8    CONCLUSIONS & Environmental Outcomes

 

8.1    Introduction

 

This Section presents a summary of the key potential environmental outcomes associated with the construction and operation of the proposed South Brothers Facility.  The purpose of the assessment was to thoroughly evaluate the South Brothers Facility in terms of predicted impacts to water quality from dredging, backfilling and capping of the pits and also concurrent activities.  It should be noted that the facility is proposed to be developed in close proximity to the existing East of Sha Chau facility which have been demonstrated to operation in an acceptable manner as indicated by the findings of an intensive EM&A programme.

 

8.2    Water Quality

 

Computer modelling was used to simulate the loss of sediment to suspension during dredging, backfilling and capping operations.  The assessment concluded that any sediment disturbed by the works would settle rapidly back onto the seabed and the suspended sediment elevations would be of short duration.  This indicates that there would be little transport of suspended sediment away from the pits and that the sediment would not impact upon sensitive receivers.  In general, the sediment plumes generated by the works remain in open waters. 

 

No residual environmental impacts, in terms of exceedances of applicable standards were predicted to occur as a result of the dredging, backfilling and capping of the South Brothers Facility, provided that the recommended mitigation measures are implemented.  An EM&A programme has been devised to confirm that the works would be environmentally acceptable.

 

8.3    Marine Ecology

 

Through the application of criteria utilised in previous EIAs in Hong Kong, impacts arising from the proposed dredging, backfilling and capping operations at the South Brothers Facility are predicted to be within acceptable levels (as defined by the WQOs) and are not expected to cause adverse impacts to marine sensitive receivers of either high or medium ecological value (habitats or species).  The loss of the subtidal habitats present within the pit boundaries is considered to be acceptable, as the habitats are of low ecological value.  Furthermore, recolonisation of the capped pits by infaunal organisms and epibenthic fauna is expected to occur following the completion of capping operations.  Impacts to marine mammals are likely to be avoided, as sightings of the Indo-Pacific Humpback Dolphin, Sousa chinensis, are infrequent in the waters of the proposed South Brothers Facility in comparison to other waters in the north and west of Lantau.

 

The residual impacts occurring as a result of the construction and operation of the South Brothers Facility are confined to the loss of the low ecological value subtidal habitats present within the pit boundaries.  The residual impacts are considered to be acceptable as the habitats are of low ecological value and because infaunal organisms and epibenthic fauna are expected to recolonise the sediments. 

 

Water quality modelling of the cumulative impacts of projects planned to be constructed simultaneously has been conducted.  The findings indicated that no adverse impacts would be expected to water quality sensitive receivers when compared the allowable increases as defined by the WQO.  Unacceptable cumulative impacts as a result of concurrent project construction and operational activities are, therefore, unlikely to occur and hence cumulative impacts to marine ecology are not anticipated.

To protect against unacceptable impacts to marine ecological resources, an EM&A programme has been designed to specifically detect and mitigate any unacceptable impacts to marine ecological resources. 

 

8.4    Fisheries

 

Reviews of existing information on commercial fisheries resources and fishing operations located within the Study Area have been undertaken.  Information from a study on fishing operations in Hong Kong and the AFCD Port Surveys indicate that fisheries production values in the vicinity of the South Brothers Facility vary but are medium to low.

 

The construction and operation of the South Brothers Facility may give rise to fisheries impacts from disturbances to benthic habitats, changes in water quality and contaminant release.  Disturbances to benthic habitats are predicted to be confined within the pit boundaries of the South Brothers facility, and recolonisation of sediments is expected to occur following completion of works.  As changes in water quality are minimal and transient, adverse impacts to fisheries resources are not predicted to arise.  Assessment of contaminant release has indicated that the minimal concentrations will be minimal and well within the relevant criteria.

 

While no special mitigation measures are required for fisheries resources, mitigation measures recommended to reduce impacts to water quality are also expected to mitigate any impacts to fisheries resources.

