1    Predicted environmental Performance of Each Facility

 

1.1    Introduction

 

This Section highlights the predicted environmental performance of the two facilities based on the information presented in Parts 2 and 3 and recommends the preferred facility.  The information presented here will feed into Section 4 that also incorporates information on marine traffic impacts and cost implications.

 

1.2    Comparison of Facilities

 

In the comparison of facilities it is important to note that under the Strategic Assessment and Site Selection Study for Contaminated Mud Disposal (Agreement CE 105/98), a detailed review of potential sites for a new contaminated mud disposal facility was undertaken throughout Hong Kong waters.  The study recommended that a site within the area East of the Airport be taken forward as the preferred site for such a facility. 

 

Although members of ACE had no objection to proceeding with the site, they considered that the remaining portions of East of Sha Chau should still be considered.  As such, this study has investigated the potential of the two areas to accommodate a new contaminated mud disposal facility. 

 

Despite the proven acceptability and close proximity of the existing facility at East of Sha Chau, the purpose of the assessment was to thoroughly evaluate both the East of Sha Chau and South Brothers Facilities in terms of acceptability of predicted impacts to water quality, marine ecology, fisheries, hazard to health, noise and cultural heritage from dredging, backfilling and capping of the pits, as well as that from concurrent activities.  Through this assessment, differences in the potential environmental performance of each facility have become apparent.  These are discussed below. 

 

Through the adoption of currently acceptable dredging, backfilling and capping rates, the construction and operation of either the East of Sha Chau or the South Brothers Facilities would result in only minor exceedances of the Water Quality Objectives.  In terms of impacts to sensitive receivers, these exceedances would be likely to occur at the Airport Exclusion Zone Artificial Reef through the construction and operation of the South Brothers Facility and in the marine waters to the east of the boundary of the Sha Chau and Lung Kwu Chau Marine Park for the East of Sha Chau Facility.  In terms of acceptability, it is considered that the potential impacts to the waters adjacent to the Marine Park would be of a slightly higher concern than those to the Artificial Reef however both impacts are considered to be minor .

 

1.3    Preferred Facility

 

A detailed evaluation of both the East of Sha Chau and South Brothers Facilities has been undertaken to determine their relative suitability for the development of a contaminated mud disposal facility in terms of environmental impacts.  Due to potential planning constraints on the North Lantau coastline, such as the landing point of the North Lantau Highway Connection of the Hong Kong Section of the Hong Kong Zhuhai Macau Bridge and the proposed reclamation of the Lantau Logistics Park, it is proposed that to avoid the possibility of cumulative impacts occurring during the construction of new developments, East of Sha Chau would be the preferred site.

It is important to note, however, that in terms of overall impacts, both facilities are considered to be acceptable on the grounds that both meet the relevant assessment criteria.  Should specific pits within the area currently selected for the East of Sha Chau Facility not be available when required, unacceptable adverse impacts associated with proceeding sequentially with the South Brothers Facility, if considered necessary, would not be expected to occur. 

 

In order to verify this assumption, a review of potential impacts to water quality from increases in suspended sediments arising from operating the East of Sha Chau Facility concurrently with the South Brothers Facility sequentially after the East of Sha Chau Facility has been conducted (Annex A).  The findings indicated that no adverse impacts would be expected to water quality sensitive receivers when compared to the allowable increases as defined by the WQO. 

 

It should be noted, however, that the assessment has been conducted on maximum operations without the use of operational controls and include the potential impact from other concurrent projects, such as disposal in the North Brothers Facility.

This conclusion is proposed with the caveat that no works proceed with Pit C due its relative proximity to the mouth of Tai Ho Bay, the landing point of the North Lantau Highway Connection  the Hong Kong Section of the Hong Kong Zhuhai Macau Bridge and the proposed reclamation of the Lantau Logistics Park.Inf proceeding with the South Brothers Facility, it is recommended that, following the guidelines of the EIAO TM, the precautionary principle be applied and operations in Pit A should be activated first.  Activity in Pit B should only proceed if monitoring results for Pit A demonstrate sufficiently the acceptability of environmental impacts.  In addition, due to the proximity of Tai Ho Bay and the, at present, uncertainty in the landing point of the North Lantau Highway Connection of the Hong Kong Section of the Hong Kong Zhuhai Macau Bridge and the proposed reclamation of the Lantau Logistics Park, operations at Pit C should be avoided following the precautionary principle. 

 

The uncertainties of the developments in the area and the potential for arisings of contaminated mud to change present us with 3 options.  These are presented below.

A tentative programme of the above three available options is presented in the following sectionsworks is presented in Figure 1.3a.  It should be noted that the timelines presentedts predicted timeframes for each works component.

 

Option 1

 

The first option would be to construct and operate the 4 proposed mud pits A, B, C and D at East of Sha Chau.  This option provides sufficient disposal capacity for existing predictions of Contaminated Mud arisings.  The timeline and sequencing is presented in Figure 1.3a.  The environmentally acceptability of this option has been confirmed in Part 3 of this report.

 

Figure 1.3a          Tentative Programme of Works for Option 1

 

Option 2

 

Option 2 assumes that planning constraints in the area do not allow for the construction and use of East of Sha Chau pits A and B.  This option therefore employs the use of East of Sha Chau Pits C and D followed by the use of South Brothers pits A and B.  This option provides enough capacity for arisings that are currently predicted between now and 2015.  The timeline and sequencing is presented in Figure 1.3b.  The environmental acceptability of this option has been confirmed in Annex A of this report.

 

Figure 1.3b          Tentative Programme of Works for Option 2

 

Option 3

 

Option 3 provides the highest capacity and allows for higher than expected arisings to occur.  This option involves the use of the four East of Sha Chau pits A, B, C and D followed by the South Brothers pits A and B.  The amount of time allocated to backfilling of the pits is shorter in the work programme to represent the higher than expected arisings.  The timeline and sequencing is presented in Figure 1.3c.  The environmental acceptability of this option has been confirmed by the modelling works presented in Annex A.  It is noted that the modelling works have assumed higher dredging, backfilling and capping rates than those that would occur following the timelines presented in the schedule.

 

Figure 1.3c          Tentative Programme of Works for Option 3

 

For options 2 and 3 it is recommended that before construction and activation of the pits at the South Brothers, a review and update of the EIA should be conducted to assess the validity of the assumptions made in this EIA report.

 

Although it has been shown that all 3 options are environmentally acceptable (see Annex A), Option 1 is recommended as it best represents the needs of the present situation.n.  

 

 


Contents

1  Predicted environmental Performance of Each Facility  1

1.1  Introduction  1

1.2  Comparison of Facilities  1

1.3  Preferred Facility  2