The works that are the subject of
the EIA Study include the construction and operation phases of the
Project. The key components of the Project include the following:
i.
Dredging of a series of seabed pits within the proposed South Brothers
Facility Boundary (Part 1, Figure 2.4a);
ii.
Backfilling each dredged pit with contaminated mud that has been
classified as requiring Type 2 disposal in accordance with ETWBTC 34/2002;
and,
iii. Capping
each backfilled pit with uncontaminated mud and/or public fill effectively
isolating the contaminated mud from the surrounding marine environment.
Despite the proven acceptability and
close proximity of the existing facility at CMP IV, the purpose of the
assessment was to thoroughly evaluate the South Brothers Facility in terms of
acceptability of predicted impacts to water quality from dredging, backfilling
and capping of the pits and also concurrent activities.
This Section describes an
engineering design for the proposed South Brothers Facility, which is based on
maximising disposal capacity, ensuring continuity in use of the site, and
ensuring that environmental impacts are environmentally acceptable and no
greater than those associated with existing CMP operations. The
information presented in this section is taken from the preliminary design and
will be refined at the detailed engineering design stage.
The Project involves the sequential
disposal of contaminated mud into a series of dredged pits, provisionally
titled Pits A, B, and C. The sequential construction and operation of the
pits has been used to develop scenarios for sediment transport modelling,
assess marine traffic issues and identify key environmental issues for water
quality, ecology, fisheries, human health, noise and heritage assessments.
Previous purpose-dredged
contaminated mud disposal facilities at the East of Sha Chau area have had
backfill levels to 3m below original seabed. Recently, however, the very
large disused sand borrow pits now used as CMP IV have an allowed backfill
level up to 6m. This greater depth was deemed necessary because of the
greater surface area of material that would be subject to exposure to the
effects of storm waves.
In contrast to the above, the South
Brothers Facility is located in a shallow water area that experiences low
energy hydrodynamics. The relatively sheltered location would also
protect contaminated mud placed within the pits from storm or excessive wave
action. In addition, the preliminary smaller, shallower pit design would
minimise exposure of contaminated mud thus reducing the potential for
dispersion outside of the pit boundary. As a result of these design
features, the same backfill level design of 3m below original seabed level has
been employed in the design of the South Brothers Facility.
Caps at previous
CMPs in the East of Sha Chau Area have consisted of 3 m layer of uncontaminated
mud placed by controlled bottom dumping from barges. Additional clean mud
has been added later to compensate for long-term consolidation of the
contaminated mud. Such practice has been employed in the design of the
South Brothers Facility. The rationale for the design of the cap
design ([1]) ([2]) is to
keep the contaminated material beyond the reach of bioturbation and to protect
it against storm erosion.
The potential for
damage and breaching of the cap due to anchorage has been considered, but the
shallow water of the South Brothers Facility restricts the size of vessel which
can anchor in the area which, in turn, restricts the size of anchor and the potential
penetration depth.
Once the EIA Report has been
formally approved by Government, CEDD will obtain an Environmental Permit (EP)
for construction of the Project. Once the EP has been obtained the first
pit is expected to be dredged during 2008 in order to be ready to receive
contaminated mud in early 2009. According to arisings estimates the third
pit at the South Brothers Facility will be backfilled during the second half of
2012. It should be noted that should the rate at which contaminated mud
arises change (either increasing or decreasing) then the third pit maybe capped
earlier or later than 2015. The tentative construction programme is
presented in Figure 1.1a. It should be noted that the timeline
presents predicted timeframes for each works component.
|
Figure 1.1a Indicative Works
Sequencing at the South Brothers Facility
A requirement in the Study Brief is
to examine the cumulative effects of other projects concurrent with
construction and operations at the South Brothers Facility. Projects that
have been identified as occurring potentially at the same time are detailed
below:
·
Disposal at North Brothers
·
Reclamations along North Lantau Coastline
-
Potential New Town Extension at Tung Chung East and Tung Chung West
-
Lantau Logistics Park
-
Potential Theme Park
-
Reclamations at Yam O
·
Permanent Aviation Fuel Facility (PAFF)
·
Highway Projects
-
Tuen Mun to Chek Lap Kok link
-
North Lantau Highway Connection to the Hong Kong - Zhuhai - Macao Bridge
·
Sewage Discharges
-
Siu Ho Wan Sewage Treatment Work (STW)
-
Pillar Point Sewage Treatment Work (STW)
The significance of the above Projects
to the proposed South Brothers Facility is discussed in more detail in the
Water Quality Impact Assessment (Part 2, Section 2).
([1])
Premchitt J and Evans NC (1993) Stability of spoil and cap materials at East Sha
Chau contaminated mud disposal area. Special Project Report No. SPR
2/93. Geotechnical Engineering Office, CED, Hong Kong.
([2])
Geotechnical Engineering Office, Civil Engineering Department, Information
Note, May 1996.