 

8.5    Hazard to Health

 

The carcinogenic risk assessment has indicated that risks associated with consumption of seafood were below the acceptability criterion for both the South Brothers and the Background areas.  Results of the hazard assessment indicated that risks associated with consumption of seafood were below the acceptability criterion for both the South Brothers and the Background areas.

 

In addition, it does not appear that Indo-pacific Humpback dolphin prey organisms are predicted to bioaccumulate contaminants to higher concentrations than in prey of the same species from nearby reference locations.  These results indicate that the disposal of contaminated sediments at the proposed South Brothers Facility is not predicted to contribute to an increased risk of harm to Indo-pacific Humpback dolphins.

 

8.6    Noise

 

Noise impact associated with the dredging, backfilling and capping works at the South Brothers Facility have been assessed.  It has been assumed that 2 grab dredgers will be deployed on-site for dredging work and 1 barge for the backfilling or capping activity.  Since restricted hours construction activities may be required, the prediction results were compared against the EIAO-TM daytime (non-restricted hours) and the evening (1900 – 2300) and night-time (2300 – 0700) restricted hours criteria.

 

The results indicated that the criteria for daytime and evening works will comply with the criteria at all representative NSRs.  To enable dredging works to be conducted at night-time, it would be necessary to operate only one grab dredger at any one time.  The predicted noise level at N6 under this scenario would be 50dB(A) and would comply with the night-time criterion.

 

It is recommended that night-time dredging by 2 dredgers at Pit C shall be avoided if the planned residential developments at Kei Tau Kok reclamation area are occupied in the years 2011 to 2012.  If the planned developments are not occupied prior to the dredging activities within Pit C, no restriction will be imposed for night-time dredging.

 

8.7    Cultural Heritage

 

The review of the literature indicated that the region adjacent to the South Brothers Facility had been occupied for over 4,000 years and had been a focal point for Chinese and international maritime trade.  On this basis there is the potential for the area to include sites and objects of archaeological and historical significance; however, a review of charts has identified no shipwreck records.

 

The findings of the geophysical survey covering one third of the South Brothers Site (Pit A) indicated that the South Brothers Facility has been heavily disturbed by anchoring, trawling and dredging.  Three sub bottom obstructions were found in the seabed of the South Brothers Project Area.  It is possible that the obstructions are either cultural heritage material of archaeological/historical significance, or recently dumped material of no archaeological/historical significance.  The likelihood of the area containing any well-preserved remains is considered minimal.  In order to determine the archaeological potential of these obstructions and ensure that, if they are in fact of archaeological importance no impacts occur, it is proposed that a qualified archaeologist conduct a Watching Brief during dredging works.  Such a brief is only considered necessary in the area where the obstructions are located.  Full details on the Watching Brief, as well as the proposed archaeologist, should be submitted to and approved by AMO prior to the commencement of works. 

 

CEDD is presently applying funding to undertake a full MAI for the South Brothers Site, the findings of the remaining two thirds of the South Brothers Site will be provided to AMO during to the detailed design stage and prior to construction.  The objective of the full MAI will be to ensure that the proposed development will impose no impact to marine archaeological resources.

 

8.8    Environmental Monitoring and Audit (EM&A)      

 

The construction and operation of the proposed South Brothers Facility has been demonstrated at rates that maintain environmental impacts to within acceptable levels.  Actual impacts during the works will be monitored through a detailed Environmental Monitoring and Audit (EM&A) programme.  Full details of the EM&A programme are presented in the EM&A Manual which has been based on the on-going and previous monitoring programmes conducted at the Contaminated Mud Disposal Facility at East of Sha Chau.  This programme will provide management actions and supplemental mitigation measures to be employed should impacts arise, thereby ensuring the environmental acceptability of the South Brothers Facility.

 

8.9    Environmental Outcome

 

No unacceptable residual impacts are predicted for the construction and operation of the facility at the South Brothers site. 

