This Section provides an evaluation
of the potential noise impacts associated with the activities at the proposed
Contaminated Mud Disposal Facilities at South Brothers. Mitigation measures will be
recommended, if necessary, to ensure that the legislative criteria will be
satisfied.
The principal noise sources
associated with the disposal facility are dredging, backfilling and capping
works within the Site. The works
programme presented in Section 1 indicates that concurrent undertakings
of dredging, backfilling and capping are possible at several time
intervals.
For dredging, it is assumed that two grab dredgers
will be operating within the Site, but a barge will be only operated at any one
time for either backfilling or capping operations. The assumed construction plant list and the corresponding
sound power levels are presented in
Table 6.1
Table 6.1Table
6.1Table 6.1.
Table 6.1 Construction Plant List and Sound
Power Levels (SWLs)
Activity |
PME |
CNP |
Quantity |
SWL/Unit |
Sub-Total SWL |
Dredging |
Dredger, Grab |
CNP063 |
2 |
112 |
115 |
Backfilling |
Derrick barge |
CNP061 |
1 |
104 |
104 |
Capping |
Derrick barge |
CNP061 |
1 |
104 |
104 |
The assessment of potential noise
impacts has been undertaken in accordance with the Technical Memorandum On
Noise From Construction Work Other Than Percussive Piling (GW-TM) and Annex
13 of the EIAO-TM. The
general methodology is summarised as follows:
·
identify the sequence and duration of noise generating
activities (i.e. dredging, backfilling and capping) required for the
implementation of the CMP Project;
·
identify the required type and number of Power
Mechanical Equipment (PME) likely to be deployed for the dredging, backfilling
and capping activities;
·
calculate the maximum total Sound Power Level (SWL)
for each activity using the PME list and SWL data given for each plant in the
GW-TM (as presented in Table 6.1);
·
identify representative NSRs with closest proximity to
the CMP Site to represent the potential impact for the area (as shown in Table
6.2);
·
identify representative NSRs around the CMP Site as
defined by the EIAO-TM based on existing and planned landuses that may be
affected by the CMP Project. In
view of the widespread and spacious extent of sites, only the representative
NSRs with closest proximity to the CMP Site will be identified to represent the
potential impact for the area;
·
measure the distance and calculate the distance
attenuation to the NSRs from worksite notional noise source point at each pit;
·
apply correction for façade reflection; and
·
predict noise levels at the NSRs in the absence of any
mitigation measures.
As the distances between most of the
NSRs and the CMP Site are over 1 km, sound absorption by the atmosphere
(assumed at 500 Hz, 20°C, RH
70%) has been accounted for in accordance with ISO 9613-1 Acoustics –
Attenuation of Sound During Propagation Outdoors – Part 1: Calculation of the
Absorption of Sound by the Atmosphere.
If the noise assessment criteria are
exceeded at the representative NSRs, mitigation measures will be explored. A re-evaluation of the total SWL for
each construction activity will be undertaken.
Noise assessments at the five representative
NSRs were made based on the tentative construction program, PME list, distances
attenuation, atmospheric absorption, façade reflection and corresponding Sound
Power Level. The results are
summarised in Table 6.2 and detailed calculations are presented in Table
1 of Annex D.
Table 6.2 Noise Assessment Results
NSR |
Description |
Area Sensitivity Rating |
Noise Criteria (1) |
Predicted Noise Levels |
N1 |
Regal
Airport Hotel |
C
(2) |
75
(3)/70 (4)/55 (4) |
19
to 33 dB(A) |
N2 |
Seaview
Crescent in Tung Chung |
B
(2) |
75/65/50 |
15
to 32 dB(A) |
N3 |
Monterey
Cove in Tung Chung |
B
(2) |
75/65/50 |
15
to 36 dB(A) |
N4 |
Planned
R(B)6 Residential Area at Area 77b (in future Kei Tau Kok reclamation area) |
B
(2) |
75/65/50 |
18
to 42 dB(A) |
N5 |
Ho
Yu School |
B
(2) |
70/65
(5) |
15
to 38 dB(A) |
N6 |
Planned
Residential Area at Area 77 (in future Kei Tau Kok reclamation area) |
B
(2) |
75/65/50 |
18
to 53 dB(A) |
Notes: (1)
Criteria
for daytime/ all days during the evening (1900-2300) and general holidays
including Sunday during the day and evening (0700-2300) / all days during the
night-time (2300-0700) (2)
Area
Sensitive Rating is assumed in accordance with the GW-TM (3)
Leq,
30min 75 dB(A) is the EIAO recommended daytime non-restricted hours
criterion (4)
Noise
criteria for restricted hours are prescribed under the NCO in LAeq 5min
(5)
Noise
criteria for normal school days / examination period |
As indicated in Table 6.2,
the predicted noise levels at the six representative NSRs would comply with the daytime
(i.e. 0700 – 1900, non-restricted hours) and evening hours (i.e. 1900 – 2300, restricted hours) noise
criteria. The highest noise level
of 53 dB(A) has been predicted at NSR N6, which is a planned residential
development. Ho Yu School (N5) will
not be affected by the dredging, backfilling and capping works during normal
school days and
examination period.
