediation.
7.8.1
After any necessary remediation of
contaminated soil being carried out, the concerned site is expected to meet the
acceptable standards and no adverse residual impact would be envisaged.
7.9.1
Mitigation measures are proposed for
handling of the contaminated materials in order to minimise (1) the potentially
adverse effects on the health and safety of construction workers and (2) the
impacts arising from the disposal of potentially contaminated materials. These
measures include:
·
Construction workers' potential
contact with contaminated materials should be minimised by using bulk
earth-moving excavator equipment;
·
Exposure to any contaminated materials
should be minimised by wearing appropriate clothing and personal protective
equipment such as gloves and masks (when interacting directly with suspected
contaminated material), providing adequate hygiene and washing facilities and
preventing smoking and eating during such activities;
·
Stockpiling of contaminated excavated
materials on site should be avoided as far as possible;
·
The use of contaminated soil for
landscaping should be prohibited unless there is proper treatment of soil;
·
Vehicles containing any excavated
materials should be suitably covered to limit potential dust emissions or
contaminated wastewater run-off, and truck bodies and tailgates should be
sealed to prevent any discharge during transport or during wet conditions;
·
Only licensed waste haulers should be
used to collect and transport any contaminated material to an appropriate
disposal site and procedures should be developed to ensure that illegal
disposal of waste does not occur;
·
The necessary waste disposal permits
should be obtained, as required, from the appropriate authorities, in
accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal
(Chemical Waste) (General) Regulation (Cap 35), as required;
·
Records of the quantities of wastes
generated and disposed of should be maintained; and
·
In accordance with good construction
practice, silt traps should be used to reduce the impact to drainage caused by
suspended solids arising from disturbed ground, or any construction materials
such as cement and gravel. Wastewater, surface runoff or extracted groundwater
should be disposed of in accordance with the WPCO.
7.10.1
Since two potential zones have been
confined for further investigation due to the presence of potential
contaminative workshops located within the proposed alignment of Pak Kong
River, a review of the preliminary Contamination Assessment Plan (CAP) would be
required by the future Environmental Team at a later stage when full site
inspection is available after the land is resumed for the Project. Such revised
CAP should be submitted to EPD for approval.
7.10.2
Site investigation for contamination
at the potential contaminated zones shall follow the requirements laid out in
the approved CAP. A Contamination Assessment Report (CAR) and Remediation
Action Plan (RAP) if necessary, shall be prepared based on the results obtained
from the site investigation and submitted for EPD’s approval. Details of the
requirements are provided in a stand-alone EM&A Manual.
7.10.3
The land contamination investigation
and the reporting may take 3 to 6 months to complete. If contamination is found, remedial actions for contaminated soil
are required which may take another 6 months or more to complete. The Project Proponent shall take into
account the time required for land contamination study at the identified
areas. These identified areas should be
handled as the first priority after land resumption. The CAP, investigation works, CAR and RAP shall be carried out as
soon as the land is available for study.
Construction work might only be carried out at these areas if the
investigation results, which are obtained either after contamination assessment
(according to CAP) or after the remediation work (according to RAP), are found
acceptable.
7.11.1
An account of the present and
historical land uses along the proposed drainage improvement areas of the three
river channels indicated that activities related to land contamination impact
was not identified in or near to Sai Kung River and Ho Chung Channel. However,
two workshops associated with contaminating uses were noted to be present near
Pak Kong River, and the main type of activities was related to vehicle
repairing works.
7.11.2
Considering the potential land
contamination impact to site workers during construction of the Project, a
detailed site investigation was recommended for those areas falling within the
project boundary after land resumption. According to the preliminary design of
Pak Kong River, only partial areas of two identified workshops were found
located within the project works area with implication of land contamination
impact. A preliminary Contamination Assessment Plan (CAP) has been prepared for
further investigation.
7.11.3
Due to the possible changes of land
use and site conditions, a review of the CAP would be required by the future
Environmental Team at a later stage after land resumption. Such revised CAP
should be submitted to EPD for approval. It is considered that the potential
residual impacts would not be significant provided that any identified
contaminated land would be remediated to the acceptable standards prior to the
site clearance/excavation works, and the mitigation measures recommended would
be properly implemented during the construction stage of the Project.