 

8.9.1    Population and Environmentally Sensitive Areas Protected

 

The EIA study has facilitated the integration of environmental considerations into the design process for the Project.  The principal measures identified are those achieved through pit and dredging design and backfilling and capping working rates.  In addition, a number of mitigation measures have been identified to minimise the potential for adverse environmental impacts.  The mitigation measures are detailed in full in the Implementation Schedule (Annex E) and will be implemented by the Contractor under enforcement by the EPD.

 

One of the key environmental outcomes has been the ability to plan, design and ultimately construct the project so that direct impacts to sensitive receivers are avoided, as far as practically possible.  A detailed assessment of alternative sites within the Study Area has been conducted.  Through this assessment, environmentally sensitive areas have been protected by the following means.

 

·        Avoidance of Direct Impacts to Ecologically Sensitive Habitats:  The site for the South Brothers Facility has been selected based on a review of the environmental considerations of the area and the most environmentally preferable site within the Study Area has been selected to avoid direct impacts to ecologically sensitive habitats and species. 

 

·        Avoidance of Indirect Impacts to Ecologically Sensitive Habitats:  The site for the South Brothers Facility has been selected so that it is located at a sufficient distance from ecological sensitive receivers so that dispersion of sediment from dredging, backfilling and capping operations does not affect the receivers.  By locating the South Brothers Facility in an area of low hydrodynamic energy the horizontal dispersion of suspended sediment is restricted to a confined area in close proximity to the pit boundary.

 

As a result, it is not expected that the construction and operation of the South Brothers Facility will result in adverse impacts to environmentally sensitive areas.

 

8.9.2    Environmentally Friendly Designs Recommended

 

A key concern in the final site and disposal option design was to take steps to ensure that both direct and indirect impacts through dredging, backfilling and capping operations were avoided or minimised.  Consequently, the following approaches were adopted.

 

·        Adoption of Existing Practices:  A review of all environmental monitoring data collected since the commencement of operations at East of Sha Chau Contaminated Mud Disposal Facility demonstrates that mud disposal activities at the East of Sha Chau area have remained within environmentally acceptable levels.  As all dredging, backfilling and capping operations proposed for the South Brothers Facility have been designed to follow the current practices, no adverse unacceptable impacts are expected to occur.

 

·        CMP Design:  The South Brothers CMPs have been designed as three separate pits which minimises the exposure time of contaminated mud to the marine environment and consequently reduces the magnitude of any potential impacts.

 

·        Adoption of Acceptable Working Rates:  The modelling work has demonstrated that the selected working rates for the dredging, backfilling and capping operations will not cause unacceptable impacts to the receiving water quality.  Consequently, unacceptable indirect impacts have been avoided.


8.9.3    Key Environmental Problems Avoided

 

Key environmental problems have been avoided through the detailed site selection process that, as discussed above, allowed environmentally sensitive areas and populations to be avoided.  In addition, through the employment of practices that have been demonstrated to be environmentally acceptable, no environmental problems are expected to occur as a result of the construction and operation of the proposed South Brothers Facility.

 

8.9.4    Compensation Areas

 

The construction and operation of the proposed South Brothers Facility will result in the temporary loss of low ecological value soft bottom habitat.  Following the completion of capping operations, the seabed will be reinstated and is expected to return to pre-dredging conditions.  As a result, compensation areas are not deemed necessary.

 

8.9.5    Environmental Benefits of Environmental Protection Measures Recommended

 

The design of the South Brothers Facility will involve the dredging of purpose-dredged pits, backfilling with contaminated mud and subsequent capping with uncontaminated mud to return the seabed and hydrodynamic regime to their original condition.  A review of long term monitoring data from in and around the existing capped pits at East of Sha Chau has demonstrated that within a relatively short period of time, recolonisation of sediments occurs returning the site to a pre-dredged state.  The employment of such environmental protection methods in the design of the South Brothers Facility will, therefore, act as an environmental benefit.