This Section provides an evaluation
of the potential noise impacts associated with the activities at the proposed
Contaminated Mud Disposal Facilities at the East of Sha Chau. Mitigation measures will be
recommended, if necessary, to ensure that the legislative criteria will be
satisfied.
The principal noise sources
associated with the disposal facility are dredging, backfilling and capping
works within the Site. The works
programme presented in Section 1 indicates that concurrent undertaking
of dredging, backfilling and capping are possible at several time intervals.
For dredging, it is assumed that two grab dredgers
will be operating within the Site, but a barge will be only operated at any one
time for either backfilling or capping operations. The assumed construction plant list and the corresponding
sound power levels are presented in
Table 6.1.
Table 6.1 Construction
Plant List and Sound Power Levels (SWLs)
Activity |
PME |
CNP |
Quantity |
SWL/Unit |
Sub-Total SWL |
Dredging |
Dredger, Grab |
CNP063 |
2 |
112 |
115 |
Backfilling |
Derrick barge |
CNP061 |
1 |
104 |
104 |
Capping |
Derrick barge |
CNP061 |
1 |
104 |
104 |
The assessment of potential noise
impacts has been undertaken in accordance with the Technical Memorandum On
Noise From Construction Work Other Than Percussive Piling (GW-TM) and Annex
13 of the EIAO-TM. The
general methodology is summarised as follows:
·
identify the sequence and duration of noise generating
activities (i.e. dredging, backfilling and capping) required for the
implementation of the CMP Project;
·
identify the required type and number of Power
Mechanical Equipment (PME) likely to be deployed for the dredging, backfilling
and capping activities;
·
calculate the maximum total Sound Power Level (SWL)
for each activity using the PME list and SWL data given for each plant in the
GW-TM (as presented in Table 6.1);
·
identify representative NSRs with closest proximity to
the CMP Site to represent the potential impact for the area (as identified in Table
6.2);
·
measure the distance and calculate the distance
attenuation to the NSRs from worksite notional noise source point at each pit;
·
apply correction for façade reflection; and
·
predict noise levels at the NSRs in the absence of any
mitigation measures.
As the distances between most of the
NSRs and the Site are over 1 km, sound absorption by the atmosphere (assumed at
500 Hz, 20°C, RH
70%) has been accounted for in accordance with ISO 9613-1 Acoustics –
Attenuation of Sound During
Propagation Outdoors – Part 1:
Calculation of the Absorption of Sound by the Atmosphere.
If the noise assessment criteria are
exceeded at the representative NSRs, mitigation measures will be explored. A re-evaluation of the total SWL for
each construction activity will be undertaken.
Noise assessments at the five
representative NSRs were made based on the tentative construction program, PME
list, distances attenuation, atmospheric absorption, façade reflection and
corresponding Sound Power Level.
The results are summarised in Table 6.2 and detailed calculations
are presented in Table 3 of Annex D.
Table 6.2 Noise
Assessment Results
NSR |
Description |
Area Sensitivity Rating |
Noise Criteria (1) |
Predicted Noise Levels |
N1 |
Regal Airport
Hotel |
C (2) |
75 (3)/70
(4)/55 (4) |
27 to 39 dB(A) |
N2 |
Seaview
Crescent in Tung Chung |
B (2) |
75/65/50 |
12 to 23 dB(A) |
N3 |
Monterey Cove
in Tung Chung |
B (2) |
75/65/50 |
13 to 24 dB(A) |
N4 |
Planned R(B)6
Residential Area at Area 77b (in Kei Tau Kok) |
B (2) |
75/65/50 |
16 to 28 dB(A) |
N5 |
Ho Yu School |
B (2) |
70/65 (5) |
12 to 24 dB(A) |
Notes: (1)
Criteria
for daytime/ all days during the evening (1900-2300) and general holidays
including Sunday during the day and evening (0700-2300) / all days during the
night-time (2300-0700) (2)
Area
Sensitive Rating is assumed in accordance with the GW-TM (3)
Leq,
30min 75 dB(A) is the EIAO recommended daytime non-restricted hours
criterion (4)
Noise
criteria for restricted hours prescribed under the NCO in LAeq 5min
(5)
Noise
criteria for normal school days/examination period |
As indicated in Table 6.2,
the predicted noise levels at the representative NSRs would comply with the
daytime (i.e. 0700 – 1900, non-restricted hours), evening hours (i.e. 1900 –
2300 restricted hours) and night-time hours (i.e. 2300 – 0700) noise
criteria. The highest noise level
of 39 dB(A) has been predicted at NSR N1.
As noise levels at all NSRs will
comply with the daytime, evening and night-time criteria, no mitigation measure
is required.
No residual environmental impacts,
in terms of exceedances of applicable noise criteria, were predicted to occur
during either the daytime, evening or at night-time.
Given the compliance with the noise
criteria, noise monitoring is not required during the construction or operation
of the East of Sha Chau facility.
Noise impact associated with the
dredging, backfilling and capping works at the East of Sha Chau Facility have
been assessed. It has assumed that
2 grab dredgers will be deployed on-site for dredging work and 1 barge for
backfilling or capping activity.
Since restricted hours construction activities may be required, the
prediction results were compared against the EIAO-TM daytime
(non-restricted hours) and the evening (1900 – 2300) and night-time (2300 –
0700) restricted hours criteria.
The results indicated that the
criteria for daytime, evening and night-time works will comply at all
representative NSRs. No mitigation
measure is recommended.