Should
dredging work be required during the night-time period (i.e. 2300 – 0700 hours)
within pit C, an exceedance of the night-time criterion by 3 dB(A) in 2008 has
been predicted at N6 due to its close proximity. Therefore, the
feasibility of the night-time dredging works within Pit C shall be evaluated in the
context of the construction programmeTherefore,
mitigation measures will be
required for night-time dredging works within Pit C.
The above assessment indicates that
no exceedance of the day and evening criteria is anticipated at the identified
NSRs. However, exceedance of the
night-time criterion has been predicted for NSR 6 during dredging activities at
Pit C.
The use of mitigation measures such
as quieter PME and noise barriers are commonly adopted at land-based
construction sites. However, these
measures are regarded infeasible and ineffective taking into account the nature
of work. Therefore, mitigation in
the form of reducing the number of dredgers from 2 to 1 is considered. This measure would reduce the
night-time noise level by 3 dB(A) to 50 dB(A).
As reduction in the number
of grab dredgers can reduce the noise level at N6 to comply with the Leq, 5min 50 dB(A)
night-time criterion, this is regarded as a feasible option.To enable dredging works
to be conducted at night-time, it would be necessary to operate only one grab dredger at any
one time. The predicted noise
level at N6 under this scenario would
be 50dB(A) and would comply with the night-time criterion. It is therefore recommended that
dredging work by 2 dredgers operating simultaneously shall be avoided at Pit C
during the night-time. This
restriction will be imposed for night-time dredging only if given the planned
housing developments (N6) are occupied prior to the dredging activities within
Pit C in 2011 to 2012.
Nevertheless, the EPD shall not be
bound by the results presented in this report when assessing any application
for a Construction Noise Permit (CNP) for works planned during restricted
hours.
No residual environmental impacts,
in terms of exceedances of applicable noise criteria, were predicted to occur
during the day and evening time. At
night-time the noise exceedance for Pit C can be avoided provided that the programming
arrangementcan be mitigated provided that the measure
described in Section 6.5 is
implemented.
Given the compliance with the noise
criteria, noise monitoring is not required during the construction or operation
of the South Brothers facility.
Noise impact associated with the
dredging, backfilling and capping works at the South Brothers Facility have
been assessed. It has been assumed
that 2 grab dredgers will be deployed on-site for dredging work and 1 barge for
the backfilling or capping activity.
Since restricted hours construction activities may be required, the
prediction results were compared against the EIAO-TM daytime
(non-restricted hours) and the evening (1900 – 2300) and night-time (2300 –
0700) restricted hours criteria.
The results indicated that the
criteria for daytime and evening works will comply with the criteria at all
representative NSRs. To enable dredging works
to be conducted at night-time, it would be necessary to operate only one grab dredger at any
one time. The predicted noise
level at N6 under this scenario would be 50dB(A) and would comply with the
night-time criterionHowever, exceedance of the night-time noise
criterion has been predicted at NSR 6 (3 dB(A)) during dredging work at Pit
C. By reducing the number of grab
dredgers from two to one, the noise level at NSR N6 is reduced by 3 dB(A) to 50
dB(A), which complies with the night-time criterion.
It is recommended that night-time
dredging by 2 dredgers at Pit C shall be avoided if the planned residential
developments at Kei Tau Kok reclamation area are occupied in the years 2011 to
2012. If the planned developments
are not occupied prior to the dredging activities within Pit C, no restriction
will be imposed for night-time dredging.